Pulinat Ettan Thomas vs Finorchem Limited on 16 July, 2026

    0
    6
    ADVERTISEMENT

    Calcutta High Court

    Pulinat Ettan Thomas vs Finorchem Limited on 16 July, 2026

    Author: Debangsu Basak

    Bench: Debangsu Basak

                                        IN THE HIGH COURT AT CALCUTTA
                                          CIVIL APPELLATE JURISDICTION
                                              (COMMERCIAL DIVISION)
                                                       ORIGINAL SIDE
    
                      Present:
                      The Hon'ble Justice Debangsu Basak
                                           And
                      The Hon'ble Justice Md. Shabbar Rashidi
    
    
                                                     AD-COM 02 of 2026
    
                                                 Pulinat Ettan Thomas
                                                            Vs.
                                                     Finorchem Limited
    
    
                      For the appellant          :      Mr. Aniruddha Mitra, Sr. Adv.
                                                        Mr. Sayan Banerjee, Adv.
    
    
                      For the respondent         :      Mr. P. P. Bishwal, Adv.

    Ms. Swastikaa Ray, Adv.

                      Hearing concluded on :            30.06.2026
    
    
                      Judgment on                :      16.07.2026
    
    
    
                      Md. Shabbar Rashidi, J.:-
    
    

    1. The appeal at the behest of defendant in the suit is directed

    SPONSORED

    against the judgment dated August 1, 2025 and consequential

    decree dated November 17, 2025 passed in CS-COM No. 175 of

    2024.

    SK SOHEL Digitally signed by
    SK SOHEL UDDIN

    UDDIN 14:43:35 +05’30’
    Date: 2026.07.16
    2

    2. By the impugned judgment and decree, the learned Trial

    Judge decreed the suit and directed the defendant to pay a sum of

    ₹55,47,422/- along with interest calculated at the rate of 8% per

    annum payable from the date of institution of the suit. At the same

    time, the counter claim preferred by the defendant was dismissed

    by the impugned judgment and decree. The learned Single Judge

    disposed of the suit being CS-COM No. 175 of 2024 in the following

    terms:

    “It is ordered, therefore, that the Defendant shall pay
    the principal sum adjudged of Rs.55, 47,422/- to the
    Plaintiff with interest at a rate of 8% per annum from the
    date of institution of the suit. The decretal amount shall be
    paid within three months from the date of decree in case of
    failure of which the Defendant shall be liable to pay
    additional interest of 2% per annum from the expiry of the
    three months on the principal sum adjudged till repayment.
    After expiry of the said period of three months, the Plaintiff
    shall be at liberty to draw up execution proceeding to
    enforce the decree in case of non-payment.

    The counter-claim stands dismissed.

    The suit is disposed of.

    Let the decree be drawn up.”

    3. Learned senior advocate for the appellant submitted that

    the learned Trial Judge committed error in holding that the

    agreement dated August 2, 2019 constituted a contingent contract

    in terms of the provision of Sections 31 and 32 of the Indian
    3

    Contract Act, 1872 (for short, ‘the Act of 1872’) insofar as the

    contract did not stipulate any uncertain future event. It was further

    submitted that the learned Single Judge failed to appreciate that

    the final agreement executed between the parties did not specify the

    number or the names of the experts and, therefore, no enforceable

    contingency could have been read in the contract. The learned

    Single Judge also failed to take into account that the list of experts

    as provided in the agreement dated August 2, 2019 was provided by

    the appellant to the respondent.

    4. Learned senior advocate for the appellant also contended

    that the learned Single Judge erred in taking into consideration the

    terms and conditions of a draft agreement as the final agreement

    which was contrary to Clause 12 of the agreement entered into

    between the parties. Such clause was in supersession of all

    previous drafts, negotiations and understandings between the

    parties.

    5. Learned senior advocate for the appellant also submitted

    that the learned Single Judge was not justified in holding that

    ‘seven’ experts were contemplated under the agreement which is not

    supported by any document whatsoever. The learned Trial Judge

    also erred in construing the provisions of Sections 31 and 32 of the

    Act of 1872 inasmuch as the joining of experts was neither an
    4

    uncertain event nor collateral to the contract between the parties.

    The learned Trial Judge was not justified in holding that the

    contract became unenforceable due to failure of the event of

    contingency in absence of the proof of impossibility.

    6. Learned senior advocate for the appellant also submitted

    that the learned Single Judge did not appreciate that the evidence

    adduced at the trial as PW 1 was not reliable. PW 1 admittedly had

    no knowledge of the post-agreement events, discussions and

    services rendered by the appellant. At the same time, learned senior

    advocate for the appellant submitted that the learned Single Judge

    ought to have drawn adverse inference against the

    plaintiff/respondent for not examining its Managing Director which

    amounted to withholding the vital evidence. Moreover, the testimony

    of PW 1 was self-contradictory.

    7. Learned senior advocate for the appellant also submitted

    that the learned Trial Judge failed to appreciate the testimony of PW

    1 which established rendering of services and visits to

    manufacturing units as well as the business development efforts

    taken by the appellant. The documentary evidence in the form of

    WhatsApp communications, emails and tax invoices, which

    supported the testimony of DW 1, was not considered by the

    learned Trial Court. In support of such contention, learned senior
    5

    advocate relied upon (2016) 12 Supreme Court Cases 288

    (Muddasani Venkata Narsaiah Vs. Muddasani Sarojana).

