Decathlon Sports India Private Limited vs Godrej Projects Development Limited on 28 April, 2026

    0
    47
    ADVERTISEMENT

    Bombay High Court

    Decathlon Sports India Private Limited vs Godrej Projects Development Limited on 28 April, 2026

    Author: Milind N. Jadhav

    Bench: Milind N. Jadhav

    2026:BHC-OS:10857
                                                                           901.IAL.9084.2026 & IAL.7684.20263.doc
    
      HARSHADA H. SAWANT
            (P.A.)
                                   IN THE HIGH COURT OF JUDICATURE AT BOMBAY
                                                  ORDINARY ORIGINAL CIVIL JURISDICTION
    
    
                                       INTERIM APPLICATION (L) NO. 9084 OF 2026
                                                         IN
                                         COMMERCIAL SUIT (L) NO. 7651 OF 2026
    
                                                        WITH
                                       INTERIM APPLICATION (L) NO. 7684 OF 2026
                                                         IN
                                        COMMERCIAL SUIT (L) NO. 7651 OF 2026
    
                    Decathlon Sports India Pvt Ltd                                        Applicant
                                                                                       .. (Org. Plaintiff)
                    IN THE MATTER BETWEEN
                    Decathlon Sports India Pvt Ltd                    .. Plaintiff
                               Versus
                    Godrej Projects Development Ltd & Anr.               Defendant
                                                 ....................
                    ï‚· Mr. Anoshak Davar a/w. Debarshi Dutta, Mr. Arjun Mookerjee, Mr.
                       Kushan Kode, Mr. Archit Viramani, Mr. Atul Gupta & Mr. Daneel
                       Pancras i/b Mr. Arcit Viramani, Advocates for Applicant / Plaintiff.
                    ï‚· Mr. Janak Dwarkadas and Mr. Girish Godbole, Senior Advocates
                      a/w. Mr. Yash Momaya, Mr. Ritish Desai, Mr. Rahul Dwarkadas,
                      Ms. Sukhada Wagle, Mr. Raushan Kumar, Mr. Arman Mulla & Ms.
                      Sonam Singh i/b M/s. RJD & Partners, Advocates for Defendant
                      No.1
                    ï‚· Mr. Gaurav Joshi, Senior Advocate a/w. Mr. Sheroy M.
                      Bodhanwalla, Ms. Sayali Puri, Mr. Akash Singh, Mr. Shreyas
                      Thakur i/b M/s. Bodhanwalla & Co. Advocates & Solicitors,
                      Advocates for Defendant No.2.
                                                            ...................
    
                                                           CORAM : MILIND N. JADHAV, J.
    
                                                           DATE          : APRIL 28, 2026
                    P.C.:
    
    

    1. Heard Mr. Davar, learned Advocate for Applicant / Plaintiff;

    Mr. Dwarkadas a/w. Mr. Godbole, learned Senior Advocates for

    SPONSORED

    Defendant No.1 and Mr. Joshi, learned Senior Advocate for Defendant

    No.2.

    1

    ::: Uploaded on – 28/04/2026 ::: Downloaded on – 29/04/2026 06:09:17 :::

    901.IAL.9084.2026 & IAL.7684.20263.doc

    2. By consent of parties Interim Application (L) No. 9084 of

    2026 and Application (L) No. 7684 of 2026 are both heard for interim

    reliefs. Common order is passed for disposing of both Interim

    Applications.

    3. Commercial Suit (L) No.7651 of 2026 is filed by Plaintiff on

    04.03.2026, inter alia, for decree of specific performance of Agreement

    to Lease (for short “ATL”) dated 17.09.2025, declaratory relief,

    mandatory injunction, perpetual injunction and damages suffered by

    Plaintiffs due to breaches of ATL.

    4. Interim Application (L) No.7684 of 2026 is filed by Plaintiff

    on 04.03.2026 along with Suit Plaint under Order XXXIX Rule 1 and 2

    and Order 50 read with Section 151 of the Code of Civil Procedure,

    1908 (for short “CPC“) for following interim reliefs:-

    (i) Ex-parte ad-interim injunction restraining Defendants
    from committing breach of ATL;

    (ii) Restraining Defendants from creating third party rights
    in respect of Leased premises;

    (iii) Appointment of Receiver over and in respect of Leased
    premises.

    5. Interim Application (L) No.9084 of 2026 is filed by Plaintiff

    on 11.03.2026 for seeking following Interim reliefs:-

    (i) Ex-parte ad-interim injunction restraining Defendant
    No.1 from committing breach of ATL;

    2

    ::: Uploaded on – 28/04/2026 ::: Downloaded on – 29/04/2026 06:09:17 :::

    901.IAL.9084.2026 & IAL.7684.20263.doc

    (ii) Restraining Defendant no.2 from making any changes
    or construction in respect of Leased premises and from
    acting in furtherance of Lease Deed dated 04.03.2026,
    also using the premises for any commercial purpose
    until disposal of the suit;

    (iii) Ex-parte order restraining both Defendants from making
    any alterations and directing them to maintain to status
    quo in respect thereof; and

    (iv) Appointment of Court Receiver over and in respect of
    Leased premises under Order XL of CPC.

    6. Brief facts relevant for deciding the above Interim

    Applications are as follows:-

    6.1. Applicant / Plaintiff evinced interest in acquiring the suit

    premises collectively admeasuring 761 sq.m. which included area on

    the Lower Ground and Ground Floor on lease and entered into a Term

    Sheet dated 18.03.2025 and thereafter Agreement to Lease dated

    17.09.2025 with Defendant No.1. in respect of suit property. This Suit

    property was 50% of the total commercial property developed by

    Defendant No.1 in its Chembur project. After both parties executed

    ATL and acted upon it, including performance of almost all contained

    in Condition Precedent-1 (CP-1), Defendant No.1 alleged that Plaintiff

    proposed further changes and alterations and refused to consider

    taking over the entire commercial area on lease. It is Plaintiff’s case

    that since it did not accede to Defendant No.1’s proposal and instead

    3

    ::: Uploaded on – 28/04/2026 ::: Downloaded on – 29/04/2026 06:09:17 :::

    901.IAL.9084.2026 & IAL.7684.20263.doc

    insisted upon execution of Lease Deed in terms of ATL in respect of

    suit premises (50% of the entire commercial area), Defendant No.1

    wrongfully “determined” the ATL in a pre-mediated and malafide

    manner, falsely alleging frustration of contract on the ground of ATL

    becoming “incapable of performance” and subsequently changing its

    stand to ATL becoming “commercially impracticable”.

    6.2. Plaintiff has argued that action of Defendant No.1 in issuing

    Letter of Intent within 7 days thereafter and executing Lease Deed

    within 15 days of termination with Defendant No.2 unequivocally

    establishes that Defendant No.1 designed termination of ATL in such

    circumstances to not only discharge itself from performance of its

    obligations under the ATL but clearly to defeat any order / injunctive

    relief that may be passed in Plaintiff’s favour in the present Suit and in

    turn procured better commercial terms by executing the Lease Deed

    with Defendant No.2 for the entire commercial area.

    6.3. By way of present Suit, Plaintiff has inter alia, sought

    declaration that ATL is valid and mandatory injunction directing

    Defendant No.1 to execute and register Lease Deed in favour of

    Plaintiff. Owing to Defendant No.1’s subsequent conduct of executing

    and registering Lease Deed dated 04.03.2026 with Defendant No.2,

    Plaintiff impleaded Defendant No.2 i.e. Titan Company Limited.

    Plaintiff further seeks cancellation of the registered Lease Deed dated

    4

    ::: Uploaded on – 28/04/2026 ::: Downloaded on – 29/04/2026 06:09:17 :::

    901.IAL.9084.2026 & IAL.7684.20263.doc

    04.03.2026 and injunctive reliefs against both Defendants for dealing

    with / altering the suit premises in furtherance of the registered Lease

    Deed.

    7. Mr. Davar, learned Advocate for Plaintiff has drawn my

    attention to the Term Sheet dated 18.03.2025 and ATL dated

    17.09.2025 and after taking me through the same has made the

    following submissions:-

    7.1. He would submit that Applicant / Plaintiff is entitled to

    interim relief of protecting the suit premises (admeasuring 761 sq.m.)

    because Defendant No.1’s action of unilaterally determining the ATL is

    fraudulent, wrongful and unlawful in the given circumstances. He

    would submit that ATL was not a determinable agreement as it did not

    confer any right or give option to Defendant No.1 to determine /

    terminate it at will, save and except in case of any breach or default if

    committed by Plaintiff. In support of this submission he has referred to

    and relied upon the decision of the Supreme Court in K. S. Manjunath

    & Ors. Vs. Moorasavirappa alias Muttanna Chennappa Batil.1

    7.2. He would submit that Defendant No.1 terminated ATL by

    notice dated 20.02.2026, acted without contractual authority and in

    direct violation of the terms of ATL, because, per clause 3.3.2

    Defendant No.1 had until 04.02.2026 to complete the pending CP-1

    1 2025 SCC OnLine SC 2378

    5

    ::: Uploaded on – 28/04/2026 ::: Downloaded on – 29/04/2026 06:09:17 :::

    901.IAL.9084.2026 & IAL.7684.20263.doc

    Condition which were infact duly completed and complied with. He

    would submit that it is wrongfully alleged by Defendant No.1 that

    Plaintiff wanted to resile from ATL and threatened termination which

    is ex facie false allegation especially after substantial investment and

    time spent for almost 14 months by both Plaintiff and Defendant No. 1

    on modifying / altering the Suit premises.

    7.3. He would submit that Defendant No.1’s plea of frustration is

    untenable in law because mere inconvenience styled as “performance,

    in its originally envisaged form, has become commercially

    impracticable” does not amount to “impossibility to perform” or

    “frustration” of the ATL. In support of this submission he has referred

    to and relied upon the decision of the Supreme Court in The Naihati

    Jute Mills Limited Vs. Khyaliram Jagannath.2 He would submit that

    ATL itself stipulated the possibility of intervening circumstances (vis-a-

    vis MMC approval and signage permission), which may have affected

    performance of ATL and provided consequences of such delay by

    giving Plaintiff option to terminate the ATL. He would submit that

    non-performance of terms and conditions of CP-1 would not destroy

    the basis and underlying object of ATL but parties herein were infact to

    execute the Lease Deed in respect of the suit premises. To support this

    submission, he has referred to and relied upon the decision of the

    Supreme Court in Satyabrata Ghose Vs. Mugneeram Bangur and

    2 [1968] 1 SCR

    6

    ::: Uploaded on – 28/04/2026 ::: Downloaded on – 29/04/2026 06:09:17 :::

    901.IAL.9084.2026 & IAL.7684.20263.doc

    Comapny and Ors.3 He would submit that Defendant No.1 cannot

    resile from ATL by citing its own failure to perform its obligation under

    the ATL, which prima facie is nothing but an excuse to enter into a

    better and lucrative contract with Defendant No. 2 to the exclusion of

    Plaintiff, which it did within 7 days of termination by repudiating the

    ATL unilaterally.

    7.4. He would submit that as per clause (ii) and (x) of CP-1

    Defendant No.1 was bound to provide, viz., revised sanctioned plan

    along with provisional fire NOC and development permission /

    commencement certificate; signage space as agreed and as specified.

    He would submit that Defendant No.1 wrongfully claimed inability to

    comply with aforesaid conditions and sought ATL to be frustrated. He

    would submit that Fire NOC and approval was already sanctioned by

    the Corporation and it was in place and all changes were executed by

    the Architect of Defendant No.1 for more than 4 months details of

    which are placed on record.

    7.5. He would submit that obtaining NOC from the Society for

    signage space was never a condition precedent in the ATL. He would

    submit that Defendant No.1 neither filed any supporting document to

    prove its contention that it had ever applied to the Society or Society

    had an issue with the signage spots or it had refused permission,

    rather Defendant No.1 by email dated 27.01.2026 had categorically
    3 AIR 1954 SC 44

    7

    ::: Uploaded on – 28/04/2026 ::: Downloaded on – 29/04/2026 06:09:17 :::

    901.IAL.9084.2026 & IAL.7684.20263.doc

    informed that it take care of the required NOC from the Society for

    putting up of signages, hence this could not be basis to justify

    termination of ATL. He would submit that in the Lease Deed dated

    04.03.2026 executed with Defendant No.2, Defendant No.1 agreed to

    comply with those very conditions for putting up of signages within 7

    days and also executed the Lease Deed and registered it, hence its

    argument that compliance of the said condition was impossible is

    vague therefore rendering its defence of frustration to be ex-facie false.

    7.6. He would submit that Defendant No.1 relied upon clause

    7.5.3 which conferred upon them right to terminate ATL irrespective

    of whether CP-1 requirements were fulfilled or not. He would submit

    that the said clause did not confer a right but rather recognized

    termination of ATL by Defendant No.1 at its own discretion and

    without any default by Plaintiff would in itself be a breach entitling

    Plaintiff to invoke the Bank Guarantee. He would submit that therefore

    Defendant No.1 filed S.C. Suit (L) No.2738 of 2026 seeking injunction

    against invocation of Bank Guarantee by Plaintiff. He would submit

    that on 23.02.2026 i.e. one day before the date of renewal of the Bank

    Guarantee, Defendant No.1 obtained ex-parte ad-interim injunction

    restraining Plaintiff from invoking the Bank Guarantee but Plaintiff

    had no intention to invoke and rather Plaintiff had called upon

    Defendant No.1 to renew it vide letter dated 21.02.2026. He would

    submit that hence act of Defendant No.1 in filing the Suit is indicative

    8

    ::: Uploaded on – 28/04/2026 ::: Downloaded on – 29/04/2026 06:09:17 :::

    901.IAL.9084.2026 & IAL.7684.20263.doc

    of the fact that it believed and accepted that its own attempt to

    terminate ATL without cause in fact conferred a right upon Plaintiff to

    invoke the Bank Guarantee. He would submit that therefore Defendant

    No.1 wrongly misinterpreted clause 7.5.3 of ATL and intention of the

    parties.

