Shri Shailendra Kumar Joshi vs The State Of Telangana on 22 April, 2026

    0
    36
    ADVERTISEMENT

    Telangana High Court

    Shri Shailendra Kumar Joshi vs The State Of Telangana on 22 April, 2026

     * THE HON'BLE THE CHIEF JUSTICE SRI APARESH KUMAR SINGH
                                    AND
               * THE HON'BLE SRI JUSTICE G.M.MOHIUDDIN
    
    
      + WRIT PETITION Nos.24835, 24837, 26367 and 29352 of 2025
    
    % Dated: 22.04.2026
    
    W.P.No.24835 of 2025:
    
    # Thanneeru Harish Rao and others
                                                             ...Petitioners
                                      vs.
    $ The State of Telangana, General Administration Department,
    Secretariat Buildings, Hyderabad, Rep. by its Chief Secretary
    and others.
                                                             ...Respondents
    ! Counsel for the petitioner in W.P.No.24835 of 2025:
          Mr. C.A.Sundaram, learned Senior Counsel,
          representing Mr. Jaggannagari Venkat Sai
    ! Counsel for the petitioner in W.P.No.24837 of 2025:
          Mr. Dama Seshadri Naidu, learned Senior Counsel,
          Representing Mr. Ponugoti Mohith Rao
    ! Counsel for the petitioner in W.P.No.26367 of 2025:
          Mr. Tarun G. Reddy
    ! Counsel for the petitioner in W.P.No.29352 of 2025:
          Mr. J.Ramachandra Rao, learned Senior Counsel,
          representing Mr. Jagannagari Venkat Sai
    ^ Counsel for respondents No.1 and 2 in W.P.No.24835 of 2025:
          Dr. Abhishek Manu Singhvi,
          learned Senior Counsel, representing Advocate General.
                                             2
    
    
    
    
    ^ Counsel for respondents No.1 and 2 in W.P.Nos.24837 and 26367
    of 2025:
              Mr. S.Niranjan Reddy, learned Senior Counsel,
              along with Mr. A.Sudarshan Reddy,
              learned Advocate General, duly assisted by
              Mr. I.V.Siddhivardhana, learned Special Government Pleader.
    ^ Counsel for respondents No.1 and 2 in W.P.No.29352 of 2025:
              Mr. P.Sri Raghu Ram, learned Senior Counsel,
              representing Advocate General.
    
    
    < Gist:
    > Head Note:
    ? Cases referred
              1. 1995 SCC OnLine AP 356
              2. (1989) 1 SCC 494
              3. 2004 SCC OnLine All 1891
              4. AIR 1958 SC 538
              5. (2003) 4 SCC 557
              6. (2008) 12 SCC 675
              7. (2001) 6 SCC 181
              8. (2003) 8 SCC 361
              9. 1968 SCC OnLine SC 46
              10. (2001) 6 SCC 50
              11. (2009) 9 SCC 173
              12. (2004) 12 SCC 278
              13. (1984) 1 SCC 43
              14. (2009) 13 SCC 102
              15. (1977) 4 SCC 608
              16. (1994) 6 SCC 632
              17. AIR 1967 SC 122
              18. (1990) 2 SCC 48
              19. AIR 1958 SC 300
              20. (2016) 7 SCC 221
                                     3
    
    
    
    
           IN THE HIGH COURT FOR THE STATE OF TELANGANA
                              AT HYDERABAD
    
    
    THE HON'BLE THE CHIEF JUSTICE SRI APARESH KUMAR SINGH
                                    AND
               THE HON'BLE SRI JUSTICE G.M.MOHIUDDIN
    
         WRIT PETITION Nos. 24835, 24837, 26367 and 29352 of 2025
    
    
                             Dated: 22.04.2026
    
    
    W.P.No.24835 of 2025:
    Between:
    Thanneeru Harish Rao
                                                          ...Petitioner
                                      and
    The State of Telangana, Rep. by its Chief Secretary,
    General Administration Department, Secretariat, Hyderabad,
    and 2 others.
                                                          ...Respondents
    
    W.P.No.24837 of 2025:
    Between:
    Sri Kalvakuntla Chandrashekar Rao
                                                          ...Petitioner
                                      and
    The State of Telangana, Rep. by its Chief Secretary,
    General Administration Department, Secretariat, Hyderabad,
    and 2 others.
                                                          ...Respondents
    
    W.P.No.26367 of 2025:
    Between:
    Shri Shailendra Kumar Joshi
                                                          ...Petitioner
                                       4
    
    
    
    
                                      and
    The State of Telangana, General Administration Department,
    Secretariat Buildings, Hyderabad, Rep. by its Chief Secretary,
    and 2 others.
                                                            ...Respondents
    
    W.P.No.29352 of 2025:
    Between:
    Smt. Smita Sabharwal
                                                              ...Petitioner
                                      and
    The State of Telangana, Rep. by its Chief Secretary,
    General Administration Department, Secretariat, Hyderabad,
    and 2 others.
                                                          ...Respondents
    
    COMMON JUDGMENT (Aparesh Kumar Singh, CJ):
    
          Mr. C.A.Sundaram, learned Senior Counsel appears for
    
    Mr. Jaggannagari Venkat Sai, learned counsel for the petitioner in
    
    W.P.No.24835 of 2025.
    
          Mr. Dama Seshadri Naidu, learned Senior Counsel appears for
    
    Mr. Ponugoti Mohith Rao, learned counsel for the petitioner in
    
    W.P.No.24837 of 2025.
    
          Mr. Tarun G. Reddy, learned counsel appears for the petitioner in
    
    W.P.No.26367 of 2025.
    
          Mr. J.Ramachandra Rao, learned Senior Counsel appears for
    
    Mr. Jagannagari Venkat Sai, learned counsel for the petitioner in
    
    W.P.No.29352 of 2025.
                                          5
    
    
    
    
           Dr. Abhishek Manu Singhvi, learned Senior Counsel appears for
    
    the State in W.P.No.24835 of 2025.
    
           Mr. S.Niranjan Reddy, learned Senior Counsel, along with
    
    Mr. A.Sudarshan Reddy, learned Advocate General duly assisted by
    
    Mr. I.V.Siddhivardhana, learned Special Government Pleader appears
    
    for the State in W.P.Nos.24837 and 26367 of 2025.
    
           Mr. P.Sri Raghu Ram, learned Senior Counsel appears for the
    
    State in W.P.No.29352 of 2025.
    
    
    2.     A Commission of Inquiry headed by Justice Pinaki Chandra
    
    Ghose, Former Judge of Supreme Court of India, was appointed in
    
    exercise of powers conferred by Section 3 of the Commissions of
    
    Inquiry Act, 1952 (hereinafter referred to as 'Act of 1952'), to conduct
    
    judicial inquiry on certain allegations of irregularities and embezzlement
    
    of public funds by corrupt practices in constructing the barrages of
    
    Medigadda and Annaram Reservoirs of Kaleshwaram Project, on the
    
    Terms of Reference contained therein. The Commission was conferred
    
    with the powers under sub-sections (2), (3), (4) and (5) of Section 5 of
    
    the Act of 1952. The Commission, after examination of several
    
    witnesses and documents, submitted its Report on 31.07.2025. The writ
                                        6
    
    
    
    
    petitioners being aggrieved by the findings preferred the present writ
    
    petitions.
    
    
    3.     The petitioner (THR) in writ petition No.24835 of 2025 is the
    
    former Minister for Irrigation in the erstwhile Telangana Government.
    
           The petitioner (KCR) in writ petition No.24837 of 2025 is the
    
    former Chief Minister of Telangana Government.
    
           The petitioner (SKJ) in writ petition No.26367 of 2025 is the
    
    Retired Indian Administrative Service Officer.
    
           The petitioner (SS) in writ petition No.29352 of 2025 is the
    
    Indian Administrative Officer serving in the State of Telangana.
    
           The petitioners in W.P.Nos.24835, 24837, 26367 and 29352 of
    
    2025 are referred to as THR, KCR, SKJ and SS respectively hereinafter.
    
    
    4.     It is stated by the petitioners that upon submission of the Report
    
    by the Commission on 31.07.2025, in a Press Conference which was
    
    convened by the Present Chief Minister, a power point presentation was
    
    made by the present Irrigation Minister on 04.08.2025. The petitioners
    
    claimed to have learnt about the prejudicial and defamatory findings
    
    against them on the basis of the power point presentation made during
    
    the Press Conference. Except in writ petition No.26367 of 2025, the
    
    petitioners in the other writ petitions, approached the writ court with
                                          7
    
    
    
    
    common prayer for a declaration that G.O.Ms.No.6, dated 14.03.2024,
    
    whereby Justice Pinaki Chandra Ghose, Former Judge of the Supreme
    
    Court of India, was appointed to conduct judicial inquiry into the
    
    alleged negligence, irregularities and lacunae in planning, designing and
    
    construction of Medigadda, Annaram and Sundilla barrages, which form
    
    integral components of the Kaleshwaram Lift Irrigation Scheme and to
    
    fix up responsibilities for any authority/official who extended undue
    
    favours to the agencies/contractors, is illegal, arbitrary, unconstitutional
    
    and ultra vires the provisions of the Act of 1952 and contrary to the
    
    judgments passed by this Court and Hon'ble Supreme Court of India.
    
    All the writ petitioners have sought a declaration that the observations
    
    and findings of the Commission in its Report dated 31.07.2025, which
    
    are prejudicial and defamatory as against them, are illegal and arbitrary,
    
    premeditated and mala fide and prayed for setting aside the same as they
    
    have been made without providing notice under Sections 8B and 8C of
    
    the Act of 1952 in violation of the principles of natural justice. They
    
    have also sought a declaration that the action of the respondents-State in
    
    making repeated publications of the Report of the Commission, dated
    
    31.07.2025 is manifestly arbitrary, illegal, mala fide, biased and
    
    premeditated and violative of principles of natural justice.
                                         8
    
    
    
    
    5.     During the proceedings of the writ petitions, interim orders were
    
    passed in the case of individual writ petitioners that no action based
    
    upon the adverse findings of the Commission should be taken against
    
    the petitioners, during the pendency of the writ petitions. It was brought
    
    to the notice of this Court that the Report was submitted before the
    
    Legislative Assembly on 31.08.2025. It was also submitted by the
    
    learned Advocate General that no adverse action based on the findings
    
    of the Report was going to be taken against the writ petitioners.
    
    However, the matter had been handed over to the Central Bureau of
    
    Investigation (CBI) vide G.O.Ms.No.104, dated 01.09.2025 to conduct
    
    investigation into the allegations of irregularities, embezzlement of
    
    public funds and corrupt practices etc., in the matter of construction of
    
    Medigadda, Annaram and Sundilla barrages of Kaleshwaram Irrigation
    
    Project against all the accused persons including the public servants and
    
    private persons, companies etc.
    
    
    6.     After completion of the pleadings, the matters had been heard at
    
    length. Detailed submissions have been made on behalf of the writ
    
    petitioners and the respondents 1 and 2-State.
                                       9
    
    
    
    
    SUBMISSIONS OF THE LEARNED COUNSEL FOR THE
    PETITIONERS:
    
    W.P.No.24835 of 2025 (THR):
    
    
    7.    Mr. C.A.Sundaram, learned Senior Counsel appearing on behalf
    
    of the writ petitioner, THR in W.P.No.24835 of 2025 has made
    
    submissions on the background of the inter-state project to utilise
    
    Godavari water for irrigational purposes and to cater to the needs of
    
    drinking water and industrial purposes. The Government of Telangana
    
    in the year 2014 had engaged the services of Water and Power
    
    Consultancy Services (WAPCO) - a Union of India Public Sector
    
    Undertaking to investigate, identify and recommend alternative site for
    
    barrage construction. The sites were identified as Medigadda, Annaram
    
    and Sundilla. According to the petitioner, in the year 2023, one of the
    
    piers, i.e., Pillar No.20 of Medigadda barrage subsided due to various
    
    factors including excessive rainfall during monsoon season and other
    
    circumstances beyond the control. They bore no relation to the design
    
    and engineering of the barrage. However, the newly elected
    
    Government, as part of their strategy to malign and discredit the
    
    previous Government and to dismantle the important infrastructural and
                                         10
    
    
    
    
    welfare projects executed by the previous administration, appointed the
    
    Commission of Inquiry with illegal, arbitrary and mala fide intentions.
    
    
    8.     One of the grounds to challenge G.O.Ms.No.6, dated 14.03.2024
    
    is that it seeks to conduct judicial inquiry. The Commission of Inquiry
    
    constituted under Section 3 of the Act of 1952 is a fact finding inquiry
    
    and not a judicial inquiry. A judicial inquiry is not permissible under the
    
    Act of 1952. It is submitted that the recitals of the Government Order
    
    record conclusive findings on the reasons for sinking of the piers of
    
    Medigadda (Lakshmi) barrage suggesting negligence, irregularities and
    
    lack of proper care to ensure quality work in the construction of the
    
    barrages leading to major loss to the public exchequer relying on the
    
    report of the National Dam Safety Authority (NDSA). The Terms of
    
    Reference of the Commission of Inquiry are indicative of premeditated
    
    state of mind of the Government to indict the petitioner and other
    
    persons entrusted with the task of decision making, execution of the
    
    contract and the maintenance of the three barrages.
    
    
    9.     The learned Senior Counsel for the petitioner has referred to
    
    certain adverse findings rendered by the Commission against the
    
    petitioner without any statutory notice under Sections 8B and 8C of the
    
    Act of 1952. The decision of the erstwhile High Court of Andhra
                                        11
    
    
    
    
    Pradesh rendered in K.Vijaya Bhaskar Reddy vs. Government of
    
    Andhra Pradesh 1 has been referred to in this regard.
    
    
    10.       Learned Senor Counsel has, in this background, assailed the
    
    constitution of a judicial inquiry as being impermissible under Section 3
    
    of the Act of 1952. The proceedings are legally biased. Section 4 of the
    
    Act of 1952 prescribes issuance of summons to secure the attendance of
    
    any person, to examine him on oath as a witness, to discover any
    
    document, to receive evidence on affidavit and requisition any public
    
    record or copy thereof. It empowers the Commission to issue
    
    commissions for the examination of witnesses or documents and any
    
    other matter which may be prescribed. The Commission has been
    
    conferred certain powers of a civil court, while trying a suit under the
    
    Code of Civil Procedure, 1908. According to the petitioner, under
    
    Section 5 of the Act of 1952, the appropriate Government may confer
    
    additional powers upon the Commission having regard to the nature of
    
    inquiry to be made and other circumstances of the case, by notification
    
    in the Official Gazette. He has referred to the powers conferred such as,
    
    sub-section (2) which provides that the Commission can require any
    
    person to furnish any information on such points or matters as, in the
    
    opinion of the Commission, may be useful for, or relevant to, the subject
    1
        1995 SCC OnLine AP 356
                                         12
    
    
    
    
    matter of the inquiry. Any person so required shall be deemed to be
    
    legally bound to furnish such information within the meaning of
    
    Sections 176 and 177 of the Indian Penal Code, 1860 (IPC). He submits
    
    that for the purposes of inquiry under these provisions, the Commission
    
    is deemed to be a civil court. As per sub-section (4) of Section 5, when
    
    any offence described in Sections 175, 178, 179, 180 or 228 of IPC is
    
    committed in the view or presence of the Commission, it may forward
    
    the case to a Magistrate as per the provisions of the Code of Criminal
    
    Procedure, 1973 to hear the complaint. He submits that any proceeding
    
    before the Commission is deemed to be a judicial proceeding within the
    
    meaning of Sections 193 and 228 of IPC, as per sub-section (5).
    
    However, these provisions do not clothe the Commission of Inquiry
    
    constituted under the Act of 1952 as a judicial inquiry. According to
    
    him, Section 8B of the Act of 1952 provides that the Commission of
    
    Inquiry shall give a reasonable opportunity to the person to be heard and
    
    to produce evidence, if the Commission considers it necessary to inquire
    
    into the conduct of any person, or is of the opinion that the reputation of
    
    any person is likely to be prejudicially affected by the inquiry. That such
    
    person should be provided with the materials and evidence on which the
    
    Commission is likely to form an opinion touching his conduct and
    
    reputation. However, no such notice was given to the petitioner. The
                                        13
    
    
    
    
    only notice or summons issued on 20.05.2025 upon the petitioner
    
    required him to appear before the Commission as a witness on
    
    09.06.2025. The petitioner himself asked for copies of the reports on
    
    06.06.2025, which were supplied to him on 09.06.2025 only on the date
    
    of his appearance before the Commission of Inquiry. These documents
    
    relate to cabinet resolutions on this project. Learned Senior Counsel for
    
    the petitioner has also countered the contention of the respondents-State
    
    that petitioner voluntarily participated in the inquiry and since all the
    
    documents relied upon in the inquiry, including the affidavits, enquiry
    
    report and cabinet resolutions were supplied to him on his request, no
    
    prejudice has been caused to the petitioner. However, according to the
    
    petitioner, none of these documents implicate him. No incriminating
    
    materials were put to him though ultimate observations and findings by
    
    the Commission in its Report dated 31.07.2025 are prejudicial and
    
    adverse on his conduct and reputation. The petitioner was examined as
    
    Commission Witness No.114 on 09.06.2025. There are critical findings
    
    of the Commission on the petitioner, who was the then Irrigation
    
    Minister and also against the then Chief Minister (KCR). The petitioner,
    
    for the first time, came to know about these findings when they were
    
    made public by way of power point presentation before the Media in a
    
    Press Conference convened by the Chief Minister, though the Report of
                                         14
    
    
    
    
    the Commission had not been tabled before the Assembly. Therefore,
    
    the constitution of Commission, the manner in which the Inquiry has
    
    been conducted, the procedure adopted by the Commission during the
    
    inquiry proceedings and its findings, are vitiated and actuated by bias.
    
