M/S. Manaksia Ltd vs The State Of West Bengal & Ors on 27 July, 2026

    0
    4
    ADVERTISEMENT

    Calcutta High Court (Appellete Side)

    M/S. Manaksia Ltd vs The State Of West Bengal & Ors on 27 July, 2026

                                                                            2011:CHC-AS:59
    
    
                     IN THE HIGH COURT AT CALCUTTA
                    CONSTITUTIONAL WRIT JURISDICTION
                             APPELLATE SIDE
    
    PRESENT:
    THE HON'BLE JUSTICE BIVAS PATTANAYAK
    
                            W.P.A. No.15313 of 2008
                               M/s. Manaksia Ltd.
                                      versus
                         The State of West Bengal & Ors.
    
    
    For the Petitioner               : Mr. Chayan Gupta, Advocate
                                       Mr. Saaqib Siddiqui, Advocate
    
    For the State                    : Mr. Amitabra Roy, Advocate
                                       Mr. Nilotpal Chatterjee, Advocate
                                       Mr. Amritalal Chatterjee, Advocate
    For the Respondent Nos. 2 & 3    : Mr. Salil Kumar Maiti, Advocate

    Ms. Dolon Samanta, Advocate

    Heard on : 02.04.2024, 26.11.2024, 10.12.2024,
    06.01.2025, 13.03.2025, 23.04.2025,
    13.05.2025, 29.10.2025

    SPONSORED

    Judgment on : 27.07.2026

    Bivas Pattanayak, J. :-

    1. By the present writ petition, the petitioner seeks for setting aside

    and/or cancellation of order under Memo no. 2652/HDA/VII-E-142/2001

    dated 5th February, 2008 (Annexure P13 to the writ petition) and order

    under Memo No. 1371/HDA/VII-E-142/2001 dated 4th July, 2008

    (Annexure P14 to the writ petition) both issued by respondent no.3, Chief

    Executive Officer, Haldia Development Authority (in short, „HDA‟) and

    direction upon respondent authorities to allow the petitioner-company to

    deposit the balance land premium of Rs.96,25,000/- at the rate of Rs.5.50
    2

    2011:CHC-AS:59

    lac per acre for settlement of 35 acres of land in favour of the petitioner-

    company on lease.

    2. The petitioner’s case in nutshell is as follows:

    (i) The petitioner is a Public Limited Company duly incorporated and

    registered under the Companies Act, 1956.

    (ii) In pursuance of the letter dated 7th September, 2001 of the petitioner-

    company, the Chief Executive Officer, HDA, respondent no.3 on 11th

    September, 2001 offered allotment of 50 acres of land comprised

    within J.L no. 122, Mouza-Bhuniaraychak, Police Station-Sutahata

    (presently Durgachak), District- Purba Medinipur (hereinafter referred

    to as „the subject land‟) in favour of the petitioner-company for setting

    up an Aluminum and Steel based industry, on lease basis in

    consideration of land premium @ 5.50 lacs per acre, on certain terms

    and conditions as per memo no. 1393/HDA/VII-E-142/01 dated 11th

    September 2001.

    (iii) By letter dated 13th September, 2001, the petitioner-company

    acknowledged the offer and requested respondent no. 3 to re-consider

    and reduce the land premium rate in appreciation of the fact that

    huge fund would be required for filling up and development of 50

    acres of land. Although respondent no.3 did not cause any reply to

    the aforesaid letter of the petitioner-company, however, the said

    prayer was duly considered in 71st Board meeting of HDA held on 4th

    October, 2001, wherein it was resolved as follows “board resolved in

    view of the fact that construction of infrastructure such as approach
    3

    2011:CHC-AS:59

    road, water supply and availability of power line upto the factory gate

    involves huge cost, it is not possible to reduce the land premium rate”.

    (iv) Admittedly, the land premium of 50 acres of land was fixed and

    accepted at the rate of Rs.5.5 lacs per acre. The petitioner-company

    on 28th December, 2001 sent two demand drafts totalling to Rs. 10

    lacs in favour of the respondent no.3 as a token booking amount for

    the scheduled land and also requested (a) to handover the possession

    of plot of land, (b) to construct the approach road and (c) to provide

    electricity connection and water supply.

    (v) By its letter under Memo no. 2479/HDA/VII-E-142/2001 dated 14th

    January, 2002, the HDA informed the petitioner-company that

    permission was accorded for soil testing and survey work of the

    petitioner-company’s project but formal possession of the land would

    be given after full and final payment of land premium. Virtually the

    petitioner-company got the physical possession of 50 acres of vacant

    land from the date of acceptance of the offer of its allotment.

    (vi) The Chief Executive Officer, respondent no.3 sent a revised site plan

    of 50 acres of land to the petitioner-company for setting up an

    aluminum and steel-based industry along with a forwarding letter

    under Memo no. 2831/HDA/VII-E-142/2001 dated 23rd February,

    2002, wherein the receipt of Rs. 10 lacs towards the advance of land

    premium were acknowledged and the terms and conditions of the

    allotment of land vide Memo no. 1393/HDA/VII-E-142/2001 dated

    11th September, 2001 would remain the same was confirmed. The

    revised site plan is nothing but alteration of shape of the plan.
    4

    2011:CHC-AS:59

    (vii) By a forwarding letter dated 26th March, 2002, the petitioner-company

    deposited Rs.1,27,50,000/- by a cheque in favour of respondent no.3

    on account of land premium in additional to earlier payment of

    Rs.10,00,000/-. As such the petitioner-company deposited 50% of the

    land premium for 50 acres of land at the accepted rate of Rs.5.50 lacs

    per acre. By the aforesaid letter, the petitioner-company once again

    requested the respondent no.3 to provide water supply and electricity

    connection at the site of the petitioner-company.

    (viii) The petitioner-company further applied before respondent no.3 by its

    letter dated 3rd July, 2002 and 4th July, 2002 for allotment of 15 acres

    of land for establishment of an Export Oriented Unit (EOU). In reply,

    respondent no.3 informed the petitioner-company on 9th July, 2002

    that 15 acres of land being part of 50 acres of land was allotment to

    the petitioner-company for the purpose of establishment of an Export

    Oriented Unit. On full and final payment of land premium 15 acres of

    land at the rate of Rs.5.50 lacs per acre, a registered lease deed was

    executed by and between the parties on 13th July, 2004 for settlement

    of 15 acres of land. The petitioner-company developed and

    constructed infrastructure on 15 acres of land and started

    commencement of commercial production at its Export Oriented Unit.

    A huge amount has also been invested by the petitioner-company for

    development of infrastructure on remaining 35 acres of land for

    setting up an aluminum and steel-based industry which was never

    objected by the concerned respondent at any point of time.
    5

    2011:CHC-AS:59

    (ix) By its resolution adopted in 73rd Board Meeting and 75th Board

    Meeting, it was resolved that the HDA would provide electricity

    connection at the doorstep of the petitioner’s site and meetings were

    held between the respondent and the Chairman of the petitioner-

    company to finalise the modalities for commencement of 132KB sub-

    station for bulk power supply to the petitioner-company and to that

    effect, resolution was also adopted in 77th Board Meeting. In 79th

    Board Meeting, it was resolved to approach West Bengal State

    Electricity Board proposing to share the cost of high-tension line at

    the rate of 25% by HDA and 75% by the West Bengal State Electricity

    Board respectively.

    (x) The Chief Executive Officer, respondent no.3 requested the petitioner-

    company to deposit balance land premium amounting to

    Rs.96,25,000/- (at the rate of Rs.5.50 lacs per acre). The petitioner

    could not deposit the aforesaid amount due to its financial

    stringencies, which was intimated to respondent no.3 vide letter dated

    2nd February, 2006 contending that the petitioner-company incurred

    a substantial investment on plant and equipment for the project as

    well as towards installation of power line and construction of sub-

    station. The petitioner-company was able to deposit the balance land

    premium of Rs. 96,25,000/- for 35 acres of land at the rate of Rs.5.50

    lacs per acre by way of a cheque to respondent no.3 on 21st January,

    2008.

