    Delhi High Court

    Indian Oil Corporation Limited vs Toyo Engineering Corporation & Anr on 15 July, 2026

    Author: Amit Bansal

    Bench: Amit Bansal

                              *      IN THE HIGH COURT OF DELHI AT NEW DELHI
                              %                                      Judgment Reserved on: 26th May, 2026
                                                                   Judgment pronounced on: 15th July, 2026
    
                              +      O.M.P. (COMM) 316/2019, I.A. 10900/2019, LA. 6428/2020,
                                     I.A.15118/2021, I.A. 15154/2021, I.A. 19429/2022, I.A. 30713/2024 &
                                     I.A. 30714/2024
    
                                     INDIAN OIL CORPORATION LIMITED                             .....Petitioner
                                                        Through:     Mr. Rajeev Sharma, Senior Advocate
                                                                     with Mr. Himanshu Gulliya, Ms. Arunima
                                                                     Singh & Mr. Nishant Kandpal,
                                                                     Advocates.
    
                                                  versus
                                     TOYO ENGINEERING CORPORATION & ANR.                       .....Respondents
                                                        Through:     Mr. Sudipto Sarkar, Senior Advocate, Mr.
                                                                     Dayan Krishnan, Senior Advocate, Mr.
                                                                     Rajshekhar Rao, Senior Advocate, along
                                                                     with Mr. Susmit Pushkar, Mr. Sudip
                                                                     Mullick, Mr. Anchit Oswal and Mr.
                                                                     Gaurav Sharma, Advocates.
                                     CORAM:
                                     HON'BLE MR. JUSTICE AMIT BANSAL
    
                                                        JUDGMENT
    

    AMIT BANSAL, J.

    1. The present petition has been filed under Section 34 of the Arbitration and
    Conciliation Act, 1996 (‘Act’) seeking setting aside of the award dated 11th
    March, 2019 passed by the Arbitral Tribunal (‘Impugned Award’).

    SPONSORED

    Signature Not Verified
    Signed By:VIVEK O.M.P. (COMM) 316/2019 Page 1 of 44
    MISHRA
    Signing Date:15.07.2026
    13:28:32

    2. Indian Oil Corporation Ltd. (respondent/counter-claimant in the
    arbitration proceedings) shall hereinafter be referred to as the petitioner, and the
    consortium of the respondent no.1/Toyo Engineering Corporation and the
    respondent no.2/Larsen & Toubro Ltd. (claimants in the arbitral proceedings)
    shall hereinafter be referred to as the respondent consortium.

    FACTUAL BACKGROUND

    3. The genesis of the present dispute lies in a contract between the parties in
    respect of the petitioner’s Naphtha Cracker Project at Panipat, Haryana
    (hereinafter ‘Panipat Naphtha Cracker Project’ or ‘PNCP’). The petitioner
    appointed Engineers India Limited (hereinafter ‘EIL’) as the Engineer-in-
    Charge/Project Management Consultant for PNCP.

    4. PNCP was to be facilitated by the engagement of 17 contractors for
    Engineering, Procurement, Construction and Commissioning (hereinafter
    ‘EPCC’). In response to the tender floated by EIL for one such EPCC contract,
    being EPCC-1, the respondents no.1 and 2 formed a consortium to jointly
    participate in the pre-qualification for the project and submitted their bid dated
    24th August, 2005 for the project. Pursuant to detailed negotiations, the
    respondent consortium submitted its final offer vide letter dated 10th May, 2006.

    5. The contract was awarded to the respondent consortium vide
    communication dated 15th May, 2006 followed by a Detailed Letter of
    Acceptance dated 19th May, 2006 (hereinafter ‘DLOA’). As per Clause 1 of the
    DLOA, the lumpsum price was fixed at USD 78,006,057 + EURO 37,633,184 +
    YEN 13,870,977,342 + INR 16,640,792,020. As per Clause 5 of the DLOA, the

    Signature Not Verified
    Signed By:VIVEK O.M.P. (COMM) 316/2019 Page 2 of 44
    MISHRA
    Signing Date:15.07.2026
    13:28:32
    total time for mechanical completion (hereinafter ‘MC’) was 36 months plus 2
    months grace period, from the effective date of the contract, i.e. 25th May, 2006.

    6. Thereafter, the parties entered into a contract dated 25th May, 2006
    (hereinafter ‘Contract’). Clause 9.0.0.0 of the General Conditions of Contract
    (hereinafter ‘GCC’) provided for the resolution of disputes under the Contract to
    be resolved through arbitration.

    7. During the execution of the Contract, disputes arose between the parties
    inter alia in relation to delays in completion of the works. Several
    communications were exchanged between the parties wherein the respondent
    consortium sought extension of time, while the petitioner maintained that such
    requests were premature as MC had not yet been achieved. Ultimately, the
    respondent consortium achieved MC on 28th February, 2010, following which
    the petitioner issued the Commissioning Certificate on 5th August, 2010.

    8. Vide letter dated 2nd April, 2012, EIL informed the respondent consortium
    about the petitioner’s decision to grant of extension of time for EPCC-1 up to
    28th February, 2010, subject to a 10% price reduction on the contract value.

    9. Aggrieved by various deductions of amounts made by the petitioner from
    the final bills of the respondent consortium, the respondent consortium invoked
    arbitration and nominated its arbitrator. In response thereto, the petitioner
    nominated its arbitrator. The two arbitrators thereafter appointed a Presiding
    Arbitrator, and the Arbitral Tribunal stood constituted on 19 th December, 2014.

    Signature Not Verified
    Signed By:VIVEK O.M.P. (COMM) 316/2019 Page 3 of 44
    MISHRA
    Signing Date:15.07.2026
    13:28:32

    PROCEEDINGS BEFORE THE ARBITRAL TRIBUNAL

    10. The respondent consortium made the following claims in their Statement
    of Claim filed before the Arbitral Tribunal on 16th July, 2015:

    i. Price Adjustment: Amounts recovered by the petitioner towards price
    adjustment on account of delay;

    ii. PGTR/Excess Steam Consumption: Amounts recovered towards excess
    utility consumption beyond guaranteed figures during the performance
    guarantee test runs (hereinafter ‘PGTR’) of the plant, which were
    conducted to verify whether the consumption of high-pressure steam,
    cooling water and electrical power remained within the guaranteed
    consumption limits under the contract;

    iii. Miscellaneous Recoveries: Various recoveries effected by the petitioner;
    iv. Changes/Deviations: Amounts withheld from the Final Bill on account
    of changes/deviations during execution from the original requirements;

                                    v.    Interest at 18% p.a.; and
                                vi.       Costs.
    

    11. The amounts claimed by the respondent no.1 were as follows:

                                                           Dispute Item                JPY           US$        Euro          INR
    
                                                   a)   Price Adjustment           1,340,953,953   5,548,277              1,077,028,553
    
                                                   b)   PGTR                       258,705,383     838,080                 322,991,024
    
                                                   c)   Miscellaneous recoveries   245,359,266     1,393,728               206,832,042
    
                                                   d)   Changes/Deviations         286,825,162     2,946,057   652,981     871,187,900
    
    
    
    
    Signature Not Verified
    Signed By:VIVEK           O.M.P. (COMM) 316/2019                                                                     Page 4 of 44
    MISHRA
    Signing Date:15.07.2026
    13:28:32
                                                  e)   Interest for (a), (b), (c)        18% per annum from due date till realization
    
                                                      and (d)
    
                                                 f)   Costs
    
    
    
    

    12. The amounts claimed by the respondent no.2 were as follows:

                                                            Dispute Item                 JPY           US$        Euro          INR
    
                                                 a)   Price Adjustment                    -              -          -       914,274,847
    
                                                 b)   PGTR                                -              -          -             -
    
                                                 c)   Miscellaneous recoveries            -              -          -        52,948,032
    
                                                 d)   Changes/Deviations                  -              -          -
    
                                                 e)    Interest for (a), (b), (c) and    18% per annum from due date till realization
    
                                                                    (d)
    
                                                 f)   Costs
    
    
    
    

    13. The petitioner challenged the arbitrability of the claims raised by the
    respondent consortium and accordingly filed an application under Section 16 of
    the Act. The Arbitral Tribunal vide order dated 04th May, 2016, dismissed the said
    application, while holding that the jurisdictional objections shall be considered
    along with the merits.

    14. The petitioner filed its Statement of Defence and Counterclaim on 31st
    July, 2015, making the following counterclaims:

    i. 15% interest on the amounts recoverable towards price discount;

                                 ii.      Costs; and
                                iii.      Interest upon (i) and (ii), if any.
    
    
    Signature Not Verified
    Signed By:VIVEK           O.M.P. (COMM) 316/2019                                                                      Page 5 of 44
    MISHRA
    Signing Date:15.07.2026
    13:28:32
    

    15. On 6th November, 2017 the Arbitral Tribunal formulated the following
    issues for the adjudication of the dispute:

    “ISSUE NO.1:

    JURISDICTION

    1. Whether the disputes between the Parties are arbitrable and whether
    the Arbitral Tribunal has jurisdiction to adjudicate on the same.

    ISSUE NO.2:

    DELAY AND PRICE ADJUSTMENTS
    2.1. Did the Claimants achieve mechanical completion.
    2.2 Was the said completion prolonged beyond the original agreed
    time/stipulated period.

    2.3 Were the Claimants ready to receive the steam in terms of the Schedule
    provided in or related to the Contract.

    2.4 If in fact completion was prolonged, were the Claimants entitled to an
    extension of time and was an extension of time granted and if so, for what
    period.

    2.5 Was there acceptance of delivery of the plant and if so on what terms, if
    any.

    2.6 Is Clause 4.4.0.0 relating to Price Adjustment, invalid and unenforceable.
    2.7 In any event, is the Respondent estopped or precluded from imposing the
    Price Adjustment provisions.

    2.8 If the Price Adjustment provisions are validly imposable and imposed,
    what is the quantum of the adjusted amount”.

    ISSUE NO.3:

    PGTR – STEAM CONSUMPTION GUARANTEE
    3.1 Did the Respondent provide the contractual design conditions for
    carrying out PGTR.