    7.7. He would submit that by Letter dated 21.02.2026 Plaintiff

    called upon Defendant No.1 to withdraw Letter dated 20.02.2026

    thereby evincing willingness to continue with ATL and execute the

    Lease Deed. He would submit that Plaintiff relied on assurances and

    representations of Defendant No.1 and substantially altered its

    position to its own detriment believing that the Suit premises would be

    handed over to it since the entire intention works were undertaken

    and completed as per sanctioned plan, thus balance of convenience is

    entirely in favour of Plaintiff. He would submit that if Suit Premises

    are not protected by way of an interim injunction and appointment of

    Receiver, then Plaintiff would suffer grave and irreparable loss and

    injury to its projected financial turnover of INR 24,50,00,000/- (in

    words Twenty-Four Crore Fifty Lakh only) for year one on its

    operation from the targeted store opening in June 2026 on the Leased

    Premises.

    7.8. He would submit that Defendant No.2 cannot plead equity

    and balance of convenience against Plaintiff and oppose interim relief

    9

    ::: Uploaded on – 28/04/2026 ::: Downloaded on – 29/04/2026 06:09:17 :::

    901.IAL.9084.2026 & IAL.7684.20263.doc

    in favour of Plaintiff, instead it can pursue appropriate action against

    Defendant No.1 for making false representation to it because it has

    argued that it had no knowledge / notice about interest of Plaintiff in

    the Suit premises. He would submit that this argument of Defendant

    No.2 is prima facie unbelievable and needs to be rejected because of

    the time line and Defendant No.1 offered Defendant No.2 a lucrative

    deal for the entire commercial premises for a longer period of time

    which suits Defendant No.2’s purpose. He would submit that both

    Defendant Nos. 1 and 2 have allegedly acted in a malafide manner by

    executing the Letter of Intent within 7 days of termination and

    registering the Lease Deed dated 04.03.2026 within 15 days after

    termination.

    7.9. He would submit that Defendant No.1 suppressed the fact of

    having obtained Fire NOC from the Deputy Chief Fire Officer on

    19.01.2026 in terms of complying with its own obligation under CP-1

    of the ATL as per the terms of draft Lease Deed exchanged on

    17.01.2026. He would submit that this conduct of Defendant No.1 is

    malafide for reasons best known to them. He would submit that

    Defendant No.1 was however repeatedly insisting and leading Plaintiff

    to re-negotiate additional terms even until 19.02.2026 while in

    contrast Defendant No.1 had already designed and made up its mind

    for imminent exit from the ATL and enter into a lucrative Lease Deed

    for the entire commercial premises. He would submit that this is

    10

    ::: Uploaded on – 28/04/2026 ::: Downloaded on – 29/04/2026 06:09:17 :::

    901.IAL.9084.2026 & IAL.7684.20263.doc

    pertinent from the fact that a Demand Draft dated 11.02.2026 was

    prepared for refunding the tranche 1 payment under ATL.

    7.10. He would submit that despite notifying awareness of

    Plaintiff’s willingness to execute Lease Deed, Defendant No.1 in

    complete disregard executed Lease Deed dated 04.03.2026 with

    Defendant No.2 for the entire commerical property admeasuring

    1456.16 sq.m. even while the ex-parte ad-interim injunction dated

    04.03.2026 was operative. He would submit that this resultantly

    allowed Defendant No.1 to obtain a more commercially profitable deal

    than the one envisaged under the ATL with Plaintiff disregarding the

    sanctity of commercial contract. He would submit that Defendant No.2

    has paid Interest Free Refundable Security Deposit of Rs.85 Lakhs on

    27.02.2026 to Defendant No.1 within 7 days from termination dated

    20.02.2026 and thereafter on 04.03.2026 i.e. merely within 5 days

    and thereafter both parties executed and registered the Lease Deed.

    7.11. He would submit that argument of Defendant No.2 that

    Lease Deed dated 04.03.2026 is a registered document and therefore,

    balance of convenience lies in its favour should not be accepted by

    Court as it is a fraudulent act on the part of both Defendants to clearly

    oust Plaintiff’s right under the ATL. He would submit that proviso to

    Section 49 of the Registration Act, 1908 allows unregistered document

    affecting immovable property, to be received as evidence of a contract

    11

    ::: Uploaded on – 28/04/2026 ::: Downloaded on – 29/04/2026 06:09:17 :::

    901.IAL.9084.2026 & IAL.7684.20263.doc

    in a suit for specific performance. He would submit that in case the

    Defendant No.2’s arguments are accepted, it would provide all parties

    that are similarly placed to take advantage of their own wrong.

    7.12. Next he would submit that according to ATL, the leased

    premises was to be used for trade and commerce and hence it falls

    within definition of “commercial dispute” under Section 2(1)(c) of the

    Commercial Courts Act, 2015. He would submit that this jurisdiction

    must be strictly construed in light of the Act’s object of speedy disposal

    of high-value commercial cases. He would submit that present dispute

    cannot fall under the domain of the Presidency Small Causes Court

    because according to Section 3(b) of the Maharashtra Rent Control

    Act, 1999, private limited companies having paid up share capital of

    one crore or more are exempted. In support of this proposition, he has

    referred to and relied upon the decision of the Madras High Court in

    the case of Ambalal Sarabhai Enterprises Ltd. Vs. K. S. Infraspace LLP.4

    7.13. Therefore, he would submit that it is clearly evident from the

    foregoing incidents that Defendant No.1 has attempted to wrongfully

    determine the ATL malafidely since negotiations between Defendant

    Nos. 1 and 2 could not have commenced and concluded merely within

    7 days. Hence, he would submit that in the aforesaid circumstances

    Plaintiff is entitled to interim reliefs in both Interim Applications as

    prayed for until final disposal of the Suit proceedings including
    4 (2020) 15 SCC 585

    12

    ::: Uploaded on – 28/04/2026 ::: Downloaded on – 29/04/2026 06:09:17 :::

    901.IAL.9084.2026 & IAL.7684.20263.doc

    appointment of Court Receiver.

    8. PER CONTRA, Mr. Dwarkadas, learned Senior Advocate for

    Defendant No.1 has drawn my attention to the two Affidavits-in-Reply

    dated 11.03.2026 in Interim Application (L) No.7684 of 2026 and

    dated 24.03.2026 in Interim Application (L) No.9084 of 2026 filed by

    authorized signatory of Defendant No.1 and has vehemently opposed

    grant of interim reliefs to the Plaintiff.

    8.1. He would submit that Interim Application (L) No. 9084 of

    2026 is filed by Plaintiff with the sole object of (i) expanding the scope

    of the ex-parte ad-interim order dated 04.03.2026 which was obtained

    without giving notice to Defendant No.1 and has in any event now

    been rendered infructuous; (ii) to bring pressure upon Defendant No.2

    by seeking to restrain it from exercising its legitimate leasehold rights

    under a duly executed registered Lease Deed; and (iii) for creating a

    false impression before this Court that Defendant No.1 has acted in

    defiance of the ex-parte order when the truth is that the Lease Deed

    with Defendant No.2 was executed and registered prior to service of

    the ex-parte order upon Defendant No.1.

    8.2. He would submit that ATL dated 17.09.2025 between

    Plaintiff and Defendant No.1 did not create, transfer, assign, or vest

    any enforceable right, title, interest or possession in the premises in

    favour of the Plaintiff as ATL was determinable, conditional and an

    13

    ::: Uploaded on – 28/04/2026 ::: Downloaded on – 29/04/2026 06:09:17 :::

    901.IAL.9084.2026 & IAL.7684.20263.doc

    executory arrangement and not a concluded lease which merely

    contemplated its future execution subject to prior fulfillment of all 16

    terms and conditions of CP-1. He would submit that Plaintiff has

    admitted in its pleadings that it was never delivered possession of the

    premises rather it had remained in the lawful possession and control of

    its owner i.e. Defendant No.1, hence Plaintiff is not entitled to restrain

    either Defendant No.1 or Defendant No.2 from exercising their lawful

    rights therein.

    8.3. He would submit that as per Section 14(d) of the Specific

    Relief Act, 1963 (for short “said Act”) ATL was determinable in nature,

    hence it stood lawfully determined by Defendant No.1 vide its letter

    dated 20.02.2026. He would submit that Section 41(e) of the said Act

    bars grant of injunction to prevent breach of a contract, the

    performance of which cannot be specifically enforced, hence interim

    application seeking injunctive relief is misconceived and contrary to

    law. He would submit that the ATL was incapable of performance on

    account of non-fulfillment of terms and conditions of CP-1 within the

    stipulated timeline and circumstances beyond control of the parties

    and thus it stood frustrated within the meaning of Section 56 of the

    Indian Contract Act, 1872 and hence became void and unenforceable

    in law.

    14

    ::: Uploaded on – 28/04/2026 ::: Downloaded on – 29/04/2026 06:09:17 :::

    901.IAL.9084.2026 & IAL.7684.20263.doc

    8.4. He would submit that Lease Deed dated 04.03.2026 between

    Defendant Nos. 1 and 2 was executed and payment of registration fees

    for same was generated at 13:45 hrs on the same day followed by its

    registration in the office of the Joint Sub-Registrar, Mumbai-13 at

    02:50 PM. He would submit that Defendant No.1 was served with the

    ex-parte order dated 04.03.2026 via email on the same day at 08:07

    PM. He would submit that Defendant No.1 being unaware of filing of

    present Suit proceedings by Plaintiff, nor being served upon with any

    notice regarding the proceedings or notice or the ex-parte order,

    entered into a commercial transaction with Defendant No.2 in the

    ordinary course of business pursuant to Letter of Intent dated

    27.02.2026 for execution and registration of the Lease Deed.

    8.5. He would submit that Defendant No.2 being a reputed

    publicly listed company and a subsidiary of the Tata Group became a

    bonafide lessee through the Lease Deed for a term of 21 years and

    paid a part of the security deposit of Rs.85,00,000/- on execution of

    the Letter of Intent dated 27.02.2026. He would submit that Plaintiff’s

    allegation of execution of Lease Deed being “pre-mediated” and done

    with intent to defeat Plaintiff’s rights is wholly baseless because ATL

    was already lawfully determined on 20.02.2026 alongwith refund of

    security deposit to Plaintiff. He would submit that it is well settled law

    that once third-party rights are created in favour of a bonafide party

    under a registered instrument, courts ought to exercise extreme

    15

    ::: Uploaded on – 28/04/2026 ::: Downloaded on – 29/04/2026 06:09:17 :::

    901.IAL.9084.2026 & IAL.7684.20263.doc

    restraint in granting injunctive relief that would disturb such rights

    and therefore mere coincidence of dates cannot give rise to any

    inference of malafides.

    8.6. He would submit that ex-parte injunction order cannot

    operate retrospectively so as to invalidate the rights and transactions

    that were lawfully concluded prior to service of such order upon the

    party sought to be restrained and is an afterthought designed to

    prejudice Defendant No.2 and the same cannot be regarded as being in

    violation of said order. He would submit that Lease Deed dated

    04.03.2026 creates a valid leasehold interest in favour of Defendant

    No.2 which is a registered document and carries presumption of

    validity under Section 35 of the Indian Registration Act, 1908 and

    Section 79 of the Indian Evidence Act, 1872, hence such a Lease Deed

    cannot be set aside or rendered inoperative merely on the basis of

    allegations made in an interim application. He would submit that

    challenge to such a Lease Deed could have been done in substantive

    proceedings and not through interim application.

    8.7. Next, he would submit that ATL is incapable of specific

    performance as it falls within the ambit of Section 14(b) of the said

    Act which stipulates that performance of a contract that involves

    performance of a continuous duty which the Court cannot supervise,

    cannot be specifically enforced. He would submit that terms and

    16

    ::: Uploaded on – 28/04/2026 ::: Downloaded on – 29/04/2026 06:09:17 :::

    901.IAL.9084.2026 & IAL.7684.20263.doc

    conditions in CP-1 contemplated under the ATL were not acts which

    could be simply enforced, however it envisaged a series of interrelated

    and sequential obligations, viz., (i) completion of construction and

    fitout works; (ii) procurement of necessary sanctions and building

    permissions; (iii) execution of structural and non-structural

    obligations; (iv) permission for installation of signages at various

    locations, which were dependent upon acts and decisions of multiple

    third parties, including regulatory authorities, municipal bodies and

    the co-operative housing society, over none of whom this Court could

    have exercised any effective supervision or control.

    8.8. He would submit that appointment of a Court Receiver

    would not cure the issue of continuous supervision contemplated

    under Section 14(b) of the said Act as it would entail Court Receiver

    engaging in ongoing negotiations and dealing with multiple third-party

    authorities independent of the jurisdiction of this Court which would

    be infructuous at this stage. He would submit that this would

    inevitably draw this Court’s attention into a protracted exercise of

    supervision which is precisely the situation above provision is designed

    to prevent. He would submit that it is well-settled law that courts of

    equity decline to grant specific performance where execution of the

    decree would require the court to supervise series of acts over an

    extended period of time. Therefore, he would submit that appointment

    of Court Receiver would be disproportionate and mere abuse of the

    17

    ::: Uploaded on – 28/04/2026 ::: Downloaded on – 29/04/2026 06:09:17 :::

    901.IAL.9084.2026 & IAL.7684.20263.doc

    process as there is no threat of waste, damage, alienation or

    dissipation of property that could justify such appointment.

