Jai Narayan Vyas University vs M/S Sawai Engineers … on 16 April, 2026

    0
    33
    ADVERTISEMENT

    Rajasthan High Court – Jodhpur

    Jai Narayan Vyas University vs M/S Sawai Engineers … on 16 April, 2026

    [2026:RJ-JD:17649-DB]
    
    
    
          HIGH COURT OF JUDICATURE FOR RAJASTHAN AT
                           JODHPUR
                D.B. Civil Miscellaneous Appeal No. 412/2025
    
    1.          Jai Narayan Vyas University, Through Its Registrar,
                Jodhpur.
    2.          Chief   Engineer         (Building       Cell),     Jai   Narayan   Vyas
                University, Jodhpur.
                                                                           ----Appellants
                                           Versus
    M/s Sawai Engineers, Through Its Proprietor, Sawai Ram Jangid,
    S/o Lt Bhoora Ram Jangid, Age About 67 Years, R/o 202,
    Mahadeo Temple, Vaishnav Nagar, 1St, OppB.r.Bidla School,
    Jodhpur.
                                                                          ----Respondent
    
    
     For Appellant(s)              :    Ms. Adwaita Sharma
     For Respondent(s)             :    Mr. Himanshu Maheshwari
                                        Mr. Bharat Maheshwari
    
    
                  HON'BLE MR. JUSTICE ARUN MONGA

    HON’BLE MR. JUSTICE SUNIL BENIWAL

    Order

    SPONSORED

    Reportable
    16/04/2026

    Per: Arun Monga, J.

    1. Assailed herein is a judgment and order dated 06.11.2024

    passed by the Commercial Court, Jodhpur Metropolitan, whereby

    the petition filed by the appellants under Section 34 of the

    Arbitration and Conciliation Act, 1996 (hereinafter, “1996 Act”)

    was dismissed, and the Arbitral Award dated 31.12.2021 was

    upheld.

    2. The dispute originates from a work order dated 22.09.2008

    between the parties for construction of a Guest House of Academic

    (Uploaded on 21/04/2026 at 01:00:49 PM)
    (Downloaded on 21/04/2026 at 08:38:19 PM)
    [2026:RJ-JD:17649-DB] (2 of 11) [CMA-412/2025]

    Staff for a total work order of Rs.71,57,743/-. The work was to be

    completed within ten months, i.e., by 05.08.2009. Subsequently,

    an additional work order dated 18.09.2010 worth Rs.25 lakhs was

    issued for completion of the remaining work, extending the

    timeline up to 27.09.2010 without imposing any penalty.

    2.1 However, due to lack of funds the University was unable to

    clear the bills. Consequently, the respondent stopped the work.

    The respondent also sent various communications to clear the

    outstanding dues. The matter was placed before the University’s

    Building Committee and Syndicate, wherein it was decided to pay

    the respondent for the work executed. The respondent was asked

    to submit his final bills. The respondent submitted final bills, and

    payments were made in parts. The respondent also submitted 14 th

    running bill dated 29.06.2011 amounting to Rs.5,90,397/-. The

    appellant made part-payment of the said bill which was accepted

    by respondent under protest, leading to a dispute over a balance

    sum of Rs.2,26,617/-.

    2.2 On 14.12.2015, respondent invoked arbitration under Clause

    23 of the agreement. Upon failure of the University to appoint an

    arbitrator, the respondent approached this Court under Section

    11(6) of 1996 Act, resulting in the appointment of a sole arbitrator

    on 15.05.2019. Arbitration proceedings were conducted, and by

    award dated 31.12.2021, the Arbitrator ruled in favour of the

    respondent. The appellants objected to the award under Section

    34 of 1996 Act; however, the award was upheld by the

    Commercial Court on 06.11.2024.