    3.2 In any event, did the Claimant duly meet the guaranteed parameters for
    the steam consumption, and in the context of any agreed correction
    provisions.

    Signature Not Verified
    Signed By:VIVEK O.M.P. (COMM) 316/2019 Page 6 of 44
    MISHRA
    Signing Date:15.07.2026
    13:28:32

    ISSUE NO.4:

    BACK CHARGES

    4. Is the Respondent entitled to impose/ in respect of “Back Charges”

    deductions in respect of each of the matters that deductions were made and in
    any event were the deductions reasonable.

    ISSUE NO.5:

    CHANGE ORDERS
    5.1 What amount if any, are the Claimants entitled to in respect of the
    Change Orders.

    5.2 Is the Respondent entitled to withhold payments in respect thereof.

    ISSUE NO.6:

    COUNTERCLAIM OF THE RESPONDENT
    6.1. Is the Respondent entitled to its counterclaim.
    6.2. If so, the quantum thereof.

    ISSUE NO.7:

    INTEREST AND COSTS
    7.1 Is interest to be ordered in respect of any amount awarded and if so, the
    rate and period.

    7.2. If costs are ordered, the quantum thereof.”

    16. The Arbitral Tribunal passed the Impugned Award dated 11th March, 2019,
    whereby claims (a) and (b), as set out in the table above, being the claims for
    Price Adjustment and Excess Steam Consumption respectively, were fully
    allowed, whereas claims (c) and (d), being the claims for Miscellaneous
    Recoveries and Changes/Deviations respectively, were partly allowed. In
    addition, the Tribunal also awarded interest and costs in favor of the respondent
    consortium. One of the members of the Arbitral Tribunal gave a partially
    dissenting award on the Issues No.1 and 2 above, while concurring with the
    ultimate findings arrived at by the majority members of the Arbitral Tribunal.

    Signature Not Verified
    Signed By:VIVEK O.M.P. (COMM) 316/2019 Page 7 of 44
    MISHRA
    Signing Date:15.07.2026
    13:28:32

    PROCEEDINGS BEFORE THIS COURT

    17. Vide order dated 9th August, 2019, this Court granted a stay on the
    enforcement of the Impugned Award subject to the petitioner paying a sum of
    Rs. 125 crores to the respondents. By a subsequent order dated 23rd January,
    2020, the amount of Rs. 125 crores was directed to be deposited with the Registry
    of this Court and the respondents were permitted to withdraw the said amount
    upon furnishing of a bank guarantee.

    18. I.A. 1296/2020 was filed on behalf of the respondents for modification of
    the order dated 9th August, 2019 passed by this Court and further seeking a full
    deposit of the arbitral amount. The said application was dismissed vide
    judgement dated 6th March, 2020.

    19. The orders dated 9th August, 2019 and 6th March, 2020 were challenged
    by the respondent consortium before the Supreme Court by way of Civil Appeal
    Nos. 4549-4550 of 2019. Vide order dated 2nd August 2021, the Supreme Court
    set aside the aforesaid orders passed by this Court and directed the petitioner to
    deposit Rs. 662 crores, i.e. 100% of the awarded amount, before this Court. The
    entire amount deposited by the petitioner has been released to the respondents
    upon the said respondents furnishing bank guarantees in terms of the orders
    passed by this Court on 10th August, 2020, 23rd September, 2020, and 22nd
    November, 2021. The said bank guarantees have been duly extended from time
    to time and continue to survive.

    20. Oral submissions were heard between 10th March, 2025, and 22nd April,
    2026. Post conclusion of oral submissions, the judgment was reserved on 26 th

    Signature Not Verified
    Signed By:VIVEK O.M.P. (COMM) 316/2019 Page 8 of 44
    MISHRA
    Signing Date:15.07.2026
    13:28:32
    May, 2026, and written submissions on behalf of both parties were filed on 29 th
    May, 2026. To be noted, in the oral as well as written submissions, the petitioner
    confined its challenge to the findings of the Arbitral Tribunal on issues no.1
    (jurisdiction) and 2 (delay and price adjustment).

    SCOPE OF INTERFERENCE UNDER SECTION 34 OF THE ACT

    21. At the outset, it is relevant to note that the challenge in the present petition
    is in relation to an award arising out of an ‘international commercial arbitration’
    as defined in Section 2(1)(f) of the Act, in view of the fact that the respondent
    no.1 is an entity incorporated overseas. Consequently, the ground of patent
    illegality under Section 34(2A) of the Act is not available as a ground of
    challenge.

    22. In the present case, the main ground of challenge is under Section
    34(2)(b)(ii)
    of the Act. Section 34(2)(b)(ii) of the Act, along with the
    Explanations to the same, is reproduced below:

    “(2) An arbitral award may be set aside by the Court only if–

    (a)…

    (b) the Court finds that–

    (i)…

    (ii) the arbitral award is in conflict with the public policy of India.

    Explanation 1.–For the avoidance of any doubt, it is clarified that an award is
    in conflict with the public policy of India, only if,–

    (i) the making of the award was induced or affected by fraud or corruption or
    was in violation of section 75 or section 81; or

    (ii) it is in contravention with the fundamental policy of Indian law; or

    (iii)it is in conflict with the most basic notions of morality or justice.

    Signature Not Verified
    Signed By:VIVEK O.M.P. (COMM) 316/2019 Page 9 of 44
    MISHRA
    Signing Date:15.07.2026
    13:28:32

    Explanation 2.–For the avoidance of doubt, the test as to whether there is a
    contravention with the fundamental policy of Indian law shall not entail a
    review on the merits of the dispute.]”

    (emphasis supplied)

    23. The scope of interference under Section 34 of the Act came before
    consideration of the Supreme Court in Associate Builders v. Delhi Development
    Authority1
    . The relevant observations with regard to fundamental policy of
    Indian law, justice and morality are set out below:

    “Fundamental Policy of Indian Law

    27. Coming to each of the heads contained in Saw Pipes [(2003) 5 SCC 705
    : AIR 2003 SC 2629] judgment, we will first deal with the head “fundamental
    policy of Indian law”. It has already been seen from Renusagar [Renusagar
    Power Co. Ltd. v. General Electric Co.
    , 1994 Supp (1) SCC 644] judgment
    that violation of the Foreign Exchange Act and disregarding orders of
    superior courts in India would be regarded as being contrary to the
    fundamental policy of Indian law. To this it could be added that the binding
    effect of the judgment of a superior court being disregarded would be equally
    violative of the fundamental policy of Indian law.

    ***

    33. It must clearly be understood that when a court is applying the “public
    policy” test to an arbitration award, it does not act as a court of appeal and
    consequently errors of fact cannot be corrected. A possible view by the
    arbitrator on facts has necessarily to pass muster as the arbitrator is the
    ultimate master of the quantity and quality of evidence to be relied upon
    when he delivers his arbitral award. Thus an award based on little evidence
    or on evidence which does not measure up in quality to a trained legal mind
    would not be held to be invalid on this score [ Very often an arbitrator is a
    lay person not necessarily trained in law. Lord Mansfield, a famous English
    Judge, once advised a high military officer in Jamaica who needed to act as
    a Judge as follows:”General, you have a sound head, and a good heart; take
    courage and you will do very well, in your occupation, in a court of equity.
    My advice is, to make your decrees as your head and your heart dictate, to

    1
    (2015) 3 SCC 49.

    Signature Not Verified
    Signed By:VIVEK O.M.P. (COMM) 316/2019 Page 10 of 44
    MISHRA
    Signing Date:15.07.2026
    13:28:32

    hear both sides patiently, to decide with firmness in the best manner you can;
    but be careful not to assign your reasons, since your determination may be
    substantially right, although your reasons may be very bad, or essentially
    wrong”.It is very important to bear this in mind when awards of lay
    arbitrators are challenged.] Once it is found that the arbitrators approach
    is not arbitrary or capricious, then he is the last word on facts…
    ***
    Justice

    36. The third ground of public policy is, if an award is against justice or
    morality. These are two different concepts in law. An award can be said to be
    against justice only when it shocks the conscience of the court. An
    illustration of this can be given. A claimant is content with restricting his
    claim, let us say to Rs 30 lakhs in a statement of claim before the arbitrator
    and at no point does he seek to claim anything more. The arbitral award
    ultimately awards him Rs 45 lakhs without any acceptable reason or
    justification. Obviously, this would shock the conscience of the court and the
    arbitral award would be liable to be set aside on the ground that it is contrary
    to “justice”.

    ***
    Morality

    39. This Court has confined morality to sexual morality so far as Section 23
    of the Contract Act, 1872 is concerned, which in the context of an arbitral
    award would mean the enforcement of an award say for specific performance
    of a contract involving prostitution. “Morality” would, if it is to go beyond
    sexual morality necessarily cover such agreements as are not illegal but
    would not be enforced given the prevailing mores of the day. However,
    interference on this ground would also be only if something shocks the
    court’s conscience.

    ***
    42.1. (a) A contravention of the substantive law of India would result in the
    death knell of an arbitral award. This must be understood in the sense that
    such illegality must go to the root of the matter and cannot be of a trivial
    nature…”

    (emphasis supplied)

    Signature Not Verified
    Signed By:VIVEK O.M.P. (COMM) 316/2019 Page 11 of 44
    MISHRA
    Signing Date:15.07.2026
    13:28:32

    24. The above-said findings in Associate Builders (supra) were reaffirmed by
    the Supreme Court in Ssangyong Engineering and Construction Company
    Limited v. National Highways Authority of India (NHAI
    )2, wherein the
    Supreme Court was dealing with the grounds of challenge to an award arising
    out of an international commercial arbitration.
    The relevant observations of the
    Supreme Court in Ssanyong (supra) are set out below:

    “34. What is clear, therefore, is that the expression “public policy of India”,
    whether contained in Section 34 or in Section 48, would now mean the
    “fundamental policy of Indian law” as explained in paras 18 and 27
    of Associate Builders [Associate Builders v. DDA, (2015) 3 SCC 49 : (2015)
    2 SCC (Civ) 204] i.e. the fundamental policy of Indian law would be relegated
    to “Renusagar” understanding of this expression.
    This would necessarily
    mean that Western Geco [ONGC v. Western Geco International Ltd., (2014)
    9 SCC 263 : (2014) 5 SCC (Civ) 12] expansion has been done away with. In
    short, Western Geco [ONGC v. Western Geco International Ltd., (2014) 9
    SCC 263 : (2014) 5 SCC (Civ) 12] , as explained in paras 28 and 29
    of Associate Builders [Associate Builders v. DDA, (2015) 3 SCC 49 : (2015)
    2 SCC (Civ) 204] , would no longer obtain, as under the guise of interfering
    with an award on the ground that the arbitrator has not adopted a judicial
    approach, the Court’s intervention would be on the merits of the award,
    which cannot be permitted post amendment.
    However, insofar as principles
    of natural justice are concerned, as contained in Sections 18 and 34(2)(a)(iii)
    of the 1996 Act, these continue to be grounds of challenge of an award, as is
    contained in para 30 of Associate Builders [Associate Builders v. DDA,
    (2015) 3 SCC 49 : (2015) 2 SCC (Civ) 204] .