    
    11.       Learned Senior Counsel for the petitioner has referred to the
    
    decision of the apex court in Kiran Bedi vs. Committee of Inquiry 2 in
    
    support of his submission that the petitioner was not afforded an
    
    opportunity to defend himself and to cross-examine the witnesses before
    
    the adverse findings were recorded against him. Reliance has also been
    
    placed in the case of K.Vijaya Bhaskar Reddy (supra) to submit that a
    
    person whose conduct and reputation are likely to be affected by the
    
    enquiry has a right to cross-examine and engage a legal practitioner
    
    before the Commission of Inquiry. He submits that the High Court in
    
    that case had quashed the impugned notice under Section 8B of the Act
    
    of 1952. Reliance has also been placed on Jai Prakash Associates
    
    Limited vs. State of Uttar Pradesh 3. Learned Senior Counsel has
    
    drawn the attention of the Court to the findings of the Commission
    
    highlighted at page 102 of the writ petition as being seriously prejudicial
    
    to the petitioner. Based on these submissions, learned Senior Counsel
    
    
    2
        (1989) 1 SCC 494
    3
        2004 SCC OnLine All 1891
                                       15
    
    
    
    
    had sought quashing of the Report containing the findings of the
    
    Commission with a declaration that they cannot be used against the
    
    petitioner.
    
    
    W.P.No.24837 of 2025 (KCR):
    
    
    12.    Mr. D.Seshadri Naidu, learned Senior Counsel for the petitioner,
    
    KCR in W.P.No.24837 of 2025, who was the former Chief Minister, has
    
    adopted the submissions made by Mr. C.A.Sundaram, learned Senior
    
    Counsel. It is submitted that the petitioner, KCR has not waived off the
    
    charge of procedural violations on the ground of non-issuance of the
    
    mandatory notice under Sections 8B and 8C of the Act of 1952. There is
    
    no substantial compliance of the notice as required under Sections 8B
    
    and 8C of the Act of 1952. According to him, not only the constitution
    
    of the Commission of Inquiry under G.O.Ms.No.6, dated 14.03.2024 is
    
    ultra vires the Act of 1952, but also the Report submitted by the
    
    Commission is arbitrary and illegal, fit to be set aside. He has also
    
    referred to the summons dated 20.05.2025, whereby the petitioner was
    
    asked to appear before the Commission for being examined and hear
    
    him upon the Terms of Reference. In order to draw comparison, the
    
    language and substance of the summons dated 14.04.2024 issued upon
    
    the petitioner by the Commission of Inquiry headed by Justice
                                        16
    
    
    
    
    L.Narasimha Reddy, Former Chief Justice of Patna High Court, to
    
    enquire into the correctness and propriety of the decisions taken by the
    
    erstwhile Government of Telangana concerning power procurement
    
    from Chhattisgarh by the State DISCOMs and the award of contracts
    
    relating to the Bhadradri and Yadadri Thermal Power Projects without
    
    competitive bidding, have been adverted to. He submitted that though
    
    the form and substance of the summons dated 14.04.2024 also not fully
    
    meet the requirement of Section 8B of the Act of 1952 but to some
    
    extent a reasonable opportunity was given to defend himself against
    
    materials and findings, which were likely to lead to adverse findings
    
    upon his conduct and reputation, whereas the summons dated
    
    20.05.2025 issued by the present Commission of Inquiry required the
    
    petitioner to appear as a witness and depose before the Commission.
    
    
    13.   Learned Senior Counsel for the petitioner has also sought to
    
    explain that the powers of the Commission under Sections 4 and 5 is for
    
    collection of evidence by requiring the presence of a person as witnesses
    
    and for production of documents. Section 8B of Act of 1952, inserted by
    
    the Act 79 of 1971, with effect from 30.12.1971, on the other hand
    
    specifically grants reasonable opportunity to defend oneself if in the
    
    opinion of the Commission, any findings rendered by it are likely to
                                        17
    
    
    
    
    affect the conduct or reputation of such a person. These are two stages in
    
    the conduct of any such enquiry by the Commission. Section 8C confers
    
    the right to cross-examine and be represented by a legal practitioner to
    
    any such person whose conduct or reputation is likely to be impeached
    
    on the basis of materials collected during such enquiry. Rule 4 of the
    
    Commissions of Inquiry (Central) Rules, 1972 (hereinafter referred to as
    
    'Rules of 1972') lays down the procedure for issue and service of
    
    summons. Rule 5 provides for procedure of inquiry. He has also
    
    contested the stand of the respondents-State that since the petitioner had
    
    participated in a challenge to the Commission of Inquiry headed by
    
    Justice L.Narasimha Reddy, Former Chief Justice of Patna High Court,
    
    in W.P.No.16588 of 2024, he was familiar with the procedure of such
    
    enquiry and after voluntarily participating in the inquiry waived his
    
    right. Learned Senior Counsel has also made the copious reference to
    
    the findings rendered by the Commission on the alleged irregularities
    
    committed by the petitioner, but the mandatory requirement of
    
    reasonable opportunity to defend himself under Section 8B was denied
    
    to him. According to him, there is a subtle distinction between the
    
    provisions of Section 5(2) and 8B of the Act of 1952. He has referred to
    
    the Report of Lord Salmon on the 'Royal Commission on Tribunals of
    
    Inquiry, 1966' which lays down six cardinal principles to be followed by
                                          18
    
    
    
    
    any such Tribunals while conducting any such inquiry. He submits that
    
    the Inquiries Act, 2005 framed by UK prescribes various safeguards
    
    regarding production of evidence and publication of reports which have
    
    a tendency of indict the conduct or reputation of a person. In conclusion,
    
    he has assailed the findings of the Commission as being vitiated due to
    
    serious violation of the procedure laid down and principles of natural
    
    justice.
    
    
    W.P.No.29352 of 2025 (SS):
    
    14.    Mr. J.Ramachandra Rao, learned Senior Counsel appearing for
    
    the petitioner, SS who was the Additional Secretary to the Chief
    
    Minister for the State of Telangana, has largely adopted the submissions
    
    made       by   learned   Senior   Counsels,   Mr.   C.A.Sundaram     and
    
    Mr. D.Seshadri Naidu. He has submitted that the summons dated
    
    12.07.2024 issued upon her was only to attend a meeting with the
    
    Chairman of the Commission of Inquiry. There is a significant
    
    difference between the summons issued on this petitioner, SS and that of
    
    the other petitioners, THR and KCR. The petitioner, on being asked, had
    
    filed an affidavit on 01.08.2024 explaining the nature of the duties
    
    allotted to her, while at the same time stating that she had no role in
    
    planning or execution of the work of these barrages. She was
                                        19
    
    
    
    
    telephonically asked to appear and depose before the Commission on
    
    19.12.2024 without any further summons or notice as required under
    
    Section 8B of Act of 1952. The petitioner, in due obedience appeared
    
    and answered all the questions which are in relation to her
    
    administrative responsibilities. No questions were put to the petitioner
    
    containing allegations against her conduct or reputation, neither were
    
    any documents supplied to her. However, the Commission rendered
    
    adverse findings against the petitioner as are reflected at page 90 of the
    
    writ petition. As such, her fundamental right to reputation which is a
    
    facet of right to life under Article 21 of the Constitution of India has
    
    been violated without following the mandatory procedure prescribed
    
    under Section 8B of the Act of 1952. Learned Senior Counsel for the
    
    petitioner has also sought to explain the significance of Sections 8B and
    
    8C of the Act of 1952, inserted by way of Act 79 of 1971, with effect
    
    from 30.12.1971, to accord reasonable opportunity to a person whose
    
    conduct and reputation are likely to be affected by, in the opinion of the
    
    Commission. He has therefore sought for quashing of the Report of the
    
    Commission.
                                         20
    
    
    
    
    W.P.No.26367 of 2025 (SKJ):
    
    15.       Mr. Tarun G.Reddy, learned counsel for the petitioner, SKJ in
    
    W.P.No.26367 of 2025 has referred to the credentials of the petitioner,
    
    an Officer of Indian Administrative Service, 1984 batch. He had retired
    
    on 31.12.2019. He has submitted that the Kaleshwaram project was
    
    started in the year 2016 and was completed on 21.06.2019. One of the
    
    piers of Medigadda barrage collapsed on 21.10.2023 four years after his
    
    retirement. Learned counsel Mr. Rao has also questioned the
    
    constitution of a judicial inquiry as contrary to Section 3 of the Act of
    
    1952. He has also referred to the decision of the apex court in Ram
    
    Krishna Dalmia vs. Justice S.R.Tendolkar 4 that the Commission of
    
    Inquiry constituted under the Act of 1952 is only a fact finding enquiry
    
    whose reports are not adjudicatory in nature. It is further submitted that
    
    the petitioner got summons on 08.07.2024 to attend a meeting with the
    
    Chairman of the Commission. He filed an affidavit on 21.07.2024
    
    detailing his roles and responsibilities during the period when the
    
    Project was being executed. Thereafter, he was telephonically called to
    
    give evidence on 18.12.2024. During his examination, he answered a
    
    number of questions posed by the Commission. However, the
    
    Commission did not follow mandatory requirement under Section 8B of
    
    4
        AIR 1958 SC 538
                                         21
    
    
    
    
    the Act of 1952 by providing adverse materials collected by it during the
    
    course of inquiry in order to properly defend himself. No reasonable
    
    opportunity was provided to the petitioner as per Sections 8B and 8C of
    
    the Act of 1952.
    
    
    16.       Learned counsel for the petitioner has also relied upon Jai
    
    Prakash Associates (supra) on the requirement of Rule 5(2)(a) and (b)
    
    of the Rules of 1972 vis-a-vis Section 8B of the Act of 1952. He has
    
    referred to Canara Bank vs. Debasis Das 5 and submitted that every
    
    material adverse to the petitioner had to be supplied for properly
    
    defending himself. He has also countered the stand of the respondents-
    
    State in their counter affidavit that petitioner having voluntarily
    
    participated in the inquiry had acquiesced in the proceedings. He has
    
    relied upon the case of State of Uttar Pradesh vs. Uttar Pradesh
    
    Rajya Khanij Vikas Nigam Sangharsh Samiti 6 to submit that there is
    
    no estoppel against the statute. If Sections 8B and 8C of the Act of 1952
    
    require a notice upon the person, such requirement cannot be said to
    
    have been waived by the petitioner. Based on these submissions, he has
    
    prayed that the writ petition deserves to be allowed.
    
    
    
    
    5
        (2003) 4 SCC 557
    6
        (2008) 12 SCC 675
                                           22
    
    
    
    
    SUBMISSIONS OF THE RESPONDENTS No.1 AND 2-STATE:
    
    
    17.    The    response    of    the        respondents-State   is   led   by
    
    Dr. A.M.Singhvi, learned Senior Counsel appearing in W.P.No.24835 of
    
    2025 preferred by THR. His submissions, at the outset, are broadly
    
    based on the constitution of the Commission of Inquiry. According to
    
    him, if the contention of the petitioner is accepted, it would amount to
    
    denudation of the State's power to constitute a Commission for
    
    undertaking a fact finding enquiry under the Act of 1952, where acts of
    
    negligence and deliberate malfeasance come to light in discharge of
    
    public duties by the people in power and agencies. By the very nature of
    
    its constitution, the Commission is empowered to conduct a fact finding
    
    enquiry than taking any coercive action on its own. It is well settled that
    
    the Report of the Commission cannot be acted upon proprio vigore i.e.,
    
    on its own. A decision is required to be taken on the findings of the
    
    Commission by the competent authority for taking any action against
    
    any person or agencies. The Government has handed over the matter to
    
    the CBI to conduct investigation into the allegations of irregularities,
    
    embezzlement of public funds, and corrupt practices etc., in the
    
    construction of Medigadda, Annaram and Sundilla barrages of
                                         23
    
    
    
    
    Kaleshwaram Irrigation Project against the accused persons, including
    
    public servants and private persons, companies etc., in view of the
    
    Reports of the National Dam Safety Authority and the findings of the
    
    Commission of Inquiry.
    
    
    18.    It is contended that the petitioners have laid a challenge to the
    
    constitution of the Commission of Inquiry as an afterthought after
    
    voluntarily participating in its proceedings. Their entire submissions are
    
    based on non-compliance of Section 8B of the Act of 1952, or lack of its
    
    reference in the summons though it does not lead to their prejudice. The
    
    petitioners are essentially insisting upon form over substance. The
    
    constitution of the Commission of Inquiry was the outcome of a
    
    multilayered institutional thinking, where the Government has taken into
    
    account the Reports such as the National Dam Safety Authority, which
    
    opined that the piers had sunk due to a combination of issues involving
    
    lacunae and negligence in planning, design, quality control and
    
    Operation and Maintenance (O&M) of the barrage. The Commission of
    
    Inquiry confirmed     grave    irregularities   across   conceptualization,
    
    planning, design, construction, contract award, execution, O&M, quality
    
    control and financial managements. It found that there was deliberate
    
    suppression of the Expert Committee Report, which advised against the
                                        24
    
    
    
    
    Medigadda site. There was violation of Article 166 of the Constitution
    
    of India and the Government Rules of Business in not ratifying the
    
    administrative approvals by the Council of Ministers. It has caused an
    
    annual debt burden of Rs.12,826 crores. The Report has been
    
    meticulously compiled with reference to various government records,
    
    orders and communications, which were all in the knowledge of the
    
    petitioner. The learned Senior Counsel for the respondents-State has
    
    made detailed references to the Commission's Report, which includes
    
    the role of the petitioner, THR as a Minister of Irrigation and a Minister
    
    of Finance and also the Chief Minister, KCR. The Commission collected
    
    large number of affidavits, made physical inspection of the sites and
    
    referred to the Reports of the National Dam Safety Authority and the
    
    Expert Committee constituted by the Government and examined the role
    
    of the petitioner, THR as Minister of Irrigation was examined. It took
    
    note that no clearance was taken from the Central Water Commission. It
    
    has referred to the Report of the High Power Committee, which did not
    
    recommend construction of these barrages at the relevant sites. It also
    
    found that there was no approval of competent authority in issuing
    
    G.O.Rt.No.776, dated 27.10.2015. The Commission found that the
    
    Government has not considered the Report of the Expert Committee
    
    which recommended against constitution of barrage at Medigadda site.
                                         25
    
    
    
    
    Moreover, the Cabinet Sub-committee did not refer to the construction
    
    of barrages at Medigadda, Annaram and Sundilla. The Commission also
    
    found that the High Power Committee and the State Level Standing
    
    Committee were not in picture in proposing/planning to entrust
    
    consultancy services to WAPCOS. He has further referred to the huge
    
    cost estimates in execution of the Project in the Report. The
    
    Commission had prepared a set of questions and also recorded clinching
    
    evidence on the irregularities committed during planning, designing and
    
    execution of the Project and design issues. In conclusion, the
    
    Commission had found that the High Power Committee did not
    
    recommend for construction of barrage at Medigadda. It was the sole
    
    decision of the then Chief Minister and the petitioner, who was the
    
    Irrigation Minister. The Commission also found that three barrages were
    
    constructed as reservoirs/dams, but they failed to design them as
    
    reservoirs/dams. Approximately Rs.87,449 crores was sanctioned for
    
    execution of the project including interest. An amount of Rs.6,519
    
    crores was paid as interest. The petitioner was involved in these
    
    decisions as a Minister of Irrigation. The project cost initially estimated
    
    at Rs.81,911.01 crores has risen to Rs.1,47,427.41 crores on completion,
    
    as per the Report of the Comptroller and Auditor General of India. The
    
    power of the Commission to conduct a fact finding enquiry under the
                                         26
    
    
    
    
    Act of 1952 is therefore not open to challenge on the grounds raised by
    
    the petitioner.
    
    
    19.    The petitioner has, after submission of the Report, made an
    
    attempt to dislodge the elaborate findings recorded by the Commission
    
    after participating in the inquiry and having availed adequate
    
    opportunity of hearing. The petitioner tendered his deposition as
    
    C.W.114 on 09.06.2025 upon service of summons and also filed
    
    documents in support of his case, which were marked as Exhibits. The
    
    proceedings were conducted in-camera at the request of the petitioner.
    
    He did not raise any objection regarding the procedure adopted by the
    
    Commission and chosen not to exercise any statutory right available to
    
    him, he is estopped from alleging violation of Sections 8B and 8C of the
    
    Act of 1952, or breach of principles of natural justice. Therefore, the
    
    plea that he was merely summoned as a witness or that the inquiry was
    
    biased is an afterthought and untenable in the light of his conscious
    
    participation in the proceedings.
    
    
    20.    The petitioner did not seek cross-examination of any witness
    
    under Section 8C of the Act of 1952, nor did he seek any additional
    
    records beyond those furnished. The Act does not prescribe any specific
    
    format for notice under Section 8B or 8C of the Act of 1952. Therefore,
                                        27
    
    
    
    
    the absence of any reference to the statutory provision does not vitiate
    
    the proceedings. The Commission's Report is founded on government
    
    records and the proceedings reflect substantial compliance of the Act of
    
    1952 and requirement of fairness. Therefore, the Commission cannot be
    
    faulted for not suo motu offering wholesale cross-examination of over
    
    119 witnesses when the petitioner did not invoke the right under Section
    
    8C of the Act of 1952, in any manner.
    
    
    21.    Dr. A.M.Singhvi, learned Senior Counsel for the respondents-
    
    State submitted that the Commission of Inquiry is not a court. The
    
    culpability of an individual will be determined by a competent court of
    
    law following a rigorous statutory investigation, which has now been
    
    ordered through the CBI. The petitioner's contention that the Terms of
    
    Reference is ultra vires the Act of 1952 is misconceived. He has referred
    
    to the decision of Ram Krishna Dalmia (supra). It is submitted that the
    
    Hon'ble Supreme Court in a catena of decisions has constantly held that
    
    while a Commission cannot act as a court to impose punishment, it is
    
    fully competent to inquire into the conduct of individuals to recommend
    
    legislative or administrative measures. The mandate of G.O.Ms.No.6,
    
    dated 14.03.2024 to fix responsibility for the lapses identified does not
    
    transgress its boundary. It merely identifies administrative and financial
                                          28
    
    
    
    
    lapses to enable informed decision making in the realms of policy
    
    correction, departmental action. It neither adjudicates guilt nor imposes
    
    consequences. He has relied upon the case of T.T.Antony vs. State of
    
    Kerala 7 in support. According to him, the Report of the Commission
    
    dated 31.07.2025 is founded exclusively on official Government
    
    records. He submits that the principles in Kiran Bedi (supra) and State
    
    of Bihar vs. Lal Krishna Advani 8 are not applicable in the present
    
    case. The case of Lal Krishna Advani (supra) does not lay down that
    
    every report containing adverse observations must be quashed. In that
    
    case, Advani was not given any notice. Hence, the Court held that the
    
    notice to the person is essential.
    