    8. It was further contended by the learned senior advocate for

    the appellant that the learned Trial Judge was not justified in

    holding that the appellant’s appointment had never commenced.

    The learned Single Judge overlooked the admitted payment,

    deduction of TDS and issuance of tax invoices which established the

    continuous engagement of the appellant by the respondent. The

    learned Trial Judge also was not justified in holding that there was

    no binding contract between the appellant and the respondent

    inspite of the fact that the conduct of the parties established that

    the parties were ad idem in respect of the existence of a contractual

    relationship.

    9. It was further contended by learned senior advocate for the

    appellant that there was clear evidence that the appellant rendered

    services and benefits which were availed by the respondent. Such

    fact was not considered by learned Trial Judge. The learned Trial

    Judge negated the claim of the appellant by misapplying the

    provision of Section 72 of the Act of 1872.

    10. Learned senior advocate for the appellant also submitted

    that the learned Trial Judge wrongly dismissed the counter claim

    put forth by the appellant, though, the respondent/plaintiff chose
    6

    not to submit any additional written statement. It was also

    submitted by learned senior advocate for the appellant that the

    appellant was entitled for severance, fees and remuneration in

    terms of the provisions of Clause 14 and Clause 17 of the

    agreement which were overlooked by the learned Trial Judge.

    11. Learned senior advocate for the appellant also submitted

    that the learned Trial Judge committed error in considering the

    clause relating to ‘simultaneous joining’ as a condition precedent

    and on such basis, the appointment of the appellant was held to be

    void and inoperative for non-joining of the other experts. It was

    submitted that the learned Trial Judge erred in not considering that

    the respondent, having availed professional services of the appellant

    for several months was estopped from contending that the contract

    never commenced or was not enforced. The respondent accepted the

    services of the appellant nevertheless denied the existence of any

    contractual relationship with the appellant. Moreover, the learned

    Single Judge did not consider that in a contingent agreement,

    performance commenced with the consent of the parties which

    amounted to waiver of the contingency.

    12. Learned senior advocate for the appellant also submitted

    that there was no agreement between the appellant and the

    respondent to recommend a fix number of experts. Whereas the
    7

    learned Single Judge erroneously held the contract unenforceable

    on the ground that all the ‘seven’ experts were not recommend by

    the appellant. In fact, the learned Single Judge did not appreciate

    that the appellant recommend more than ‘seven’ experts to the

    respondent. By limiting the number of the recommendations to be

    made by the appellant, the learned Single Judge erred in

    considering the true purport of the agreement which amounted to

    re-writing of the agreement. It was also submitted that admittedly

    ‘four’ experts had already joined to the plaintiff concerned. The

    learned Single Judge failed to consider the joining of the ‘four’

    experts as part performance of the agreement. Learned senior

    advocate for the appellant submits that such part performance

    coupled with rendering services by the appellant gave rise to a claim

    on the basis of ‘quantum meruit’, which was not considered by the

    learned Single Judge. The learned Single Judge did not consider the

    provisions contained under Section 70 of the Act of 1872. In

    support of such proposition, learned senior advocate for the

    appellant relied upon the authority of (2007) 13 Supreme Court

    Cases 544 (Food Corporation of India and Others Vs. Vikas

    Majdoor Kamdar Sahkari Mandli Limited).

    13. Learned senior advocate for the appellant also submitted

    that the learned Single Judge failed to appreciate that the services
    8

    and expertise rendered by the appellant were accepted by the

    respondent, nevertheless, the learned Single Judge directed the

    appellant to refund all the monies paid in advance to the appellant.

    The learned senior advocate for the appellant also submitted that

    the claim of interest on such money was not supported by any

    contractual or statutory provision and also without proof of the

    actual damages suffered by the respondent rather; the same was

    awarded in the form of penalty.

    14. On the other hand, learned advocate for the respondent

    submitted that the respondent had hired the services of the

    appellant as part of a team of experts of business consultant in the

    Rubber Chemical field. It was agreed between them that the seven

    experts would be joined in the assignment simultaneously and that

    the contract of engagement of each member of the team of expert

    would kick start with the joining of all the seven experts. Since all

    the seven experts did not join, the contract of employment of the

    appellant with the respondent company never commenced.

    15. According to learned advocate for the respondent, the

    agreement between the appellant and respondent was in the form of

    a contingent contract dependent upon happening of a future event

    which did not happen. Therefore, the alleged agreement between the
    9

    parties cannot be enforced in view of the provisions of Section 31

    and 32 of Indian Contract Act, 1872.

    16. Learned advocate for the respondent further submitted that

    at the time of agreement, the respondent/plaintiff, at the request of

    the appellant, had made an advance payment of a sum of ₹

    50,47,422/- to the appellant. Since, the contract of engagement of

    the appellant with the respondent company did not commence for

    non-joining of the remaining members of the team of experts, the

    appellant is liable to refund the advance. At the same time, learned

    advocate for the respondent also submitted that for the self-same

    reasons, the appellant is not entitled to the monthly remuneration

    fixed in the agreement dated August 2, 2019.