    35. It is important to notice that the ground for interference insofar as it
    concerns “interest of India” has since been deleted, and therefore, no longer
    obtains. Equally, the ground for interference on the basis that the award is
    in conflict with justice or morality is now to be understood as a conflict with
    the “most basic notions of morality or justice”. This again would be in line
    with paras 36 to 39 of Associate Builders [Associate Builders v. DDA, (2015)

    2
    (2019) 15 SCC 131.

    Signature Not Verified
    Signed By:VIVEK O.M.P. (COMM) 316/2019 Page 12 of 44
    MISHRA
    Signing Date:15.07.2026
    13:28:32

    3 SCC 49 : (2015) 2 SCC (Civ) 204] , as it is only such arbitral awards that
    shock the conscience of the court that can be set aside on this ground.

    36. Thus, it is clear that public policy of India is now constricted to mean
    firstly, that a domestic award is contrary to the fundamental policy of
    Indian law, as understood in paras 18 and 27 of Associate
    Builders [Associate Builders v. DDA
    , (2015) 3 SCC 49 : (2015) 2 SCC (Civ)
    204] , or secondly, that such award is against basic notions of justice or
    morality as understood in paras 36 to 39 of Associate Builders [Associate
    Builders v. DDA
    , (2015) 3 SCC 49 : (2015) 2 SCC (Civ) 204] .
    Explanation
    2 to Section 34(2)(b)(ii) and Explanation 2 to Section 48(2)(b)(ii) was added
    by the Amendment Act only so that Western Geco [ONGC v. Western Geco
    International Ltd., (2014) 9 SCC 263 : (2014) 5 SCC (Civ) 12] , as understood
    in Associate Builders [Associate Builders v. DDA, (2015) 3 SCC 49 : (2015)
    2 SCC (Civ) 204] , and paras 28 and 29 in particular, is now done away with.

    39. To elucidate, para 42.1 of Associate Builders [Associate
    Builders v. DDA
    , (2015) 3 SCC 49 : (2015) 2 SCC (Civ) 204] , namely, a
    mere contravention of the substantive law of India, by itself, is no longer a
    ground available to set aside an arbitral award.
    Para 42.2 of Associate
    Builders [Associate Builders v. DDA
    , (2015) 3 SCC 49 : (2015) 2 SCC (Civ)
    204] , however, would remain, for if an arbitrator gives no reasons for an
    award and contravenes Section 31(3) of the 1996 Act, that would certainly
    amount to a patent illegality on the face of the award.

    69. We therefore hold, following the aforesaid authorities, that in the guise
    of misinterpretation of the contract, and consequent “errors of
    jurisdiction”, it is not possible to state that the arbitral award would be
    beyond the scope of submission to arbitration if otherwise the aforesaid
    misinterpretation (which would include going beyond the terms of the
    contract), could be said to have been fairly comprehended as “disputes”
    within the arbitration agreement, or which were referred to the decision of
    the arbitrators as understood by the authorities above. If an arbitrator is
    alleged to have wandered outside the contract and dealt with matters not
    allotted to him, this would be a jurisdictional error which could be corrected
    on the ground of “patent illegality”, which, as we have seen, would not
    apply to international commercial arbitrations that are decided under Part
    II of the 1996 Act. To bring in by the backdoor grounds relatable to Section
    28(3)
    of the 1996 Act to be matters beyond the scope of submission to

    Signature Not Verified
    Signed By:VIVEK O.M.P. (COMM) 316/2019 Page 13 of 44
    MISHRA
    Signing Date:15.07.2026
    13:28:32
    arbitration under Section 34(2)(a)(iv) would not be permissible as this
    ground must be construed narrowly and so construed, must refer only to
    matters which are beyond the arbitration agreement or beyond the reference
    to the Arbitral Tribunal”

    (emphasis supplied)

    25. The legal position emerging from the aforesaid decisions is that “public
    policy of India” is to be construed narrowly, in line with the principles laid down
    in
    Renusagar Power v. General Electric3. The Supreme Court has consistently
    held that the ground of “public policy of Indian law” does not permit a review of
    the merits of the dispute. Proceedings under Section 34 of the Act do not
    constitute an appeal against the arbitral award. Consequently, courts cannot
    reappreciate evidence or substitute their own view for that of an arbitral tribunal.
    Mere contravention of substantive law of India, an erroneous interpretation of
    contractual provisions, or even a finding that the tribunal has acted beyond the
    terms of the contract would not, by themselves, furnish grounds for interference.
    The award must be shown to be patently illegal to the fundamental policy of
    Indian law or the public policy of India, or so perverse that it shocks the
    conscience of the court or is contrary to the most basic notions of justice and
    morality. Pertinently, if an arbitrator decides issues beyond the scope of the
    contract, the same amounts to a jurisdictional error that can be challenged on the
    ground of patent illegality. However, this ground is not available in the case of
    awards arising from international commercial arbitrations.

    3

    1994 Supp (1) SCC 644.

    Signature Not Verified
    Signed By:VIVEK O.M.P. (COMM) 316/2019 Page 14 of 44
    MISHRA
    Signing Date:15.07.2026
    13:28:32

    26. Next, a reference may also be made to the judgment of the Division Bench
    of this Court in Municipal Corporation of Delhi v. IJM Corporation Berhad4.
    The challenge here was also in the context of an international commercial
    arbitration. The Division Bench dismissed the petition, making the following
    observations:

    “23. Conflict with the fundamental policy of Indian law does not refer to
    violation of any statute or misconstruction of any clause of a contract. The
    fundamental policy of law is a substratal policy on which the edifice of law
    is founded. It is the basic legal values that instruct laws in India. Thus, an
    arbitral award would fall foul of the fundamental policy of India if it offends
    the basic policy underlying Indian law.

    ***

    27. It is clear that in the present case, MCD’s challenge is based on the
    interpretation of contractual clauses. This is not a ground that falls within
    Section 34(2)(b)(ii) of the A&C Act.

    28. It is also relevant to refer to Explanation 2 to Section 34(2)(b) of the A&C
    Act, which amply clarifies that the test whether there is any contravention to
    the fundamental policy of Indian law would not entail a review on the merits
    of the dispute. In the present case, this is precisely what MCD invites the Court
    to do. It seeks a judicial review of the Arbitral Tribunal’s interpretation of terms
    of the Agreement, on merits.

    ***

    30. A dispute regarding the interpretation of a contract falls within the
    jurisdiction of the Arbitral Tribunal and unless the interpretation is not a
    plausible one and amounts to rewriting the bargain between the parties, the
    same would not warrant any interference under Section 34 of the A&C Act. In
    Assam SEB v. Buildworth (P.) Ltd., the Supreme Court had observed that
    “matters relating to the construction of a contract lie within the province of
    the Arbitral Tribunal” and are not amenable to review on merits unless, the
    interpretation is not a possible one.”

    (emphasis supplied)

    4
    2024 SCC OnLine Del 3597.

    Signature Not Verified
    Signed By:VIVEK O.M.P. (COMM) 316/2019 Page 15 of 44
    MISHRA
    Signing Date:15.07.2026
    13:28:32

    27. With this background, I shall now proceed to apply the aforesaid principles
    in the facts and circumstances of the present case to consider the challenges
    raised in the present petition.

    ISSUE NO. 1: DELAY AND PRICE ADJUSTMENT
    Submissions on behalf of the petitioner

    28. The 10% price discount clause was the result of commercial negotiations
    between the parties, and in exchange for the same, the respondent consortium
    had proposed higher consideration and enhancement in the time for completion
    of the contract, which was agreed to by the petitioner.

    29. In terms of Clause 4.5.0.0 of the GCC, the discount provision was not to
    be construed as a penalty clause under Section 74, Indian Contract Act, 1872
    (hereinafter ‘ICA’). The Arbitral Tribunal, by holding that the discount clause is
    not enforceable, has in effect rewritten the contract, resulting in unjust
    enrichment of Rs.89.05 crores to the respondent consortium without it being
    bound to perform its reciprocal obligations of price discount. Reliance in this
    regard is placed on IOCL v. Fiberfill Engineers5 and Man Industries v. GAIL6.

    30. The finding of the Arbitral Tribunal that the price discount provision is a
    penalty under Section 74 ICA, in the absence of any finding that the price
    discount was unconscionable, extravagant or unfair, in the context of the specific
    transaction at hand, is contrary to Indian Law.

    5

    (2025) 316 DLT 172.

    6

    Judgment dated 25th March, 2026, in O.M.P. (COMM) 191/2019.

    Signature Not Verified
    Signed By:VIVEK O.M.P. (COMM) 316/2019 Page 16 of 44
    MISHRA
    Signing Date:15.07.2026
    13:28:32

    31. The Arbitral Tribunal failed to adjudicate on each element of delay and
    whether the same was attributable to the petitioner or the respondent consortium.
    Despite Issue No. 2.3 having been framed in this regard, no specific finding was
    given by the Arbitral Tribunal on the said issue. In view of the fact that the delay
    in achieving MC was the crux of the dispute between the parties, the said non-
    adjudication goes to the root of the matter.

