― Advertisement ―

HomeN.P. Vijaya Lakshmi vs Atul P Desai on 17 April, 2026

N.P. Vijaya Lakshmi vs Atul P Desai on 17 April, 2026

ADVERTISEMENT

Telangana High Court

N.P. Vijaya Lakshmi vs Atul P Desai on 17 April, 2026

Author: K. Lakshman

Bench: K. Lakshman

  IN THE HIGH COURT FOR THE STATE OF TELANGANA
                          AT: HYDERABAD
          HON'BLE SRI JUSTICE K. LAKSHMAN
                         AND
        HON'BLE JUSTICE B.R.MADHUSUDHAN RAO

 CIVIL REVISION PETITION Nos. 783, 785 AND 894 OF 2026
Date: 17-04-2026

Between in CRP No.783 of 2026
N.P.Vijayalakshmi and two others                        ....Petitioners
                                  and
Atul P Desai and others                               .....Respondents

This Court passed the following

COMMON ORDER (Per Hon'ble Sri Justice K.Lakshman)

Since the parties and the lis involved in these revisions are one

and the same, these revisions are heard together and being disposed of

SPONSORED

by the common order.

2. Heard Sri T. Bala Mohan Reddy, learned counsel for the

petitioners in all the revisions and Sri R.Sushanth Reddy, learned

counsel for respondents in CRP No.783 of 2026 and respondent No.1

in CRP Nos.785 and 894 of 2026.

2

3. Learned counsel for the petitioners filed a memo vide USR

No.35471 of 2026 dated 18.03.2026 in CRP No.783 of 2026 stating

that 3rd respondent is also a Judgment Debtor, she stands on the same

footing as that of the petitioners, since she is residing in Australia, and

they could get her vakalath in time. Therefore, she is only a formal

party. Therefore, petitioners are not seeking any relief against her.

4. Learned counsel for the petitioners also filed a memo vide

USR No.35470 of 2026 dated 18.03.2026 in CRP No.785 of 2026

stating that 2nd respondent is also a Judgment Debtor, she stands on

the same footing that of the petitioners, since she is residing in

Australia, and they could get her vakalath in time. She is only a

formal party. Therefore, petitioners are not seeking any relief against

her.

5. Even in CRP No.894 of 2026 also, it is mentioned in the

cause title itself that 2nd respondent is a formal party.

6. These Civil Revision Petitions are filed under Section 115 of

Civil Procedure Code, 1908 (for short, ‘the CPC‘). CRP No.783 of

2026 is filed assailing the order dated 27.02.2026 passed in E.A.No.24
3

of 2026 in E.P.No.47 of 2026 by the learned XIV Additional Chief

Judge, City Civil Court, Hyderabad. Likewise, CRP No.783 of 2026 is

filed aggrieved by the order of the learned XIV Additional Chief

Judge, City Civil Court, Hyderabad in numbering and entertaining

E.P.No.47 of 2026 filed by 1st respondent under Order XXI Rule 11 of

CPC. Likewise, CRP No.894 of 2026 is filed challenging the order

dated 09.02.2026 passed in E.P.No.47 of 2026.

7. Facts which are not in dispute are as follows:-

i. Husband and father of the petitioners respectively i.e. Sri

N.Peethambar Naidu have executed two registered

development agreements -cum – General Power of

Attorney bearing document Nos.1865 and 1866 of 2004

both dated 30.06.2024 in favour of the 1st respondent for

development of old building with the land admeasuring

550 sq.yards bearing Municipal H.Nos. 4-1-410, 4-1-411,

4-1-414 situated at Abid Road, Hyderabad i.e. Schedule –

A property, and old building with land admeasuring

171.87 sq.yards bearing Municipal H.Nos.4-1-415, B.2,
4

situated at Abid Road, Hyderabad i.e. Schedule-B

property (for short, ‘the subject property’).

ii. There were disputes between the parties with regard to

development of the said property. Therefore, 1st

respondent had invoked arbitration clause in the said

development agreement – cum – GPA vide Arb.Appl.

No.22 of 2011 before the sole Arbitrator.

iii. Learned Arbitrator has passed an Award on 03.05.2012.

iv. Challenging the said Award, the petitioners filed a

petition vide O.P.No.1663 of 2012 under Section 34 of

the Arbitration and Conciliation Act, 1996 (for short, ‘the

Act, 1996″) and the same was dismissed on 11.06.2024.

v. Feeling aggrieved and dissatisfied with the said order,

the petitioners preferred an appeal vide CMA No.611 of

2024 before this Court and it is pending. No interim order

is granted in the said appeal.

vi. On 07.01.2026, 1st respondent herein has filed an

Execution Petition vide E.P.No.47 of 2026 seeking
5

execution of the Award, dated 03.5.2012 passed in

Arb.Appl.No.22 of 2011 passed by the sole Arbitrator.

vii. Along with the said EP, 1st respondent has also filed two

Execution Applications. Learned XIV Additional Chief

Judge, City Civil Court, Hyderabad, issued warrant under

Order XXI Rule 35 of CPC and directed the Bailiff to

deliver possession of schedule -A and B properties. The

Bailiff filed report on 24.02.2026 stating that the

premises is locked.

viii. 1st respondent had filed E.A.No.24 of 2026 seeking a

direction to break open the lock and deliver possession of

the E.P.Schedule -A and B properties. On 27.02.2026,

learned XIV Additional Chief Judge, City Civil Court,

Hyderabad allowed the said EA and posted the matter to

18.03.2026 directing the Bailiff to break open the lock, if

necessary to remove obstruction, if any, in accordance

with law and deliver vacant and actual physical

possession of the schedule-A and B properties to the 1st
6

respondent/D.Hr. if remind by take up by police aid, for

execution of the warrant, the Bailiff is directed to prepare

a detailed panchanamas at the time of execution and

submit a compliance report by 18.03.2026.