    2.3 Hence, the instant appeal.

    (Uploaded on 21/04/2026 at 01:00:49 PM)
    (Downloaded on 21/04/2026 at 08:38:19 PM)
    [2026:RJ-JD:17649-DB] (3 of 11) [CMA-412/2025]

    3. Ms. Adwaita Sharma, learned counsel for the appellants

    vehemently contends that the impugned judgment dated

    06.11.2024, as well as the Arbitral Award dated 31.12.2021, are

    contrary to the settled principles of law and the facts borne out

    from the record. Being perverse, patently illegal, and in conflict

    with the public policy, the same deserve to be set aside. It is

    submitted that the learned Commercial Court failed to exercise the

    jurisdiction vested in it under Section 34 of the 1996 Act, having

    mechanically observed that the scope of interference is limited,

    without duly adjudicating upon the specific objections raised by

    the appellants. Such failure to consider material issues strikes at

    the very root of the matter and renders the impugned judgment

    wholly unsustainable.

    3.1 It is further contended that the learned Arbitrator gravely

    erred in interpreting Clause 6 of the agreement by importing

    conditions such as obtaining consent of the contractor and

    recording reasons for re-measurement, which are not

    contemplated under the contract. The clause clearly provides that

    measurements determined by the Engineer-in-Charge are final

    and binding, and only requires reasonable notice. The Arbitrator,

    therefore, not only misinterpreted the contractual terms but also

    travelled beyond the scope of reference by deciding issues not

    raised by the parties, thereby vitiating the award on grounds of

    patent illegality.

    3.2 Learned counsel also submits that both the learned Arbitrator

    and the Commercial Court failed to appreciate that the appellants

    had already paid the entire amount due for the work executed,

    (Uploaded on 21/04/2026 at 01:00:49 PM)
    (Downloaded on 21/04/2026 at 08:38:19 PM)
    [2026:RJ-JD:17649-DB] (4 of 11) [CMA-412/2025]

    along with the security deposit, and it was the respondent who

    abandoned the project midway. This compelled the appellants to

    engage another contractor and incur additional financial burden.

    Despite this, the Arbitrator erroneously allowed multiple claims,

    including amounts towards idle machinery, rental charges, and

    salaries, without any cogent evidence and in direct contravention

    of the terms of the agreement, particularly Clauses 6 and 18.

    3.3 It is further argued that the claims were ex facie barred by

    limitation, as the cause of action admittedly arose in May 2012,

    whereas arbitration was invoked after an inordinate delay of

    several years. The Arbitrator adopted inconsistent dates for

    limitation while adjudicating different claims and ignored material

    facts, including suppression by the claimant regarding prior

    rejection of the arbitration request and non-impleadment of a

    necessary party, namely the University Engineer. In these

    circumstances, it is submitted that the impugned award and

    judgment are liable to be set aside in toto.

    3.4 Learned counsel for the appellant relies on a judgment

    rendered by Hon’ble Supreme Court in BSNL and Anr. Vs.

    Nortel Networks India Private Limited.1

    4. Au contraire, M/s Maheshwari, learned counsels for the

    respondent, in unison, emphatically oppose the present appeal.

    They submit that the same is wholly devoid of merit and liable to

    be dismissed for the reasons duly recorded in the impugned

    judgment. It is contended that the findings returned therein are

    well-reasoned, based on the material available on record, and

    1 (2021) 5 SCC 738

    (Uploaded on 21/04/2026 at 01:00:49 PM)
    (Downloaded on 21/04/2026 at 08:38:19 PM)
    [2026:RJ-JD:17649-DB] (5 of 11) [CMA-412/2025]

    warrant no interference by this Court in the exercise of its

    appellate jurisdiction.

    4.1. Qua limitation, it is urged that having sifted through the

    corresponding evidence adduced by both the sides, learned

    Arbitrator found the claims to be within the period of limitation.

    Similar was the view expressed by the learned Commercial Court.

    Moreover, 14th running bill dated 29.06.2011 submitted by the

    claimant before the appellant was finally rejected on 19.12.2012.

    After approving part-payment and basis thereof, alleged final

    payment was made on 07.01.2013. Thus, it is argued by the

    learned counsel for the respondent that being a running account,

    the limitation period would reckon from the date of rejection of

    part claim and the date of last payment remitted thereof.

    5. In the aforesaid backdrop, we have heard the rival

    contentions and perused the material available on record as well

    as the impugned judgment and the arbitral award.

