M/S. D.C. Construction vs State Of Chhattisgarh on 9 April, 2026

    0
    35
    ADVERTISEMENT

    Chattisgarh High Court

    M/S. D.C. Construction vs State Of Chhattisgarh on 9 April, 2026

    Author: Ramesh Sinha

    Bench: Ramesh Sinha

                                                               1
    
    
    
    
                                                                          2026:CGHC:16276-DB
    Digitally signed by ALOK
    SHARMA
    Date: 2026.04.20
                                                                                         NAFR
    20:12:54 +0530
    
    
                                    HIGH COURT OF CHHATTISGARH AT BILASPUR
    
                                                   WPC No. 1610 of 2026
    
                          M/s. D.C. Construction Through Partner Shri Hari Shankar Rathore, S/o
                          Dev Charan Rathore, Aged About 50 Years, R/o Parijat Extension Nehru
                          Nagar, Bilaspur, District Bilaspur Chhattisgarh
                                                                               ... Petitioner(s)
    
                                                           versus
    
                          1 - State Of Chhattisgarh Through The Secretary, Public Works
                          Department, Mantralaya, Mahanadi Bhawan, Atal Nagar, Nawa Raipur,
                          District Raipur Chhattisgarh
    
                          2 - Engineer In Chief Public Works Department, Atal Nagar Nawa
                          Raipur, District Raipur Chhattisgarh
    
                          3 - Chief Engineer (Central Tender Cell) Office Of Engineer In Chief P W
                          D Nawa Raipur, District Raipur Chhattisgarh
    
                          4 - Collector District Surajpur Chhattisgarh
    
                          5 - Chief Engineer Public Works Department, Sarguja Range, District
                          Sarguja Ambikapur Chhattisgarh
    
                          6 - Superintendent Engineer Public Works Department, Ambikapur
                          Circle, District Sarguja Ambikapur Chhattisgarh
    
                          7 - Executive Engineer Public Works Department, Surajpur Division,
                          District Surajpur Chhattisgarh
    
                          8 - Sub-Divisional Officer Public Works Department, Sub-Division Prem
                          Nagar, District - Surajpur Chhattisgarh
                                                                              ... Respondent(s)

    2

    For Petitioner(s) : Mr. Abhishek Sinha, Sr. Advocate, along with
    Mr. Achyut Tiwari, Advocate.

    SPONSORED

    For Respondent(s) : Mr. Praveen Das, Additional Advocate
    General.

    Hon’ble Shri Ramesh Sinha, Chief Justice
    Hon’ble Shri Ravindra Kumar Agrawal, Judge

    Order on Board

    Per Ramesh Sinha, Chief Justice

    09/04/2026

    1. The petitioner has filed the present writ petition challenging the

    order dated 11.02.2026 (Annexure-P/1) and order dated

    30.12.2025 (Annexure-P/15) issued by the Respondent No. 7,

    also claiming for restoration of an agreement and quashing of

    fresh NIT issued by the Respondent No. 3, and prayed the

    following relief in the writ petition:-

    “10.1 That, this Hon’ble Court may kindly be pleased
    to call for the entire record from the
    respondents’ authorities pertaining to the case
    of the petitioner.

    10.2 That this Hon’ble Court may kindly be pleased
    to quash/set aside impugned orders dated
    11.02.2026 (Annexure P/1) and order dated
    30.12.2025 (Annexure P/15) issued by
    respondent no. 7, in the interest of justice.

    10.3 That this Hon’ble Court may kindly be pleased
    to quash/set aside impugned notice inviting
    tender (Annexure P/17) issued by respondent
    no. 3 and its subsequent proceedings, in the
    3
    interest of justice.

    10.4 That, this Hon’ble Court may kindly be pleased
    to direct the respondent authorities to restore
    the agreement (Annexure P/8) and work order
    (Annexure P/9) and also to extend the due
    date mentioned therein as this Hon’ble Court
    may deem fit, in the interest of justice.

    10.5 That, this Hon’ble Court may kindly be pleased
    to grant any other relief, as it may deem fit and
    appropriate, in favor of petitioner, in the
    interest of justice.

    2. The subject matter, in brief, is that the petitioner firm is Class- A

    contractor and eligible to participate in tenders for five years from

    the date of issuance of his certificate issued by the Engineer In

    Chief (PWD), C.G. Respondent No. 3 issued an NIT No.