    8.9. He would submit that by virtue of Section 14(b) the ATL is

    incapable of specific performance and therefore grant of injunction to

    prevent breach of a contract that cannot be specifically enforced is

    barred under Section 41(e) of the said Act. Moreover, the ATL is a

    determinable contract according to Section 14(d) of the said Act.

    8.10. He would submit that Plaintiff has failed to make out case

    under Order XXXIX Rules 1 and 2 of CPC so as to satisfy any of the

    settled parameters for grant of interim relief, viz., (I) prima facie case;

    (ii) balance of convenience in its favour; and (iii) likelihood of

    irreparable injury. He would submit that balance of convenience is

    rather in favour of Defendant No.1 in the present case because Plaintiff

    was never in possession of the Leased Premises and did not invest any

    capital expenditure in the same. In contrast, he would submit that

    Defendant No.1 invested approximately Rs.3,00,00,000/- (Rupees

    Three Crores Only) towards fulfillment of the CP-1 requirement. He

    would submit that Defendant No.2 has entered into a binding

    registered Lease Deed is entitled to therefore take possession and

    commence its business operations.

    8.11. He would submit that despite absence of any subsisting

    contractual right in favour of Plaintiff, its loss, if any, would be purely

    18

    ::: Uploaded on – 28/04/2026 ::: Downloaded on – 29/04/2026 06:09:18 :::

    901.IAL.9084.2026 & IAL.7684.20263.doc

    commercial and financial which would be fully quantifiable whereas

    injunction would place restraint on proprietary rights of Defendant

    No.1 and contractual rights of Defendant No.2 causing significant and

    irreparable prejudice to both of them.

    8.12. He would submit that in present dispute since it seeks

    recovery of possession of the premises, it falls within the local limits of

    exclusive jurisdiction of the Small Causes Court, Mumbai as per

    Section 41 of the Presidency Small Cause Courts Act, 1882 and not

    within the jurisdiction of this Court and hence on this ground

    application is liable to be dismissed. On the basis of the above

    submissions he would persuade the Court to reject interim relief to

    Plaintiff.

    9. Mr. Joshi, learned Senior Advocate for Defendant No.2

    would submit that Defendant No.2 being a bonafide party to the lease

    with Defendant No.1 cannot be deprived of its right, title and interest

    subsisting under the registered Lease Deed dated 04.03.2026. He

    would submit that Plaintiff did not opt to register the captioned

    proceedings as a lis pendens under Section 52 of the Transfer of

    Property Act, 1882 read with Section 18(ee) of the Registration Act,

    1908 which enables registration of notices for pending suits providing

    constructive notice to potential buyers. He would submit that Plaintiff

    failed to register the ATL possibly owing to stamp duty considerations

    19

    ::: Uploaded on – 28/04/2026 ::: Downloaded on – 29/04/2026 06:09:18 :::

    901.IAL.9084.2026 & IAL.7684.20263.doc

    and also to impute any prior notice whether actual or constructive on

    part of Defendant No.2. He would submit that Plaintiff cannot seek

    relief of specific performance against Defendant No.2 who had no

    knowledge of the alleged prior ATL, also Plaintiff nowhere in its Plaint

    has pleaded that Defendant No.2 had prior knowledge of the ATL. In

    support of this proposition, he has referred to and relied upon the

    decision of the Madras High Court in the case of P Retnaswamy Vs. A

    Raja & Anr.5

    9.1. He would submit that any interim or ad-interim relief as

    against Defendant No.2 would seriously and irreversibly impair its

    contractual rights under the registered Lease Deed dated 04.03.2026

    because Defendant No.2 has paid stamp duty amount of

    Rs.94,10,000/- together with registration charges of Rs.30,000/-,

    initial security deposit amount of Rs.85,00,000/- with balance security

    deposit amount of Rs.2,97,50,000/- which was due to be paid within

    10 days from the date of registration of the Lease Deed.

    9.2. He would submit that according to the “priority principle”

    laid down under Section 50 the Registration Act, 1908, registered

    documents take precedence over unregistered documents when both

    relate to the same property. Therefore, he would submit that

    registered Lease Deed dated 04.03.2026 prevails over the ATL dated

    17.09.2025. He would submit that an Agreement to Lease must be
    5 2001-3-L.W.603

    20

    ::: Uploaded on – 28/04/2026 ::: Downloaded on – 29/04/2026 06:09:18 :::

    901.IAL.9084.2026 & IAL.7684.20263.doc

    distinguished in fact and in law from an executed and registered Lease

    Deed which has been explained in the decision of the Supreme Court

    in the case of Ramnath Agrawal & Ors. Vs. Food Corporation of India

    & Ors6.

    9.3. He would submit that Plaintiff has failed to make out any

    prima facie case against Defendant No.2 for grant of relief because

    there is absence of pleading or prior notice proving awareness of prior

    agreement which is a foundational requirement under Section 19(b) of

    the said Act and hence no relief can be claimed by Plaintiff against

    Defendant No.2. He would submit that settled tests for grant of relief

    are also not satisfied by Plaintiff. To conclude his argument, he would

    submit that balance of convenience is decisively in favour of

    Defendant No.2 whose contractual and possessory rights would be

    prejudiced by any order of restraint causing irreparable injury to

    Defendant No.2.

    9.4. He would submit that Plaintiff was admittedly never in

    possession of the leased premises and even if its claim is sustainable at

    any point of time during trial, it is compensable in damages. He would

    submit that in the aforesaid circumstances Defendant No.2’s peaceful

    possession and lawful enjoyment of the leased suit premises under

    registered Lease Deed dated 04.03.2026 be undisturbed and the

    Interim Applications be dismissed in limine.
    6 (2020) 19 SCC 355

    21

    ::: Uploaded on – 28/04/2026 ::: Downloaded on – 29/04/2026 06:09:18 :::

    901.IAL.9084.2026 & IAL.7684.20263.doc

    10. I have heard Mr. Davar, learned Advocate for Plaintiff; Mr.

    Dwarkadas and Mr. Godbole, learned Senior Advocates for Defendant

    No.1 and Mr. Joshi, learned Senior Advocate for Defendant No.2 and

    with their able assistance perused the record of the case. Submissions

    made by the learned Senior Advocates and Advocate appearing for the

    respective parties have received due consideration of the Court.

    11. The facts in the present case are in a narrow compass.

    Admittedly Plaintiff and Defendant No.1 executed Term Sheet dated

    18.03.2025 and Agreement to Lease dated 17.09.2025 whereby

    Plaintiff decided to take on lease. Suit premises admeasuring 633

    sq.m. (equivalent to 6814 sq.ft.) and 128 sq.m. (equivalent to 1378

    sq.ft.) situated in the basement and ground floor of the subject

    building, collectively admeasuring appropriately 761 sq.m. (8192 sq.

    ft.) alongwith appurtenant area, 24 car parking spaces and rights to

    use the common area. It is seen that these suit premises form a part of

    the larger commercial area spread out over the Lower Ground, Ground

    and 1st Floor of the project totally admeasuring 1456.16 sq.m. (15,674

    sq.ft.).

    12. What is observed is that in view of the ATL between Plaintiff

    and Defendant No.1, the balance area admeasuring 695.16 sq.m.

    (equivalent to 7482 sq.ft.) on the Ground and 1st Floor remained

    vacant and status of this area has led to the present lis between the

    22

    ::: Uploaded on – 28/04/2026 ::: Downloaded on – 29/04/2026 06:09:18 :::

    901.IAL.9084.2026 & IAL.7684.20263.doc

    parties. It appears that after execution of the Term Sheet and ATL and

    during fructification of 14 out of the 16 conditions contained in CP-1,

    Defendant No.1 proposed alteration of terms and conditions of ATL by

    insisting that Plaintiff should in addition to the Suit premises, also take

    on lease the balance area. This is Plaintiff’s case before the Court and it

    is also not denied by Defendant No.1. According to Plaintiff, it declined

    the proposal of Defendant No.1 and instead insisted upon execution of

    Lease Deed in terms of the ATL for the suit premises only.

    13. According to Plaintiff, Defendant No.1 therefore wrongfully

    ‘determined’ the ATL in a pre-mediated and malafide manner, falsely

    alleging frustration of contract on the ground of the ATL becoming

    ‘incapable of performance’ and subsequently informing Plaintiff that

    ATL had been ‘commercially impracticable’. It is seen that on the date

    when Plaintiff obtained ex-parte interim injunction i.e. on 04.03.2026

    on the same date, Defendant Nos.1 and 2 entered into a Lease Deed

    for the entire larger premises admeasuring 1456.16 sq.m..

    14. Grievance of Plaintiff is that by virtue of the Term Sheet of

    ATL dated 17.09.2025 and ATL not been a determinable Agreement,

    plea of fructification of the ATL is untenable in law and the conduct of

    Defendant No.1 is prima facie malafide. On the other hand, contention

    of Defendant No.1 is that the ATL was an unregistered document

    which became ‘incapable of performance’ due to two specific

    23

    ::: Uploaded on – 28/04/2026 ::: Downloaded on – 29/04/2026 06:09:18 :::

    901.IAL.9084.2026 & IAL.7684.20263.doc

    conditions contained in CP-1 being ‘incapable of performance’ and

    execution of the registered Lease Deed in respect of the entire

    premises in favour of Defendant No.2 being a registered document will

    take precedent over any substantive right of Plaintiff and the highest

    Plaintiff would be entitled to is damages and compensation in terms of

    money. Even though ATL maybe be unregistered agreement it is

    crucial to note that it has been fully acted upon by parties.

    15. The facts in the present case are with respect to rights of the

    parties as stated in the ATL which governed their actions. Defendant

    No.2 has no nexus / privity with Plaintiff qua the suit premises. Hence,

    it would be convenient to look into the specific clauses of the ATL to

    understand the substantive right of parties and the facts and

    circumstances which trasnpired leading to determination of ATL. Copy

    of the ATL is appended below Exhibit ‘C’ at page No.168 in the Suit

    plaint. Both Plaintiff and Defendant No.1 have heavily relied upon

    various terms and conditions and clauses of ATL in support of their

    respective submissions.

    16. Plaintiff, Defendant No.1 and Defendant No.2, all three

    parties in their own right are leading companies in their own right.

    There is elaborate material and pleadings placed on record by all 3

    companies which in my opinion need not be gone into for the present

    adjudication. The fundamental facts, inter alia, leading to execution of

    24

    ::: Uploaded on – 28/04/2026 ::: Downloaded on – 29/04/2026 06:09:18 :::

    901.IAL.9084.2026 & IAL.7684.20263.doc

    the Term Sheet and ATL between Plaintiff and Defendant No.1 are not

    in dispute. Infact on reading the entire paper, I am of the opinion that

    until 19.02.2026, there was nothing on the horizon for determination

    of the ATL, and for the first time on 19.02.2026, Defendant No.1 made

    know its intention of determining the ATL not on the basis of reasons

    stated in the Termination Letter dated 20.02.2026 but on the Minuites

    of Meeting held on 19.02.2026 itself. Similarly, the registered Lease

    agreement dated 04.03.2026 executed between Defendant No.1 and

    Defendant No.2 on the other hand is also not in dispute. Repercussions

    of termination of ATL by Defendant No.1 and immediate execution

    and registration of the lease deed between Defendant No.1 and

    Defendant No.2 on 04.03.2026 (by giving Letter of Intent on

    27.02.2026) has its genesis in the conduct of Defendant No.1.

    17. Record shows that since January 2025 Plaintiff evincing

    interest in taking over the suit premises on lease admeasuring 761

    sq.m. (8192 sq.ft.) distributed between ground floor (128 sq.m.) and

    lower ground floor (633 sq.m.). his stance of Plaintiff is consistent

    throughout. According to Plaintiff it took a strategic business decision

    to develop one commercial store in Defendant No.1’s project known as

    Godrej RKS in Chembur area since it was Plaintiff’s requirement was to

    develop a store of about 8000 sq.ft. which suited its plans and

    investments. For this Plaintiff decided to shut down its two other

    flagship stores in Mumbai situated at Bandra and Worli and

    25

    ::: Uploaded on – 28/04/2026 ::: Downloaded on – 29/04/2026 06:09:18 :::

    901.IAL.9084.2026 & IAL.7684.20263.doc

    commission a new store from the suit premises in Chembur area

    considering the area’s location and enormous potential and it being a

    prime catchment area for Plaintiff’s business.

    18. Plaintiff therefore executed Term Sheet dated 18.03.2025

    followed by ATL dated 17.09.2025 and decided to take the suit

    property on lease i.e. property situated on the ground and lower

    ground floor to the extent of 761 sq.m. (8192 sq.ft.) out of the total

    developed commercial area (15843 sq.ft.). The aforesaid two

    documents executed between parties are replete with humongous

    correspondence prior and later to their execution over a period fo 14

    months which are all placed on record. Fundamental terms of the

    aforementioned ATL being Defendant No.1 receiving Rs.21 lakh as

    monthly lease rent for lease of suit premises along with 24 reserved

    car parking slots. Tenure agreed between parties was for 10 years with

    escalation clause.

    19. It is seen that, Defendant No.1 on 20.02.2026 terminated

    ATL dated 17.09.2025 on the ground that 2 out of the 16 CP – 1

    conditions became incapable of performance and the ATL was

    therefore frustrated. Defendant No.1 pleaded that unfulfilled condition

    No.1 pertained to non recept pf Municipal approval under Section 342

    of MMC Act which could not be obtained due to return of file by the

    Municipal Officer whereas unfulfilled condition No.2 pertained to no

    26

    ::: Uploaded on – 28/04/2026 ::: Downloaded on – 29/04/2026 06:09:18 :::

    901.IAL.9084.2026 & IAL.7684.20263.doc

    permission received from the Co – operative Housing Society for

    installation of signages which it refused to grant to the parties. Copy of

    Termination Letter is appended at page No. 917 of the Suit Plaint.