    32. The postponement of the starting date for the calculation of price discount
    under Clause 4.4.2.1 of the GCC was permissible only where extension of time
    was granted “with a view” to such extension resulting in an equivalent extension
    in the starting date of price discount. The Arbitral Tribunal erroneously
    proceeded on the basis that every extension of time would automatically shift the
    starting date for calculation of discount, despite the extension itself being
    conditional upon levy of price discount.

    33. The effect of the price adjustment clause made it evident that the delay
    was not for reasons contemplated under Clause 4.3.6.0. Reliance in this regard
    is placed on the judgment dated 1st June, 2018, passed by a Coordinate Bench of
    this Court in OMP (COMM) 366/2017 titled “Indian Oil Corporation Ltd. v.
    Larsen & Toubro Ltd.
    ” (hereinafter ‘IOCL v. L&T’), which was a petition filed
    under Section 34 of the Act in respect of an interlinked EPCC contract for PNCP,
    being EPCC-4. In the said judgment, the Court rejected the interpretation of an
    identical clause, as is being canvassed by the respondent consortium in the
    present petition. The Arbitral Tribunal has effectively rewritten the contract and

    Signature Not Verified
    Signed By:VIVEK O.M.P. (COMM) 316/2019 Page 17 of 44
    MISHRA
    Signing Date:15.07.2026
    13:28:32
    consequently, the Award is liable to be set aside under Section 34(2)(b)(ii) of the
    Act read with Explanation (1) (ii) and (iii).

    34. There was no delay in the supply of steam from the petitioner to the
    respondent consortium. The nature of the transaction required the steam header
    to be put in place by the respondent consortium in order for steam to be provided.
    Hence, the respondent consortium could not have insisted on the supply of steam
    until the steam header was in place. Steam was provided to the respondent
    consortium on 8th August, 2009, shortly after installation of the steam header in
    the first week of August, and there is material on record to show that the
    respondent consortium was not ready to receive the steam prior to 7th August,
    2009.

    Submissions on behalf of the respondent consortium

    35. The primary finding of the Arbitral Tribunal was that once extension of
    time had been granted, and there was no material on record to suggest that such
    extension was granted for reasons dehors Clause 4.3.6.0, i.e. for reasons
    otherwise than the delay being justified, it necessarily followed that EIL and/or
    the petitioner was satisfied that the delay was justified.

    36. In view of the primary finding returned by the Arbitral Tribunal, the
    Impugned Award cannot be assailed solely on the basis of its secondary finding
    regarding the applicability of Section 74 ICA to the price discount clause, i.e.
    Clause 4.4.0.0 of the GCC.

    Signature Not Verified
    Signed By:VIVEK O.M.P. (COMM) 316/2019 Page 18 of 44
    MISHRA
    Signing Date:15.07.2026
    13:28:32

    37. The issue concerning readiness to receive steam stood subsumed within
    the larger issue of delay analysis undertaken by the petitioner itself. The
    petitioner, despite being in possession of the complete delay analysis concerning
    all interlinked EPCC packages, failed to produce the same before the Arbitral
    Tribunal. In the absence of such material, the Arbitral Tribunal rightly proceeded
    on the basis of the petitioner’s own decision to grant extension of time up to 28 th
    February 2010. No contemporaneous communication existed demonstrating that
    the petitioner was ready to supply steam prior to 10 th August 2009. In the
    proceedings concerning EPCC-4, the delay in supply of steam and related
    infrastructure was held attributable to the petitioner.

    Analysis

    Extension of Time and Effect on Price Discount

    38. As per the terms of the Contract, the period for MC was 36 months, with
    2 months grace period, from the effective date of the Contract, i.e. 25th May,
    2006. The Contract contains two clauses that provide for the extension of time
    for MC, i.e. Clause 4.3.5.0 and Clause 4.3.6.0.

    39. Clause 4.3.5.0 of the GCC provides for an extension of time for MC upon
    the request of the Contractor (respondent consortium herein) at the discretion of
    the Engineer-in-Charge (EIL herein). Similarly, the date for completion of the
    contract could also be extended in terms of Clause 4.3.6.0 at the discretion of the
    Owner (petitioner herein). Clause 4.3.6.0, which is the relevant clause for the
    purposes of the present adjudication, is set out below:-

    Signature Not Verified
    Signed By:VIVEK O.M.P. (COMM) 316/2019 Page 19 of 44
    MISHRA
    Signing Date:15.07.2026
    13:28:32

    “4.3.6.0 Notwithstanding the provisions of clause 4.3.5.0 hereof, the
    OWNER may at any time after final completion of the Unit or works in all
    respects of its own initiative consider a request for extension of time made
    by the CONTRACTOR to the Engineer-in-Charge under Clause 4.3.5.0or at
    the request of the CONTRACTOR made by way of appeal either against the
    decision of the Engineer-in-Charge taken under clause 4.3.5.0 or against the
    Engineer-in-Charge’s failure to take a decision under the said clause, If
    satisfied of the existence of any ground(s) justifying the delay, extend the
    date for completion of the work or any item or operation thereof for such
    period(s) as the OWNER may consider necessary, and the decision of
    OWNER as to the existence or otherwise of any grounds justifying the
    extension and as to the period(s) of extension necessary shall be final and
    binding upon the CONTRACTOR..”

    (emphasis supplied)

    40. A reading of Clause 4.3.6.0 reveals that an extension for completion of the
    work could be granted upon the satisfaction of the Owner (petitioner herein) of
    grounds justifying the delay. Hence, the sole discretion with regard to grounds
    justifying the delay was with the petitioner and the decision of the petitioner was
    to be binding on the Contractor (respondent consortium herein). At this stage, it
    is also relevant to refer to Clause 4.4.0.0 of the GCC, which provides for price
    adjustment. The relevant extracts of Clause 4.4.0.0 are set out below:

    “4.4.0.0 PRICE ADJUSTMENT FOR SLIPPAGE IN COMPLETION
    4.4.1.0 The Lumpsum Price specified in the Contract is based (i) On the
    Mechanical Completion of the Unit(s) by the CONTRACTOR; and (in) On
    Mechanical Completion of the Unit[s) within the time for Mechanical
    Completion of the Unit(s) specified in the Time Schedule. The Lumpsum
    Price shall be subject to adjustment by way of discount as hereinafter
    specified, if the Unit(s) is/are not mechanically completed by the
    CONTRACTOR or if the Unit(s) is/are mechanically completed subsequent
    to the date of Mechanical Completion specified in the Time Schedule.

    Signature Not Verified
    Signed By:VIVEK O.M.P. (COMM) 316/2019 Page 20 of 44
    MISHRA
    Signing Date:15.07.2026
    13:28:32

    4.4.2.0 If Mechanical Completion of the Unit(s) is/are not achieved by
    thedate of Mechanical Completion of the Unit(s) specified in the Time
    Schedule or if any works for which a separate Progress Schedule has been
    established is/are not achieved by the date of completion thereof specified in
    the relevant Progress Schedule (each of the said date(s) is hereinafter referred
    to as the “starting dale for discount calculation”), the OWNER shall be
    entitled to a discount in the Lumpsum Price in a sum equivalent to the
    Lumpsum Price specified below for each week or part thereof that the work
    remains incomplete beyond the starting date for discount calculation,
    namely….

    4.4.2.1 The starting date for discount calculation shall be subject to
    variation upon extension of the date for Mechanical Completion of the
    Unit(s) or final competition of the works as the case may be by the Engineer-
    in-Charge under Clause 4.3.5.0 or by the OWNER under Clause 4.3.6.0,
    with a view that upon any such extension there shall be an equivalent
    extension in the starting date for discount calculation under Clause 4.4.2.0
    hereof”

    (emphasis supplied)

    41. Clause 4.4.1.0 provides for price adjustment by way of discount if MC is
    not achieved in accordance with the specified time schedule. Clause 4.4.2.0
    provides for the manner of calculation of price adjustment. Clause 4.4.2.1 is in
    the nature of an exception to Clauses 4.4.1.0 and 4.4.2.0. Once extension of time
    is granted under Clause 4.3.5.0 or 4.3.6.0, Clause 4.4.2.1 provides that there will
    be an equivalent shift in the starting date in terms of which price discount is to
    be calculated under Clause 4.4.2.0.

    42. During the course of execution of the contract, the respondent consortium
    apprised the petitioner of delays in completion of the works attributable to factors
    beyond its control and sought extension of time. The petitioner, however,
    declined to consider the request at that stage, taking the stand that it was not
    feasible to assess the consequences of the delay until completion of the works

    Signature Not Verified
    Signed By:VIVEK O.M.P. (COMM) 316/2019 Page 21 of 44
    MISHRA
    Signing Date:15.07.2026
    13:28:32
    and the request for extension was therefore premature (Ref. communications
    dated 1st October 2009 and 23rd December 2009).

    43. It is not disputed that MC was achieved on 28th February 2010. Almost
    two years later, EIL vide letter dated 2nd April, 2012, informed the respondent
    consortium that the petitioner has granted extension of time up to 28th February,
    2010. However, the extension of time was granted with a condition of price
    reduction of 10% of the contract value as per Clause 4.4.0.0. The relevant
    extracts from the said letter are set out below:-

    “As advised by IOCL, the time extension of EPCC-1 has been granted by
    competent authority upto 28.02.2010 with price reduction of 10% of contract
    value as per G.C.C. clause no. 4.4.0.0.”

    44. Placing reliance on Clause 4.4.2.0, read with Clause 4.4.2.1, the Arbitral
    Tribunal held that on account of extension of time till 20th February, 2010, the
    starting date for purposes of calculation of discount also stood advanced to 20 th
    February, 2010 and hence, the petitioner was not entitled to any price discount.
    The relevant findings of the Arbitral Tribunal are set out below:-

    “92. It is quite clear (we provide some contextual emphasis) that in respect
    of an application for EOT by the Claimants, what EIL could do was to extend
    the time for completion and what the Respondent could also do and
    importantly did do, was to extend the time for completion of the entire works
    to 28 February 2010. In the absence of evidence or at least a
    contemporaneous statement of EIL or the Owner, that the EOT was granted
    for reasons other than set out in Clause 4.3.6.0 (there was no such evidence
    or statement), the Tribunal has to assume and does assume, that EIL and/or
    the Owner, was satisfied that the delay was justified.

