Neeli Prathap vs The State Of Telangana on 9 April, 2026

    0
    35
    ADVERTISEMENT

    Telangana High Court

    Neeli Prathap vs The State Of Telangana on 9 April, 2026

                                      1
    
    
    
    
         IN THE HIGH COURT FOR THE STATE OF TELANGANA AT
                            HYDERABAD
    
          THE HON'BLE SRI JUSTICE SUDDALA CHALAPATHI RAO
    
                          WP.No. 26799       of 2016
    
                                Dt.09.04.2026
    
    Between:
    
    Neeli Prathap
    
                                                           .... Petitioner
    
                                     and
    
    The State of Andhra Pradesh, rep. by its
    Principal   Secretary   to   the Municipal
    Administration and two others.
                                                          ...Respondents
    
    O R D E R:

    1. The present Writ Petition has been filed to declare the notice

    issued by the 2nd respondent in Lr.Roc.No.G1/646/2016,

    SPONSORED

    dt.04.04.2016, directing the petitioner to stop construction in plot

    admeasuring 155.55 sq. yards in Survey No. 1398 situated at

    Korutla Town, though permission has been granted by the 2nd

    respondent for construction of ground + First floor on 11.03.2015

    through permit No. 37/2016, as arbitrary, illegal, void ab initio

    and violative of principles of natural justice and also violative of

    Articles 14, 19, 21 and 300A of the Constitution of India and to
    2

    pass such other order or orders as deemed fit and necessary in

    the interest of justice and circumstances of the case.

    2. The brief facts of the case are that the petitioner is the

    absolute owner and possessor of land admeasuring 155.55 sq.

    yards in Survey No.1398 situated at Korutla Village & Mandal,

    Karimnagar District, having purchased the same through a

    registered document bearing No.2607/2015, dt.08.05.2015, after

    getting the said plot surveyed from the office of the Assistant

    Director, Survey & Land Records and the boundaries having been

    duly fixed by the said authority by way of panchanama, in the

    presence of respondent No.3, vide panchanama dt.02.05.2015.

    3. The petitioner further contended that he had made an

    application to the 2nd respondent for grant of permission for

    construction of a commercial building consisting of Ground + First

    Floor in the said plot and the 2 nd respondent addressed a letter

    dt.31.07.2015, to clarify whether the plot of the petitioner situated

    in Survey No. 1398 is patta land or government land or belongs to

    Sri Venkateshwara Swamy Temple, Korutla, and that pursuant to

    the said letter, the Office of the Assistant Director, Survey & Land
    3

    Records addressed a letter to the 2 nd respondent on 08.10.2015

    stating that the plot belonging to the petitioner is in Survey

    No.1398, it is a patta land and also furnished a location sketch of

    the said plot of the petitioner along with the said letter and

    thereafter, the 2nd respondent granted permission vide permit No.

    37/2016, dt.11.03.2015.

    4. It is further stated by the petitioner that after granting the

    said permission by the 2nd respondent, the petitioner started

    construction and completed till basement level and pillars, and at

    this juncture, the 2nd respondent issued a notice, dt.04.04.2016,

    to the petitioner stating that the 3rd respondent submitted an

    objection petition and also addressed a letter to the Joint Collector

    requesting not to accord building permission in the land of Sri

    Venkateshwara Swamy Temple, Korutla, i.e., the 3 rd respondent

    herein, and directed the petitioner to stop construction work till

    the said land is surveyed. Challenging the said letter, the instant

    writ petition has been filed.

    5. On the other hand, the 2nd respondent-Municipality filed

    counter contending that though the petitioner has produced
    4

    certain registered documents to establish title, the claim of

    absolute ownership is disputed, and that the petitioner failed to

    disclose in his affidavit that the land in question is under dispute,

    despite the 3rd respondent having brought the ownership dispute

    to the notice of the 2nd respondent, and thus, there is suppression

    of material facts.

