National Highways Authority Of India … vs South Indian Bank Ltd And Union Bank Of … on 9 July, 2026

    0
    7
    ADVERTISEMENT

    Delhi High Court

    National Highways Authority Of India … vs South Indian Bank Ltd And Union Bank Of … on 9 July, 2026

    Author: V. Kameswar Rao

    Bench: V. Kameswar Rao

                              *     IN THE HIGH COURT OF DELHI AT NEW DELHI
    
                              %                                              Judgment reserved on: 10.04.2026
                                                                            Judgment delivered on: 09.07.2026
                                                               Judgment uploaded on: As per Digital Signature~
    
                              +     FAO(OS) (COMM) 137/2025 & CM APPL. 56772/2025
                              +     FAO(OS) (COMM) 152/2025 & CM APPL. 60827/2025
    
                                    NATIONAL HIGHWAYS AUTHORITY OF INDIA (NHAI)
                                                                             .....Appellant
                                                  versus
                                    SOUTH INDIAN BANK LTD AND UNION
                                    BANK OF INDIA LTD & ANR.            .....Respondents
    
                              Advocates who appeared in this case
    
                              For the Appellant            :       Mr. Sudhir Nandrajog, Sr. Advocate with
                                                                   Mr. Nishant Awana, Ms Rini Badoni and
                                                                   Ms. Ankita Singh, Advs.
    
                              For the Respondents          :       Mr. Sandeep Sethi, Sr. Advocate with Mr.
                                                                   Manish Dembla Adv. Mr. Shubham
                                                                   Kaushik Advocate for R1.
    
                              CORAM:
                              HON'BLE MR. JUSTICE V. KAMESWAR RAO
                              HON'BLE MR. JUSTICE VINOD KUMAR
    
                                                                   JUDGMENT
    

    V. KAMESWAR RAO, J.

    1. These appeals have been filed by the appellant under Section 37 of
    the Arbitration and Conciliation Act, 1996 (‘the Act’, for short) challenging
    the common judgment passed by the learned Single Judge in O.M.P
    (Comm.) Nos.125/2025 & 126/2025, whereby the learned Single Judge has

    SPONSORED

    Signature Not Verified
    Signed By:PRADEEP FAO OS (COMM) 137/2025 & 152/2025 Page 1 of 61
    SHARMA
    Signing Date:09.07.2026
    20:07:25
    dismissed the petitions filed by the appellant/National Highways Authority
    of India (NHAI) under Section 34 of the Act challenging the Arbitral
    Awards dated 13.11.2024. The appeals are filed with the following prayers:-

    FAO(OS) (COMM) 137/2025
    “A. Set aside the Order dated 01.07.2025 (“Impugned Judgement”)
    passed by the Ld. Single Judge of this Hon’ble Court;”

    FAO(OS) (COMM) 152/2025
    “A. Set aside the Order dated 01.07.2025 (“Impugned Judgement”)
    passed by the Ld. Single Judge of this Hon’ble Court in O.M.P.
    (COMM.) 126/2025;”

    2. Since the issues in both the appeals arise out of a common impugned
    judgment, against the Awards passed by the Arbitral Tribunal (‘Tribunal’)
    both the appeals have been heard and decided together.

    FACTS

    3. On 12.07.2010, the appellant and the respondent no.2 entered into a
    Concession Agreements (‘CAs’) for Two-laning of the Trichy-Karaikudi
    Road Section of NH-210 (10.00 Km to 94.00 Km ), including the Trichy
    bypass (110.016 Km to 135.930 Km) (“Concession Agreements I”, CA-I for
    short) & Two-laning with paved shoulder of Dindigul-Theni Section from
    Km 2.750 to Km 73.400 of NH -45 (Extn.) and Theni-Kumili Section of
    NH-220 from Km 215.500 to Km 273.600 (“Concession Agreements II”,
    CA-II, for short), in Tamil Nadu under NHDP Phase III” (‘Project’) on a
    Design, Build, Finance, Operate and Transfer (“DBFOT”) Annuity basis.

    4. On 08.01.2011, the respondent No. 1 (Lender) and the respondent
    No.2 (the concessionaire) entered into a Common Loan Agreements (‘CLA’,

    Signature Not Verified
    Signed By:PRADEEP FAO OS (COMM) 137/2025 & 152/2025 Page 2 of 61
    SHARMA
    Signing Date:09.07.2026
    20:07:25
    for short) vide which the respondent No.1 agreed to make available financial
    assistance to tune of ₹ 198,00,00,000/- & ₹ 187,00,00,000/- to the
    respondent No. 2.

    5. On 04.05.2011, An Escrow Agreement (EA) was executed between
    the appellant, respondent no.1/Lenders & respondent no.2.

    FACTS IN FAO(OS) (COMM) 137/2025

    6. In terms of CA-I, the Scheduled Completion Date was 31.08.2013.
    The Annuity Payment was to start from 07.07.2013 and to end on
    07.01.2032, subjected to modification, contingent upon the appointed date
    and compliance of the terms of the CA-I.

    7. On 27.07.2011, the appellant under the CA-I, out of the total 133.793
    Km of land required for construction of the Project, handed over 85.150 km
    of land to respondent No. 2 as per the Joint Memorandum signed by the
    appellant and respondent No.2, i.e., handed over 63.64% of the land to
    respondent No. 2. The parties agreed that as per the CA-I, the appointed date
    is 01.09.2011 and deemed the said date as commencement of concession
    period and commencement of the construction. On 31.05.2013, a
    Substitution Agreement (‘SA’) was entered into between the appellant, the
    respondent No. 1 and 2 for granting substitution rights to the respondent No.
    1 in case of occurrence of financial default by the respondent No. 2.

    8. According to the appellant, the appellant has handed over 110.177
    Km of the total land to respondent No. 2 as on 31.12.2013, meaning 82.34%
    of the total land had been handed over to the respondent No.2. Despite

    Signature Not Verified
    Signed By:PRADEEP FAO OS (COMM) 137/2025 & 152/2025 Page 3 of 61
    SHARMA
    Signing Date:09.07.2026
    20:07:25
    handing over of 82.34% of the land, from April 2013 till March 2014, the
    progress on the Project site was a dismal (1.83%). By December 2013, the
    work on the Project site had come to a complete stop.

    9. On 15.04.2014, 16.04.2014, 21.01.2015, and 25.02.2015, the
    Independent Engineer (‘IE’, for short) and the Project Director of the
    appellant issued letters to respondent No. 2, calling upon it to resume the
    work on the Project site, however, was of no avail. On 28.02.2015, the
    appellant had handed over 100% of the land qua the Project to the
    respondent No. 2, i.e., a stretch of 133.793 Km.