ix. Challenging the said order dated 27.02.2026 in E.P.No.24

of 2026, the petitioners/J.Drs. filed C.R.P.No.783 of

2026.

x. The petitioners have also filed a revision vide CRP

No.785 of 2026 to declare the order of learned IV

Additional Chief Judge, City Civil Court, Hyderabad in

numbering and entertaining the E.P.No.47 of 2026.

xi. The petitioners have also filed a revision vide CRP

No.894 of 2026 challenging the order darted 09.02.2026

in the said E.P.

xii. Vide order dated 09.02.2026, learned Executing Court

passed the order as “Register. Issue Warrant U/O-XXI

R.35 to J.Dr. No.1 to 4 through Court and RPAD. Call on

24.02.2026.”

7

8. CONTENTIONS OF THE PETITONERS:-

i. 1st respondent/J.Dr. has filed the aforesaid E.P.No.47 of 2026

straightaway before the learned IV Additional Chief Judge, City

Civil court, Hyderabad, which is contrary to the procedure laid

down under the Arbitration and Conciliation Act, 1996, CPC

and Telangana Civil Courts Act, 1972. Referred Section 21 of

the Act, 1996, Section 3 of CPC and also Section 6 the

Telangana Civil Courts Act in support of his contentions. The

E.P. is barred by limitation.

ii. Award is dated 03.05.2012 and therefore, Amendment 2015 to

the Act, 1996 is not applicable to the present arbitration

proceedings.

iii. 1st respondent has not filed certified copies of Award dated

03.05.2012 in Arb.Appl.No.22 of 2011 which is mandatory in

terms of Rule 240 of Civil Rules of Practice.

iv. Though the 1st respondent has filed an application to dispense

with filing of certified copy of the said Award, without passing
8

any order, Executing Court passed orders dated 09.02.2026 and

27.02.2026 illegally.

v. The aforesaid E.P.No.47 of 2026 was filed beyond two years of

the Award dated 03.05.2012 in Arb.Appl. No.23 of 2011 and

even then learned Executing Court passed orders without

issuing notice to the petitioners.

vi. Learned Executing Court passed orders dated 09.02.2026 and

27.02.2026 without assigning any reasons.

vii. 1st respondent has filed an application under Section 151 CPC

seeking a direction to Bailiff to break open the lock of the

schedule property and deliver vacant and actual possession of

the schedule properties to the D.Hr., by putting the D.Hr. in

possession thereof. He did not seek any relief of police aid.

Even then, vide impugned order, learned Executing Court

directed the Bailiff to take possession by executing the warrant

by seeking police aid.

viii. Executing Court cannot go beyond the scope of the Award.

Executing Court cannot interpret the Award.

9

ix. The Execution Petition is barred by limitation.

x. Reliance was placed on Article 136 and Section 15 of the

Limitation Act.

xi. Before amendment 2015, to the Act, 1996, filing of an

application under Section 34 itself is sufficient and there is no

need of filing stay petition. The stay is automatic. After

amendment 2015, to the Act, 1996, the J.Dr. has to necessarily

obtain stay in terms of Section 36 of the Act, 1996. In the

present case, the Award is dated 03.05.2012 i.e. prior to

amendment 2015. Without considering the said aspects, learned

Executing Court passed orders dated 07.02.2026 and

27.02.2026.

xii. Pursuant to the order dated 27.02.2026, Bailiff delivered

possession of both the schedule properties to 1st

respondent/D.Hr. who in turn demolished portion of schedule-A

property on 02.03.2026 at 3.00 A.M. Therefore, the entire

procedure adopted by Executing Court, is arbitral and illegal.
10

xiii. After amendment to Section 36 of the Act, 1996 in the year

2015, filing of an application under Section 34 of the Act, does

not operate as an automatic stay on enforcement of the arbitral

award. In the absence of any order of stay, the respondent was

always at liberty to initiate execution proceedings. Despite the

same, respondent failed to initiate execution for several years

and has come up with the present Execution Petition only in the

year 2026.

xiv. The Executing Court out not to have entertained the EP which

is not filed before the Court within the meaning of Section

2(1)(e) of the Act. The said EP is not maintainable before the

learned XIV Additional Chief Judge, City Civil Court,

Hyderabad, for execution of the Award directly.

xv. The Executing Court failed to follow the mandatory procedure

in numbering the EP that too, in the absence of filing of

certified copy of the award.

11

xvi. The Executing Court without passing order in EASR No.113 of

2026 filed by the respondent/D.Hr. to dispense with the filing of

certified copy of the original award, proceeded with the EP.

xvii. The Executing Court erred in passing the order dated

09.02.2026 in the EP filed beyond two years for handing over

physical possession in respect of the schedule-A and B

properties without notice to the J.Dr. is illegal and liable to be

set aside.

xviii. The Executing Court erred in passing order dated 09.02.2026 in

EP for non-existing relief by travelling beyond the relief

granted in the Award.

9. With the said submissions, the petitioners sought to set aside

the order dated 27.02.2026 and dismiss E.P.No.47 of 2026 as barred

by law.

10. Whereas, respondent/D.Hr. filed counter opposing the

present execution petition contending as follows:-
12

i. It is the learned XIV Additional Chief Judge, City Civil Court,

who dismissed AOP No.1663 of 2012 filed by the petitioners

under Section 34 of the Act, 1996 and therefore, 1st respondent

has filed execution petition straightaway before the said Court.