    Paragraph Nos. 1 to 5 thereof are relevant and reproduced below for

    immediate reference.

    “1. We refer to the Agreement to Lease dated 17 September 2025
    executed between Godrej Projects Development Limited (therein
    “Lessor”) and Decathlon Sports India Private Limited (therein
    “Lessee”) in respect of the Leased Premises referred above, situated
    at Godrej RKS, Mumbai (“Agreement”).

    2. Clause 3 of the Agreement contemplates the fulfilment of the
    Conditions Precedent within the stipulated agreed timelines,
    including Condition Precedent – 1, as more particularly set out in
    Annexure D of the Agreement. It was further mutually agreed
    between the Parties that upon completion of Condition Precedent –
    1, the Parties shall proceed to execute the final Lease Deed.
    Accordingly, fulfilment of all the Conditions Precedent- 1 within the
    stipulated timelines constitutes a mandatory precondition for
    execution of the final Lease Deed.

    3. Despite our bona fide efforts and due diligence, we regret to
    inform you that we are unable to fulfil certain crucial Conditions
    Precedent – 1, namely: provision of revised sanction plans with fire
    NOC & development permission/commencement certificate (clause

    ii) and provision of signage spaces ( clause X). as their fulfilment is
    presently impeded due to certain practical and regulatory
    constraints that are beyond our reasonable control and as a natural
    corollary, the Agreement stands frustrated.

    4. Thus, in order to place on record the factual and practical
    constraints faced by us in complying with the said Conditions
    Precedent – 1, and after careful consideration of the circumstances,
    we regret to inform you that we are constrained to determine the
    Agreement at this stage, as the same has become incapable of being
    performed. Accordingly, we hereby notify you that we shall not be
    proceeding further with the execution of the Final Lease Deed.

    5. In view thereof, we hereby intimate our decision to determine
    the Agreement with immediate effect.”

    20. From paragraph No.3 Defendant No.1’s case as pleaded and

    argued is that it has acted bonafide and with due diligence but

    fulfillment of the two conditions was beyond its control since it had no

    27

    ::: Uploaded on – 28/04/2026 ::: Downloaded on – 29/04/2026 06:09:18 :::

    901.IAL.9084.2026 & IAL.7684.20263.doc

    authority to compel the Municipal Authority to approve revised

    drawings with all revisions under Section 342 of MMC Act or compel

    the Co – operative Housing Society to grant permissions to put up

    signages as required by Plaintiff. These are the only two grounds on

    which Defendant No.1 terminated the ATL on 20.02.2026. However

    juxtaposed with the above happening of above events between

    Plaintiff and Defendant No.1, it is seen that Defendant No.1

    immediately thereafter on 23.02.2026 filed a Suit under Sections 34,

    37 and 38 of the Specific Relief Act against Plaintiff to restrain Plaintiff

    from invoking the bank guarantee which was to otherwise expire on

    24.02.2026.

    21. On 23.02.2026, Defendant No.1 obtained injunction from

    invoking the bank guarantee. Thereafter on 27.02.2026 i.e. within 7

    days of termination of ATL, Defendant No.1 issued Letter of Intent to

    Defendant No.2. agreeing to enter into lease for the entire

    commercially developed area (1471.86 sq.m. ~ 15843 sq.ft.) in the

    same project at RKS Chembur (which included the area under the

    ATL). This letter of intent was fructified into a lease document which

    was executed and registered on 04.03.2026 between Defendant No.1

    and Defendant No.2. It is seen that the tenure agreed between

    Defendant No.1 and Defendant No.2 in it was for 21 years at the rate

    of Rs.42.5 lakhs lease rent per month with 39 reserved car parking

    slots. This area admittedly included the suit premises admeasuring 761

    28

    ::: Uploaded on – 28/04/2026 ::: Downloaded on – 29/04/2026 06:09:18 :::

    901.IAL.9084.2026 & IAL.7684.20263.doc

    square meters being part thereof. Present suit was filed on 04.03.2026

    and this Court was moved for urgent ad interim relief when on that

    date the following order was passed:-

    “1. Not on Board. Mentioned by way of filing praecipe dated
    04.03.2026. Perused the praecipe.

    2. Heard Mr. Daver, learned Advocate for Plaintiff. He
    mentions exigency due to which ad-interim relief is pressed by him.

    3. At the outset, Mr. Daver seeks leave to amend and correct
    factual error in paragraph No.67 of the suit plaint. Necessary
    amendment is permitted to be carried out within a period of one
    week from today. Reverification stands dispensed with.

    4. Plaintiff executed Agreement to Lease (for short ‘ALT’) dated
    17.09.2025 which had all necessary clauses in place. According to
    Mr. Daver, one of the key clause namely clause No.2 required
    Defendant to obtain fire No-Objection Certificate and
    Commencement Certificate for the subject premises. Amount of Rs.
    42,00,000/- was received by Defendant from Plaintiff as deposit
    towards performance of the aforesaid condition.

    5. He would submit that on 17.01.2026, fire No-Objection
    Certificate was received but it was not informed to Plaintiff.
    Plaintiff did suspect that there would be an attempt to resile from
    the ALT. On the following day Defendant addressed letter to
    Plaintiff stating that they wanted to negotiate better commercial
    terms. Since the ALT was executed Plaintiffs had undertaken
    certain steps. However the entire scheme and plan of Plaintiff got
    stalled.

    6. On 20.02.2026 read with further letter dated 23.02.2026
    Defendant resiled and determined the ALT. Mr. Daver informs the
    Court that the second pre-condition regarding issuance of
    Commencement Certificate is almost fructified. He would also
    submit that Defendant had addressed a letter to Plaintiff that all
    terms of the ALT were accepted by them and therefore the conduct
    of Defendant to resile from the ALT Contract is illegal and
    incorrect.

    7. In that view of the matter he would submit that this Court
    be pleased to grant ex parte ad-interim injunction restraining
    Defendant from creating third party right or parting with
    possession of subject premises and accordingly after hearing both
    the parties pass appropriate reliefs.

    8. Prima facie after going through record of the case and the
    aforementioned correspondence an arguable case has been made
    by Mr. Daver for grant of ad-interim relief which is in terms of
    prayer clause 61(b) of the Interim Application which reads thus:-

    “(b) Ex-parte ad-interim injunction during the pendency of
    the present application thereby restraining the defendant
    and/or its men, agents representatives, assigns and/or

    29

    ::: Uploaded on – 28/04/2026 ::: Downloaded on – 29/04/2026 06:09:18 :::

    901.IAL.9084.2026 & IAL.7684.20263.doc

    persons claiming under them from transferring, selling,
    alienating, encumbering, disposing of and/or otherwise
    creating third party rights over and in respect of the Leased
    Premises described in Schedule C appended herewith.”

    9. Hence, issue notice to Defendant.

    10. Humdast permitted. In addition to Court’s notice,
    Plaintiff /Applicant is directed to serve the Defendant a copy of
    this order, Suit and Interim Application and inform about the next
    date of hearing by any permissible mode of service and file
    appropriate affidavit of service with tangible proof thereof.

    11. Affidavit-in-Reply is directed to be filed within a period of
    two weeks from today and apprise the Court accordingly.

    12. Liberty to apply.

    13. Stand over to 25th March 2026.

    14. Praecipe is disposed.”

    22. However before the order could be conveyed to the

    Defendants by that time on 04.03.2026 itself, lease deed was

    executed and registered between Defendant No.1 and Defendant No.2.

    It is today vehemently argued by Mr. Joshi learned Senior Advocate

    that Defendant No.2 is a bonafide lessee without notice and due to its

    registered lease deed with Defendant No.1, indivisible rights have been

    vested in Defendant No.1 qua the leased property which includes the

    Suit property and substantive right of Defendant No.2 would far

    outweigh any right of the Plaintiff under the ATL (which is an

    unregistered document). The Defendant No.1 has supported the

    aforesaid submission of Defendant No.2. However in the facts and

    circumstances of the present case which are delineated hereunder I am

    unable to accept the submissions made by Mr. Joshi on behalf of

    Defendant No.2 and for the matter of Mr. Dwarkadas, learned Senior

    30

    ::: Uploaded on – 28/04/2026 ::: Downloaded on – 29/04/2026 06:09:18 :::

    901.IAL.9084.2026 & IAL.7684.20263.doc

    Advocate for Defendant No.1 for more than one reasons.

    23. The limited case of Defendant No.1 is that the two aforesaid

    conditions, inter alia, pertaining to receipt of revised NOC from the

    Chief Fire Officer and Co – operative Housing Society’s permission for

    putting up signages were not received due to which on 20.02.2026

    ATL was terminated due to frustration of contract. Incidentally not a

    word about this was discussed in the Meeting held between the said

    parties on the previous day i.e. 19.01.2026.

    24. Conduct and intention of Defendant No.1 is clearly spelt out,

    rather revealed on the basis of the stand it adopted in the meeting held

    with Plaintiff on 19.02.2026. Minutes of the meeting between the

    parties held on 19.02.2026 at Godrej One premises, Vikroli are

    appended on page No. 671 of Suit plaint. For the sake of reference and

    convenience they are reproduced below:-

    ” 1. Signage Annexure (Boundary Wall Signage)
    Godrej informed that they will not be able to honour one of
    the critical points (CP) under the Signage Annexure agreed
    and signed in the ATL, specifically relating to Boundary Wall
    Signage.

    ï‚· The constraint arises due to resistance from the
    housing society.

    ï‚· Godrej expressed concerns regarding potential
    tenure-related challenges.

    ï‚· They categorically stated they cannot assume
    the risk of any rent withholding linked to this
    issue.

    2. Broader Leasing Strategy – “As Is” Basis
    Godrej communicated that they have taken an internal
    decision to lease the entire premises to a single party strictly
    on an “as is” basis.

    31

    ::: Uploaded on – 28/04/2026 ::: Downloaded on – 29/04/2026 06:09:18 :::

    901.IAL.9084.2026 & IAL.7684.20263.doc

    ï‚· No technical or legal modifications to current
    condition of the premises would be undertaken.

                             ï‚·     They will not be able to manage multiple
                             leases in the same premises with the society.
                3.     Agreement Status
    

    Godrej stated that the agreement in its present form is not
    acceptable to them.

    ï‚· The above two issues must be addressed before
    any further progress can be made.

    4. Formal Communication Requested

    Godrej has been requested to formally communicate their
    position via email, clearly, outlining the revised acceptable
    conditions, to enable DSI to evaluate internal next steps.

    5. Bank guarantee Decathlon requested to renew the Bank
    Guarantee for a period of atleast 60 days.”

    25. From the above it is clearly gathered that in so far as the

    first unfulfilled condition under CP-1 is concerned, it was never even

    discussed between the parties on 19.02.2026 and rightly so since the

    said condition stood already fulfilled in January 2026 itself. So far as

    the second condition is concerned the only bone of contention for

    which objection was raised related to the Boundary signage hoarding

    and nothing else. Infact, Defendant No. 1 was very categorical about

    its stand and decision which is reflected in the above minutes of the

    meeting and infact it was looking for a ruse to deceptively walk out of

    the ATL.

    26. I say this because on reading the minutes of the meeting

    which are not denied by Defendant No. 1, the acts of Defendant No.1

    and its fraudulent intention to walk out of the ATL stands fully

    exposed and proved prima facie on the face of record. The real bone of

    32

    ::: Uploaded on – 28/04/2026 ::: Downloaded on – 29/04/2026 06:09:18 :::

    901.IAL.9084.2026 & IAL.7684.20263.doc

    contention for ATL to be terminated was not the nonfulfillment of the

    two CP-1 conditions but the decision of Defendant No.1 to lease the

    entire commercial premises to a single party on “as is” basis. Thus this

    was a Commercial decision taken by Defendant No.1 to suit its

    purpose and reason given by Defendant No. 1 in that meeting was that

    they will not be able to manage multiple leases in the same premises

    with the Society proves this point.

    27. What is crucial is that Defendant No.1 refused to accept the

    ATL and the proposed lease between Plaintiff and Defendant No.1 in

    its present form as it was in regard to 50% of the entire commercial

    property, but Plaintiff requested Defendant No.1 to formally

    communicate their position as it was never agreeable and maintained

    that stance since inception. From reading from the above minutes of

    the meeting between Plaintiff and Defendant No.1 it is therefore

    crystal clear that the reasons stated in the Termination Letter dated

    20.02.2026 are totally incorrect or rather camouflaged by Defendant

    No.1 to walk out of the ATL and lease the entire commercial property

    to a single party only for obvious commercial consideration.

    28. Though it is argued by Defendant No.2 that it did not have

    knowledge about the ATL, such pleading and stand by Defendant No.2

    that is was unaware of the ATL or Plaintiff is prima facie unbelievable.

    Defendant No.2 has in connivance with Defendant No.1, attempted a

    33

    ::: Uploaded on – 28/04/2026 ::: Downloaded on – 29/04/2026 06:09:18 :::

    901.IAL.9084.2026 & IAL.7684.20263.doc

    hostile take over of the entire commercial area in Defendant No.1’s

    Chembur project as per Defendant No.2’s requirement and which

    suited Defendant No.1’s internal decision to lease the entire premises

    to one single party only. Further tenure and terms of Defendant No.2’s

    lease document are prima facie beneficial to the Defendant No.1 on

    long term basis and the maneuver between Defendant No.1 and

    Defendant No.2 about issuing the Letter of Intent within 7 day of

    termination and executing and registering the lease deed with

    Defendant No.2 clearly was an action plan intended to deceive

    Plaintiff’s right under the ATL.