    10. During the safety audits conducted by the road safety consultant for
    the Project, the consultant notified several deficiencies and lapses in the
    maintenance of the highway to respondent No.2 vide a letter dated
    19.03.2015. On 10.06.2015, the appellant invoked Article 37.1 of the CA
    and issued a Cure Period Notice thereby detailing the non-compliance of the
    provisions of the CA and directed respondent No.2 to immediately cure the
    defaults enumerated in the said notice within 60 days there from, failing
    which the appellant would exercise its rights and remedies under the CA.

    11. On 13.08.2015, the Notice of Intention to Terminate was issued by the
    appellant to respondent No. 2 under Article 37.1.2 of the CA, and gave last
    and final opportunity to send its representation within 15 days, as to why the
    CA should not be terminated. The appellant under Article 37.1.3 issued a
    copy of the Notice of Intention to Terminate to respondent no.1 inviting it to
    state its intention to substitute respondent No. 2 in accordance with the SA.

    Signature Not Verified
    Signed By:PRADEEP FAO OS (COMM) 137/2025 & 152/2025 Page 4 of 61
    SHARMA
    Signing Date:09.07.2026
    20:07:25

    12. On 27.08.2015, the respondent No. 1 and 2 entered into a second
    Supplementary CLA. On the commitments of the respondent No. 2 and
    assurances of the respondent No.1, the appellant vide letter dated 28.09.2015
    to respondent No.2 decided to the keep the Intention to Terminate Notice
    under abeyance for 90 days, thereby allowing respondent No.2 to resume
    work at the Project site.

    13. On 08.12.2016 the IE issued the ‘Provisional Completion Certificate’
    (“PCC”) to respondent No.2. On 17.12.2016, the IE informed the respondent
    No. 2 that the PCC is kept in abeyance until the completion of the Theni
    Bypass, as was agreed by respondent No.2 qua the Supplementary
    Agreement.

    14. On 31.03.2018, the account of respondent No. 2 was classified as a
    Non-Performing Asset (‘NPA’) as per RBI guidelines. On 11.10.2018, the
    appellant issued ‘Suspension Notice’ under Article 36.1 of the CA. The
    respondent No. 1 issued a Notice of Financial default dated 26.03.2019 to
    the respondent No.2. On 01.04.2019, the respondent No.1 issued Notice of
    Financial Default to the appellant informing it about the material breach of
    the terms of the CLA and “Event of Default” under Clauses 7.1 (a) & 7.1 (b)
    of the CLA.

    15. The respondent No. 1 requested the appellant to terminate the CA on
    account of “Financial Default” under Article 5.1 of the SA by issuing
    Termination Notice in accordance with the provisions of CA.

    16. On 22.05.2019, under Article 36.5 of the CA, the same was
    terminated w.e.f. 09.04.2019. The appellant issued Termination Notice to

    Signature Not Verified
    Signed By:PRADEEP FAO OS (COMM) 137/2025 & 152/2025 Page 5 of 61
    SHARMA
    Signing Date:09.07.2026
    20:07:25
    respondent No.2, and informed respondent No.2 that, it had taken over the
    Project. On 04.11.2019, the respondent no.1/Lenders filed a petition under
    Section 9 of the Act being OMP (I) COMM. No.406/2019, against the
    appellant to deposit the Termination Payment in the Escrow Account.

    17. On 26.11.2019, the respondent No. 2 issued a notice to the appellant
    invoking arbitration under the CA. On 28.01.2020, respondent No. l issued a
    Notice invoking the arbitration under Clause 10 of the EA and Clause 8 of
    the SA. The respondent No.1 preferred a petition under Section 11 of the
    Act on 25.08.2021, seeking appointment of 3rd Arbitrator. The petition under
    Section 9 of the Act was disposed of vide order dated 12.05.2022, to agitate
    the same before the learned Tribunal. The learned Tribunal stood constituted
    vide order dated 12.05.2022.

    18. As the respondent No.2 did not enter appearance before the learned
    Tribunal, it was proceeded ex-parte. The learned Tribunal framed the
    following issues for its consideration:-

    “78. The final issues based on these amended pleadings were
    finalized on 9.8.2023by the Tribunal, as follows:

    “1. Whether the present arbitral proceedings are liable to
    be terminated on the ground that the claims of the Claimant
    are beyond the scope of Escrow Agreement and/or the
    Substitution Agreement?

    2. Whether the Claimant is entitled to seek Termination
    Payment or 90% Debt Due and interest thereon from the
    Respondent No. 2 having invoked the arbitration under the
    Escrow Agreement and/or the Substitution Agreement?

    3. Whether the issue of “Debt Due” can be termed as a
    “dispute” under the arbitration clause of the Escrow
    Agreement or the Substitution Agreement?

    Signature Not Verified
    Signed By:PRADEEP FAO OS (COMM) 137/2025 & 152/2025 Page 6 of 61
    SHARMA
    Signing Date:09.07.2026
    20:07:25

    4. Whether the issue of “Debt Due” was referred to
    arbitration in accordance with notice under Section 21 of
    the Arbitration and Conciliation Act, 1996?

    5. Whether the Claimant is entitled to a declaration that the
    letter dated 17.12.2016 issued by I.E purportedly keeping
    the PCC dated 08.12.2016 in abeyance was non-est, void
    ab-initio and beyond the scope and powers of I.E and
    Respondent No.2?

    6. Whether the Claimant is entitled to a declaration that
    Respondent No. 2 is liable to deposit in the Escrow
    Account i.e., account no. 0246073000005523 with the
    Secunderabad Branch of SIB, the termination payment?

    7. Whether the Claimant is entitled to a declaration that
    Respondent No. 2 is liable to deposit an amount of Rs.

                               393,49,97,509/- or any        other amount as termination
                               payment in the Escrow Account as             claimed in the
                               Statement of Claim?
    

    8. Whether the Respondent is liable to deposit a total
    termination payment of Rs.393,49,97,509/- on account of
    termination of the Concession Agreement?

    9. Whether Respondent No. 2 is liable to pay 90% of Debt
    Due of Rs.258,13,11,357/- or any other amount to the
    Claimant as damages for non-deposit of Termination
    Payment in the Escrow Account?

    10. Whether the Claimant can claim damages on account of
    default of Respondent if the contract provides for interest?

    11. Whether the Claimant is entitled to pre-reference
    interest of Rs.95,21,85,647/- on 90% Debut Due at the rate
    of 12% p.a. for the period 16.04.2019 to 12.05.2022 as
    damages for non-deposit of Termination Payment in the
    Escrow Account?

    12. Whether the Claimant is entitled to pendente lite interest
    on 90% Debt Due as damages for non-deposit of
    Termination Payment in the Escrow Account? If so, from
    which date and at what rate?