    
    22.    In the present case, the petitioner was served with a formal notice
    
    dated 20.05.2025 and appeared before the Commission on 09.06.2025,
    
    tendered his testimony, sought and obtained relevant records and raised
    
    no objection either to jurisdiction or procedure. He has distinguished the
    
    case of P.V.Jagannath Rao vs. State of Orissa 9 and submitted that the
    
    said decision merely reiterates that an administrative action may be
    
    invalidated if its dominant purpose lies outside the statute. In the present
    
    case, the dominant purpose of G.O.Ms.No.6 squarely falls within the
    
    7
      (2001) 6 SCC 181
    8
      (2003) 8 SCC 361
    9
      1968 SCC OnLine SC 46
                                              29
    
    
    
    
    scope of Section 3 of the Act of 1952. The challenge, therefore,
    
    proceeds on a misreading of both the statutory framework and the settled
    
    law governing Commissions of Inquiry.
    
    
    23.    It is further submitted that the allegation that the inquiry is a
    
    political stratagem is baseless. The inquiry was necessitated by
    
    objective, undeniable facts: the structural collapse of the Medigadda
    
    barrage and the National Dam Safety Authority's Reports on quality
    
    control and planning failures. The State has a constitutional duty to
    
    protect the public exchequer. The Commission of Inquiry has completed
    
    the task in strict adherence to the Act of 1952 and its findings are based
    
    on official records. The State accepted the Report and handed over the
    
    matter for investigation to CBI.
    
    
    24.    Learned Advocate General appeared for the respondents-State in
    
    W.P.No.24837 of 2025, which has been preferred by the petitioner,
    
    KCR.    He    has    adopted       the        broad   submissions   made   by
    
    Dr. A.M.Singhvi, learned Senior Counsel. Besides that he has referred to
    
    the findings of the National Dam Safety Authority, which are
    
    incorporated in G.O.Ms.No.6, dated 14.03.2024. According to him, the
    
    Terms of Reference contained in said G.O., are not premeditated or
    
    prejudged.
                                        30
    
    
    
    
    25.       He submits that in the case of P.V.Jagannath Rao (supra)
    
    similar terms of enquiry were in question. In the said Commission of
    
    Inquiry, the Terms of Reference named persons also in the Schedule,
    
    against whom the Commission was asked to conduct enquiry. He has
    
    also referred to the case of P.Janardhana Reddy vs. State of Andhra
    
    Pradesh 10 where though the High Court had quashed the constitution of
    
    Commission of Inquiry, the Hon'ble Supreme Court proceeded to set
    
    aside the judgment of the High Court. He has refuted the attack made by
    
    the petitioner on the expression 'judicial inquiry' used in the impugned
    
    G.O.Ms.No.6, dated 14.03.2024, by submitting that the Commission of
    
    Inquiry has been constituted under the Act of 1952. Since it is headed by
    
    a former Judge, the said expression has been used. The Commission has
    
    identified its duties within the scope and mandate of the Act of 1952.
    
    Therefore, the use of expression 'judicial' does not render it anything
    
    other than the Commission of Inquiry under the Act of 1952. He has
    
    also referred to the case of Ram Krishna Dalmia (supra), where at
    
    paras 8 and 9, it has been held that the Report of the Commission under
    
    the Act of 1952 does not apply proprio vigore. Learned Advocate
    
    General has referred to the recommendation of the High Power Expert
    
    Committee. He has submitted that the administrative approval was
    10
         (2001) 6 SCC 50
                                        31
    
    
    
    
    granted for construction of Medigadda Barrage and for Annaram
    
    Barrage by the petitioner, KCR. He has also referred to the findings of
    
    the Commission of Inquiry to show that present petitioner as Chief
    
    Minister and the petitioner, THR as Irrigation Minister had full
    
    knowledge of the planning, construction and completion of the three
    
    barrages and were fully aware of the scope of the inquiry.
    
    
    26.   Learned Advocate General has referred to the Report of the
    
    Comptroller and Auditor General of India (CAG) on performance audit
    
    which refers to the Report of the Commission of Inquiry. The CAG
    
    Report was tabled before the Legislature on 15.02.2024. The executive
    
    summary of the CAG Report has made strong observations as regards
    
    the construction of these barrages. He points out that the petitioner was
    
    asked to appear after examination of all others was completed. The
    
    petitioner was aware of nature of the proceedings since he had
    
    challenged the similar Commission of Inquiry constituted by the State
    
    Government appointing Justice L.Narasimha Reddy, Former Chief
    
    Justice of Patna High Court, by filing W.P.No.16588 of 2024. Learned
    
    Advocate General has also distinguished the case of the Lal Krishna
    
    Advani (supra), where no notice was issued to Mr. Advani. He submits
    
    that the petitioner has been given fair hearing as prescribed under
                                        32
    
    
    
    
    Section 8B of the Act of 1952. There is no specific format for notice
    
    under Sections 8B and 8C of the Act of 1952. Therefore, substantive
    
    fairness had been followed. Mere non-mentioning of a provision does
    
    not render the notice fatal or illegal. He has referred to P.K.Palanisamy
    
    vs. N.Arumugham 11. He has cited the case of N.Mani vs. Sangeetha
    
    Theatre 12 on the proposition that mere non-mentioning of Section 8B of
    
    the Act of 1952 in the summons issued upon the petitioner would not
    
    nullify it. He has also relied upon the case of K.L.Tripathi vs. Union of
    
    India 13 on the requirement of showing real prejudice in matters of
    
    compliance of principles of natural justice. All that is required to be
    
    done is fair play in action. The petitioner has not disputed that he was
    
    not given the statement of witnesses or documents. In order to
    
    substantiate the submission, he has placed reliance on Union of India
    
    vs. Bishamber Das Dogra 14. He has submitted that the Government
    
    has handed over the investigation to the CBI in the matter of
    
    construction of Medigadda, Annaram and Sundilla barrages of
    
    Kaleshwaram Irrigation Project. He has relied upon the learned Single
    
    Bench judgment of the Punjab and Haryana High Court in
    
    
    
    11
       (2009) 9 SCC 173
    12
       (2004) 12 SCC 278
    13
       (1984) 1 SCC 43
    14
       (2009) 13 SCC 102
                                         33
    
    
    
    
    C.W.P.No.23285 of 2018 and on State of Karnataka vs. Union of
    
    India 15.
    
    
    27.       Learned Advocate General has later pointed out that notices to
    
    the two petitioners, SKJ and SS were of the same nature and content as
    
    to other witnesses. However, it is submitted that the notices issued to the
    
    petitioners, THR and KCR were different from other witnesses. Based
    
    on these submissions, learned Advocate General has prayed that the writ
    
    petition being devoid of merit and fit to be dismissed.
    
    
    28.       Mr. P.Sri Raghu Ram, learned Senior Counsel has appeared for
    
    the respondents-State in W.P.No.29352 of 2025, filed by the petitioner,
    
    SS. It is submitted that the petitioner has also made similar challenge to
    
    the G.O., and the findings of the Report of the Commission of Inquiry
    
    on the grounds that the findings of the Commission prejudicially affect
    
    her conduct and reputation and are violative of Article 21 of the
    
    Constitution of India. The petitioner was served notice dated 12.07.2024
    
    to attend the meeting with the Chairman of the Commission on
    
    15.07.2024 at 12.30 pm. The petitioner had been granted a reasonable
    
    opportunity of hearing. The petitioner filed an affidavit on 01.08.2024 in
    
    
    
    
    15
         (1977) 4 SCC 608
                                         34
    
    
    
    
    compliance to the notice issued upon her and was thereafter asked to
    
    appear before the Commission and examined as C.W.95, on 19.12.2024.
    
    
    29.    Mr. Sri Raghu Ram, learned Senior Counsel has referred to the
    
    Rules of 1972, which govern the requirement of notice under Rule 5 or
    
    Section 8B of the Act of 1952. According to him, the Commission of
    
    Inquiry fully followed the procedure prescribed in law. He has referred
    
    to the counter affidavit, i.e., I.A.No.1 of 2026 which contains the
    
    remarks of the Commission against the petitioner. According to him, all
    
    government orders were shown to her though she could not answer
    
    properly. Therefore, the Commission has commented that she was not
    
    diligent. The opinion of the Commission is, therefore, based on
    
    materials placed before it after a reasonable opportunity to the petitioner.
    
    He has referred to Rule 4(2) of the Rules of 1972 which provides for
    
    giving evidence and for producing documents. Rule 5(2)(a) provides for
    
    opportunity of hearing to the person. Rule 5(2)(b) also prescribes notice
    
    to the person acquainted with the subject matter. Rule 5(3) requires
    
    submission of affidavit. The petitioner did not complain of lack of notice
    
    or materials as she was aware about the nature of the documents on
    
    which she was asked to depose. The petitioner being an Officer of
                                         35
    
    
    
    
    Indian Administrative Service stands on a different footing and is
    
    governed by the All India Services (Conduct) Rules, 1968.
    
    
    30.    It is submitted that the findings of the Commission in respect of
    
    the petitioner are at pages 161 to 167 of the Report. They conclusively
    
    establish her involvement and dereliction of duty. At page 161 of the
    
    Report, the Commission considered her affidavit dated 01.08.2024 and
    
    her oral statement. In her oral examination at pages 161 to 163 of the
    
    Report, the petitioner admitted that she had knowledge of placing
    
    matters before the Cabinet and stated that all proposals to the barrages
    
    were placed before the Cabinet for approval. Based on the documentary
    
    evidence, the Commission concluded that she has violated the Business
    
    Rules, which as an Officer of Indian Administrative Service she was
    
    obligated to follow. The learned Senior Counsel sought to distinguish
    
    the decisions relied upon by the petitioner in Kiran Bedi (supra), Lal
    
    Krishna Advani (supra), Sanjay Gupta (supra), Jai Prakash
    
    Associates (supra) and with that of Ram Krishna Dalmia (supra) and
    
    Vijay Bhaskar Reddy (supra) relied on during the course of arguments.
    
    
    31.    It has been contended that since the findings of the Commission
    
    are on pure question of facts, they cannot be decided under the writ
    
    jurisdiction. Therefore, this Court may refuse to interfere in the matter.
                                       36
    
    
    
    
    32.   Mr. S.Niranjan Reddy, learned Senior Counsel has appeared for
    
    the respondents-State in W.P.No.26367 of 2025, preferred by the
    
    petitioner, SKJ, who was the Chief Secretary when the project was
    
    conceived and under execution. He had superannuated on 31.12.2019. In
    
    the written submissions on behalf of the State, broadly the same grounds
    
    had been taken as in the case of other petitioners. Learned Senior
    
    Counsel submits that in the present batch of cases, there are 11 other
    
    persons, who are bureaucrats and Engineers against whom also certain
    
    findings or remarks have been made by the Commission of Inquiry in
    
    the Report. However, such findings are not admissible in evidence.
    
    Therefore, those officers/engineers have not chosen to lay any challenge
    
    to the Report. A careful perusal of the findings of the Commission
    
    would show that there are no findings on their personal conduct or
    
    reputation on any of them. The findings against the petitioners are only
    
    in respect of discharge of their public duties. The petitioners were
    
    supplied all the documents which were relevant and formed the basis for
    
    the Commission's Report. Even if the contention of the petitioners on
    
    the issue of service of notice under Sections 8B and 8C of the Act of
    
    1952 is accepted, nothing turns out upon that as the Commission has not
    
    commented upon their conduct or personal reputation. He has referred to
                                        37
    
    
    
    
    the case of R. Rajagopal alias R.R. Gopal vs. State of Tamil Nadu 16
    
    and submitted that if the petitioner cannot succeed in a suit for damages
    
    on the findings recorded by the Commission, they obviously cannot
    
    succeed in writ jurisdiction. Leaned Senior Counsel has also referred to
    
    the Reports of the National Dam Safety Authority, the CAG regarding
    
    the sinking of the piers, the change of the dam site and the staggering
    
    cost involved in the project. According to him, in State of
    
    J&K v. Bakshi Gulam Mohammad 17, the petitioner had demanded the
    
    statements of more than 400 witnesses, examined by the Commission,
    
    which was turned down by the Hon'ble Supreme Court. It is submitted
    
    that the scope and purpose of such an enquiry is to render the findings
    
    on the discharge of public duties by persons like the petitioners. If the
    
    contention of the petitioner that each and every statement of a witness
    
    and the documents were to be supplied to the petitioner before
    
    examining him, the functioning of the Commission of Inquiry would be
    
    rendered unworkable. The petitioner had served as a Principal Secretary
    
    and Special Chief Secretary to the Government, Irrigation and
    
    Command Area Development Department between 12.01.2015 and
    
    31.01.2018 and thereafter as Chief Secretary from 01.02.2018 to
    
    31.12.2019. In his affidavit and oral examination, he had admitted that
    
    16
         (1994) 6 SCC 632
    17
         AIR 1967 SC 122
                                       38
    
    
    
    
    he was responsible for overall coordination within the Irrigation
    
    Department of the newly formed State of Telangana and for securing
    
    statutory and administrative clearances from the Government of India in
    
    relation to the Pranahita - Chevella Lift Irrigation Scheme.
    
    Notwithstanding this admitted responsibility, the Commission found that
    
    he was unable to recollect whether the proposal for construction of the
    
    barrages was placed before the High Power Committee, the State Level
    
    Standing Committee or the Expert Committee constituted under
    
    G.O.Rt.No.28, dated 21.01.2015 thereby demonstrating lack of diligence
    
    in matters of critical importance. The Commission further relied upon
    
    G.O.Rt.No.776, of Irrigation and Command Area Development
    
    Department (Project-II) dated 27.10.2015, which accorded Government
    
    approval for modifications recommended by the High Power Committee
    
    for Packages 6 to 8 and 10 to 12 under PCSS project. The Government
    
    Order was issued by the petitioner himself. The Commission held that a
    
    Cabinet Sub-committee was constituted under G.O.Rt.No.655, GAD
    
    (Cabinet) Department, dated 07.03.2016 to examine issues relating to re-
    
    engineering of major irrigation projects. Pursuant to the report of the
    
    Cabinet Sub-committee, G.O.Rt.Nos.607 to 611, dated 30.06.2016 were
    
    issued. All these Government Orders were signed by the petitioner. The
    
    Commission, on appreciation of his answers, found his evidence to be
                                        39
    
    
    
    
    inconsistent, lacking coherence, reinforcing the conclusion that his
    
    version could not be relied upon. The Commission further examined the
    
    Inter-State Board Meeting held on 23.08.2016 attended inter alia by the
    
    then Chief Minister, concerned Ministers and the petitioner as Special
    
    Chief Secretary, I&CAD Department. The Commission, after taking
    
    note of it, concluded that the Special Chief Secretary failed to exercise
    
    due diligence and propriety though the project led to considerable
    
    burden on the exchequer. The Commission further recorded that the
    
    Report of the Expert Committee constituted under G.O.Rt.No.28, dated
    
    21.01.2015 was not considered by the Government, which resulted in
    
    enormous loss to the public exchequer. The Commission at page 547 of
    
    the Report observed that the petitioner in his dual role as Principal
    
    Secretary to Government, I&CAD Department and Chairman of the
    
    Kaleshwaram Irrigation Project Corporation Limited (KIPCL) could not
    
    feign ignorance of the Government Order mandating that projects
    
    undertaken by KIPCL shall be Turn Key projects. This act of putting up
    
    a note proposing a departure from the approved Turn Key model to
    
    EPC/LS mode was held to be contrary to binding Government policy
    
    and reflective of administrative impropriety. Therefore, the findings of
    
    the Commission against the petitioner are based on substantial evidence,
    
    logical inference and established administrative norms, and fully justify
                                          40
    
    
    
    
    the conclusions and recommendations made therein. Based on these
    
    submissions, learned Senior Counsel for the State, Mr. Niranjan Reddy
    
    has also prayed that the writ petition is devoid of any merit and is fit to
    
    be dismissed.
    
    
    33.       Reply submissions had been made by Mr. D.Seshadri Naidu on
    
    behalf of the petitioner (KCR) in W.P.No.24837 of 2025. He submits
    
    that the test of prejudice is to be seen in a case of violation of principles
    
    of natural justice. He has referred to the case of Management of M/s.
    
    Nally Bharat Engineering Company Limited vs. State of Bihar 18. He
    
    has once again referred to the notice issued under Section 8B of the Act
    
    of 1952 headed by Justice L.Narasimha Reddy, Former Chief Justice of
    
    Patna High Court. According to him, waiver has no application as public
    
    interest have been statutorily safeguarded by introduction of Sections 8B
    
    and 8C of the Act of 1952. It is mandatory to issue notice in a case
    
    where the conduct and reputation of any person are likely to be affected
    
    by the opinion of the Commission. He has countered the submissions
    
    based upon the alleged escalation of cost in the execution of the project.
    
    He submits that the Kaleshwaram Lift Irrigation Project initially
    
    conceived at Rs.80,190 crores in the year 2017, got increased to the
    
    revised estimate of Rs.1,27,000 crores, which is only 1.59 times the
    18
         (1990) 2 SCC 48
                                        41
    
    
    
    
    original estimates. It is much less compared to other public projects
    
    executed across the country. He further submits that the Report of the
    
    CAG has no probative value. The contention of the State's Senior
    
    Counsel that there was no attack on personal reputation of the petitioner
    
    does not have any merit. He has also distinguished the case of Bakshi
    
    Gulam Mohammad (supra), where the petitioner had asked for 400
    
    affidavits which the Supreme Court held that it would lead to a situation
    
    where the proceedings would be unterminable. According to him, the
    
    absence of a proper notice under Section 8B of the Act of 1952 and right
    
    to cross-examination under Section 8C of the Act of 1952 is writ large
    
    on the face of the Report. Therefore, the contention to the contrary by
    
    the State's Senior Counsel cannot be sustained.
    
    
    34.       Mr. J.Ramachandra Rao, learned Senior Counsel for the
    
    petitioner (SS) in W.P.No.29352 of 2025 has also reiterated his
    
    submissions on non-compliance of the requirement of Section 8B of the
    
    Act of 1952. He has referred to the case of Khem Chand v. Union of
    
    India 19 and Subramanian Swamy vs. Union of India 20 on the right to
    
    reputation. According to him, several statutory clearances were taken
    
    before the project was launched. There was no infirmity in the planning
    
    
    19
         AIR 1958 SC 300
    20
         (2016) 7 SCC 221
                                             42
    
    
    
    
    or design of the project or fault or negligence on the part of the
    
    petitioner.
    
