Raj Construction And Co vs Garrison Engineer (Central) And Anr on 24 February, 2026


1. The petitioner is a proprietorship concern. The notice inviting tender was

issued by the respondent no.1 on February 16, 2024. The petitioner

participated and emerged as the successful bidder. The petitioner was

issued a letter of acceptance on March 9, 2024. Formal contract was

executed. The date of handing over the possession of the site was

scheduled on April 8, 2024 and the actual date of completion was

scheduled on January 2, 2025. The GCC (IAFW-2249) along with its

subsequent amendments were made applicable to the subject contract.

The work related to Periodical Services Plastering ATT and Miscellaneous

Works at MAP PH-II under GE(C) Kolkata. According to the petitioner, the

work site was not handed over within the stipulated time. The buildings

were occupied by residents. As such, the maintenance work could not

commence on time. The samples of the materials were sent to the

respondents, but the respondents did not approve the same. The

petitioner commenced work later but contends to have performed some

extra work. However, on account of non-approval of the samples, the

petitioner could not execute the work in the mode and manner provided in

the tender document. Show-cause notice was issued to the petitioner.

The petitioner replied to the show-cause notice. By a notice dated

January 23, 2025, time for completion was extended.