    13. Whether the Claimant is entitled to future interest? If so,
    at what rate?

    14. Costs?””

    Signature Not Verified
    Signed By:PRADEEP FAO OS (COMM) 137/2025 & 152/2025 Page 7 of 61
    SHARMA
    Signing Date:09.07.2026
    20:07:25

    19. On 13.11.2024, the learned Tribunal passed the award in favour of the
    respondent no.1/Lenders and directed the appellant to deposit the
    Termination Payment in the Escrow Account, as under:-

    “308. For the reasons provided above, the Tribunal DECIDES,
    DIRECTS and ORDERS as follows:

    i. Respondent No. 2 is directed to deposit into the Escrow
    Account, by way of Termination Payment, a sum of Rs.
    229.50 crore, along with interest thereon at the rate of 3%
    above the Bank Rate with effect from 16.4.2019 till the date
    of such deposit.

    ii. Respondent No. 2 is directed to pay the Claimant a sum
    of Rs. 91,38,274/- towards costs.

    iii. Respondent No. 2 is directed to pay the Claimant simple
    interest at the rate of 9% per annum on the costs, to be
    calculated from the date of the award till the date of
    realisation.”

    20. The appellant under Section 33 of the Act, 1996, sought
    modification/correction in the Arbitral Award with regard to the non-
    deposit of the arbitral fee by the appellant. The learned Tribunal rejected the
    said application under Section 33 of the Act, on the ground that the same
    was filed after the passage of 30 days from the date of the Award. However,
    the Award offered to refund the excess amount paid by the respondent No. 1
    on the condition that respondent No.1 would not recover the said amount
    from the appellant.

    FACTS IN FAO(OS) (COMM) 152/2025

    21. In terms of the Concession Agreement-II (‘CA-II’), the Scheduled
    Completion Date was 14.05.2013. The Annuity Payment was to start from
    07.07.2013 and end on 07.01.2026 subject to compliance of the terms of the

    Signature Not Verified
    Signed By:PRADEEP FAO OS (COMM) 137/2025 & 152/2025 Page 8 of 61
    SHARMA
    Signing Date:09.07.2026
    20:07:25
    CA. The appellant made certain modifications in the CLA, which were
    incorporated through the Supplementary CLA dated 15.04.2011.

    22. On 06.03.2013, a SA was entered by the appellant and the respondent
    No. 1 and 2 for granting substitution rights to the respondent No. 1 in case of
    occurrence of financial default by the respondent No. 2.

    23. On 17.02.2014, the PCC was granted to the respondent No. 2 and the
    respondent No. 2 was notified of certain Punch-List items which remained
    to be completed by the respondent No. 2. The Punch-List items remain
    unexecuted by the respondent No. 2.

    24. According to the appellant, from 17.02.2014 till 17.08.2017, the
    appellant paid a total of ₹149.415 Crores (paid ₹ 139.294 Crores after
    deduction of ₹ 10.12 crores towards default of the concessionaire to the
    respondent No. 2) in 7 installments. Despite the same, no substantial
    progress of the project was achieved. Details of the Annuity payments
    recommended by the IE were as per Article 27.1.1. and Schedule M of the
    CA-II.

    25. Due to the pace of execution of the works at the Project which
    remained abysmally low and no positive action, the appellant invoked
    Article 37.1.1 of the CA and issued a Cure Period Notice dated 10.08.2015
    and directed the respondent No.2 to immediately cure the defaults as
    enumerated in the said notice within 60 days therefrom, failing which the
    appellant would exercise its rights and remedies under the CA-II.

    Signature Not Verified
    Signed By:PRADEEP FAO OS (COMM) 137/2025 & 152/2025 Page 9 of 61
    SHARMA
    Signing Date:09.07.2026
    20:07:25

    26. The respondent No. 2 was found not performing the work.
    Accordingly, 3rd Supplementary Agreement dated 30.01.2018 was entered.
    The respondent No. 2 failed to complete the Project in its entirety including
    the punch list items.

    27. On 31.03.2018, the respondent No. 1 declared the Project loan
    account as NPA as per RBI guidelines. On 05.10.2018, appellant issued
    ‘Suspension Notice’ under Article 36.1 of the CA. On 26.03.2019
    respondent No. 1 issued a Notice of Financial default dated 26.03.2019 to
    respondent No.2 detailing the events of defaults.

    28. On 01.04.2019, the respondent No. 1 requested the appellant to
    terminate the CA-II on account of “Financial Default” of the respondent
    No.2 under Clause 5.1 of the SA by issuing Termination Notice.

    29. The respondent No. 2 vide its letter dated 29.04.2019 replied to the
    respondent No.l’s Notice of Financial Default and stating that the delays
    were on account of reasons beyond its control. On 31.05.2019, the appellant
    issued Termination Notice terminating the CA-II w.e.f. 03.04.2019 and
    informed respondent No. 2 that it had taken over the Project.

    30. On 16.07.2019, the appellant issued a letter to the respondent No. 2
    informing that, it would appropriate a sum of ₹19,43,569/- from the
    upcoming Annuity Payment on account of maintenance works, etc. being
    carried by it on the Project through another agency. The appellant issued
    another letter dated 17.07.2019 to the respondent No.2 informing it of
    various defects in the Project. It informed that, to cure such defects, the cost

    Signature Not Verified
    Signed By:PRADEEP FAO OS (COMM) 137/2025 & 152/2025 Page 10 of 61
    SHARMA
    Signing Date:09.07.2026
    20:07:25
    has been estimated by the IE as ₹ 13.27 Crores. The respondent No. 2 was
    directed to cure these defects within 15 days.

    31. On 09.08.2019, the appellant issued a letter to the respondent No. 2
    that the IE had identified certain defects and deficiencies in the Project
    Highway. It was further informed that the IE has directed the respondent No.
    2 to deposit a sum of ₹ 328.18 crores against the damages / recoveries and
    also directed the respondent No. 2 to maintain retention money of minimum
    of 5% of the Annuity in the Escrow Account to take care of the defects.

    32. The respondent no.1/Lender filed a petition under Section 9 of the
    Act, being OMP (I) COMM. No. 275 of 2019, seeking directions against the
    appellant to deposit the Termination Payment in the Escrow Account. The
    said petition was disposed of vide an Order dated 22.12.2021 with a
    direction to the respondent no.1 to agitate the same before the Tribunal.

    33. On 03.09.2019, the appellant issued a letter to the respondent No.1
    clarifying the issues with respect to the termination of the CA. As per the
    provisions of the Article 37 of the CA, on account of the occurrence of an
    Event of Financial Default, to release of the Termination Payment
    amounting to ₹ 278,93,30,890/- to the Escrow Account.

