Become a member

Get the best offers and updates relating to Liberty Case News.

― Advertisement ―

HomeHigh CourtMeghalaya High CourtThe State Of Meghalaya Represented By ... vs Shri Jolian Marak on...

The State Of Meghalaya Represented By … vs Shri Jolian Marak on 9 May, 2025

Meghalaya High Court

The State Of Meghalaya Represented By … vs Shri Jolian Marak on 9 May, 2025

Author: W. Diengdoh

Bench: W. Diengdoh

                                                            2025:MLHC:372-DB



Serial No.01
Daily List
                        HIGH COURT OF MEGHALAYA
                               AT SHILLONG
   FA No.2/2024

                                                       Date of CAV: 30.04.2025
                                             Date of Pronouncement: 09.05.2025
   1. The State of Meghalaya represented by the Commissioner and
   Secretary, Community and Rural Development, Shillong.
   2. The Director Community and Rural Development, Shillong.
   3. The Executive Engineer, Community and Rural Development,
   Shillong.                                     ..... Appellants

                                             Vs.
   Shri Jolian Marak                                    ..... Respondent
   Coram:
           Hon'ble Mr. Justice I.P. Mukerji, Chief Justice
           Hon'ble Mr. Justice W. Diengdoh, Judge
   Appearance:
   For the Appellants             : Mr. N.D. Chullai, AAG with
                                    Ms. Z. E. Nongkynrih, GA.
                                    Mr. E. R. Chyne, GA

   For the Respondent         :     Mr. A. S. Siddiqui, Sr. Adv with
                                    Mr. D. Hynniewta, Adv.

   i)          Whether approved for                        Yes
               reporting in Law journals etc.:

   ii)         Whether approved for publication            Yes/No
               in press:

   Note: For proper public information and transparency, any media
         reporting this judgment is directed to mention the
         composition of the bench by name of judges, while reporting
         this judgment/order.



                                                                       Page 1 of 7
                                                       2025:MLHC:372-DB




                            JUDGMENT

(Delivered by the Hon’ble, the Chief Justice)
The State of Meghalaya has preferred this appeal. They are

aggrieved by a judgment and decree made on 24th May, 2023 by the

learned Judge, Commercial Court, East Khasi Hills, Shillong in Money

Suit No.1 of 2016 between the parties.

By this judgment and decree, the respondent/plaintiff has been

awarded ₹9,85,098/- with interest at the rate of 12 per cent per annum

from the date of filing of the suit i.e. 24th October, 2016 till payment. In

addition, the appellant was directed to refund the security deposit of

₹5,99,613/- with interest at the rate of 12 per cent per annum from 24th

October, 2016 till payment. The respondent/plaintiff was also awarded

₹30,000/- as costs.

The principal ground of challenge of the appellant/defendant is

limitation. A hopelessly time-bared claim has been decreed for

₹9,85,098/-, it was submitted. Learned counsel for appellant/defendant

also attacked the decree on merits.

At this stage, it may be stated that it was conceded by learned

counsel for the appellant/defendant that his clients were ready and willing

to refund the security amount of ₹5,99,613/- as decreed.

Page 2 of 7

2025:MLHC:372-DB

The cause of grievance of the appellant/defendant is that the

agreement between the parties was entered into on 6th April, 2005. On

31st March, 2008 after completion of the work under the agreement, the

building was handed over by the respondent/plaintiff to the

appellant/defendant. After more than 5 years, on 19th August, 2013 a

revised claim was submitted by the respondent/plaintiff. The value of the

contract was ₹78,82,800/-. The respondent/plaintiff had been paid

₹68,97,704/- on handing over the completed building in full satisfaction

of his claim. The value of the contract was unilaterally revised by him to

₹1,07,03,265/-. The difference was claimed. On 15th April 2015, the

appellant/defendant refused payment of his claim. On that alleged cause

of action, the suit was filed in 2016, the respondent/plaintiff basing his

cause of action on the rejection of the revised bill and contending that the

suit had been filed within 3 years from that date, within the period of

limitation. According to the appellant/defendant, basing the accrual of the

cause of action and the right to sue on rejection of this revised bill of a

work completed long ago with the handing over of the building to the

appellant/defendant, was untenable. The suit was liable to be dismissed

outright on the ground of limitation.