    17. Learned advocate for the respondent also submitted that

    since the agreement between the appellant and the respondent was

    yet to be commenced, the appellant has not rendered any service to

    the respondent company. The respondent has not utilized any

    services from the appellant. As such, the appellant is not entitled to

    any remuneration in terms of the alleged agreement. He stood by

    the impugned judgment and decree and submitted that the same is

    liable to be affirmed.

    18. The plaintiff company negotiated with the defendant to join

    its concern as business consultant. An agreement in this regard
    10

    was executed between the two parties on August 2, 2019. According

    to the case made out in the plaint, the defendant represented

    himself to be an expert in rubber chemical field. He further

    represented that he was in a team of such experts in rubber

    chemical field. Plaintiff/respondent required a team of experts from

    rubber chemical field. It was agreed between the defendant and the

    plaintiff company that the defendant and his seven associates

    namely, Dr. Jaybalan Lakhmanan, Mr. Thomas Valera, Mr.

    Yashwant VA, Mr. Praveen Patil, Mr. Manoj Choudhury, Mr.

    Mukesh Singh and Mr. Mathew would join simultaneously. The

    plaintiff company was not interested in appointing the

    appellant/defendant alone. The plaintiff had specifically given out

    that in case all the seven experts or any of them does not join, the

    respondent would search for another team. Accordingly, the

    respondent issued a letter to the defendant on August 2, 2019. At

    the request of the appellant/defendant, the respondent/plaintiff

    also made an advance payment of ₹ 50,47,422/-. According to the

    case of the respondent/plaintiff, the appointment letter issued in

    favour of appellant, clearly stipulated that the appointment of the

    appellant would commence when the defendant and other experts

    join simultaneously.

    11

    19. However, the plaintiff company could appoint only four of

    the named experts namely Mr. Praveen Patil, Mr. Manoj Choudhury,

    Mr. Mukesh Singh and Mr. Mathew. According to the case of the

    respondent made out in the plaint, the agreement did not come into

    effect as the other three experts Dr. Jaybalan Lakhmanan, Mr.

    Thomas Valera, Mr. Yashwant VA did not join.

    20. On such pretext, the respondent/plaintiff came up with the

    suit being CS-COM No. 175 of 2024 seeking a declaration that the

    appointment of the appellant in the respondent company had not

    commenced. The respondent also sought refund of the advance sum

    of ₹50,47,422/- together with interest, since the contract between

    the parties had failed.

    21. The suit was contested by the defendant/appellant by filing

    written statement coupled with a counter claim. The defendant

    denied all the material allegations made in the plaint. It was the

    positive case of the defendant that the defendant was approached

    by the plaintiff company with a proposal to work as a business

    consultant in the capacity of ‘Chairman Emeritus’. The defendant

    agreed to such proposal. Consequently, a letter of appointment was

    issued in his favour on August 2, 2019 which contained the terms

    and conditions of the appointment.

    12

    22. It was further case of the appellant the parties also agreed

    that the respondent would appoint some experts in the field of

    Rubber Chemical and requested the appellant to recommend such

    experts who would be finally appointed by the respondent after due

    negotiations. The appellant actually, recommended some experts.

    Out of his recommendation, four experts were appointed by the

    respondent/plaintiff in August 2019. The appellant submitted that

    other persons recommended by him were not under his authority

    that they could be forced to join the plaintiff company. It was

    further case of the appellant, in his written statement that his

    appointment with the plaintiff was completely independent and had

    no nexus with the joining of other experts recommended by him.

    Since his joining in the plaintiff company, the appellant/defendant

    discharged his job responsibilities in strict compliance of the terms

    of job profile enumerated in his letter of appointment.

    23. According to the case made out by the

    appellant/defendant, it was agreed that the appellant would be paid

    a sum of ₹1,50,00,000/- upfront on his joining in the respondent

    company. Out of such agreed amount, the respondent paid a sum of

    ₹50,00,000/- at the time of his joining. The respondent did not pay

    the remaining amount of ₹1,00,00,000/- inspite of repeated

    demands. However, the appellant came out with a case that the
    13

    respondent company never denied its liability to pay the balance

    amount. Besides the upfront payment, it was also agreed that the

    appellant would be paid a sum of ₹15,00,000 a month as

    consultancy fee together with travelling, food and lodging expenses

    on actuals. However, despite raising such bills, the respondent did

    not reimburse a sum of ₹58,770.47/- towards such expenses. The

    respondent company also did not pay the agreed consultancy fees

    for the months of August, September, October and November, 2019

    although, the appellant rendered extensive services. The respondent

    company utilized the services so rendered.

    24. It was the further case of the appellant/defendant that by

    an email message dated September 7, 2019, the respondent was

    informed that in terms of the discussions the experts namely Dr.

    Balan, Mr. Thomas Valera and Mr. Yashavant were to join the

    Plaintiff/Company with the Defendant but they did not join.