    34. On 28.01.2020, the respondent No. 1 issued notice to the appellant &
    respondent No. 2 invoking the arbitration under Clause 10 of the EA and
    Clause 8 of the SA. On 05.02.2020, the respondent No.2 issued notice
    invoking arbitration under Article 44.3 of CA to the appellant.

    Signature Not Verified
    Signed By:PRADEEP FAO OS (COMM) 137/2025 & 152/2025 Page 11 of 61
    SHARMA
    Signing Date:09.07.2026
    20:07:25

    35. On 02.09.2021, the respondent No. 1 preferred an application under
    Section 11 of the Act seeking appointment of 3rd Arbitrator in terms of the
    provisions of the EA/SA, since the respondent No. 2 had not appointed its
    Nominee Arbitrator. This Court vide order dated 22.12.2021 in Arb. (P) No.
    867 of 2021, appointed 3rd arbitrator and referred the disputes to the learned
    Tribunal.

    36. The learned Tribunal framed the issues based on, in the following
    manner: –

    “76. The final issues based on these amended pleadings were
    finalized on 9.8.2023 by the Tribunal, as follows:

    “1. Whether the present arbitral proceedings are liable to
    be terminated on the ground that the claims of the
    Claimant are beyond the scope of Escrow Agreement
    and/or the Substitution Agreement?

    2. Whether the Claimant is entitled to seek Termination
    Payment or 90% Debt Due and interest thereon from the
    Respondent No. 2 having invoked the arbitration under the
    Escrow Agreement and/or the Substitution Agreement?

    3. Whether the issue of “Debt Due” can be termed as a
    “dispute” under the arbitration clause of the Escrow
    Agreement or the Substitution Agreement?

    4. Whether the issue of “Debt Due” was referred to
    arbitration in accordance with notice under Section 21 of
    the Arbitration and Conciliation Act, 1996?

    5. Whether the Claimant is entitled to a declaration that
    “Respondent No. 2 is liable to deposit in the Escrow
    account, the Termination Payment and the Claimant is
    entitled to release thereof in its favour to the extent of 90%
    of Debt Due”?

    6. Whether Respondent No. 2 is liable to deposit a total
    Termination Payment of Rs. 278.93 crore on account of
    termination of the Concession Agreement?

    7. Whether Respondent No. 2 is liable to pay 90% of Debt
    Due of Rs. 193,62,27,188/- or any other amount to the

    Signature Not Verified
    Signed By:PRADEEP FAO OS (COMM) 137/2025 & 152/2025 Page 12 of 61
    SHARMA
    Signing Date:09.07.2026
    20:07:25
    Claimant as damages for non-deposit of Termination
    Payment in the Escrow Account?

    8. Whether the Claimant can claim damages on account of
    default of Respondent if the contract provides for interest?

    9. Whether the Claimant is entitled to a sum of
    Rs.62,44,73,053/- from Respondent No. 2 towards the pre-
    reference interest on 90% Debt Due at the rate of 12%
    p.a. for the period from 16.04.2019 to 22.12.2021 as
    damages for non-deposit of Termination Payment in the
    Escrow Account?

    10. Whether the Claimant is entitled to pendente lite interest
    on 90% Debt Due as damages for non-deposit of
    Termination Payment in the Escrow Account? If so, from
    which date and at what rate?

    11. Whether the Claimant is entitled to future interest? If so,
    at what rate?

    12. Costs?””

    37. It is the case of the appellant that the Tribunal passed Arbitral Award
    on 13.11.2024, in the following manner: –

    “264. The Tribunal answers the issues as follows:

    i. The claims with regard to the Termination Payment are
    not beyond the scope of Escrow Agreement and/or the
    Substitution Agreement but the claims with regard to Debt
    Due are beyond the scope of the present arbitration.
    ii. The Claimant is entitled to seek deposit of the
    Termination Payment with interest thereon by NHAI in
    the Escrow Account. The Claimant is not entitled to its
    claim of 90% Debt Due and interest thereon from the
    Respondent No. 2 being (a) beyond the scope of the present
    arbitration and (b) premature.

    iii. The issue of “Debt Due” can be termed as a “dispute”

    under the arbitration clause of the Escrow Agreement or
    the Substitution Agreement but the same does not arise in
    the present arbitration.

    iv. The issue of “Debt Due” was not referred to arbitration
    in accordance with notice under Section 21 of the
    Arbitration and Conciliation Act, 1996.

    Signature Not Verified
    Signed By:PRADEEP FAO OS (COMM) 137/2025 & 152/2025 Page 13 of 61
    SHARMA
    Signing Date:09.07.2026
    20:07:25

    v. The Claimant is entitled to a declaration that
    “Respondent No. 2 is liable to deposit in the Escrow
    account, the Termination Payment” but the Claimant is
    not entitled in this arbitration to a declaration that it is
    entitled to the release thereof in its favour to the extent of
    90% of Debt Due.

    vi. Respondent No. 2 is liable to deposit in the Escrow
    Account, i.e., Account number 0246073000005524, with
    the Secunderabad branch of SIB, the Termination
    Payment of Rs. 181.81 crore on account of termination of
    the Concession Agreement.

    vii. Respondent No. 2 is not liable to pay 90% of the alleged
    Debt Due of Rs. 193,62,27,188/- or any other amount to
    the Claimant as damages for nondeposit of Termination
    Payment in the Escrow Account.

    viii. The Claimant cannot claim damages on account of
    default of Respondent No. 2 in not depositing the
    Termination Payment. There was no such obligation of
    NHAI towards the Lenders (i.e., the Claimant). The
    obligation was to pay the Concessionaire the Termination
    Payment by depositing the same in the Escrow Account.

    The remedy for delay in making such deposit was
    provided in Article 37.3.3 of the Concession Agreement
    by payment of interest on the Termination Payment at the
    rate of 3% above the Bank Rate into the Escrow Account.
    ix. The Claimant is not entitled to a sum of
    Rs.62,44,73,053/- from Respondent No. 2 towards alleged
    pre-reference interest on the alleged 90% Debt Due at the
    alleged rate of 12% p.a. for the period from 16.04.2019 to
    22.12.2021 as purported damages for non-deposit of
    Termination Payment in the Escrow Account.

    x. The Claimant is not entitled to any pendente lite interest
    as no principal amount is payable to the Claimant.

    xi. Since the deposit of the Termination Payment along with
    interest is to be made by Respondent No. 2 into the
    Escrow Account and the Escrow Bank, under Clause 2.3.2
    of the Escrow Agreement, is mandated to maintain the
    Escrow Account in accordance with the terms of the Escrow
    Agreement and its usual practices and applicable

    Signature Not Verified
    Signed By:PRADEEP FAO OS (COMM) 137/2025 & 152/2025 Page 14 of 61
    SHARMA
    Signing Date:09.07.2026
    20:07:25
    regulations, and pay the maximum rate of interest payable
    to similar customers on the balance in the said account
    from time to time, the Claimant is not entitled to future
    interest.

    xii. The Claimant is entitled to costs. However, as the
    Claimant has only partially succeeded in respect of its
    claims, it would be reasonable to award about half of the
    costs claimed. The Claimant has claimed Rs.