Page 3 of 7

2025:MLHC:372-DB

In principle, the judgment of the Supreme Court in Nikhila

Divyang Mehta & anr v. Hitesh P. Sanghvi & ors decided on 15th April,

2025 (S.L.P. (C) No.13459 of 2024), is in accordance with my notion of

the start of the period of limitation in respect of a cause of action. The

start date is to be reckoned from the date when the cause of action with

the right to sue first arose and not from subsequent facts simply adding

to the cause of action. (See paragraph 24 of the judgment). The exception

is in case of admission, acknowledgement or part payment and so on

which extend the period of limitation, if made within the period of

limitation. (See Sections 18 and 19 of the Limitation Act, 1963).

Usually in a works contract Article 18 of the schedule to the

Limitation Act, 1963 applies. It lays down that where no time for

payment is prescribed, the period of limitation is three years from the date

the work is done. In case of contracts where running accounts of payment

are maintained by a RA bill, usually 113 of the Limitation Act, 1963,

applies. This Article provides that where no period of limitation is

provided in the schedule, time would be three years from when the right

to sue accrues. It would have to be seen when the running accounts bills

could be claimed to be payable and the suit is to be instituted within three

years from that date.

Page 4 of 7

2025:MLHC:372-DB

The case of the respondent, however, is identical on facts with

Aries & Aries v. Tamil Nadu Electricity Board decided by the Supreme

Court on 21st March, 2017 and reported in (2018) 12 SCC 393. Here the

work had been completed and payment made on 13th January, 1981.

Thereafter, the plaintiff contractor raised supplementary bills claiming

additional amounts through a legal notice dated 16th May, 1981. The

defendant in that case informed the plaintiff on 25th August, 1981, that

the matter was “under-study” and the reply would be sent in due course.

After about six months on 6th November 1981, the defendant replied that

the claims of the plaintiff were rejected. The suit was filed on 6th

November, 1984. The High Court dismissed the suit on the ground of

limitation.

The Supreme Court held that there was accrual of a fresh cause

of action and right to sue from the date the bills claiming additional

amounts in respect of the contract were rejected on 6th November, 1981.

The time period again started running for three years from such rejection.

In our case also a similar thing has happened.

I feel myself bound by the above decision. Therefore, the

argument based on the ground of limitation fails.

Now, I deal with the merit of the claims.

Page 5 of 7

2025:MLHC:372-DB

The value of the work to be done under the agreement was

₹78,82,800/-.

The appellants are agreeable to release the security deposit of

₹5,99,613/-. Hence, out of the contract value of ₹78,82,800/-,

₹68,97,704/- is deemed to have been received by the respondent/plaintiff,

inclusive of the security deposit.

The agreement was of 6th April, 2005. The construction was

completed in about three years and the building handed over to the

appellant on 31st March, 2008. Hence, the contract was fully discharged

by performance and came to an end. The respondent/plaintiff accepted

such payment and was silent for five years. Only on 19th August, 2013, a

revised claim was submitted. A claim for the balance ₹9,85,098/- was

also made.

Once a contract is concluded and discharged by full performance

and acceptance of payment, there is no scope of any additional claims or

payments under the same contract and that too after five years. Hence,

the claim for the balance ₹9,85,098/- was completely misconceived and

speculative. The learned judge made a serious error in entertaining such

claims. The part of the decree granting such claim is set aside. Such error

of the learned judge was aggravated by further entertainment of claims

Page 6 of 7
2025:MLHC:372-DB

based on a purported revised estimate. The decree which she has sought

to pass on such claim is vague and untenable. A decree must always be a

certain sum and not uncertain, contingent and vague.

For all those reasons, the respondent/plaintiff shall only be

entitled to a refund of the security deposit of ₹5,99,613/- with interest at

the reduced rate of seven per cent per annum from the date of filing the

suit i.e., 24th October, 2016 till payment. The order for payment of costs

is set aside. The impugned judgment and decree is modified to the above

extent.

The appeal is partly allowed to the above extent.

After pronouncement of the judgment, it was submitted by Mr.

N.D. Chullai, learned AAG that the appellant has deposited ₹20,00,000/-

with the Registrar General of this Court. This deposit may be made over

to the appellant No.1 by the Registrar General within two weeks of

communication of this order.

                                (W. Diengdoh)                                   (I.P. Mukerji)
                                    Judge                                        Chief Justice

                       Meghalaya
                       09.05.2025
                        "Lam DR-PS"



                                                                                          Page 7 of 7

Signature Not Verified
Digitally signed by
LAMPHRANG KHARCHANDY
Date: 2025.05.09 03:35:22 IST



Source link