    060/TC/24-25 for strengthening work of Tara- Prem Nagar,

    Ramanuj Nagar- Krishnapur Road, Length – 27 km. District

    Surajpur with the (Work code- W 25918). The petitioner was

    declared as L1, and an agreement was executed between the

    petitioner and the Respondent No. 7, and he was allowed to start

    work there. The work order was also issued on 19.11.2024 for the

    aforesaid work, for the duration of work of 18 months. The total

    cost of work was Rs. 5076.94 lakhs. The petitioner had also

    submitted the bank guarantee of Rs. 2,52,86,983/- issued on

    18.11.2024, and has also submitted the bank guarantee for

    Additional Performance Security Deposit. The petitioner prepared

    another bank guarantee amounting to Rs. 2,53,84,000/- issued on
    4
    12.03.2025 for mobilization advance, however, the said bank

    guarantee was revoked by the petitioner, and afresh bank

    guarantee was prepared by him on 23.09.2025. After issuance of

    work order, the petitioner started the work of strengthening the

    aforesaid road under the terms and conditions of the agreement,

    and raising running bills on regular monthly basis. However, due

    to inaction of the respondent authorities, the running bills were not

    realized within the stipulated time, and the work was adversely

    affected. The subject work falls and goes through the residential

    areas, and the residents of various places started creating

    hindrance because of their nuisance, the progress of work was

    affected, and the petitioner was facing difficulties of smooth

    working for various reasons like nuisance, pipeline and poles

    standing on the roads. He made several representations to the

    authorities concerned for clearance of the aforesaid difficulties,

    also prepared for release of the running bills within the prescribed

    time, but his representation had not been given any heed, and the

    position remained as itself. The respondent No. 7 issued a letter

    on 16.09.2025, to the Axis Bank, Rama Trade Centre Branch,

    issued the bank guarantee to the petitioner, directing the bank to

    verify the bank guarantee of the petitioner.

    3. It is also the case of the petitioner that during the execution of the

    work, an inspection was carried out on 28.11.2025 by the

    respondent authorities at the site, wherein it was found that

    approximately 24% work had been completed. However, the
    5
    authorities have prepared an adverse report against the petitioner,

    and then the Chief Engineer recommended to the Executive

    Engineer for termination of the contract of the petitioner. The said

    recommendation by Chief Engineer violates Clause 28 of the

    agreement, which provides for arbitration mechanism, and the

    same is violated, as the said clause 28 contemplates adjudication

    by the Superintending Engineer, thereafter, an appeal before the

    Chief Engineer. However, in the present case, the Chief Engineer

    himself recommended for termination of the contract and per-

    determined, therefore, no remedy would be available to the

    petitioner in the appeal, if ultimately filed before it.

    4. It is also the case of the petitioner that the petitioner is

    continuously working under the terms and conditions of the

    contract and showing the progress of the work, however, on

    30.12.2025, the respondent No. 7 issued a letter to the petitioner

    terminating the agreement executed between them, alleging

    disproportionate progress in the work. After receiving the

    termination letter, the petitioner replied to the respondent

    authorities on 06.01.2026, intimating them that one of the partners

    of the firm had suffered a severe attack of brain on 02.01.2026,

    and because of which the work is affected, and the progress of

    the work will be taken care of and will be completed within the

    prescribed time limit, and prayed for relaxation and reinstatement

    of the agreement. The respondent No. 7, without considering the

    representation of the petitioner, issued the impugned letter dated
    6
    11.02.2026, alleging that the petitioner left the work incomplete,

    and directing the petitioner to deposit the amount of Rs.

    5,10,05,349.00/- on various heads, and ordered for forfeiting the

    total amount of Rs. 3,09,15,704.00/- including the security

    deposit, Additional Performance Security, and on the same date,

    the respondent No. 3 issued fresh NIT for the same work.

    5. The petitioner had challenged the order dated 11.02.2026 in

    WP(C) No. 1158 of 2026 before this Court, however, the said writ

    petition was dismissed as withdrawn, with liberty to file a fresh

    petition, and then the present petition has been filed by the

    petitioner with additional facts and grounds.