    
    35.    Mr. Tarun G. Reddy, learned counsel for the petitioner (SKJ) in
    
    W.P.No.26367 of 2025 has also replied on the same lines. He submits
    
    that the doctrine of substantive compliance on the requirement of a
    
    statutory notice under Section 8B of the Act of 1952 is not applicable in
    
    the instant case. He has again referred the case of Lal Krishna Advani
    
    (supra) and Bakshi Gulam Mohammad (supra) in support of the
    
    submission that the findings of the Commission without reasonable
    
    opportunity to the petitioner and without furnishing the incriminating
    
    material are unsustainable in law and on facts.
    
    
    Discussion and Analysis:
    
    36.    We have heard learned counsel for the parties at length. We have
    
    also taken note of the relevant materials relied upon by learned counsel
    
    for the parties and placed from record. We have also perused the
    
    decisions cited by the rival parties.
    
    
    37.    The writ petitioners question the vires of G.O.Ms.No.6, dated
    
    14.03.2024 as being illegal, arbitrary, unconstitutional and ultra vires
    
    the provisions of the Commissions of Inquiry Act, 1952. However, the
                                         43
    
    
    
    
    petitioner, SKJ has not laid any challenge to G.O.Ms.No.6, dated
    
    14.03.2024. All the writ petitioners have assailed the findings of the
    
    Commission headed by Sri Pinaki Chandra Ghose, Former Judge of
    
    Supreme Court of India, against them as being prejudicial, scurrilous,
    
    mala fide and in violation of provisions of Sections 8B and 8C of the
    
    Act of 1952 and in violation of principles of natural justice.
    
    
    38.    Both the parties have referred to copious materials from record to
    
    substantiate their stand on the aforesaid challenge. Therefore, based
    
    upon the submissions of learned counsel for the parties and pleadings on
    
    record, two essential issues arise for adjudication by this Court.
    
           (i) Whether the constitution of the Commission of Inquiry under
    
    Section 3 of the Commissions of Inquiry Act, 1952, vide G.O.Ms.No.6,
    
    dated 14.03.2024 is arbitrary, illegal and ultra vires the Constitution of
    
    India and the Commissions of Inquiry Act, 1952?
    
           (ii) Whether the findings rendered by the Commission are
    
    prejudicial to the conduct and reputation of the petitioners without
    
    following the statutory safeguard provided under Sections 8B and 8C of
    
    the Commissions of Inquiry Act, 1952 and thereby in violation of the
    
    principles of natural justice?
                                             44
    
    
    
    
    39.    Both the issues are dealt with hereinafter. In order to appreciate
    
    the controversy surrounding the first issue relating to the constitution of
    
    the Commission of Inquiry, it is pertinent to refer to G.O.Ms.No.6, dated
    
    14.03.2024, which is usefully extracted hereunder:
    
    
                          GOVERNMENT OF TELANGANA
                                 ABSTRACT
    
            COMMISSIONS - Commission of Inquiry under the
            Commissions of Inquiry Act, 1952 (Central Act 60 of 1952) -
            Appointment of Justice Sri Pinaki Chandra Ghose, Former Judge
            of Supreme Court of India to conduct Judicial Inquiry on certain
            allegations of irregularities and embezzlement of public funds by
            corrupt practices in constructing the barrages of Medigadda,
            Annaram and Sundilla of Kaleshwaram Project - Orders - Issued.
            _____________________________________________________
    
               IRRIGATION AND CAD (Projects-IV) DEPARTMENT
    
            G.O.Ms.No.6.                                   Dated: 14/03/2024
    
            ORDER:

    The Hon’ble Supreme Court of India has time and again
    held that Government contracts involve expenditure out of the
    public exchequer. Therefore, the moneys expended must not be
    spent arbitrarily. The procurements should be made at best price
    and the process should be transparent. The State does not have
    absolute discretion while spending public money. All government
    actions including government contracts awarded by the State must
    be tested on the touchstone of Article 14 and the process must not
    be discriminatory.

    2. In the year 2015, the Government of Telangana proposed to
    construct the Kaleshwaram Lift Irrigation Project at an estimated
    cost of approximately 81,911 Cr. to irrigate a new ayacut of 19.63
    lakh acres besides stabilization of ayacuts under existing projects,
    and supply of water to industries and drinking water purposes.
    Kaleshwaram Project envisages construction of 3 Barrages across
    river Godavari at Medigadda, Annaram & Sundilla, and lifting
    water in reverse direction through a system of large pumps,
    pressure mains and gravity canals into the existing Yellampally
    Project. From there onwards, Kaleshwaram Project is almost
    similar to Dr.B.R.Ambedkar Pranahita-Chevella Sujala Sravanthi
    45

    SPONSORED

    Project with enhanced capacities of Reservoirs and distributary
    system.

    3. The works of Construction of Medigadda Barrage were
    entrusted to M/s.L&T-PES JV with final estimate of the Barrage
    approved for Rs.4613.00 Crores. Annaram barrage works were
    entrusted to AFCONS-VIJETHA-PES JV with final estimate
    approved for Rs.2734.81 Crores. Sundilla barrage works were
    entrusted to M/S NAVAYUGA- GMW JV and final estimate was
    approved for Rs.2111.10 Crores.

    4. Kaleshwaram project was planned to be entirely based on
    loans raised by a newly formed SPV, the Kaleshwaram Irrigation
    Project Corporation Ltd. (KIPCL). Loans to a tune of
    Rs.87,449.16 Crores were sanctioned from Banks and Financial
    Institutions of Government of India resulting in principal
    repayment and interest commitment of Rs.12,826 Crores to
    Government per year.

    5. Since the project envisages lifting of a huge quantity of
    water through multiple stages, the cost of power burden if the
    project is run at full capacity works out at a prohibitive cost of
    Rs.10,374.56 Crores per annum.

    6. On 21.10.2023, some of the piers of Medigadda Barrage
    sank into the river bed.

    7. On 22.10.2023, National Dam Safety Authority (NDSA)
    constituted a committee to examine the reasons for sinking of the
    piers of Medigadda (Lakshmi) Barrage. The NDSA committee
    inspected Medigadda Barrage on 24.10.2023 and communicated
    the report to Government on 01.11.2023. The broad findings of
    the Committee are inter alia as follows:

    i) The Committee reported that the Piers had sunk due to a
    combination of issues involving lacunae and negligence in
    planning, design, quality control and Operation and
    Maintenance (O&M) of the barrage.

    ii) The Committee further opined that the distress condition
    developed is adversely affecting the functionality of the
    barrage. The barrage under the present condition is
    rendered useless until fully rehabilitated.

    iii) The Committee was of the view that, filling the reservoir in
    the present condition would worsen the barrage’s health and
    should not be resorted to.

    iv) The Committee observed that the two barrages constructed
    upstream of Medigadda under the Kaleshwaram Project,
    viz: Annaram and Sundilla barrages, have similar design
    46

    and construction methodologies, making them prone to
    similar failure modes.

    8. It is also apparent from the Report that after the
    inauguration of the Project no operations and maintenance was
    carried out by either the private Agency or by the concerned
    Department. In fact such acts are even against the Standard
    Clauses which were in relation to the maintenance of a Dam.

    9. It has also come to light through certain reports that during
    the construction of the dam, certain deviations were approved
    without appropriate inspection notes. It appears that even the
    Defect Liability Period was changed even when work was
    pending. The facts which have surfaced by the way of Reports
    indicate that the Government Departments and even the private
    agency were negligent in undertaking their responsibilities
    towards inter alia construction and repair and upkeep of the dam
    which has resulted into damages. It is prima facie indicated that
    certain deliberate omissions and commissions on part of
    functionaries have happened which has resulted into the present
    situation.

    10. The deviations in the Standard contract and the manner in
    which certain aspects of the project construction of certain blocks
    were undertaken indicate that interests of general public and state
    exchequer has been compromised to favour a select few.

    11. From the content of the report, and the visible evidence of
    the damage that has occurred to the structure, it appears that
    certain irregularities, lack of proper care to ensure quality work,
    gross negligence in execution and monitoring of the work, and
    other malpractices, lacunae have taken place in the construction of
    the barrages at Medigadda, Annaram and Sundilla, leading to
    major losses to the public exchequer.

    12. The casual approach towards the upkeep and safety of the
    dam itself compels the Government to look into the entire
    conspectus of events and get to the root of the matter.

    13. Therefore, Government of Telangana is of the opinion that
    it is necessary to appoint a Commission of Inquiry to inquire into
    the events and circumstances connected with the construction of
    the barrages at Medigadda, Annaram and Sundilla into the said
    allegations of irregularities resulting in huge losses to the public
    exchequer.

    14. The following Notification shall be published in an
    Extraordinary issue of the Telangana State Gazette, dated:

    14/03/2024.

    47

    NOTIFICATION-I

    WHEREAS Government of Telangana is of the opinion
    that it is necessary to appoint a Commission of Inquiry to inquire
    into the events and circumstances connected with the construction
    of the barrages at Medigadda, Annaram and Sundilla into a
    definite matter of public importance hereinafter specified.

    2. Now, THEREFORE, in exercise of powers conferred by
    Section 3 of the Commissions of Inquiry Act, 1952 (Central Act
    No.60 of 1952), the Government of Telangana hereby appoint
    Justice Sri Pinaki Chandra Ghose, Former Judge of Supreme
    Court of India, as Commission of Inquiry to conduct Judicial
    Inquiry on certain allegations of irregularities and embezzlement
    of public funds by corrupt practices in constructing the barrages of
    Medigadda and Annaram Reservoirs of Kaleshwaram Project.

    3. The above Commission of Inquiry shall have the following
    Terms of Reference for inquiry:

    i. To enquire into the negligence, irregularities and
    lacunae in Planning, Designing and Construction of
    Medigadda, Annaram and Sundilla Barrages.

    ii. To enquire into the manner of award and execution
    of Contract including but not limited to deviations
    in the contract and following of the strict financial
    discipline in the execution of such Contract.
    iii. To enquire into the negligence and lacunae in
    Operation & Maintenance of three barrages by the
    agencies concerned and the Department, thereby
    leading to major damage to the structure.

    iv. To enquire into the Quality Control & Monitoring
    aspects, negligence and other malpractices by the
    agencies/ contractors and the Department.

    v. To enquire, identify and fix up responsibilities for
    any authority/official who extended undue favours
    to the Agencies/ contractors in terms of allowing
    unjustified EOTS (extension of time), wrong
    completion of work certificates, premature
    releasing of Bank Guarantees, and such other
    matter.

    vi. The Commission shall fix responsibilities for the
    lapses identified by it during its enquiry into the
    above matters and financial implications on the
    lapses identified.

    vii. Any other matter that might be referred by the
    Government at a later date.

    48

    4. The Commission will hold its sittings at Hyderabad and
    will complete its Inquiry and report to State Government by 30th
    June, 2024.

    5. The Engineer-in-Chief (General), Irrigation & CAD Dept.
    shall make arrangements for the remuneration, office
    accommodation, mobility, staff, communication and other
    necessary infrastructure to conduct the said Inquiry.

    6. All the officers concerned shall hand over immediately all
    requisite documents and material evidence to the Commission of
    Inquiry.

    NOTIFICATION – II

    Whereas, the Government of Telangana are of the opinion
    having regard to the nature of the inquiry to be made by the
    Commission and other circumstances of the case that all the
    provisions of Sub-Sections (2), (3), (4) and (5) of Section 5 of the
    Commission of Inquiry Act, 1952, should be made applicable to
    the Commission appointed in the Notification – I above.

    2. Now, Therefore, in exercise of the powers conferred by
    sub-section (1) of Section 5 of the said Act, the Government of
    Telangana hereby direct that all the provisions of the sub-sections
    (2), (3), (4) and (5) of Section 5 of the Commissions of Inquiry
    Act, 1952 shall apply to the Commission.

    (BY ORDER AND IN THE NAME OF THE GOVERNOR
    OF TELANGANA)

    RAHUL BOJJA
    SECRETARY TO GOVERNMENT

    40. The petitioners have assailed the impugned G.O.Ms.No.6, dated

    14.03.2024 as a ‘judicial inquiry’ beyond the scope and mandate of

    Section 3 of the Act of 1952. According to them, the recitals of the

    impugned G.O., make it abundantly clear that the Government has

    already formed an opinion as regards the culpability of the individuals

    based upon the reports of the National Dam Safety Authority. Therefore,
    49

    since inception the proceedings are legally biased. It has been contended

    that WAPCOS was engaged in the year 2014 to investigate, identify and

    recommend alternative site for barrage construction. The sites were

    identified as Medigadda, Annaram and Sundilla. The Government of

    Telangana had an intention to cover the irrigation to an extent of

    37,08,670 acres. Apart from that the project also intended to cater to the

    needs of drinking water to an extent of 40 TMC and water for industrial

    purposes, of about 16 TMC. The execution of the project has shown the

    highest increase in paddy cultivation in the State of Telangana and is

    termed as the Rice Bowl of the country. It is only after the change of the

    Government in 2023 that the new Government decided to conduct an

    enquiry using a mishap in 2023 where one pillar No.20 in Block 7 of

    Medigadda barrage subsided due to various factors including excessive

    rainfall during monsoon season. Therefore, the initiation of the

    Commission of Inquiry in the nature of judicial inquiry by

    G.O.Ms.No.6, dated 14.03.2024 is vitiated.

    41. On the part of the respondents-State, copious reference has been

    made to Terms of Reference under G.O.Ms.No.6, dated 14.03.2024, to

    refute the contention of the petitioner that they are premeditated and pre-

    prejudiced. The reference is also made to the Commission of Inquiry
    50

    constituted by the State Government in exercise of powers under Section

    3 of the Act of 1952 consisting of Shri Justice H.R.Khanna of the Delhi

    High Court, which was the subject matter in P.V.Jagannath Rao

    (supra). In the present case, the Terms of Reference does not refer to the

    name of any person in G.O.Ms.No.6, dated 14.03.2024, unlike in the

    case of P.V.Jagannath Rao (supra). That the expression ‘judicial

    inquiry’ is of no significance as the Commission has been constituted

    under the Act of 1952, except that it is presided over by a Former Judge

    of the Supreme Court of India. It has been constituted and has performed

    its functions within the scope and mandate of Act of 1952. The Report

    of the Commission is not acted upon proprio vigore. The State has also

    referred to the recommendations of the Expert Committee which had

    recommended against the construction of the barrage at Medigadda,. But

    the then Chief Minister, KCR has desired alternative locations. It is also

    evident from the Report of the Central Water Commission that

    administrative approvals were thereafter given for construction of the

    Medigadda barrage and the Annaram barrage at the present site. The

    respondents-State has also placed reliance on the case of P.Janardhana

    Reddy (supra) to submit that there were sufficient materials to form the

    basis for subjective satisfaction of the State Government that the matter

    is one of the definite public importance into which an enquiry is
    51

    necessary to be made. The Government was therefore well within its

    right to inquire into the lapses and the omission and commission,

    negligence and irregularities in the execution of the project and also in

    its operation and maintenance through an independent Commission of

    Inquiry under the Act of 1952. The report and findings of the

    Commission are meant for information of the Government. Under

    Section 3(4) of the Act, the appropriate Government is bound to lay the

    report before the Legislature together with a memorandum of the action

    taken thereon within a period of six months of the submission of the

    report by the Commission to the appropriate Government. The Courts,

    civil or criminal, are not bound by the report or findings of the

    Commission of Inquiry as they have to arrive at their own decision on

    the evidence placed before them in accordance with law, as observed in

    the case of T.T.Antony (supra). Therefore, the constitution of the

    Commission of Inquiry per se is not ultra vires the Act of 1952 or in

    violation of Article 21 of the Constitution of India.

    42. Upon consideration of the rival submissions of the parties,

    materials on record and the wordings and content of G.O.Ms.No.6, dated

    14.03.2024, we are of the opinion that the constitution of the

    Commission of Inquiry headed by Sri Pinaki Chandra Ghose, Former
    52

    Judge of the Supreme Court of India, is neither illegal, arbitrary, nor

    unconstitutional or ultra vires the provisions of the Act of 1952 or

    contrary to the judgments of the Hon’ble Supreme Court or the High

    Courts. We say so for the following reasons.

    43. The National Dam Safety Authority was constituted to examine

    the reasons for sinking of the piers of Medigadda (Lakshmi) barrage. It

    recorded findings that the piers had sunk due to a combination of issues

    involving lacunae and negligence in planning, design, quality control

    and Operation and Maintenance (O&M) of the barrage. The distress

    condition developed adversely affected the functionality of the barrage

    rendered useless until fully rehabilitated. It also found that keeping the

    reservoir full in the present condition would worsen the barrages and

    should not be resorted to. That the two barrages constructed upstream of

    Medigadda under the Kaleshwaram Project, i.e., Annaram and Sundilla

    barrages had similar design and construction methodologies, making

    them prone to similar failure modes. It also indicated negligence of the

    Government departments and the private agencies in construction and

    repair and upkeep of the dam that has resulted into damages. These acts

    indicated certain omissions and commissions on the part of the

    functionaries. In this background, the Commission was appointed under
    53

    the Act of 1952 to undertake the fact finding enquiry upon the Terms of

    Reference and to enquire, identify and fix up responsibilities for any

    authority/official who extended undue favours to the Agencies/

    contractors in terms of allowing unjustified extension of time, wrong

    completion of work certificates, premature releasing of Bank Guarantees

    and such other matter. The Commission was also entrusted to fix

    responsibilities for the lapses identified by it during its enquiry into the

    above matters and financial implications on the lapses identified. It was

    also indicated that any other matter might be referred by the

    Government at a later date.