    93. Having concluded that an extension of time was granted, we turn to the
    effect of that extension upon the Owner’s right to a discount for delay under
    Clause 4.4.2.0 (see paragraph 68.2 hereof). As has been noted, that

    Signature Not Verified
    Signed By:VIVEK O.M.P. (COMM) 316/2019 Page 22 of 44
    MISHRA
    Signing Date:15.07.2026
    13:28:32
    paragraph has to be read in accordance with Clause 4.4.2.1 (see paragraph
    68.3 hereof). That provides for the starting point for discount calculation to
    be varied upon the grant of an EOT.

    94. In our view, it follows and we find that the starting date for the discount
    calculation was, by reason of the EOT, advanced to 28 February, 2010.

    95.It follows that as EOT in respect of the entire works was granted up to
    28 February 2010 which meant that MC was to be effected by 28 February
    2010, and as the Respondent has accepted that MC was achieved on 28
    February 2010, the starting date for discount calculation has to be from the
    day immediately after 28 February 2010.

    96. Accordingly, we have to and conclude, and it is our finding, that as EOT
    was granted up to 28 February 2010 and MC was achieved on 28 February
    2010, in effect there was no delay and accordingly the Owner Respondent
    was not entitled to any Clause 4.4.2.0 discount, or any other discount, of the
    lumpsum price.

    97.It follows and we hold that the purported imposition of the 10% discount
    for delay, when in fact in effect there was no delay, was wrong and should be
    set aside.”

    (emphasis supplied)

    45. Before this Court, it has been contended on behalf of the petitioner that
    the Arbitral Tribunal has ignored the second part of the letter dated 2 nd April,
    2012, to the effect that the petitioner granted extension subject to price reduction.
    It is contended that Clause 4.4.2.1 of the GCC would be applicable only if the
    extension of time was given unconditionally, and in the present case, since the
    extension of time was conditional, i.e. coupled with a price discount clause, the
    benefit of Clause 4.4.2.1 could not be given to the respondent consortium. The
    petitioner places reliance on the phrase “with a view” in Clause 4.4.2.1 to contend
    that Clause 4.4.2.1 is conditional in nature.

    Signature Not Verified
    Signed By:VIVEK O.M.P. (COMM) 316/2019 Page 23 of 44
    MISHRA
    Signing Date:15.07.2026
    13:28:32

    46. To be noted, the Arbitral Tribunal has specifically observed that the
    petitioner did not advance any submissions in respect of Clause 4.4.2.1. In this
    regard, paragraphs 84 and 85 of the Impugned Award are set out below:

    “84. Startlingly, the Respondent did not in its Written Closing Submissions,
    even touch on the Clause 4.4.2.1 G.C.C. aspect of the Claimants’ contention
    in respect of Price Discount and Adjustment, that upon any extension of the
    date for MC, there shall be an equivalent extension in the starting date for
    discount calculation.

    85. It is also to be noted that in summarizing the various aspects of the
    Claimants’ claim on Price Discount at paragraph 8 of the Respondent’s Final
    Submissions which were drafted and submitted well after the Claimants’
    Closing Written Submissions, the contention of the Claimants based on
    invoking Cause 4.4.2.1 was again ignored.”

    47. Evidently, this argument is being raised for the first time before this Court
    in the present proceedings under Section 34 of the Act, which is impermissible.
    Even otherwise, I am unable to accept this submission. The phrase “with a view”

    used in Clause 4.4.2.1 has been used to highlight the effect of the extension, i.e.
    the time period by which the starting date for discount calculation would be
    extended. Clause 4.4.2.1 does not provide that extension of time has to be
    unconditional. Even if the extension is granted by the petitioner subject to price
    reduction, it would not have any bearing on the shifting of the starting date as
    stipulated in Clause 4.4.2.1. Therefore, the contention of the petitioner that the
    extension of time was granted with a condition of price discount and hence not
    covered under Clause 4.4.2.1, cannot be accepted.

    48. On the aspect of delay, the petitioner in its reply to the claim statement
    before the Arbitral Tribunal, took a stand that amounts towards price discount

    Signature Not Verified
    Signed By:VIVEK O.M.P. (COMM) 316/2019 Page 24 of 44
    MISHRA
    Signing Date:15.07.2026
    13:28:32
    were lawfully deducted by the petitioner after a thorough delay analysis.
    Between 2009 and 2010, there was no allegation of any delay. It is only in the
    communication sent by EIL to the respondent consortium on 17 th April, 2012,
    two years after the MC was achieved, it was communicated that a 10% price
    discount for delay has been claimed on account of analysis of the delay by EIL
    and the petitioner. Pertinently, the delay analysis which the petitioner claims to
    have conducted was never produced before the Arbitral Tribunal. The relevant
    observations of the Arbitral Tribunal in this regard are set out below:

    “67. However, if in fact EIL or the Respondent had carried out a delay
    analysis, such analysis, according to the Claimants, and without challenge,
    was not disclosed to the Claimants, and certainly was not disclosed or
    produced in the arbitration.”

    49. In the communication dated 2nd April, 2012, there is no explanation given
    as to why the extension has been given with price reduction. Even in the
    subsequent communication of 17th April, 2012, even though the petitioner has
    alleged that there is a delay of 219 days in achieving MC, no delay analysis has
    been provided. In the absence of any delay analysis provided by the petitioner,
    the Arbitral Tribunal has correctly come to the conclusion that once the petitioner
    has thought it fit to grant extension of time, it has to be taken that the petitioner
    is satisfied that the delay is justified in terms of Clause 4.3.6.0. There are no other
    grounds for extension of time provided in Clause 4.3.6.0 other than delay being
    justified. The petitioner has not drawn the attention of the Court to any other
    clause in the Contract in terms of which the petitioner could grant extension of
    time to the respondent consortium.

    Signature Not Verified
    Signed By:VIVEK O.M.P. (COMM) 316/2019 Page 25 of 44
    MISHRA
    Signing Date:15.07.2026
    13:28:32

    50. The view taken by the Arbitral Tribunal as set out in the paragraphs
    hereinabove is clearly a plausible view and cannot be subject matter of
    interference under Section 34 of the Act.

    51. It is a settled position of law that the interpretation placed by the Arbitral
    Tribunal on various clauses of the contract is final and cannot be interfered with
    under Section 34 of the Act. Reference in this regard may be made to Ssangyong
    (supra) and Municipal Corporation of Delhi v. IJM Corporation Berhad
    (supra).

    52. In support of its contention that the petitioner was entitled to grant an
    extension of time with price discount, as was communicated vide letter dated 2nd
    April, 2012, the petitioner places reliance on the judgment of this Court in IOCL
    v. L&T (supra). This judgment was in the context of a petition filed by the
    petitioner herein (IOCL) under Section 34 of the Act in respect of EPCC-4, a
    contract also relating to PNCP, challenging an arbitral award wherein the
    petitioner’s claim for price discount on account of delay in completion of the
    EPCC-4 was held to be unjustified. In the said case also, the petitioner had relied
    upon a similar communication dated 5th April, 2012, sent by EIL, wherein
    extension of time for EPCC-4 was granted subject to price reduction of 10%. The
    EPCC-4 also contained identical Clauses 4.4.0.0 and 4.4.2.1. The relevant
    observations on which the petitioner places reliance, i.e. paragraphs 28 and 29
    are set out below:-

    “28. The Arbitral Tribunal has treated the letter dated 5th April, 2012 as a
    decision to extend the time for completion of the work and has rejected the
    arguments of the petitioner that the reference to extension of time in the said
    letter was merely a misnomer and it was actually a communication of the

    Signature Not Verified
    Signed By:VIVEK O.M.P. (COMM) 316/2019 Page 26 of 44
    MISHRA
    Signing Date:15.07.2026
    13:28:32
    decision to levy price discount. It further held that as the recommendations
    made by the EIL and the decision taken thereon by the petitioner in its noting
    dated 26th March, 2012 were not communicated to the respondent, they were
    ineffective and that once the extension of time was granted, the extended date
    of completion shall be deemed to be the relative date of completion in the
    Progress Schedule, and therefore, price discount cannot be applied.

    29. In my view, this is a complete mis-reading of the letter dated 5th April,
    2012 addressed by EIL to the respondent. The said letter in no ambiguous
    words states that the competent authority has taken a decision to levy the
    price discount of 10% on the contract value in terms of clause 4.4.0.0. The
    said clause is applicable, as noted above, only where the contractor is unable
    to complete the work within the specified time schedule. Whether the decision
    to levy price discount on the respondent was justified or not is an issue distinct
    from stating that the decision of the competent authority was to grant
    extension of time unconditionally and, therefore, there can be no levy of price
    discount by the petitioner. Therefore, the finding of the Arbitral Tribunal on
    this issue cannot be sustained.”

    53. The Court held the findings of the Arbitral Tribunal to be unsustainable to
    the extent that once an extension has been granted to the Contractor, the price
    discount cannot be levied. However, in the same judgment, the Court upheld the
    view of the Arbitral Tribunal that the respondent therein was entitled to extension
    of time as the delay was not solely attributable to the respondent. Paragraph 30
    of the said judgment is set out below:

    30. However, the above finding is not sufficient to set aside the Impugned
    Award as the Impugned Award considers the question whether the respondent
    would be entitled to an extension of time on its own merit. Paragraphs 338 and
    339 of the Impugned Award record such decision of the Arbitral Tribunal and are
    reproduced hereinunder:-

    “338. In light of the above discussion, the Tribunal holds that
    although there was delay on the part of L&T in performance of its

    Signature Not Verified
    Signed By:VIVEK O.M.P. (COMM) 316/2019 Page 27 of 44
    MISHRA
    Signing Date:15.07.2026
    13:28:32
    obligations under the Contract, IOCL did contribute to the extra time
    taken in completion of the Project and is responsible for delay in
    supply of ECS data as well as supply of fuels. The Tribunal further
    holds that both parties contributed to delay and delay is not solely
    attributable to the Claimant. L&T entitled for extension of time till
    the actual dates of commissioning of Modules 1 and 2 and for
    Mechanical Completion of Module 3.