    (xi) The Chief Executive Officer, respondent no.3 asked the petitioner-

    company by letter under Memo no. 2652/HDA/VII-E-142/2001 dated
    6

    2011:CHC-AS:59

    5th February, 2008 to pay full land premium for 35 acres of land at

    the present enhanced rate of Rs.15 lacs per acre totaling to

    Rs.4,28,75,000/- on the ground of alleged failure on the part of the

    petitioner-company to deposit 50% of the land premium for 35 acres

    at the rate of Rs.5.50 lacs per acre i.e. Rs.96,25,000/- within time.

    (xii) The petitioner-company by its letter dated 6th June, 2008 informed

    respondent no.3 that the balance payment could not be made due to

    inordinate delay in commissioning of the project.

    (xiii) By its letter under Memo No. 1371/HDA/VII-E-142/2001 dated 4th

    July, 2008, the Chief Executive Officer, respondent no.3 asked the

    petitioner-company to deposit the land premium amounting to

    Rs.4,28,75,000/- within 15 days from the date of issue of the said

    letter failing which HDA will evict the petitioner-company from the

    land measuring 35 acres occupied by the petitioner-company.

    (xiv) In the aforementioned allotment memo, there are no express

    conditions that the land premium rate may be enhanced for deferred

    payment of the balance 50% of the land premium by the petitioner-

    company or the petitioner-company can be evicted from the schedule

    land either for deferred payment of 50% of the land premium @ 5.50

    lacs per acre or for non-payment of the land premium at an enhanced

    rate without any due process of law.

    (xv) Being aggrieved by and dissatisfied with the impugned letters dated

    5th February, 2008 and 4th July, 2008, the petitioner has preferred

    the present writ petition seeking for quashing of the said letters.
    7

    2011:CHC-AS:59

    3. The writ petition has been keenly contested by the respondent no.3,

    Chief Executive Officer, HDA denying, inter alia, the case of the petitioner

    and contending as follows.

    (i) The HDA is the owner of the scheduled land comprised within Mouza

    – Bhunia Raychak and other adjoining lands which was acquisitioned

    for the purpose of establishing industries.

    (ii) By letter dated 7th September, 2001, Mr. B. K. Agarwal, Chairman and

    Managing Director, Hindustan Seals Limited requested for purchasing

    a plot of land measuring 50 acres within the Industrial Zone at Haldia

    on the bank of River Bhagirathi to set up an aluminum and steel-

    based industry. The HDA upon receipt of the said request by Memo

    No. 1393/HDA/VII-E-142/2001 dated 11th September, 2001 offered

    to lease out land measuring about 50 acres only for a period of 90

    years for setting up of aluminum and steel-based industry with

    certain agreed terms and conditions. The acceptance of the offer

    should be done after complying the terms and conditions within a

    specific period of two months from date of issue of that offer letter i.e.

    by 10th November, 2001.

    (iii) As per clause 3 and 4 of the offer letter, two months time was fixed for

    acceptance within which period the company had to deposit 50% of

    the land premium at the rate Rs. 5.50 lacs per acre. The 50% of the

    land premium was paid by the petitioner-company by way of several

    installments starting from 28th December, 2001 to 30th December,

    2003, which is long after the stipulated period of two months.

    Therefore, such acceptance of the offer after the specified period
    8

    2011:CHC-AS:59

    amounts to breach of the mandatory terms and accordingly, the

    proposal made by the offer became unenforceable and the same

    cannot be extended as time was the essence of the offer.

    (iv) The petitioner-company has failed to act strictly in terms of the offer

    in not depositing the 50% of the land premium within the specified

    period without any plausible reason and as such, the petitioner-

    company cannot pray for any relief under the offer dated 11th

    September, 2001.

    (v) The petitioner-company itself changed the mode of requirement by

    proposing the set of industries in different norms contrary to their

    prayer dated 7th September, 2001. The subsequent split of the total

    allotted land in the name of different industries are in clear violation

    of the offer made on 11th September, 2001. The petitioner has come

    up seeking permission to make payment of balance 50% of the land

    premium at the rate of Rs.5.50 lacs per acre as per original offer after

    lapse of more than 7 years, which is not at all sustainable in the eye

    of law.

    (vi) The question whether the offer dated 11th September, 2001 continues

    beyond the specific period of two months or any counter offer is

    created in lieu of original offer can only be decided by a competent

    civil court and not by invoking writ jurisdiction under Article 226 of

    the Constitution of India since disputed questions of facts are

    involved in the present writ petition.

    (vii) The original offer was made for the purpose of establishment of

    industry in the Industrial Zone. However, it is evident from record
    9

    2011:CHC-AS:59

    that the said company as per its whims and caprice erected

    residential complex over the said offered land within the periphery of

    35 acres of land. Such deviation from the original offer amounts to

    breach of the said offer.

    (viii) Despite several communications by the Haldia Development

    Authority, the petitioner-company deliberately avoided to make any

    payment of balance premium and on the contrary, made construction

    over the said land without taking necessary permission from the

    competent authority i.e. Haldia Municipality. The entire construction

    is illegal and unauthorized made in violation of Municipal Rules and

    is liable to be demolished. On receipt of letter dated 27th January,

    2006, the petitioner-company has made attempt to pay the balance

    premium, after lapse of 7 years from the original offer in order to cover

    up the wrongful acts. The petitioner-company committed to make

    payment of balance amount from April, 2006 but did not make any

    payment by deliberately violating its own commitment.

    (ix) The present market rate in respect of Industrial Zone is much more

    than Rs. 5.50 lacs per acre. The adjoining companies namely (i) M/s.

    Modern India Con-cast Ltd., (ii) M/s. Rahit Ferro Tech Pvt. Ltd., (iii)

    M/s. Mortex Pvt. Ltd. and (iv) M/s. Dhunsheri Poly carbonate Ltd. were

    offered land at rate of Rs. 15 lacs per acre and they have all accepted

    the same as per their required area. The claim of the Haldia

    Development Authority for present rate of Rs. 15 lacs per acre is thus

    absolutely reasonable and the petitioner is bound to pay the balance

    premium of land of Rs.4,28,75,000/- forthwith.

    10

    2011:CHC-AS:59

    (x) The petitioner-company has repeatedly harped about the so-called

    commitment by the Haldia Development Authority but has not

    forwarded any iota of ground which might prove its claim. The

    petitioner-company, on being requested by the WBSEB to deposit

    Rs.30,000/- for bulk power supply at 33 KV, duly deposited the same

    on 18th July, 2002. Such fact clearly shows that there was no

    commitment or promise by the Haldia Development Authority to

    supply power to doorstep of the petitioner-company. In spite of no

    commitment by Haldia Development Authority to the petitioner,

    however, just to facilitate industrial growth and to provide

    infrastructure, the Haldia Development Authority allotted 7.5 acres of

    land absolutely free of cost to the WBSEB (at present WBSEDCL)

    adjacent to the petitioner-company in order to provide power to the

    Industrial Zone, which has acted upon the decision of the Board. The

    petitioner-company got the power on August, 2006, which has been

    accepted by them in their letter dated 6th June, 2008, however, they

    did not take any initiative to make the balance payment even though

    they committed to make payment from April, 2006 vide letter dated

    2nd February, 2006. Hence, the intention of the petitioner-company

    was not noble and they took lame excuses for not making payment

    which remained due to HDA.

    (xi) For the betterment of establishment, the HDA took lenient view for

    recovery of balance land premium from the petitioner-company upto

    27th January, 2006 and vide letter under Memo no. 3123/HAD/VII-E-

    142 dated 27th January, 2006, granted further 7 days’ time to make
    11

    2011:CHC-AS:59

    such payment. The petitioner-company has not submitted any iota of

    document showing that it is ready and willing to pay the balance

    premium amount as per offer letter or counter offer letter. In spite the

    petitioner-company has taken resort to so-called commitment for

    development of infrastructure by the Haldia Development Authority

    such as water, power and approach road etc. to its door step. The

    Haldia Development Authority admittedly on or before August, 2006

    fulfilled all its obligations, however, the petitioner-company

    deliberately did not take any initiative to make balance payment, even

    though they committed to make payment from April, 2006.