    29. What is significance is that Defendant No.1 has vehemently

    argued that it invested Rs. 3,00,00,000/- towards fulfillment of CP-1

    conditions and its intention was therefore to now lease the entire

    property on “as is” basis to a single party only. This case is true but

    then Defendant No.1 wants to forgo the said expenses in favour of

    Defendant No.2 terminating the ATL.

    30. Further Defendant No.1 has not filed any counter claim

    against Plaintiff for its investment Rs.3,00,00,000/- towards fulfillment

    of CP-1 conditions. Infact, it will be seen from what is held herein

    below, CP-1 conditions were never a bone of contention. Infact, all CP-

    1 conditions are duly satisfied, though issue of signage is argued

    vehemently by Defendant No.1 however the said condition is a

    34

    ::: Uploaded on – 28/04/2026 ::: Downloaded on – 29/04/2026 06:09:18 :::

    901.IAL.9084.2026 & IAL.7684.20263.doc

    complete non-starter and nothing but a disguise and a smokescreen

    created by Defendant No.1 to walk out of the ATL only for a more

    lucrative deal with Defendant No.2. The conduct of Defendant No.1

    and equally that of Defendant No.2 in my prima facie opinion, in

    aforesaid facts clearly reeks of deceit and unworthy of trust and belief

    with fraudulent behavior of Defendant No.1 determining the ATL by

    Termination Letter dated 20.02.2026.

    31. Defendant No.1 has relied upon return of proposal

    submitted to BMC as the principle ground for termination. This return

    of file / proposal on 30.01.2026 is on the basis of a screenshot from

    the website of BMC, copy of which is appended at Exhibit ‘G’ – page

    No. 281 of Defendant No.1’s Affidavit-in-Reply dated 11.03.2026.

    However if the same is read, it is revealed that there are no such

    remarks of return of proposal or rejection of proposal whatsoever

    stated in the alleged screenshot pertaining to return of file and or

    rejection of permission under Section 342 of MMC Act as alleged by

    Defendant No.1. All that it merely states as “please attach corrected

    drawing” and nothing more. Significantly between 30.01.2026 and

    20.02.2026 Defendant No.1 maintained a stoic silence on its argument

    on return of file or rejection of permission under Section 342 of MMC

    Act and the same also does not find reflected in the Minutes of Order

    dated 17.02.2026.

    35

    ::: Uploaded on – 28/04/2026 ::: Downloaded on – 29/04/2026 06:09:18 :::

    901.IAL.9084.2026 & IAL.7684.20263.doc

    32. What is crucial is Defendant No.1’s Architect namely Mr.

    Harsh D. Gangar of M/s. Harsh Gangar & Associates and Structural

    Engineer – Mr. Sanjay Gambhir were appointed by separate

    appointment letters both dated 03.10.2025 by Defendant No.1, copies

    of which are appended at Page Nos. 182 and 184 of Defendant No.1’s

    Affidavit-in-Reply. It is seen that on 03.10.2025 itself Defendant No.

    1’s Architect applied to the Corporation for provisional NOC which was

    granted on 11.10.2025, copies of which are appended at Page Nos.

    173 and 179 of its Affidavit-in-Reply.

    33. The correspondence relied upon by Defendant No.1 placed

    at Page Nos. 173 to 307 between Plaintiff and Defendant No.1 when

    seen and read, prima facie, reveal that right since 03.10.2025 there

    has been extensive correspondence between these parties regarding

    submission of plans under Section 342 of MMC Act for the proposed

    work undertaken for amalgamation, addition, alteration, direction, etc.

    of the Suit property along with all necessary detailed drawings / plans

    submitted from time to time along with scrutiny fee, fire service fee

    and all compliances by Defendant No.1’s Architect and Structural

    Engineer. Plaintiff has entered into separate Agreements with Lewis &

    Hickey India Pvt. Ltd. dated 03.04.2025, Turnkey contract with

    AAKAR for interior / turnkey works, signage Agreement dated

    20.06.2025 to execute the terms of Term Sheet and ATL.

    36

    ::: Uploaded on – 28/04/2026 ::: Downloaded on – 29/04/2026 06:09:18 :::

    901.IAL.9084.2026 & IAL.7684.20263.doc

    34. It is seen that notably Compliance Report dated 16.01.2026

    has been given by Defendant No.1’s Architect about Completion

    Certificate of the works in the Suit property, copy of which is

    appended at Page No. 253 of Defendant No.1’s Affidavit-in-Reply. It is

    further seen that the Deputy Chief Fire Officer, the Deputy Fire Officer

    and the Assistant Deputy Fire Officer have jointly issued the Final Fire

    Safety Approval for the aforesaid works as per inspection carried out

    by the Inspecting Officer with a specific remark that further additions,

    alterations, amalgamations, amendments shall be approved by the

    Licensed Surveyor before occupying the premises and starting trade

    activity. Copy of this Approval letter is appended at Exhibit ‘F’ – Page

    Nos. 257 to 261. This approval was given as far back on 17.01.2026

    and 21.01.2026 which can be seen from the date of the digital

    signatures appended thereon. Certain excerpts of the above Final Fire

    Safety Approval which are relevant to adjudicate the present case are

    reproduced below for reference:-

    “BRIHANMUMBAI MUNICIPAL CORPORATION
    MUMBAI FIRE BRIGADE
    Office of Dy. Chief Fire Officer (R-V), Mankhurd Regional
    Command Centre, Mankhurd Fire Station, Ghatkopar Mankhurd
    Link Road, Opp. Sathe Nagar, Mankhurd, Mumbai -400 043.

    ———————————————————————————————–

    Sub: Final Fire Safety approval from the fire safety
    installations point of view for amalgamations, addition/
    alteration and erection of wooden/glass/siporex/gypsum
    partition in proposed Shop (earlier retail unit no. 2) on
    Ground floor and Shop No. 1 to Shop no. 4 at 1 Basement in
    Wing A of the existing Commercial cum residential building
    known as Godrej RKS on plot bearing C.T.S. Nos. 673/A,
    673/C, 783/A/1, 783/A/3 and Old C.T.S. Nos. 673, 673/1 to

    37

    ::: Uploaded on – 28/04/2026 ::: Downloaded on – 29/04/2026 06:09:18 :::

    901.IAL.9084.2026 & IAL.7684.20263.doc

    673/20, 783 (pt) of Village Borla at Chembur, Mumbai.

    Ref: i) Online proposal submission by Architect, Mr. Harsh
    Deepak Gangar of M/s. Harsh Gangar & Associates,
    under file No. P-28028/2025/(673 And Other)/M/W
    Ward/BORLA-M/W-CFO/1/New.

    ii) Earlier MFB NOC: –

    a) P-28028 / 2025 / (673 And Other)/M/W
    Ward/BORLA-M/WCFO/1/New. Dt.14/10/2025

    b) P-28028/2025/(673 And Other)/M/W
    Ward/BORLA-M/W-CFO/1/New. Dated, 26/12/2025

    iii) Joint Inspection Date: – 13.01.2026

    M/S. GODREJ PROJECTS DEVELOPMENT LTD.,

    The premises under reference is proposed shop (earlier retail unit
    no.2) on ground floor and Shop No. 1 to Shop no. 4 at 1st basement of
    Wing A of the existing commercial cum residential building known as
    Godrej RKS, comprising of 03 Wings, i.e., Wing ‘A’, ‘B’ & ‘C’. Wing ‘A’ is
    having 03 level basements + Common Ground floor + 1 part for
    Commercial use & Extended portion used as Additional R. G. + 2nd to
    14th upper residential floors, with a total height of 49.95 mtrs. from the
    general ground level up to the terrace level. Wing ‘B’ is having 03 level
    basements (Common for Wings ‘A’ to ‘C’) + Ground floor + 1st floor for
    Amenities & Extended portion used as R. G. + 2nd to 14th upper
    residential floors, with a total height of 49.45 mtrs. from the general
    ground level up to the terrace level. Wing ‘C’ is having 03 level basements
    (Common for Wings ‘A’ to ‘C’) + Ground floor + 1st to 14th upper
    residential floors, with a total height of 49.45 mtrs. from the general
    ground level up to the terrace level.

    Final NOC for Part Occupation certificate issued by this department
    under No. P-2314/2019/(673 And Other)/M/W Ward/BORLA-M/W-
    CFO/1/New, dated 10.03.2022, to occupy & use of Part Basement 1+ Part
    Ground Floor + Part 1st Floor of TAR High-Rise Commercial-cum-
    Residential Building.

    Further, the party had obtained Part O.C. from E.E. (B.P.) E.S. vide
    No. P-2314/2019/ (673 And Other)/M/W
    Ward/BORLA-M/W/OCC/1/New of 16 March 2022 for a commercial cum
    residential building comprising of 1 Part Basement + Part Ground floor
    Part 1st floor of Wing A.

    In this case, please refer to the Provisional fire safety approval issued by
    this department u/r. no. P-28028/2025/(673 And Other)/M/W
    Ward/BORLA-M/WCFO/ 1/New. Dt. 14/10/2025 for the proposed
    amalgamations, addition/alteration and erection of
    wooden/glass/siporex/gypsum partition in Retail Unit No. 2 on the ground
    floor and Shop No. 1 to 04 on 1st Basement in Wing A of the existing
    Commercial cum residential building known as Godrej RKS.

    In this case approval letter from EEBP (E.S.) u/r.no. P-28028 /
    2025 /(673 And Other)/M/W Ward/BORLA-M/W/342/1/New. Dt.
    06/11/2025 for the proposed amalgamations, addition/alteration and
    erection wooden/glass/siporex/ gypsum partition in Retail Unit No. 2 on

    38

    ::: Uploaded on – 28/04/2026 ::: Downloaded on – 29/04/2026 06:09:18 :::

    901.IAL.9084.2026 & IAL.7684.20263.doc

    the ground floor and Shop No. 1 to 04 on 1 Basement in Wing A of the
    existing Commercial cum residential building at the above-mentioned
    address.

    In this case, please refer to the Provisional fire safety approval issued
    by this department u/r. no. P-28028/2025/ (673 And Other)/M/W
    Ward/BORLA-M/W-CFO/1/New. Dated, 26/12/2025 for the proposed
    amalgamations, addition/alteration and erection of
    wooden/glass/siporex/gypsum partition in proposed Shop (earlier retail
    unit no. 2) on the ground floor and Shop No. 1 to Shop no. 4 at 1
    Basement in Wing A of the existing Commercial cum residential building
    known as Godrej RKS.

    Now, the Licensed Surveyor has informed that the proposed
    addition/alteration and erection wooden of amalgamations,
    /glass/siporex/gypsum partition in proposed Shop (earlier retail unit no.

    2) on Ground floor and Shop No. 1 to Shop no. 4 at 1 Basement in Wing A
    of the existing Commercial cum residential building known as Godrej
    RKS., is completed and complied with all the stipulated fire safety
    measures as referred above & requested to issue for final fire safety
    approval of the fire safety measures for the same.

    On receipt of the Licensed Surveyor application, a senior officer of
    this department visited the said premises to verify & ensure the completion
    of fire safety measures stipulated by this department vide above-referred
    Fire Safety Requirements Letter, where it was observed that the party has
    complied with the fire protection & firefighting requirements stipulated by
    this department vide above-referred Fire Safety Requirements Letter.

    During the site inspection, the firefighting requirements such as an
    automatic sprinkler system, an automatic smoke detection system, a pre-
    action system, a manual call point, etc., were tested & found in good
    working order & the party has also provided fire extinguishers & signage
    as mentioned in the above – referred NOC.

    The Architect uploaded the following documents:-

    I. Area Certificate, the Architect, Mr. Harsh Deepak Gangar of M/s. Harsh
    Gangar & Associates has uploaded the gross built-up area certificate of
    800.00 sq. mtrs. Dated 06.01.2026.

    ii. Structure Stability certificate, dated 06.01.2026, from Mrs. Sanjay
    Banarasilal Gambhir, Consulting Structural Engineer of M/s. Sanjay
    Gambhir Structural Consultant bearing Reg. No. STR/G/95.
    iii. FORM-A dated 02.01.2026 from Gov. Licensed Agency M/s. Aim Fire
    Engineering bearing license No. MFS/LA/F-358/D-339 for the installation
    of the fixed firefighting system & Smoke detection system.

    iv. FORM-B dated 03.01.2026 from Gov. Licensed Agency M/s. Aim Fire
    Engineering Bearing License No. MFS/LA/F-358/D-339 for the
    maintenance in good working condition of the existing fixed firefighting
    installation of the building.

    v. FORM-A certificate regarding FRD from the Gov. Licensed Agency M/s.
    MP SWASTIK DOORS LLP bearing license No. MFS/LA/RP-108 dated

    39

    ::: Uploaded on – 28/04/2026 ::: Downloaded on – 29/04/2026 06:09:18 :::

    901.IAL.9084.2026 & IAL.7684.20263.doc

    05.01.2026
    viii. Electrical test certificate, dated 31.12.2025, from M/s. Jay Ambe
    Electricals, Mumbai, bearing License No. 22913 as registered with the
    Electrical Inspector of Industries, Energy & Labour Department of the
    Government of Maharashtra.

    In view of the above, as far as this department is concerned, this
    Final Fire Safety Approval is issued from a fire safety installation point of
    view for the amalgamations, addition/alteration and erection of
    wooden /glass/siporex/gypsum partition in proposed Shop (earlier retail
    unit no. 2) on Ground floor and Shop No. 1 to Shop no. 4 at 1st Basement
    in Wing A of the existing Commercial cum residential building known as
    Godrej RKS.

    The party had paid a scrutiny fee of Rs. 25,440/- vide Online
    Receipt No.6/10/2025/55093, dated 06.10.2025, on the total gross built-
    up area of 800.00 sq. mtrs. of the premises as certified by the Architect
    vide area certificate 03.10.2025.