    Following such email, the respondent also served a letter dated

    November 23, 2019 upon the appellant intimating him that

    Defendant’s appointment in the plaintiff company had not

    commenced as it was agreed to commence upon the joining of other

    experts. By the said letter, the plaintiff also sought refund of

    ₹55,00,000/-.

    14

    25. By filing the written statement, the appellant/defendant

    denied all the allegations made in the plaint. The defendant also

    took out a counter claim which was noted by learned Trial Judge. It

    would be apposite to reproduce the heads of counter claim made by

    the appellant in his written statement that is to say:

    “i) Balance payment payable on appointment ₹1,00,00,000/-

    ii) Fees for the month of August, 2019 ₹17,70,000/-

    iii) Fees for the month of September, 2019 ₹17,70,000/-

    iv) Fees for the month of October, 2019 ₹17,70,000/-

    v) Fees for the month of November, 2019 ₹17,70,000/-

      vi) Reimbursement of expenses                            ₹58,770/-
    
          for travel, food and lodging
    
      vii) Severance fee as per Clause                         ₹50,00,000/-
    
          14 of the agreement dated 02/08/2019
    
      viii) Interest at a rate of 18% p.a.                     ₹59,77468/-
    
      Total                                                    ₹2,81,16,238/-"
    
    
    

    26. On the basis of rival pleadings put in by the parties, the

    learned Trial Judge, framed as many as 12 issues for proper

    adjudication of the disputes which are,

    1. “Is the suit maintainable in its present form?

    2. Are the claims and the counter-claim barred by the laws of

    limitation?

    15

    3. Is the Plaintiff right in alleging that the Defendant’s

    appointment did not take effect as all the seven experts did

    not join the Plaintiff along with the Defendant?

    4. Whether the appointment of the Defendant was dependent

    upon all the seven other experts joining the Plaintiff Company?

    5. Whether the Plaintiff is entitled to its claim for refund of

    Rs.55,47,422/- or any part thereof?

    6. Whether the Defendant is entitled to fees and expenses as

    agreed upon as per the Terms of Engagement dated 2nd

    August, 2019?

    7. Whether the Defendant is entitled to the sum of Rs.2,81, 16,

    238/- as claimed?

    8. Whether the Defendant is entitled to any compensation for the

    valuable knowledge imparted to the Plaintiff?

    9. What other reliefs the parties are entitled to?

    10. Whether the appointment of the Defendant as a business

    consultant in the Plaintiff did not fructify in view of the fact

    that the experts did not join the Plaintiff?

    11. Whether the Defendant is entitled to the reliefs claimed in the

    written statement and the counter-claim?

    12. Whether the reliefs claimed in the written statement and the

    counter-claim are barred by limitation?”

    27. It was noted in the impugned judgment and decree that the

    parties did not press and argue issue nos. 1, 2 and 12 at the time of
    16

    hearing of the suit. The learned Trial Judge also held that the suit

    as well as the counter claim was presented within the time of

    limitation. Consequently, the learned Trial Court decided the issues

    in favour of the plaintiff/respondent. The aforesaid issued were not

    raised during the hearing of instant appeal as well. In such view of

    the facts, we find no reason to interfere with the findings of the

    learned Trial Judge in respect of these issues.

    28. Issue nos. 3, 4 and 10 namely, were taken up together by

    the learned Trial Judge. Evidence on record goes to demonstrate

    that the plaintiff company and the defendant were in a negotiation

    regarding appointment of the defendant. According to the case

    made out in the plaint, the defendant had agreed to join the plaintiff

    company as a business consultant along with seven other experts

    on certain terms and conditions. One of the conditions was that the

    appointment of the defendant was agreed to commence with the

    joining of defendant and other seven experts simultaneously. Per

    contra, the defendant came up with a case that he agreed to

    recommend certain other experts in the Rubber Chemical field who

    were to be appointed by the plaintiff company after due

    negotiations. According to defendant’s case, he actually

    recommended some names of such experts, out of which, four

    persons joined the plaintiff company.

    17

    29. A case was made out by the defendant that under the

    agreement, he was obliged to recommend the names of some

    experts in the field of Rubber Chemical and that there was no

    stipulation in the agreement to recommend specific persons or

    specified number of such experts. Therefore, the appointment of the

    defendant was independent of such recommendation and

    commenced when appointment letter was served upon him.

    30. The learned Trial Judge decided issue nos. 3, 4 and 10 in

    favour of the plaintiffs to the following terms, that is to say:

    “Clause 1 of the agreement is very clear and
    conspicuous. This Clause stated that appointment of the
    Defendant would commence on simultaneous joining of
    other experts from rubber chemicals field. From forgoing
    discussions, it is clear and established that seven experts
    were to be appointed based on recommendation of the
    Defendant and approval of the Plaintiff. The Defendant
    accepted this term as pre-condition for his appointment.
    Subsequently, a plea was taken that their appointment
    dependent on their own will and approval of the Plaintiff
    but the Defendant agreed to the terms and bound himself
    with its terms and conditions as stipulated in Clause 1.
    Once it is accepted and agreed upon that the Defendant’s
    appointment was dependent of simultaneous joining of
    other experts, he is bound by such term; there was no exit
    rout from that. It is admitted that seven experts were not
    appointed or did join. The case of the Defendant was that
    four of them joined. It is not established that the Defendant
    recommended the names of all the seven experts. Therefore,
    18

    obviously and very clearly, in the absence of joining all the
    seven other experts the Defendant’s appointment did not
    take place. It is not a case that their appointment became
    subsequently impossible. No such plea is there. Therefore, it
    is safe conclusion, in view of discussions made above, that
    there was a contingent contract between the parties dated
    02/08/2019. Since the contingency failed, no formation of
    contract took place and the contract became unenforceable
    under Section 32 of the Contract Act, 1872.