There is no irregularity.

ii. The petition filed under Section 34 of the Act, 1996 filed by the

petitioners was dismissed by the learned XIV Additional Chief

Judge, City Civil Court, Hyderabad on 11.06.2024. Though

they preferred an appeal vide CMA No.611 of 2024, there is no

stay in the said appeal and it is pending before this Court.

Therefore, the 1st respondent has filed the present Execution

Petition on 07.01.2026 i.e. within two years. Therefore, learned

XIV Additional Chief Judge, City Civil Court, registered the

said EP and issued warrant. Therefore, the said E.P. is within

limitation.

iii. Despite making efforts, 1st respondent could not get certified

copy of the said Award.

iv. Learned sole Arbitrator who passed Award is no more.
13

v. The Copy Application filed by 1st respondent before the learned

XIV Additional Chief Judge was returned. Therefore, 1st

respondent has filed an application in the said E.P. to dispense

with the filing of the certified copy of the said Award. The same

was allowed. Therefore, there is no error.

vi. In E.A.No.24 of 2026 in E.P.No.47 of 2026, 1st respondent

sought other orders which the Executing Court deems fit and

proper in the interest of justice. On consideration of the same

only, learned Executing Court directed the Bailiff to take police

aid in execution of the warrant. Therefore, there is no

irregularity.

vii. There is no challenge to the order dated 09.02.2026. Learned

XIV Additional Chief Judge passed the said order considering

the Award dated 03.12.2012 and the impugned order is within

the scope of the said Award. On consideration of the said

aspects only, learned XIV Additional Chief Judge, City Civil

Court, Hyderabad passed the order dated 09.02.2026 and there

is no irregularity.

14

11. With the said submissions, 1st respondent/D.Hr. sought to

dismiss the present CRPs.

12. We have heard Sri T. Bala Mohan Reddy, learned counsel

for the petitioners in all the revisions and Sri R.Sushanth Reddy,

learned counsel for the 1st respondent at length. Sri T.Bala Mohan

Reddy, learned counsel for the petitioners filed synopsis/note along

with judgments vide USR No.41877, dated 02.04.2026 in CRP

Nos.783 of 2026 and 785 of 2026. Whereas, Sri R.Sushanth Reddy,

learned counsel for the 1st respondent filed written arguments vide

USR No.35615, dated 18.03.2026 in CRP Nos.783 and 785 of 2026

and submissions vide USR No.42193, dated 02.04.2026.

13. Sri T.Bala Mohan Reddy, learned counsel for the petitioners

placed reliance on the principle laid down by the High Court for the

State of Telangana and the State of Andhra Pradesh in Potlabathuni

Srikanth vs. Shriram City Union Finance Limited 1, Board of

Control for Cricket in India vs. Kochi Cricket Private Limited 2,

1
2016 (2) ALD page 10
2
(2018) 6 SCC 287
15

Fountain Head Developers and others vs. Mrs. Maria Arcangela

sequeira and others3, Cheran properties Limited vs. Kasturi and

Sons Limited and other 4, Sundaram Finance Limited vs. Abdul

Samad and another 5, and M/s Nkg Infrastructure Limited vs.

State and others 6

14. Sri R.Sushanth Reddy, learned counsel for the 1st

respondent placed reliance on the principle laid down by the Apex

Court in Birma Devi vs. Subhash7, State of West Bengal vs.

Associated Contractors 8 and the judgment of learned Single Judge of

the High Court of Madhya Pradesh at Jabalpur in Dr. Subhash

Chandra Jain vs. Shri Digambar Jain Mahila Trust9 and the

principle laid down by the Apex Court in India Media Services

Pvt.Ltd. vs. SBPL Infrastructures 10, and the Division Bench of the

3
2007 SCC OnLine Bom 340
4
(2018) 16 SCC 413
5
(2018) 3 SCC 622
6
Manu/uc/0871/2012
7
2024 SCC Online SC 3676
8
(2015) 1 SCC page 32
9
S.A.No.1824 of 2025
10
(2022) SCC Online TS 3422
16

erstwhile High Court of Andhra Pradesh in Prabhakar Rao H

Mawle vs. Hyderabad State Bank11.

15. Considering the aforesaid contentions of the petitioners,

more particularly, procedural irregularities said to have been

committed by the learned XIV Additional Chief Judge, City Civil

Court, Hyderabad, vide order dated 17.03.2026, we have directed the

registry to call for the original record in E.P.No47 of 2026 from the

learned Executing Court. In compliance with the said order, Registry

has called for the original record. We have perused the same.

16. As discussed supra, there is no dispute with regard to the

Award passed by learned sole Arbitrator on 03.05.2012 and dismissal

of an application vide AOP No.1663 of 2012 filed by the petitioners

under Section 34 of the Act, 1996 by learned XIV Additional Chief

Judge, on 11.06.2024. It is also not in dispute that the petitioners have

preferred an appeal vide CMA No.611 of 2024 under Section 35 of the

Act and it is pending. There is no stay in the said appeal.

11

AIR 1964 AP 101
17

17. Perusal of the original record in E.P.No.47 of 2026 would

reveal that the 1st respondent i.e. M/s AB Holding Company, a

partnership firm, represented by its Managing Partner and Chief

Executive Mr. Atul P Desai, has filed the said EP under Rule 141 (2)

of Civil Rules of Practice read with Order 21 Rule 11 of CPC, against

the petitioners and 2nd/3rd respondent in respective Revisions i.e.

