Emr Chowdary vs Engineering Projects India Limited on 27 April, 2026

    0
    38
    ADVERTISEMENT

    Delhi High Court

    Emr Chowdary vs Engineering Projects India Limited on 27 April, 2026

                      $~
                      *      IN THE HIGH COURT OF DELHI AT NEW DELHI
                      %                                         Judgment reserved on: 16.04.2026
                                                             Judgment pronounced on: 27.04.2026
    
                      +      O.M.P. (COMM) 400/2017
                             EMR CHOWDARY                                             .....Petitioner
                                        Through:                    Mr. Arjun Natarajan, Mr.
                                                                    Ayush Kumar & Mr. Nakul
                                                                    Gupta, Advocates.
                                                     versus
    
                             ENGINEERING PROJECTS INDIA LIMITED
                                                                                .....Respondent
                                                     Through:       Mr. Manish Paliwal, Ms.
                                                                    Megha Yadav, Ms. Srashti
                                                                    Sahu & Mrs. Trupti Das,
                                                                    Advocates.
    
                      +      O.M.P. (COMM) 408/2017
                             ENGINEERING PROJECT (INDIA) LIMITED .....Petitioner
                                          Through: Mr. Manish Paliwal, Ms.
                                                    Megha Yadav, Ms. Srashti
                                                    Sahu & Mrs. Trupti Das,
                                                    Advocates.
                                          versus
    
                             ASSOCIATED CONSTRUCTION COMPANY
                                                                                   .....Respondent
                                                     Through:       Mr. Arjun Natarajan, Mr.
                                                                    Ayush Kumar & Mr. Nakul
                                                                    Gupta, Advocates.
    
                             CORAM:
                             HON'BLE MR. JUSTICE HARISH VAIDYANATHAN
                             SHANKAR
                                                      JUDGMENT
    

    Signature Not Verified
    Digitally Signed
    By:NEERU

    O.M.P. (COMM) 400/2017 & connected matter
    Signing Date:29.04.2026 Page 1 of 37
    10:39:10

    SPONSORED

    1. The present Petitions, being OMP (COMM) 400/2017 and OMP
    (COMM) 408/2017, have been filed under Section 34 of the
    Arbitration and Conciliation Act, 19961, challenging various
    findings and aspects of the common Arbitral Award dated 05.04.2017,
    as subsequently modified by the additional/modified award dated
    19.08.2017. Since both petitions arise out of the same arbitral
    proceedings and involve interconnected as well as overlapping issues,
    they are being decided together by way of this common judgment.

    2. At the outset, it is noted that both the present Petitions are in the
    nature of cross-objections under Section 34 of the A&C Act. It is also
    an undisputed position that Associated Construction Company is the
    sole proprietorship concern of EMR Chowdary. Accordingly, for the
    sake of clarity and consistency throughout this judgment, the
    expressions “Associated Construction Company” and “EMR
    Chowdary” are used interchangeably, wherever the context so
    requires.

    BRIEF FACTS:

    3. The dispute arises out of a contract pertaining to the execution
    of work for blast hole drilling, blasting, excavation, loading,
    transportation and dumping of overburden at the Gauthamkhani Open
    Cast Project of the Singareni Collieries Company Limited2 in the
    State of Andhra Pradesh.

    4. Engineering Projects (India) Limited3, a public sector
    undertaking, intended to participate in the tender floated by the SCCL.

    1

    A&C Act
    2
    SCCL
    3
    EPI
    Signature Not Verified
    Digitally Signed
    By:NEERU
    O.M.P. (COMM) 400/2017 & connected matter
    Signing Date:29.04.2026 Page 2 of 37
    10:39:10

    5. Associated Construction Company4, through its proprietor
    EMR Chowdary, approached EPI, expressing its willingness to
    associate in the execution of the project and sought a copy of the
    Notice Inviting Tender5.

    6. Pursuant thereto, a pre-tender meeting was held between EPI
    and ACC on 03.10.2003, wherein the parties agreed upon various
    terms and conditions governing their relationship. It was, inter alia,
    agreed that ACC would undertake the complete execution of the work
    as per the tender conditions on a back-to-back basis, and that all terms
    applicable between SCCL and EPI would apply mutatis mutandis
    between EPI and ACC. These understandings between the parties
    were reduced to writing in the Minutes of Meeting dated
    03.10.20036.

    7. ACC submitted its offer to EPI on 06.10.2003, based on which
    EPI submitted its bid to SCCL. The bid of EPI was accepted by SCCL
    on 14.01.2004, and EPI, in turn, informed ACC of the acceptance and
    directed it to commence the work in terms of the understanding
    between the parties.

    8. The SCCL issued a formal work order dated 19.01.2004 in
    favour of EPI for the execution of approximately 285 Lakh Bench
    Cum Work7, followed by a target schedule dated 26.03.2004
    prescribing the timelines for execution.

    9. Thereafter, a Work Order dated 14.05.20048 was issued by
    EPI in favour of ACC for execution of the entire scope of work on an
    item-rate basis, with an estimated value of approximately Rs. 99.21
    4
    ACC
    5
    NIT
    6
    MoM
    7
    LBCM
    8
    Work Order
    Signature Not Verified
    Digitally Signed
    By:NEERU
    O.M.P. (COMM) 400/2017 & connected matter
    Signing Date:29.04.2026 Page 3 of 37
    10:39:10
    Crores. The completion period for the said work was stipulated as 36
    months in terms of the arrangement between EPI and SCCL, with the
    execution to be carried out in accordance with the schedule issued by
    SCCL.

    10. The said work order made reference to, inter alia, the MoM,
    ACC’s offer dated 06.10.2003, and the work order dated 19.01.2004
    and letter dated 26.03.2004 issued by SCCL, and provided that the
    terms and conditions applicable between SCCL and EPI would apply
    mutatis mutandis between EPI and ACC on a back-to-back basis,
    except to the extent otherwise agreed between the parties.

    11. Subsequently, in a meeting held on 30.06.2004, in view of the
    shortfall in achieving the stipulated monthly targets, it was mutually
    decided between EPI and ACC that the scope of work would be
    divided, and ACC would execute only 50% of the project.

    12. Pursuant thereto, EPI issued a Letter of Intent dated 01.07.2004
    in favour of a third party, namely, M/s. CGR Associates, for the
    remaining 50% of the work.

    13. EPI thereafter issued Amendment No. 1 dated 06.07.20049 to
    the work order, reducing ACC’s scope of work by 50% and providing
    for secured advance for the procurement of dumpers. Amendment
    No. 2 dated 30.08.200410 further modified the terms relating to
    repayment of the secured advance.

    14. The work, however, did not proceed as contemplated, and the
    SCCL terminated the work order issued to EPI on 01.10.2004.
    Consequently, EPI terminated the work order issued to ACC on
    08.10.2004.

    9

    Amendment No.1
    10
    Amendment No.2
    Signature Not Verified
    Digitally Signed
    By:NEERU
    O.M.P. (COMM) 400/2017 & connected matter
    Signing Date:29.04.2026 Page 4 of 37
    10:39:10

    15. Following the termination, ACC returned the equipment,
    including dumpers procured for the execution of the project.
    Thereafter, the SCCL raised a demand upon EPI towards penalty and
    differential cost incurred due to termination, and EPI, in turn, raised
    similar claims against ACC.

    16. Disputes having arisen between the parties, EPI invoked the
    arbitration clause contained in the Agreement.

    17. In terms thereof, the Chairman and Managing Director of EPI
    appointed a Sole Arbitrator vide letter dated 24.02.2006 to adjudicate
    the disputes, claims and counterclaims between the parties.

    18. The learned Arbitrator entered upon reference upon accepting
    the appointment on 02.03.2006.

    19. Upon completion of arbitral proceedings, the learned Arbitrator
    passed the Arbitral Award dated 05.04.201711. The claims and
    counter-claims as adjudicated in the Impugned Award are reproduced
    hereunder:

    “12. Summary of the award

    12.1 The award with regard to various claims filed by EPI is
    summarized below:

                                S. No.      Description        Amount         Amount
                                                               claimed in Rs. Awarded in Rs.
                                Claim       Penalty on         2,35,16,330.00.1,35,41,073.52*
                                no. 1       unexecuted                        *Subject to
                                            quantity                          undertaking by
                                                                              EPI
                                Claim       Differential Cost 20,52,46,934.63 9,08,96, 719.00*
                                no. 2                                         *Payable by
                                                                              ACC
                                                                              only if EPI pays
                                                                              this amount to
                                                                              SCCL
                                Claim       Amount            9,61,896.11     (-) 27,92,282.00*
    
                      11
                           Impugned Award
    Signature Not Verified
    Digitally Signed
    By:NEERU
    

    O.M.P. (COMM) 400/2017 & connected matter
    Signing Date:29.04.2026 Page 5 of 37
    10:39:10
    no. 3 recoverable *Payable by EPI
    against to ACC.