    6. Before we proceed to render our opinion, let us see as to

    what primarily transpired on the mind of the learned Commercial

    court Judge. Qua that, the translated relevant extract of the

    impugned judgment is reproduced herein below:

    “12. The principal objection raised by the petitioner is
    that the claim application of the respondent firm was
    barred by limitation, yet the arbitral award in question
    was passed in favour of the respondent firm by the
    Arbitral Tribunal. In this regard, upon perusal of the
    impugned award, it is evident that the petitioner had
    raised an objection before the Sole Arbitrator regarding
    the claim being time-barred. The Sole Arbitrator, after
    considering the evidence available on record and after
    affording due opportunity of hearing to both parties, held
    that the claim application was within limitation and
    accordingly passed the award. In such circumstances, in
    light of the views expressed by the Hon’ble Constitutional
    Courts, this Court cannot re-examine or re-analyse the
    findings of the Arbitral Tribunal on this issue. Moreover,

    (Uploaded on 21/04/2026 at 01:00:49 PM)
    (Downloaded on 21/04/2026 at 08:38:19 PM)
    [2026:RJ-JD:17649-DB] (6 of 11) [CMA-412/2025]

    the question as to whether the claim was within the
    prescribed limitation period is essentially within the
    domain of the Arbitrator to adjudicate.

    X-X-X-X-X

    15. In view of the judicial precedents laid down by the
    Hon’ble Supreme Court, the determination made by the
    Arbitrator in this regard does not suffer from any
    illegality and is hereby affirmed. Further, the petitioner
    has failed to demonstrate before this Court as to how the
    present case falls within the scope of interference under
    Section 34 of the Arbitration and Conciliation Act, 1996.
    Therefore, interference with the reasoned order passed by
    the Arbitrator on the issues in dispute is not warranted.

    16. Ordinarily, if an arbitral award is found to be in
    violation of the fundamental policy of Indian law or is in
    conflict with the most basic notions of morality or justice,
    such an award cannot be sustained.

    17. However, where the Arbitral Tribunal, while passing
    the award, has not violated the provisions of law
    prevailing in India, and the award is not against the basic
    notions of morality or justice, is not induced or affected
    by fraud or corruption, does not contravene public policy,
    and is based on the conscious application of mind by the
    Tribunal, then such an award must be upheld. This is
    because the powers of the Court while dealing with an
    application under Section 34 of the Arbitration and
    Conciliation Act are limited and circumscribed.

    18. Furthermore, the petitioner has failed to substantiate
    the grounds pleaded in the application for setting aside
    the award with any cogent material or evidence. The
    petitioner has merely made allegations without
    demonstrating how the award is arbitrary, biased, or
    predetermined. A mere assertion that the award is not
    based on facts or law is insufficient, particularly when
    nothing on record indicates that the Arbitrator acted with
    bias or in contravention of the expected standards of
    conduct.

    19. In the process of adjudication, a decision-maker
    often experiences multiple internal considerations before
    arriving at a conclusion. Where the matter is
    straightforward, such deliberations are minimal; however,
    in complex cases, it is natural for multiple considerations
    to arise in the mind of the adjudicator. Ultimately, after
    due deliberation, the adjudicator arrives at a decision.
    The recording of such internal thought processes in the
    award is neither necessary nor expected. Even if such
    reflections are mentioned, it cannot be a ground to
    conclude that the award is imaginary or biased. Hence,
    the argument advanced by the petitioner in this regard is
    untenable.

    20. The Arbitral Tribunal has passed the award after
    affording an opportunity of hearing to both parties and
    after considering the oral and documentary evidence as
    well as the terms and conditions of the contract executed
    between the parties.

    21. The role of the Court while deciding an application
    under Section 34 of the Arbitration and Conciliation Act
    is supervisory in nature and not that of an appellate court.
    Unlike a regular civil appeal where the appellate court
    can re-appreciate evidence and analyse facts, the Court

    (Uploaded on 21/04/2026 at 01:00:49 PM)
    (Downloaded on 21/04/2026 at 08:38:19 PM)
    [2026:RJ-JD:17649-DB] (7 of 11) [CMA-412/2025]

    under Section 34 cannot re-evaluate the findings of the
    Arbitral Tribunal or substitute its own conclusions.