    339. In this view of the matter, even if it be assumed (although the
    Tribunal has recorded its finding on Issue No.1 that L&T was granted
    extension of time upto the actual date of commissioning Module 1 and
    Module 2 and Mechanical Completion of Module 3 of the CPP) that
    there was no extension of time granted by IOCL, the Tribunal holds
    that L&T is entitled to extension of time till the actual dates of
    commissioning of Modules 1 and 2 and for Mechanical Completion
    of Module 3. As a result of this finding, Clause 4.3.9.0 comes into
    operation.”

    (emphasis supplied)

    54. The petitioner (IOCL) filed an appeal against the aforesaid judgment,
    being FAO (OS)(COMM) 171/2018, which was dismissed by a Division Bench
    of this Court on 25th January, 2023.

    55. In fact, at the first hearing of the present petition dated 9th August, 2019,
    the petitioner had placed reliance on the very same findings in the judgment of
    the Single Judge in IOCL v. L&T (supra), and accordingly, this Court directed a
    partial deposit of the awarded amount. The respondent consortium filed an SLP
    against the order dated 9th August, 2019, wherein the Supreme Court held the
    findings of the Single Judge in IOCL v. L&T (supra) to be irrelevant for the
    purposes of the present case. Based on the above, the Supreme Court set aside
    the order dated 9th August, 2019, and directed the petitioner to make a full deposit

    Signature Not Verified
    Signed By:VIVEK O.M.P. (COMM) 316/2019 Page 28 of 44
    MISHRA
    Signing Date:15.07.2026
    13:28:32
    of the awarded amount. The relevant observations of the Supreme Court are set
    out below:-

    “…As a matter of fact, the very matter referred to in the order dated 09.08.2019 and
    06.03.2020, namely, O.M.P. (COMM) No. 366/2017 has resulted in a dismissal of a
    Section 34 petition in an award that was granted out of one of 17 other contracts
    arising out the same general transaction. Mr. Sharma was at pains to point that the
    Section 34 petition was dismissed in that matter on completely different grounds. Be
    that as it may, O.M.P. (COMM) No 366/2017 at the highest, therefore, would be
    irrelevant This O.M.P. (COMM) No. 366/2017 appears to be the main plank on which
    an amount of Rs. 125 Crores alone was ordered to be deposited out of an awarded
    amount of Rs. 662 Crores. Resultantly, we set aside both the orders and require a
    100% deposit of the awarded amount to be made within a period of six weeks from
    today. The appellants may apply to the High Court to withdraw this amount on
    security.”

    (emphasis supplied)

    56. The finding of the Arbitral Tribunal on the issue of effect of price discount
    was based on its findings that upon granting extension of time, the petitioner had
    accepted that the delay was justified and, consequently, the starting date for
    discount calculation stood correspondingly shifted in terms of Clauses 4.3.6.0
    and 4.4.2.1 of the GCC, rendering the levy of price discount inapplicable. The
    view adopted by the Arbitral Tribunal is a plausible interpretation of the Contract
    based on the material on record and does not suffer from any patent illegality or
    perversity so as to warrant interference under Section 34 of the Act.

    Delay in supply of steam

    57. On the aspect of delay, counsel for the petitioner submitted that there was
    no delay by the petitioner in supply of steam to the respondent consortium, and

    Signature Not Verified
    Signed By:VIVEK O.M.P. (COMM) 316/2019 Page 29 of 44
    MISHRA
    Signing Date:15.07.2026
    13:28:32
    that the delay was on the part of the respondent consortium as it was not ready
    to receive the steam.

    58. Per contra, counsel for the respondent consortium pointed out that this
    submission has not been raised in the present petition under Section 34 of the
    Act, nor in the opening submissions, and has only been raised in the rejoinder
    submissions.

    59. As per the terms of the Contract, the petitioner was to supply steam to the
    respondent consortium by 1st February, 2009, however, the same was provided
    only on 10th August, 2009. Nothing has been placed on record on behalf of the
    petitioner to show that the petitioner was ready to supply steam to the respondent
    consortium prior to the said date.

    60. It is an admitted position that various contracts with respect to PNCP were
    interlinked and that the steam to be produced in EPCC-4 was to be utilised for
    the purposes of EPCC-1. The witness of the petitioner was cross-examined on
    this aspect, wherein it was admitted that EPCC-4 had to supply some of the
    utilities for EPCC-1, including steam. The relevant extracts from the said cross-
    examination are set out below:

    “Q. Is it correct that EPCC-1 required utilities to be supplied from other EPCC
    projects?

    A. Yes, sir.

    Q. Is it correct that EPCC-4 had to supply utilities to EPCC-1?
    A. Yes, some of the utilities.

    Q. What would those utilities be?

    A. Steams, all sorts of steams, SHP, HP, MP, LP.

    Signature Not Verified
    Signed By:VIVEK O.M.P. (COMM) 316/2019 Page 30 of 44
    MISHRA
    Signing Date:15.07.2026
    13:28:32

    Q. Is it correct that EPCC-5 was also to supply utilities to EPCC-1?
    A. EPCC-5, Cooling water, You can say that, because they constructed the
    cooling tower.”

    61. What emerges from the above is that if there was any delay in the
    completion of EPCC-4, it would result in delay in supply of utilities from EPCC-
    4 to EPCC-1. The factum of delay in completion of EPCC-4 has already been
    established in terms of the judgment of this Court in IOCL v. L&T (supra), which
    has been upheld by the Division Bench of this Court vide judgment dated 25th
    January, 2023 in FAO (OS)(COMM) 171/2018.

    62. One of the objections taken by the petitioner is that the Arbitral Tribunal
    failed to adjudicate on each element of delay and whether the same was
    attributable to the petitioner or the respondent consortium. It is contended that
    despite framing a specific issue on the attributability of delay, i.e. Issue no. 2.3,
    no finding was returned by the Arbitral Tribunal on the said issue.

    63. In this regard, the relevant observations of the Arbitral Tribunal are
    extracted below:

    “In the light of the decision the Tribunal has arrived at on the grant of EOT
    coinciding with the date of MC, and particularly as the Parties had contractually
    agreed by Clause 4.3.6.0 that the decision of the owner in that respect is final, there
    is no call for the Tribunal to consider each alleged item of delay and/or which party
    was responsible for such delay and the extent of each item of delay.”

    64. In the overall context of the contract, price discount would be applicable
    only upon the failure of the respondent consortium to achieve MC in terms of the

    Signature Not Verified
    Signed By:VIVEK O.M.P. (COMM) 316/2019 Page 31 of 44
    MISHRA
    Signing Date:15.07.2026
    13:28:32
    specified time schedule and was not dependent on individual elements of delay.
    Since the Arbitral Tribunal held that the overall delay was accepted by the
    petitioner as being justified by granting an extension in terms of Clause 4.3.6.0
    of the GCC, there was no occasion for the Arbitral Tribunal to go into this issue
    and give individual findings on various elements of delay.

    Applicability of Section 74 ICA

    65. Next, I will deal with the finding given by the Arbitral Tribunal that the
    price reduction clause, i.e. Clause 4.4.0.0, read with Clauses 4.4.2.0 and 4.4.2.1
    of the GCC, is in the nature of a penalty in terms of Section 74 ICA.

    66. The Arbitral Tribunal prefaces the aforesaid finding by noting that the
    arguments raised by the respondent consortium to the effect that the Clause
    4.4.0.0, read with Clauses 4.4.2.0 and 4.4.2.1, falls under Section 74 ICA and is
    in the nature of a penalty, was an argument in the alternative. The Arbitral
    Tribunal clearly holds that, in light of the findings given by the Arbitral Tribunal
    in paragraph 97, the Arbitral Tribunal is not required to give a finding on this
    aspect and that the Arbitral Tribunal is giving these findings out of deference to
    the submissions made by the parties. Paragraphs 98.1 and 98.2 of the Award,
    which set out the context of the aforesaid finding, are set out below:

    “98.1 As a second string to their bow, as an “in-any-event proposition”, the Claimants
    contend that the imposition of Price Adjustment falls within the scope of Section
    74
    of the Indian Contract Act, 1872 and that failure to meet the Section 74
    requirements, is fatal to the Respondent making the 10% deduction.
    98.2 Although in the light of our decision set out in paragraph 97 hereof, there is not
    much point in our considering the further contentions of the Parties, out of

    Signature Not Verified
    Signed By:VIVEK O.M.P. (COMM) 316/2019 Page 32 of 44
    MISHRA
    Signing Date:15.07.2026
    13:28:32
    deference to the submissions and arguments of the Parties in respect thereof, we
    direct our minds to the Section 74 point.”

    67. Relying on the judgment of the Supreme Court in Fateh Chand v.
    Balakrishnan Dass7
    , the Arbitral Tribunal held that the aforesaid clauses are
    penal clauses in terms of Section 74 ICA. Paragraphs 110 and 113 of the Award
    are set out below:

    “110. Guided by Fateh Chand (supra) and other decisions of the Indian Courts
    including in Punj Lloyd Ltd vs Hindustan Petroleum Corp, [2015] see online Bom
    752, (where the price reduction clause of Rupees 1,000.00 per day was held by
    the High Court, to be in the nature of a penalty), the Tribunal notes and
    respectfully accepts that the trend in the Indian Courts is to thwart attempts by
    parties to a contract, to try, by the use of dexterous language, to get round the
    Section 74 Contracts Act treatment against penalty clauses, and in the context,
    using a commonsense approach, the Tribunal is satisfied that on the facts of the
    instant matter, the price reduction clause, Clause 4.4.0.0 read in particular with
    Clause 4.4.2.0 and 4.4.2.1, is in the context of Section 74 of the Contracts Act, a
    “stipulation by way of penalty”.