    1,14,71,235/-. Accordingly, the Claimant would be entitled
    to Rs. 57,35,617.50. However, the Claimant was also
    directed to deposit, in terms of the Arbitration and
    Conciliation Act, 1996
    , a sum of Rs. 34,50,000 for all the
    arbitrators, as Respondent No. 2 had failed to deposit its
    full share of fees. Thus, the Claimant is entitled to a
    payment of Rs. 57,35,617.50 plus Rs. 34,50,000, i.e., Rs.
    91,85,617.50 rounded off to Rs. 91,85,618/- towards costs
    from Respondent No. 2. The Claimant is also entitled to
    simple interest at the rate of 9% per annum on the costs, to
    be calculated from the date of the award till realisation.”

    38. On 07.02.2025, the appellant filed a petition under Section 34 of the
    Act challenging the Award passed by the learned Tribunal.

    39. After the impugned judgment, the appellant received a
    communication email dated 16.07.2025 whereby the appellant has been
    informed that Serious Fraud Investigation Office (“SFIO”) is conducting an
    investigation into the affairs of the concessionaire and therefore, sought
    certain information/ documents.

    SUBMISSIONS BEFORE THE LEARNED SINGLE JUDGE: –

    40. The appellant/petitioner alleged that the respondent No. 2 violated the
    terms of the CAs and it issued “Suspension Notice” under Article 36.1 of
    CAs to the respondent No.2. The respondent No.1 also issued a Notice of

    Signature Not Verified
    Signed By:PRADEEP FAO OS (COMM) 137/2025 & 152/2025 Page 15 of 61
    SHARMA
    Signing Date:09.07.2026
    20:07:25
    Financial Default dated 26.03.2019 to the respondent No.2 informing about
    the material breach of the terms of the Common Loan Agreement.

    41. The appellant issued Termination Notice dated 22.05.2019 thereby
    terminating the CA w.e.f. 09.04.2019 and informed the respondent No. 2
    that it had taken over the Project Highway. Consequently, respondent No. 1
    wrote letters to the appellant/petitioner to release the Termination Payment
    amounting to ₹393,49,97,509/-. along with the applicable interest. The
    appellant denied depositing the Termination Payment into the Escrow
    Account vide its letter dated 24.06.2019 and stated that since the
    Commercial Operation Date (“COD”) for the Project could not be achieved
    and the CA was terminated prior to the occurrence of COD, no Termination
    Payment for the Project was payable. In its letter dated 24.06.2019, the
    appellant also stated that the letter dated 17.12.2016 issued by the IE
    keeping the PCC in abeyance had been issued under the instructions of the
    appellant.

    FINDINGS OF THE LEARNED SINGLE JUDGE

    42. The learned Single Judge has noted that the Arbitral Award(s) can
    only be set aside on the ground, inter alia, being in conflict with the public
    policy of India, patent illegality and violation of principles of natural justice.

    43. The findings of the learned Single Judge on different issues are as
    under:-

    a) Concession Agreement form part of the EA and SA :-

    Signature Not Verified
    Signed By:PRADEEP FAO OS (COMM) 137/2025 & 152/2025 Page 16 of 61
    SHARMA
    Signing Date:09.07.2026
    20:07:25

    The EA and SA by clear phraseology incorporate the CA in
    both the EA as well as the SA. The recitals of EA and SA are clear
    and unambiguous, there is no need for any external aid. The CA
    was not merely a reference or a statement in the passing but the
    parties expressly agreed to it forming and becoming a part of the
    two Agreements i.e. EA and SA. The learned Single Judge
    referring to paragraphs 96,126 and 132 of the Arbitral Award held
    that the learned Tribunal has rightly held that the CAs forms part
    of the EA and SA and the conclusion of the learned Tribunal calls
    for no interference.

    b) PCC cannot be kept in abeyance :-

    Keeping the PCC in abeyance by the IE vide letter dated
    17.12.2016, was beyond the terms of the said Article i.e. 14.5 of
    CAs. The CA nowhere provides that the PCC once issued can be
    kept in abeyance or withdrawn. The interpretation that IE after
    realizing its mistake, kept the PCC in abeyance as 75% of the total
    length of the Project Highway was not completed, is against the
    Article quoted above which gives IE the only right to withhold the
    PCC before it is issued but not once the PCC is issued. The PCC
    was issued after inspection by the IE and approval by the
    appellant/petitioner. If the interpretation propounded by the
    appellant/petitioner is accepted then said Article will lead to
    absurdity. The view taken by the Tribunal is the correct view and
    most definitely is a plausible view and does not shake the
    conscience of the Court.

    Signature Not Verified
    Signed By:PRADEEP FAO OS (COMM) 137/2025 & 152/2025 Page 17 of 61
    SHARMA
    Signing Date:09.07.2026
    20:07:25

    c) Jurisdiction of the AT over the disputes :-

    The respondent No. 1 invoked the Arbitration Clause of the
    EA which is Clause 10. On perusal of the same, it clearly indicates
    that “any dispute, difference or claim arising out of or in
    connection with this Agreement” shall be referred to arbitration. It
    includes the disputes arising in connection with the EA which also
    includes the CA.

    It is the case of the respondent No.1 that the appellant/
    petitioner refused to deposit the Termination Payment vide letter
    dated 24.06.2019 which clearly violated Clause 3.2 of the EA.
    Hence, the respondent No. 1 was constrained to invoke the
    arbitration clause of the EA. The learned Tribunal had the
    jurisdiction to entertain the disputes arising out of the EA and
    more particularly non deposit of Termination Payment by the
    petitioner in the Escrow Account. The learned Single Judge held
    that the above reasoning is sound, borne out of the correct
    interpretation of the contractual terms and there is no merit in the
    contention of the appellant/petitioner that the learned Tribunal
    lacked jurisdiction over the dispute of non deposit of Termination
    Payment in the Escrow Account.

    d) Contentions qua Termination Payment :-

    The learned Single Judge has held that the respondent No. 2
    under the CAs has been described as “concessionaire” which
    includes its successors and permitted assigns and substitutes. It is

    Signature Not Verified
    Signed By:PRADEEP FAO OS (COMM) 137/2025 & 152/2025 Page 18 of 61
    SHARMA
    Signing Date:09.07.2026
    20:07:25
    clear that there is a conscious and deliberate intent on the part of
    the contracting parties to transfer and assign all rights, title, and
    interest held by the concessionaire to the Lenders Representative
    i.e. the respondent No. 1. After the execution of the SA, the
    respondent No. 1/ lender steps into the shoes of the
    concessionaire, acting in the capacity of the respondent No. 2 and
    is entitled to make such demands. The argument that the
    concessionaire can only demand the Termination Payment
    completely ignores the plain language and “commercial purpose”
    of the Agreements. This interpretation would disregard the intent
    of the parties, who clearly intended that the lender, upon
    substitution, would possess all the rights necessary to recover its
    dues including the Termination Payment. The Termination
    Payment can only be sought by respondent No. 2, is rejected.