    6. Learned counsel for the petitioner would submit that the petitioner

    was continuously working as best of his eligibility, however,

    because of delay in payment of running bills, some delay in

    progress of work was caused. The respondent authorities,

    neglecting the provisions of the agreement and without affording

    proper opportunity of hearing to the petitioner, and without

    awarding due date for completion of work i.e. 17.03.2026, they

    terminated the agreement and forfeited the security deposit of the

    petitioner, also issued fresh NIT. The order dated 11.02.2026

    passed by the respondent authorities, and issuance of NIT, is

    arbitrary and unreasonable. He would also submit that the

    impugned order is based on the recommendation of the Chief

    Engineer, and the supporting authorities are bound to follow the

    recommendation of the higher authorities, the Executive Engineer,
    7
    i.e. respondent No. 7, exercised its powers under the

    recommendation of the Chief Engineer, which is impermissible in

    law, and they have to exercise their own discretion while taking

    such decision. The termination order dated 30.12.2025 cannot by

    itself constitute the valid basis for termination of the contract

    under Clause 2 or 3 of the said contract. The said clause provide

    the mechanism for dealing with delay or slow progress in

    execution of the work including grant of extension of time either

    with penalty or without penalty, depends upon the facts and

    circumstances of the case. Clause 28 of the agreement

    constitutes arbitration/dispute resolution clause providing a two-

    tier departmental mechanism for adjudication of the dispute

    arising out of the contract. As per the said clause, the disputes are

    first required to be referred to the Superintending Engineer,

    thereafter, an appeal lies to the Chief Engineer. In the present

    case, the Chief Engineer, in the inspection report dated

    28.11.2025, already recorded a finding and recommended that

    since the petitioner was unwilling to complete the contract, his

    contract is liable to be terminated. In such per-determined finding

    by the appellate authority itself, the dispute resolution mechanism

    under Clause 28 stands exhausted, and no efficacious remedy of

    arbitration is available to the petitioner. He would also submit that

    on various occasions, the work of the petitioner was inspected

    and found satisfactory, however, with fraudulent intention to

    provide the work to a favorable person, the contract of the

    petitioner has been terminated, and order of recovery and
    8
    forfeiture of security deposit has been passed. Further, on the

    same day, fresh NIT has been issued for the same work. He

    would further submit that the respondent authorities cannot take

    advantage of their own fault for not releasing the running bills in

    time, which hampered the progress of work. The respondent

    authorities themselves have violated Clause 8 of the agreement,

    which deals with the submission of running bills and its payment.

    The petitioner had submitted the running bills of work done by him

    periodically and within time, however, the said running bills have

    not been released periodically, and huge sum was withheld by the

    respondent authority. The vehicles and machineries of the

    petitioner are on loans, and the offfice and other properties of the

    petitioner have been mortgaged before the bank concerned for

    issuance of bank guarantee, and forfeiture of bank guarantee and

    Additional Performance Security would cause hardship to the

    petitioner. The reasons for delay in completion of the work is also

    that it was the forest area, some portion comes under the

    residential urban area where the lands could not be available and

    also the pipeline and poles are there. In between 20.01.2025 to

    25.01.2025, the work was affected due to panchayat elections,

    therefore, the petitioner requested the respondent authorities for

    extension of time to complete the work, but they have not

    considered his application. Approximately 25% of the work had

    already been completed by the petitioner, and the vehicles and

    machineries are still lying on the project site. He would also

    submit that under Clause 2 or 3 of the contract, the respondent
    9
    authorities are not empowered for forfeiting the security deposit,

    Earnest Money Deposit, and Additional Performance Security

    deposit, therefore, the recovery of Rs. 5,10,05,349/- and forfeiture

    of END and APS is arbitrary, illegal and void, therefore, the

    petition may be allowed, and the impugned order, as well as fresh

    NIT, may be quashed, and the petitioner may be permitted to

    carry out and to complete the work awarded to him under the

    work order dated 19.11.2024.