    113. However applying the Judgment in EIL vs Tema India Ltd, 2016 SCC On
    Line DEL 86 paragraph 21 and the Judgment of Rohinton Fali Nariman J
    speaking for the Supreme Court in Kailash Nath Associates [2015] 4 SCC 136
    (see paragraphs 43.6 and 44 of the report), we have to and hold, that Section
    74
    operates to defeat the Respondent’s Price Reduction Claim inter alia
    because the Respondent has failed to prove damage.”

    (emphasis supplied)

    68. Pertinently, one of the Arbitrators, Justice S.B. Sinha (Retd.), in his
    partially dissenting award, held that the price adjustment clause is not void,
    however he agreed with the ultimate finding of the Arbitral Tribunal. The

    7
    AIR (1963) SC 1405.

    Signature Not Verified
    Signed By:VIVEK O.M.P. (COMM) 316/2019 Page 33 of 44
    MISHRA
    Signing Date:15.07.2026
    13:28:32

    relevant extracts from the partially dissenting award of Justice Sinha are set out
    below:-

    “2. ISSUE NO.2 – PRICE ADJUSTMENT
    2.1 The question as to whether the Price Reduction Clause can be held to be
    a penal clause, depends upon the facts and circumstances of each case as well as
    the conduct of the parties.

    2.2 In India, unlike the English law, penalty and estimated damages have been
    held to be at part.

    See Fateh Chand v. Balkishan Dass, AIR (1963) SC 1405 followed in
    Kailash Nath Associates v. DDA (2015) 4 SCC 136.

    In Construction and Design Services v. Delhi Developmental Authority
    (2015) 14 SCC 263 only 50% of the penalty imposed in terms of the Contract has
    been awarded by the Supreme Court of India.

    2.3 Price Adjustment Clause contained in the contract, in my opinion, is not
    void.

    2.4 Validity of a Price Adjustment clause inter alia has been upheld in
    Cavendish Square Holdings BV v. Tala/ El Makdessi [2016] 2 All E.R. 519 (SC),
    paras 71 to 74)
    2.5 In a case of this nature, the Price Adjustment clause cannot be said to be
    penal in nature as is understood in Common Law as it does not disentitle the
    contractor of money which otherwise would have been due to him totally. It is
    merely contemplates a reduction in the amount payable to the Contractor in case
    of delay.

    2.6 The Claimants have entered into such a contract with their eyes wide
    open. They have themselves been asking the Respondent not to invoke the Price
    reduction Clause.

    2.7 I, however, agree with the ultimate finding that in this case Section 74
    of the Indian Contract Act shall be attracted in the peculiar facts and
    circumstances of the case.”

    (emphasis supplied)

    69. As noted above, the finding of the Arbitral Tribunal that, in the facts and
    circumstances of the case, Clauses 4.4.2.0 and 4.4.2.1 of the GCC are hit by
    Section 74 ICA, is only a finding given in the alternative. The primary finding

    Signature Not Verified
    Signed By:VIVEK O.M.P. (COMM) 316/2019 Page 34 of 44
    MISHRA
    Signing Date:15.07.2026
    13:28:32
    of the Arbitral Tribunal is to the effect that delay on the part of the respondent
    consortium was justified in terms of Clause 4.3.6.0 and hence, the petitioner
    could not have imposed a price discount (Ref: Paragraph 97 of the Impugned
    Award). In view of the aforesaid primary finding returned by the Arbitral
    Tribunal, the Impugned Award cannot be interfered with under Section 34 of the
    Act solely on the basis of its secondary finding (finding in the alternative)
    regarding the applicability of Section 74 ICA to the price discount clause, i.e.
    Clause 4.4.0.0 of the GCC. The aforesaid secondary finding would not affect the
    ultimate outcome of the award. This view also finds support from the partially
    dissenting award of Justice Sinha.

    70. Counsel for the petitioner contends that Clause 4.4.0.0, read with Clauses
    4.4.2.0 and 4.4.2.1, providing for price discount cannot be considered to be a
    penal clause under Section 74 ICA. In this regard the petitioner places reliance
    on IOCL v. Fiberfill Engineers8

    71. The decision in IOCL v. Fiberfill Engineers (supra), is in the context of
    an appeal under Section 37 of the Act with respect to a domestic award dealing
    with a similar price reduction clause. A Division Bench of this Court dismissed
    the appeal filed by the IOCL, as IOCL had failed to establish loss. In the present
    case also, the Arbitral Tribunal has held that the petitioner has failed to prove
    damages (Ref. Para 113 of the Impugned Award set out above).

    72. Counsel for the respondent consortium places reliance on the judgement
    of the Madras High Court in Indian Oil Corporation Limited v. Fabtech Works

    8
    2024 SCC OnLine Del 8133.

    Signature Not Verified
    Signed By:VIVEK O.M.P. (COMM) 316/2019 Page 35 of 44
    MISHRA
    Signing Date:15.07.2026
    13:28:32

    and Constructions9 to submit that there is no infirmity in the finding of the
    Tribunal that Clause 4.4.2.0 and 4.4.2.1 are penal in nature.

    73. In Indian Oil Corporation Limited v. Fabtech Works and Constructions
    (supra), the Madras High Court held a similar price adjustment clause to be in
    the nature of a stipulation for compensation on account of breach and, hence,
    subject to Section 74 ICA. Accordingly, in the absence of proof of loss, it was
    held that no amount could be awarded to the petitioner by way of price reduction.
    The relevant findings of the Court are extracted hereunder:

    “…As stated earlier, Section 74 of the Contract Act does not refer specifically
    to liquidated damages. On the other hand, it refers to a stipulation by way of
    compensation. Therefore, Clause 4.4 of the GCC would qualify as a stipulation
    by way of compensation. Once it qualifies as a stipulation by way of
    compensation, it became necessary for the Petitioner to prove that loss was
    incurred as a result of breach, although it may not be necessary to prove the
    exact quantum of loss, if it is difficult or impossible to prove the same. These
    are the settled principles as per the decisions of the Hon’ble Supreme Court in
    Fateh Chand vs. Balkishan Dass, (1964) 1 SCR 515, Maula Bux vs. Union of
    India
    , (1969) 2 SCC 554, Oil & Natural Gas Corporation Ltd vs. Saw Pipes
    Ltd
    ,(2003) 5 SCC 705 and Kailash Nath vs. DDA(the Kailash Nath case)(2015)
    4 SCC 136. ….. The Petitioner cannot circumvent the legal regime governing
    the imposition of liquidated damages merely by using the label, price
    adjustment. Therefore, in the admitted absence of proof of the factum of loss,
    it would be an injuria sine damnum scenario and the Petitioner is not entitled
    to compensation by way of price adjustment. Therefore, I do not find any
    reason to interfere with the Arbitral Award.”

    (emphasis supplied)

    74. Therefore, even the secondary finding given by the Arbitral Tribunal
    with regard to the interpretation of Clauses 4.4.2.0 and 4.4.2.1 of the GCC being
    penal in terms of Section 74, ICA cannot be said to be unconscionable in terms

    9
    (2020) 1 Mad LJ 52.

    Signature Not Verified
    Signed By:VIVEK O.M.P. (COMM) 316/2019 Page 36 of 44
    MISHRA
    Signing Date:15.07.2026
    13:28:32

    of Associate Builders (supra) and Ssanyong (supra) so as to warrant interference
    under Section 34 (2)(b)(ii) of the Act. To be noted, the present award has been
    rendered in an international commercial arbitration, where the ground of patent
    illegality is not available as a ground for interference.

    ISSUE NO. 2: JURISDICTION

    Submissions on behalf of the petitioner

    75. The claims raised by the respondent consortium did not satisfy the
    mandatory preconditions under Clause 9.1.0.0 of the GCC, inasmuch as the
    claims were neither duly notified under Clause 6.6.1.0, nor included in the final
    bill. Consequently, the Arbitral Tribunal lacked jurisdiction to adjudicate the said
    claims. Reliance in this regard is placed on Indian Oil Corporation Ltd. v. NCC
    Limited10
    , wherein, while considering an identical arbitration clause, the Court
    held that claims neither notified nor included in the final bill would not be
    arbitrable.

    76. The Arbitral Tribunal erroneously relied upon Clause 9.4.1.0 of the GCC
    to hold that the deductions made by the petitioner constituted claims by the
    petitioner. The said clause applies only where the contractor is a Public Sector
    Undertaking (hereinafter ‘PSU’), whereas the respondents no.1 and 2 herein are
    not PSUs.

    Submissions on behalf of the respondent consortium

    10
    (2023) 2 SCC 539.

    Signature Not Verified
    Signed By:VIVEK O.M.P. (COMM) 316/2019 Page 37 of 44
    MISHRA
    Signing Date:15.07.2026
    13:28:32

    77. The claims referred to the Arbitral Tribunal were arbitrable. The said
    claims were in respect of deductions made by the petitioner consequential to the
    amounts claimed by the petitioner from the respondent consortium. Accordingly,
    they fell within the second category of arbitrable disputes contemplated under
    Clause 9.1.0.0 of the GCC and did not require notification.

    78. The interpretation placed by the Arbitral Tribunal on Clause 9.1.0.0 is a
    plausible interpretation arising from the terms of the contract and cannot be
    interfered with in proceedings under Section 34 of the Act.

    Analysis

    79. At the outset, it may be relevant to refer to Clause 9.1.0.0 of the GCC,
    which is the arbitration clause. Clause 9.1.0.0 is set out below:

    “9.1.0.0. Subject to the provisions of Clauses 6.7.1.0, 6.7.2.0 and 9.1.1.0
    hereof, any dispute arising out of a Notified Claim of the CONTRACTOR
    included in the Final Bill of the CONTRACTOR in accordance with the
    provisions of Clause 6.6.3.0 hereof, if the CONTRACTOR has not opted for the
    Alternative Dispute Resolution Machinery referred to in Clause 9.2.0.0 in
    respect thereof, and any dispute arising out of an amount claimed by the
    OWNER against the CONTRACTOR shall be referred to the arbitration by
    an Arbitral Tribunal comprised of 3 (three) arbitrators selected in accordance
    with the provisions of the Arbitration & Conciliation Act, 1996. It is specifically
    agreed that the OWNER may prefer its Claim(s) against the CONTRACTOR as
    counter-claim(s). The CONTRACTOR shall not, however, be entitled to raise as
    a setoff, defence or counter-claim any claim which is not a Notified Claim
    included in the CONTRACTOR’s Final Bill in accordance with the provisions
    of Clause 6.8.3.0 hereof.”