    The party has already paid the Fire Service Fee of Rs. 6,41,715/-
    vide C.F.C./SAP Receipt Nos. 1004002446 & Challan No. 750129, dated
    10.06.2021, on the total gross built-up area of 42780.43 sq. mtrs. of the
    complete building at the time of the final fire safety approval for OC.

    Now party had paid scrutiny fee of Rs. 25,440/- vide Online Receipt
    No. 9/12/2025/59221, dated 09/12/2025 on total gross built up area of
    800.00 sq. mtrs. of the premises as certified by the Architect.

    However, E.E.(B.P.) E.S. is requested to verify the total gross built-
    up area & share of total common services area of the said premises and
    inform this department if the same is found to be more for the purpose of
    levying additional Fire & Emergency Service Fee & Scrutiny fees, if
    required.

    Now, the Architect has uploaded the undertaking on 500/- bond
    paper & stated that as per Government Notification No.
    FFS-2022/C.R.36/UD-14 dated 30.05.2023, TP-1821/C.R.103/2021/UD-
    13, dated 02.08.2021, FPS-2012 /C.R.42/UD-20 dated 03.03.2024,
    Maharashtra Fire Prevention & Life Safety Measures (Amendment) Act,
    2023
    coming into effect from 31.05.2023, from the State Govt. of
    Maharashtra regarding revisions in Fire and Emergency Fee, and & as per
    letter u/no. MPS/51/2024 from Directorate of Maharashtra Fire Services
    “Hereby state that if necessary modification as proposed in the Rule 19 of
    Maharashtra Fire Prevention & Life Safety Measure Rules, 2009 is not
    carried out in the revised Fire Rules by Directorate, Maharashtra Fire
    Services then additional fee if any levied if necessary by Mumbai Fire
    Brigade will be paid as demanded by Mumbai Fire Brigade vide new
    circular / notification in future.

    It shall be the responsibility of the Builder/ Developer/
    Owner/Occupier, as the case may be, to observe all the fire safety
    measures stipulated by this department & maintain all the fire-fighting
    installations in good working order from the next day of the inspection. If
    any item or requirement is missing/not working from the next day of the
    inspection, this department or the inspecting officer will not be responsible
    for the same & accordingly, the completion certificate will not be issued.

    40

    ::: Uploaded on – 28/04/2026 ::: Downloaded on – 29/04/2026 06:09:18 :::

    901.IAL.9084.2026 & IAL.7684.20263.doc

    The concerned Builder/Developer/Owner/Occupier, as the case may
    be, shall give an annual maintenance contract for fire-fighting equipment
    to the registered License Agency & submit the Form B every 06 months (In
    January & July), as per the Maharashtra Fire Prevention & Life Safety
    Measures Act
    . 2006. Strict Compliance with the stipulated fire safety
    measures is for minimizing the chance of occurrence/spread of Fire
    through active & passive measures. The consequential life & property loss
    due to fire, due to any non-compliance at any instance, the owner/user
    will be solely responsible.

    E.E.B.P(E.S.) shall verified civil work, interior work and all other
    requirements stipulated in all NOCs issued by this department, pertaining
    to the Civil Engineering side including width of the abutting road/access
    road, internal access road, all shafts, ducts, voids, floor occupancy /floor
    wise user, common corridors, lift lobby and its ventilation, travel distance,
    doors, windows, height of the building, structural stability etc. and also
    any additions/alterations/amendments other than approved plans as well
    as gross built up area shall be verified before grant of any
    permission/approval. If any contradiction, the said completion certificate
    shall be referred back to this department for offering fresh remarks from a
    fire safety point of view.

    However, further additions /alterations/amalgamations /
    amendments if any, during the construction work, the licensed
    surveyor/Architect shall get it approved from the concerned competent
    authority and Municipal Authority before occupying the premises also
    necessary permission / licences shall be obtained from concerned
    competent Municipal Authority before starting any trade activity
    u/s.394/390 of MMC Act in the any part of the building.

    This Final Fire Safety Approval for amalgamations, addition
    /alteration and erection of wooden/glass/siporex/gypsum partition in
    proposed Shop (earlier retail unit no. 2) on Ground floor and Shop No. 1
    to Shop no. 4 at 1″ Basement in Wing A of the existing Commercial cum
    residential building known as Godrej RKS is issued as per inspection
    carried out by the inspecting officer from a fire safety point of view only,
    without prejudice to legal matters pending in the court of law, if any.

    Digitally signed by DATTATRAY MARUTI PATIL
    Date: 2025.01.17 09:11:54
    A.D.F.O.
    (Inspecting Officer)

    MAHENDRA YESHWANT MITHBAONKAR
    D.F.O.
    (Primary Approval by)

    KRISHNAT RAMCHANDRA YADAV
    Digitally signed by
    Dy. Chief Fire Officer (Approved by)

    Copy to:

    1. E.E.B.P (E.S.)

    2. Mr. Harsh Deepak Gangar of M/s. Harsh Gangar & Associates

    41

    ::: Uploaded on – 28/04/2026 ::: Downloaded on – 29/04/2026 06:09:18 :::

    901.IAL.9084.2026 & IAL.7684.20263.doc

    35. It is seen that for issuance of the above sanction and

    approval every statutory document that was required was submitted by

    Defendant No.1, copies of which are all appended to the reply which

    include Form A under section 3(3) and rule 4(1), Area Certificate, list

    of fire protection equipments installed and its quantities, list of fire

    alarm system equipments installed and its quantities, Form B under

    section 3(3) and rule 4(2), Certification for electrical work

    compliance, Manufacture Test Certificate of metal doors for Service

    Shaft, Electrical Shaft, UPS Room, Electrical room, etc. All these

    documents have been duly considered in detail for issuance of the

    Final Fire Safety Approval which is seen from the said approval

    appended at page no. 257. Therefore, the excuse pleaded by

    Defendant No.1 in the Termination Letter for frustration of ATL on this

    ground of rejection of permission by the Municipal Corporation is a

    completely false ground which is prima facie evident on the face of

    record. The alleged screenshot dated 30.01.2026 merely states the

    remark “please attach corrected drawing” and nothing more. It is

    intriguing and equally shocking that even though parties having

    entered into humongous and substantial correspondence before and

    pursuant to ATL and after having fructified all conditions, Defendant

    No.1 merely for greed and better and lucrative contract, reneged upon

    the ATL in this surreptitious manner.

    42

    ::: Uploaded on – 28/04/2026 ::: Downloaded on – 29/04/2026 06:09:18 :::

    901.IAL.9084.2026 & IAL.7684.20263.doc

    36. It is seen that authorized representative of Defendant No.1 –

    Godrej – Ms. Shruthi Nayanar has filed the Affidavit-in-Reply and she

    has been actively involved in all correspondence upto the end of

    January 2026. The most shocking part is that if it was Defendant

    No.1’s case that on 30.01.2026 the alleged screenshot amounted to

    rejection of permission by Municipal Corporation under Section 342

    then not a single letter was addressed by Defendant No.1 to the

    Plaintiff informing about the same neither was it discussed or formed

    part of the Minutes of Meeting dated 19.01.2026.

    37. On the contrary Ms. Shruthi Nayanar had addressed two

    specific letters dated 14.01.2026 and 16.01.2026 to the Executive

    Engineer and Assistant Engineer (M-ward) of BMC certifying and

    confirming completion of works as per the plans under the supervision

    of Defendant No.1’s Architect Mr. Harsh D. Gangar in accordance with

    the permission sanctioned by the corporation and payment of all

    assessment charges as applicable under the said permission. These

    letters are appended at Page Nos. 283 and 284 of the Defendant

    No.1’s Affidavit-in-Reply. These letters read as under:-

    *******
    “Date: 14.01.2026

    To,
    The Executive Engineer,
    M.C.G.M, L.B.S Marg,
    Vikhroli (West),
    Mumbai-400 083
    Sub: Completion certificate for Amalgamations, Addition / alteration and
    erection of wooden/ glass/ siporex/ gypsum partition in proposed shop

    43

    ::: Uploaded on – 28/04/2026 ::: Downloaded on – 29/04/2026 06:09:18 :::

    901.IAL.9084.2026 & IAL.7684.20263.doc

    (Earlier retail unit no.2) on Ground floor and Shop no. 1 t 4 at 1 s
    Basement in Wing A of the existing Commercial cum residential building
    known as Godrej RKS on plot bearing C.T.S. Nos. 673/A, 673/C, 783/A/3
    and Old C.T.S Nos. 673, 673/1 to 673/20, 783 (pt.) of Village Borla at
    Chembur, Mumbai-400071.

    Ref: File no.: -P-28028/2025(673 And Other)/M/W
    Ward/BORLA-M/W/342/1/New

    With reference to above refer subject, we hereby confirm that work
    as shown in the plans on Amalgamations, Addition / alteration and
    erection of wooden/ glass/ siporex/ gypsum partition in proposed ship
    (Earlier retail unit no.2) on Ground floor and Shop no. 1 to 4 at 1 st
    Basement in Wing A of the existing Commercial cum residential building
    known as Godrej RKS on plot bearing C.T.S. Nos. 673/A, 673/C, 783/A/3
    and Old C.T.S Nos. 673, 673/1 to 673/20, 783 (pt.) of Village Borla at
    Chembur, Mumbai-400071, is completed on dt.25.12.2025 under the
    supervision of Architect Shri. Harsh D. Gangar of M/s. Harsh Gangar &
    Associates with accordance of the permission sanctioned no P-
    28028/2025(673 And Other)/M/W Ward/BORLA-M/W/342/1/New

    Thanking You,

    Yours Faithfully,
    For, M/s. Godrej Projects Development Ltd.

    Shruthi
    Nayanar
    (Authorized signatory)”

    *******
    “Date: 16th Jan 2026

    To,
    Assistant Engineer (M Ward),
    2nd Floor, Building proposal,
    L.B.S Marg, Paper Mill Compound,
    Vikhroli (W), Mumbai.

    Sub: Completion certificate for Amalgamations, Addition / alteration and
    erection of wooden/ glass/ siporex/ gypsum partition in proposed shop
    (Earlier retail unit no.2) on Ground floor and Shop no. 1 t 4 at 1 s
    Basement in Wing A of the existing Commercial cum residential building
    known as Godrej RKS on plot bearing C.T.S. Nos. 673/A, 673/C, 783/A/3
    and Old C.T.S Nos. 673, 673/1 to 673/20, 783 (pt.) of Village Borla at
    Chembur, Mumbai-400071.

    Ref: File no.: -P-28028/2025(673 And Other) /M/W
    Ward/BORLA-M/W/342/1/New

    Dear Sir,
    With reference to above subject matter, we have paid the necessary
    charges to assessment Dept. till March 2026 and we are enclosing the
    receipt for your reference.

    This is for your information & record please.

    44

    ::: Uploaded on – 28/04/2026 ::: Downloaded on – 29/04/2026 06:09:18 :::

    901.IAL.9084.2026 & IAL.7684.20263.doc

    Thanking You,
    Yours Faithfully,
    Shruthi Nayanar

    For, Godrej Projects Development Ltd.”

    *******

    38. Once, the aforesaid documents and documentary evidence

    are prima facie seen, it is clearly discernible that the case with which

    Defendant No.1 has approached this Court is dishonest and contrary to

    record. From the conduct of Defendant No.1 it is clearly discernible

    that Defendant No.1 has acted malafide and dishonestly to issue the

    termination letter dated 20.02.2026 solely driven by its greed for

    money since by that time it already had a suitor in the form of

    Defendant No.2 who was ready and willing to take over the entire

    commercial property in the said project which included the suit

    property for a tenure of 21 years and at the rate of 42.5 lakhs per

    month with 15% escalation every 3 years alongwith 39 car parking

    slots. Defendant No.1 and Plaintiff had agreed under the ATL to lease

    761 sq.m. on the lower ground floor (633 sq.m.) and ground floor

    (128 sq.m.) along with 24 car parking slots for a period of 10 years on

    monthly lease rental for Rs. 21 lakhs as against the terms with

    Defendant No.2.

    39. As against the above Defendant No.2 agreed to take over the

    entire commercial area admeasuring 1471.86 sq.m. which included the

    entire lower ground floor area (634.34 sq.m.), entire ground floor area

    45

    ::: Uploaded on – 28/04/2026 ::: Downloaded on – 29/04/2026 06:09:18 :::

    901.IAL.9084.2026 & IAL.7684.20263.doc

    (388.43 sq.m.), entire first floor area (449.04 sq.m.) along with 39 car

    parking slots. From the above figures and from a commercial

    profitability point of view it is clearly derived that Defendant No.1 has

    acted in the most malafide manner in terminating the ATL on a

    completely innocuous ground of rejection of fire NOC which is in fact

    not the case when the aforesaid documentation is considered prima

    facie. The minutes of meeting dated 19.02.2026 discussed and alluded

    to hereinabove clearly exposes the hypocrisy and pretense of

    Defendant No.1’s behavior and conduct in the present case. Thus since

    the edifice of Defendant No.1’s case is based upon fraud and

    fraudulent conduct which is prima facie evidence in terminating the

    ATL, any further statutory Act in furtherance thereof cannot be

    countenanced.

    40. It can be prima facie seen that Defendant No.1 not only

    defrauded Plaintiff after leading it on the golden path and executing

    the Term Sheet and ATL and fructifying the conditions, but once it got

    a better deal for the entire commercial premises for a much longer

    tenure, it has virtually thrown caution to the winds by terminating the

    ATL wrongfully and issuing the Letter of Intent to Defendant No.2

    within 7 days and executing the Lease Deed within 15 days thereafter.

