Advertisement
Advertisement

― Advertisement ―

Internship at the Institute For Alternative Dispute Resolution

About InADR Promote peaceful and efficient resolution of disputes to reduce reliance on litigation, thereby alleviating the burden on judicial systems. While the judiciary’s...
HomeM/S Khodal Corporation vs West Central Railway ... on 7 April, 2026

M/S Khodal Corporation vs West Central Railway … on 7 April, 2026

ADVERTISEMENT

Rajasthan High Court – Jaipur

M/S Khodal Corporation vs West Central Railway … on 7 April, 2026

[2026:RJ-JP:14404]

        HIGH COURT OF JUDICATURE FOR RAJASTHAN
                    BENCH AT JAIPUR

                  S.B. Civil Writ Petition No. 6148/2026

M/s Khodal Corporation, Viramgam, 7, Ramnagar Society, Ioc
Colony Road, Viramgam - 382150 Gujarat, India Through Its
Through Its Power Of Attorney Holder Shri Shubham Hareshbhai
Patel Aged S/o Shri Hareshbhai Patel, Around 26 Years R/o
Viramgam, 7, Ramnagar Society, Ioc Colony Road, Viramgam -
382150 Gujarat
                                                                        ----Petitioner
                                        Versus
1.       West Central Railway, Through Its General Manager, Head
         Quarter Office, Opposite Indira Market, Jabalpur, Madhya
         Pradesh -482001
2.       Chief       Administrative        Officer      (Construction),      Western
         Central Railway, Head Quarter Office, Opposite Indira
         Market, Jabalpur, Madhya Pradesh -482001
3.       Chief Project Manager (Cpm), West Central Railways, Drm
         Office, Kota, Rajasthan - 324002.
4.       Deputy Chief Engineer (Construction-Ii), West Central
         Railways, Drm Office, Kota, Rajasthan - 324002.
                                                                     ----Respondents
For Petitioner(s)             :     Mr. O.P. Singh Tanwar
                                    Ms. Rajeshwari Tanwar
                                    Mr. Adesh Arora
For Respondent(s)             :     Mr. C.S. Sinha with
                                    Ms. Anima Chaturvedi for ASG



                 HON'BLE MR. JUSTICE SAMEER JAIN

                                     Judgment

07/04/2026

1. Learned counsel for the petitioner submitted that the present

petition is filed assailing the illegal and arbitrary termination notice

SPONSORED

dated 25.03.2026. It is submitted that a NIT (Notice Inviting

Tender) was issued on 13.02.2024 by the respondents; resultant

(Uploaded on 13/04/2026 at 12:07:14 PM)
(Downloaded on 14/04/2026 at 08:50:04 PM)
[2026:RJ-JP:14404] (2 of 5) [CW-6148/2026]

to which upon completing due formalities a letter of acceptance

was issued in favor of the petitioner, and as per terms and

conditions of the tender, petitioner furnished the required

Performance Bank Guarantee and also submitted the security

deposit. It is submitted that time was essence of the contract and

completion period of the work was nine months i.e. up to

15.01.2025.

2. It is contended that there was a delay on account of late

handover of the working site, and that these circumstances are

beyond the petitioner’s control, therefore, the petitioner has

sought extension of time vide letter dated on 30.12.2024. It is

further submitted that with Price Variation Clause (PVC), the

respondents themselves acknowledged the delay and essentials

were granted, however in spite of the same being done

respondents issued a seven days’ notice dated 23.01.2026 under

Clause 62 of the GCC, alleging inadequate progress.

3. Further, it is submitted that another seven days’ notice dated

20.02.2026 was issued alleging similar deficiencies, thereafter a

48 hours’ notice dated 28.02.2026 was also issued, threatening

rescission of the contract. It is submitted that the petitioner has

replied the said notice(s) on 28.02.2026, explaining that more

than 85% of the work is already completed, and that delays were

on the part of the respondents. It is submitted that in-between

the said period, the Commissioner of Railway Safety (CRS)

conducted the statutory inspection of the project on 18.03.2026

and the railway line was provisionally authorized on 21.03.2026

for public carriage of passengers at a speed of 75 kmph.