N.P.Shashikala seeking the following reliefs:-

“a) Issue warrant under Order XXI, Rule 35 of Civil Procedure Code,
1908, directing the bailiff to receive the vacant physical possession of
the “A” and “B” schedule properties from the J.Drs. and hand over the
vacant physical possession to the D.Hr.

b) To execute a General Power of Attorney on behalf of the J.Drs. in
favour of D.Hr. in respect of both the Development Agreements – cum
General power of Attorney bearing Document Nos. 1865 and 1866 of
2004 both dated 30.06.2004, and pass such and other orders as this
Hon’ble court may deem fit and proper in the circumstances of the
case.”

18. As discussed supra, respondent No.1/D.Hr. has filed the said

EP on 07.01.2026 vide E.P.(SR) No.109 of 2026 and learned

Executing Court returned the said EP on 20.01.2026 with the

following objection:-

18

1. Original GPA to be filed

2. C.C. of Arbitration Award to be filed.

3. Claiming schedule-A and B property not mentioned in
Arbitrator Award.

4. Against whom to be executed not mentioned in E.P.
Hence, returned.

Time (7) days.”

19. The said seven days time granted to the 1st respondent /

D.Hr. was expired on 27.01.2026. Even then, 1st respondent has re-

submitted the bundle on 28.01.2026 vide SR No.580 of 2026 without

compliance of the aforesaid objections taken by the Executing Court

on 20.01.2026. The said bundle was again returned on 31.01.2026

with the following objection:-

“Previous objections not complied. Hence, returned. Time (7)
days.”

20. 1st respondent has re-submitted the bundle on 02.02.2026

vide Re.SR No.724 of 2026 with the following explanation:-

1) Original Board of Resolution is filed.

2) Original Award not called for by Court.

3) Statement of claim is filed.

4) Corrections made and endorsed Counsel sign.
19

All objections are complied herewith. Hence, re-submitted.

“Call for Bench”

21. On 04.02.2026, Office of the learned Executing Court put

up the following Note:-

“This E.P. is filed by the decree-holder prays to direct the
bailiff of the court to delivery of possession of the Execution
petition schedule property against JDR No.1 to 4 U/O.XXI
Rules 35 R/W 151 of CPC and handover the same to the decree
holder by putting the decree holder into vacant and physical
possession of the EP schedule property be delivered to the DHR.

1. JDRs preferred ARB O.P.No.1663/2012 on the file of the XIV
ACJ, CCC, Hyderabad. Dismissed vide order Dated 11/06/2024.

2. C.M.A.No.611/2024 on the file of the Hon’ble High Court of
Judicature for the state of Telangana, Hyderabad.

3. Petition filed u/s 151 of cpc, seeking to dispense with filing of
CC of ARB Award in A.A.No.22 of 2011 dated 03.05.2012.

4. No interim orders are granted, appeal is pending adjudication.

5. No appeal is preferred by the aggrieved party.

6. No appeal is preferred by the aggrieved party.

7. No stay as per the Affidavit filed by D.Hr.

8. This E.P. is filed within two years.

CMO
Sd/
04/02/2026

22. Learned Executing Court passed the following Order:-

“Register. Issue warrant under Order -XXI R.35 CPC to
JDR No.1 to 4 through court and RPAD. Call on 24.02.2026.”

“I/warrant
13/2”

20

23. Perusal of the original record in the said E.P. would also

reveal that the learned Executing Court did not mention the date of the

aforesaid order. The Chief Ministerial Officer of the Executing Court

put up note on 04.02.2026, but learned Executing Court did not

mention the date of the aforesaid order.

24. Learned Executing Court did not mention any reasons as to

whether the aforesaid objections raised were complied with by the 1st

respondent or not and as to whether the explanation offered by the 1st

respondent/D.Hr. on 02.02.2026 is satisfied by the Executing Court or

not. Therefore, the aforesaid order dated 09.02.2026 is without

assigning reasons and therefore, it is erroneous. On the said ground

itself it is liable to be set aside.

25. Even in the warrant to the Bailiff to give possession of land

etc., in Form No.11 issued under Order XXI Rule 35 of CPC, the date

is mentioned as 13.02.2026 and the date of the aforesaid order is not

mentioned.

21

26. Perusal of the original record in the said E.P. would also

reveal that there is endorsement with black ink i.e. i/warrant,13/2″.

27. On 24.02.2026, learned Executing Court passed the

following order:-

“Warrant retd. as unexecuted. EA–/2026 u/s-151 CPC is
filed and is pending. Call on 27.02.2026.

Sd/-

28. On 27.02.2026, learned Executing Court passed the

following order:-

“E.A.No.24/26 is allowed. For bailiff report – 18/3.
Sd/-

I/warrant
28/2.

18/03/2026.

CA 4605/26

1) E.P.pet.& vakalat-17,

2) EA24/26 Pet.u/s.151-4,

3) Pet.EASR 113/26-5, Kept in bundle

4) No stay affidavit-2 Sd/-

5) Warrant Report-1
22

29. On 18.03.2026, learned Executing Court passed the

following order:-

“Mr. M/s Syed Ahmed Ali, filed petition u/o-XXI R-26 r/w
Sec-151 of CPC, along with list of documents. JDR.1 to 4
filed memo stating that status quo is passed by Hon’ble
High Court in CRP. Call on 16.04.2026.”

30. Perusal of the record would also reveal that respondent

Nos.1 and 2 in CRP No.783 of 2026 filed E.A.No.12 of 2026 on

07.01.2026 vide EASR No.112 of 2026 under Rule 32 of Civil Rules

of Practice, seeking permission to the deponent of the said application

i.e. Atul P Desai, to represent and proceed in all proceedings before

the Court on behalf of the petitioner No.2 i.e. M/s AB Holding

Company.