    (xii) The petitioner-company is estopped from claiming any legitimate

    expectation after a lapse of more than 6 years from the stipulated

    period of 2 months. The petitioner-company has deliberately and

    willfully violated terms of the offer letter in not making payment of the

    balance land premium and is unwilling to perform its part of the offer

    letter.

    (xiii) On aforesaid ground, respondents-Haldia Development Authority

    sought for dismissal of the writ petition.

    4. The petitioner filed affidavit-in-reply denying the averments in the

    affidavit-in-opposition and contending that Haldia Development Authority

    in its letter under Memo No. 3123/HDA/VII-E-142/2001 dated 27th

    January, 2006 requested the petitioner-company to deposit the balance

    land premium of Rs.96,25,000/- within 7 days from the date of issue of

    the letter, otherwise the offer letter may be treated as cancelled. Thus, the

    expression „the offer letter may be treated as cancelled‟ does not amount to
    12

    2011:CHC-AS:59

    cancellation of the offer letter automatically. As such the offer letter dated

    11th September, 2001 still remains in force. In reply to the letter dated 27th

    January, 2006, the petitioner expressed its inability to deposit the balance

    amount land premium. Ultimately on 18th January, 2008 the petitioner-

    company tendered the balance land premium of Rs.96,25,000/- but the

    same was not accepted by the office of respondent no.3-HDA. As the

    petitioner-company has been allowed to construct the industry on 50 acres

    of land, the question of forfeiture by the concerned respondents does not

    arise at all. Further no lease agreement has yet been executed between the

    parties in respect of allotment of 50 acres of land nor possession of the

    land has been formally delivered to the petitioner-company but respondent

    no.3 has been realizing the lease rent in respect of leasehold property from

    the petitioner-company.

    5. The respondent no.3, on the contrary, has filed supplementary

    affidavit-in-opposition stating that the notice of payment of lease rent is

    nothing but a token rent as per the offer letter dated 11th September, 2001

    and it does not confer any special right to the petitioner-company to claim

    to the effect that the said offer letter is still binding upon the parties and is

    enforceable in the eye of law. A tenancy is only created as and when lease

    agreement is executed, registered and possession is delivered. Mere

    demand of token rent as made on 7th March, 2007 is not a rent at all and

    may be treated as user’s fee and/or licence fee.

    6. Mr. Abhrotosh Majumdar, learned Senior Advocate appearing for the

    petitioner submitted that Chief Executive Officer of HDA being respondent

    No.3 offered allotment of 50 acres of land at the subject plot in favour of
    13

    2011:CHC-AS:59

    the petitioner for setting up aluminium and steel-based industry on

    certain terms and conditions @ Rs.5.50 lacs per acre by dint of memo

    dated 11th September, 2001 and a token rent @ Rs.0.25% of the total land

    premium per acre which would be enhanced @ 5% annually. The petitioner

    acknowledged the said offer, however, by letter dated 13th September, 2001

    requested the authority concerned to reconsider the rate of premium. The

    petitioner pointed out that the subject-land is a very low land and

    substantial amount of funds would be spent for its development. In 71st

    Board meeting held on 4th October, 2001, the HDA considered the prayer

    made by the petitioner for reduction of rate of premium. However, it was

    resolved that in view of the fact that constructional infrastructure such as

    approach road, water supply and availability of power line up to the factory

    gate would involve huge costs, it would not be possible to reduce the land

    premium rate. Hence the counter offer made by the petitioner was rejected.

    On a conjoint reading of the offer letter dated 11th September, 2001, and

    71st Board resolution dated 4th October, 2001, it would be apparent that

    the land premium rate in the offer letter was inclusive of the cost of

    construction of infrastructure such as approach road, water supply and

    availability of power line up to the factory gate. The petitioner accepted the

    offer and made payment of Rs 1,68,75,000/- i.e. 61.36% of the total land

    premium of Rs.2,75,00,000/-@ of Rs. 5.5 lacs per acre for 50 acres.

    Further, on perusal of the minutes of 73rd Board meeting dated 11th April,

    2002, 75th Board meeting dated 23rd August, 2002, 77th Board meeting

    dated 27th December, 2002 and 79th Board meeting dated 8th July, 2003, it

    would be apparent that HDA was not able to provide the infrastructure for
    14

    2011:CHC-AS:59

    enhancement of commercial production to the industrial unit of the

    petitioner. Hence, it is not gainsaid by the respondent authorities namely

    HDA that the rate of land premium i.e. Rs. 5.50 lacs per acre as provided

    in the offer letter dated 11th September 2001, was not inclusive of the cost

    of infrastructure development. As such the offer letter made by the

    respondent authorities for allotment of the subject land was coupled with

    their unequivocal commitment to provide necessary infrastructure for

    industrial development.

    Needles to say that the petitioner made payment of 1.27 crores towards

    50% of the total land premium payable for 50 acres of land. Thereafter, a

    decision was taken to split up the lands into 15 acres and 35 acres and

    lease deed was executed for 15 acres of land in favour of the petitioner for

    a land premium @ Rs. 5.50 lacs per acre. The petitioner made a further

    payment of Rs. 41.25 lacs on 30th December 2003, and subsequently had

    made payment of the balance amount of Rs.96.25 lacs in accordance with

    the directions passed by this Hon’ble Court vide order dated 18th July,

    2008. The respondent authorities continue to charge rent in respect of 15

    acres of land till now taking the base of Rs.5.50 lacs per acre as land

    premium.

    Once the respondent authorities had accepted the rent for the entire 50

    acres of land taking the base of Rs. 5.50 per acre, it is not open to the

    respondent authorities to enhance the land premium unilaterally. There

    has been an abject failure on the part of respondent authority to provide

    necessary infrastructure of the industrial units of the petitioner as

    committed by the respondent authorities in the 71st Board resolution dated
    15

    2011:CHC-AS:59

    4th October, 2001. Therefore, the respondent authorities could not have

    arbitrarily enhanced the land premium @ Rs. 15 lacs per acre.

    The HDA being an instrumentality of the State, is therefore, an ‘authority‟

    within the meaning of Article 12 of the Constitution of India and is

    amenable to writ jurisdiction of the court. The consequence which follows

    is that in all its action, it must be governed by Article 14 of the

    Constitution and cannot act with arbitrariness and capriciousness. It is

    settled principle of law that the State and its instrumentalities have to be

    just, fair and reasonable in all their activities including those in the field of

    contracts. The State and its authorities playing the role of the landlord or

    tenant cannot be heard or seen causing displeasure or discomfort of Article

    14 of the Constitution. In support of his contention, he relied on the

    decision of the Hon’ble Supreme Court passed in Jamshed Hormusji

    Wadia versus Board of Trustees, Port of Mumbai and Another1.

    In the present case the HDA has accepted 50% of land premium for 50

    acres of land. The petitioner had been regularly paying rent to HDA for 50

    acres of land which has been accepted by the HDA Authorities till 31st

    March, 2007 without any demur. Despite such payment been made by the

    petitioner, the HDA failed to provide necessary infrastructure, the cost of

    which were included in the rate of land premium of Rs. 5.5 lacs per acres.

    Hence it is not open to HDA to issue the impugned memo dated 5th

    February, 2008, enhancing the land premium to Rs. 15 lacs per acre and

    memo dated 4th July, 2008 resorting to coercive actions of threatening the

    petitioner of consequences like eviction. Furthermore, since the petitioner

    1 (2004) 3 SCC 214
    16

    2011:CHC-AS:59

    had deposited the entire land premium upon deposit of the balance

    amount in terms of order of this Court which has not been challenged by

    the HDA authorities, hence the impugned notices are liable to be quashed

    and HDA be directed to execute lease deed in respect of the remaining 35

    acres of land for a land premium @ Rs. 5.50 lacs per acre with effect from

    13th July, 2004, that is the date on which deed of lease for 15 acres was

    executed and registered.