    22. It is pertinent to note that under Section 28(3) of the
    Act, the Arbitrator is required to decide in accordance
    with the terms of the contract. If the award is contrary to
    the contractual terms, it may be held to be unsustainable.
    Similarly, under Section 34(2A), an award may be set
    aside if it is vitiated by patent illegality.

    23. As already discussed, the powers and limitations of
    this Court under Section 34 have been delineated. This
    Court cannot re-analyse the factual findings of the
    Arbitral Tribunal, nor can it act as an appellate forum.
    The Court cannot substitute its own view for that of the
    Tribunal. Only in cases where there is a manifest error in
    the award can interference be justified. Therefore, in the
    interest of brevity and in view of the limited jurisdiction of
    this Court, the detailed findings and reasoning of the
    Arbitral Tribunal are not being reproduced herein and are
    instead affirmed.

    24. The Sole Arbitrator has passed a well-reasoned
    award based on the oral and documentary evidence on
    record, and no illegality is found therein. The award does
    not fall within any of the grounds for interference under
    Section 34 of the Arbitration and Conciliation Act, 1996.
    The petitioner has failed to establish that the impugned
    award is contrary to public policy or public interest.
    Accordingly, in view of the foregoing discussion and
    conclusions, the application filed by the petitioner under
    Section 34(2) of the Act deserves to be rejected, and the
    arbitral award dated 31.12.2021 is liable to be upheld.”

    7. At the outset, while we duly appreciate the strenuous effort

    and perseverance with which, Ms. Sharma, learned counsel for the

    appellant has advanced her submissions in an earnest endeavour

    to dissuade us from the view taken by the learned Commercial

    Court and the learned Arbitrator, but we are unable to persuade

    ourselves to accept the position canvassed by her. Upon due

    consideration, we find ourselves in agreement with the reasoning

    adopted by the learned Commercial Court, read in conjunction

    with the findings recorded in the award rendered by the learned

    Arbitral Tribunal. We proceed to examine the matter accordingly in

    the succeeding part.

    8. We commence with the caveat that the present proceedings

    arise from an appeal under Section 37 of the Arbitration and

    (Uploaded on 21/04/2026 at 01:00:49 PM)
    (Downloaded on 21/04/2026 at 08:38:19 PM)
    [2026:RJ-JD:17649-DB] (8 of 11) [CMA-412/2025]

    Conciliation Act, 1996, directed against an order passed under

    Section 34 of the Act whereby the Arbitral Award has been upheld.

    Our appellate jurisdiction in such matters is, therefore, even more

    narrowly circumscribed than the already limited scope of

    interference exercisable under Section 34 of the Act. In an

    arbitration appeal, though technically first appeal, this Court does

    not sit as a court of appeal over the arbitral award so as to re-

    appreciate evidence, reassess factual findings, or substitute its

    own interpretation merely because another view may also be

    possible. Interference is warranted only where the award, or the

    order under section 34, ibid, refusing to set it aside, is shown to

    suffer from patent illegality, perversity going to the root of the

    matter, jurisdictional error, or conflict with the limited grounds

    recognised under the Act.

    9. The submission that the learned Commercial Court

    mechanically dismissed the objections without considering the

    specific grounds raised is not borne out from the record. A perusal

    of the impugned judgment reveals that the Commercial Court was

    conscious of the objections regarding limitation, interpretation of

    contractual clauses, alleged excess of jurisdiction, and

    maintainability of the claims. Having examined the award in the

    backdrop of the settled parameters under Section 34, it concluded

    that none of the objections disclosed any ground warranting

    interference. Merely because the learned commercial Court did not

    accept the appellants’ submissions, it cannot be said that the

    objections were not considered.