                                         payment                                + Interest
                                         released in                            34,20,545.00
                                         excess of
                                         contractual
                                         payments
                             Claim       Loss of profit        4,57,56,039.00   NIL
                             no. 4
                             Claim       Interest payable      38,45,637.11     NIL
                             no. 5       against
                                         unadjusted
                                         amount
                             Claim       Addl.                 10,91,406.00     NIL
                             no. 6       Expenditure
                                         incurred during
                                         execution of the
                                         project
                             Claim       Forfeiture            53,37,828.37     50,00,000.00
                             no. 7       amount of EMD                          Mode of
                                         and security                           recovery
                                                                                as per the verdict
                                                                                of the Hon'ble
                                                                                Court
                                                                                Balance
                                                                                3,20,059.67*
                                                                                *Included in
                                                                                amount under
                                                                                claim no.3
                                                                                above.
                             Claim       Interest on           Will be worked   1,53,46,550.00*
                             no. 8       amount claimed        out and          *Subject to
                                                               submitted        undertaking by
                                                               during           EPI
                                                               pleadings
                             Claim       Amount                As per actuals   NIL
                             no. 9       recoverable on
                                         account of cost
                                         and expenses of
                                         arbitration
                                                                                Plus interest @
                                                                                10% per annum
                                                                                from the 4th
                                                                                month from the
                                                                                date of award till
                                                                                the date of actual
                                                                                payment by ACC
    
    Signature Not Verified
    Digitally Signed
    By:NEERU
    

    O.M.P. (COMM) 400/2017 & connected matter
    Signing Date:29.04.2026 Page 6 of 37
    10:39:10
    12.2 The award with regard to various counter claims filed by
    ACC is summarized below:

                                S. No.      Description        Amount            Amount
                                                               claimed in        Awarded in Rs.
                                                               Rs.
                                Claim       Work done but      36,33,382.85   27,92,282.00 +
                                no. 1       not paid                          interest
                                                                              34,20545.00
                                Claim       Loss on            1,99,53,000.00 NIL
                                no. 2       machinery
                                Claim       Loss on            96,43,500.00      NIL
                                no. 3       workmen etc.
                                Claim       Loss on vehicles   86,70,952.00      Hon'ble Court to
                                no. 4                                            Decide
                                Claim       Loss on            45,70,000.00      NIL
                                no. 5       establishment
                                Claim       Loss on profit     8,88,92,646.00 NIL
                                no. 6       and goodwill
                                                                                 Plus interest @
                                                                                 10% per annum
                                                                                 from the 4th
                                                                                 month from the
                                                                                 date of award till
                                                                                 the date of actual
                                                                                 payment by EPI
                                                                                                 ....."
    
    

    20. Subsequently, upon applications filed by both parties under
    Section 33 of the A&C Act before the learned Arbitrator, certain
    modifications were carried vide Modified Award dated 19.08.201712.
    The modifications by the learned Arbitrator with effect to claims and
    counterclaims by the Modified Award are extracted herein below:

    “12.1 The award with regard to various claims filed by EPI is
    summarized below:

                                S. No.      Description        Amount             Amount
                                                               claimed in Rs.     Awarded in
                                                                                  Rs.
    

    Claim Penalty on 2,35,16,330.00. 1,35,41,073.52*
    no. 1 unexecuted *Subject to
    quantity undertaking by

    12
    Modified Award
    Signature Not Verified
    Digitally Signed
    By:NEERU
    O.M.P. (COMM) 400/2017 & connected matter
    Signing Date:29.04.2026 Page 7 of 37
    10:39:10
    EPI
    Claim Differential Cost 20,52,46,934.63 9,08,96,
    no. 2 719.00*
    *Payable by
    ACC
    only if EPI pays
    this amount to
    SCCL
    Claim Amount 9,61,896.11 NIL
    no. 3 recoverable
    against
    payment
    released in
    excess of
    contractual
    payments
    Claim Loss of profit 4,57,56,039.00 NIL
    no. 4
    Claim Interest payable 38,45,637.11 NIL
    no. 5 against
    unadjusted
    amount
    Claim Addl. 10,91,406.00 NIL
    no. 6 Expenditure
    incurred during
    execution of the
    project
    Claim Forfeiture 53,37,828.37 50,00,000.00
    no. 7 amount of EMD Mode of
    and security recovery
    as per the
    verdict
    of the Hon’ble
    Court
    Balance
    3,20,059.67*
    *Included in
    amount under
    claim no.3
    above.

                             Claim       Interest on           Will be worked   1,53,46,550.00*
                             no. 8       amount claimed        out and          *Subject to
                                                               submitted        undertaking by
                                                               during           EPI
                                                               pleadings
                             Claim       Amount                As per actuals   3,73,650.00
                             no. 9       recoverable on                              +
                                         account of cost                        @ 10% from
    Signature Not Verified
    Digitally Signed
    By:NEERU
    

    O.M.P. (COMM) 400/2017 & connected matter
    Signing Date:29.04.2026 Page 8 of 37
    10:39:10
    and expenses of the date
    arbitration of payment till
    its
    realization.

    12.2 The award with regard to various counter claims filed by
    ACC is summarized below:

                             S. No.      Description           Amount           Amount
                                                               claimed in Rs.   Awarded in
                                                                                Rs.
                             Claim       Work done but         36,33,382.85     27,92,282.00 +
                             no. 1       not paid                               interest
                                                                                34,20545.00
                             Claim       Loss on               1,99,53,000.00   NIL
                             no. 2       machinery
                             Claim       Loss on               96,43,500.00     NIL
                             no. 3       workmen etc.
                             Claim       Loss on vehicles      86,70,952.00     10,08,949.00
                             no. 4                                                 +
                                                                                Interest
                                                                                12,61,186.00
                             Claim       Loss on               45,70,000.00     NIL
                             no. 5       establishment
                             Claim       Loss on profit        8,88,92,646.00   NIL
                             no. 6       and goodwill
                                                                                Plus interest @
                                                                                10% per
                                                                                annum from
                                                                                the 4th month
                                                                                from the date
                                                                                of award till
                                                                                the date of
                                                                                actual payment
                                                                                by EPI
                                                                                            ......"
    
    

    21. Aggrieved by the Impugned Award, as modified by the Order
    dated 19.08.2017, both parties have preferred the present cross
    Petitions under Section 34 of the A&C Act before this Court.

    Signature Not Verified
    Digitally Signed
    By:NEERU

    O.M.P. (COMM) 400/2017 & connected matter
    Signing Date:29.04.2026 Page 9 of 37
    10:39:10
    SUBMISSIONS ON BEHALF OF PARTIES IN OMP(COMM.)
    400/2017:

    ACC’s Submissions

    22. Learned counsel for ACC, in the Petition filed by ACC, would
    submit that the Impugned Award, as well as the Modified Award, is
    liable to be set aside as the learned Arbitrator has proceeded on
    fundamentally erroneous premises in fact and law. He would contend
    that the MoM was only a preliminary understanding and did not
    constitute a binding contract, particularly in the absence of any formal
    agreement approved by SCCL.

    23. He would further submit that the learned Arbitrator has
    erroneously assumed the existence of binding targets from March
    2004, despite the work order having come into existence only on
    14.05.2004 and no agreed schedule being in place thereafter. He
    would argue that the learned Arbitrator has, in effect, created
    contractual obligations by imposing targets which were never agreed
    upon, and has proceeded on an imaginary schedule despite recording
    that no revised schedule existed.

    24. Learned counsel would contend that such an approach amounts
    to rewriting the contract, which is impermissible in law. Reliance
    would be placed by the learned counsel for ACC on PSA Sical
    Terminals Pvt. Ltd. v. Board of Trustees of V.O. Chidambranar Port
    Trust13
    to submit that an arbitral tribunal cannot travel beyond the
    contract or impose obligations dehors it. He would also submit that
    ACC was deprived of an opportunity to deal with such assumed
    targets, thereby violating principles of natural justice.

    13

    (2023) 15 SCC 781
    Signature Not Verified
    Digitally Signed
    By:NEERU
    O.M.P. (COMM) 400/2017 & connected matter
    Signing Date:29.04.2026 Page 10 of 37
    10:39:10

    25. He would further contend that the imposition of a penalty and
    differential cost is without a contractual basis, particularly when the
    learned Arbitrator himself records the absence of any agreement to
    share profit and loss. He would submit that no default can be
    attributed to ACC in the absence of a mutually agreed schedule and
    that ACC had duly performed during the limited period where any
    schedule could arguably be said to exist.