    Moreover, once the writ petition had been entertained and is pending for

    merely for last 17 years and an interim order is still subsisting, it is not

    open to the respondent authorities at this belated stage to contend that the

    writ petition is not maintainable and the petitioner should be relegated to

    the civil court. The respondent authorities did not challenge the order

    dated 18th July, 2008 wherein the petitioner was directed to deposit the

    balance amount and as a matter of fact the respondent authorities have

    also accepted the payment. It is no more res integra that when the court

    has already entertained the writ petition and issued an interim order,

    affidavits have been filed and the matter have been heard at length, the

    court in such circumstances would not be justified in rejecting the writ

    petition on the ground of availability of alternative remedy. In support of

    his contention, he relied on the following decisions.

    (i) L. Hirday Narain versus Income-Tax Officer, Bareilly2;

    (ii) State of H.P. and Others versus Gujarat Ambuja Cement Ltd.

    and Another3;

    2 1970(2) SCC 355
    3 (2005) 6 SCC 499
    17

    2011:CHC-AS:59

    (iii) Naffar Chandra Jute Mills Ltd. versus Assistant Collector of

    C. Ex.4;

    (iv) Raja Mookherjee and Others versus Wealth-Tax Officer and

    Others5.

    In light of his aforesaid submissions, he prayed for setting aside and/or

    cancellation of order under Memo no. 2652/HDA/VII-E-142/2001 dated

    5th February, 2008 (Annexure P13) and order under Memo No.

    1371/HDA/VII-E-142/2001 dated 4th July, 2008 (Annexure P14) both

    issued by the Chief Executive Officer, HDA, respondent no.3 and direction

    upon respondent authorities to allow the petitioner-company to deposit the

    balance land premium in terms of the letter dated 11th September, 2001.

    7. Mr. Kallol Kumar Basu, learned advocate appearing for respondent

    nos. 2 & 3- Haldia Development Authority submitted that by letter dated

    11th September, 2001 the authority had proposed to hand over 50 acres of

    land @ Rs.5.50 lakh per acre provided that the petitioner deposited such

    land premium within a period of two months from date of issuance of the

    said letter (Annexure P1, page-37). Such letter can be viewed as

    constituting a proposal within the meaning of Section 2(a) of the Indian

    Contract Act, 1872 (hereinafter referred to as „Act of 1872‟). Only if an

    assent had been provided by the petitioner- company in respect of the said

    proposal, a promise would have been formed and deposition of land

    premium at the rate mentioned in the said letter would have constituted

    the consideration for such promise within the meaning of Section 2(d) of

    4 1993 (66) E.L.T. 574 (Cal.)
    5 204 ITR 276
    18

    2011:CHC-AS:59

    the Act of 1872. However, it reveals that the said proposal was not

    accepted unconditionally as required under Section 7 of the Act of 1872 for

    a proposal to transform into a promise. As such, the earlier proposal of the

    respondent authorities never materialized into a promise and, therefore, no

    contract was formed.

    The acknowledgement of receipt of Rs.10,00,000/- on 21st February, 2002

    by the authority formed a part of a revised offer whereunder the terms

    governing the allotment of land remained unchanged but the site plan of

    the said land was altered. In other words, a revised offer similar to the

    initial offer dated 11th September, 2001 was made by the authority which

    meant that the balance land premium ought to have been deposited within

    the period of two months from date of receipt of the revised order. In view

    thereof, the deposit of a sum of Rs.1,27,50,000/- on 23rd March, 2002

    (Annexure P-7, page-45) could well be considered to form a part of the land

    premium payable at the applicable rate, as the same was deposited within

    two months from the date of issuance of the revised offer letter. Thereafter,

    the petitioner did not make any further payment and as such, the said

    revised offer did not materialize into promise and/or culminate into a

    contract. Upon offer made on behalf of the petitioner on 3rd July, 2002 and

    4th July, 2002 for transfer of 15 acres of land, the same was accepted and

    upon full and final payment of the requisite land premium, the said 15

    acres of land was allotted to the petitioner-company, as would be evident

    from the possession certificate dated 25th June, 2004 referred to in

    paragraph no. 17 of the affidavit-in-opposition.

    19

    2011:CHC-AS:59

    By letter dated 27th January, 2006 (Annexure P-10, page-59) the said

    authority had demanded payment of the balance land premium in respect

    of remaining 35 acres of land out of 50 acres initially offered in September,

    2001. This was, by all means, a fresh offer to allow the petitioner-

    company to gain possession over the remaining 35 acres but the same was

    turned down by the petitioner-company through its letter dated 2nd

    February, 2006 (Annexure P11, page-60 and 61). As such, the said offer

    letter dated 27th January, 2006 also did not materialize into a promise.

    Although much has been contended by the petitioner-company of the

    authority’s alleged commitment to ensure supply of electricity and water to

    the factory premises set up by the petitioner-company but such purported

    commitment did not find any mention in the original terms of proposal

    dated 11th September, 2001, revised proposal dated 21st February, 2002

    and/ or letter dated 27th January, 2006. Further much reliance has been

    placed upon the 73rd and 75th Board resolutions (Annexure P-9, page 47 to

    51) of the authority by the petitioner-company to bolster their claim that it

    was due to the delay caused by the said authority in not holding up their

    end of bargain and in failing to ensure supply of water and electricity to

    the doorstep of the factory. The aspect of delay could have been relevant

    only if it could have been shown that the initial offer dated 11th September,

    2001 was subsisting and the provision of electricity/water supply formed a

    part of the reciprocal promises in respect of such offer. Assuming but not

    admitting that the initial offer was subsisting, the provisioning of the

    electricity had been completed in the month of August, 2006 as has been

    admitted by the petitioner-company in its letter dated 2nd February, 2006
    20

    2011:CHC-AS:59

    (Page 58 of the affidavit-in-opposition), however, non-payment of land

    premium by the petitioner-company for more than one year from August,

    2006, contrary to their own representation that balance will be paid on

    and from April, 2006, remains unexplained. Moreover, the Board

    resolution does not amount to communication with or to the petitioner to

    the effect of acceptance of continuance of any promise. Additionally,

    commercial difficulty, inconvenience or hardship in performance of the

    conditions in a proposal can provide no justification in not complying with

    the same specially when the petitioner-company claims subsistence of the

    original proposal dated 11th September, 2001. To buttress his contention,

    he relied on the decision of Hon’ble Supreme Court passed in Joshi

    Technologies International Inc. versus Union of India and Others6.

    The petitioner has also based its argument in relation to interpretation of

    the terms of the initial offer letter dated 11th September, 2001. Effectively,

    the writ petitioner has invited this Hon’ble Court to adjudicate questions

    which squarely fall within the realm of private contractual law. In this

    regard it is submitted that negotiations and/or communications

    exchanged between the said authority and the petitioner-company do not

    give any indication of a concluded contract having a statutory character.

    Merely because the HDA constituted under Section 17 of the West Bengal

    Town and Country (Planning and Development) Act, 1979 is one of the

    parties to a purported contract, does not give rise to sufficient cause for

    maintaining a writ petition before this Hon’ble Court under Article 226 of

    the Constitution of India. Moreover, disputes regarding the true meaning,

    6 (2015) 7 SCC 728
    21

    2011:CHC-AS:59

    purport and/or interpretation of covenants in the private contractual

    realm, must be placed beyond the writ jurisdiction and fall within the

    domain of a civil court. In support of his contention, he relied on the

    decision of Hon’ble Supreme Court passed in Kerala S.E.B versus Kurien

    E. Kalathil7. Thus, the disputes raised in the writ petition cannot be

    adjudicated in the writ jurisdiction and same ought to be not

    maintainable, especially when no public law element is involved. Reliance

    is also placed on the decision of a Co-ordinate Bench of this court passed

    in Haldiram Ltd. versus The State of West Bengal & Ors8.

    Further, the initial offer expired on 11th November, 2001 and as such the

    writ petition seeking relief is hopelessly delayed and displays abject laches

    on the part of the petitioner-company. When extraordinary jurisdiction is

    sought to be invoked, the petitioner has to approach the Court within a

    reasonable period. If it is found that there is delay and laches, in such

    event the Court ought to dismiss the writ petition on such ground only. In

    support of his contention, he relied on the decision of Hon’ble Supreme

    Court passed in Tridip Kumar Dingal and Others versus State of West

    Bengal and Others9.

