Supreme Court – Daily Orders
The Kerala Water Authority vs T I Raju on 9 February, 2026
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NO(s). OF 2026
(@ SLP(C) NO(s). 17823/2023)
THE KERALA WATER AUTHORITY & ORS. Appellant(s)
VERSUS
T I RAJU & ORS. Respondent(s)
WITH
CIVIL APPEAL NO(s). OF 2026
(@ SLP(C) NO(s). 24631/2023)
O R D E R
1. Leave granted.
2. The brief facts relevant for determination of the
present appeals arising out of the same impugned order
dated 23.02.2023 are produced as under:
i) The appellant – T.I. Raju in Civil Appeal arising out
of SLP (C) No.24631/2023, who is a Government
Contractor had entered into a preliminary agreement
dated 30.04.2013 for the execution of a work contract
pertaining to the construction of Sewage Treatment
Plant at Medical College, Calicut with appellant No.1
in Civil Appeal arising out of SLP (C) No.17823/2023.
ii) On 07.07.2014, the construction work was completed and
the principal sum of Rs.86,64,846/- was due to
appellant – T.I. Raju. Thereafter, in 2015, the
Signature Not VerifiedDigitally signed by
RADHA SHARMA
Date: 2026.02.17 appellant-T.I. Raju preferred a Writ Petition before
18:01:20 IST
Reason:the High Court seeking disbursal of the principal sum
1
due to him, which was allowed and resultantly, thefunds were released in his favour by 02.03.2016.
iii) On 25.11.2017, the appellant-T.I. Raju filed a suit for
recovery of interest for delayed payment between the
completion of work till the date of disbursal of
pending dues, i.e. between 09.07.2014 to 02.03.2016 at
the rate of 14% per annum.
iv) The suit filed by the plaintiff/appellant-T.I. Raju was
decreed holding that the defendants/appellants in Civil
Appeal @ SLP (C) No17823/2023 are jointly and severally
liable to pay a sum of Rs.21,48,411/-, with an interest
of 14% from the date of filing the suit till the date
of realization.
v) The High Court partly allowed the appeal filed by the
defendant Nos.2, 3 and 7 against the decree for
recovery of interest and reduced the rate of interest
to 9% per annum, which amounts to a sum of
Rs.12,90,469/-.
3. The present issue is one of the payment of
interests. Clause (5) of the preliminary agreement dated
30.04.2013 states as under:
“The contractor further assures that it is clearly
understood that the settlement of claims either by
part bill or by final bills will be made only
accordingly to the availability of budget provisions
2
allotment of funds made with the Divisional Officerin charge of the work under the respective heads of
account in which the work is sanctioned and arranged
and also subject to the seniority of such bills. No
claims or interest for damages whatsoever shall be
made for the belated settlement of claims of bill.”
4. On a reading of the aforesaid clause, it is clear
that at the time when the tender was floated for a public
project, a conscious decision was taken to commence the
same, notwithstanding the issue pertaining to the
availability of necessary funds. For this reason, clause
(5) has been introduced at the first place in the
preliminary agreement. This clause not only deals with the
issue pertaining to the belated payments, but also touches
upon the consequential interest which is to be paid in the
nature of damages. This is a clause introduced on behalf
of the contractor meaning thereby, that the contractor is
not only aware of the said clause but he is the one who
introduced the same, and hence, he is expected to quote
the amount, while being conscious of a situation
pertaining to belated payments followed by the
consequential interest in the nature of damages.
5. Previously, in the writ petition filed by the
3
respondent – T. I. Raju, the High Court left the issue ofthe payment of interest open. Thereafter, the respondent
filed the subject suit for recovery of interest on the
principal amount. The decree was modified by the High
Court in the impugned judgment to the effect of payment of
interest at the rate of 9% per annum, on belated payment
of the principal sum, and the pendente lite interest was
reduced to 6% per annum.
6. Though the provision under Section 3(1) of Interest
Act, 1978 has been taken note of by the High Court, and the
exception contained under Section 3(3) of the Interest Act,
1978 has been ignored. The object of the Interest Act, 1978
is to mandate the payment of interest to the parties in the
absence of, or any vacuum in the agreement, or where the
interest so fixed is contrary to law, being in the nature
of an exorbitant charge.