    26. He would also submit that the work order does not constitute a
    binding contract governing inter se rights, and that EPI failed to
    perform its reciprocal obligations, which has not been duly
    considered. He would further contend that the rejection of counter-

    claims is arbitrary and unsupported by a proper appreciation of
    evidence.

    27. He would, during the course of oral submissions, submit that
    the ACC’s challenge is confined to Claim Nos. 1, 2, 7 and 9 and
    Counter Claim Nos. 2, 3, 5 and 6, and that the Impugned Award as
    well as the Modified Award, to that extent, is vitiated by patent
    illegality.

    28. He would contend that in the absence of any concluded
    contract, the learned Arbitrator could not have imposed liabilities, and
    even otherwise, the Impugned award travels beyond the contractual
    framework in violation of Section 28(3) of the A&C Act and is bereft
    of reasons in violation of Section 31(3) thereof.

    29. He would, therefore, pray that the Impugned Award, as
    modified, be set aside to the aforesaid extent.

    Signature Not Verified
    Digitally Signed
    By:NEERU

    O.M.P. (COMM) 400/2017 & connected matter
    Signing Date:29.04.2026 Page 11 of 37
    10:39:10
    EPI’s Submissions

    30. Per contra, learned counsel for EPI would submit that the
    present Petition is not maintainable within the limited scope of
    Section 34 of the A&C Act, as ACC seeks to re-agitate issues on
    merits which have already been adjudicated by the learned Arbitrator
    upon appreciation of evidence and construction of contractual
    documents.

    31. He would submit that it is well settled that the Court does not sit
    in appeal over an arbitral award and cannot reappreciate evidence or
    substitute its own view, unless the findings are perverse or patently
    illegal. He would rely upon Associate Builders v. DDA14 and upon
    McDermott International Inc. v. Burn Standard Co. Ltd.15, to
    contend that findings of fact and interpretation of contract by the
    arbitrator are definite unless perverse.

    32. He would further submit, relying on NHAI v. ITD Cementation
    India Ltd.16, that the construction of contractual terms falls within the
    domain of the arbitrator and cannot be interfered with unless the view
    taken is wholly unreasonable.

    33. He would contend that the learned Arbitrator has rightly held
    that the MoM, read with the subsequent work orders dated 16.01.2004
    and 14.05.2004, constitutes a binding contractual framework. He
    would submit that the work order dated 14.05.2004 was accepted by
    ACC without demur and expressly incorporated the SCCL terms on a
    back-to-back basis, thereby establishing binding obligations between
    the parties.

    14

    (2015) 3 SCC 49
    15
    (2006) 11 SCC 181
    16
    (2015) 14 SCC 21
    Signature Not Verified
    Digitally Signed
    By:NEERU
    O.M.P. (COMM) 400/2017 & connected matter
    Signing Date:29.04.2026 Page 12 of 37
    10:39:10

    34. He would further contend that the plea of ACC regarding the
    absence of any target schedule is misconceived, as the SCCL work
    order prescribed the schedule, which stood incorporated by virtue of
    the mutatis mutandis clause. He would submit that the learned
    Arbitrator has, on appreciation of evidence, recorded a finding of
    persistent shortfall in performance by ACC, which, being a finding of
    fact, does not warrant interference under Section 34 of the A&C Act.

    35. He would further submit that the learned Arbitrator has not
    created any new contractual obligations but has merely interpreted the
    existing contractual framework, and such interpretation cannot be
    interfered with unless wholly unreasonable. He would further submit
    that the Impugned award contains detailed reasons and does not suffer
    from any infirmity under Sections 28(3) or 31(3) of the A&C Act.

    36. He would also contend that the allegation of violation of natural
    justice is vague and without substantiation, and that ACC was
    afforded full opportunity to present its case. He would submit that the
    award of penalty is in accordance with the contractual framework, and
    the learned Arbitrator has awarded only proportionate liability
    relatable to ACC.

    37. It would further be submitted that the counter-claims of ACC
    have been rightly rejected on the finding that ACC was in breach,
    which does not warrant interference. He would, however, contend that
    insofar as Counter Claim No. 4 is concerned, the learned Arbitrator, in
    the Modified award, has erroneously awarded Rs. 10,08,949/- along
    with interest, which EPI has independently challenged in OMP
    (COMM) 408/2017.

    Signature Not Verified
    Digitally Signed
    By:NEERU

    O.M.P. (COMM) 400/2017 & connected matter
    Signing Date:29.04.2026 Page 13 of 37
    10:39:10

    38. He would, therefore, submit that the Impugned Award is well
    reasoned and does not suffer from any perversity or patent illegality,
    to the extent of the challenge raised by ACC, warranting interference
    under Section 34 of the A&C Act, and the present Petition is liable to
    be dismissed.

    SUBMISSIONS ON BEHALF OF PARTIES IN OMP(COMM.)
    408/2017:

    EPI’s Submissions

    39. Learned counsel for EPI would submit that, notwithstanding the
    various grounds urged in the petition, the challenge is confined to two
    aspects of the Impugned Award dated 05.04.2017 and the Modified
    Award dated 19.08.2017.

    40. Firstly, he would contend that the learned Arbitrator has
    exceeded his jurisdiction under Section 33 of the A&C Act by
    awarding Counter Claim No. 4 in the Modified Award despite having
    consciously not awarded the same in the Impugned Award on the
    ground that the issue was sub judice. He would submit that such re-
    adjudication on merits amounts to a review of the award, which is
    impermissible under Section 33 of the A&C Act.

    41. Secondly, learned counsel for EPI would submit that the
    learned Arbitrator has erred in making the awards under Claim Nos. 1
    and 8 conditional upon the outcome of recovery proceedings with
    SCCL, including directing EPI to furnish an undertaking to ACC. He
    would contend that such conditional directions are unwarranted and
    contrary to the contractual framework.

    42. He would, therefore, submit that the Impugned Award as well
    as the Modified Award suffer from patent illegality and are contrary to
    Signature Not Verified
    Digitally Signed
    By:NEERU
    O.M.P. (COMM) 400/2017 & connected matter
    Signing Date:29.04.2026 Page 14 of 37
    10:39:10
    the contractual terms, and are liable to be set aside or modified to the
    extent challenged.

    ACC’s Submissions

    43. Per contra, learned counsel appearing for ACC, in response to
    the first prong of challenge raised by EPI, during the oral hearing,
    fairly conceded that the learned Arbitrator, in the Modified Award,
    rendered findings on Counter Claim No. 4 despite no such relief
    having been granted in the Impugned Award. He further submitted
    that such an exercise may not be strictly in consonance with the
    limited scope of Section 33 of the A&C Act, and to that extent, the
    modification may not be sustainable in law.

    44. However, learned counsel for ACC would contend that the
    challenge to the conditional nature of the award under Claim Nos. 1
    and 8 is misconceived.

    45. Learned counsel for ACC would submit that, in view of the
    back-to-back contractual arrangement and the application of the
    principle of mutatis mutandis, any recovery or adjustment by SCCL
    from EPI would necessarily have to be passed on proportionately to
    ACC. He would submit that the learned Arbitrator has rightly directed
    EPI to furnish an undertaking to ACC in this regard, and no
    interference is warranted on this aspect.

    ANALYSIS:

    46. This Court has carefully considered the submissions advanced
    on behalf of both sides and, with their able assistance, has perused the
    Impugned and the Modified Award and the material placed before this
    Court for the adjudication of both Petitions.

    Signature Not Verified
    Digitally Signed
    By:NEERU

    O.M.P. (COMM) 400/2017 & connected matter
    Signing Date:29.04.2026 Page 15 of 37
    10:39:10

    47. At the outset, it is apposite to note that this Court remains
    conscious of the limited scope of its jurisdiction while examining an
    objection petition under Section 34 of the A&C Act. There is a
    consistent and evolving line of precedents whereby the Hon’ble
    Supreme Court has authoritatively delineated and settled the contours
    of judicial intervention in such proceedings.

    48. In this regard, a 3-Judge Bench of the Hon’ble Supreme Court,
    after an exhaustive consideration of a catena of earlier judgments, in
    OPG Power Generation Pvt. Ltd. v. Enexio Power Cooling Solutions
    (India) Pvt. Ltd17
    , while dealing with the grounds of conflict with the
    public policy of India, perversity and patent illegality, grounds which
    have also been urged in the present case, made the following
    observations, which are reproduced hereunder:

    “Relevant legal principles governing a challenge to an arbitral
    award

    30. Before we delve into the issue/sub-issues culled out above, it
    would be useful to have a look at the relevant legal principles
    governing a challenge to an arbitral award. Recourse to a court
    against an arbitral award may be made through an application for
    setting aside such award in accordance with sub-sections (2), (2-A)
    and (3) of Section 34 of the 1996 Act. Sub-section (2) of Section
    34 has two clauses, (a) and (b). Clause (a) has five sub-clauses
    which are not relevant to the issues raised before us. Insofar as
    clause (b) is concerned, it has two sub-clauses, namely, (i) and (ii).
    Sub-clause (i) of clause (b) is not relevant to the controversy in
    hand. Sub-clause (ii) of clause (b) provides that if the Court finds
    that the arbitral award is in conflict with the public policy of India,
    it may set aside the award.