    It is inevitable conclusion, therefore, that there was no
    binding and enforceable agreement or contract between the
    parties.

    Issue No.3, 4 and 10 are decided in favour of the
    Plaintiff.”

    29. While deciding these issues, the learned Trial Court held

    that the agreement between the plaintiff company and the defendant

    was a contingent contract depending upon the joining of the other

    seven experts. The learned Trial Judge, although held in reference to

    Exhibit D, that the agreement was not explicit in relation to the

    number or specific names of experts but referring to Exhibit B, it

    observed that the draft agreement, which ultimately culminated into

    final agreement (Exhibit D) had a reference of specific names of

    experts who were to join the plaintiff company concurrently with

    defendant to kick start the appointment of defendant. Besides that,

    in answer to question No. 16, the defendant (DW1) stated that

    basically he had suggested seven names to the plaintiff company
    19

    but it was his request not to include his suggestions in the

    agreement.

    30. Clause 1 of Exhibit D i.e. agreement dated August 2, 2019

    stipulated that the appointment of the Defendant in the

    Plaintiff/Company as the business consultant would commence on

    joining simultaneously with joining of other experts from rubber

    chemicals field. It also provided that the experts would be selected

    and recruited based on recommendation of the Defendant and

    approval of the Plaintiff. However, referring to the evidence of DW1,

    the learned Trial Court observed that DW1, in his deposition, when

    his attention was drawn to Exhibit B, admitted that he had

    recommended the name of seven experts. He had further stated in

    his deposition that basically he had suggested seven people to be

    inducted but told Mr. Holani not make it a part of the agreement.

    Learned Trial Court also noted that DW 1 reiterated in his cross-

    examination at question no. 122 that in the draft document Mr.

    Holani and himself had mentioned seven experts but on suggestion

    of the Defendant those names were not incorporated in the final

    agreement because their joining was subject to the personal

    decisions and subject to the approval of the Plaintiff. Such evidence

    by the defendant himself together with various Clauses of the

    agreement dated August 2, 2019 (Exhibit D) clearly indicates the
    20

    intention of the parties that the parties had agreed on simultaneous

    appointment of defendant and seven experts named in Exhibit B

    and that the appointment of defendant was to commence upon

    joining of all such experts. In view of the evidence so discussed

    hereinabove, we find no reason to fault the findings of learned Trial

    Judge.

    31. Issue nos. 5, 6, 7, 8, 9 & 11 with regard to refund of the

    advance money paid by the plaintiff to the defendant as well as

    counter claim raised by the defendant were decided by learned Trial

    Judge together. The plaintiff claimed that a sum of ₹55,47,422/-

    was paid to the defendant in pursuance of an agreement dated

    August 2, 2019 (Exhibit D). Such money was paid as advance, in

    anticipation of an enforceable contract. However, the contract

    became unenforceable on account of non-happening of contingency

    contemplated in the agreement. Since the agreement failed, the

    defendant is liable to refund such advance payment.

    32. On the contrary, it was the case of the defendant that his

    appointment in the plaintiff company was not dependent upon the

    simultaneous joining of other seven experts. He received the amount

    under the agreement and had been discharging his obligations as

    business consultant from the very time when he received his

    appointment letter. The agreement entered into between the
    21

    defendant and the plaintiff company was in force after its execution.

    Therefore, he is not liable to refund the money received under the

    contract. Besides that, the defendant also made out a case that

    since after his appointment in terms of appointment letter dated

    August 2, 2019, the defendant has been diligently rendering

    services to the plaintiff company as a business consultant. The

    plaintiff company has also utilized his services in such capacity

    without any demur. Therefore, the plaintiff is obliged to pay the

    defendant the monthly consultation fee as agreed in the agreement.

    The plaintiff also did not pay the agreed travelling expenses as well

    as lodging and boarding expenditure incurred by the defendant in

    discharge of his obligations under the contract. The defendant, on

    such heads, made a counter claim to the tune of ₹2,81,16,238/- as

    against the plaintiff company.