    Now whether, Defendant No.2 was kept in the dark about the ATL is

    something which I am not inclined to believe. The swiftness with

    which it has acted without any trace of the ATL or Plaintiff right in the

    46

    ::: Uploaded on – 28/04/2026 ::: Downloaded on – 29/04/2026 06:09:18 :::

    901.IAL.9084.2026 & IAL.7684.20263.doc

    premises raises suspicion and doubt on the face of record especially

    when the minutes of meeting dated 19.01.2026 are read and seen.

    41. In so far as the second ground regarding the Co-operative

    Housing Society not giving its permission to install signages is

    concerned, there are two documents which are appended at Page Nos.

    899 and 912. One document is email dated 23.01.2026 is addressed

    by Shailesh Jaiswal on behalf of Plaintiff to Ms. Shriya Khanna on

    behalf of Defendant No.1 is appended at Page No.912 of Plaint and it

    reads thus:-

    ******
    “Dear Shriya,
    As shared and represented by you at the signing of the Agreement to
    Lease regarding the formation of a society under the name of R.K.S.
    Co-operative Housing Society Limited (“Society”), we are re-seeking
    confirmation of the same understanding before signing of the Lease
    Deed.

    Kindly acknowledge and confirm the following points as the
    understanding between GPDL and DSI at the time of signing of the
    Lease deed. (Kindly reply to each point, as required, for clarity)

    1. As on date, the conveyance to the Society is still under process (ref.

    Email dated 27 June 2025 in the same trail)and is yet to be
    completed, and there is no transfer of rights to the Society relating to
    DSI.

    2. Once the conveyance to the Society is completed, will there be a
    need for an NOC from the Society with respect to our leased premises?
    If yes, what would be the timelines for obtaining and sharing the
    same?

    3. Upon completion of the conveyance to the Society, the conveyance
    deed is to be shared with the Lessee for its records.

    4. The Society shall not cause any disruption to the DSI technical
    team’s and our vendor’s operations at the time of fit-out, and the DSI
    team will only follow the fit-out rule book as shared by the GPDL team.

    5. The GPDL team will be direct and sole point of contact for
    resolution in case of any disruption to the fit-out works and operations
    of the construction team at the time of fit-out by anyone acting on
    behalf of the Society.

    47

    ::: Uploaded on – 28/04/2026 ::: Downloaded on – 29/04/2026 06:09:18 :::

    901.IAL.9084.2026 & IAL.7684.20263.doc

    6. GPDL and DSI, under the provisions of the Lease deed, being the
    Lessor and the Lessee respectively, shall be responsible for their
    reciprocal obligations.

    7. DPDL shall be the single point of contact for DSI during the Lease
    Term.”

    42. Reference is also drawn to email dated 07.11.2025

    addressed by Ms. Shriya Khanna on behalf of Defendant No.1 to Mr.

    Kedar of Decathlon. The said email is appended at Page No. 303 of its

    Affidavit-in-Reply dated 11.03.2026 which reads thus:

    Email dated 07.11.2025

    “Dear Kedar,
    Good Afternoon! Please find attached the approved documents
    received for the retail area at Godrej RKS, namely:

    1. Approval Letter and Plan issued under Section 342 of the MMC
    Act for the proposed amalgamations, additions, and alterations in
    the retail area; and

    2. Provisional Fire Safety Approval (NOC) along with the approved
    layout plan from the Mumbai Fire Brigade.

    These approvals comprehensively cover the retail unit at the ground
    floor and basement 1 of Wing A as per the submissions made by our
    architect, M/s Harsh Gangar & Associates.

    With these key statutory approvals now in place, we request you to
    kindly share the draft Lease Deed at the earliest. This will allow us to
    review it internally and provide our comments, if any, before
    proceeding to execution. We would want to execute the Lease Deed
    before the 20th of this month.

    Please not that most of the other requirements under the Conditions
    Precedent (as per Annexure of the agreement) will be completed in
    parallel, in coordination with Decathlon.

    Look forward to receiving the draft document soon.
    Regards,
    Shriya Khanna
    Cluster Head*****”

    48

    ::: Uploaded on – 28/04/2026 ::: Downloaded on – 29/04/2026 06:09:18 :::

    901.IAL.9084.2026 & IAL.7684.20263.doc

    43. From the above it is prima facie seen that insofar as

    permission under Section 342 of MMC Act is concerned to the extent

    of the suit property it was Defendant No.1’s own case that far back as

    in November 2025 the said permission was in place. Hence its stand

    on this ground is prima facie fraudulent and dishonest.

    44. Insofar as the second objection relating to Co – operative

    Housing Society not giving permission for putting up of signages as

    contemplated by Annexure ‘D’ of the ATL is concerned there is one

    document which is placed on record dated 23.01.2026 addressed by

    Plaintiff to Defendant No.1. This letter reiterates the fact that there is a

    society in existence and conveyance to the said Society is yet to be

    completed. The Plaintiff has raised a question as to whether there will

    be a need for an NOC from the Society with respect to the leased

    premises reiterating the fact that Defendant No.1 will be the single

    point of contact for the Plaintiff during the term of the lease.

    45. Though in the letter of termination Defendant No.1 has

    stated that provision of signage spaces (x) is impeded due to practical

    and regulatory constraints beyond its control, it nowhere states that

    the Society has refused permission for the putting up of signages on

    the main gate as argued by Mr. Dwarkadas. In any event, at the outset

    itself, Mr. Davar clarifies this position regarding the issue of boundary

    signage since Plaintiff was taking over only 50% of the commercial

    49

    ::: Uploaded on – 28/04/2026 ::: Downloaded on – 29/04/2026 06:09:18 :::

    901.IAL.9084.2026 & IAL.7684.20263.doc

    premises and therefore undoubtedly availing only 4 shops on the

    ground floor, the boundary signage issue could be easily worked out

    between parties. He would rather submit that the alleged boundary

    signage issue is once again nothing but a ruse by Defendant No. 1

    trying to walk out of the ATL which I am inclined to accept. In the

    above facts and circumstances I agree with Mr. Davar. The Society’s

    letter is not produced by Defendant No.1 refusing permission.

    Defendant No.1 is the Developer who has helped in forming the

    Society. Society cannot refuse permission for display on or above the

    shops and premises leased by Plaintiff. Regarding boundary signage, if

    Society refuses, certainly Plaintiff would have to agree. This cannot be

    termed non – fulfillment of CP – 1 condition for terminating the ATL.

    46. In the present case the Plaintiff has clearly demonstrated

    from the conduct and flow of events that termination of ATL by letter

    dated 20.02.2026 is nothing but a completely malafide act on the part

    of Defendant No.1 solely for the purpose of securing a better rather

    lucrative and profitable commercial deal in respect of the entire

    commercial area developed by the Defendant No.1 in the said project.

    In my opinion above prima facie grounds clearly stand out and are

    evident from the facts and circumstances in the present case to

    pointedly show the malafide conduct of Defendant No.1 in terminating

    the ATL solely for the purpose of securing a more commercially viable

    and profitable deal without adhering to the sanctity of contract namely

    50

    ::: Uploaded on – 28/04/2026 ::: Downloaded on – 29/04/2026 06:09:18 :::

    901.IAL.9084.2026 & IAL.7684.20263.doc

    term sheet and ATL in the present facts.

    47. The submissions made by Defendant No.1 that the ATL is a

    non-binding contract and in view of non-compliance of two conditions

    of CP-1, it stands frustrated is nothing but a ruse by Defendant No.1 to

    walk out of the contract unilaterally on the above pretext for a

    lucrative and better commercial deal offered by Defendant No.2 to

    Defendant No.1.

    48. First and foremost the reasons given in the termination letter

    in paragraph no. 3 are as innocuous as possible on the face of record.

    In view of the aforementioned observations made by me qua both the

    reasons they do not justify premature termination of the ATL in the

    manner in which it is done by Defendant No.1. Admittedly from

    almost January 2025 upto 19.02.2026 substantial negotiations took

    place between Plaintiff and Defendant No.1 which is evident from the

    execution of Term Sheet dated 18.03.2025 and the ATL dated

    17.09.2025 in addition to humongous correspondence between the

    parties.

    49. Insofar as the issue of fire NOC is concerned Architect Harsh

    D. Gangar representing Defendant No.1 was at the forefront and

    instrumental in carrying out all changes as per the sanctioned plan in

    terms of Plaintiff’s requirements leading to issuance of the NOC allured

    to hereinabove. Insofar as the putting up of signages is concerned non-

    51

    ::: Uploaded on – 28/04/2026 ::: Downloaded on – 29/04/2026 06:09:18 :::

    901.IAL.9084.2026 & IAL.7684.20263.doc

    fulfillment of that condition is nothing but a ploy employed by

    Defendant No.1 to frustrate the ATL when the actual issue pertained to

    the boundary signage only and Society not having issued any refusal

    whatsoever. Defendant No.1 is the developer of the project and in the

    course of submissions Mr. Davar has clarified about the issue of

    signages and more specifically the signage that was to be put up on the

    main gate (boundary signage) and the fact that it should not be an

    impediment for the Plaintiff to accept, since it was only taking 50% of

    the commercial property on lease.

    50. In this background what is critical is that Defendant No.1

    has got a much lucrative deal with Defendant No.2 for the entire

    commercial area and in order to fructify the same Defendant No.1 has

    terminated the ATL after making its intention clear in the meeting held

    on 19.02.2026 with Plaintiff. It is crystal clear that ATL was in respect

    of 50% of the commercial premises comprising of entire lower ground

    area and 1/3rd portion of the ground area along with 24 reserved car

    parking spaces for a period of 10 years. Whereas on the other hand

    Defendant No.2 has offered to take the entire lower ground, the entire

    ground floor area and the entire first floor area as a one stock deal for

    21 years but alongwith 39 reserved car parking slots.

    51. The aforesaid transaction with Defendant No.2 is, on the

    face of record, commercially viable and profitable to Defendant No.1

    52

    ::: Uploaded on – 28/04/2026 ::: Downloaded on – 29/04/2026 06:09:18 :::

    901.IAL.9084.2026 & IAL.7684.20263.doc

    since, it saves the trouble for Defendant No.1 to look for another

    potential incumbent lessee/licensee to occupy 50% of the commercial

    area in future an issue with which it stood troubled, which can be

    gathered from the minutes of the meeting held on 19.02.2026.

    52. The Defendant No.1 wants the Court to believe that the ATL

    was indeed frustrated on the alleged aforementioned twin grounds but

    that is prima facie unbelievable because of the nexus with Defendant

    No.2. It is seen that Defendant No.1 issued a Letter of Intent dated

    27.02.2026 on the terms agreed between them within seven days of

    the issuance of termination letter to Plaintiff. Thereafter immediately

    on 04.03.2026 i.e. within next eight days Defendant Nos. 1 and 2

    executed the Lease Deed as per the Letter of Intent. Though it is

    vehemently argued by Defendant No.2 that it is a bonafide purchaser

    for value without notice of the previous relationship between Plaintiff

    and Defendant No.1, for all the above reasons I am not willing to

    accept or believe the same.

    53. Though Defendant No.2 pleads that there is no specific

    averment in the Suit plaint that Defendant No.2 had no prior

    knowledge of Plaintiff’s ATL, the said submission cannot be accepted

    by the Court in view of the fraudulent conduct of Defendant No.1 and

    as a consequence thereof Defendant No.2 directly benefiting from the

    same. Fraud vitiates all future transactions. This is primarily because

    53

    ::: Uploaded on – 28/04/2026 ::: Downloaded on – 29/04/2026 06:09:18 :::

    901.IAL.9084.2026 & IAL.7684.20263.doc

    the Letter of Intent dated 27.02.2026 cannot be believed to have been

    issued to Defendant No.2 without its knowledge about the ATL

    between Plaintiff and Defendant No.1. Defendant No.2 is pretending

    to be innocent, but that is not the case to be believed in the above

    facts.

    54. I say this because the substantial changes carried out in the

    suit property as per the sanctioned plan approved by the Corporation

    for the changes suggested by Plaintiff for which Defendant No.1 has

    incurred expenditure of Rs. 3 crores prima facie subsisting and in

    existence on the suit premises could not have escaped the notice of

    Defendant No.2. The Defendant No.2 is pleading ignorance of nexus

    between Plaintiff and Defendant No.2 but in conduct it is also equal to

    that of the Defendant No.1 who has terminated the ATL and

    immediately within seven days issued a Letter of Intent to Defendant

    No.2 for the entire commercial property.

    55. That apart conduct of Defendant No.2 in completing due

    diligence speaks volumes about its conduct. The timeline and manner

    in which Defendant Nos. 1 and 2 have acted in cohort and executed

    the Letter of Intent and registered the Lease Deed clearly establishes

    their dubious conduct which no prudent, reasonable person would act

    in such a manner ever, and in the circumstances especially when

    consequences of the earlier ATL could be well within its knowledge.

    54

    ::: Uploaded on – 28/04/2026 ::: Downloaded on – 29/04/2026 06:09:18 :::

    901.IAL.9084.2026 & IAL.7684.20263.doc

    Thus, there are two prima facie findings which are rendered herein by

    me. Firstly, termination of ATL on both grounds was not in accordance

    with the clauses of the ATL especially and or the CP – 1 conditions,

    when the detailed correspondence between parties is observed by the

    Court which includes the Fire NOC and sanctioned plan approved by

    Corporation and which does not include the rejection letter by Society.

    56. Secondly, conduct of Defendant Nos. 1 and 2 on the face of

    record is nothing less than dubious whereby solely driven by greed for

    money and better terms and conditions which give a much higher

    return over a much larger period of time, Defendant No.1 has thrown

    caution to the winds and terminated the ATL on innocuous, untenable

    and illegal grounds only to enter into a much commercially profitable,

    lucrative contract with Defendant No.2, thereby repudiating the ATL.