    Public policy

    31. “Public policy” is a concept not statutorily defined, though it
    has been used in statutes, rules, notification, etc. since long, and is
    also a part of common law. Section 23 of the Contract Act, 1872
    uses the expression by stating that the consideration or object of an
    agreement is lawful, unless, inter alia, opposed to public policy.
    That is, a contract which is opposed to public policy is void.

    *****

    17
    (2025) 2 SCC 417
    Signature Not Verified
    Digitally Signed
    By:NEERU
    O.M.P. (COMM) 400/2017 & connected matter
    Signing Date:29.04.2026 Page 16 of 37
    10:39:10

    37. What is clear from above is that for an award to be against
    public policy of India a mere infraction of the municipal laws of
    India is not enough. There must be, inter alia, infraction of
    fundamental policy of Indian law including a law meant to serve
    public interest or public good.

    *****
    The 2015 Amendment in Sections 34 and 48

    42. The aforementioned judicial pronouncements were all prior to
    the 2015 Amendment. Notably, prior to the 2015 Amendment the
    expression “in contravention with the fundamental policy of Indian
    law” was not used by the legislature in either Section 34(2)(b)(ii) or
    Section 48(2)(b). The pre-amended Section 34(2)(b)(ii) and its
    Explanation read:

    *****

    44. By the 2015 Amendment, in place of the old Explanation to
    Section 34(2)(b)(ii), Explanations 1 and 2 were added to remove
    any doubt as to when an arbitral award is in conflict with the public
    policy of India.

    45. At this stage, it would be pertinent to note that we are dealing
    with a case where the application under Section 34 of the 1996 Act
    was filed after the 2015 Amendment, therefore the newly
    substituted/added Explanations would apply [Ssangyong Engg. &
    Construction Co. Ltd. v. NHAI
    , (2019) 15 SCC 131].

    46. The 2015 Amendment adds two Explanations to each of the
    two sections, namely, Section 34(2)(b)(ii) and Section 48(2)(b), in
    place of the earlier Explanation. The significance of the newly
    inserted Explanation 1 in both the sections is two-fold. First, it does
    away with the use of words : (a) “without prejudice to the
    generality of sub-clause (ii)” in the opening part of the pre-

    amended Explanation to Section 34(2)(b)(ii); and (b) “without
    prejudice to the generality of clause (b) of this section” in the
    opening part of the pre-amended Explanation to Section 48(2)(b);
    secondly, it limits the expanse of public policy of India to the three
    specified categories by using the words “only if”.
    Whereas, Explanation 2 lays down the standard for adjudging
    whether there is a contravention with the fundamental policy of
    Indian law by providing that a review on merits of the dispute shall
    not be done. This limits the scope of the enquiry on an application
    under either Section 34(2)(b)(ii) or Section 48(2)(b) of the 1996
    Act.

    47. The 2015 Amendment by inserting sub-section (2-A) in Section
    34
    , carves out an additional ground for annulment of an arbitral
    award arising out of arbitrations other than international
    commercial arbitrations. Sub-section (2-A) provides that the Court
    may also set aside an award if that is vitiated by patent illegality
    appearing on the face of the award. This power of the Court is,
    however, circumscribed by the proviso, which states that an award

    Signature Not Verified
    Digitally Signed
    By:NEERU
    O.M.P. (COMM) 400/2017 & connected matter
    Signing Date:29.04.2026 Page 17 of 37
    10:39:10
    shall not be set aside merely on the ground of an erroneous
    application of the law or by reappreciation of evidence.

    48. Explanation 1 to Section 34(2)(b)(ii), specifies that an arbitral
    award is in conflict with the public policy of India, only if:

    (i) the making of the award was induced or affected by fraud or
    corruption or was in violation of Section 75 or Section 81; or

    (ii) it is in contravention with the fundamental policy of Indian law;
    or

    (iii) it is in conflict with the most basic notions of morality or
    justice.

    49. In the instant case, there is no allegation that the making of the
    award was induced or affected by fraud or corruption, or was in
    violation of Section 75 or Section 81. Therefore, we shall confine
    our exercise in assessing as to whether the arbitral award is in
    contravention with the fundamental policy of Indian law, and/or
    whether it conflicts with the most basic notions of morality or
    justice. Additionally, in the light of the provisions of sub-section
    (2-A) of Section 34, we shall examine whether there is any patent
    illegality on the face of the award.

    50. Before undertaking the aforesaid exercise, it would be apposite
    to consider as to how the expressions:

    (a) “in contravention with the fundamental policy of Indian law”;

    (b) “in conflict with the most basic notions of morality or justice”;
    and

    (c) “patent illegality” have been construed.

    In contravention with the fundamental policy of Indian law

    51. As discussed above, till the 2015 Amendment the expression
    “in contravention with the fundamental policy of Indian law” was
    not found in the 1996 Act. Yet, in Renusagar Power Co.
    Ltd. v. General Electric Co.
    , 1994 Supp (1) SCC 644, in the
    context of enforcement of a foreign award, while construing the
    phrase “contrary to the public policy”, this Court held that for a
    foreign award to be contrary to public policy mere contravention of
    law would not be enough rather it should be contrary to:

    (a) the fundamental policy of Indian law; and/or

    (b) the interest of India; and/or

    (c) justice or morality.

    *****

    55. The legal position which emerges from the aforesaid discussion
    is that after “the 2015 Amendments” in Section 34(2)(b)(ii) and
    Section 48(2)(b) of the 1996 Act, the phrase “in conflict with the
    public policy of India” must be accorded a restricted meaning in
    terms of Explanation 1. The expression “in contravention with the
    fundamental policy of Indian law” by use of the word
    “fundamental” before the phrase “policy of Indian law” makes the
    expression narrower in its application than the phrase “in
    contravention with the policy of Indian law”, which means mere
    contravention of law is not enough to make an award vulnerable.

    Signature Not Verified
    Digitally Signed
    By:NEERU

    O.M.P. (COMM) 400/2017 & connected matter
    Signing Date:29.04.2026 Page 18 of 37
    10:39:10
    To bring the contravention within the fold of fundamental policy of
    Indian law, the award must contravene all or any of such
    fundamental principles that provide a basis for administration of
    justice and enforcement of law in this country.

    56. Without intending to exhaustively enumerate instances of such
    contravention, by way of illustration, it could be said that:

    (a) violation of the principles of natural justice;

    (b) disregarding orders of superior courts in India or the binding
    effect of the judgment of a superior court; and

    (c) violating law of India linked to public good or public interest,
    are considered contravention of the fundamental policy of Indian
    law.

    However, while assessing whether there has been a contravention
    of the fundamental policy of Indian law, the extent of judicial
    scrutiny must not exceed the limit as set out in Explanation 2 to
    Section 34(2)(b)(ii).

    *****
    Patent illegality

    65. Sub-section (2-A) of Section 34 of the 1996 Act, which was
    inserted by the 2015 Amendment, provides that an arbitral award
    not arising out of international commercial arbitrations, may also
    be set aside by the Court, if the Court finds that the award is visited
    by patent illegality appearing on the face of the award. The proviso
    to sub-section (2-A) states that an award shall not be set aside
    merely on the ground of an erroneous application of the law or by
    reappreciation of evidence.

    66. In ONGC Ltd. v. Saw Pipes Ltd., (2003) 5 SCC 705, while
    dealing with the phrase “public policy of India” as used in Section
    34
    , this Court took the view that the concept of public policy
    connotes some matter which concerns public good and public
    interest. If the award, on the face of it, patently violates statutory
    provisions, it cannot be said to be in public interest. Thus, an award
    could also be set aside if it is patently illegal. It was, however,
    clarified that illegality must go to the root of the matter and if the
    illegality is of trivial nature, it cannot be held that award is against
    public policy.

    67. In Associate Builders v. DDA, (2015) 3 SCC 49, this Court
    held that an award would be patently illegal, if it is contrary to:

    (a) substantive provisions of law of India;

    (b) provisions of the 1996 Act; and

    (c) terms of the contract [See also three-Judge Bench decision of
    this Court in State of Chhattisgarh v. SAL Udyog (P) Ltd., (2022)
    2 SCC 275].

