09.04.2026 vs The State Of Meghalaya Represented By on 9 April, 2026

    0
    54
    ADVERTISEMENT

    Meghalaya High Court

    Date Of Decision: 09.04.2026 vs The State Of Meghalaya Represented By on 9 April, 2026

    Author: H. S. Thangkhiew

    Bench: H. S. Thangkhiew

                                                            2026:MLHC:328
    
    
    
    
    Serial No. 03
    Supplementary List
                         HIGH COURT OF MEGHALAYA
                                  AT SHILLONG
    WP(C) No. 166 of 2025
                                              Date of Decision: 09.04.2026
    Shri Firstbornson Lyngkhoi,
    S/o (L) L. Lyngdoh,
    R/o Mawten, Mawkyrwat,
    South West Khasi Hills District, Meghalaya
                                                      .... Petitioner(s)
                 Versus
    
       1. The State of Meghalaya represented by
          The Chief Secretary, Government of Meghalaya, Shillong.
    
       2. The Department of Public Works (Roads & Building) Department,
          Represented by the Secretary, Government of Meghalaya.
    
       3. The Chief Engineer, Public Works Department (Roads)
          Lachumiere, Shillong Meghalaya. 793119, Meghalaya
    
       4. The Superintendent Engineer, Western Circle,
          Public Works Department (Roads), Nongstoin,
          West Khasi Hills District, Meghalaya.
    
       5. The Executive Engineer, Public Works Department (Roads),
          Nongstoin Division, Nongstoin - 793119,
          West Khasi Hills District, Meghalaya.
    
       6. Shri. Bunsing Sohphoh,
          R/o Upper New Colony. Laitumkhrah. Shillong-03,
          East Khasi Hills District, Meghalaya.
    
       7. Shri. Specialist Rilung Marbaniang,
          R/o Pyndengrei, Nongstoin,
          West Khasi Hills District, Meghalaya-793119.
    
                                                                  Page 1 of 12
                                                           2026:MLHC:328
    
    
    
    
       8. Smti. Banrihun Wahlang,
          R/o Nongrangoi, Nongstoin,
          West Khasi Hills District, Meghalaya-793119.
    
       9. Smti. Brillianda Marngar,
          R/o Lumpyngad, Nongstoin,
          West Khasi Hills District. Meghalaya-793119.
    
       10. Smti. Droining lawphniaw,
          R/o Upper New Nongstpon, Nongstoin,
          West Khasi Hills District, Meghalaya-793119.
    
       11. Smti. Kynsai Kurbah,
          R/o New Nongstoin, Nongstoin,
          West Khasi Hills District, Meghalaya-793119.
    
       12. Shri. Ioanis Lyngdoh,
          R/o Ksehkohlong, Nongstoin,
          West Khasi Hills District, Meghalaya-793119.
    
       13. Smti. Rosiful Wanniang,
          R/o Mawrusyiar, Nongstoin,
          West Khasi Hills District, Meghalaya-793119. ... Respondent(s)

    Coram:

    Hon’ble Mr. Justice H. S. Thangkhiew, Judge

    Appearance:

    For the Petitioner(s)    :    Ms. T. Sutnga, Adv. with
                                  Ms. A. Ksoo, Adv.
    For the Respondent(s)    :    Mr. A. Kumar, AG with
                                  Mrs. T. Yangi B, AAG
                                  Mr. J.N. Rynjah, GA (For R 1-5)
                                  Mr. G. Syngkrem, Adv. (For R 6-13)
    
    
    
                                                               Page 2 of 12
                                                               2026:MLHC:328
    
    
    
    

    __________________________________________________________

    i) Whether approved for reporting in Yes/No
    Law journals etc:

    ii)   Whether approved for publication                   Yes/No
          in press:
    
    
                       JUDGMENT AND ORDER(ORAL)
    
    

    1. The writ petitioner a registered Class-I Government contractor

    under the Public Works Department being aggrieved with the action of the

    respondent No. 5, in commencing the execution of a public road

    construction work for the “Improvement of the existing road including

    MBT of New Nongstoin to Nongstoin Village” including different link

    roads within Nongstoin in the month of October, 2024, without any

    approved sanction order or Notice Inviting Tender (NIT) is before this

    Court assailing the same.