    Contracts form the backbone of most business relationships. They

    establish rights and obligations of the parties involved. The grounds of

    frustration of ATL as pleaded by Defendant No.1 are therefore an

    illegal grounds pleaded for termination which are prima facie seen

    from the above findings.

    57. It is argued fairly by Mr. Dwarkadas that Defendant No.1

    accepted the fact that it had suggested to the Plaintiff as a viable

    alternative to take the entire commercial premises on lease. This is

    confirmed by the minutes of meeting dated 19.01.2026. According to

    55

    ::: Uploaded on – 28/04/2026 ::: Downloaded on – 29/04/2026 06:09:18 :::

    901.IAL.9084.2026 & IAL.7684.20263.doc

    the Defendant No.1 between 28.01.2026 and 19.02.2026 several

    meetings were held between the parties virtually. Hence grounds in

    the Termination Letter are nothing but a smokescreen created by

    Defendant No.1 as a ground to walk out of the ATL and enter into a

    much lucrative contract with Defendant No.2 which is to its advantage.

    58. In the present case, on the basis of the aforesaid

    observations and findings, I am of the clear opinion that all the

    parameters of injunction namely making out of a prima facie case,

    balance of convenience, irreparable loss and conduct of the parties

    clearly make out a case in favour of Plaintiff and do not entitle

    Defendant No.1 to terminate the ATL. The said termination is done by

    Defendant No.1 solely because Plaintiff refused to take the other

    balance half portion of the commercial property developed by

    Defendant No.1 alongwith the suit property as per the ATL and

    simultaneously Defendant No.1 had taken an internal decision to lease

    out the entire commercial property to one single party only.

    59. Hence, in such a situation when Defendant No.1 was already

    courting Defendant No.2’s proposal to take the entire commercial

    property on lease, it had no option than to wriggle out of the situation

    and terminate the ATL which it attempted to do so for the reasons

    stated in paragraph No.3 in the termination letter dated 20.02.2026.

    However, as alluded to herein above, the principal reason for

    56

    ::: Uploaded on – 28/04/2026 ::: Downloaded on – 29/04/2026 06:09:18 :::

    901.IAL.9084.2026 & IAL.7684.20263.doc

    termination is on the face of record illegal and unsustainable regarding

    receipt of NOC from the Fire Department. In so far as the second

    reason is concerned regarding boundary wall signage, the same is a

    complete non-starter whatsoever and during the course of submissions,

    Plaintiff has infact agreed to the issue of boundary wall signage and

    most importantly the said reason is without the rejection letter of the

    Society which Defendant No.1 has pleaded.

    60. Thus, in such facts and circumstances, Defendant Nos.1 and

    2 cannot plead that the contract with Plaintiff is determinable and

    compensable in terms of money. This is a situation where Defendant

    No.1 on being offered a better and profitable deal with respect to the

    entire commercial premises by Defendant No.2 has resiled from the

    ATL on innocuous and untenable grounds only to make its intentions

    very clear of entering into the Lease Deed with Defendant No.2.

    61. The conduct of defendant no.1 is such that it has on its own

    sweet will repudiated the contract i.e. ATL. The minutes of meeting

    dated 19.02.2026 prima facie also prove the fact that by that time

    Defendant No.1 was in all probability courted by Defendant No.2 and

    therefore the internal management of Defendant No.1 took a decision

    to lease the entire commercial property to one single party only.

    Though it is not explicitly clear but from the conduct of Defendant

    Nos.1 and 2 it clearly appears that both of them kept their negotiations

    57

    ::: Uploaded on – 28/04/2026 ::: Downloaded on – 29/04/2026 06:09:18 :::

    901.IAL.9084.2026 & IAL.7684.20263.doc

    and deal under wraps until Defendant No.1 terminated the ATL and

    within no time thereafter Defendant Nos.1 and 2 entered into the

    Lease Deed.

    62. In the present case, termination of ATL by Defendant No.1

    can be safely said to be a termination for convenience at its own sweet

    will, but if termination of convenience has to happen in view of

    Defendant No.1 getting a better deal, then it was incumbent upon

    Defendant No.1 to follow the due process of law and not illegally

    terminate the ATL in the manner in which it has done. Plaintiff has

    invested its efforts for the past more than 14 months since January

    2025 when Plaintiff and Defendant No.1 negotiated their deal. It

    initially entered into a term sheet in March 2025 followed by the ATL

    in September 2025, pursuant to which, substantial works were fully

    undertaken and fructified in the suit property for the purpose of

    Plaintiff opening its commercial store therein.

    63. Just as the aforesaid circumstances have offered a better

    deal to Defendant No.1 with Defendant No.2, in a similar manner

    when Plaintiff decided to take the suit property in 2025 it had also

    planned accordingly by shutting its two flagship stores in Bandra and

    Worli area and launching itself from the suit property in Chembur area

    with a projected turnover of 24 crore in its first year from the date of

    launch in June 2026. Defendant No.1 is on the other hand a renowned

    58

    ::: Uploaded on – 28/04/2026 ::: Downloaded on – 29/04/2026 06:09:19 :::

    901.IAL.9084.2026 & IAL.7684.20263.doc

    Company having its presence in all Sectors for past more than 125

    years. It has ventured into real estate in a big way and, it is also a

    prominent brand in India which is recognized for building a

    reputation, quality and trust. It is this trust which in my opinion which

    has been eroded by Defendant No.1 in the present case by issuing the

    Termination Letter in the manner in which it is done and within no

    time entering into a Lease Deed with Defendant No.2 – Titan

    Company.

    64. Defendant No. 1 has in the Short Cause Suit filed before the

    Bombay Civil Civil Court at Bombay on 23.02.2026 in paragraph No.1

    stated that it is a part of Godrej Industries Group which comprises of

    varied business portfolios. Copy of the Plaint is appended at page Nos.

    708 onwards. It would be appropriate to reproduce the said

    paragraph verbatim herein:-

    “1. Plaintiff is a company incorporated under the Companies
    Act, 1956
    and continuing under the Companies Act, 2013
    having its address at the place more particularly described in
    the cause title of the Plaint. The Plaintiff is a public limited
    company and is one of India’s most respected and diversified
    business conglomerates that has successfully created an
    enviable legacy of trust, leadership and admiration since its
    inception. The Plaintiff is a part of Godrej Industries Group
    which comprises of varied business portfolios that include real
    estate development, fast-moving consumer goods, advanced
    engineering, home appliances, furniture, security, and agri-care.
    The Appellant is amongst India’s most diversified and trusted
    conglomerates. The Plaintiff combines a 127-year legacy of
    excellence and trust with commitment to cutting-edge design
    and technology. The Plaintiff has received over 250 awards and
    recognitions, including the Porter Prize 2019, The Most Trusted
    Real Estate Brand in the 2019 Brand Trust Report, Builder of
    the Year at the CNBC-Awaaz Real Estate Awards 2019, The
    Economic Times 109 Best Real Estate Brand 2018, and Real

    59

    ::: Uploaded on – 28/04/2026 ::: Downloaded on – 29/04/2026 06:09:19 :::

    901.IAL.9084.2026 & IAL.7684.20263.doc

    Estate Company of the Year at the 8th Annual Construction
    Week India Awards 2018 for its quality and ethical business
    practices. The Plaintiff has consistently demonstrated and
    upheld the highest standards of integrity, business ethics, and
    corporate governance.”

    64.1. From the above, though it is a claim of Defendant No. 1 that

    it has consistently demonstrated and upheld higher standards of

    integrity, business ethics and corporate governance, in the facts of the

    present case after what transpired between Plaintiff and Defendant

    No. 1 on 19.02.2026 in the joint meeting held and the termination of

    ALT effected by Defendant No.1 on the following day and for all the

    aforementioned observations and findings, I am of the clear opinion

    that Defendant No. 1 has repudiated the ALT unilaterally for

    completely innocuous reasons which are not supported by the material

    placed on record. In fact Defendant No.1 has terminated the ALT

    solely on the ground that Plaintiff refused its offer to take the entire

    commercial area on lease and by which time Defendant No. 2 was

    ready and willing to take the entire commercial area from Defendant

    No. 1.

    64.2. This being the real reason is in fact suppressed by Defendant

    No. 1 in the termination letter and the termination is effected on

    completely innocuous, untenable and illegal grounds altogether. If

    such practices adopted by Defendant No. 1 are allowed to be

    perpetrated it would send a wrong signal to the Society at large

    considering that Defendant No.1 touts itself to be the most trusted real

    60

    ::: Uploaded on – 28/04/2026 ::: Downloaded on – 29/04/2026 06:09:19 :::

    901.IAL.9084.2026 & IAL.7684.20263.doc

    estate brand having received 250 awards and recognitions over the

    years. On the contrary, it is expected of Defendant No. 1 to maintain

    the highest standards and integrity, business ethics and corporate

    governance in such a case.

    65. I need not give any further reasons since on all parameters

    for grant of injunction, Defendant No.1 has failed in its endeavour to

    prima facie prove that its termination of the ATL is valid and legal in

    the present facts and circumstances of the present case before me.

    66. In that view of the matter, Defendant No.1 is restrained from

    taking any further steps with respect to handing over of the suit

    property on “as is” basis to Defendant No.2 and there shall be an

    injunction with respect to the suit property until the present Suit is

    decided. In so far as the remaining 50% of entire commercial area of

    the larger commercial property in the said project is concerned,

    Defendant No.1 shall be free to hand it over to Defendant No.2 on

    terms and conditions as available to the said parties. I reject the

    submissions made by Defendant No.2 that the registered Lease

    Agreement will have precedence over the ATL in the facts and

    circumstances of the present case in view of my aforesaid observations

    and findings, since the edifice on which the said Lease Deed has been

    executed and registered within no time of termination of the ATL

    raises grave suspicion and doubt of malafides on the part of Defendant

    61

    ::: Uploaded on – 28/04/2026 ::: Downloaded on – 29/04/2026 06:09:19 :::

    901.IAL.9084.2026 & IAL.7684.20263.doc

    No.1’s conduct.

    67. Both the Defendants are restrained from making any

    alterations in the suit property and are directed to maintain status quo

    thereof. In my opinion, in the aforesaid facts and circumstances, this

    is a fit case for appointment of Court Receiver in view of the dubious

    conduct of Defendant No.1 which has been opined and highlighted

    hereinabove so that the suit property should not be wasted in any

    manner. Hence, I am inclined to appoint the Court Receiver. Court

    Receiver, Bombay High Court so stands appointed for the suit property

    with all powers under Order XL of Civil Procedure Code, 1908. He is

    directed to take possession of the suit property forthwith and

    accordingly make a Report to the Court about the precise status of the

    suit property and give a copy of the said Report to Plaintiff and

    Defendant No.1. Until the Report is made by the Court Receiver, status

    quo to be maintained in regard to the suit property.

    68. Both the parties are at liberty to move the Court after the

    Court Receiver’s Report is made for any further orders. Court Receiver

    shall take possession of the suit property forthwith from Defendant

    No.2 and or any person in possession thereof and shall make a Report

    within a period of two weeks from today to enable the Court to take

    further steps in determining the conduct of operations in the suit

    property for any further dealing after hearing the parties.

    62

    ::: Uploaded on – 28/04/2026 ::: Downloaded on – 29/04/2026 06:09:19 :::

    901.IAL.9084.2026 & IAL.7684.20263.doc

    69. In so far as Defendant No.2 is concerned, since it has

    pleaded before me that it is a bonafide purchaser for value without

    notice of the ATL, in the aforesaid facts and circumstances, it shall be

    open to Defendant No.2 to take appropriate steps as available to it in

    law against the Defendant No.1.

    70. All contentions of the parties are expressly kept open.

    71. In so far as Defendant No.2 is concerned, it is restrained

    from creating any changes or construction in respect of the suit

    property and from acting it in furtherance of its Lease Deed dated

    04.03.2026 in so far as the suit property is concerned. In so far as the

    other remaining 50% commercial property is concerned, Defendant

    No.2 will be free to take steps as available to it in law in that regard in

    accordance with law or according to the lease deed.

    72. With the above directions, Interim Application (L) No.9084

    of 2026 and Interim Application (L) No.7684 of 2026 are allowed and

    disposed.

    73. All parties are directed to act on a server copy of this order

    downloaded from the website of the High Court of Bombay.

    74. Liberty to apply.

    75. List the Suit as per its turn.

    [ MILIND N. JADAV, J. ]

    63

    ::: Uploaded on – 28/04/2026 ::: Downloaded on – 29/04/2026 06:09:19 :::

    901.IAL.9084.2026 & IAL.7684.20263.doc

    76. After the above order is pronounced in Court Mr.

    Dwarkadas, learned Senior Advocate persuades the Court to stay the

    order appointing Court Receiver in order to enable Defendant No.1 to

    test the validity and legality of this order before the superior Court.

    77. I have considered the request made by Mr. Dwarkadas.

    However, in view of my prima facie observations and findings which

    are rendered hereinabove, I am not able to persuade myself to accede

    to the request made by Mr. Dwarkadas. The request for stay of Court

    Receiver’s appointment is declined.

    H. H. SAWANT                                                 [ MILIND N. JADAV, J. ]
    
                              Digitally
                              signed by AJAY
                              TRAMBAK
                   AJAY       UGALMUGALE
                   TRAMBAK
                   UGALMUGALE Date:
                              2026.04.28
                              13:18:04
                              +0530
    
    
    
    
                                                                                                     64
    
    
                         ::: Uploaded on - 28/04/2026                   ::: Downloaded on - 29/04/2026 06:09:19 :::
     



    Source link

    LEAVE A REPLY

    Please enter your comment!
    Please enter your name here