    The Court clarified that if an award is contrary to the substantive
    provisions of law of India, in effect, it is in contravention of
    Section 28(1)(a) of the 1996 Act. Similarly, violating terms of the
    contract, in effect, is in contravention of Section 28(3) of the 1996
    Act.

    Signature Not Verified
    Digitally Signed
    By:NEERU

    O.M.P. (COMM) 400/2017 & connected matter
    Signing Date:29.04.2026 Page 19 of 37
    10:39:10

    68. In Ssangyong Engg. & Construction Co. Ltd. v. NHAI, (2019)
    15 SCC 131 this Court specifically dealt with the 2015
    Amendment which inserted sub-section (2-A) in Section 34 of the
    1996 Act. It was held that “patent illegality appearing on the face
    of the award” refers to such illegality as goes to the root of matter,
    but which does not amount to mere erroneous application of law.
    It
    was also clarified that what is not subsumed within “the
    fundamental policy of Indian law”, namely, the contravention of a
    statute not linked to “public policy” or “public interest”, cannot be
    brought in by the backdoor when it comes to setting aside an award
    on the ground of patent illegality [ See Ssangyong Engg. &
    Construction Co. Ltd. v. NHAI
    , (2019) 15 SCC 131].
    Further, it
    was observed, reappreciation of evidence is not permissible under
    this category of challenge to an arbitral award [See Ssangyong
    Engg. & Construction Co. Ltd. v. NHAI
    , (2019) 15 SCC 131].
    Perversity as a ground of challenge

    69. Perversity as a ground for setting aside an arbitral award was
    recognised in ONGC Ltd. v. Western Geco International Ltd.,
    (2014) 9 SCC 263. Therein it was observed that an arbitral
    decision must not be perverse or so irrational that no reasonable
    person would have arrived at the same. It was observed that if an
    award is perverse, it would be against the public policy of India.

    70. In Associate Builders v. DDA, (2015) 3 SCC 49 certain tests
    were laid down to determine whether a decision of an Arbitral
    Tribunal could be considered perverse. In this context, it was
    observed that where:

    (i) a finding is based on no evidence; or

    (ii) an Arbitral Tribunal takes into account something irrelevant to
    the decision which it arrives at; or

    (iii) ignores vital evidence in arriving at its decision, such decision
    would necessarily be perverse.

    However, by way of a note of caution, it was observed that when a
    court applies these tests it does not act as a court of appeal and,
    consequently, errors of fact cannot be corrected. Though, a possible
    view by the arbitrator on facts has necessarily to pass muster as the
    arbitrator is the ultimate master of the quantity and quality of
    evidence to be relied upon. It was also observed that an award
    based on little evidence or on evidence which does not measure up
    in quality to a trained legal mind would not be held to be invalid on
    that score.

    71. In Ssangyong Engg. & Construction Co. Ltd. v. NHAI, (2019)
    15 SCC 131, which dealt with the legal position post the 2015
    Amendment in Section 34 of the 1996 Act, it was observed that a
    decision which is perverse, while no longer being a ground for
    challenge under “public policy of India”, would certainly amount
    to a patent illegality appearing on the face of the award. It was
    pointed out that an award based on no evidence, or which ignores
    vital evidence, would be perverse and thus patently illegal.
    It was
    Signature Not Verified
    Digitally Signed
    By:NEERU
    O.M.P. (COMM) 400/2017 & connected matter
    Signing Date:29.04.2026 Page 20 of 37
    10:39:10
    also observed that a finding based on documents taken behind the
    back of the parties by the arbitrator would also qualify as a decision
    based on no evidence inasmuch as such decision is not based on
    evidence led by the parties, and therefore, would also have to be
    characterised as perverse [ See Ssangyong Engg. & Construction
    Co. Ltd. v. NHAI
    , (2019) 15 SCC 131].

    72. The tests laid down in Associate Builders v. DDA, (2015) 3
    SCC 49 to determine perversity were followed in Ssangyong
    Engg. & Construction Co. Ltd. v. NHAI
    , (2019) 15 SCC 131 and
    later approved by a three-Judge Bench of this Court in Patel Engg.
    Ltd. v. North Eastern Electric Power Corpn. Ltd.
    , (2020) 7 SCC

    167.

    73. In a recent three-Judge Bench decision of this Court in DMRC
    Ltd. v. Delhi Airport Metro Express (P) Ltd., (2024) 6 SCC 357,
    the ground of patent illegality/perversity was delineated in the
    following terms: (SCC p. 376, para 39)
    “39. In essence, the ground of patent illegality is available
    for setting aside a domestic award, if the decision of the
    arbitrator is found to be perverse, or so irrational that no
    reasonable person would have arrived at it; or the
    construction of the contract is such that no fair or
    reasonable person would take; or, that the view of the
    arbitrator is not even a possible view. A finding based on
    no evidence at all or an award which ignores vital
    evidence in arriving at its decision would be perverse and
    liable to be set aside under the head of “patent illegality”.
    An award without reasons would suffer from patent
    illegality. The arbitrator commits a patent illegality by
    deciding a matter not within its jurisdiction or violating a
    fundamental principle of natural justice.”

    Scope of interference with an arbitral award

    74. The aforesaid judicial precedents make it clear that while
    exercising power under Section 34 of the 1996 Act the Court does
    not sit in appeal over the arbitral award. Interference with an
    arbitral award is only on limited grounds as set out in Section 34 of
    the 1996 Act. A possible view by the arbitrator on facts is to be
    respected as the arbitrator is the ultimate master of the quantity and
    quality of evidence to be relied upon. It is only when an arbitral
    award could be categorised as perverse, that on an error of fact an
    arbitral award may be set aside. Further, a mere erroneous
    application of the law or wrong appreciation of evidence by itself is
    not a ground to set aside an award as is clear from the provisions of
    sub-section (2-A) of Section 34 of the 1996 Act.

    75. In Dyna Technologies (P) Ltd. v. Crompton Greaves Ltd.,
    (2019) 20 SCC 1, paras 27-43, a three-Judge Bench of this Court
    held that courts need to be cognizant of the fact that arbitral awards
    are not to be interfered with in a casual and cavalier manner, unless
    the court concludes that the perversity of the award goes to the root
    Signature Not Verified
    Digitally Signed
    By:NEERU
    O.M.P. (COMM) 400/2017 & connected matter
    Signing Date:29.04.2026 Page 21 of 37
    10:39:10
    of the matter and there is no possibility of an alternative
    interpretation that may sustain the arbitral award. It was observed
    that jurisdiction under Section 34 cannot be equated with the
    normal appellate jurisdiction. Rather, the approach ought to be to
    respect the finality of the arbitral award as well as party’s autonomy
    to get their dispute adjudicated by an alternative forum as provided
    under the law.”

    49. In the aforesaid backdrop, the challenge raised by ACC in OMP
    (COMM) 400/2017 and the limited challenge laid by EPI in OMP
    (COMM) 408/2017 are required to be examined.

    I. ACC’S CHALLENGE:

    50. In OMP (COMM) 400/2017, ACC has confined its challenge to
    the findings rendered in respect of Claim Nos. 1, 2, 7 and 9, as well as
    Counter Claim Nos. 2, 3, 5 and 6, as adjudicated in the Impugned
    Award and the Modified Award.

    Binding Contract

    51. The principal contention urged by ACC is that no binding
    contract came into existence between EPI and ACC and that the MoM
    was merely a preliminary understanding and not a concluded contract.
    This contention stands rejected by the learned Arbitrator, and this
    Court finds no infirmity in the said finding. The relevant finding in the
    Impugned Award is reproduced hereunder:

    “10.0 WHETHER THERE WAS A VALID, LEGAL AND
    BINDING CONTRACT BETWEEN EPI AND ACC?