    6. It is further contended that the petitioner’s assertion that

    the land was surveyed through the office of the Assistant Director,

    Survey & Land Records and that boundaries were fixed in the

    presence of panchas and the 3 rd respondent is specifically denied,

    and in any event, such survey, panchanama, or fixation of

    boundaries does not conclusively establish ownership rights, and

    the presence of officials of the 3rd respondent does not amount to

    relinquishment or confirmation of title in favour of the petitioner.

    7. By the counter affidavit the 2nd respondent admitted when

    the petitioner applied for building permission, a letter

    dt.31.07.2015 was addressed seeking clarification as to whether

    the land in Survey No.1398 is patta land or belongs to Sri

    Venkateshwara Swamy Temple, and that the office of the Assistant
    5

    Director, Survey & Land Records replied stating that the land falls

    in Survey No. 1398 and is patta land and furnished a location

    sketch, but however, contended that such initial response did not

    conclusively determine title or deny the claim of the 3rd

    respondent, and the matter required further enquiry and

    verification, for which process was undertaken.

    8. It is further submitted that, upon prima facie satisfaction of

    the petitioner’s claim, building permission was granted, but the

    same was subject to conditions and restrictions, including that

    such permission does not confer or validate title, and if the claim

    is found to be false or unsupported, the permission is liable to be

    revoked.

    9. It is submitted that subsequently, the 3rd respondent

    addressed a letter stating that the land claimed by the petitioner

    forms part of temple property in Survey No.1398/1 and also

    addressed a communication to the Joint Collector, marking a copy

    to the 2nd respondent, thereby raising a serious dispute regarding

    ownership, in view of which the 2nd respondent, taking note of the

    boundary dispute between Survey Nos.1398 and 1398/1, issued
    6

    the impugned notice dt.04.04.2016 directing the petitioner to stop

    construction until completion of a survey.

    10. It is further contended in the said counter affidavit that the

    stoppage of construction is only a temporary measure, and it

    would be reconsidered upon clarification and re-survey with

    regard to the land in Survey No.1398 claimed by both the

    petitioner and the 3rd respondent-temple authorities, and that the

    impugned notice has been issued by following due procedure

    under law, and therefore, the writ petition is devoid of merits and

    liable to be dismissed.

    11. Heard Sri A.Venu Madhav, learned counsel for petitioner,

    Sri Putta Krishna Reddy, learned Standing Counsel for 2 nd

    respondent, and Sri C.S.Satish Kumar, learned counsel for 3rd

    respondent.

    12. Learned counsel for petitioner contended that initially the

    Assistant Director, Survey & Land Records has fully demarcated

    the plot of the petitioner by conducting survey along with sketch

    map and also panchanama, dt.02.05.2015, in the presence of the

    3rd respondent and categorically stated that the land of the
    7

    petitioner was situated in survey No.1398 and that it is a private

    patta land and that the 2nd respondent also while granting

    permission for construction of Ground + First floor commercial

    building has also addressed a letter to the Assistant Director,

    Survey & Land Records, wherein the said survey was conducted in

    the presence of the 3rd respondent and the Assistant Director has

    categorically opined that the plot of the petitioner is located in

    Survey No. 1398 and also furnished the details of the survey to

    the 2nd respondent and the 2nd respondent having satisfied with

    the prima facie title of the petitioner and also the plot where the

    petitioner’s land is situated was in Survey No.1398, being a patta

    land, granted due permission for construction of commercial

    building consisting of Ground + First floor and that now after

    granting permission and also commencing construction up to

    basement level, the impugned letter vide Lr.Roc.No.G1/646/2016,

    dt.04.04.2016, was issued by the 2nd respondent, which is

    untenable and violative of due procedure of law.

    13. It is further stated by the learned counsel that in a similar

    set of facts, this Hon’ble Court in the case of K.Pavan Raj Vs.
    8

    Municipal Corporation of Hyderabad 1 held that once the

    municipal authorities are prima facie satisfied with the legal title

    of the applicant and lawful possession, they are bound to consider

    the building permission on merits, leaving the objector free to

    approach the appropriate Court.