    Moreover, the petitioner-company tried to make out a case that due to

    failure of the part of the said authority in arranging for electricity and

    water supply, the production activities were delayed and as such no

    revenue could be generated so as to remit land premium within time.

    However, the petitioner-company deliberately suppressed their own letter

    7 (2000) 6 SCC 293
    8 (2009)1 CAL LT 158 (HC)
    9 (2009) 1 SCC 768
    22

    2011:CHC-AS:59

    dated 6th June, 2008 wherefrom it would be revealed that requirement of

    electricity and water had been met since August, 2006 but the petitioner-

    company failed to remit a single farthing for more than one and half years.

    Thus, the petitioner has not approached this Hon’ble Court with unclean

    hands and as such the writ petition is liable to be dismissed on the ground

    of suppression of fact.

    Furthermore, the petitioner’s claim of possession having been handed over

    by the said authority without full and final payment in the absence of any

    possession certificate is incorrect and such claim is essentially a distorted

    fact. Therefore, any relief granted would be based on distorted facts and

    would amount to abuse of process of law. To buttress contention, he relied

    on the decision of Hon’ble Supreme Court passed in K.D. Sharma versus

    Steel Authority of India Limited and Others10.

    Further it has been argued on behalf of the petitioner-company that once

    a writ is admitted, it would not be proper to dismiss the same on the

    ground of availability of alternative remedy relying on L. Hirday Narain

    (supra), Gujarat Ambuja Cement Ltd. (supra), Naffar Chandra Jute Mills

    (supra), Raja Mookherjee (supra). However, relying on the decision of

    Hon’ble Supreme Court in State of State of Uttar Pradesh and Another

    verus Uttar Pradesh Rajya Khanij Vikas Nigam Sangharsh Samiti

    and Other11, he submitted that the Hon’ble Court observed that it cannot

    be laid down as a proposition of law that once the petition is admitted, it

    could never be dismissed on the ground of alternative remedy.

    10 (2008) 12 SCC 481
    11 (2008) 12 SCC 675
    23

    2011:CHC-AS:59

    Further in case of Jamshed Hormusji Wadia (supra) relied upon by the

    petitioner-company, the Hon’ble Court held that the State and its

    instrumentalities have the liberty of revising the rate of rents so as to

    compensate themselves against loss caused by inflationary tendencies. The

    said authority by hiking the land premium rate was accounting for

    inflationary tendencies. Moreover, in the cited decision there was an

    existing lease agreement which was sought to be renewed whereas in the

    instant case, no concluded contract had been reached in respect of the

    balance 35 acres of land and as such it is not applicable.

    In light of his aforesaid submissions, he sought for dismissal of the writ

    petition.

    8. Mr. Amitabra Roy, learned advocate for the State respondents leaves

    the matter to the discretion of the court since the answering respondent is

    HDA.

    9. Upon hearing the learned advocates for the respective parties,

    following issues falls for consideration.

    (i) Whether the present writ petition is maintainable?

    (ii) Whether the order/letter dated 5th February, 2008 (Annexure P-

    13) and order/letter dated 4th July, 2008 (Annexure P14) both

    issued by the Chief Executive Officer, Haldia Development

    Authority, respondent no.3 are arbitrary and unsustainable?

    Issue no.(i): Whether the present writ petition is maintainable?

    10. The maintainability of the writ petition is challenged precisely on

    three-fold grounds. Firstly, merely because HDA constituted under Section

    17 of the West Bengal Town and Country (Planning and Development) Act,
    24

    2011:CHC-AS:59

    1979 is one of the parties to a purported contract does not give rise to

    sufficient cause for maintaining a writ petition before this Hon’ble Court

    under Article 226 of the Constitution of India. Secondly, as the initial offer

    expired on 11th November, 2001 and as such the writ petition seeking relief

    is hopelessly delayed and displays abject laches on the part of the

    petitioner-company. Thirdly, the disputes regarding the true meaning,

    purport and/or interpretation of covenants in the private contractual

    realm, must be placed beyond the writ jurisdiction and fall within the

    domain of a civil court, which is an alternative remedy available to the

    petitioner.

    10.1. There cannot be any quarrel that in pursuance of the letter dated 7th

    September, 2001 of the petitioner-company, the Chief Executive Officer,

    Haldia Development Authority, respondent no.3 on 11th September, 2001

    offered allotment of 50 acres of subject land in favour of the petitioner-

    company for setting up an Aluminum and Steel based industry, on lease

    basis in consideration of land premium @ 5.50 lacs per acre, on certain

    terms and conditions as per memo no. 1393/HDA/VII-E-142/01 dated

    11th September, 2001. The petitioner-company paid a part of land

    premium and sought direction upon respondent authorities to allow the

    petitioner-company to deposit the balance land premium of

    Rs.96,25,000/- @ Rs.5.50 lac per acre for settlement of 35 acres of land in

    favour of the petitioner-company on lease. By letter under Memo no.

    2652/HDA/VII-E-142/2001 dated 5th February, 2008 (Annexure P-13) the

    said Authority claimed the land premium @ Rs.15 lac per acre.

    Indisputably, there is no concluded contract in respect of the subject land
    25

    2011:CHC-AS:59

    measuring 35 acres. Thus, the challenge in the present writ petition is

    against the enhanced rate of land premium claimed by the HDA and not

    against terms of any concluded contract. Undeniably, HDA has been

    constituted under Section 17 of the West Bengal Town and Country

    (Planning and Development) Act, 1979 and thus is a Statutory Authority.

    10.2. In order to dilate the aforesaid aspect further, it would be profitable

    to consider the observation of Hon’ble Supreme Court in following

    decisions.

    10.3. In Federal Bank Ltd. versus Sagar Thomas and Others12, in

    paragraph no.18 held as follows.

    “18. From the decisions referred to above, the position that emerges is that
    a writ petition under Article 226 of the Constitution of India may be
    maintainable against (i) the State (Government); (ii) an authority; (iii) a
    statutory body; (iv) an instrumentality or agency of the State; (v) a
    company which is financed and owned by the State; (vi) a private body
    run substantially on State funding; (vii) a private body discharging public
    duty or positive obligation of public nature and (viii) a person or a body
    under liability to discharge any function under any statute, to compel it to
    perform such a statutory function.”

    10.4. Further in Andi Mukta Sadguru Shree Muktajee Vandas Swami

    Suvarna Jayanti Mahotsav Smarak Trust and others versus V.R.

    Rudani and others13 the Hon’ble Supreme Court in Paragraph 20 of the

    Report held as follows:

    “20. The term ‘authority’ used in Article 226, in the context, must receive a
    liberal meaning unlike the term in Article 12. Article 12 is relevant only for
    the purpose of enforcement of fundamental rights under Article 32. Article
    226
    confers power on the High Courts to issue writs for enforcement of the
    fundamental rights as well as non-fundamental rights. The words ‘any
    person or authority’ used in Article 226 are, therefore, not to be confined
    only to statutory authorities and instrumentalities of the State. They may
    cover any other person or body performing public duty. The form of the
    body concerned is not very much relevant. What is relevant is the nature
    of the duty imposed on the body. The duty must be judged in the light of
    positive obligation owed by the person or authority to the affected party.

    12 (2003) 10 SCC 733
    13 (1989) 2 S.C.C. 691
    26

    2011:CHC-AS:59

    No matter by what means the duty is imposed, if a positive obligation
    exists mandamus cannot be denied.”

    This principle establishes that the scope of Article 226 extends beyond

    entities that qualify as “State” under Article 12.

    10.5. In Bareilly Development Authority versus Ajay Pal Singh14 the

    Hon’ble Supreme Court after considering a catena of judgments observed

    that where the contract entered into between the State and the persons

    aggrieved is non-statutory and purely contractual and the rights are

    governed only by the terms of the contract, no writ or order can be issued

    under Article 226 of the Constitution of India so as to compel the

    authorities to remedy a breach of contract pure and simple.

    10.6. However, in Indore Development Authority versus Smt. Sadhna

    Agarwal and others15 the Supreme Court affirmed and approved the view

    taken by the Apex Court in Bareilly Development Authority (supra), but it

    further provided that the High Court, while exercising its extraordinary

    jurisdiction under Article 226 of the Constitution, may satisfy itself on the

    materials on record that the State has not acted in arbitrary or erratic

    manner.