    10.1 Before taking up the claims and counter claims, it is necessary
    to determine if there was a valid, legal and binding contract
    between both parties. On a thorough perusal of documents
    submitted and the verbal arguments by both the parties it is noted
    that the first document submitted by EPI as Exhibit C-1 and by
    ACC as Enclosure page 1 is the letter dated 03.10.2003 from
    ACC in which ACC have clearly mentioned about EPI’s intention
    to participate in the tender for the subject work and ACC were
    keen to associate with EPI in execution of work on back to back
    basis. ACC agreed to submit EMD and all the securities as per
    Signature Not Verified
    Digitally Signed
    By:NEERU
    O.M.P. (COMM) 400/2017 & connected matter
    Signing Date:29.04.2026 Page 22 of 37
    10:39:10
    NIT and accept the conditions stipulated in the NIT. ACC
    requested EPI to issue a set of tender documents.
    10.2 Further, when the meeting was held on 03.10.2003, ACC
    agreed that all terms and conditions between EPI and SCCL shall
    be applicable “mutatis mutandis”. These were in addition to the
    terms and conditions of the tender invited by EPI. ACC agreed to
    engage sufficient experienced engineers and supervisory staff and
    construction plant and equipment for execution of the work from
    their existing stock or leasing/ purchasing of these equipment
    from market meaning that ACC had some of the machinery
    required for execution of such projects in their existing stock.
    ACC agreed to arrange all securities as per NIT and arrange all
    finance required for execution of project. It is expected that while
    submitting the tender, ACC would have known the scope of work,
    working conditions at site and all terms and conditions of work.
    No bidder shall give an offer for work of this magnitude without
    knowing the scope of work, site conditions and terms and
    conditions. It is important to note that even before receiving a
    letter dated 16.01.2004 from EPI requesting ACC to make
    arrangements for commencement of work, ACC vide their letter
    dated 17.12.2003 informed EPI that they had entered into a
    pretender tie up and to execute the work and started mobilizing
    their machinery. ACC stated that apart from the existing
    machinery ACC were planning to procure few new machinery. It
    is quite evident that ACC agreed to commence work even on the
    basis of the MOM.

    10.3 In a letter dated 27.02.2004 to EPI, ACC stated that they had
    made all arrangement for the finances for procurement of 45
    vehicles and other connected machinery except excavators and
    proposed to procure 4 excavators at an estimated cost of Rs. 4 cr.
    ACC requested EPI to enter into a lease agreement with the
    financer directly for a maximum exposer of Rs.3.5 cr. ACC
    mentioned that necessary agreement in the required format of EPI
    shall be signed by them or a clause to this effect may be included
    in the contract agreement.

    10.4 The Work Order was placed later by EPI on 14.05.2004 when
    the site work was in progress and this was accepted by ACC.
    During hearing held on 02.09.2016, ACC stated that they had
    started the work at site and subsequently EPI issued amendment
    to the order with the consent of ACC. In response to a quarry
    from me, ACC confirmed that the reasons given by the Claimant
    for issuing amendment were considered by ACC and then ACC
    gave their unconditional consent to EPI and ACC continued their
    work till termination. ACC mentioned that the problems started
    after termination of the contract.

    10.5 It may be noted from the above that if MOM or the letter from
    EPI asking for commencement of work were not valid, legal or
    binding, ACC were within their rights not to commence the work.

    Signature Not Verified
    Digitally Signed
    By:NEERU

    O.M.P. (COMM) 400/2017 & connected matter
    Signing Date:29.04.2026 Page 23 of 37
    10:39:10
    In fact, even before EPI’s letter dated 16.01.2004, ACC had
    intimated EPI about commencement of work and mentioned that
    they had started mobilizing their machinery. ACC have submitted
    a letter dated 20.12.2003 in which they informed EPI about the
    existing equipment and their plans to obtain on lease/procure new
    equipment for project implementation. This is in contradiction to
    the background information furnished by ACC where they stated
    that ACC did not have earth moving equipment, tippers and other
    infrastructure to take up the work and. EPI promised to help by
    financing the procurement of machinery etc.
    10.6 I find that even after placement of Work Order on 14.05.2005,
    ACC did not write to EPI or insist for any agreement or any other
    document. In letter dated 17.06.2004, ACC mentioned about
    equipment deployment, progress of work at site, financing of new
    equipment, proposal for withdrawal of 50% scope of work,
    secured advance etc. ACC informed that they had booked six
    TATA tippers available with M/s. Jasper Industries, Vijayawada.
    I have not been able to find any letter on record from ACC
    questioning the legality and validity of the MOM and the work
    order until termination of work of ACC.

    10.7 I have examined the records submitted by the parties and their
    oral arguments, The contents of the Writ Petition filed by EPI
    have also been examined. The relevant findings of the Hon’ble
    High Court are reproduced hereunder
    Quote
    ……….At the outset, it is to be noted that the Work Order deals
    with the scope and nature of the work, quantities and value of the
    work, work completion schedule, payment terms, rates of
    payment, penalty for delay in works apart from other conditions
    with regard to security deposits, forfeiture of deposits. It also
    provides for termination of work in case the progress of work is
    not satisfactory or if it is found essential to expedite the works.
    Thus, it is clear that all the rights and liabilities of the parties are
    regulated by the terms and conditions specified in the Work Order
    itself.

    ………..

    The Writ Petition was dismissed by the Hon’ble High Court
    Unquote
    Considering the above, I hold that the MOM between ACC & EPI
    dated 03.10.2003 and the Work Order No. DLI/CON/466/282
    dated 14.05.2004 are valid, legal and binding between the
    parties.”

    52. A perusal of the above-stated finding reflects a continuous
    chain of documents evidencing a concluded contractual relationship. It
    is undisputed that ACC itself approached EPI vide letter dated
    Signature Not Verified
    Digitally Signed
    By:NEERU
    O.M.P. (COMM) 400/2017 & connected matter
    Signing Date:29.04.2026 Page 24 of 37
    10:39:10
    03.10.2003 expressing its willingness to execute the work on a back-
    to-back basis, and in the meeting held on the same date, agreed to the
    essential terms governing the arrangement, including incorporation of
    SCCL terms mutatis mutandis.

    53. It is also not in dispute that ACC proceeded to act upon the
    arrangement even prior to execution of the formal work order, as is
    evident from its communication dated 17.12.2003 regarding
    mobilisation of machinery. In this regard, the work order dated
    14.05.2004 was subsequently accepted by ACC without demur and
    expressly incorporated the MoM, ACC’s offer, and the SCCL work
    order as part of the contractual framework.

    54. The learned Arbitrator has also rightly noticed the inconsistency
    in ACC’s stand. While disputing the binding nature of the MoM and
    the work order, ACC has simultaneously founded its counterclaims on
    the very same documents. Such a position cannot be sustained, as a
    party cannot both approbate and reprobate the same transaction. The
    finding of the learned Arbitrator that a valid and binding contractual
    framework existed between the parties is thus a finding based on the
    material on record and does not warrant interference under Section 34
    of the A&C Act.

    55. ACC’s further contention that no binding monthly targets
    existed, particularly in the absence of any revised schedule, does not
    merit acceptance. As rightly held by the learned Arbitrator, a binding
    contractual framework existed between the ACC and EPI. The work
    order dated 14.05.2004 expressly incorporates the SCCL schedule
    dated 26.03.2004, and the MoM, which stipulates that SCCL terms

    Signature Not Verified
    Digitally Signed
    By:NEERU
    O.M.P. (COMM) 400/2017 & connected matter
    Signing Date:29.04.2026 Page 25 of 37
    10:39:10
    would apply mutatis mutandis. Thus, the performance schedule
    formed an integral part of the contractual arrangement.

    56. This position is further reinforced by the conduct of ACC at the
    meeting held on 30.06.2004, where it acknowledged the shortfall in
    achieving the stipulated targets and proposed corrective measures. The
    subsequent Amendment No.1, providing for the recovery of penalties
    or liquidated damages imposed by SCCL from ACC, further
    underscores that the schedule and corresponding obligations were
    known to and accepted by ACC. The document constitutes an
    admission to the factual matrix as espoused by the Respondent and
    which stands accepted by the learned Arbitrator.

    57. In this view, the contention that the learned Arbitrator has
    created obligations dehors the contract is misconceived. The learned
    Arbitrator has merely construed and applied the contractual
    framework in light of the contemporaneous record and the conduct of
    the parties. The reliance placed by ACC on PSA Sical Terminals Pvt.
    Ltd.
    (supra) is, therefore, misplaced, as the said findings do not travel
    beyond the contractual framework but are firmly rooted within it.

    58. Having held so, the consequences of ACC’s failure to adhere to
    its performance obligations, as determined by the learned Arbitrator,
    now fall to be considered in the context of the claims under challenge.

    Claim No. 1

    59. The challenge to Claim No. 1 pertaining to penalty on the
    unexecuted quantity rests, at its core, on the submission that no
    binding monthly targets existed, and that the learned Arbitrator has, in
    effect, created contractual obligations by imposing a schedule that was
    never agreed upon between EPI and ACC.

    Signature Not Verified
    Digitally Signed
    By:NEERU

    O.M.P. (COMM) 400/2017 & connected matter
    Signing Date:29.04.2026 Page 26 of 37
    10:39:10

    60. The said submission has already been addressed and rejected in
    the context of the challenge to the binding nature of the contractual
    framework. Having held that the work order dated 14.05.2004, read
    with the MoM and the SCCL schedule dated 26.03.2004, constituted a
    binding contractual arrangement, and that the performance obligations
    thereunder were known, acknowledged and accepted by ACC, most
    evidently from its conduct at the meeting of 30.06.2004, the
    foundational premise of ACC’s challenge to Claim No. 1 does not
    survive.