    44. The Commission of such nature is essentially appointed to render

    the findings of fact which may not only identify the lapses, negligence

    omissions and commissions in execution of the public project involving

    substantial expenditure from public exchequer, but also to facilitate

    rectification and prevention of recurrence of such lapses. It is also

    intended to restore public confidence in the execution of such projects

    undertaken by the Government involving considerable expenditure. The

    report of such a fact finding inquiry is not acted upon proprio vigore for

    inflicting punishments on the persons held responsible in the nature of

    an adjudicatory power (see Ram Krishna Dalmia (supra)). Its reports
    54

    are purely recommendatory and the statement made by the person before

    the Commission of Inquiry under Section of the Act of 1952 is wholly

    inadmissible in evidence in future proceedings – civil or criminal. The

    report forms the basis for taking decisions uninfluenced by the view of

    any person or body, howsoever august or high powered, it may be,

    involved in such acts of omission or commission, lapses or negligence in

    execution of public project involving substantial expenditure. Such an

    exercise of statutory power authorised by law cannot be labelled as ultra

    vires or without jurisdiction or mala fide. The petitioners have not been

    able to show that the Terms of Reference identify the culpability of any

    individual or body or agency, in a premeditated manner. The proper test

    to be applied in such a case is to see what is the dominant purpose for

    which the administrative power is exercised. Reference in this regard is

    made to the case of P.V.Jagannath Rao (supra). In the said case, the

    State Government had appointed the Commission of Inquiry consisting

    of Sri Justice H.R.Khanna of the Delhi High Court (As His Lordship

    then was) to inquire into and submit report in respect of various acts of

    malfeasance, misfeasance, misappropriation, fraud, negligence,

    favouritism, nepotism, illegalities, irregularities, improprieties by the

    then Chief Minister and others during the period from 23.06.1961 to

    08.03.1967 naming the Chief Ministers and other Ministers in the
    55

    Schedule to the notification constituting the Commission of Inquiry. The

    challenge to the constitution of the Commission was dismissed by the

    Delhi High Court. The aggrieved petitioners preferred the Appeals

    before the apex court. The apex court applied the dominant test and

    came to the opinion that the setting up of the Commission of Inquiry

    was to promote measures for maintaining purity and integrity of the

    administration in the political life of the State and not the character

    assassination of the Chief Minister and their group. The impugned

    notification dated 26.10.1967 was held legal and valid. In the present

    case, we find that the dominant purpose to appoint the Commission of

    Inquiry by the impugned G.O.Ms.No.6, dated 14.03.2024 was to inquire

    into the negligence, irregularities and lacunae in planning, designing and

    construction of Medigadda, Annaram and Sundilla barrages, also the

    award and execution of contract, its Operation and Maintenance, quality

    control and monitoring aspects and fix up responsibilities on any

    authority/official for the lapses including the financial implications on

    the lapses identified. None of the petitioners have been named in the

    recitals or identified in the Terms of Reference, unlike the case of

    P.V.Jagannath Rao (supra).

    56

    45. Reliance is also placed upon the opinion of the apex court in the

    case of Ram Krishna Dalmia (supra), wherein the apex court examined

    the scope of Section 3 of the Act of 1952 and held that the Government

    has the power to appoint Commission of Inquiry into the administrative

    matters of public importance. Therefore, the notification was well within

    the powers conferred on the proper Government. It could not be

    questioned on the ground that it is acting beyond the provisions of the

    Act of 1952. In the light of the above discussion, the mere use of

    expression ‘judicial’ in G.O.Ms.No.6, dated 14.03.2024 does not make

    the Commission a Judicial Inquiry. It has been constituted to undertake

    fact finding enquiry on the terms of reference within the scope and

    mandate of the Act of 1952. Therefore, we are of the considered opinion

    that the appointment of the Commission is neither illegal, arbitrary,

    unconstitutional nor ultra vires the Commissions of Inquiry Act, 1952.

    46. The next question which falls for consideration is whether the

    findings of the Commission are prejudicial and adversely affect the

    conduct and reputation of the petitioners and are vitiated for non-

    compliance of proper notice under Sections 8B and 8C of the Act of

    1952 in violation of principles of natural justice..
    57

    47. It is pertinent to mention here that the Commission recorded the

    statement of 119 witnesses. The petitioners, THR, KCR, SKJ and SS

    were examined as C.W.114, C.W.No.115, C.W.92 and C.W.95

    respectively.

    48. The petitioners, THR and KCR were issued notices, both dated

    20.05.2025 calling upon them to appear before the Commission on

    09.06.2025 and 05.06.2025 respectively. Upon receipt of the said

    notices, they made a request for certain documents on 06.06.2025. The

    said documents were supplied to them on 09.06.2025. The notices

    issued upon them are of the same language and content. Therefore, the

    notice issued to the petitioner, THR, is reproduced hereunder for

    appreciation of the issue at hand:

    HON’BLE SRI JUSTICE PINAKI CHANDRA GHOSE
    Former Judge, Supreme Court of India
    Former Chairman, Lokpal of India

    Commission of Inquiry on Kaleshwaram Project
    8th Floor, “D” Block, Burgula Ramakrishna Rao (BRKR,)
    Bhavan, Tank Bund Road, Hyderabad-500063

    SUMMONS

    To
    Sri T.Harish Rao
    Former Minister for Irrigation
    State of Telangana.

    Villa No.1025, KRINSS Villas,
    NANAKRAMGUDA, Ranga Reddy District.

    58

    Quarter No.504, 5th Floor, M.S.Block-III,
    Old MLA Quarters, Hyderabad-500029.

    Whereas, in exercise of powers conferred by Section 3 of
    the Commissions of Inquiry Act, 1952, the Government of
    Telangana has appointed Hon’ble Sri Justice Pinaki Chandra
    Ghose, former Judge, Supreme Court of India and former
    Chairman, Lokpal of India as the Commission of Inquiry, vide
    G.O.Ms.No.6, Irrigation and CAD (Projects-IV), dated 14th
    March, 2024 (published in Part-I Extraordinary Gazette on 14th
    March, 2024), to conduct Judicial Inquiry on certain allegations of
    irregularities and embezzlement of public funds by corrupt
    practices in constructing the barrages of Medigadda, Annaram and
    Sundilla of Kaleshwaram Project and the Terms of Reference
    under the said Government Order are as under:

    i. To enquire into the negligence, irregularities and lacunae in
    Planning, Designing and Construction of Medigadda,
    Annaram and Sundilla Barrages.

    ii. To enquire into the manner of award and execution of
    Contract including but not limited to deviations in the
    contract and following of the strict financial discipline in the
    execution of such Contract.

    iii. To enquire into the negligence and lacunae in Operation &
    Maintenance of three barrages by the agencies concerned
    and the Department, thereby leading to major damage to the
    structure.

    iv. To enquire into the Quality Control & Monitoring aspects,
    negligence and other malpractices by the agencies/
    contractors and the Department.

    v. To enquire, identify and fix up responsibilities for any
    authority/official who extended undue favours to the
    Agencies/ contractors in terms of allowing unjustified EOTS
    (extension of time), wrong completion of work certificates,
    premature releasing of Bank Guarantees, and such other
    matter.

    vi. The Commission shall fix responsibilities for the lapses
    identified by it during its enquiry into the above matters and
    financial implications on the lapses identified.

    vii. Any other matter that might be referred by the Government
    at a later date.

    59

    Since you are the then Minister for Irrigation and the then
    Minister for Finance for the State of Telangana during the relevant
    period of Planning, Awarding of Contracts, Designing,
    Construction and Inauguration of the Medigadda, Annaram and
    Sundilla barrages, this Commission is of the opinion to examine
    and hear you upon the Terms of Reference before this
    Commission. Therefore, you are hereby requested to attend before
    this Commission on Monday the 9th day of June, 2025 at 11.30
    am for examination. You are at liberty to produce documents/
    records upon which you desire to rely upon and/or to place before
    this Commission for consideration. A copy of G.O.Ms.No.6,
    Irrigation and CAD (Projects-IV) Department, dated 14.3.2024 is
    enclosed herewith.

    Given by order and under the authority and seal of the
    Commission of Inquiry
    on this the 20th day of May, 2025.

    Secretary to the Commission of Inquiry

    49. Both the petitioners, THR and KCR made their statements before

    the Commission on 09.06.2025 and 11.06.2025 respectively.

    50. The summons, dated 08.07.2024 and 12.07.2024 issued upon the

    petitioners, SKJ and SS respectively are identical but conspicuously

    different in their language and content from that of the other two

    petitioners, THR and KCR. They are asked to attend the meeting with

    the Chairman of the Commission of Inquiry on 15.07.2024. One of the

    said summons is extracted as under:

    Hon’ble Mr Justice Pinaki Chandra Ghose
    Commission of Inquiry on Kaleshwaram Project

    8th Floor, D-Block BRKR Bhavan, Tank Bund Road,
    Hyderabad-500063
    [email protected]
    60

    Letter No. dated 08.07.2024.

    SUMMONS

    Vide G.O.Ms.No.6, Irrigation and CAD (Projects-IV) Department,
    dated 14.3.2024, the Government of Telangana has appointed
    Hon’ble Mr Justice Pinaki Chandra Ghose, former Judge, Supreme
    Court of India and former Chairman, Lokpal of India as
    Commission of Inquiry to conduct judicial inquiry on certain
    allegations of irregularities and embezzlement of public funds by
    corrupt practices in constructing the barrages of Medigadda,
    Annaram and Sundilla of Kaleshwaram Project. The Terms of
    Reference for inquiry are:

    i. To enquire into the negligence, irregularities and lacunae in
    Planning, Designing and Construction of Medigadda,
    Annaram and Sundilla Barrages.

    ii. To enquire into the manner of award and execution of
    Contract including but not limited to deviations in the
    contract and following of the strict financial discipline in the
    execution of such Contract.

    iii. To enquire into the negligence and lacunae in Operation &
    Maintenance of three barrages by the agencies concerned
    and the Department, thereby leading to major damage to the
    structure.

    iv. To enquire into the Quality Control & Monitoring aspects,
    negligence and other malpractices by the agencies/
    contractors and the Department.

    v. To enquire, identify and fix up responsibilities for any
    authority/official who extended undue favours to the
    Agencies/ contractors in terms of allowing unjustified EOTS
    (extension of time), wrong completion of work certificates,
    premature releasing of Bank Guarantees, and such other
    matter.

    vi. The Commission shall fix responsibilities for the lapses
    identified by it during its enquiry into the above matters and
    financial implications on the lapses identified.

    vii. Any other matter that might be referred by the Government
    at a later date.

    Therefore, you are requested to attend the Meeting with the
    Hon’ble Chairman, Commission of Inquiry on Monday the
    61

    15th day of July, 2024 at 11.00 am in the Office of the Hon’ble
    Commission of Inquiry in connection with the inquiry and further
    request you to furnish information on such points or matters as,
    may be useful for, or relevant to, the subject matter of the inquiry.

    // By order of the Hon’ble Chairman, Commission of Inquiry //

    SECRETARY to the Commission of Inquiry

    To
    Sri S K Joshi IAS
    Former Secretary to Govt of Telangana
    Irrigation Department.

    51. The petitioners, SKJ and SS have submitted their affidavits

    before the Commission on 21.07.2024 and 01.08.2024 respectively. The

    gist of their affidavits reflect the positions which they held and their role

    in the decision making process. Both the petitioners did not make any

    incriminating statements in their affidavits regarding their involvement

    in the decision making process which led to the execution of the project

    and later sinking of the piers of the Medigadda barrage on 21.10.2023.

    52. After 4 months of submission of their affidavits filed on

    21.07.2024 and 01.08.2024, the petitioners, SKJ and SS were

    telephonically asked to appear before the Commission to make

    statements. The petitioner SKJ appeared on 18.12.2024 when his

    statements were recorded as C.W.92. The petitioner SS appeared before

    the Commission on 19.12.2024. The Commission recorded her

    statements as C.W.95.

    62

    53. The Commission submitted its Report on 31.07.2025 to the

    Government. The report was tabled before the Legislative Assembly on

    31.08.2025. A Press Conference was held on 04.08.2025 by the

    Government in which the findings of the Commission were shown by

    way of power point presentation. All the petitioners, thereupon, claimed

    to have knowledge of the findings made by the Commission against

    them. They have also assailed the findings of the Commission as being

    prejudicial, scurrilous, mala fide as against them rendered without

    following the procedure prescribed under Sections 8B and 8C of the Act

    of 1952 in the teeth of principles of natural justice.

    54. The petitioners have culled out some of the findings rendered

    against them in the Report dated 31.07.2025 by the Commission as

    being adverse and prejudicial to their conduct and reputation. The

    relevant findings as are borne on the records of each of these writ

    petitions are extracted hereunder in order to examine whether they are

    prejudicial in nature and adverse affect the conduct and reputation of the

    petitioners:

    Petitioner (THR):

    a. That, “Along with the Chief Minister, “intentionally
    have not considered the Report of the Expert Committee””.

    63

    b. That “It can be categorically held that there is rank
    irregularity from the stage of conceptualization of Kaleshwaram
    project till the issuance of Administrative approvals on 1.3.2016
    for construction of the three barrages. This is not the decision of
    the Government but of individuals.”

    c. That “The proposal and the decision to construct
    barrages at Medigadda, Annaram and Sundilla is of the then
    Minister for Irrigation and Chief Minister”.

    d. That “Letter from Ms. Uma Bharti, the then MoWR,
    dated 13.3.2015 has stated that Hydrology of the PCSS project
    was cleared on 24.10.2014. However project authorities vide their
    letter dated 24.11.2014 have submitted the modified hydrological
    series for approval…” Minister for Irrigation made an endorsement
    on the said letter on 20.3.2015.When the CWC has already cleared
    Hydrology of Dr BRAPCSS project as back as on 24.10.2014, the
    reason for the project authorities to submit modified hydrological
    series for approval of the CWC is not forthcoming.”

    e. That “Retired engineers committee constituted vide GO
    No.28″ … the expert committee had extensively studied the merits
    and demerits of the barrage being constructed at Tummidihetti and
    at Medigadda and concluded that the construction of barrage at
    Medigadda is not advisable and also not economical. On the other
    hand, the Expert committee recommended to construct barrage at
    Vemanapally on Pranahita river instead of at Medigadda.”

    f. That “The said Expert Committee stated in their Note
    submitted to this Commission on 25.6.2024 that they have
    submitted their Report titled “Barrages on Godavari and
    Pranahitha Rivers” on 7.4.2015 to the Minister for Irrigation,
    Principal Secretary, Irrigation Department, Engineer-in- Chief
    (Irrigation)….” Sri T.Harish Rao has not denied in his evidence the
    submission of the report by the Expert committee on 7.4.2015″

    g. That “It should be held that Sri S.K.Joshi, Sri
    C.Muralidhar and Sri B.Hari Ram suppressed the Report of the
    Expert Committee with malicious intention to enable the then
    Minister for Irrigation and the then Chief Minister to go ahead
    with their intention to construct barrage at Medigadda. Thus by
    suppressing this Report, they facilitated to construct barrage at
    Medigadda and they indulged in this malicious act at the cost of
    huge public money and putting the economy of the State at stake”.
    The commission has noted on suppression of the report of the
    expert committee that “The action to be taken shall be severe for
    the reason that had this Report not been suppressed, construction
    of barrage at Medigadda could not have been taken up”.

    h. That “The Note File is signed by the Principal Secretary
    to Government (Irrigation) on 26.2.2016, the Minister for
    Irrigation on 26.2.2016 and also by the then Chief Minister. Since
    the approval of the Cabinet is not obtained, there is violation of
    the Business Rules of the Government. An analysis of the above
    factual position would lead to one and only categorical conclusion
    64

    that the conception of Kaleshwaram project, the proposal of
    entrusting the consultancy services for preparation of DPR in
    respect of KP to WAPCOS and according administrative approval
    in that regard is the sole and individual decision of the Minister
    (Irrigation) and the Chief Minister”

    i. That “In the present case, the shifting of location of
    barrage to Medigadda on the alleged ground of availability of
    water is the decision of the then CM and this decision is taken
    suppressing the report of the Expert Committee under G.O 28.
    Right from the beginning till the stage of inauguration of the
    barrages by impounding water at the peril of the health of the
    barrages is done with the instructions of the then CM. The then
    Minister for Finance and Planning remained as a tacit perpetrator
    and the then Minister for Irrigation allowed the then Chief
    Minister to fulfil his desire. In fact, the then CM being political
    executive functioned as Administrative executive also in
    implementing the policy of the Government and the manner of
    planning and execution caused huge loss to the state public
    exchequer.

    j. “It can conclusively be held that the issuance of G.O Rt
    Nos.231, 232 dated 1.3.2016, according Administrative approval
    of Rs.2591 crores for construction of Medigadda project is not
    placed before the cabinet and is issued pursuant to the orders of
    the Minister (Irrigation) and the Chief Minister.”

    k. That “The Commission does not see any compelling
    urgency in taking such decisions by the Minister (Irrigation) and
    the Chief Minister alone and this irregularity is more so in the
    light of the fact that the cabinet has not ratified the same”. “21. 1.
    When the Government Orders 231, 232 and 233 are not placed
    before the Cabinet for approval/ratification and thereby there is
    violation of the Business Rules of the Government, the Minister
    for Irrigation and the Chief Minister shall also be held liable for
    violation of the Business Rules of the Government. In this regard,
    the evidence of the then Minister for Irrigation is false and cannot
    be substantiate his deposition.

    l. That “Acted complicity, allowing CM to take over the
    administrative role.

    n. The then Minister for Irrigation gave instructions at
    random and Minister for Finance and Planning conducted himself
    apathetical towards the Finance and economical health of the
    State, it is the then CM who can be directly and vicariously
    accountable for the irregularities and the illegalities in planning,
    construction, completion, Operation & Maintenance of the three
    barrages. One such example that Govt has brought to the notice of
    the Commission the then Irrigation Minister has instructed to
    adopt secant piles in the meeting dated 09.01.2017.”

    65

    19. The Commission further fixed responsibility upon the
    petitioner as under:

    a. “Political Executives Held Liable: The lapses related to
    Political Executives i.e., the then Chief Minister Sri. K.
    Chandrasekhar Rao, the then Minister for Irrigation Sri. T.Harish
    Rao and the then Minister for Finance Sri Etela Rajendar”.

    b. “The Commission concludes that the entire project was
    characterized by ‘rampant and brazen procedural and financial
    irregularities’. The report underscores that the Kaleshwaram
    project, intended as a ‘lifeline of the State of Telangana’, became
    a colossal waste of public money due to a profound failure of
    governance, planning, technical oversight, and financial
    discipline, driven by the individual decisions and undue influence
    of political leadership. The Commission of Inquiry Report dated
    31.07.2025, pertaining to allegations of irregularities and
    embezzlement of public funds through corrupt practices in the
    construction of the Medigadda, Annaram, and Sundilla barrages of
    the Kaleshwaram Project, is now placed.”