31. It was also returned and resubmitted on 28.01.2026 vide

SRNo.582 of 2026. It was again re-submitted on 02.02.2026 vide SR

No.726 of 2026.

32. Perusal of the docket of the said application in E.A.No.12 of

2026 would reveal that learned Executing Court passed the order
23

holding “Heard. Petition is allowed.” But there is no date mentioned

in the said order. Even in the docket of E.P., there is no date on which

the learned Executing Court allowed the said application.

33. In fact, Sri Atul P Desai is claiming that he is the Managing

Partner and Chief Executive of M/s AB Holding Company. Even

before the learned Arbitrator and in the petition filed under Section 34

of the Act, he only represented the said firm. Even then, he has filed

the aforesaid application under Rule 32 of Civil Rules of Practice

seeking permission to represent M/s AB Holidng company. Without

giving any reasons, learned Executing Court allowed the said

application observing “Heard. Petition is allowed.”

34. Perusal of record would also reveal that the learned counsel

for the petitioners/J.Drs. has filed a memo vide SR No.2126 of 2026

dated 18.03.2026 in the present revisions by duly serving a copy on

the learned counsel appearing for 1st respondent/D.Hr. stating that he

has filed copy applications vide C.A.Nos.4767 of 2026, 4868 of 2026

and 5296 of 2026 seeking certified copies of the docket order dated

07.02.1996, 08.02.2026, till date, said Copy Applications have not
24

been complied with by the concerned section. It is also further stated

that this Court called for original records in E.P.No.47 of 2026.

35. Perusal of the record would also reveal that 1st respondent

has filed another application in the said E.P. on 07.01.2026 vide SR

No.113 of 2026 u/sec. 151 of CPC to dispense with filing of certified

copy of Arbitral Award in A.A.No.23 of 2011 dated 03.05.2012. The

same was re-submitted vide SR No.584 of 2026 dated 28.01.2026 and

again re-submitted on 02.02.2026 vide SR No.728 of 2026. There is

no mention of the objection on which it was returned and the

explanation offered by the 1st respondent/D.Hr. while resubmitting the

said E.A. However, learned Executing Court passed the order holding

“Heard. Petition is allowed.” There is no date mentioned in the said

order.

36. It is apt to note that learned Executing Court did not give

any number to the said EA.

37. In the affidavit filed in support of the said application, there

is mention about filing of application seeking certified copy of the
25

Award and return of the same with an endorsement that “the award

available in the file is true copy and true copy cannot be applied in

CA.” There is also mention with regard to demise of learned sole

arbitrator. Even then, without giving any reasons, learned Executing

Court passed the aforesaid order, i.e. “Heard. Petition is allowed.”

38. As discussed supra, learned Executing Court returned the

aforesaid E.P. with a direction to re-submit the bundle within seven

days. The seven days period was expired on 27.01.2026. However,

learned counsel for the 1st respondent/D.Hr. re-submitted bundle on

28.02.2026 vide SR No.580 of 2026 without complying with the

aforesaid objections raised by the Executing Court and without filing

an application seeking extension of time granted to re-submit the

bundle. .

39. Even then, learned Executing Court entertained the said E.P.

which was re-submitted beyond the seven days time granted to 1st

respondent. Even on 28.01.2026, 1st respondent did not comply with

the aforesaid objections raised by the Executing Court. Therefore, the
26

said E.P. was returned on 31.01.2026 holding that the previous

objections are not complied with. Hence, returned.

40. Ultimately, the 1st respondent has re-submitted the bundle

on 02.02.2026 with the foresaid explanation. Even then, learned

Executing Court did not give any reasons as to compliance of the

aforesaid objections by it and also satisfaction of the aforesaid

explanation offered by the 1st respondent/D.Hr. learned Executing

Court simply passed the order holding register and issue warrant

under Order 21 Rule 35 of CPC, to J.Drs Nos.1 to 4 through Court

and RPAD and call on 24.02.2026.

41. Perusal of the record would also reveal that Mr. Atul P

Desai filed E.A.No.24 of 2026 in E.P.No.47 of 2026 seeking a

direction to Bailiff to break open the lock of the schedule property and

deliver vacant and actual possession of the schedule property by

putting D.Hr. in possession thereof.

42. As discussed supra, M/s AB Holding Company is the D.Hr.

Mr. Atul P Desai has filed an application vie E.A.No.12 of 2026 along
27

with E.P.No.47 of 2016 seeking permission of the Court to represent

M/s AB Holding Company, the same was allowed. Therefore, M/s AB

Holding Company represented by its Managing Partner & Chief

Executive Mr. Atul P Desai has to file the aforesaid application

E.A.No.24 of 2026 seeking a direction to bailiff to break open the

lock. Without considering the said aspect, vide order dated

27.02.2026, learned Executing Court allowed the said application

directing the Bailiff to break open the lock and deliver possession of

the schedule – A and B properties, if necessary, to remove any

obstruction, if any, in accordance with law and deliver vacant and

actual physical possession of the schedule-A and B properties to the

1st respondent/D.Hr.. if remind by take up by police aid, for execution

of the warrant, the Bailiff is directed to prepare a detailed

panchanamas at the time of execution and submit a compliance report

to the Court by 18.03.2026.

43. Perusal of the said order would reveal that there are

corrections. There is no initial of the officer of the learned Executing

Court. As rightly contended by the learned counsel for the petitioner,
28

1st respondent has not sought any police aid in E.A.No.24 of 2026 in

E.P.No.47 of 2026.