    10.7. Bearing in mind the aforesaid principle since the challenge in the

    present writ petition is against the enhanced rate of land premium claimed

    by the Authority, which is a decision of the authority and not against any

    terms concluded contract, hence writ petitions are maintainable against

    orders passed by statutory authorities in exercise of their statutory

    functions. The legality, validity and maintainability of the order/decision of

    14 AIR 1989 SC 1076
    15 (1995) 3 SCC 1
    27

    2011:CHC-AS:59

    statutory authority can always be made subject matter of judicial review,

    albeit, within the well-recognized limitations applicable to the process of

    judicial review.

    10.8. Although much have been argued on behalf of Authority relying on

    Kurien E. Kalathil (supra) and Haldiram Ltd (supra) that the writ petitioner

    has invited this Hon’ble Court to adjudicate questions which squarely fall

    within the realm of private contractual law and must be vouched before

    the civil court, however, as it is found that admittedly there is no

    concluded contract between the petitioner-company and HDA, hence such

    proposition does not apply to the facts of this case. Since the present case

    is not concerning adjudication of any contractual obligation but a

    challenge to the claim of enhanced rate of land premium, hence the aspect

    of availability of alternative remedy cannot stand in the way of the writ

    petitioner to press its prayer under writ jurisdiction. Although it is settled

    position of law that it cannot be laid down as a proposition of law that once

    the petition is admitted, it could never be dismissed on the ground of

    alternative remedy as observed by Hon’ble Supreme Court in Uttar Pradesh

    Rajya Khanij Vikas Nigam Sangharsh Samiti (supra), however, the said

    proposition is not relevant to the facts and circumstances of this case.

    10.9. With regard to the second ground of challenge to the maintainability

    of the writ petition of delay and laches it would be appropriate to analyze

    the chronology of events which stands undisputed, in order to examine

    such ground. The initial offer was made on 11th September, 2001, however,

    subsequent thereto letter of communication was made on 13th September,

    2001 by the petitioner-company acknowledging the offer and requesting
    28

    2011:CHC-AS:59

    respondent no. 3 to re-consider and reduce the land premium rate in

    appreciation of the fact that huge fund would be required for filling up and

    development of 50 acres of land which was considered in the 71st Board

    Meeting of HDA held on 4th October, 2001 and rejected. The petitioner-

    company on 28th December, 2001 sent two demand drafts totalling to Rs.

    10 lacs in favour of the respondent no.3 as a token booking amount for the

    scheduled land. Indisputably a revised offer was made whereunder the

    terms governing the allotment of land remained unchanged but the site

    plan of the said land was altered as per letter of HDA dated 23rd February,

    2002. On 26th March, 2002, the petitioner-company deposited

    Rs.1,27,50,000/-. Respondent no.3 informed the petitioner-company on

    9th July, 2002 that 15 acres of land being part of 50 acres of land was

    allotted to the petitioner-company for the purpose of establishment of an

    Export Oriented Unit and a registered lease deed was executed by and

    between the parties on 13th July, 2004. On 27th January, 2006 HDA

    demanded payment of the balance land premium in respect of remaining

    35 acres of land out of 50 acres initially offered in September, 2001. The

    petitioner-company informed to respondent no.3 vide letter dated 2nd

    February, 2006 of its inability to make payment. By letter under Memo no.

    2652/HDA/VII-E-142/2001 dated 5th February, 2008 (Annexure P13) the

    said Authority claimed the land premium @ Rs.15 lac per acre. The

    petitioner-company by its letter dated 6th June, 2008 informed respondent

    no.3 that the remaining balance payment could not be made due to

    inordinate delay in commissioning of the project. By its letter under Memo

    No. 1371/HDA/VII-E-142/2001 dated 4th July, 2008, the Chief Executive
    29

    2011:CHC-AS:59

    Officer, respondent no.3 asked the petitioner-company to deposit the land

    premium amounting to Rs.4,28,75,000/- within 15 days from the date of

    issue of the said letter failing which Haldia Development Authority will

    evict the petitioner-company from the land measuring 35 acres occupied

    by the petitioner-company. The writ petition has been filed thereafter on

    16th July, 2008. Thus, although the initial offer was made on 11th

    September, 2001 yet considering the entire conspectus of the cause of

    action it appears that the grievance of the petitioner arose upon issuance

    of letter dated 5th February, 2008 and 4th July, 2008 by the Authority

    concerned. Therefore, it cannot be said that there is delay in filing of the

    writ petition. Hence, the argument advanced on behalf of the said

    Authority relying on the decision of Hon’ble Supreme Court in Tridip

    Kumar Dingal (supra) that the writ petition is liable to be dismissed on the

    ground of delay alone cannot be accepted in the backdrop of the facts

    noted hereinabove.

    10.10. So far as the third ground of thrust to maintainability of the writ

    petition pertaining to availability of alternative remedy is concerned, it has

    been vociferously argued on behalf of the said Authority that effectively, the

    writ petitioner has invited this Hon’ble Court to adjudicate questions

    which squarely fall within the realm of private contractual law. Disputes

    regarding the true meaning, purport and/or interpretation of covenants in

    the private contractual realm, must be placed beyond the writ jurisdiction

    and fall within the domain of a civil court. Reliance has been placed on the

    decision of Hon’ble Supreme Court Kurien E. Kalathil (supra) and thus, the

    disputes raised in the writ petition cannot be adjudicated in the writ
    30

    2011:CHC-AS:59

    jurisdiction and same ought to be not maintainable, especially no public

    law element is involved.

    The rule of exclusion of writ jurisdiction by availability of alternative

    remedy is a rule of discretion and not one of compulsion. In spite of

    availability of alternative remedy, the High Court may still exercise its writ

    jurisdiction in at least three contingencies: (i) where the writ petition seeks

    enforcement of any of the fundamental rights; (ii) where there is failure of

    principles of natural justice; (iii) where the orders or proceedings are

    wholly without jurisdiction or the vires of the Act is challenged. (See

    Harbanslal Sahania versus Indian Oil Corporation Limited16).

    Bearing in mind the aforesaid proposition, let me revert back to the facts of

    the case. It has already been found that the challenge in the present writ

    petition is against the enhanced rate of land premium claimed by the

    Authority, which is a decision of the authority and not against terms of

    any concluded contract, hence writ petition is maintainable against orders

    passed by statutory authorities in exercise of their statutory functions.

    Therefore, the argument on behalf of the authority that disputes regarding

    the true meaning, purport and/or interpretation of covenants in the

    private contractual realm, must be placed beyond the writ jurisdiction and

    fall within the domain of a civil court, is misconceived and plea of

    availability of alternative remedy in civil court being a bar in maintaining a

    writ petition is unacceptable.

    10.11. In light of the above discussion, this Court is of the opinion that the

    present writ petition is very much maintainable.

    16 (2003) 2 SCC 107
    31

    2011:CHC-AS:59

    Issue no.(ii): Whether the order/letter dated 5th February, 2008 (Annexure P-

    13) and order/letter dated 4th July, 2008 (Annexure P14) both issued by the
    Chief Executive Officer, Haldia Development Authority, respondent no.3 is
    arbitrary and unsustainable?

    11. The principle dispute revolves around an offer letter of the said

    Authority dated 11th September, 2001. For better analysis and

    appreciation of the instant issue, it would be profitable to reproduce the

    relevant offer letter as hereunder:

    “Office of the
    Chief Executive Officer
    Haldia Development Authority
    P.O. Durgachak, Haldia, Midnapore
    West Bengal – 721 602
    Memo No. 1393/HDA/VII-E-142/01 Dated the 11th September, 2001.

                   From    : Chief Executive Officer
                             Haldia Development Authority
    
                   To      : M/S Hindustan Seals Limited,
    

    8/1, Lalbazar Street, Bikaner Building (3rd Floor),
    Kolkata – 700001

    Sub: Offer of land measuring 50.0 acres for setting up of
    an aluminum and steel based industry.

    Ref: Your letter no. NIL dated 07.09.2001.