    7. On the other hand, learned counsel appearing for the respondent-

    state would submit that the chief engineer had submitted the

    inspection report dated 28.11.2025 which was carried out by a

    team headed by executive engineer and other authorities of the

    department. there is no finding of the chief engineer so that it can

    be said that since the chief engineer has already made up his

    mind, the availing of arbitration clause would be of no use. He

    would also submit that a complete mechanism has been provided

    under Clause- 28 of the contract which deals with the arbitration

    clause. He would also referred to Section 7 of The Chhattisgarh

    Madhyastham Adhikaran Adhiniyam, 1983, and submits that

    irrespective of the fact whether the agreement contains an

    arbitration clause or not, refer in writing they dispute to the

    tribunal, therefore, the petitioner is having an efficacious

    alternative remedy to avail the arbitration clause of the

    agreement. He would further submit that considering the progress

    of the work which is much less than the schedule work, the
    10
    authorities have decided to terminate the work order issued in

    favour of the petitioner and ultimately vide order dated

    30.12.2025, the work order has been cancelled and vide order

    dated 11.02.2026, the EMB, SD and APS have been forfeited

    which is strictly in accordance with the law. In the aforesaid

    circumstances, the writ petition filed by the petitioners is liable to

    be dismissed.

    8. We have heard learned counsel for the parties and perused the

    material annexed with the writ petition.

    9. It is undisputed in the case that the petitioner was awarded

    contract for strengthening work of Tara-Premnagar-

    Ramanujnagar-Krishnapur road, length 27 KM, Dist- Surajpur and

    a work order was issued in his favour on 19.11.2024. It is also not

    in dispute that the total cost of Rs. 5076.94 Lakh and the total

    period of work were 18 months. Since the petitioner could not

    carry out the progress of work in its due schedule, the respondent

    authorities had inspected the work site and found less work than

    its schedule and they submitted a report to the chief engineer.

    From the report dated 28.11.2025 (Annexure-P/21), it also

    transpires that the quality of work done by the petitioner is also

    inferior to the standard. And then the authorities have decided not

    to continue with the agreement with the petitioner and ultimately

    terminated the contract on 30.12.2025 and forfeited the security

    deposit and EMD, SD and APS vide its order dated 11.02.2026.

    The recovery order after adjustment of the work done and
    11
    payment received by the petitioner was also issued by the order

    dated 11.02.2026, and the petitioner was held liable for Rs.

    5,10,5349/-.

    10. From the document (Annexure-P/22) annexed with the petitioner,

    which is the explanation submitted by the petitioner, on

    30.05.2025 in reply to the letter dated 22.05.2025 sent by the

    respondent authorities, the petitioner explained various reasons

    that caused hindrance in the smooth progress of work and delay

    in the execution of work under the work order.

    11. Clause 28 of the contract stipulates the arbitration clause which

    reads as under:-

    Arbitration Clause: Clause 28

    Except as otherwise provided in this contract
    all question and dispute relating to the
    meaning of the specification, designs,
    drawings and instruction herein before
    mentioned as to thing whatsoever in any way
    arising out of or relating to the contract
    designs, drawings, specifica estimate,
    concerning the works, or the execution or
    failure to execute the same, whether arising
    during the progress of the work, or a after the
    abandonment there of shall be referred to the
    Superintending Engineer for his decision,
    within a period of 30 (thirty) days of such an
    occurrence (s). There upon the
    Superintending Engineer shall give his written
    instructions and/or decisions, after hearing
    the contractor and Executive Engineer within
    a period of 15 (fifteen) days of such request.
    This period can be extended by mutual
    consent of parties.

    Upon receipt of written instructions or
    decisions, of Superintending Engineer the
    parties shall promptly proceed without delay
    to comply such instructions or decisions. If
    12
    the Superintending Engineer fails to give his
    instruction or decisions in writing within a
    period of 15 (fifteen) day’s or mutually agreed
    time after being requested and/or, if the party
    (es) is/are aggrieved against the decision of
    the Superintending Engineer, the aggrieved
    party may within 30 days prefer an appeal to
    the Chief Engineer, who shall afford an
    opportunity to the parties of being heard and
    to offer evidence in support of his appeal.

    The, Chief Engineer will give his decision
    within 30 (thirty) days, or such, mutually
    agreed period.

    If any party is not satisfied with the
    decision of the Chief Engineer he can file the
    petition for resolving the dispute through
    arbitration in the arbitration tribunal.

    A reference to Arbitration Tribunal shall
    be no ground for not continuing the work on
    the part of the Contractor. Payment as per
    original terms and condition of the agreement
    shall be continued by the Executive Engineer
    in accordance with clause 8 above.”