    If the CA is terminated due to the defaults committed by the
    respondent No. 2 before achieving COD, the Termination
    Payment shall not be due and payable. Article 37.3.1 states that, if
    the Agreement is terminated on account of the concessionaire
    default during the operation period then the Authority i.e. the
    appellant/petitioner would pay as per the Article quoted above.
    Articles 37.3.2 and 37.3.3 state the formula to be applied for
    Termination Payment along with the interest component.

    Once the COD is achieved on the date of issuance of PCC,
    the demand made by the respondent No. 1 for Termination
    Payment was valid. The calculation of the Termination Payment is

    Signature Not Verified
    Signed By:PRADEEP FAO OS (COMM) 137/2025 & 152/2025 Page 19 of 61
    SHARMA
    Signing Date:09.07.2026
    20:07:25
    a question of fact not a question of jurisdiction. The answer to the
    said contention i.e. calculation of Termination Payment, clearly
    lies in Article 37 of the CA and more particularly in Article 37.3.2
    and 37.3.3.

    The learned Single Judge held that the appellant has not
    argued that the amount of ₹ 229.50 Crore suffer from any errors or
    that extra amounts have been added instead of this, only a mere
    averment has been made without any evidence. On perusing the
    Statement of Defence filed by the petitioner, the calculation of
    Termination Payment has not been disputed. The Tribunal has
    dealt with the said contention in paragraph 157 of the Arbitral
    Award. Therefore, the Tribunal has rightly dealt with the said
    contention and hence, no interference is required.

    44. The learned Single Judge in view of its above findings has held that
    no interference is required with the Arbitral Awards and dismissed the
    petitions.

    SUBMISSIONS ON BEHALF OF THE APPELLANT:-

    45. Mr. Sudhir Nandrajog, learned Senior Counsel appearing for the
    appellant submitted that the CAs are not a part of the EA or the SA. The
    conclusion drawn by the learned Tribunal that CAs formed part of
    agreements is erroneous; it was merely annexed to EA and SA as annexures.
    The terms of the CAs were never made “part and parcel” of these
    agreements. He also submitted that the learned Single Judge failed to

    Signature Not Verified
    Signed By:PRADEEP FAO OS (COMM) 137/2025 & 152/2025 Page 20 of 61
    SHARMA
    Signing Date:09.07.2026
    20:07:25
    consider that the learned Tribunal has erred by substituting the agreements
    in its own wisdom, which is impermissible in law.

    46. According to him, intention of annexing the CAs in the agreements
    can be deduced from Clauses 2 & 3 in the SA and Clauses 2.5 & 2.6 of the
    EA. He submitted that CAs were annexed to the agreements so that the non-
    signatory to CAs, i.e., the respondent no. 1 is aware of the terms of the CAs
    to enable the respondent no. 1/lender to exercise its rights under Clauses 2 &
    3 in the SA and Clauses 2.5 & 2.6 of the EA.

    47. He submitted that the appellant could not have been directed to
    deposit Termination Payment in accordance with Clause 3.2 of the EA, as
    the same never became “due and payable”. For Termination Payment to
    become due and payable, the concessionaire as well as the learned Tribunal
    was obligated to follow the procedure prescribed under Article 37.3 of the
    CAs. The mere factum of the recital annexing the CAs to EA(s) and SA(s)
    does not make the CA ‘part and parcel’ of the said agreements in the
    absence of a clear or specific indication that the CAs in its entirety was
    intended to be made part of the EA(s) and SA(s). In support of his
    submission, he has relied on the judgment of the Supreme Court in M.R.
    Engineers & Contractors (P) Limited v. Som Datt Builders Limited
    (2009)
    7 SCC 696.

    48. According to Mr. Nandrajog, the award is patently illegal as the
    Termination Payment under the CAs is not payable if termination happens
    due to concessionaire’s default occurring prior to COD under Article 37.3.1

    Signature Not Verified
    Signed By:PRADEEP FAO OS (COMM) 137/2025 & 152/2025 Page 21 of 61
    SHARMA
    Signing Date:09.07.2026
    20:07:25
    of the CAs. The COD is achieved upon issuance of Completion Certificate /
    PCC which is issued by IE.

    49. He submitted that the CODs were not achieved as the PCC which was
    issued by IE was kept in abeyance, as 75% of the total length of the Project
    was not completed by the respondent No.2/concessionaire. In terms of
    Article 14.3.2 of CA, PCC could have only been issued upon completion of
    75% of the total length of the Project, i.e., 100.350 KM out of the total
    length of 133.793 Km. The respondent No.2 had only completed 90.671
    Km. Therefore, issuance of PCC/achieving COD, raising a demand by the
    concessionaire/ respondent No. 2 for the Termination Payment, and
    providing necessary particulars, all were a sine qua non to the claim of
    Termination Payment. He also submitted that the same was submitted by the
    appellant in its Statement of Defence which was not decided by the learned
    Tribunal on its merits in the Award and came to a conclusion that, act of
    keeping the PCC in abeyance could not have been done without considering
    Article 14.5 of the CA-I.

    50. It is his submission that the learned Single Judge has failed to
    consider that the learned Tribunal has failed to note that, even if the
    appellant is obliged to pay the Termination Payment, it shall be upon the
    demand of the respondent no.2/concessionaire within 15 days of the
    termination, which was admittedly never did by the respondent No.2. He
    also submitted that the learned Tribunal erred in interpreting Article 37.3.3
    of the CAs and held that there is no requirement for the concessionaire to
    demand Termination Payment from the Authority/appellant. The learned
    Tribunal has given complete go-by to the categorical and unambiguous

    Signature Not Verified
    Signed By:PRADEEP FAO OS (COMM) 137/2025 & 152/2025 Page 22 of 61
    SHARMA
    Signing Date:09.07.2026
    20:07:25
    provisions of Article 37.3.3 which mandates “demand” by the
    concessionaire with “necessary particulars”. Such an interpretation to Article
    37.3.3 of CAs has the effect of altering the binding terms of the contract
    between the parties, which is impermissible in law and is patently illegal.