    2. Ms. T. Sutnga, learned counsel for the petitioner submits that

    in October, 2024 on coming to learn that road construction activities were

    being undertaken along the stretch from New Nongstoin to Nongstoin

    Village under the PWD (Roads) Nongstoin Division, the petitioner had

    sought information under the RTI Act on 14.10.2024. In reply thereto she

    submits, it was explicitly stated no sanction had been issued, nor was any

    NIT floated. Thereafter, she submits the petitioner came across a letter

    dated 27.03.2025, whereby it was revealed that administrative approval and

    Page 3 of 12
    2026:MLHC:328

    sanction for construction and improvement of different link roads at

    Nongstoin Village, were approved only in the month of March, 2025, for

    an amount of Rs. 6,82,26,100/- (Rupees Six Crores Eighty-Two Lakhs

    Twenty-Six Thousand and One Hundred) only for the period of 2024-25.

    3. The learned counsel for the petitioner then submits that the

    respondents had acted illegally and arbitrary, inasmuch as, without the

    publication of a Notice Inviting Tender, the execution and commencement

    of the work had started in October, 2024 itself, prior to the receipt of

    administrative approval and sanction. The work she submits had been

    allotted with a mala fide intention to the respondents Nos. 6 to 13, in an

    oblique and un-transparent manner. It is further submitted that the petitioner

    has the right to participate in government contract works being a registered

    Class-I contractor, and the action of the respondents in favouring the

    selected persons without due process being followed in public matters, is

    illegal and arbitrary. The learned counsel has also contended that Courts

    have the power to review government actions including those related to

    infrastructure projects, to ensure that they are lawful and fair.

    4. In the instant case she submits, though the work in question was

    in relation to a congregation that was to be held by the Nongstoin Church,

    the manner in which local contractors were selected was totally arbitrary

    and in violation of established procedures. The learned counsel has then

    Page 4 of 12
    2026:MLHC:328

    referred to the additional affidavit filed on behalf of the petitioner to show

    that though the respondents had produced a letter which reflected that the

    selection of contractors was on the basis of a letter issued by the Balang

    Presbyterian, Nongstoin dated 19.09.2024, however the undertaking for the

    construction as annexed to the affidavit of the State respondents, had

    already been signed and submitted by the contractors on 16.09.2024, which

    was prior to the date of the letter of the Church. She therefore, submits that

    the manner and conduct of the State respondents with regard to the

    suggestion and recommendation, clearly shows that the allocation of work

    was done in a collusive manner and on extraneous considerations. The

    learned counsel has also touched upon the principles of the Rule of Law,

    that mandates that all actions must be in accordance with law and not be

    based on personal discretion or bias, especially with regard to the adherence

    to financial rules and procedures, which are designed to ensure

    transparency and prevent misuse of public funds. In conclusion, the learned

    counsel has submitted that this Court in exercise of powers under Article-

    226, has wide discretionary powers to mould the relief, even if the same is

    SPONSORED

    not pleaded or prayed for.

    5. In support of her case, the learned counsel has placed reliance on the

    following judgments: –

    i) State of Andhra Pradesh & Ors. vs. Dr. Rao, V.B.J. Chelikani
    & Ors. 2024 SCC Online Sc 3432

    Page 5 of 12
    2026:MLHC:328

    ii) Union of India & Ors. vs. Dinesh Engineer Corporation &
    Anr. (2001) 8 SCC 491

    iii) J. Ganapatha & Ors. vs. N. Selvarajalou Chetty Trust Rep.

    by its Trustees & Ors. 2025 SCC OnLine SC 633

    iv) Rajesh D. Darbar & Ors. vs. Narasingrao Krishnaji Kulkarni
    & Ors.
    (2003) 7 SCC 219

    v) M/s Power Carriers (India) Pvt. Ltd. vs. Shri G.M. Lanong &
    Ors. Writ Appeal No. 49 of 2010

    vi) The Meghalaya State Electricity Board (now Meghalaya
    Energy Corporation Ltd.) vs. Shri G.M. Lanong & Anr.
    Writ Appeal No. 6 of 2011