    Sir,
    With reference to the above, we are pleased to provisionally offer you
    50.0 acres of land at mouza Bhuniaraychak (122), P.S. Sutahata Dist.
    Midnapore. As regards the allotment of land the following terms may
    please be noted:

    1. The land will be given on 90 (ninety) years lease basis and is
    renewable also.

    2. The land premium rate is Rs.5.50 lakhs (Rs.five lakhs fifty thousand)
    only per acre and token rent @ Rs.0.25% of the total land premium per
    year will have to be paid, which will be enhanced @ Rs.5% annually,
    subject to the approval of the Board of Haldia Development Authority.

    3. This offer letter is valid for 2 (two) months from the date of issue of this
    letter.

    4. You have to deposit 50% of the land premium as an acceptance of this
    offer letter.

    5. The possession of land will be delivered after completion of the full
    land final payment of land premium.

    6. Payment have to be made in favour of Chief Executive Officer, Haldia
    Development Authority by Demand Draft/Bankers Cheque payable at
    Haldia only.

    7. In case you fail to establish your project within the stipulated time and
    as per terms and conditions of agreement and if you pray for refund of
    the advance premium, the subject shall be decided by the Board of
    HDA which shall be final and binding on all concerned.

    32

    2011:CHC-AS:59

    8. Final terms and conditions will be settled during execution of lease
    deed.

    Thanking you,
    Yours faithfully

    Chief Executive Officer
    Haldia Development Authority”

    11.1. Upon bare reading of the aforesaid offer letter, it manifests that the

    subject land was proposed to be given for lease of 90 years, which is

    renewable. The land premium was fixed @ Rs.5.50 lac per acre with a

    token rent @ 0.25% of the total land premium per year which was to be

    enhanced @ 5% annually subject to approval of the said Authority. The

    offer letter was made valid for two months from date of its issuance i.e. 11th

    September, 2001. Further the petitioner-company had to deposit 50% of

    the land premium as an acceptance of the offer letter and the possession of

    the land was to be delivered after completion of the full and final payment

    of the land premium. Thus, the total land premium was fixed at

    Rs.2,75,00,000/-. On 13th September 2001 the petitioner-company sent a

    letter to the said Authority acknowledging the offer and agreed to the terms

    and conditions stipulated therein and requested respondent no. 3, Chief

    Executive Officer to re-consider and reduce the land premium rate in

    appreciation of the fact that huge fund would be required for filling up and

    development of 50 acres of land. The prayer for reduction of land premium

    made in the aforesaid letter by the petitioner-company was discussed and

    duly considered in the 71st Board Meeting of Haldia Development Authority

    held on 4th October, 2001 wherein it was resolved as follows “board

    resolved in view of the fact that construction of infrastructure such as

    approach road, water supply and availability of power line upto the factory
    33

    2011:CHC-AS:59

    gate involves huge cost, it is not possible to reduce the land premium rate”.

    Subsequent thereto, by letter dated 28th December, 2001, the petitioner-

    company sent two demand drafts totalling to Rs. 10 lacs in favour of the

    respondent no.3 as a token booking amount for the scheduled land and

    also requested to handover the possession of plot of land by 31st

    December, 2001 so that the company may proceed with soil testing, land

    filling and construction activity. Thus, since after the prayer for reduction

    of land premium of the petitioner-company was turned down by the said

    Authority, the petitioner-company tendered the token booking amount

    requesting for handing over of the subject land, it can well be construed

    that the petitioner-company accepted the land premium fixed by HDA.

    There was no dispute raised thereafter with regard to the land premium

    fixed in respect of the subject land.

    11.2. Indisputably a revised offer was made whereunder the terms

    governing the allotment of land remained unchanged but the site plan of

    the said land was altered as informed by the said Authority vide letter

    under Memo no. 2831 dated 21st February, 2002 and the Authority in its

    said letter also acknowledged the receipt of Rs. 10,00,000/-. Thereafter, on

    26th March, 2002, the petitioner-company deposited Rs.1,27,50,000/- by a

    cheque in favour of respondent no.3 on account of land premium in

    addition to earlier payment of Rs.10,00,000/-. As per the offer letter the

    same was made valid for a period of two months meaning thereby that the

    validity was for two months from the date of revision of the plan on 21st

    February 2002. Though 50% of the land premium was paid but remaining

    was not paid within the period of validity of two months. Although the
    34

    2011:CHC-AS:59

    petitioner-company has raised the issue that the said Authority did not

    provide supply of electricity and water to the factory premises set up by the

    petitioner-company and resulted in delayed execution of their project but

    needless to mention that the payment of land premium was never subject

    to providing such infrastructure as is evident from the original terms of

    proposal dated 11th September 2001. The revised proposal dated 21st

    February 2002 also did not contain any change in the terms and

    conditions which subjected the payment of balance amount of land

    premium to providing of infrastructure. By letter dated 9th July, 2002, 15

    acres out of 50 acres offered land was allotted to the petitioner-company

    for establishing Export Oriented Unit. Though on 18th April, 2003 a letter

    of communication was made by petitioner-company to the said Authority

    for arranging for power supply at the site of the petitioner-company yet

    since 9th July, 2002 the petitioner-company did not take any endeavour to

    make payment of remaining amount of the land premium for almost more

    than three years. Ultimately the said Authority on 27th January 2006

    issued a letter of reminder for depositing the remaining land premium of

    Rs. 96,25,000/- within seven days otherwise the offer letter shall be

    treated as cancelled. Though the petitioner-company acknowledged that

    the balance land premium of Rs.96,25,000/- is due at their end but

    addressed their inability to make payment as commissioning of the project

    was inordinately delayed as per schedule for the reasons of lack of power

    and water supply. Such payment was not made even after a lapse of

    almost two years of issuance of reminder by HDA. The amount was

    tendered only on 18th January, 2008. It is pertinent to reiterate that there
    35

    2011:CHC-AS:59

    is no alteration/change in the original terms and conditions in the

    meantime subjecting payment of remaining balance amount of the land

    premium to providing power and water supply. Thus, it is found from the

    original offer letter, revised offer letter and from subsequent events as

    above, that neither of those clause contains any terms that the payment of

    land premium was subject to providing infrastructure to the petitioner-

    company namely power and water supply by HDA. In the aforesaid

    conspectus, it is seen that no plausible reason is coming up from the side

    of the petitioner-company in not tendering the remaining amount of land

    premium within the validity period of the offer letter or within the period

    stipulated in the letter of reminder. Despite the balance land premium

    remaining unpaid for long, the petitioner-company was given opportunity

    to pay the balance land premium within a stipulated period of seven days

    but it has failed to make payment in response to the said letter. Hence,

    there cannot be any manner of doubt that despite getting opportunity to

    make payment, the petitioner-company did not do so without any rhyme or

    reason. Once the petitioner-company acknowledged and accepted the offer

    it was incumbent upon it to honour such offer and proceed in accordance

    with the terms and conditions of the offer letter which clearly stipulated

    that the offer letter would be valid for two months. Such payment therefore

    has to be made with the period of validity of the offer letter. Although upon

    non-compliance of the terms of the offer letter by not paying the balance

    amount within the schedule time period the offer letter deemed to have

    stood invalidated, yet a last opportunity was given to the petitioner-

    company to make payment vide letter dated 27th January, 2006, or else
    36

    2011:CHC-AS:59

    the offer letter would be treated as cancelled, which has also not been

    complied with. In reply, the petitioner-company vide its order dated 2nd

    February, 2006 disclosed its inability to make payment of balance land

    premium and committed to pay the same from April, 2006. However, no

    endeavour was taken to make good such commitment. There cannot be

    any dispute that by its own letter dated 6th June 2008 at page 59 of the

    affidavit-in-opposition of respondent no.3 dated 5th September, 2008, the

    petitioner-company has admitted that the power supply was made

    available from August, 2006. There is iota of materials showing that as a

    bonafide action the petitioner-company tendered the balance amount soon

    thereafter. It appears that on the plea of non-availability of power and

    water supply the petitioner-company did not make payment which is

    unacceptable, since the payment under the offer letter was not conditioned

    upon availability of power and water supply. Furthermore, while accepting

    the offer made in the said letter the petitioner-company had the prior

    knowledge of the condition of the land and the infrastructure available

    thereat and as such plea of non-availability of power and water supply

    cannot be a ground to delay full and final payment under the offer letter.