    61. The learned Arbitrator, upon appreciating the material produced
    before him, has correctly noted that the reduction of ACC’s scope to
    145 LBCM consequent upon the meeting of 30.06.2004 did not
    exonerate ACC from its prior defaults.

    62. As is apparent, and which aspect is not contested, the said
    meeting was called precisely because of ACC’s persistent
    underperformance, and ACC’s agreement to the reduction constitutes
    an acknowledgement of its inability to carry out the Contract as
    originally agreed upon. The same cannot be construed to be in the
    nature of a release from any liability, but in fact, points in the contrary
    direction. Accordingly, the learned Arbitrator computed the penalty on
    the unexecuted quantity under ACC’s revised scope of 145 LBCM,
    arriving at Rs. 1,35,41,073.52 after setting off the penalty of Rs.
    23,16,379.60 already recovered from ACC’s running bills.

    63. ACC’s further submission that the learned Arbitrator proceeded
    on an imaginary schedule despite recording the absence of a revised
    schedule is also misconceived. Contrary to the said submission, it is
    noted that the learned Arbitrator proceeded on the SCCL schedule as

    Signature Not Verified
    Digitally Signed
    By:NEERU
    O.M.P. (COMM) 400/2017 & connected matter
    Signing Date:29.04.2026 Page 27 of 37
    10:39:10
    incorporated by the contractual framework, which was the only
    schedule in existence. The absence of a separately negotiated revised
    schedule as between EPI and ACC does not create a vacuum; it
    simply means that the incorporated SCCL schedule continued to
    govern. The amendment no.1 itself expressly stated that the revised
    schedule would be mutually agreed upon, which never happened, as
    the contractual arrangement was terminated before any such
    agreement could be reached.

    64. Giving effect to the aforesaid circumstances and in the absence
    of a revised schedule, the learned Arbitrator correctly applied the
    original targets as adjusted proportionately for the reduced scope,
    which is precisely the approach ACC had itself proposed at the
    30.06.2004 meeting when it undertook to achieve 6 LBCM per month.

    65. The contention that the imposition of a penalty is without a
    contractual basis is equally unsustainable. Clause 8 of Annexure-A to
    the SCCL work order dated 19.01.2004, incorporated mutatis
    mutandis into the EPI-ACC framework, which expressly provides that
    where the contractor fails to complete the total work, a penalty @
    15% will be levied on the value of work left unexecuted. It is noted
    that SCCL had already imposed penalties on EPI under this clause and
    adjusted the same from EPI’s bills. Therefore, the recovery of a
    proportionate share of those penalties from ACC, as the party whose
    underperformance caused the termination, is a straightforward
    application of the contractual framework and of the back-to-back
    principle that governed the parties throughout.

    66. This Court finds no merit in the contention that the learned
    Arbitrator has created any obligation dehors the contract. The

    Signature Not Verified
    Digitally Signed
    By:NEERU
    O.M.P. (COMM) 400/2017 & connected matter
    Signing Date:29.04.2026 Page 28 of 37
    10:39:10
    obligation in question is traceable to the contractual framework, and
    its existence as well as quantum stand supported by the material
    placed before the learned Arbitrator.

    67. Therefore, the present challenge, in substance, seeks a
    reappreciation of factual findings and does not warrant interference
    under Section 34 of the A&C Act.

    Claim No. 2

    68. As regards the challenge to Claim No. 2, which pertains to the
    differential cost arising from SCCL entrusting the unexecuted work to
    a third party at a higher rate, the learned Arbitrator, by holistically
    applying and considering the contractual scheme, has rightly held that
    the ACC is obliged to bear the said cost imposed upon EPI on a
    conditional basis. The recovery from ACC has been made contingent
    upon EPI having actually incurred, or being held liable to incur, such
    differential cost towards SCCL.

    69. The afore-said approach espoused by the learned Arbitrator is
    consistent with the back-to-back arrangement governing the parties,
    whereby ACC’s liability is co-extensive with that of EPI. By
    recognising the claim while deferring its enforceability to the
    crystallisation of liability, the learned Arbitrator has adopted a course
    that is both contractually consistent and equitable. The challenge to
    this finding, therefore, does not merit acceptance.

    Claim No. 7

    70. Moving to the challenge pertaining to Claim No. 7, ACC
    contends that in the absence of any concluded contractual
    arrangement, the learned Arbitrator has nonetheless granted the said
    claim in favour of EPI, thereby warranting interference under Section
    Signature Not Verified
    Digitally Signed
    By:NEERU
    O.M.P. (COMM) 400/2017 & connected matter
    Signing Date:29.04.2026 Page 29 of 37
    10:39:10
    34 of the A&C Act. The said premise having already been rejected,
    the challenge to this claim is rendered largely academic.

    71. Insofar as the security deposit of 1% of the value of work
    executed is concerned, it is relevant to note that the learned Arbitrator,
    in the Modified Award, has clarified that the amount of Rs.
    3,20,059.67 representing the said security deposit was already
    adjusted and dealt with under Claim No. 3, and the separate
    endorsement of that amount under Claim No. 7 was redundant and has
    accordingly been deleted. However, the said correction was not
    contested, and ACC itself agreed that there was confusion regarding
    the same and that the correction was warranted. Therefore, the net
    position under Claim No. 7 as it stands, in the Modified Award, is
    confined to the EMD of Rs. 50,00,000/-.

    72. As regards the EMD of Rs. 50 lakhs, the learned Arbitrator has
    directed that the mode of recovery shall abide by the verdict of the
    competent court before which the matter is pending. This Court finds
    no infirmity in that approach. The subject matter underlying the EMD
    claim is sub judice before a competent court, and this Court expresses
    no opinion thereon. The said direction to abide by the court’s verdict
    avoids the risk of conflicting determinations and is a sound and
    judicious course. Consequently, the challenge to Claim No. 7 does not
    merit acceptance.

    Claim No. 9

    73. To the extent Claim No. 9 is concerned, which pertains to
    arbitration costs, the learned Arbitrator, in the Impugned Award,
    directed that each party shall bear its own costs. However, the learned
    Arbitrator had, by order sheets forming part of the record, directed
    Signature Not Verified
    Digitally Signed
    By:NEERU
    O.M.P. (COMM) 400/2017 & connected matter
    Signing Date:29.04.2026 Page 30 of 37
    10:39:10
    that EPI, having paid the outstanding Arbitrator’s fee on behalf of
    ACC, would be entitled to recover the same.

    74. In the Modified Award, the learned Arbitrator quantified the
    said amount at Rs. 3,73,650/- along with interest. The contention of
    ACC that the learned Arbitrator could not have revisited the claim
    under Section 33 of the A&C Act does not merit acceptance. The said
    direction regarding recovery of the arbitrator’s fee is distinct from the
    general claim for costs. The same emanates from a specific direction
    recorded during the arbitral proceedings and forms part of the award.

    75. The said modification does not amount to a fresh adjudication
    of Claim No. 9 but is in the nature of giving effect to an already
    recorded direction by incorporating the quantified amount. Such a
    correction falls within the scope of Section 33 of the A&C Act.

    76. It is also not in dispute that ACC had failed to discharge its
    share of the Arbitrator’s fee despite opportunities and agreed
    schedules, necessitating payment by EPI to avoid disruption of the
    proceedings. In these circumstances, the direction permitting recovery
    of the said amount cannot be faulted.

    77. Accordingly, this Court is not inclined to interfere with the
    findings on Claim No. 9.

    Counter-Claim Nos. 2, 3, 5 and 6

    78. Turning to the counter-claims assailed by ACC, namely,
    Counter Claim Nos. 2, 3, 5 and 6, pertaining to loss on machinery,
    loss on workmen, loss on establishment, and loss on profit and
    goodwill, respectively, this Court finds that each has been rejected by
    the learned Arbitrator upon a considered appreciation of the evidence
    on record, and that none of the rejections discloses any perversity or
    Signature Not Verified
    Digitally Signed
    By:NEERU
    O.M.P. (COMM) 400/2017 & connected matter
    Signing Date:29.04.2026 Page 31 of 37
    10:39:10
    patent illegality warranting interference under Section 34 of the A&C
    Act.

    79. Insofar as Counter Claim No. 2 for loss on machinery is
    concerned, ACC claimed Rs. 1,99,53,000/- representing compensation
    allegedly paid to machinery and vehicle owners for three months
    following termination. Before the learned Arbitrator, ACC tendered
    cash vouchers in support. The learned Arbitrator subjected these
    vouchers to scrutiny and found them to be suspicious, as most of the
    payments were made in cash to unnamed or unidentified individuals,
    the vouchers were largely unsigned, and several did not even disclose
    the name of the payee to whom payment was allegedly made.