    6. The learned Advocate General assisted by Mr. J.N. Rynjah,

    learned GA for the respondents Nos. 1 to 5, at the outset has submitted that

    the writ petition does not survive for adjudication, as the work in question

    has been completed and that the petitioner has failed to provide justifiable

    ground for the delay in invoking writ remedy. It is submitted that the

    petitioner by his own admission, was aware about the on-going project in

    early October but however, filed the instant writ petition only in May, 2025,

    and as such on the ground of delay itself, the writ petition is not

    maintainable. It is further submitted that the writ petition is also liable to be

    dismissed, inasmuch as, the same relates to purely private interest of the

    petitioner in participating in the project at the cost of larger public interest,

    which is the improvement of the roads. The learned Advocate General, has

    Page 6 of 12
    2026:MLHC:328

    also submitted that the petitioner has failed to disclose the existence of any

    enforceable legal right in his favour, to seek a mandamus and on this failure

    to demonstrate any violation of a legal right or fundamental right, the writ

    petition is liable to be rejected.

    7. The work in question it is further submitted was assigned to the

    contractors due to urgency which had arisen out of an emergent situation

    i.e. the holding of the event of a major congregation in the State, and that

    on the plea of the Nongstoin Presbyterian Church, vide letter dated

    10.09.2024, the urgency of the project was recognised and local qualified

    and registered contractors who were aware of the ground realities, came

    forward to carry out the work, though with the knowledge that approval etc.

    would have taken time. The action of the respondents he submits, satisfies

    all the parameters that have been laid down by the Hon’ble Supreme Court,

    inasmuch as, the same was occasioned by genuine emergency, is in public

    interest and transparency was maintained through proper estimates with no

    advance payment, with the grant of work to multiple local contractors,

    based on their capability and past performance. With regard to the

    discrepancy in dates as pointed out by the learned counsel for the petitioner,

    the learned Advocate General has submitted that though the undertakings

    had been signed by the contractors prior to the recommendation made by

    the Church, the same was because the request of the Church was ongoing

    Page 7 of 12
    2026:MLHC:328

    as can be seen from the earlier letters dated 10.09.2024, requesting for

    construction of the road. He therefore, submits that there being no illegality

    in the entire process, the writ petition apart from having been rendered

    infructuous, is liable to be dismissed.

    8. Mr. G. Syngkrem, learned counsel for respondents 6 to 13, has

    adopted the submissions made by the learned Advocate General and has not

    advanced any other arguments, except to iterate that the settlement of works

    was occasioned due to the urgency involved and the private respondents

    having the capacity, were tasked with the same.

    9. Heard learned counsel for the parties. As observed, the

    grievance of the writ petitioner centers only around the deprivation of a

    chance to be considered for the aforementioned work, in spite of being

    eligible in all respects, due to the impugned actions of the State respondents

    who allocated the work to the respondents Nos. 6 to 13, without the same

    being tendered, or any due process being followed. In the narration of the

    facts as discussed above, the fact that the said work amounting to Rs.

    6,82,26,100/- (Rupees Six Crores Eighty-Two Lakhs Twenty-Six

    Thousand and One Hundred) had been allocated to the respondents Nos. 6

    to 13, without there being any semblance of due process such as the floating

    of a tender, is not disputed. Though strong objections have been raised by

    the State respondents on the ground of locus and delay, in the considered

    Page 8 of 12
    2026:MLHC:328

    view of this Court in the circumstances of the case, the same will not suffice

    to render the writ petition futile. The reason for this is primarily in the

    manner in which the work was allocated, which was admittedly not to

    public knowledge, or in the public domain, but confined only to the Church

    authority and the State respondents. Thus, it could only have been with the

    commencement of the construction, that the writ petitioner would be aware,

    or come to the knowledge that a project for which he also would have been

    otherwise eligible had been initiated. The subsequent steps taken such as

    obtaining the RTI replies and collating the other information, having been

    pursued by the petitioner, it therefore, cannot be held that the writ petition

    is hopelessly barred by delay. As for locus, the petitioner himself being an

    eligible contractor, the project being executed in the vicinity itself, for

    which he would have participated if the same was tendered, it is well within

    his right to question the procedure adopted in settling the work with the

    private respondents, de hors any known process.