    This court finds substance in submission of Mr. Basu, learned advocate for

    the said Authority relying on Joshi Technologies International Inc.(supra)

    that commercial difficulty, inconvenience or hardship in performance of

    the conditions in a proposal can provide no justification in not complying

    with the same specially when the petitioner-company claims subsistence of

    the original proposal dated 11th September 2001.

    37

    2011:CHC-AS:59

    11.3. Moreover, from paragraph no.23 of affidavit-in-opposition, it appears

    that the rate of land premium of Rs.15 lacs per acre has been accepted by

    other companies namely (i) M/s. Modern India Con-cast Ltd., (ii) M/s. Rohit

    Ferro Tech Ltd., (iii) M/s. Mortex Alloys Pvt. Ltd. and (iv) M/s. Dhunsheri

    Polycarbonate Ltd.

    11.4. In Jamshed Hormusji Wadia (supra), the Hon’ble Supreme Court

    observed as follows.

    “18. In our opinion, in the field of contracts the State and its
    instrumentalities ought to so design their activities as would ensure fair
    competition and non-discrimination. They can augment their resources but
    the object should be to serve the public cause and to do public good by
    resorting to fair and reasonable methods. The State and its
    instrumentalities, as the landlords, have the liberty of revising the rates of
    rent so as to compensate themselves against loss caused by inflationary
    tendencies. They can — and rather must — also save themselves from
    negative balances caused by the cost of maintenance, payment of taxes
    and costs of administration. The State, as the landlord, need not
    necessarily be a benevolent and good charitable Samaritan. The felt need
    for expanding or stimulating its own activities or other activities in the
    public interest having once arisen, the State need not hold its hands from
    seeking eviction of its lessees. However, the State cannot be seen to be
    indulging in rack-renting, profiteering and indulging in whimsical or
    unreasonable evictions or bargains.”

    11.5. Bearing in mind the aforesaid observation, since it is found that

    other companies have also accepted the rate of land premium of Rs.15 lacs

    per acre, therefore, the enhanced rate at Rs.15 lacs per acre as made by

    the authority towards counter offer to the petitioner-company cannot said

    to be lacking in rationality or is discriminatory.

    11.6. In the aforesaid backdrop, letter under Memo no. 2652/HDA/VII-E-

    142/2001 dated 5th February, 2008 (Annexure P-13) asking the petitioner-

    company to deposit land premium at an enhanced rate of Rs. 15 lacs per

    acre amounting to Rs. 4,28,75,000/- within a specified period and letter

    under Memo No. 1371/HDA/VII-E-142/2001 dated 4th July, 2008

    (Annexure P14) for eviction of the petitioner-company from the subject
    38

    2011:CHC-AS:59

    land, both issued by the Chief Executive Officer, Haldia Development

    Authority, respondent no.3 is not arbitrary since several opportunity was

    given to the petitioner-company to make payment of the balance amount

    at the earlier rate of land premium offered which has not been complied

    and availed of by the petitioner-company without any credible and

    acceptable reason. Further the petitioner-company has also not lived upto

    its commitment to make payment of balance land premium.

    12. It has been strenuously argued on behalf of the petitioner-company

    relying on Jamshedji Hormusji Wadia (supra) that the State and its

    instrumentalities have to be just, fair and reasonable in all their activities

    including those in the field of contracts. The State and its authorities

    playing the role of the landlord or tenant cannot be heard or seem causing

    displeasure or discomfort of Article 14 of the Constitution. However, in the

    light of above discussion as it has already been found that there is no

    arbitrariness in the action of Chief Executive Officer, Haldia Development

    Authority, respondent no.3 in issuing the letters under challenge, such

    observation in the above decision cannot come in the aid of the petitioner-

    company.

    13. It has been categorically contended in the writ petition that the

    petitioner-company virtually got physical possession of the 50 acres of

    vacant land from the date of acceptance of the offer of its allotment. Mr.

    Basu, learned advocate for said Authority relying on K.D Sharma (supra)

    argued that petitioner’s claim of possession having been handed over by

    the said authority without full and final payment in the absence of any

    possession certificate is incorrect and such claim is sincerely distorted fact
    39

    2011:CHC-AS:59

    and therefore, any relief granted would be based on distorted facts. Be that

    as it may, from the letter under challenge dated 4th July,2008 it is found

    that the said Authority requested the petitioner-company to deposit land

    premium amounting to Rs.4,28,75,000/- within fifteen days from the date

    of issuance of the letter otherwise HDA will evict the petitioner-company

    from HDA’s land. Such contention in the impugned letter clearly indicates

    that the Authority accepts the fact that the petitioner-company is in

    possession of the subject land though admittedly no possession letter has

    been issued in the favour of the petitioner-company. Hence, the argument

    that statement made in the writ petition that the petitioner-company is in

    possession of the subject land is distorted fact does not stand to reason

    and at the same time the ratio of the aforesaid decision does not apply to

    the facts of the case. It is, however, pertinent to note from the above fact

    that the petitioner-company continued in possession of the subject land

    from the date of acceptance of the offer letter without making payment of

    the balance land premium which in the opinion of this court is illegal. It is

    settled proposition that a person who seeks equity must do equity.

    14. It has been vociferously argued on behalf of the said Authority that

    the petitioner-company deliberately suppressed their own letter dated 6th

    June, 2008 wherefrom it would reveal that requirement of electricity and

    water had been met since August 2006 and thus has not approached this

    Hon’ble Court with unclean hands and as such the writ petition is liable to

    be dismissed on the ground of suppression of fact. In this context it is

    relevant to note that the petitioner-company in paragraph 14(a) has

    disclosed the existence of the aforesaid letter and craved leave to produce
    40

    2011:CHC-AS:59

    the same at the time of hearing and as such there is no such material

    suppression and therefore the argument advanced in this regard by the

    learned advocate for the said Authority falls short of merit.

    15. It has been vociferously contended on behalf of HDA that with the

    expiry of the stipulated period the offer stood extinguished but such

    contention cannot be sustained for the simple reason that HDA accepted

    rent for the subject land in respect of the offer letter and has also asked for

    payment of balance amount by its letter of reminder dated 27th January,

    2006 within certain period or else the offer should be treated as cancelled

    which presupposes existence of the offer on the date of issuance of such

    letter of reminder.

    16. In view of the above discussion the impugned letter dated 5th

    February, 2008 (Annexure P-13) and 4th July, 2008 (Annexure P14) of

    Chief Executive Officer, Haldia Development Authority, respondent no.3

    are held to be not arbitrary and thus does not call for interference.

    17. Admittedly, in compliance to order dated 18th July, 2008 of Co-

    ordinate Bench of this court, petitioner-company deposited the balance

    amount of Rs.96,25,000/- as per offer letter dated 11th September, 2001.

    18. Accordingly, petitioner-company is directed to deposit the remaining

    amount of the enhanced land premium of Rs.3,32,50,000/-

    (Rs.4,28,75,000/- less Rs.96,25,000/-) in favour of Haldia Development

    Authority within a period of six weeks from date of this order. Failing

    compliance as above, the Haldia Development Authority shall be at liberty

    to take steps for eviction of the petitioner-company from the subject land

    to the extent of 35 acres in accordance with law. In the event of eviction of
    41

    2011:CHC-AS:59

    the petitioner-company from the land-in-question, the said Authority shall

    refund the amount of land premium received by it from the petitioner-

    company over and above the value of 15 acres of land of Rs.82,50,000/-,

    together with interest @ 7% per annum from the respective dates of

    payment of the amount till the date of actual refund.

    19. With the aforesaid direction, the writ petition being WPA 15313 of

    2008 stands disposed of.

    20. Interim order, if any, stand vacated.

    21. All connected applications, if any, stand disposed of.

    22. Urgent photostat certified copy of the order, if applied for, be given to

    the parties upon compliance of all necessary legal formalities.

    (Bivas Pattanayak, J.)



    Source link

    LEAVE A REPLY

    Please enter your comment!
    Please enter your name here