(Uploaded on 13/04/2026 at 12:07:14 PM)
(Downloaded on 14/04/2026 at 08:50:04 PM)
[2026:RJ-JP:14404] (3 of 5) [CW-6148/2026]

4. In this background, learned counsel for the petitioner has

submitted that the conciliation attempt of invocation of bank

guarantee forfeited, qua the risk and cover of petitioner is

unjustified. In support of the contentions made insofar, learned

counsel has relied upon the ratio encapsulated in 2024 SCC

OnLine SC 1682: Subodh Kumar Singh Rathour V. Chief

Executive Officer & Ors., and 2016 (11) SCC 720: Gangotri

Enterprises V. Union of India and submitted that judicial review

is permissible in tender matters, especially qua the issue of bank

guarantee encashment.

5. Per contra, learned counsel for the respondents has

submitted that the assertions made in the writ petition are

factually disputed. It is submitted that time was essence of the

contract, as also affirmed by the learned counsel appearing for the

petitioner, as the matter pertains to Railway department, and

there was a delay on the part of the petitioner. It is further

submitted that as per the terms of the agreement, there is a

remedy before the Dispute Redressal Board i.e. qua conciliation

and thereafter the arbitration clause could be invoked, thence, in a

scenario where there are disputed questions of facts, judicial

review ought not be made and the remedy as under Section 9 of

the Arbitration and Conciliation Act may be adopted.

6. In support of the said submissions, learned counsel has

placed reliance upon the ratio enunciated in D.B. Civil Special

Appeal (Writ) No.1245/2025 title MKC Infrastructure Ltd.

Vs. Union of India and Ors. wherein whilst placing reliance upon

Hon’ble Supreme Court in the case of Tata Motors Ltd. Vs.

Brihan Mumbai Electric Supply and Transport Undertaking

(Uploaded on 13/04/2026 at 12:07:14 PM)
(Downloaded on 14/04/2026 at 08:50:04 PM)
[2026:RJ-JP:14404] (4 of 5) [CW-6148/2026]

(BEST): AIR 2023 SC 2717 and Midnapore Peoples’ Coop.

Bank Ltd. and Ors. Vs. Chunilal Nanda and Ors.: (2006) 5

SCC 399, the Court has opined that no interfere is to be made in

the termination proceedings.

7. Having heard the submissions made by learned counsel

representing the parties, scanning the material available on

record, and perusing the judgments cited at Bar, this Court is not

inclined to interfere in the present writ petition for the following

reasons:

7.1 That disputed questions of facts are involved.

7.2 That there is an alternate available remedy as the

concerned agreement has an ‘arbitration clause’.

7.3 That as per settled position of law, where there are

disputed question of facts, appellate/writ courts should restrain to

interfere. The said view is made unambiguous, yet again, in the

ratio encapsulated in Tata Motors Limited (supra), the relevant

extract from which is reproduced hereinbelow:

“52. Ordinarily, a writ court should refrain itself
from imposing its decision over the decision of the
employer as to whether or not to accept the bid of
a tenderer unless something very gross or palpable
is pointed out. The court ordinarily should not
interfere in matters relating to tender or
contract. To set at naught the entire tender
process at the stage when the contract is well
underway, would not be in public interest.
Initiating a fresh tender process at this stage
may consume lot of time and also loss to the
public exchequer to the tune of crores of
rupees. The financial burden/implications on
the public exchequer that the State may have
to meet with if the Court directs issue of a
fresh tender notice, should be one of the
guiding factors that the Court should keep in
mind. This is evident from a three-Judge Bench

(Uploaded on 13/04/2026 at 12:07:14 PM)
(Downloaded on 14/04/2026 at 08:50:04 PM)
[2026:RJ-JP:14404] (5 of 5) [CW-6148/2026]

decision of this Court in Association of Registration
Plates v. Union of India and Others
, reported in
(2005) 1 SCC 679.”

(Emphasis supplied)

8. Accordingly, and in view of the ratio encapsulated in MKC

Infrastructure Ltd. (supra), the present writ petition is

dismissed. However, it is clarified that if the petitioner is desirous,

to avail the remedy as specified by the respondents, he is free to

choose the same. It is made clear that no prejudice be caused to

the petitioner on account of dismissal of the present writ petition.

(SAMEER JAIN),J

DEEPAK /s-230

(Uploaded on 13/04/2026 at 12:07:14 PM)
(Downloaded on 14/04/2026 at 08:50:04 PM)

Powered by TCPDF (www.tcpdf.org)



Source link