    51. According to him, it is settled proposition of law that, only parties to a
    contract can enforce their rights and liabilities under such contract and no
    stranger is allowed/ permitted to agitate claim(s) or seek to enforce terms of
    such contract against the parties to such contract. The respondent no. 1 is
    precluded in law from seeking enforcement of terms of CAs to which it is
    not a party to. An arbitrator/Tribunal being a creature of a contract, cannot
    step out of the four corners of the contract. Hence, the Tribunal erred in
    travelling beyond SA and EA to adjudicate disputes which could only be
    agitated and adjudicated by a competent Arbitral tribunal constituted under
    the arbitration Article contained in CAs. The findings of the learned
    Tribunal that Clause 10 of EA & Clause 8 of SA are widely worded and
    indicate that, it would include disputes “arising out of or in connection with”

    including those under the Cas, is erroneous. He submitted that the CAs were
    beyond the scope of reference and the respondent no. 1 not being a party to
    the CAs, could not have sought to enforce the terms.

    52. He submitted that the learned Tribunal erred in relying upon Clause 2
    of the SA, that, once the assignment takes place SIB/Lender steps into the
    shoe of respondent no.2/concessionaire. It is his submission that the Clause
    2 is subject to Clause 3.1 of the SA. The ‘substitution/assignment’ rights of
    the respondent no. 1 are only restricted to appointment of a ‘Nominated
    Company’ to perform the obligations under the CAs. Whereas, Clause 2.1

    Signature Not Verified
    Signed By:PRADEEP FAO OS (COMM) 137/2025 & 152/2025 Page 23 of 61
    SHARMA
    Signing Date:09.07.2026
    20:07:25
    nowhere reads that the Lender would step into the shoe of the respondent
    no.2/concessionaire and shall be entitled to all rights under the CAs. If the
    same analogy is followed, then for the claims of the appellant against the
    concessionaire, the appellant can agitate and raise claims against the
    respondent No.1/Lender for the wrongs/defaults of the concessionaire/
    respondent no.2. He also submitted that Clause 5.1 of the SA nowhere
    assigns any right to respondent No. 1 to call upon the appellant to deposit
    the Termination Payments, which have not become due and payable and is
    subject to Article 37.3.3 of CAs.

    53. According to him, the learned Tribunal erred in holding that
    calculation of Termination Payment was a “mechanical exercise” whereas
    there are two preconditions for the Termination Payments to become “due
    and payable; Firstly, there must be demand by the respondent No. 2;
    Secondly, the respondent No. 2 must submit necessary particulars. Both the
    preconditions were missing and without complying with the preconditions
    under Article 37.3.3 of the CAs.

    54. On the issue of calculation /computation of the Termination Payment,
    he submitted that the learned Tribunal could not have arrived at the figure of
    ₹ 229.50 Crore in CA-I and ₹ 181.81 Crore in CA-II, as the Termination
    Payment is beyond the scope of reference. There is no provision in the EA
    and SA which enables the learned Tribunal or the parties to these
    agreements to calculate Termination Payment. The Termination Payment
    can only be adjudicated and calculated arising out of the CAs, which are
    subject matter of arbitral proceedings between the respondent No.2 and the
    appellant. He also submitted that, it is perverse finding of the learned

    Signature Not Verified
    Signed By:PRADEEP FAO OS (COMM) 137/2025 & 152/2025 Page 24 of 61
    SHARMA
    Signing Date:09.07.2026
    20:07:25
    Tribunal that the appellant did not dispute the calculation made by the
    respondent No.1.

    55. In support of his submissions, he has relied upon the following
    judgments: –

    a) Associated Engineering Co. v. Government of A.P., 1991 4
    SCC 93.

    b) Rajasthan State Mine and Minerals Ltd. v. Eastern
    Engineering Enterprises
    , 1999 9 SCC 283.

    c) Food Corporation of India v. Chandu Construction, 2007 4
    SCC 697.

    d) Indian Oil Corporation Limited v. Shree Ganesh Petroleum
    Rajgurunagar
    , 2022 4 SCC 463.

    56. He submitted that the appellant approached the learned Tribunal
    under Section 33 of the Act seeking modification/correction in the Arbitral
    Award dated 13.11.2024 on the issue with regards to the ‘non-deposit of the
    Arbitral Fee’ by the appellant. The appellant had pointed out to learned
    Tribunal that it had paid full share of its Arbitral Fee to respondent no. 1. A
    sum of Rs. 34.50 Lakhs towards the Arbitral Fee which was incorrectly
    noted to have not been paid by the appellant, the Tribunal offered to refund
    the excess amount paid by the respondent no. 1 on the condition that
    respondent no. 1 would not recover the said amount from the appellant.

    57. Mr. Nandrajog submitted that the appellant has the authority to
    withhold PCC under the CAs and the learned Tribunal erred in holding that
    the act of the IE in keeping the PCC dated 08.12.2016 in abeyance was non-
    est, void ab-initio and beyond the scope and powers of the IE under Article
    14.5
    of CAs. He also submitted that the IE was well within its power to

    Signature Not Verified
    Signed By:PRADEEP FAO OS (COMM) 137/2025 & 152/2025 Page 25 of 61
    SHARMA
    Signing Date:09.07.2026
    20:07:25
    correct its own error / mistake. When a party has an administrative duty to
    act and in exercise of such duty it commits an error, the same authority is
    duty bound and obligated to correct it as soon as it is brought to its
    knowledge and the IE rightly corrected its mistake by keeping the PCC in
    abeyance vide its letter dated 17.12.2016 until 75% of the total length of the
    Project Highway was completed. The learned Tribunal failed to consider
    that, in terms of Article 14.3.2 of the CAs, PCC can only be issued upon the
    completion of 75% of the total length of the Project Highway. Thus the
    learned Tribunal erred by overruling the contractual obligation of the IE.

    58. He submitted that, as per Article 37.3.1 of CA, the concessionaire
    acknowledges that no Termination Payment shall be due or payable on
    account of a concessionaire Default occurring prior to COD. The issue of
    withholding PCC is sub judice before a Tribunal wherein the appellant and
    respondent No. 2 (concessionaire) are parties.

    59. In support of his submission he has relied on the following
    judgments:-

    a) Visa International Ltd. v. Continental Resources (USA) Ltd.,
    (2009) 2 SCC 55;

    b) Nandram Hanutram v. Raghunath and Sons, 1953 SCC
    OnLine Cal 219;

    c) Transstroy Tirupati Tiruthani Chennai Tollways Pvt. Ltd. v.

    Allahabad Bank and Anr., 2019 SCC OnLine Del 9080.