    Petitioner (KCR):

    The Commission found that the Petitioner:

    a. Is “directly and also vicariously accountable for the
    irregularities and the illegalities in planning, construction,
    completion, operation and maintenance of the three barrages.” His
    “involvement and directions minutely… is the cause and result of
    irregularities and the cause of distress to these three barrages.”

    b. That “It can be categorically held that there is rank
    irregularity from the stage of conceptualization of Kaleshwaram
    project till the issuance of Administrative approvals on 1.3.2016
    for construction of the three barrages. This is not the decision of
    the Government but of individuals.”

    c. That “The then Chief Minister is pre-determined and bent
    upon to construct barrage at Medigadda at his free choice and the
    authorities associated with the decision making facilitated them.”

    d. That “The decision of construction of barrage at
    Medigadda and also at Annaram and Sundilla is solely of the then
    Chief Minister”.

    e. That “It is abundantly clear that the Government has not
    considered the report of the Expert Committee constituted under
    G.O.Rt. No. 28, dated 21.1.2015”

    f. That “It can conclusively be held that the issuance of
    G.O. Rt. Nos.231, 232 and 233, dated 1.3.2016, according
    Administrative approval of Rs.2591 crores for construction of
    66

    Medigadda project is not placed before the cabinet and is issued
    pursuant to the orders of the Minister (Irrigation) and the Chief
    Minister.”

    g. That “The Commission does not see any compelling
    urgency in taking such decisions by the Minister (Irrigation)
    and the Chief Minister alone and this irregularity is more so in
    the light of the fact that the cabinet has not ratified the same.”

    h. That “In the review meeting dated 9.12.2017, the Chief
    Minister directed to entrust the additional works not covered in the
    scope of agreements to the existing agencies.”

    i. That “The Government agreed to execute coffer dam and
    guide bunds which were in the contractor’s scope of work, citing
    verbal instructions from the Chief Minister. This resulted in
    huge additional burden on the exchequer. Works worth ₹369 crore
    were added in RE-1 without basis in DPR, which the
    Commission termed ‘clinching evidence’ of an intent to siphon
    public funds to unduly favour agency.

    j. That “One of the factors for failure of proper operation
    and maintenance and consequential failure of the barrage is on
    account of impounding of water. It has categorically been
    observed and held that the then Chief Minister has directed
    the authorities to store water in the barrages to their full
    capacity for the purpose of lifting of water through pump
    houses. Therefore, the then Chief Minister acted against the
    interests of the State and have no sincere, honest and
    conscientious mind to protect and safeguard the three
    barrages constructed at huge cost of thousands of crores of
    public money. The Chief Minister acted not as the head of the
    Government but as the administrative executive himself.”

    k. That “Involvement and directions of the then Chief
    Minister minutely towards planning, construction and operation of
    these three barrages is the cause and result of irregularities and
    distress to these three barrages”. From the formation of the State
    of Telangana on 2.6.2014 till 1.3.2016 (the date of granting
    Administrative Approvals for construction of these three barrages)
    it is the sole decision of the then Chief Minister from the stage of
    conceptualization of Kaleshwaram Project, allegedly as part of re-
    engineering of the Dr BRA PCSS Project and to take up
    construction of these three barrages. The alleged non-availability
    of water at Tummidi Hetti is not the correct and the decision of
    construction of barrage at Medigadda and also at Annaram and
    Sundilla is solely of the then Chief Minister.”

    1. That regarding “Continuous Impounding of Water: The
    then Chief Minister directed continuous impounding of water in
    the barrages to their full capacity for lifting water through pump
    houses, even though barrages are typically ‘diversion structures
    with low head, not as storage structures. This continuous
    impounding was a major cause for distress.”

    67

    19. The Commission purportedly fixed responsibility on
    the petitioner, THR and KCR, as follows:

    a. “Political Executives Held Liable: The lapses related to
    Political Executives i.e., the then Chief Minister Sri.
    K.Chandrasekhar Rao, the then Minister for Irrigation Sri.
    T.Harish Rao and the then Minister for Finance Sri Etela
    Rajendar”

    b. “The Commission concludes that the entire project was
    characterized by ‘rampant and brazen procedural and financial
    irregularities’. The report underscores that the Kaleshwaram
    project, intended as a ‘lifeline of the State of Telangana’, became
    a colossal waste of public money due to a profound failure of
    governance, planning, technical oversight, and financial
    discipline, driven by the individual decisions and undue influence
    of political leadership. The Commission of Inquiry report dated
    31.07.2025, pertaining to allegations of irregularities and
    embezzlement of public funds through corrupt practices in the
    construction of the Medigadda, Annaram, and Sundilla barrages of
    the Kaleshwaram Project, is now placed.”

    Petitioner (SKJ):

    “Sri S.K.Joshi, IAS (examined as C.W.92) was the
    Principal Secretary to Government, Irrigation Department, from
    12.01.2015 to 31.01.2018…. They have not chosen even to
    whisper in their affidavit evidence or oral evidence regarding the
    constitution of the Expert Committee under G.O.Rt.No.28 and/or
    the submission of the Report by the said Expert Committee. Their
    silence on this crucial aspect is inexplicable and their conduct in
    discharge of their duties is not fair.”

    “Sri S.K.Joshi, in the capacities of Principal Secretary to
    Government/Special Chief Secretary to Government and the Chief
    Secretary to Government, has signed G.O.Rt.No.212, G.O.
    Rt.No.776 and G.O.Rt.Nos.607 to 611. He also stated in his
    affidavit that the ‘administrative sanctions were accorded for
    different components over a period of time after approval by the
    competent authority (Council of Ministers, Chief Minister/
    concerned Minister). This is a false statement made by him.”

    “The irresponsibility and impropriety of ….. (b) Sri S.K.
    Joshi… in these facts and circumstances, the proposal for revised
    administrative approval and the decision to accord revised
    administrative approval on these grounds involving huge amounts
    of public money shall have to be presumed to be tainted with
    malice on the part of the authorities who had proposed and also on
    the part of the authorities who were involved in taking the
    68

    decision to accord revised administrative approval. All these
    authorities shall be held to be dishonest in their duties and
    dishonest to the high offices they held, and they shall be held to
    have caused, without diligence, huge expenditure from the State
    exchequer, without verifying the pros and cons of the matter in
    case of public governance.”

    “Sri S.K. Joshi, IAS, the Principal Secretary to
    Government, I&CAD Department is also the Chairman of KIPCL.
    He cannot be oblivious to the fact that the projects to be taken up
    by KIPCL shall be Turnkey Projects. Since the Government Order
    setting up KIPCL specifically and in unequivocal terms states that
    the projects to be taken up by KIPCL shall be Turnkey Projects,
    and the Kaleshwaram Lift Irrigation System is to be funded by
    KIPCL and to be taken up by KIPCL, Sri S.K.Joshi, being the
    Principal Secretary to Government, I&CAD Department, and also
    the Chairman of KIPCL, is not expected to put up a note
    mentioning that the earlier system of EPC has been dispensed with
    and LS system of awarding work is being considered.”

    “Sri S.K.Joshi, IAS, Principal Secretary to Government,
    Irrigation Department … are liable for action for intentionally
    suppressing the Report of the Expert Committee constituted under
    G.O.Rt.No.28 with an oblique motive to enable the Government to
    go ahead with its resolve to construct the barrage at Medigadda.
    Appropriate action shall be taken against them in accordance with
    law. The action to be taken shall be severe, for the reason that had
    this Report not been suppressed, the construction of the barrage at
    Medigadda could not have been taken up.”

    “Appropriate action in accordance with law shall be taken
    against Sri S.K.Joshi, IAS, Principal Secretary to Government …
    for committing irregularities and violating the Business Rules of
    the Government by not placing the file relating to G.O.Rt.No.212,
    dated 13.04.2015, and G.O.Rt.No.40, dated 18.01.2016, before the
    Cabinet for approval (though G.O.Rt.No. 212 was subsequently
    ratified by the Cabinet on 03.06.2016).”

    “Appropriate action in accordance with law shall be taken
    against Sri S. K.Joshi, IAS. Principal Secretary to Government,
    Irrigation Department for committing irregularities and violating
    the Business Rules of the Government by not placing the file
    relating to G.O.Rt.Nos.231, 232, and 233, dated 01.03.2016 before
    the Cabinet for approval.”

    Petitioner (SS):

    a. That, “The Agency-L&T PES JV filed photographs of
    the Medigadda barrage site taken during the course of construction
    of the barrage. Some of those photographs show Smt. Smitha
    Sabharwal reviewing the progress of the construction. It may have
    to be noted that in the said photographs, either the Minister
    69

    (Irrigation), Minister (Finance & Planning) or the Chief Minister
    are not seen and further she also stated in her oral evidence that
    “in respect of all the subjects I was actively touring the districts
    causing feed back to the CM in respect of inter-departmental
    coordination with Collectors, Forest Department, neighbouring
    States, and intervening in order to take the projects forward”.
    Inference can be drawn from these circumstances that Smt. Smitha
    Sabharwal visited the three barrages construction sites in the
    capacity of the Special Secretary to CMO to review the progress
    of the three barrages.” (Pg No. 166 of the Report)
    b. That, “Mrs. Smitha Sabharwal is the Secretary to the
    Government and belongs to the Indian Administrative Service and
    it must be presumed that she must have been taken as Secretary to
    the Chief Minister in that capacity. The File Notes placed before
    the Chief Minister contained observations of the Finance
    Department that the approvals/permissions shall be obtained as
    per the Business Rules of the Government and she states in her
    oral evidence that “all files which were put up by CMO for CM
    approval had necessary concurrences and Business Rules
    compliance”. As part of the secretarial assistance to the Chief
    Minister, holding the cadre under Indian Administrative Service,
    and having herself stated in her affidavit that her role as Secretary
    to Chief Minister is to coordinate among different departments of
    the Government, it is very much ordained on her to verify whether
    the Business Rules of the Government are followed before placing
    the Files for orders before the Chief Minister. As is observed in
    the files relating to grant of Administrative Approvals, the Finance
    Department made endorsements to the effect that the approval of
    the competent authority as per the Business Rules shall be
    obtained. Mrs. Smitha Sabharwal also stated in her answer to
    question 14 that if any flag or deviation by any of the processing
    authorities such as Chief Secretary was put on file, it was her duty
    to inform the same and brief the Chief Minister. The G.O.Rt.
    Nos.231, 232 and 233 granting Administrative Approvals for
    construction of Medigadda, Annaram and Sundilla barrages
    are not placed before the Cabinet for approval/ratification
    and thus there is violation of Business Rules of the
    Government.” (Pg No. 166 of the Report)

    c. That, “Therefore, Mrs Smita Sabharwal, as
    Additional Secretary to the Chief Minister and Secretary to
    the Chief Minister must be held to be not diligent, is negligent
    and irresponsible in the discharge of her duties and she is also
    liable for action for violation of the Business Rules of the
    Government. In the circumstances, appropriate action shall be
    taken against her.” (Pg No. 167 of the Report)
    70

    14. In view of the aforementioned scathing remarks,
    the Commission purportedly fixed responsibility as follows:

    “Appropriate action in accordance with law shall be taken
    against Sri S.K.Joshi IAS, Principal Secretary to Government,
    Irrigation Department and Smt. Smita Sabharwal, Additional
    Secretary to Chief Minister (SS) for committing irregularity and
    violation of the Business Rules of the Government in not placing
    the File relating to G.O.Rt.No.212, dated 13.4.2015 and
    G.O.Rt.No.40, dated 18.1.2016 before the Cabinet for approval.
    (though G.O.Rt.No.212 is ratified by the Cabinet on 3.6.2016).”

    (Pg No. 634)
    And “Appropriate action in accordance with law shall be
    taken against Sri S.K.Joshi IAS, Principal Secretary to
    Government, Irrigation Department and Smt. Smita Sabharwal,
    Additional Secretary to Chief Minister (SS) for committing
    irregularity and violation of the Business Rules of the Government
    in not placing the File relating to G.O.Rt.Nos.231, 232 and 233,
    dated 1.3.2016 before the Cabinet for approval.”(Pg No. 635)

    55. The petitioners have strongly contended that the above findings

    are seriously prejudicial and defamatory against them. They have also

    challenged them as being illegal, arbitrary, premeditated and actuated by

    mala fides without following the statutory safeguard under Sections 8B

    and 8C of the Act of 1952 in violation of principles of natural justice.

    56. The respondents-State in its reply have adverted to the materials

    relied upon by the Commission to render findings as against the

    petitioners. The materials referred to by the State include the Reports of

    the Expert Committee dated 07.04.215; the National Dam Safety

    Authority; the Cabinet Sub-committee; the State Level Standing

    Committee; the Report of the CAG; the resolutions of the Cabinet and
    71

    other official documents. On behalf of the State, the State Government

    has taken the plea that the petitioners were fully aware of the documents

    relied upon by the Commission on which they were asked to depose.

    The petitioners, THR and KCR were supplied all the documents on

    09.06.2025 on their request. All these documents were made available to

    them when they made their statements i.e., 09.06.2025 and 11.06.2025

    respectively. The other petitioners SKJ and SS were Government

    officials, whose Conduct Rules require them to assist the Commission in

    such enquiry based upon official documents such as above. It is also

    their case that neither Sections 8B and 8C of the Act of 1952 nor the

    Rules framed thereunder specify a particular format for issuance of

    summons. Moreover, mere non-mentioning of the provision does not

    invalidate the power conferred upon by the Commission to issue a notice

    in the nature contemplated under Sections 8B and 8C of the Act of 1952.

    The petitioners, THR and KCR, both were legally aware of the

    procedure adopted by the Commission having challenged the

    constitution of the Commission headed by Justice L.Narasimha Reddy,

    constituted vide G.O.Ms.9, dated 14.03.2024 in W.P.No.16588 of 2024.

    The petitioners having consciously participated in the proceedings,

    thereby acquiesced in the procedure adopted by the Commission and are

    now estopped by their conduct in questioning the same. Moreover, the
    72

    findings of the Commission are in respect of the public duty required to

    be performed by the petitioners in their capacity as Irrigation Minister,

    Chief Minister, Special Secretary to the Chief Minister and Chief

    Secretary in the Government during the relevant point of time. It has

    also been submitted that the findings of the Commission do not reflect

    upon the conduct or reputation of the person but is limited to the

    discharge of their public duties. This Court in exercise of writ

    jurisdiction would refrain from interfering in the findings of the

    Commission derived after detailed inquiry and after reasonable

    opportunity to the petitioners touching upon the acts committed by them

    in discharge of their public duties.

    57. On the other hand, according to the petitioners, the notice issued

    upon them conformed to the requirement of Rules 4 and 5 of the Rules

    of 1972 to appear and depose as a witness before the Commission.

    However, if the Commission during the course of proceedings was of

    the opinion that its findings would adversely comment upon the conduct

    and reputation of the petitioners, the incriminating materials ought to

    have been conveyed to them by way of notice under Section 8B of the

    Act of 1952 to enable them to properly defend themselves. In this

    regard, the petitioners have relied upon the cases of Kiran Bedi (supra),
    73

    Lal Krishna Advani (supra), Jai Prakash Associates (supra), Sanjay

    Gupta (supra) and ECIL vs. B.Karunakar (supra). The petitioners

    have also contended that the right to cross-examine the witnesses whose

    incriminating statements were relied upon by the Commission to render

    its findings against the petitioners was denied. The petitioners, SKJ and

    SS both have contended that they were not served any summons or

    notice to depose before the Commission to defend themselves in the

    manner contemplated under Section 8B of the Act of 1952 nor were they

    supplied any documents which were the basis of the adverse findings

    against them. Therefore, the procedure adopted by the Commission is in

    violation of principles of natural justice and the statutory safeguard

    contained in Sections 8B and 8C of the Act of 1952.

    58. In order to appreciate the issue at hand, it is necessary to extract

    relevant provisions of the Act and the Rules, which prescribe the

    procedure to be followed by the Commission. Sections 4, 5, 5A, 6, 8, 8B

    and 8C of the Act of 1952 and Rules 4 and 5 of the Rules, 1972 are

    extracted as under:

    4. Powers of Commission:- The Commission shall have the
    powers of a civil court, while trying a suit under the Code of Civil
    Procedure
    , 1908 (5 of 1908), in respect of the following matters,
    namely:–

    (a) summoning and enforcing the attendance of any person
    from any part of India and examining him on oath;

    (b) requiring the discovery and production of any document;

    (c) receiving evidence on affidavits;

    74

    (d) requisitioning any public record or copy thereof from
    any court or office;

    (e) issuing commissions for the examination of witnesses
    or documents;

    (f) any other matter which may be prescribed.

    5. Additional Powers of Commission:- (1) Where the
    appropriate Government is of opinion that, having regard to the
    nature of the inquiry to be made and other circumstances of the
    case, all or any of the provisions of sub-section (2) or sub-section
    (3) or sub-section (4) or sub-section (5) should be made applicable
    to a Commission, the appropriate Government may, by
    notification in the Official Gazette, direct that all or such of the
    said provisions as may be specified in the notification shall apply
    to that Commission and on the issue of such a notification, the
    said provisions shall apply accordingly.

    (2) The Commission shall have power to require any person,
    subject to any privilege which may be claimed by that person
    under any law for the time being in force, to furnish information
    on such points or matters as, in the opinion of the Commission,
    may be useful for, or relevant to, the subject-matter of the inquiry
    and any person so required shall be deemed to be legally bound to
    furnish such information within the meaning of Section 176 and
    Section 177 of the Indian Penal Code (45 of 1860).

    (3) The Commission or any officer, not below the rank of a
    gazetted officer, specially authorised in this behalf by the
    Commission may enter any building or place where the
    Commission has reason to believe that any books of account or
    other documents relating to the subject-matter of the inquiry may
    be found, and may seize any such books of account or documents
    or take extracts or copies therefrom, subject to the provisions of
    Section 102 and Section 103 of the Code of Criminal Procedure,
    1898 (5 of 1898), in so far as they may be applicable.
    (4) The Commission shall be deemed to be a civil court and
    when any offence as is described in Section 175, Section 178,
    Section 179, Section 180 or Section 228 of the Indian Penal Code
    (45 of 1860), is committed in the view or presence of the
    Commission, the Commission may, after recording the facts
    constituting the offence and the statement of the accused as
    provided for in the Code of Criminal Procedure, 1898 (5 of 1898),
    forward the case to a Magistrate having jurisdiction to try the
    same and the Magistrate to whom any such case is forwarded shall
    proceed to hear the complaint against the accused as if the case
    had been forwarded to him under Section 482 of the Code of
    Criminal Procedure, 1898.

    (5) Any proceeding before the Commission shall be deemed
    to be a judicial proceeding within the meaning of Sections 193 and
    228 of the Indian Penal Code (45 of 1860).