    33. The learned Trial Court decided Issue nos. 5, 6, 7, 8, 9 & 11

    to the following terms:

    “It is the case of the Defendant that the agreement
    came into being and he took money on the strength of the
    agreement. The case of the Plaintiff, on the other hand, is
    that the money was nothing but advance payment. As
    decided above, the executory contract could not be
    performed and stood unenforceable in view of failure of the
    contingency on which the agreement dependent. The
    Defendant cannot be allowed to retain the money so
    received from the Plaintiff for his unjust enrichment. Money
    22

    was paid on expectation of fulfillment of the contingency.
    The contingency did not happen. Therefore, the Defendant
    is liable to refund money taken under an unenforceable
    contract. This is based on the principal “Nul ne doit
    senrichir aux depens des autres”–No one ought to enrich
    himself at the expense of others. This doctrine at this stage
    of English common law was remedied by indebitatus
    assumpsit which action lay for money had and received to
    the use of the Plaintiff. In Mahabir Kishore & Ors. Vs. State
    of Madhya Pradesh
    [(1989) 4 SCC 1], the Supreme Court
    India observed that it lay to recover money paid under a
    mistake, or extorted from the Plaintiff by duress of his
    goods, or paid to the Defendant on a consideration which
    totally failed.
    In Mafatlal Industries Ltd. Vs. Union of India
    [(1997) 5 SCC 536], the principal so laid down was
    considered by the Nine Judges Bench of the Supreme Court
    of India with reference to this case.
    The principal laid down
    in
    Mahabir Kishore‘s case was reiterated that the principal
    of unjust enrichment requires – first that the Defendant has
    been enriched by the received of a benefit; that this
    enrichment is an expense of the Plaintiff and thirdly that
    retention of the enrichment is unjust. This justifies
    restitution.
    Money can be refunded under provision of
    section 72 of the Indian Contract Act, 1872, which itself
    embodies the principle of equity (see Mafatlal Industries
    Ltd. Vs. Union of India
    [(1997) 5 SCC 536]). Similarly, the
    Defendant cannot rely upon an unenforceable contract to
    vindicate his right to demand any money as claimed here.
    In absence of any executed and enforceable contract, the
    Defendant cannot claim money as prayed for in the counter-
    claim.”

    23

    For reasons stated above, this Court is of opinion that
    Plaintiff’s case succeeds and the Plaintiff is entitled to
    recover the money from the Defendant and the Defendant is
    liable to pay the amount to the Plaintiff with interest. This is
    also conclusion of this Court that the Defendant has not
    right to claim any money as prayed for.

    In nutshell, the plaint case succeeds and the counter-
    claim fails.

    These issues are decided in favour of the Plaintiff.”

    34. On the basis of evidence led at the trial, we have held

    hereinbefore, that since the defendant did not join simultaneously

    with the other seven experts, agreed in the negotiations between the

    parties, the contract of employment of the defendant did not

    commence. Although, the defendant has made out a case that the

    appointment of the other experts was not within his control and

    contractual obligation, but, materials on record establishes that the

    defendant/appellant expressively accepted such condition. He

    cannot now turn around to say that the other experts were not

    under his control. Apparently, the money was advanced to the

    defendant in relation to engagement of the defendant and other

    experts in the plaintiff company. Since, such engagement was not

    started; the defendant has had no right to retain such money

    advanced to him which was dependent upon the terms of his

    engagement. He is liable to refund the same to the plaintiff.
    24

    35. So far as the counter claim of the defendant is concerned,

    the defendant has claimed a sum of ₹2,81,16,238/- as counter

    claim. This amount includes ₹1,00,00,000/- towards the balance of

    upfront amount of ₹1,50,00,000/- which was agreed to be paid

    upon joining of the defendant in the plaintiff company in terms of

    Para I of the letter dated August 2, 2019 (Exhibit D) which reads,

    thus:

    “Your appointment with ML as a business consultant will
    commence on your joining ML simultaneously with joining of
    other experts from the rubber chemicals field. The aforesaid
    experts will be selected and recruited based on your
    recommendation and our approval thereof. These experts
    will be absorbed in ML for the smooth running of the
    business and those experts will be absorbed as consultants
    or on permanent employment in the payroll of ML at not less
    than their current emoluments. Your appointment as above
    shall be valid from the date of joining of all aforesaid
    experts and shall be in force for a period of 5 (Five) years
    unless terminated/separated earlier by either side subject
    to the terms and conditions mentioned herein below.”

    36. At the same time, as per the letter dated August 2, 2019

    (Exhibit D), the defendant was entitled to various remuneration and

    incentives detailed in Para 17 of such letter. It would be appropriate

    to set out paragraph 17, which is as follows:

    “17. (A) Against compliances/provision of services
    mentioned in Para 16 above, you will be entitled to receive
    25

    i. Fixed amount of ₹.1.80 crores (₹. 1 crore 80 lakhs only)
    per annum, which will be payable to you on monthly
    basis at the end of every month in equal instalments
    of ₹ 15 lakhs (₹ Fifteen lakhs only) per month,
    ii. ₹. 150 lakhs (rupees one crore Fifty lakhs only) after
    your appointment as referred to in paragraph 1
    hereinabove.

    iii. Loyalty Bonus of ₹ 1 50 lakhs (Rupees One Crore Fifty
    Lakh only) on completion of rendering of your services
    person to the sacrament for and an interrupted period
    of 2 years (Two Years) from the date of your
    appointment as referred to in para 1 hereinabove.
    iv. Special Loyalty Bonus of ₹ 200 lakhs (Rupees Two
    Crore only) on completion of rendering of your
    services person to the sacrament for and an
    interrupted period of 4 years (Four Years) from the
    date of your appointment as referred to in Para one
    hereinabove.

    v. While on official tour, he will be entitled for travelling,
    food & lodging as per actual incurred in terms of
    policy of ML in this regard.