7. In other words, when the parties have agreed upon by
way of a contract executed between them, either to give
away the interest so accrued or to receive belated
payments, they are indeed governed by the terms mentioned
thereunder. Therefore clause (5) of the agreement is
settled between the parties and thus binding upon them.
There is no question regarding the appellants being in a
position to dictate the terms of the same, since clause 5
of the agreement merely shows the nature of the contract
entered into.
8. The appellants in Civil Appeal arising out of SLP(C)
4
No. 17823/2023 fall within the definition of ‘State’ under
Article 12 of the Constitution of India, as the project
was undertaken for public purposes. The idea was to
initiate the project so that the general public would not
suffer due of lack of infrastructure, notwithstanding any
delay in the payment. Any profits in favour of the
contractor is also a governing factor to the said clause.
9. In our considered view, the High Court did not take
into consideration Section 3(3) of the Interest Act, 1978,
and thereafter, only read the clause 5 of the preliminary
agreement, contextually.
10. Much reliance has been placed by the learned Senior
counsel appearing for the respondents on Section 34 of the
Code of Civil Procedure, 1908 (for short ‘CPC’). Section
34 of the CPC merely speaks about the rate of interest to
be applied and, therefore, sub-section (5) cannot be
interpreted to have an overriding effect on Section 3(3)
of the Interest Act, 1978.
11. Thus, looking from any perspective, we are not in a
position to give an imprimatur to the decision of the High
Court.
12. In such view of the matter, the impugned order(s)
are set aside. Consequently, the appeal filed by the
appellants in Civil Appeal arising out of SLP(C)
5
17823/2023 stands allowed and the appeal filed by the
appellant in Civil Appeal arising out of SLP(C) No.
24631/2023 stands dismissed.
13. Pending application(s), if any, shall stand disposed
of.
………………………………………………………J.
( M.M. SUNDRESH )
…………………………………………………………J.
( NONGMEIKAPAM KOTISWAR SINGH )
NEW DELHI;
FEBRUARY 09, 2026
6
ITEM NO.63 COURT NO.3 SECTION XI-B
S U P R E M E C O U R T O F I N D I A
RECORD OF PROCEEDINGS
Petition(s) for Special Leave to Appeal (C) No(s). 17823/2023
[Arising out of impugned final judgment and order dated 23-02-2023
in RFA No. 56/2020 passed by the High Court of Kerala at Ernakulam]
THE KERALA WATER AUTHORITY & ORS. Petitioner(s)
VERSUS
T I RAJU & ORS. Respondent(s)
WITH
SLP(C) No. 24631/2023 (XI-B)
(FOR ADMISSION and I.R.)
Date : 09-02-2026 This petition was called on for hearing today.
CORAM :
HON’BLE MR. JUSTICE M.M. SUNDRESH
HON’BLE MR. JUSTICE NONGMEIKAPAM KOTISWAR SINGHFor Petitioner(s) Mr. Bijo Mathew Joy, AOR
Ms. Gifty Marium Joseph, Adv.
Mr. Thomas. P. Joseph, Sr. Adv.
Mr. M Gireesh Kumar, Adv.
Mr. Ankur S. Kulkarni, AOR
Mr. Sanjay Singh, Adv.
Ms. Sneha Mathew, Adv.
For Respondent(s) Mr. Thomas. P. Joseph, Sr. Adv.
Mr. M. Gireesh Kumar, Adv.
Mr. Ankur S. Kulkarni, AOR
Mr. Sanjay Singh, Adv.
Ms. Sneha Mathew, Adv.
Mr. Bijo Mathew Joy, AOR
Ms. Gifty Marium Joseph, Adv.
Mr. C. K. Sasi, AOR
Ms. Meena K Poulose, Adv.
UPON hearing the counsel the Court made the following
O R D E R
1. Leave granted.
7
2. The appeal filed by the appellants in Civil Appeal
arising out of SLP(C) No. 17823/2023 stands allowed
and the appeal filed by the appellant in Civil Appeal
arising out of SLP(C) No. 24631/2023 stands dismissed
in terms of the signed order.
3. Pending application(s), if any, shall stand disposed
of.
(RADHA SHARMA) (POONAM VAID)
ASTT. REGISTRAR-cum-PS ASSISTANT REGISTRAR
(Signed order is placed on the file)
8