    75

    5-A. Power of Commission to utilise the services of
    certain officers and investigation agencies for conducting
    investigation pertaining to inquiry:- (1) The Commission may,
    for the purpose of conducting any investigation pertaining to the
    inquiry, utilise the services,–

    (a) in the case of a Commission appointed by the
    Central Government, of any officer or investigation
    agency of the Central Government or any State
    Government with the concurrence of the Central
    Government or the State Government, as the case
    may be; or

    (b) in the case of a Commission appointed by the State
    Government, of any officer or investigation agency
    of the State Government or Central Government
    with the concurrence of the State Government or
    the Central Government, as the case may be.

    (2) For the purpose of investigation into any matter pertaining
    to the inquiry, any officer or agency whose services are utilised
    under sub-section (1) may, subject to the direction and control of
    the Commission,–

    (a) summon and enforce the attendance of any person
    and examine him;

            (b)     require the discovery and production of any
                    document; and
            (c)     requisition any public record or copy thereof from
                    any office.
    

    (3) The provisions of Section 6 shall apply in relation to any
    statement made by a person before any officer or agency whose
    services are utilised under sub-section (1) as they apply in relation
    to any statement made by a person in the course of giving
    evidence before the Commission.

    (4) The officer or agency, whose services are utilised under
    sub-section (1), shall investigate into any matter pertaining to the
    inquiry and submit a report thereon (hereafter in this section
    referred to as the investigation report) to the Commission within
    such period as may be specified by the Commission in this behalf.

    (5) The Commission shall satisfy itself about the correctness
    of the facts stated and the conclusions, if any, arrived at in the
    investigation report submitted to it under sub-section (4), and for
    this purpose the Commission may make such inquiry (including
    the examination of the person or persons who conducted or
    assisted in the investigation) as it thinks fit.]

    6. Statements made by persons to the Commission:- No
    statement made by a person in the course of giving evidence
    before the Commission shall subject him to, or be used against
    him in any civil or criminal proceeding except a prosecution for
    giving false evidence by such statement:

    Provided that the statement–

    76

    (a) is made in reply to a question which he is required
    by the Commission to answer, or

    (b) is relevant to the subject-matter of the inquiry.

    8-B.Persons likely to be prejudicially affected to be
    heard.–If, at any state of the inquiry, the Commission–

    (i) considers it necessary to inquire into the conduct of any
    person; or

    (ii) is of opinion that the reputation of any person is likely to
    be prejudicially affected by the inquiry,
    the Commission shall give to that person a reasonable opportunity
    of being heard in the inquiry and to produce evidence in his
    defence:

    Provided that nothing in this section shall apply where the
    credit of a witness is being impeached.

    8-C.Right of cross-examination and representation by legal
    practitioner.–The appropriate Government, every person referred
    to in Section 8-B and, with the permission of the Commission, any
    other person whose evidence is recorded by the Commission–

    (a) may cross-examine a witness other than a witness
    produced by it or him;

    (b) may address the Commission; and

    (c) may be represented before the Commission by a legal
    practitioner or, with the permission of the Commission, by any
    other person.

    The Commissions of Inquiry (Central) Rules, 1972:

    4. The issue and service of summons.–(1) A Commission
    may issue summons to persons whose attendance before it may be
    required either to give evidence or to produce documents.

    (2) Every summons issued by a Commission shall be in
    duplicate and shall be signed by the Chairman thereof or by such
    person as he may empower in this behalf. It shall be sealed with
    the seal of the Commission and shall specify the time and place at
    which the person summoned is required to attend and also whether
    his attendance is required for the purpose of giving evidence or to
    produce a document, or for both the purposes.

    (3) A person may be summoned to produce a document,
    without being summoned to give evidence and any person
    summoned merely to produce a document shall be deemed to have
    complied with the summons if he causes such document to be
    produced instead of attending personally to produce the same.
    (4) A summons to produce documents may be for the
    production of all documents of a certain description in the
    possession or control of the person summoned.

    77

    (5) Every summons shall be served by sending it by post to
    the person, for whom it is intended or in such other manner as the
    Commission may direct.

    (6) The provisions of sub-rules (1) to (5) shall apply, as far as
    may be, to every other process issued by a Commission.

    5. Procedure of Inquiry.–(1) A Commission may sit in
    public or in private as it thinks fit:

    Provided that a Commission shall sit in private on a request
    being made by the Central Government in that behalf.

    (2) A Commission shall, as soon as may be after its
    appointment–

    (a) issue a notice to every person, who in its opinion
    should be given an opportunity of being heard in
    the inquiry, to furnish to the Commission a
    statement relating to such matters as may be
    specified in the notice;

    (b) issue a notification, to be published in such manner
    as it may deem fit, inviting all persons acquainted
    with the subject matter of the inquiry to furnish to
    the Commission a statement relating to such
    matters as may be specified in the notification.
    (3) Every statement furnished under clause (a) of sub-rule (2)
    shall be accompanied by an affidavit in support of the facts set out
    in the statement sworn by the person furnishing the statement.

    (4) Every person furnishing a statement under clause (a) of
    sub-rule (2) shall also furnish to the Commission along with the
    statement a list of the documents, if any, on which he proposes to
    rely and forward to the Commission, wherever practicable, the
    originals or true copies of such of the documents as may be in his
    possession or control and shall state the name and address of the
    person from whom the remaining documents may be obtained.

    (5)(a) A Commission shall examine all the statements
    furnished to it under clause (b) of sub-rule (2) and if, after such
    examination, the Commission considers it necessary to record
    evidence, it shall first record the evidence, if any, produced by the
    Central Government and may thereafter record evidence in such
    order as it may deem fit–

    (i) the evidence of any person who has furnished a
    statement under clause (a) of sub-rule (2) and
    whose evidence the Commission having regard to
    the statement, considers relevant for the purpose of
    the inquiry; and

    (ii) the evidence of any other person whose evidence,
    in the opinion of the Commission, is relevant to the
    inquiry:

    Provided that the Commission may dispense with the
    attendance of any person for the purpose of giving evidence
    before it, if in its opinion–

    78

    (i) such attendance cannot be enforced except by
    causing undue hardship or inconvenience to that
    person;

    (ii) such attendance should be dispensed with for any
    other sufficient reason to be recorded by it in
    writing.

    (b) if after all the evidence is recorded under clause (a), the
    Commission is satisfied that it is necessary for the proper
    determination of any relevant fact to do so, it may recall any
    witness already examined or examine any new witness.

    (6) The Commission may pay the travelling and other
    expenses to a person who is summoned to assist the Commission
    at the stage of preliminary investigation or to give evidence or to
    produce documents before a Commission, as prescribed from time
    to time by the Central Government.

    (7) The Commission shall have the powers of a civil court to
    make local investigation, either personally or through any person,
    duly authorised by it into any matters falling within its terms of
    reference.

    (8) A Commission shall have the power to regulate its own
    procedure in respect of any matter for which no provision is made
    in these rules.

    59. It is pertinent to state that Sections 8B and 8C of the Act of 1952

    were introduced by the Amendment Act 79 of 1971 with effect from

    30.12.1971, almost two decades after the enactment of the main Act.

    The object behind the introduction of Section 8B in the statute book by

    Amendment Act 79 of 1971 has been discussed in the case of Lal

    Krishna Advani (supra) at paragraph 8 as under:

    “8. It may be noticed that the amendment was brought
    about, about 20 years after passing of the main Act itself. The
    experience during the past two decades must have made the
    legislature realize that it would but be necessary to notice a person
    whose conduct the Commission considers necessary to inquire
    into during the course of the inquiry or whose reputation is likely
    to be prejudicially affected by the inquiry. It is further provides
    that such a person would have a reasonable opportunity of being
    heard and to adduce evidence in his defence. Thus the principles
    of natural justice were got inducted in the shape of a statutory
    provision. It is thus incumbent upon the Commission to give an
    opportunity to a person, before any comment is made or opinion is
    79

    expressed which is likely to prejudicially affect that person.
    Needless to emphasise that failure to comply with the principles of
    natural justice renders the action non est as well as the
    consequences thereof.”

    60. As held above, the principles of natural justice got inducted in the

    shape of a statutory provision making it incumbent upon the

    Commission to give an opportunity of hearing before any comment is

    made or opinion is expressed, which is likely to prejudicially affect that

    person. As held in the above case, failure to comply with the principles

    of natural justice would render the action non est as well as the

    consequences thereof. A careful reading of the statutory scheme, which

    prescribes the procedure for the Commission in the conduct of an

    inquiry, shows that Section 4 confers the Commission with the power of

    the civil court under the Code of Civil Procedure, 1908 inter alia for

    summoning and enforcing the attendance of any person and examining

    him on oath; requiring the discovery and production of any document;

    receiving evidence on affidavits; requisitioning any public record and

    issue commissions for the examination of witnesses or documents. This

    provision is the source of power for ensuring the attendance and

    examination of witnesses for collecting evidence in the course of the

    Commission’s fact finding function.

    80

    61. Under G.O.Ms.No.6, dated 14.03.20224, the Commission has

    also been conferred the additional powers under Section 5 of the Act of

    1952. Section 5(2) confers power upon the Commission to require

    information from any person on the points which in the opinion of the

    Commission may be useful for, or relevant to, the subject matter of the

    inquiry. Any person so required shall be deemed to be legally bound to

    furnish such information within the meaning of Sections 176 and 177 of

    the Indian Penal Code, 1860. It is the investigative tool during the stage

    of enquiry for obtaining information from any person. This provision

    does not confer any specific right of legal representation upon the person

    so summoned. Section 5A confers power upon the Commission to

    utilise the services of certain officers and investigation agencies for

    conducting investigation pertaining to inquiry. Section 6 provides that

    no statement made by a person in the course of giving evidence before

    the Commission shall subject him to, or be used against him in any civil

    or criminal proceeding except a prosecution for giving false evidence,

    provided that the statement is made in reply to a question which he is

    required by the Commission to answer, or is relevant to the subject

    matter of the inquiry. Section 8 provides that the Commission shall,

    subject to any rules that may be made in this behalf, have power to

    regulate its own procedure including the fixing of place and times of its
    81

    sittings and deciding whether to sit in public or in private. In the

    aforesaid scheme of the Act, Sections 8B and 8C were introduced by

    amendment with effect from 30.12.1971 with a specific purpose as

    explained in the case of Lal Krishna Advani (supra). In the statutory

    scheme, this provision appears after Sections 4 and 5 which confer upon

    the Commission the power for ensuring compulsory attendance of

    examination of witnesses in order to collect evidence for the purposes of

    rendering finding on the terms of reference made to it. Section 8B, on

    the other hand, imposes an obligation upon the Commission to give a

    reasonable opportunity to a person of being heard in the inquiry and to

    produce evidence in his defence, if the Commission considers it

    necessary to inquire into the conduct of any person, or is of the opinion

    that reputation of any person is likely to be prejudicially affected by the

    inquiry. This power can be exercised at any stage of the inquiry if the

    aforesaid ingredients are made out in the opinion of the Commission. It

    is a facet of audi alteram partem rule to ensure that procedural fairness

    is observed before any adverse findings are made against such person.

    62. Section 8C provides for right to cross-examine any adverse

    witness referred to in Section 8B, whose evidence is recorded by the

    Commission. It also confers the right to appear through the legal
    82

    practitioner. The provisions under Sections 4 and 5(2) relate to

    inquisitorial power of the Commission for obtaining facts. Section 8B is

    the statutory embodiment of the audi alteram partem, if the Report of

    the Commission is likely to be stigmatic upon the conduct or reputation

    of that person, though it is not legally binding, unlike the adjudicatory

    findings rendered by a court. On behalf of the petitioners, reliance has

    been placed on the case of K.Vijaya Bhaskar Reddy (supra) where the

    notices were vague on account of not referring to materials on record of

    the Commission, which, if accepted, would prejudicially affect the

    reputation of the petitioners. In the said case, notice under Section 8B

    was quashed on that ground.

    63. It is true that the Rules of 1972, framed under Section 12 of the

    Act of 1952 do not prescribe any statutory format for issue of service of

    summons. Rule 4 provides for the issue of summons to persons whose

    attendance before it may be required to give evidence or to produce

    documents and the manner in which the summons is to be served. Rule 5

    provides that the Commission may issue a notice to every person who in

    its opinion should be given an opportunity of being heard in the enquiry,

    to furnish to the Commission a statement relating to such matters as may
    83

    be specified in the notice. Rule 5(2)(b), on the other hand, provides for

    issuance of notification inviting all persons acquainted with the subject

    matter of the inquiry to furnish to the Commission a statement relating

    to such matters as may be specified in the notification. Under sub-rule

    (3) every statement furnished under clause (a) of sub-rule (2) shall be

    accompanied by an affidavit in support of the facts set out in the

    statement sworn by the person furnishing the statement. Under sub-rule

    (4), every such person furnishing a statement under clause (a) of sub-

    rule (2) shall also furnish to the Commission along with the statement, a

    list of the documents on which he proposes to rely and forward to the

    Commission. Under sub-rule (5), the Commission shall examine all

    statements furnished to it under clause (b) of sub-rule (2) and if, after

    such examination, the Commission considers it necessary to record

    evidence, it shall first record the evidence, if any, produced by the

    Central Government and may thereafter record evidence in such order as

    it may deem fit, of persons who furnished a statement under clause (a)

    of sub-rule (2), and whose evidence is considered relevant for the

    purpose of inquiry and any other person whose evidence, in the opinion

    of the Commission, is relevant to the inquiry. Proviso to sub-rule (5)(a)

    provides that the Commission may dispense with the attendance of any
    84

    person for the purpose of giving evidence for the reasons of hardship or

    inconvenience, or any other sufficient reasons to be recorded in writing.

    64. In Jai Prakash Associates (supra), it has been held that under

    Rule 5(2) notice or summons is issued to elicit information for the

    purpose of inquiry, whereas Section 8B applies when the Commission

    proposes to inquire into any person’s conduct or the reputation of any

    person which is likely to be affected, in which case he must be given a

    reasonable opportunity of hearing and to produce evidence in his

    defence. In the case of Jai Prakash Associates (supra), the Commission

    had issued a general notice and later a notice calling upon the petitioner

    to place its stand. The petitioner had sought clarification and time to

    respond contending that no specific allegations were disclosed. The

    request for adjournment was refused. The Commission proceeded to

    submit its Report which was challenged on the ground that the Report

    has not complied with the provisions of Sections 8B and 8C of the Act

    of 1952 and Rule 5 of the Rules of 1972. The Allahabad High Court

    quashed the report as the petitioner was not given reasonable

    opportunity of being heard and opportunity to produce evidence in his

    defence. It was further held that the report submitted by the Commission

    is in violation of the mandatory and statutory requirements.
    85

    65. In Kiran Bedi (supra), the apex Court opined that if conduct or

    reputation of the petitioners was being examined issuance of a notice

    under Section 8B of the Act of 1952 is attracted. Paragraphs 17, 20 and

    21 of the said judgment are extracted hereunder:

    “17. Consequently, we find it unnecessary to consider in
    any further detail, the submissions made by counsel for the parties
    on this point. Insofar as point (ii) is concerned, it would be seen
    that the use of the word “or” between clauses (a) and (b) of
    Section 8-B of the Act makes it clear that Section 8-B would be
    attracted if requirement of either clause (a) or clause (b) is
    fulfilled. Clause (b) of Section 8-B applies when the conduct of
    any person is to be enquired into whereas clause (b) applies to a
    case where reputation of a person is likely to be prejudicially
    affected. As regards the enquiry about the conduct of Smt Kiran
    Bedi and Jinder Singh, even the Committee in its interim report
    specifically stated that the conduct of these two petitioners among
    others was to be examined. Having once so stated in unequivocal
    terms, it was not open to the Committee to still take the stand that
    Section 8-B was not attracted insofar as they were concerned.
    Recourse to procedure under Section 8-B is not confined to any
    particular stage and if not earlier, at any rate, as soon as the
    Committee made the aforesaid unequivocal declaration of its
    intention in its interim report, it should have issued notice under
    Section 8-B to the two petitioners, if it was of the view as it seems
    to be, for which view there is apparently no justification, that issue
    of a formal notice under Section 8-B was the sine qua non for
    attracting that section. At all events, the Committee could not
    deny the petitioners the statutory protection of Section 8-B by
    merely refraining from issuing a formal notice even though on its
    own declared intention the section was clearly attracted.

    xxx xxx

    20. Keeping in view the nature of the allegations made in the
    statements of case and the supporting affidavits filed on behalf of
    the various Bar Associations including the Delhi High Court Bar
    Association requirement of even clause (b) of Section 8-B was
    fulfilled inasmuch as if those allegations were proved they were
    likely to prejudicially affect the reputation of the two petitioners.
    Indeed, in view of the term of reference which contemplated
    taking of “stringent action” against all those responsible, even the
    86

    career of the petitioners as police officers was likely to be affected
    in case an adverse finding was recorded against them. In view of
    the aforesaid specific term of reference, the principle that the
    report of a Commission of Enquiry has no force proprio vigore
    does not on a pragmatic approach to the consequences seem to
    constitute sufficient safeguard so far as the petitioners are
    concerned.

    21. The reason for the importance attached with regard to the
    matter of safeguarding the reputation of a person being
    prejudicially affected in clause (b) of Section 8-B of the Act is not
    far to seek.”

    66. In Lal Krishna Advani (supra), the apex court also reiterated the

    principle that right to reputation is a facet of right to life of a citizen

    under Article 21 of the Constitution of India. At para 6, it was held as

    under:

    “6. The High Court, while referring to a decision reported
    in State of J&K v. Bakshi Gulam Mohammad [AIR 1967 SC 122]
    observed that when an authority takes a decision, which may have
    civil consequences and affects the right of a person, the principles
    of natural justice would at once come into play. Reputation of an
    individual is an important part of one’s life. The High Court then
    quoted a passage from a decision of this Court reported in Kiran
    Bedi v. Committee of Inquiry
    [(1989) 1 SCC 494 : AIR 1989 SC
    714] which passage (SCC p. 515, para 25) contains the
    observations from an American decision in D.F. Marion v. Minnie
    Davis [55 American LR 171] and reads as follows:

    “The right to enjoyment of a private reputation,
    unassailed by malicious slander is of ancient origin, and
    is necessary to human society. A good reputation is an
    element of personal security, and is protected by the
    Constitution equally with the right to the enjoyment of
    life, liberty and property.”