    (B) In case ML gets opportunity to use and utilise
    manufacturing facilities at Marchem India Private
    Limited by virtue of outright purchase on mutually
    amicable terms and condition, you will be entitled to
    receive such additional sum as may be decided to
    mutually between you and ML after ML gets the said
    opportunity.”

    37. As noted above, the appointment of appellant/defendant

    did not start in terms of the condition envisaged at Para 1 of the

    agreement, the defendant was not entitled to retain the sum of
    26

    ₹55,47,422/-paid in advance towards the payment contemplated in

    Para 17 (A)(ii) of the agreement dated August 2, 2019. The

    defendant is liable to refund such amount. We therefore, affirm the

    findings of learned Trial Court, in so far as refund of advance money

    is concerned. Applying the same analogy of non-starter of the

    employment, the claim of defendant towards severance fee in terms

    of clause 14 of the agreement dated August 2, 2019 cannot be

    allowed.

    38. So far as payment under the condition envisaged at Para 17

    (A)(i)of the agreement is concerned, the defendant was to receive a

    remuneration of ₹15,00,000 a month on account of consultation fee.

    According to the case of the plaintiff company, since the

    appointment of the defendant did not kick start, the defendant was

    not entitled for such payment. On the other hand, the defendant

    claims that upon his engagement in the plaintiff company in terms

    of an appointment letter issued in his favour, the defendant has

    been rendering diligent services to the plaintiff. He travelled

    extensively under directions of the plaintiff company and provided

    his expertise for smooth functioning of the plaintiff company in

    accordance with the terms and conditions of his engagement. The

    plaintiff company never raised any objection rather, utilized such

    services without any demur and therefore, the defendant is entitled
    27

    to the monthly consultation fees for the months of August,

    September, October and November 2019. The defendant also

    claimed travelling, food and lodging expenses incurred by him

    amounting to ₹58,770/-.

    39. At the time of his cross examination, the answer to question

    numbers 27 and 28 by the defendant (DW1) shows that the

    defendant was neither aware of the location of the office of Plaintiff

    Company nor he visited such office. As regards the claim of the

    plaintiff that he rendered services to the Plaintiff Company, answer

    to question no. 32, DW1 stated that he had been interacting with

    Mr. Holani, the Managing Director of the company on almost daily

    basis and that too, at the direction of Mr. Holani. He used to be in

    discussions with unit heads at Panoli, Gujrat and Cochin, Kerala

    and suggested various measures to be undertaken for

    commissioning the plants in Panoli and Cochin. He also personally

    visited Panoli Plant and called joint meeting in presence of Mr.

    Holani. All other team members including the General Manager and

    unit head participated in the discussions, exchanged information

    and several documents required for commissioning the unit.

    40. DW1 further stated in such deposition that in Cochin Plant

    also he held several meetings. The General Manager and Mr. Holani

    visited his office in Cochin a couple of times to obtain appropriate
    28

    directions to proceed with the commissioning of the plant. DW1 also

    travelled to Mumbai to assist Mr. Holani in taking interview of

    certain other persons who were discussed by the defendant and the

    plaintiff Company. DW1 also stated in his deposition that he used to

    send his bills through electronic mail and WhatsApp messages.

    41. However, we find from the materials on record, specially the

    deposition of DW1 that the plaintiff has not cross examined DW1 as

    to his claim regarding holding of meetings and providing expert

    support for commissioning of the Panoli and Cochin plants of the

    plaintiff company in presence of Mr. Holani and others. There is

    absolutely no cross examination of DW1 that as to his statement

    that he undertook travel to Mumbai to assist Mr. Holani in the

    recruitment interview. Moreover, the witness examined on behalf of

    the plaintiff company (PW1) was not conversant with and had no

    personal knowledge about the facts of the case.

    42. In Muddasani Venkata Narsaiah (supra), it was observed

    by the Hon’ble Supreme Court that,

    “15. Moreover, there was no effective cross-examination
    made on the plaintiff’s witnesses with respect to factum of
    execution of sale deed, PW 1 and PW 2 have not been cross-
    examined as to factum of execution of sale deed. The cross-
    examination is a matter of substance not of procedure one
    is required to put one’s own version in cross-examination of
    opponent. The effect of non-cross-examination is that the
    29

    statement of witness has not been disputed. The effect of
    not cross-examining the witnesses has been considered by
    this Court in Bhoju Mandal v. Debnath Bhagat. This Court
    repelled a submission on the ground that the same was not
    put either to the witnesses or suggested before the courts
    below. Party is required to put his version to the witness.
    If
    no such questions are put the Court would presume that the
    witness account has been accepted as held in Chuni Lal
    Dwarka Nath v. Hartford Fire Insurance Co. Ltd
    .