    12. Further Section 7 of the Chhattisgarh Madhyastham Adhikaran

    Adhiniya, 1983, provided a remedy to reference to tribunal

    irrespective of availability of arbitration clause in the contract.

    Section 7 of the Adhiniyam, 1983 is as under:-

    “7. Reference to Tribunal.-(1) Either party to
    a works contract shall irrespective of the fact
    whether the agreement contains an
    arbitration clause or not, refer in writing the
    dispute to the Tribunal.

    (2) Such reference shall be drawn up in such
    form as may be prescribed and shall be
    supported by an affidavit verifying the
    averments.

    (3) The reference shall be accompanied by
    such fee as may be prescribed.

    [(4) Every reference shall be accompanied by
    such documents or other evidence and by
    such other fees for service or execution of
    processes as may be prescribed.

    13

    (5) On receipt of the reference under sub-

    section (1), if the Tribunal is satisfied that the
    reference is a fit case for adjudication, it may
    admit the reference but where the Tribunal is
    not so satisfied it may summarily reject the
    reference after recording reasons therefor.]”

    13. The Hon’ble Supreme Court in the case of Tata Motors Limited v

    The Brihan Mumbai Electric Supply & Transport Undertaking

    (Best) and Others passed in Civil Appeal No. 3897 of 2023 vide

    judgment dated 19.05.2023 held as follows :

    “48. This Court being the guardian of
    fundamental rights is duty-bound to interfere
    when there is arbitrariness, irrationality, mala
    fides and bias. However, this Court has cautioned
    time and again that courts should exercise a lot
    of restraint while exercising their powers of
    judicial review in contractual or commercial
    matters. This Court is normally loathe to interfere
    in contractual matters unless a clear-cut case of
    arbitrariness or mala fides or bias or irrationality
    is made out. One must remember that today
    many public sector undertakings compete with
    the private industry. The contracts entered into
    between private parties are not subject to
    scrutiny under writ jurisdiction. No doubt, the
    bodies which are State within the meaning of
    Article 12 of the Constitution are bound to act
    fairly and are amenable to the writ jurisdiction of
    superior courts but this discretionary power must
    be exercised with a great deal of restraint and
    caution. The courts must realise their limitations
    and the havoc which needless interference in
    commercial matters can cause. In contracts
    involving technical issues the courts should be
    even more reluctant because most of us in
    Judges’ robes do not have the necessary
    expertise to adjudicate upon technical issues
    beyond our domain. The courts should not use a
    magnifying glass while scanning the tenders and
    make every small mistake appear like a big
    lunder. In fact, the courts must give “fair play in
    14
    the joints” to the government and public sector
    undertakings in matters of contract. Courts must
    also not interfere where such interference will
    cause unnecessary loss to the public exchequer.
    (See: Silppi Constructions Contractors v. Union of
    India
    , (2020) 16 SCC 489).

    52. Ordinarily, a writ court should refrain itself
    from imposing its decision over the decision of
    the employer as to whether or not to accept the
    bid of a tenderer unless something very gross or
    palpable is pointed out. The court ordinarily
    should not interfere in matters relating to tender
    or contract. To set at naught the entire tender
    process at the stage when the contract is well
    underway, would not be in public interest.

    Initiating a fresh tender process at this stage may
    consume lot of time and also loss to the public
    exchequer to the tune of crores of rupees. The
    financial burden/implications on the public
    exchequer that the State may have to meet with if
    the Court directs issue of a fresh tender notice,
    should be one of the guiding factors that the
    Court should keep in mind. This is evident from a
    three-Judge Bench decision of this Court in
    Association of Registration Plates v. Union of
    India and Others
    , reported in (2005) 1 SCC 679.

    53. The law relating to award of contract by the
    State and public sector corporations was
    reviewed in Air India Ltd. v. Cochin International
    Airport Ltd.
    , reported in (2000) 2 SCC 617 and it
    was held that the award of a contract, whether by
    a private party or by a State, is essentially a
    commercial transaction. It can choose its own
    method to arrive at a decision and it is free to
    grant any relaxation for bona fide reasons, if the
    tender conditions permit such a relaxation. It was
    further held that the State, its corporations,
    instrumentalities and agencies have the public
    duty to be fair to all concerned. Even when some
    defect is found in the decision-making process,
    the court must exercise its discretionary powers
    under Article 226 with great caution and should
    exercise it only in furtherance of public interest
    15
    and not merely on the making out of a legal point.
    The court should always keep the larger public
    interest in mind in order to decide whether its
    intervention is called for or not. Only when it
    comes to a conclusion that overwhelming public
    interest requires interference, the court should
    interfere.