    Some decisions, to which our attention has been drawn by Shri
    Harish N. Salve, learned Senior Counsel appearing for
    Respondent 1, may be referred: Board of Trustees of the Port of
    Bombay v. Dilipkumar Raghavendranath Nadkarni
    [(1983) 1 SCC
    124 : 1983 SCC (L&S) 61] wherein it was observed that right to
    reputation is a facet of right to life of a citizen under Article 21 of
    the Constitution. He has also referred to the International
    87

    Covenant on Civil and Political Rights, 1965 (ICCPR),
    recognizing the right to have opinions and the right of freedom of
    expression subject to the right of reputation of others. The
    Covenant provides:

    “1. Everyone shall have the right to hold opinions without
    interference.

    2. Everyone shall have the right to freedom of expression; this
    right shall include freedom to seek, receive and impart
    information and ideas of all kinds, regardless of frontiers, either
    orally, in writing or in print, in the form of art, or through any
    other media of his choice.

    3. The exercise of the rights provided for in paragraph 2 of
    this article carries with it special duties and responsibilities. It may
    therefore be subject to certain restrictions, but these shall only be
    such as are provided by law and are necessary:

    (a) for respect of the rights or reputations of others;

    (b) for the protection of national security or of public order
    (ordre public), or of public health or morals.”

    It is thus amply clear that one is entitled to have and preserve one’s
    reputation and one also has a right to protect it. In case any
    authority, in discharge of its duties fastened upon it under the law,
    traverses into the realm of personal reputation adversely affecting
    him, it must provide a chance to him to have his say in the matter.
    In such circumstances right of an individual to have the safeguard
    of the principles of natural justice before being adversely
    commented upon by a Commission of Inquiry is statutorily
    recognised and violation of the same will have to bear the scrutiny
    of judicial review. A reference may be made to Peter Thomas
    Mahon v. Air New Zealand Ltd. [1984 AC 808 : (1984) 3 All ER
    201 : (1984) 3 WLR 884 (PC)]

    67. It flows therefrom that if the right to reputation, which is a facet

    of right to life of a citizen under Article 21 of the Constitution of India,

    is likely to be affected by the decision of an authority, and it may have

    civil consequence, such a person is entitled to mandatory notice under

    Section 8B of the Act of 1952 giving a reasonable opportunity of being

    heard in the inquiry and to produce evidence in his defence. Therefore, it

    was incumbent upon the Commission to disclose the adverse materials
    88

    whether in the form of oral or documentary evidence, which in the

    opinion of the Commission, would affect the conduct of such person or

    his reputation prejudicially by its findings. What constitutes the

    ingredients of a statutory notice, such as one under Section 8B of the

    Act of 1952? In this regard, it is to be observed that though the Rule

    does not specifically provide for a statutory format, the allegations or

    adverse material and the source from which it has been derived are

    required to be referred to and indicated in the notice under Section 8B of

    the Act of 1952 to enable such person a reasonable opportunity to

    defend himself. Section 8C provides every such person a right to cross-

    examine and representation by legal practitioner. This is considered

    necessary not only to test the veracity of the statement of witness but

    also to impeach the credibility of such a witness.

    68. In the statutory scheme of the Act of 1952 and the Rules framed

    therein and the legal position rendered by the Supreme Court and the

    High Courts referred to above, it is now necessary to examine whether

    the findings of the Commission in its Report dated 31.07.2025 were

    adverse to the conduct or reputation of the petitioners.

    69. A perusal of the findings of the Commission as extracted

    hereinabove vis-a-vis each of these petitioners would show that they
    89

    adversely comment upon the petitioners’ conduct and are definitely

    prejudicial to their reputation. It is also evident from the nature of the

    summons issued upon them that none of the incriminating material

    relied upon by the Commission to record its findings against the

    petitioners were referred to or indicated in the summons.

    70. A perusal of the summons upon the petitioners, THR and KCR,

    would show that they were called upon to be examined and hear them

    upon the terms of reference of the Commission on 09.06.2025. The

    summons also indicated that the petitioners are at liberty to produce

    documents and records upon which they desire to rely upon and place

    before the Commission for consideration. These petitioners were

    examined as Commission Witnesses Nos.114 and 115 respectively. The

    total number of witnesses examined by the Commission was 119. As

    such by the time these petitioners were examined, the Commission had

    almost examined rest of the witnesses. The Commission also had the

    records relating to the cabinet resolutions, reports of the WAPCOS,

    National Dam Safety Authority, High Power Committee, State Level

    Standing Committee etc. The petitioners upon receipt of the summons

    requested for certain documents on 06.06.2025. The said documents

    were supplied to them on 09.06.2025, i.e., the date of the appearance of
    90

    the petitioner, THR before the Commission. The petitioner, THR was

    examined on 09.06.2025. The petitioner was put questions regarding the

    reason for construction of barrages at Medigadda, Annaram and Sandilla

    and also on whether cabinet approvals for construction of these barrages

    were taken. The Commission also put questions on the recommendation

    of the High Power Committee to shift the location of Annaram and

    Sundilla barrages. A perusal of the statement made by the petitioner

    indicates that he was examined on various aspects relating to the

    approval of the construction of the barrage, recommendations of the

    High Power Committee and the Expert Committee etc.

    71. The petitioner, KCR was examined on 11.06.2025. The petitioner

    was also put a number of questions relating to construction of the

    barrages at the three places as above. He was also questioned on other

    related aspects of the construction of the three barrages and matters

    regarding the Minutes of the Review Meeting; how the KIPCL will pay

    off the dues taken from various institutions; whether the Cabinet

    approval was there for construction of these barrages etc. However, the

    Commission had not referred to any adverse or incriminating materials –

    documentary or oral, in its summons to these petitioners, which in the
    91

    opinion of the Commission were likely to affect the conduct or

    reputation of the petitioner.

    72. The argument of the respondents-State that the petitioners THR

    and KCR were fully cognizant of the documentary evidence in the form

    of resolutions of the Cabinet and the reports of various Committees,

    which on their request were also supplied to them, amounted to

    substantive compliance of the requirement of reasonable opportunity of

    being heard and to defend themselves as per Section 8B of the Act does

    not merit acceptance. It is settled law that there can be no estoppel

    against the statute. The petitioners, THR and KCR were not offered

    reasonable opportunity to defend themselves during their examination

    on the materials relied upon by the Commission to record its findings

    which are impinging upon their conduct and reputation. The mere

    supply of the documents on the same day, i.e., 09.06.2025 to the

    petitioner, THR would not amount to giving a reasonable opportunity as

    contemplated under Section 8B of the Act of 1952 which is inserted

    with a specific object and purpose to allow such persons notice of the

    adverse materials collected and available with the Commission for being

    confronted during the course of their examination. Similarly, the supply

    of documents asked for to petitioner, KCR on 09.06.2025 two days
    92

    before his examination on 11.06.2025 cannot be considered as discharge

    of the statutory responsibility upon the Commission to refer to and

    provide the incriminating materials on which it wanted to rely and form

    opinion on the conduct or reputation of the petitioner as contemplated

    under Section 8B of the Act of 1952. It is not in dispute that the

    materials sought for and supplied by the Commission to these petitioners

    on 09.06.2025 on 11.06.2025 were several and voluminous. Their

    examination on such materials either on the same day 09.06.2025 or

    11.06.2025 in the respective cases cannot be construed as reasonable

    notice for defending themselves on questions put to them in relation to

    the decision making process, execution, implementation, operation and

    maintenance, awarding of tender of the three barrages. As such, whether

    the summons or notices upon these petitioners specifically referred to

    Section 8B of the Act of 1952 or not could not be of any significance as

    in substance the summons did not conform to the requirement of proper

    notice under Section 8B of the Act of 1952, to which the petitioners

    were entitled before any findings or comments adverse and prejudicial

    to their conduct and reputation could be recorded by the Commission.

    The argument to the contrary made on behalf of the respondents-State

    does not merit acceptance. The findings of the Commission on lapses

    related to Political Executives i.e., petitioners, THR and KCR, the then
    93

    Irrigation Minister and the then Chief Minister respectively that the

    entire project was characterised by rampant and brazen procedural and

    financial irregularities adversely comment upon the conduct of the

    petitioners and are prejudicial to their reputation. The Commission has

    also recorded that the petitioner, KCR is directly and vicariously

    accountable for irregularities and illegalities in planning, construction,

    completion, operation and maintenance of the three barrages. His

    involvement and directions are the cause and result of irregularities and

    distress to the three barrages. That the then Chief Minister, i.e., KCR

    was pre-determined and bent upon to construct barrage at Medigadda at

    his free choice and the authorities associated with the decision making

    facilitated them. The Commission had also observed that there was

    clinching evidence of an intent to siphon public funds to unduly favour

    agencies. These findings are definitely prejudicial to their conduct and

    reputation.

    73. The requirement of a mandatory notice under Section 8B of the

    Act of 1952 is a statutory safeguard introduced in public interest to

    prevent loss of reputation, which is a facet of right to life to such

    persons. Any inference of waiver of such a right cannot be inferred by

    their appearance and examination by the Commission on the dates fixed.
    94

    Their participation in any other Commission of Inquiry constituted

    earlier like the one headed by Justice L.Narasimha Reddy cannot also be

    taken as a defence by the respondents-State to sustain the findings of the

    Commission against these petitioners. The respondents-State has placed

    reliance on the decision of K.L.Tripathi (supra) in support of their

    submissions. In K.L.Tripathi (supra), conduct of the appellant as a

    Branch Manager of the Bank was being enquired. The appellant was

    associated with the preliminary investigation and his versions or

    explanations were sought for and recorded. He had participated in the

    investigation, gave his explanation, neither disputed any of the facts

    questioning the veracity of the witnesses or the entries or the letters or

    documents shown to him upon which the charges were framed and upon

    which he was found guilty. The observations of the apex court that

    where there is no lis regarding the facts but certain explanation of the

    circumstances, there is no requirement of cross-examination to be

    fulfilled to justify fair play in action and no real prejudice has been

    caused to the party aggrieved by the order was rendered in the aforesaid

    context. The facts of the present case are distinct as the petitioners were

    not associated with the enquiry conducted by the Commission while

    recording the statement of other witnesses and collection of

    documentary evidence any time before they were asked to appear by the
    95

    summons dated 06.09.2025. The Commission did not refer to the

    incriminating materials in the summons issued to them on which the

    Commission sought to rely upon in course of their examination and

    while recording its finding against them. The proposition laid down in

    the cases of N.Mani (supra) and P.K.Palanisamy (supra) relied on by

    the respondents-State that mere non-mentioning or reference to a wrong

    provision of law would not vitiate the exercise of power so long as the

    source of power can be traced is well settled. However, insertion of

    Sections 8B and 8C in the Act of 1952 is a statutory procedural

    safeguard with a salutary purpose for protecting any adverse or

    prejudicial finding by the Commission on the conduct or reputation of

    such person without proper notice to them. The absence of a prescribed

    format or non-mentioning of Section 8B in the summons is not an issue.

    The absence of the incriminating material or its reference in the

    summons issued on the petitioners in substance renders the summons

    illusory and failing to comply with the statutory safeguard provided

    under Section 8B of the Act. The learned Senior Counsel for the

    respondents-State has referred to the decision of R.Rajagopal (supra)

    specifically paragraph 26, but the said case deals with the right to

    privacy guaranteed under the right to life and liberty to the citizens of

    the country under Article 21 of the Constitution of India. The decision
    96

    was rendered in the context of publication of the life story or biography

    of one Auto Shankar who was convicted for six murders and sentenced

    to death. In this background, the apex court examined the principles of

    right to privacy and freedom of speech and expression guaranteed under

    Article 19(1)(a) of the Constitution of India, which is subject to

    reasonable restrictions. The said decision in inapplicable in the facts of

    the present case, where the findings of the Commission have been

    assailed on the ground that they are prejudicial to the conduct and

    reputation of the petitioners which is a facet of right to life, without

    following the statutory safeguard under Section 8B of the Act of 1952.

    74. The petitioners, SKJ and SS, who were serving as Indian

    Administrative Service officers working as the Chief Secretary and the

    Additional Secretary to the Chief Minister respectively during the

    decision making and execution of the project, also received a notice to

    attend the meeting before the Commission on 15.07.2024. Both the

    notices are in the same language and content and have been extracted in

    the foregoing paragraphs.

    75. Pursuant to the notice, both the petitioners appeared before the

    Commission. They were asked to submit an affidavit containing their

    statement on affidavit. The petitioner, SKJ submitted the statement on
    97

    affidavit on 21.07.2024. He had retired in the year 2019. The petitioner,

    SS also submitted her statement on affidavit on 01.08.2024. Both the

    statements delineate in substance that their role and responsibilities in

    their official capacity during the relevant period. Thereafter, no notice or

    summons was issued upon them till December, 2024 when they were

    telephonically asked to appear before the Commission for examination.

    They appeared before the Commission on 18.12.2024 (SKJ) and

    19.12.2024 (SS) respectively. Their statements were recorded as

    witnesses C.W.92 and C.W.95 respectively.

    76. The petitioner, SKJ was asked questions relating to the decision

    on construction of barrages at Medigadda, Annaram and Sundilla; on the

    constitution of the High Power Committee, the scope of the State Level

    Standing Committee and whether any administrative approvals covering

    the project were taken. He was also asked questions regarding the design

    and plan of the project and the cause of the defect found in Medigadda

    barrage in Block No.7. The petitioner, SS was also asked questions

    regarding the construction of barrages at Medigadda, Annaram and

    Sundilla; whether the matter was placed before the cabinet for approval

    in respect of the said barrages, her role as Secretary to the Chief
    98

    Minister and whether any dissenting notes were placed before the Chief

    Minister.

    77. The Commission evidently did not serve any notice containing

    any adverse materials upon these two petitioners as contemplated under

    Section 8B of the Act of 1952. The summons issued to the petitioners,

    SKJ and SS, dated 08.07.2024 and 12.07.2024 was only to attend the

    meeting with the Chairman of the Commission. It can in no way be

    treated as summons under Section 8B of the Act of 1952. No summons

    in any form was issued thereafter upon these two petitioners. They were

    telephonically informed to appear before the Commission for

    examination in December, 2024. It can therefore be concluded that no

    notice under Section 8B of the Act of 1952 was issued upon these two

    petitioners giving them a reasonable opportunity of being heard and

    defend themselves, against the materials collected during the inquiry by

    the Commission. The Commission recorded adverse findings on their

    conduct and reputation without giving them any reasonable opportunity

    of being heard as required under Section 8B of the Act. The petitioners

    have relied upon the case of Canara Bank (supra) on the proposition

    that notice must be precise and unambiguous as an approved rule of fair

    play in action and the principles of natural justice. The respondents-State
    99

    has on the other hand contended that all the findings are based upon the

    public records produced before the Commission. However, no such

    documents were supplied to the petitioners SKJ and SS to defend

    themselves during their examination. Evidently, the examination of

    these petitioners was not in course of the inquisitorial or investigative

    role of the Commission under Section 4 or 5(2) of the Act of 1952 for

    collecting evidence. If the Commission had the basis to render findings

    prejudicial to the conduct or reputation of these petitioners, it was

    obligatory upon it to provide them with the incriminating material,

    which it failed to do so. The contention of the respondents-State that the

    findings rendered by the Commission are confined to their role as public

    servants and do not impinge upon their personal conduct or reputation

    does not merit acceptance. The Commission has recorded that petitioner,

    SS was not diligent, rather negligent and irresponsible in discharge of

    her duties and is also liable for action for violation of the Business Rules

    of the Government. Similarly, the Commission has rendered a finding

    against the petitioner, SKJ as being liable for intentionally suppressing

    the Report of the Expert Committee constituted under G.O.Rt.No.28

    with an oblique motive to enable the Government to construct the

    project at Medigadda. Therefore, appropriate action should be taken

    against him in accordance with law for committing irregularities and
    100

    violating the Business Rules of Government by not placing the file

    relating to G.O.Rt.No.212, dated 13.04.2025 and G.O.Rt.No.40, dated

    18.01.2016 before the Cabinet for approval, though G.O.Rt.No.212 was

    subsequently ratified by the Cabinet on 03.06.2016. The findings cannot

    be construed as innocuous in nature. Such findings of the Commission

    prejudicially affect the conduct and reputation of the petitioners. They

    were, therefore, entitled to the statutory notice under Section 8B of the

    Act introduced to provide safeguard to the personal reputation of such

    persons likely to be affected by the findings of the Commission of

    Inquiry. The right of reputation has been treated as facet of right to life

    as reiterated in the case of Lal Krishna Advani (supra). This Court is,

    therefore, of the opinion that the Commission failed to observe the

    statutory requirement of service of notice under Section 8B of the Act of

    1952 before recording the findings, which are prejudicial to the conduct

    and reputation of these petitioners. In these circumstances, following the

    ratio rendered by the apex court in the case of Kiran Bedi (supra) and

    Lal Krishna Advani (supra) and other decisions referred to

    hereinabove, it is held that the findings in the Report of the Commission

    dated 31.07.2025 which are prejudicial in nature and adversely affect the

    conduct and reputation of these petitioners shall be inoperative and no

    action shall be taken on the basis thereof. As observed in the case of Lal
    101

    Krishna Advani (supra), it may not be necessary for a person to wait

    till certain action is initiated by the Government considering the report

    of the Inquiry Commission, where the observations made by the

    Commission are such which militate against the reputation of a person

    and particularly, without giving any chance to such a person to explain

    his conduct.

    Conclusion:

    78. In view of the elaborate discussion made and the reasons

    recorded hereinabove, this Court holds:

    (i) that the constitution of the Commission of Inquiry under

    Section 3 of the Commissions of Inquiry Act, 1952 vide G.O.Ms.No.6,

    dated 14.03.2024 is neither arbitrary, illegal nor ultra vires the

    Constitution of India and the Commissions of Inquiry Act, 1952; and

    (ii) that the findings rendered by the Commission as are

    prejudicial to the conduct and reputation of the petitioners and have been

    rendered in violation of the principles of natural justice and the statutory

    safeguard provided under Section 8B of the Commissions of Inquiry

    Act, 1952, shall be inoperative and no action can be taken on the basis

    thereof.

    102

    79. The writ petitions are accordingly partly allowed in the manner

    indicated above. There shall be no order as to costs.

    Miscellaneous applications pending, if any, shall stand closed.

    ______________________________________
    APARESH KUMAR SINGH, CJ

    ______________________________________
    G.M.MOHIUDDIN, J

    22.04.2026

    Note: LR Copy be marked
    (By order)
    Pln



    Source link

    LEAVE A REPLY

    Please enter your comment!
    Please enter your name here