    (emphasis supplied)

    Signature Not Verified
    Signed By:VIVEK O.M.P. (COMM) 316/2019 Page 38 of 44
    MISHRA
    Signing Date:15.07.2026
    13:28:32

    80. In terms of the aforesaid clause, there are two types of disputes that can be
    referred to arbitration:

    i. Disputes arising out of a notified claim of the contractor included in
    the final bill of the contractor in terms of Clause 6.6.3.0, and
    ii. Disputes arising out of an amount claimed by the owner against the
    contractor.

    81. The Arbitral Tribunal held that the subject disputes fell within the scope
    of the second part of the arbitration clause, as the petitioner, towards its claims,
    deducted amounts from the bills raised by the respondent consortium. The
    relevant findings of the Arbitral Tribunal in this regard in paragraph 45.3 of the
    Impugned Award are set out below:

    “45.3 The Tribunal is satisfied that each of the 4A claims are in effect in respect
    of deductions made by the Respondent consequential to amounts claimed by the
    Respondent owner against the Claimants. It is the Tribunal finding that each of
    the 4A claims is a Clause 9.1.0.0 second category claim by the Owner
    Respondent. Accordingly, it is the Tribunal’s finding that the requirement for
    “notification” in respect of each of the 4A claims, has no relevance and
    accordingly was not required”

    82. In the opinion of this Court no fault can be found with the aforesaid finding
    of the Arbitral Tribunal with regard to interpretation of Clause 9.1.0.0 . Merely
    because the respondent consortium (Contractor) has invoked the arbitration
    clause, it would not mean that the claims made in the arbitration cannot fall under
    the second category of Clause 9.1.0.0.

    83. To arrive at the aforesaid finding, the Arbitral Tribunal also relied on
    Clause 9.4.1.0 of the GCC, which is the arbitration clause applicable in respect

    Signature Not Verified
    Signed By:VIVEK O.M.P. (COMM) 316/2019 Page 39 of 44
    MISHRA
    Signing Date:15.07.2026
    13:28:32
    of a contractor which is a PSU. The said clause also uses the words ‘amounts
    claimed by the contractor’, followed by an explanation of the same in
    parenthesis. Clause 9.4.1.0 is set out below:

    “9.4.1.0. If the CONTRACTOR is a Public Sector Undertaking or Enterprises or
    is a Government Department, any dispute or difference between the parties hereto
    arising out of any notified claim of the CONTRACTOR in terms hereof and/or
    arising out of any amount claimed by the OWNER (whether or not the amount
    claimed by the OWNER or any part thereof shall have been deducted from the
    Final Bill of the CONTRACTOR or any amount paid by the OWNER to the
    CONTRACTOR In respect of the work) which cannot be resolved amicably by
    mutual consultation or through the good offices of empowered agencies of the
    Government, shall be referred to arbitration of one of the arbitrators to be
    nominated by Secretary to the Government of India in charge of the Bureau of
    Public Enterprises. The Arbitration Act, 1996 (26 of 1996) shall not be applicable
    to the arbitration under this clause the award of the Arbitrator shall be binding up
    on the parties to the dispute, provided, however, that any party aggrieved by such
    award may make a further reference for setting aside or revision of the award to
    the Law Secretary, Department of Legal Affairs, Ministry of Law and Justice,
    Government of India. Upon such reference the dispute shall be decided by the Law
    Secretary or the Special Secretary or Additional Secretary, as the case may be,
    whose decision on the appeal shall bind the parties finally and conclusively. The
    parties to the dispute will share equally the cost of arbitration as intimated by the
    Arbitrator.”

    (emphasis supplied)

    84. The words occurring in the parenthesis in Clause 9.4.1.0 make it
    unambiguous that arbitration could have been invoked in respect of an amount
    claimed by the Owner (petitioner herein), whether the same has been deducted
    from the final bill of the Contractor (respondent consortium herein) or not. The
    relevant findings of the Arbitral Tribunal in this regard are set out below:

    Signature Not Verified
    Signed By:VIVEK O.M.P. (COMM) 316/2019 Page 40 of 44
    MISHRA
    Signing Date:15.07.2026
    13:28:32

    “43.4 The Tribunal recognises that it is a trite canon of construction of a
    contract that in construing a term of a contract, reliance may be placed, or
    guidance sought, on what is set out in other terms of the contract.

    44. The Tribunal has to and agrees with the Claimants that the words in
    parenthesis in Clause 9.4.1.0 evidences a recognition that the amounts
    deducted by the Respondent is pursuant to a claim by it..”

    85. The respondent consortium has correctly placed reliance on the judgment
    of this Court in Shapoorji Pallonji v. Ratan India Power11, in support of its
    submission that words, clauses, or a sentence appearing in a parenthesis are
    generally inserted as an explanation. Paragraph 52 of the said judgment is set out
    below:

    “52. It can be discerned from the aforesaid decisions that words, clauses or a
    sentence appearing in parenthesis are inserted in a passage as an explanation,
    which is otherwise also, grammatically complete without it. In other words, the
    purpose of a parenthesis is ordinarily to insert an illustration, explanation,
    definition or additional piece of information of any sort in a sentence that is
    logically and grammatically complete without it.”

    86. In Bank of India v. K. Mohandas and Ors.12, the Supreme Court held that
    a contract must be read as a whole in order to ascertain the true meaning of its
    several clauses and the words of each clause should be interpreted so as to bring
    them into harmony with the other provisions.

    87. Accordingly, the Arbitral Tribunal held that the explanation given in the
    parenthesis of Clause 9.4.1.0 can be read into Clause 9.1.0.0 and the two clauses
    of the contract have to be read in a harmonious manner.

    11

    2021 SCC OnLine Del 3688.

    12

    (2009) 5 SCC 313.

    Signature Not Verified
    Signed By:VIVEK O.M.P. (COMM) 316/2019 Page 41 of 44
    MISHRA
    Signing Date:15.07.2026
    13:28:32

    88. By contrast, Justice S.B. Sinha (Retd.), in his partially dissenting award,
    held that the respondent consortium was required to notify its claims. However,
    he held that the said requirement was satisfied in terms of the notice for
    arbitration issued by the respondent consortium. Hence, he agreed with the
    ultimate finding that the Arbitral Tribunal had jurisdiction over the subject
    disputes. The relevant findings from the partially dissenting opinion of Justice
    Sinha are set out below:-

    “1.5. The Claimants had to recover the said amount and, thus, were obligated to
    raise a dispute with regard thereto. The Claimant, therefore was required to and
    did notify the said claims by seeking recovery of the deducted amount in its
    Notice for Arbitration, in terms of Section 21 of the Arbitration and
    Conciliation Act, 1996…”

    (emphasis supplied)

    89. It is a settled position of law that interpretation of contractual clauses falls
    squarely within the domain of the Arbitral Tribunal. Reference in this regard may
    be made to Ssangyong (supra) and Municipal Corporation of Delhi v. IJM
    Corporation Berhad
    (supra).

    90. Counsel for the petitioner has placed reliance on Indian Oil Corporation
    Ltd. v. NCC Limited
    (supra). The said judgment arose out of an appeal against
    an order of the High Court allowing a petition under Section 11 of the Act.
    Pertinently, the said judgment was rendered in the context of a clause which
    expressly required deductions from the contractor’s bills to be notified, which is
    not the requirement under the Clause 6.6.1.0 in the present case. Hence, the
    reliance placed by the petitioner upon the said judgment is misplaced.

    Signature Not Verified
    Signed By:VIVEK O.M.P. (COMM) 316/2019 Page 42 of 44
    MISHRA
    Signing Date:15.07.2026
    13:28:32

    91. The finding of the Arbitral Tribunal that the subject disputes fell within
    the scope of the arbitration agreement, and were hence arbitrable, is based on its
    interpretation of the Clause 9.1.0.0 of the GCC and the surrounding contractual
    framework governing the parties. In the opinion of this Court, , the said finding
    is a plausible construction of the Contract and no grounds have been made out
    for interference with the same under Section 34 of the Act.

    CONCLUSION

    92. In view of the foregoing discussion and upon examination of the
    Impugned Award in light of the scope of jurisdiction available under Section 34
    of the Act, this Court finds no grounds warranting interference with the findings
    returned by the Arbitral Tribunal. The findings of the Arbitral Tribunal on
    arbitrability of the disputes and on issues concerning delay, extension of time and
    price adjustment are based on the interpretation of the relevant contractual
    provisions and appreciation of the evidence led by parties before the Arbitral
    Tribunal. The petitioner, by way of the present petition, in effect, seeks a re-
    appreciation of evidence and an alternative interpretation of clauses the Contract,
    which is beyond the scope of interference under Section 34 of the Act.

    93. Accordingly, the present petition is dismissed.

    94. The bank guarantees furnished by the respondents shall stand discharged
    after a period of four (4) weeks from today.

    Signature Not Verified
    Signed By:VIVEK O.M.P. (COMM) 316/2019 Page 43 of 44
    MISHRA
    Signing Date:15.07.2026
    13:28:32

    I.A. 30713/2024 & I.A. 19429/2022

    95. I.A. 30713/2024 has been filed by the respondents seeking a direction to
    the petitioner to deposit further amounts towards the principal and interest as per
    the Impugned Award.

    96. I.A. 19429/2022 has been filed by the respondents, seeking reimbursement
    of amounts towards the sums incurred by the respondent towards the bank
    guarantees.

    97. In view of the order passed above dismissing the petition under Section 34
    of the Act, the present applications are disposed of with liberty to the respondents
    to agitate these issues in the execution proceedings.

    AMIT BANSAL
    (JUDGE)
    JULY 15, 2026
    Rzu

    Signature Not Verified
    Signed By:VIVEK O.M.P. (COMM) 316/2019 Page 44 of 44