    10. Coming to the sequence of events, it is noted from the

    submissions and materials on record, that it is an admitted fact that no

    procedure of tendering the work, or any action to ensure transparency or

    equal opportunity, had been adopted by the respondents. A perusal of the

    affidavit filed by the State respondents at Para-12 thereof, would show that

    the process for sanction had already started and the estimates for the said

    Page 9 of 12
    2026:MLHC:328

    work of the road, had already been submitted by the Executive Engineer,

    PWD (Roads) vide letter dated 29.02.2024 to the Chief Engineer.

    Notwithstanding this aspect, what deserves the attention of this Court as

    highlighted by the petitioner, is the manner of allocation and identification

    of the private respondents to be only the persons suitable to be favoured

    with this public largesse. This Court has also noted the glaring contradiction

    in the stand of the State respondents, who have maintained that the

    contractors were appointed solely on the recommendation of the Church

    authorities vide a letter dated 19.09.2024, which is part of the record, when

    in fact in their affidavit itself, at running Annexure-R/4, the State

    respondents had already obtained undertakings from the respective

    contractors on 16.09.2024, to execute the work even though sanction was

    awaited. It would also be pertinent to note herein that on a pointed query

    by the Court from the counsel for the private respondents on this point, no

    answer was forthcoming, which all the more reinforces the case of the

    petitioner as to the arbitrary manner of allocation of the work. Though it

    has been argued that the course of action taken by the State respondents

    was necessitated, due to the paucity of time required to put the project

    through a formal tender process, it is however not understood as to how

    only the respondents Nos. 6 to 13, were cherry picked to be favoured with

    Page 10 of 12
    2026:MLHC:328

    the said works and why no recourse was taken to a issuance of a Short

    Tender Notice as is the norm for urgent works.

    11. It is thus imperative to note at this juncture, that in matters

    involving dispensation of public largesse, such as allocation of contracts,

    or other resources, Courts especially the Supreme Court of India have laid

    down principles to ensure transparency, fairness and non-arbitrariness

    under Article-14 of the Constitution. It is therefore, necessary that the State

    must formulate well defined rules and guidelines before distributing any

    largesse to avoid arbitrary decisions. This would entail the adherence to the

    set procedure of public notification (tender), to allow competitive process,

    to maintain transparency in criteria, to ensure equal opportunity, to avoid

    arbitrariness, so that decisions must not be based on personal preferences,

    but should be rational and based on objective standards. To ensure

    accountability, the authorities should also document reasons for selecting

    or rejecting applicants, and if it is found necessary to deviate from

    following such due process or procedure, the same must be justified by the

    authorities, inasmuch as, the ultimate goal must be to serve public welfare

    not private or political interests.

    12. In conclusion, looking into the totality of circumstances, what

    can be clearly discerned is that there has been a clear deviation from the

    established procedure in the settlement of contracts, notwithstanding the

    Page 11 of 12
    2026:MLHC:328

    urgency, or the other factors such as the want of sanction, where the state

    respondents have sought to justify their impugned actions. However, as the

    works have since been completed, and the reliefs prayed for are no longer

    available for consideration, and though the writ petitioner would have only

    be a potential bidder had an NIT been floated, this Court while disposing

    of the instant writ petition, deems it fit to award costs to the petitioner

    quantified at Rs. 50,000/- (Rupees Fifty Thousand) only.

    13. The said cost, shall be borne by the State respondents to the

    extent of Rs. 10,000/- and the private respondents Nos. 6 to 13, Rs. 5,000/-

    each, to be paid within 4(four) weeks from the date of this order.

    14. For the foregoing reasons, and as ordered above, the instant

    writ application is closed and disposed of.

    JUDGE

    Meghalaya
    09.04.2026
    “V. Lyndem-PS”

    Signature Not Verified Page 12 of 12
    Digitally signed by
    VALENTINO LYNDEM
    Date: 2026.04.10 19:28:40 IST

    [ad_1]

    Source link

    LEAVE A REPLY

    Please enter your comment!
    Please enter your name here