    54. As observed by this Court in Jagdish Mandal
    v. State of Orissa and Others
    , reported in (2007)

    14 SCC 517, that while invoking power of judicial
    review in matters as to tenders or award of
    contracts, certain special features should be
    borne in mind that evaluations of tenders and
    awarding of contracts are essentially commercial
    functions and principles of equity and natural
    justice stay at a distance in such matters. If the
    decision relating to award of contract is bona fide
    and is in public interest, courts will not interfere
    by exercising powers of judicial review even if a
    procedural aberration or error in assessment or
    prejudice to a tenderer, is made out. Power of
    judicial review will not be invoked to protect
    private interest at the cost of public interest, or to
    decide contractual disputes.”

    14. It is trite law that judicial review in contractual matters is confined

    to examining the decision-making process and not the merits of

    the decision itself. The Court does not sit as an appellate authority

    over administrative decisions relating to contracts. In Tata Cellular

    v. Union of India,(1994) 6 SCC 651, the Hon’ble Supreme Court

    laid down that judicial review is concerned with reviewing not the

    merits of the decision but the decision-making process, and

    interference is warranted only when the action of the State is

    arbitrary, unreasonable, or violative of Article 14. In the present

    case, the material on record indicates that the respondent

    authorities conducted inspection, assessed the progress and
    16
    quality of work, and thereafter took a decision to terminate the

    contract. Whether the progress was adequate or whether the

    petitioner had valid justifications are essentially factual issues,

    which are not amenable to adjudication in writ jurisdiction. Hence,

    this Court is not inclined to re-appreciate such factual

    determinations.

    15. The petitioner has contended that the recommendation made by

    the Chief Engineer amounts to pre-determination, thereby

    rendering the remedy under Clause 28 illusory. However, on

    perusal of the inspection report dated 28.11.2025, it appears that

    the said report is based on factual assessment of the work

    executed and does not conclusively adjudicate the rights of the

    parties. Mere recommendation by a superior authority, based on

    inspection, cannot be equated with final adjudication so as to

    vitiate the contractual dispute resolution mechanism. In the

    present matter, the petitioner was issued notices and had

    submitted explanations, which have been considered by the

    authorities. Therefore, it cannot be said that there has been a

    complete denial of opportunity or violation of natural justice

    warranting interference under Article 226.

    16. With regard to the challenge to the termination order dated

    30.12.2025 and the consequential order dated 11.02.2026, this

    Court finds that the respondent authorities have exercised their

    contractual powers on the basis of alleged slow progress and

    inferior quality of work. The terms of the contract empower the

    employer to terminate the contract and forfeit security deposits in
    17
    the event of default. The petitioner’s contention regarding delay in

    payment of running bills and site hindrances gives rise to disputed

    questions of fact, which would require evidence and cannot be

    adjudicated in writ proceedings. In ABL International Ltd. v. Export

    Credit Guarantee Corporation of India Ltd., (2004) 3 SCC 553, it

    has been held that although writ jurisdiction may be invoked in

    contractual matters, the same is confined to cases where the

    action of the State is arbitrary or unreasonable on the face of the

    record. In the present case, the decision to issue a fresh Notice

    Inviting Tender (NIT) after termination of the contract appears to

    be a consequential administrative step to ensure completion of

    public work and cannot, prima facie, be termed arbitrary.

    17. Accordingly, no case for interference is made out. The writ petition

    is, therefore, dismissed, with liberty to the petitioner to avail

    appropriate remedies before the competent forum, in accordance

    with law.

                       Sd/-                                         Sd/-
    
           (Ravindra Kumar Agrawal)                        (Ramesh Sinha)
                    Judge                                   Chief Justice
    
    
    Alok
     



    Source link

    LEAVE A REPLY

    Please enter your comment!
    Please enter your name here