    16. In Maroti Bansi Teli v. Radhabai, it has been laid down
    that the matters sworn to by one party in the pleadings not
    challenged either in pleadings or cross-examination by
    other party must be accepted as fully established. The High
    Court of Calcutta in A.E.G. Carapiet v. A.Y. Derderian has
    laid down that the party is obliged to put his case in cross-
    examination of witnesses of opposite party. The rule of
    putting one’s version in cross-examination is one of
    essential justice and not merely technical one.
    A Division
    Bench of the Nagpur High Court in Kuwarlal Amritlal v.
    Rekhlal Koduram has laid down that when attestation is
    not specifically challenged and witness is not cross-
    examined regarding details of attestation, it is sufficient for
    him to say that the document was attested. If the other side
    wants to challenge that statement, it is their duty, quite
    apart from raising it in the pleadings, to cross-examine the
    witness along those lines. A Division Bench of the Patna
    High Court in Karnidan Sarda v. Sailaja Kanta Mitra has
    laid down that it cannot be too strongly emphasised that
    the system of administration of justice allows of cross-
    examination of opposite party’s witnesses for the purpose of
    testing their evidence, and it must be assumed that when
    the witnesses were not tested in that way, their evidence is
    30

    to be ordinarily accepted. In the aforesaid circumstances,
    the High Court has gravely erred in law in reversing the
    findings of the first appellate court as to the factum of
    execution of the sale deed in favour of the plaintiff.”

    43. In the facts of the case, if the claim of the

    defendant/appellant with regard to rendering services and plaintiff

    company accepting and utilizing such services, is not challenged by

    the respondent/plaintiff by filing written statement or by cross

    examination of the concerned witness, Section 70 of the Indian

    Contract Act, 1872 is immediately pressed into service. The Hon’ble

    Supreme Court, in the case of Food Corporation of India (supra)

    laid down that,

    “19. The principle of quantum meruit is often applied where
    for some technical reason a contract is held to be invalid.
    Under such circumstances an implied contract is assumed,
    by which the person for whom the work is to be done
    contracts to pay reasonably for the work done, to the
    person who does the work. The provisions of this section
    are based on the doctrine of quantum meruit, but the
    provisions of the Contract Act admit of a more liberal
    interpretation; the principle of the section being wider than
    the principle of quantum meruit. The principle has no
    application where there is a specific agreement in operation.
    A person who does work or who supplies goods under a
    contract, if no price is fixed, is entitled to be paid a
    reasonable sum for his labour and the goods supplied. If
    the work is outside the contract, the terms of the contract
    31

    can have no application; and the contractor is entitled to be
    paid a reasonable price for such work as was done by him.

    20. If a party to a contract has done additional construction
    for another not intending to do it gratuitously and such
    other has obtained benefit, the former is entitled to
    compensation for the additional work not covered by the
    contract. If an oral agreement is pleaded, which is not
    proved, he will be entitled to compensation under Section

    70. Payment under this section can also be claimed for
    work done beyond the terms of the contract, when the
    benefit of the work has been availed of by the defendant.”

    44. Therefore, in view of the ratio laid down by the Hon’ble

    Supreme Court in Food Corporation of India (supra), we are of the

    opinion that although, the contract of employment of the defendant

    did not commence but the defendant did render services to the

    plaintiff company and such services were not gratuitous. Therefore,

    the defendant is entitled to the remuneration for the services

    rendered. As such we do hold that the defendant is entitled for the

    remuneration at the agreed rate of ₹15,00,000/- a month, in terms

    of Exhibit D, for the months from August, 2019 to November 2019

    totaling to ₹60,00,000/-

    45. The respondent paid a sum of ₹55,00,000/- to the appellant

    as part payment including ₹5,00,000/- towards Tax Deducted at

    Source (TDS), as evident from Exhibit E and Exhibit G. The

    appellant would therefore be entitled to ₹5,00,000/- towards
    32

    remuneration after adjusting the sum of ₹55,00,000/- which he

    already received towards the receivable ₹60,00,000/-. Therefore,

    there will be a decree for ₹5,00,000/- in favour of the appellant and

    as against the respondent. Appellant will be entitled to recover the

    sum of ₹5,00,000/- from the respondent. There will be decree for

    interest at the rate of 8% per annum from the sum of ₹5,00,000/-

    from December 1, 2019 till realization.

    46. Interest at the rate of 8% per annum is awarded in view of

    the nature of transactions between the parties.

    47. Moreover, the defendant has also claimed for the travelling,

    food and lodging expenses incurred by him for his travel to and stay

    at Mumbai. However, such expenses are not substantiated by any

    documentary evidence led at the trial. Exhibit G is the document

    which shows payment of ₹47,422/- towards reimbursement of

    travelling, food and lodging expenses incurred by the defendant for

    his visit to Calcutta. But the claim for visit at Mumbai has not been

    substantiated by any such document. For such reason, we are not

    in a position to allow such claim of the defendant as against the

    plaintiff.

    48. AD-COM 2 of 2026 is disposed of accordingly. Connected

    application(s), if any, shall also stand disposed of.
    33

    49. Urgent photostat certified copy of this judgment, if applied

    for, be supplied to the parties on priority basis upon compliance of

    all formalities.

    [MD. SHABBAR RASHIDI, J.]

    50. I agree.

    [DEBANGSU BASAK, J.]



    Source link

    LEAVE A REPLY

    Please enter your comment!
    Please enter your name here