    14. Learned counsel for the petitioner further contended that the

    petitioner herein is similarly placed as in the aforesaid judgment,

    as in the instant case the 2nd respondent having satisfied as to the

    prima facie title and possession of the petitioner over the subject

    land and granted permission by following due procedure of law, is

    estopped from giving directions to the petitioner to stop

    construction till the measurement of the land of the 3 rd

    respondent is completed, which is violative of due procedure

    contemplated under law and that at present, in view of the interim

    suspension granted by this Court, the petitioner has compelted

    the construction in accordance with the building permission and

    thus, the impugned proceeding is liable to be set aside and

    quashed.

    1 2008 (1) ALD 792
    9

    15. Per contra, learned Standing Counsel while reiterating the

    counter averments, contended that, though the petitioner placed

    reliance on certain registered documents, his claim of absolute

    ownership is disputed by the Revenue and Endowments

    Departments, and he suppressed the material fact that the land is

    under dispute, despite the same having been brought to the notice

    of the 2nd respondent by the 3rd respondent.

    16. It is further contended that though clarification was sought

    and a reply was received stating the land to be patta land, the

    same was only preliminary and did not conclusively determine

    title, as counter claims require further enquiry and further

    building permission granted was only upon prima facie

    satisfaction and subject to conditions that it does not confer title

    and is liable to be revoked if based on incorrect or disputed

    claims, and thus, the impugned notice dt.04.04.2016 was issued

    directing stoppage of construction pending survey and prayed to

    dismiss the writ petition.

    17. It is contended that such stoppage is only temporary,

    pending clarification and re-survey, and that the impugned action
    10

    is lawful, procedural, and the writ petition is devoid of merits and

    liable to be dismissed.

    18. I have given earnest consideration to the submissions made

    by the counsel appearing on either side and perused the record.

    19. It is an admitted fact that the building permission has been

    approved by the 2nd respondent by following due procedure as

    contemplated under the Greater Hyderabad Municipal

    Corporation Act, 1955 and it is also an admitted fact that even

    before the issuance of the building permission, the 2nd

    respondent addressed a letter to the Assistant Director, Survey &

    Land Records, so as to confirm whether the plot of the petitioner is

    a patta land or belongs to the government or 3rd respondent-

    Temple and in pursuance of the same, the Assistant Director,

    Survey & Land Records conducted a detailed survey in the

    presence of the 3rd respondent authorities and addressed a letter

    along with site plan and sketch plan of the plot to the 2 nd

    respondent by categorically stating that the said plot of the

    petitioner is a patta land and is not coming in any way or belongs

    to the 3rd respondent or Government and that a panchanama was
    11

    conducted by clearly fixing the boundaries of the said plot on

    02.05.2015.

    20. Evidently, the petitioner has established prima facie title

    over the said plot, which is falling under Survey No. 1398 and the

    2nd respondent having satisfied with the prima facie title of the

    petitioner over the said plot, now cannot in any way obstruct the

    construction of the house over the said plot.

    21. Initially, when the matter came up for hearing for admission

    on 11.08.2016, this Court in WP.MP.No.33173 of 2016, has

    observed the aforesaid fact and granted interim suspension of the

    said letter dt.04.04.2016 and it is stated by the learned counsel

    for petitioner that as of date, entire construction is completed.

    22. Further, the 2nd respondent has not denied the positive

    assertion of the petitioner in respect of survey conducted by the

    Assistant Director, Survey & Land Records, moreover, specifically

    admitted the fact that the petitioner has prima facie title, but in

    view of the letter addressed by the 3rd respondent to the Joint

    Collector in respect of the claim of the 3rd respondent’s title over
    12

    the plot along with other lands, the impugned notice has been

    issued.

    23. Further, in view of the order passed by this Court in

    K.Pavan Raj‘s case that once the municipal authorities are

    satisfied with the prima facie title of the applicant or the

    prospective person, and also the lawful possession, they are

    bound to consider the building permission application on merits

    leaving the objectors to approach the appropriate Court of law.