44. As discussed supra, there are corrections in the docket order

dated 27.02.2026 in E.A.No.24 of 2026. In the certified copy of the

said order, learned executing Court observed that “if remind by take

up by police aid, for effective execution of the warrant, the Bailiff is

directed to prepare a detailed panchanama at the time of execution and

submit a compliance report to the Court. Call on 18.03.2026.

45. The aforesaid part of order does not make sense. In fact, in

the corrected portion of the said order, it is mentioned as ‘if required’,

but in the certified copy of the order, it is mentioned as ‘remind’.

Thus, learned Executing Court passed the orders dated 07.02.2026 and

27.02.2026 in a hurried manner, without considering the aforesaid

aspects, provisions and law laid down by the Apex Court and various

High Courts.

46. As discussed supra, Rule 240 Civil Rules of Practice,

certified copy of the decree to be filed. It says that the Judgment
29

creditor shall, together with the first petition for execution or

transmission of a decree, file in court a certified copy of the decree

sought to be executed, and shall not be required, upon any subsequent

application, to file a further copy or the same decree, unless the copy

already filed has been sent to another court, under Order XXXI Rule 6

of the Code, and has not been returned and application is made to the

court which passed the decree for simultaneous execution. Thus, the

word ‘shall’ is used. Therefore, D.Hr. has to file certified copy of the

decree (award in the present case) necessarily along with the EP. In

the present case, 1st respondent/DHr. has not filed certified copy of the

Award.

47. It is apt to note that 1st respondent has filed an Execution

Application along with the E.P. under Section 151 of CPC to dispense

with filing of certified copy of the said Award contending that the sole

arbitrator who passed the Award is no more. They have filed a Copy

Application before the learned XIV Additional Chief Judge, City Civil

Court, Hyderabad seeking certified copy of the said Award. The same

was returned with an endorsement that certified copy is not available
30

and certified copy of the Award cannot be furnished. Even then,

learned Executing Court without giving any reason, allowed the said

application holding ‘Heard. Petition is allowed.” Thus, it is not a

reasoned order. Any order passed without reasons is an order passed

without application of mind and the same is non-est. Thus, the learned

Executing Court committed procedural irregularity.

48. As discussed supra, Mr. Atul P Desai, has filed an

application under Rule 32 of Civil Rules of Practice vide E.A.No.12

of 2026 seeking permission of the Court to represent M/s AB Holding

Company/D.Hr.

49. As discussed supra, it is M/s AB Holding Company

represented by its Managing Partner and Chief Executive Mr. Atul P

Desai, who filed the aforesaid Arbitration Application, he only

represented the said firm in a petition filed under Section 34 of the

Act, 1996 vide Arb.O.P.No.1663 of 2012. Even then, he has filed the

aforesaid application. Without considering the said aspects, learned

Executing Court allowed the said application holding ‘Heard. Petition

is allowed”. Even the said order is also not a reasoned order and no
31

reasons were assigned. Any order passed without assigning reasons is

an order without application of mind and it is non-est.

50. It is also apt to note that in both the aforesaid orders, there

is no date.

51. As discussed supra, the application filed by the petitioners

under Section 34 of the Act, vide AOP No.1663 of 2012 challenging

the Award dated 03.05.2012 in A.A.No.22 of 2011 was dismissed on

11.06.2024. However, 1st respondent /D.Hr. has filed the E.P. only on

07.01.2026. The same was returned along with the aforesaid

objections on 20.06.2026, the same was re-submitted on 28.06.2026

again the same was returned on 30.06.2026 on the ground that the 1st

respondent did not comply with the objections raised by the Executing

the Court. The same was re-submitted on 02.02.2026

52. Perusal of the record would also reveal that the 1st

respondent mentioned about preferring of an appeal by the petitioners

under Section 37 of CPC vide CMA No.611 of 2024, pendency of the

same and that there is no stay in the said CMA.

32

53. Thus, the 1st respondent filed the aforesaid E.P. almost after

one year six and half months from the date of dismissal of the Arb.OP.

No.1663 of 2012. The said E.P. was returned thrice without passing

any orders on satisfying with the explanation offered by 1st

respondent and also with regard to compliance of the objections raised

and learned Executing Court passed an order “Register E.P. and Issue

warrant”. There is no date mentioned in the said order. No reasons

were assigned.

54. Order XXI Rule 22 of CPC deals with notice to show cause

against execution in certain cases. The same is relevant and extracted

below:-

(1) Where an application for execution is made-

(a) more than two years after the date of the decree, or

(b) against the legal representative of a party to the decree or where an
application is made for execution of a decree filed under the
provisions of section 44A, or

(c) against the assignee or receiver in insolvency, where the party to
the decree has been adjudged to be an insolvent, the Court executing
the decree shall issue a notice to the person against whom execution is
applied for requiring him to show cause, on a date to be fixed, why the
decree should not be executed against him:

Provided that no such notice shall be necessary in consequence of
33

more than two years having elapsed between the date of the decree
and the application for execution if the application is made within two
years from the date of the last order against the party against whom
execution is applied for, made on any previous application for
execution, or in consequence of the application being made against
the legal representative of the judgment-debtor if upon a previous
application for execution against the same person the Court has
ordered execution to issue against him.

(2) Nothing in the foregoing sub-rule shall be deemed to preclude the
Court from issuing any process in execution of a decree without
issuing the notice thereby prescribed, if, for reasons to be recorded, it
considers that the issue of such notice would cause unreasonable delay
or would defeat the ends of justice.