    (Uploaded on 21/04/2026 at 01:00:49 PM)
    (Downloaded on 21/04/2026 at 08:38:19 PM)
    [2026:RJ-JD:17649-DB] (9 of 11) [CMA-412/2025]

    10. Equally untenable is the challenge founded upon

    interpretation of Clause 6 of the agreement. Construction of

    contractual terms falls primarily within the domain of the Arbitral

    Tribunal. Unless the interpretation adopted is one that no

    reasonable person could take, or is plainly contrary to the express

    language of the contract, the commercial or appellate Court ought

    not to interfere. We find that the view taken by the learned

    Arbitrator while construing Clause 6 cannot be said to be irrational

    or impossible. At the highest, the learned counsel for the appellant

    seeks to propound an alternative interpretation of the clause,

    which by itself is no ground to set aside an award.

    11. The contention that the learned Arbitrator travelled beyond

    the scope of reference is also devoid of substance. The award

    reflects adjudication of disputes arising out of execution of the

    contract, measurements, payments, and consequential claims

    between the parties. These were matters directly connected with

    the contractual relationship and squarely within the ambit of the

    disputes referred to arbitration. No material has been shown to

    establish that the Arbitral Tribunal adjudicated an issue wholly

    foreign to the reference.

    12. The argument that the respondent had abandoned the work

    and that the appellants had already discharged all dues pertains

    essentially to disputed questions of fact. These issues were placed

    before the learned Arbitrator, who, upon appreciation of the oral

    and documentary evidence, returned findings adverse to the

    appellants. Likewise, the grievance regarding grant of claims

    towards idle machinery, rentals, salaries, and allied heads does

    (Uploaded on 21/04/2026 at 01:00:49 PM)
    (Downloaded on 21/04/2026 at 08:38:19 PM)
    [2026:RJ-JD:17649-DB] (10 of 11) [CMA-412/2025]

    not merit acceptance. Assessment of entitlement and

    quantification of damages or compensation lies within the fact-

    finding jurisdiction of the Arbitrator. Unless it is established that

    such claims were awarded in the complete absence of evidence or

    in express disregard of a contractual prohibition, no case for

    interference arises. The appellants have failed to establish any

    such manifest infirmity.

    13. Once such findings, as above, are based on material available

    on record and are plausible, the same cannot be reopened in

    proceedings under Sections 34 or 37, ibid. Re-appreciation of

    evidence under the guise of exercising power under section 37 is

    ordinarily impermissible, unless, in a fit case it is so deemed

    appropriate by stating the reasons thereof.

    14. As regards limitation, both the learned Arbitrator and the

    Commercial Court have concurrently held the claims to be within

    time after considering the relevant dates, including the running

    bills, part payments, rejection of bills, and final payments

    exchanged between the parties. Limitation in the facts of the

    present case involved mixed questions of fact and law. Once the

    conclusion reached is based on appreciation of the record and

    represents a possible view, this Court would not interfere in

    appellate jurisdiction under Section 37 and we find no grounds to

    interfere on that count as well.

    15. Reliance placed upon BSNL and Another v. Nortel

    Networks India Private Limited (supra) is also misplaced. In

    that case, the claim was found to be ex facie and hopelessly

    barred by limitation after an unexplained delay of several years (5

    (Uploaded on 21/04/2026 at 01:00:49 PM)
    (Downloaded on 21/04/2026 at 08:38:19 PM)
    [2026:RJ-JD:17649-DB] (11 of 11) [CMA-412/2025]

    and ½ years). The present matter stands on a different factual

    footing, where the claims have been held to be within limitation

    upon consideration of subsequent payments and continuing

    transactions between the parties. The said decision, therefore,

    does not advance the appellants’ case.

    16. Appeal is accordingly, dismissed.

    17. All pending applications stand disposed of.

                                       (SUNIL BENIWAL),J                                               (ARUN MONGA),J
                                        97-ajayS/-
    
    
    
    
                                                                (Uploaded on 21/04/2026 at 01:00:49 PM)
                                                               (Downloaded on 21/04/2026 at 08:38:19 PM)
    
    
    
    Powered by TCPDF (www.tcpdf.org)
     

    [ad_1]

    Source link

    LEAVE A REPLY

    Please enter your comment!
    Please enter your name here