    24. Also, in Sura Kumaraswamy vs. State of Telangana and

    others2, a Division Bench of this Court while considering the

    similar issues, held as under:

    “9. It is settled proposition of law that mere regularisation or
    payment of tax does not confer title in the property. Further,
    the suit instituted by the appellant is against the vendor of
    the petitioner, that too a suit for injunction simplicitor, which
    does not decide the inter se dispute with regard to title or
    ownership. The appellant knowing very well that the
    petitioner has purchased the property through a registered
    sale deed, vide document bearing No.13985 of 2021 dated
    26.04.2021, and her vendor in turn purchased the same

    2Judgment dated 18.10.2022 passed in Writ Appeal No.585 of 2022 by the Hon’ble
    Division Bench of this Court
    13

    through a registered sale deed vide document No.22232 of
    2019 dated 31.08.2019, did not take any steps for
    impleading the petitioner as a party defendant in the
    pending suit. Further, except submitting objection petition to
    the municipal corporation, the appellant has not instituted
    any suit disputing the title or obtained any orders
    restraining the Commissioner from entertaining the building
    application. Unless there are prohibitory/ restraining
    orders, the statutory authorities can proceed to examine the
    claims of the parties. As per provisions of Sections 428 and
    439 of the Greater Hyderabad Municipal Corporation Act,
    1955 (briefly “the GHMC Act“, hereinafter) the
    Commissioner is empowered to examine the building
    applications basing on the title deeds. While examining
    prima facie verification of the title, the Commissioner cannot
    assume the role of an adjudicator or arbitrator to decide the
    inter se title disputes between the applicant for building
    permission and the objector. If the petitioner is able to show
    prima facie title and he has right to proceed with the
    construction in conformity with the building permission
    granted by the Corporation. 10. Section 450 of the GHMC
    Act prescribes that at any time after permission to proceed
    with any building or work has been given, if the
    Commissioner is satisfied that such permission was
    granted in consequence of any material misrepresentation
    or fraudulent statement contained in the notice given or
    information furnished under Section 428 or 433, he is
    empowered to cancel building permission.

    14

    12. It is also a settled principle that the person setting up a
    rival claim of title is free to approach the Court of competent
    jurisdiction and seek appropriate relief in that regard. If the
    applications for building permission are rejected, merely on
    the ground of third party claims or disputes of title, it may
    result in serious hardship to the owners of the properties.
    Since the Commissioner has not applied his mind while
    issuing revocation orders, the learned Single Judge has
    rightly allowed the writ petition which does not warrant
    interference of this Court in exercise of Letters Patent
    jurisdiction.

    25. In the instant case also, the 2nd respondent having satisfied

    with the prima facie title of the petitioner in the light of the survey

    report of the Assistant Director, Survey & Land Records, and the

    panchanama conducted in the presence of the officials of the 3 rd

    respondent, having granted permission to the petitioner, and

    moreover, pending writ petition, pursuant to the interims

    suspension granted by this Court, the petitioner is stated to have

    competed the construction, this Court is of the considered view

    that the 3rd respondent-Temple has got appropriate course under

    Section 87 of the Endowments Act and thus, the impugned notice

    is not tenable and is liable to be set aside and quashed.
    15

    26. In view of the above stated findings, the Writ Petition is

    allowed and the impugned proceeding, dt.04.04.2016, is hereby

    set aside and quashed. However, this does not preclude the 3rd

    respondent from approaching the Endowment Tribunal under

    Section 87 of the Charitable and Endowments Act, 1890, if they

    intend to do so. No order as to costs.

    As a sequel, miscellaneous petitions pending if anyu shall

    stand closed

    ________________________________
    SUDDALA CHALAPATHI RAO, J

    09th April, 2026

    gra
    16

    THE HON’BLE SRI JUSTICE SUDDALA CHALAPATHI RAO

    WP.No. 26799 of 2016

    Dt.09.04.2026

    gra



    Source link

    LEAVE A REPLY

    Please enter your comment!
    Please enter your name here