55. There is no dispute that the Executing Court can issue

warrant without issuing notice to J.Drs. if the E.P. is filed within two

years from the date of dismissal of the aforesaid application filed by

the petitioners under Section 34 of the Act, 1996. At the same time,

the Executing Court has to assign reasons for issuing warrant

dispensing with the notice to the petitioners/J.Drs. The said principle

was also laid down by the High Court of Madhya Pradesh at Jabalpur

in Dr. Subhash Chandra Jain and the relevant paragraphs are

extracted below:-

24. In view of the aforesaid discussion and as has been observed in
foregoing paragraph 15, if an execution application is filed within a
period of two years from the date of judgment and decree, notice to
the judgment debtor is not necessary, but the period of two years shall
34

start from the date of final order/judgment/decree. Meaning thereby, if
an appeal is preferred against a judgment and decree sought to be
executed, the requisite period of two years under Order XXI Rule 22
of C.P.C
. has to be computed from the date of decision of the said
appeal, which may be First Appeal, Second Appeal or the appeal filed
before Hon’ble Supreme Court.

25. Although Order XXI Rule 22 of CPC provides that no notice is
necessary if the execution petition is filed within two years from the
date of final order but an exception must be carved out in certain cases
of decrees for possession/eviction. It is a settled principle of law that
the decree-holder should not be deprived of the fruits of the decree.

However, if the execution is carried out with undue haste, or if there is
element of fraud, collusion, or procedural irregularity, and the
judgment debtor is dispossessed even before the appeal period lapses,
it may result in grave injustice. Particularly where the possession of a
house, shop, or land is taken away, which directly affects residence or
livelihood, the judgment debtor must be given a fair opportunity to
approach the appellate Court.

56. In the present case, the Executing Court did not assign any

reasons while issuing warrant under Order XXI Rule 35 of CPC,

which is relevant and extracted below:-

Order 21 Rule 35 of Code of Civil Procedure 1908 –
Decree for immovable property:

(1) Where a decree is for the delivery of any immovable property,
possession thereof shall be delivered to the party to whom it has been
35

adjudged, or to such person as he may appoint to receive delivery on
his behalf, and, if necessary, by removing any person bound by the
decree who refuses to vacate the property.

(2) Where a decree is for the joint possession of immovable property,
such possession shall be delivered by affixing a copy of the warrant in
some conspicuous place on the property and proclaiming by beat of
drum, or other customary mode, at some convenient place, the
substance of the decree.

(3) Where possession of any building on enclosure is to be delivered
and the person in possession, being bound by the decree, does not
afford free access, the Court, through its officers, may, after giving
reasonable warning and facility to any woman not appearing in public
according to the customs of the country to withdraw, remove or open
any lock or bolt or break open any door or do any other act necessary
for putting the decree-holder in possession.

57. In the present case, the Executing Court did not follow the

aforesaid procedure while passing an order dated 09.02.2026 and

27.02.2026. Thus, the Executing Court committed procedural

irregularity.

58. It is also apt to note that the sole arbitrator has passed an

Award dated 03.05.2012 in A.A.No.22 of 2011. The relevant part of

the said order is extracted below:-

i) The claimant has not committed breach of any of the terms of
Ex.C.-7 and C-8 development agreements dated 30-6-2004 and it
cannot be said that the said agreements stood cancelled and have
become unenforceable due to efflux of time or on account of any
36

alleged failure on his part in complying with the terms and conditions
specified there in. The said two development agreements are still
valid, legal, subsisting and enforceable and binding on the
respondents, who are the Legal Representatives of the deceased
Sri.N.Pitamber Naidu, and the claimant is entitled to develop the “A”

and “B” schedule properties as per the terms of the said agreements as
and when the obstacles created by the interim injunction orders passed
by the High Court in CCCAMP.No.11607/2004 are removed, and
when there is no legal bar for him to take necessary steps to proceed
with the development activity as per the terms of the two agreements;

ii) The respondents will be liable to execute fresh General Power of
Attorneys in favour of the claimant in case such fresh General Power
of Attorneys are required, apart from the General Power of Attorneys
contained in Exs.C-7 and C-8 to enable the claimant to perform the
various activities enumerated in Sub-Clause 1 to 24 of Clause 36 in
Ex.C-7 and similar Clauses contained in Ex.C-8 agreements;

59. It is apt to note that Smt. N.Dhanalaxmi, sister of Sri

Pitambar Naidu, husband and father of the petitioners herein

respectively, has filed a suit in O.S.No.152 of 1995 seeking share in

schedule – A and B properties. The said suit was dismissed on

10.04.2004. Thereafter, the said Sri Pitambar Naidu has entered into

the aforesaid two registered development agreements – cum – GPAs

both dated 30.06.2004 with D.Hr. Thereafter, the said Smt.
37

N.Dhanalaxmi, preferred an appeal CCCA No.206 of 2004

challenging the judgment and decree dated 10.02.2004 in O.S.No.152

of 1995. She has filed interlocutory applications vide CCCA MP

Nos.11607 and 11638 of 2004 and vide orders both dated 1308.2004,

this Court granted interim injunction and interim stay of the said

judgment and decree. The said interim stay was vacated and the said

appeal was dismissed as withdrawn on 19.07.2017.

60. Referring to the same, it is the specific contention of the

learned counsel for the petitioners that the Execution Petition filed by

1st respondent is beyond the scope of the aforesaid Award dated

03.05.2012.

61. Whereas, it is the contention of the 1st respondent that the

aforesaid E.P. is well within the ambit of the aforesaid award.