    80. At the same instance, ACC even failed to produce any hire
    agreements or contemporaneous letters engaging the machinery
    owners for the full project period, which would have been the
    foundational document to establish any legal obligation to pay
    compensation upon premature termination.

    81. In the absence of such evidence, the learned Arbitrator rightly
    declined to act upon the cash vouchers alone. Since the said finding is
    based on the evidentiary record perused sincerely by the learned
    Arbitrator and in view of the ruling in OPG Power (supra), this Court
    deems it appropriate not to interfere with the above finding.

    82. As regards Counter Claim No. 3, the learned Arbitrator, upon
    examining the lists of workers submitted by ACC, noticed a pattern of
    irregularity that goes to the root of the authenticity of the claim. Since
    identical names appeared in identical sequence across multiple
    categories of workers, the same individuals were listed as drivers,
    signalmen, tripper helpers, and water tank drivers simultaneously. The

    Signature Not Verified
    Digitally Signed
    By:NEERU
    O.M.P. (COMM) 400/2017 & connected matter
    Signing Date:29.04.2026 Page 32 of 37
    10:39:10
    total number of workmen also varied between the counter-claim
    statement and ACC’s supporting additional documents, with no
    explanation for the discrepancy. The promissory notes submitted by
    ACC purportedly reflecting loans taken to fund compensation
    payments were for amounts exceeding four times the quantum of the
    counter-claim itself, a disproportion that the learned Arbitrator found
    incapable of explanation.

    83. In these circumstances, the rejection of Counter Claim No. 3 is
    not merely a plausible view; it is the only reasonable conclusion
    available on such material. Therefore, a finding resting on fabricated
    or unreliable documents cannot be said to be perverse simply because
    it goes against ACC. Consequently, the challenge to this finding fails.

    84. In respect of Counter Claim No. 5, the learned Arbitrator has
    observed that such costs are ordinarily embedded in the quoted rates
    for execution of the work and cannot be claimed separately in the
    absence of cogent evidence. The documents relied upon by ACC,
    being unverified and unsupported, were found insufficient. The said
    finding is in accord with the contractual framework, and also based
    upon rigorous scrutiny of the material produced, and therefore does
    not warrant interference.

    85. Insofar as Counter Claim No. 6 is concerned, the learned
    Arbitrator has declined the claim in the absence of any material
    establishing that ACC would have earned the projected profits,
    particularly in view of its own underperformance.

    86. In the present case, no such evidentiary foundation was laid.
    ACC had consistently failed to meet the stipulated monthly targets
    and did not demonstrate the capacity to execute the work at the

    Signature Not Verified
    Digitally Signed
    By:NEERU
    O.M.P. (COMM) 400/2017 & connected matter
    Signing Date:29.04.2026 Page 33 of 37
    10:39:10
    required scale. In such circumstances, the claim of 15% profit on the
    balance work is speculative and unsupported by material on record.
    On the same footing, the claim for loss of goodwill is also
    unsupported by any material indicating reputational or commercial
    harm. In this light, the said approach of the learned Arbitrator is
    consistent with settled principles governing the award of damages and
    does not disclose any infirmity.

    87. In view of the settled principles laid down in OPG Power
    (supra), the rejection of the aforesaid claims and counter-claims does
    not suffer from perversity or patent illegality, nor does it disclose any
    infirmity on the touchstone of Section 28(3) or 31(3) of the A&C Act,
    and consequently does not warrant interference under Section 34 of
    the A&C Act thereof.

    II. EPI’S CHALLENGE:

    88. In OMP (COMM) 408/2017, EPI has confined its challenge to
    two aspects of the award as modified on 19.08.2017, the first relating
    to Counter Claim No. 4 and the second relating to the conditional
    nature of the award under Claim Nos. 1 and 8.

    Counter-Claim No. 4

    89. In respect of counter claim no.4, it was fairly conceded on
    behalf of ACC during the course of arguments that in the Impugned
    Award, the learned Arbitrator had consciously declined to adjudicate
    the said counter claim on the ground that the said issue stood sub
    judice before a competent court.

    Signature Not Verified
    Digitally Signed
    By:NEERU

    O.M.P. (COMM) 400/2017 & connected matter
    Signing Date:29.04.2026 Page 34 of 37
    10:39:10

    90. This Court notes that the learned Arbitrator, in the Impugned
    Award, restrained himself and consciously refrained from rendering
    any finding on the subject matter of Counter Claim No. 4.

    91. However, by way of the Modified Award, passed on an
    application under Section 33 of the A&C Act, the learned Arbitrator
    proceeded to award a sum of Rs. 10,08,949/- in favour of ACC under
    the said counter-claim. The scope of Section 33 thereof, however, is
    limited to correction of clerical, computational or similar errors, or to
    dealing with claims which were omitted from the award and does not
    extend to a case where the learned Arbitrator has consciously declined
    to adjudicate a claim, as such a decision cannot be treated as an
    omission within the meaning of said provision.

    92. In the present case, the non-adjudication of Counter Claim No.
    4 by the learned Arbitrator in the Impugned Award was deliberate and
    supported by reasons and was lawfully valid. The subsequent
    Modified Award of the said claim, under the guise of modification,
    amounts to a re-adjudication on merits, which falls outside the scope
    of Section 33 of the A&C Act.

    93. Considering the foregoing findings, as well as the statement
    made by learned counsel for ACC during the course of oral
    submissions fairly conceding the error in such adjudication by the
    learned Arbitrator, this Court is of the considered view that the
    modification dated 19.08.2017, to that extent, cannot be sustained in
    law. Accordingly, the challenge laid by EPI on this ground is upheld.

    Claim Nos. 1 and 8

    94. The second limb of challenge pertains to the conditional nature
    of the award under Claim Nos. 1 and 8, whereby the learned
    Signature Not Verified
    Digitally Signed
    By:NEERU
    O.M.P. (COMM) 400/2017 & connected matter
    Signing Date:29.04.2026 Page 35 of 37
    10:39:10
    Arbitrator directed that any recovery would be subject to the outcome
    of EPI’s proceedings with SCCL, coupled with a direction to furnish
    an undertaking to ACC.

    95. This challenge does not merit acceptance. The conditionality
    flows from the back-to-back arrangement governing the parties, as
    reflected in the MoM and the work order. The rights and liabilities of
    ACC were structured to be co-extensive with those of EPI vis-à-vis
    SCCL. In such a framework, any variation in the liability of EPI
    towards SCCL would necessarily impact the corresponding liability of
    ACC.

    96. The direction requiring EPI to furnish an undertaking ensuring
    proportionate adjustment is, therefore, consistent with the contractual
    arrangement and avoids unjust enrichment. The approach adopted by
    the learned Arbitrator is both equitable and in consonance with the
    contractual framework; therefore, no ground for interference is made
    out.

    CONCLUSION:

    97. In view of the foregoing discussions and analyses, OMP
    (COMM) 400/2017 filed by ACC is dismissed. The findings of the
    learned Arbitrator on the existence of a binding contractual
    framework, the applicability of performance obligations thereunder,
    and the claims and counter-claims assailed by ACC are either findings
    of fact, based on appreciation of evidence or plausible constructions of
    the contractual terms, and do not warrant interference under Section
    34
    of the A&C Act.

    98. Insofar as OMP(COMM) 408/2017 filed by EPI is concerned,
    the same is partly allowed. The modification dated 19.08.2017, to the
    Signature Not Verified
    Digitally Signed
    By:NEERU
    O.M.P. (COMM) 400/2017 & connected matter
    Signing Date:29.04.2026 Page 36 of 37
    10:39:10
    extent it awards a sum of Rs. 10,08,949/- together with interest of Rs.
    12,61,186/- in favour of ACC under Counter Claim No. 4, is set aside,
    being beyond the scope of Section 33 of the A&C Act. Save to the
    aforesaid extent, the said Petition is dismissed.

    99. In view of the aforesaid terms, both Petitions, being OMP
    (COMM) 400/2017 and OMP (COMM) 408/2017, along with pending
    applications, if any, stand disposed of.

    100. No order as to costs.

    HARISH VAIDYANATHAN SHANKAR, J.

    APRIL 27, 2026/jk

    Signature Not Verified
    Digitally Signed
    By:NEERU
    O.M.P. (COMM) 400/2017 & connected matter
    Signing Date:29.04.2026 Page 37 of 37
    10:39:10



    Source link

    LEAVE A REPLY

    Please enter your comment!
    Please enter your name here