However, the Executing Court has to consider the said aspect.

62. As discussed supra, the 1st respondent has also filed an

affidavit stating that the petitioners have already preferred an appeal

under Section 37 of the Act vide CMA No.611 of 2024 and the same
38

is pending. There is no interim order in it. Without considering the

said aspects, the learned Executing Court passed the orders dated

09.02.2026 and 27.02.2026 in hurried manner and in gross violation

of the aforesaid procedure.

63. It is also the specific contention of the learned counsel for

the petitioners that the E.P. is barred by limitation. The Executing

Court has to consider the said aspect. The same were not considered

by the learned Executing Court while passing the aforesaid orders.

64. During the course of hearing, it is brought to the notice of

this Court that two Bailiffs went to the subject property for execution

of the warrant. In proof of the same, learned counsel for the

petitioners filed photographs. Perusal of the same would reveal that

the learned Executing Court has directed bailiff to execute warrant

and along with him Mr. B.V.Reddy, another bailiff, is also present.

The said fact is not disputed by the learned counsel appearing for

respondents Nos.1 and 2.

39

65. It is apt to note that learned counsel for the petitioners

specifically contended that the E.P. filed in learned XIV Additional

Chief Judge, City Civil Court, Hyderabad straightaway is not

maintainable. In support of his contention, he has placed reliance on

the principle laid down in Potlabathuni Srikanth (supra), a Full

Bench of High Court of Bombay in Fountain Head Developers

(supra), Cheran Properties Limited (supra), Sundaram Finance

Limited (supra), M/s Nkg Infrastructure Limited (supra) of High

Court of Uttarakhand at Nainital. Learned counsel for the petitioners

would contend that 1st respondent/D.Hr. sought to execute the Award

passed by learned sole arbitrator and not the order passed by learned

XIV Additional chief Judge, City Civil Court, Hyderabad in a petition

filed under Section 34 of the Act, 1996, and therefore, E.P. filed by 1st

respondent straightaway in XIV Additional Chief Judge Court is not

maintainable. There is force in the said contention of learned counsel

for the petitioners. However, learned XIV Additional Chief Judge,

passed the aforesaid orders dated 09.02.2026 and 27.02.2026 without
40

issuing notice to the petitioners and without affording them an

opportunity.

66. Sri R.Sushanth Reddy, learned counsel for 1st

respondent/D.Hr. would contend that the petitioners have not raised

the said ground at an earliest point of time and therefore, they cannot

take the said plea in the present revisions. He has also placed reliance

on the principle laid down by the Apex court in Pathuma vs.

Kuntalan Kutty 12 and Heralal Patni vs. Sri Kalinath13. He would

further submit that the objections taken by the petitioners are too

technical and should not be entertained. He also placed reliance on

the principle laid down by the Apex Court in Kiran Singh and others

vs. Cheman Pashwan 14.

67. Sri R.Sushanth Reddy, learned counsel appearing for 1st

respondent/D.Hr. would further contend that EP filed by 1st

respondent is within the limitation and he also placed reliance on the

12
(1981) 3 SCC 589
13
AIR 1962 SC 199
14
(1954) 1 SCC 710
41

principle laid down by Delhi High Court in Growth Techno Projects

Limited vs. Eshwar Industries Limited 15

68. As discussed supra, learned XIV Additional Chief Judge,

passed orders dated 09.02.2026 and 27.02.2026 without putting the

petitioners on notice and affording them an opportunity. Therefore, it

is for the petitioners and 1st respondent to raise all the aforesaid

grounds/contentions before the learned XIV Additional Chief Judge,

City Civil Court, Hyderabad, and it is for the said Court to consider

the same.

69. In the light of the aforesaid discussion, these revisions are

disposed of:-

i. The impugned orders dated 09.02.2026 and consequential order

dated 27.02.2026 passed in E.P.No.47 of 2026 in A.A.No.22 of

2011 by the learned XIV Additional Chief Judge, City Civil

Court, Hyderabad, are hereby set aside.

ii. Learned Executing Court shall decide the aforesaid E.P. No. 47

of 2026 strictly in accordance with law after hearing both the
15
(2024) SCC OnLine Delhi 4510
42

parties. Both the parties are at liberty to raise all the grounds /

contentions which they have raised in the present CRPs before

the learned Executing Court in E.P.No.47 of 2026 and learned

Executing Court shall consider the same.

iii. Learned Executing Court shall consider the contentions of the

petitioners that 1st respondent/D.Hr. cannot file the Execution

Petition straightaway in XIV Additional Chief Judge, City Civil

Court, Hyderabad and decide the same by considering the

principle laid down in the aforesaid judgments.

iv. In Periyammal (dead through L.Rs.) vs. V.Rajamani 16, the

Apex Court directed Executing Courts to dispose of execution

petitions within six (6) months without fail.

v. In the light of the same, both the petitioners and respondents

shall cooperate with the Executing Court in disposing of the

aforesaid E.P. in accordance with law.

16
2025 INSC 329
43

vi. Till disposal of the said E.P., both the petitioners and

respondents shall maintain status quo ante with regard to the

subject property in all respects.

vii. Learned Executing Court shall consider the aforesaid aspects

while deciding the Execution Petition.

viii. Registry shall transmit the original record to the Executing

Court under proper acknowledgment.

ix. There shall be no order as to costs.

Consequently, miscellaneous petitions, if any, pending in these
revisions shall stand closed.

_________________________
JUSTICE K. LAKSHMAN,

___________________________________
JUSTICE B.R MADHUSUDHAN RAO
Date: 17.04.2026.

vvr



Source link