    60. He seeks prayer as made in the appeal.

    SUBMISSION ON BEHALF OF THE RESPONDENT NO.1

    Signature Not Verified
    Signed By:PRADEEP FAO OS (COMM) 137/2025 & 152/2025 Page 26 of 61
    SHARMA
    Signing Date:09.07.2026
    20:07:25

    61. Mr. Sandeep Sethi, learned Senior Counsel appearing for the
    respondent no.1 would submit that the only issue in FAO (OS) (COMM)
    137/2025 is with regard to PCC which was kept in abeyance. No such issue
    arises in FAO (OS) (COMM) 152/2025 regarding the achievement of
    Commercial Operation Date (COD).

    62. On the submission of the appellant that the liability to make
    Termination Payment is exclusively under CAs, to which the
    lender/respondent no.1 is not a party, he submitted that, under Clause 3.2 of
    the EA, it is the obligation of the appellant to deposit the Termination
    Payment when it becomes due and payable as the CAs forms part of EA and
    SA. The dispute that was referred to arbitration arose from the appellant’s
    failure to perform its obligation to deposit Termination Payment in the
    Escrow Account under the EA and the SA, both of which are tripartite
    agreements.

    63. He submitted that, under the CAs, the Projects were awarded as a
    DBFOT on an annuity basis, the appellant did not make any investment in
    the Projects. The funds were independently sourced by the concessionaire
    through equity contribution and/or by taking loan(s), and the Lender Banks
    invested huge amounts to bring the Project to life. The Awards record this
    commercial backdrop. Upon termination, the contractual mechanism is not
    that the appellant unilaterally adjusts the amounts claimed by it from the
    concessionaire from the Termination Payment. Rather, the parties had
    agreed on a structured escrow waterfall.

    64. Clause 4.2 of the EA read with Article 31.4.1 of the CA, stipulates the

    Signature Not Verified
    Signed By:PRADEEP FAO OS (COMM) 137/2025 & 152/2025 Page 27 of 61
    SHARMA
    Signing Date:09.07.2026
    20:07:25
    priority in which monies to be credited to the Escrow Account are to be
    applied upon termination. These clauses make it clear that payment of 90%
    of the Debt Due excluding Subordinated Debt is the highest priority after
    payment of taxes due and payable by the concessionaire. All payments and
    damages claimed by the appellant from the concessionaire are to be paid
    only after the payment of taxes and 90% of Debt Due. If the appellant had
    deposited Termination Payment in the Escrow Account, respondent No.1
    could have appropriated an amount of at least up to 90% of the Debt Due
    from the said account in terms of Clause 4.2 of the EA.

    65. According to Mr. Sethi, the Clause 3.2 of the EA read with Article
    37.3
    of the CA, no discretion is granted to appellant in making the
    Termination Payment. It is his submission that CA forms part of the EA and
    SA, as both are tripartite agreement executed by the lender/respondent no.1
    and as well as Escrow Bank, respondent no.2/the concessionaire and the
    appellant. Both the agreements are identically worded and inter alia states
    that, a copy of the CAs are annexed hereto and marked as ‘Annex-A to form
    part of this agreement’ and therefore the CAs forms part of both agreements
    by express incorporation.

    66. On the judgment relied upon by the appellant in M. R. Engineers and
    Contractors (P) Ltd.
    (supra), he submitted that, it is not the case that a
    document is merely referred in the contract, the arbitration clause was
    invoked under Clause 10.1 of the EA, the relevance of the Recital A is that,
    it incorporates the CA(s) into EA(s) & SA(s) as part of contractual
    framework.

    Signature Not Verified
    Signed By:PRADEEP FAO OS (COMM) 137/2025 & 152/2025 Page 28 of 61
    SHARMA
    Signing Date:09.07.2026
    20:07:25

    67. On the appellant’s plea that the learned Tribunal had decided the
    matter beyond its scope of reference, Mr. Sethi placing reliance upon the
    judgment in the case of State of Goa v. Parveen Enterprises (2012) 12 SCC
    581 and Ssangyong Engineering and Construction Company Limited v.
    National Highway Authority of India
    (2019) 15 SCC 131, submitted that
    the dispute referred to the learned Tribunal was due to the refusal of the
    appellant to deposit the Termination Payment in the Escrow Account.

    68. On the issue of whether the lender can invoke arbitration under EA
    and SA and to deposit the Termination Payment in Escrow Account upon
    termination, Mr. Sethi has relied upon the judgment of this Court in the case
    of National Highways Authority of India v. Punjab National Bank (2021)
    SCC OnLine Del 3413 to submit that learned Single Judge of this Court has
    held that once the CAs stood terminated, the loaned amount is required to be
    returned. The lenders, had no concern with the inter se disputes between
    parties therein (NHAI and JST). It is for this reason that the CA, rightly,
    made deposit by NHAI, into the Escrow Account, as well as the withdrawal,
    thereby, by the lenders, the inevitable sequitur to termination of the CA,
    which has been upheld by a Coordinate Bench of this Court vide the above
    judgment. The SLP filed was also dismissed.

    69. On the issue of Termination Payment, had become ‘due and payable’,
    Mr. Sethi submitted that under the security assignment under Clause 2.1 of
    the SA, the concessionaire/respondent no.2 had assigned all its rights title,
    and interest in the concession to the lenders’ representative by way of
    security. According to him, the lenders assignee is entitled to enforce the
    relevant Termination Payment mechanism for the purpose of ensuring that

    Signature Not Verified
    Signed By:PRADEEP FAO OS (COMM) 137/2025 & 152/2025 Page 29 of 61
    SHARMA
    Signing Date:09.07.2026
    20:07:25
    the Termination Payment is demanded/deposited in accordance with the
    contractual scheme.

    70. On the argument of the appellant that, Lenders cannot demand
    Termination Payment because they could not execute the project is
    misconceived because the said clause merely clarifies that the lenders cannot
    themselves execute the project work. He submitted that, it neither dilute the
    lenders security assignment nor does it curtail their contractual right to seek
    deposit of Termination Payment into Escrow Account upon termination.
    According to him, the respondent No.1 is only seeking to enforce the escrow
    deposit mechanism triggered by the termination.

    71. Mr. Sethi, on the submission of the appellant that, if the lenders are
    treated as concessionaires then the concessionaires would go out of the
    picture and claims between the appellant and the concessionaire would be
    derailed. He submitted that the Clause 2.1 of the SA is a security interest
    meant to be exercised to the extent necessary to protect the lenders exposure
    upon the defined events. The respondent no.1’s case is limited to deposit of
    Termination Payment into the Escrow Account and does not see the
    adjudication of inter se disputes between the appellant and the
    concessionaire/respondent no.2 under the CAs does not seek to supplant the
    concessionaire in the arbitration. The respondent no.1 invoked the
    arbitration only because of the appellant refusal / failure to deposit the
    Termination Payment.

    72. He submitted that Clause 7.2(v) of the CLA provides that, in the
    event of default by the concessionaire under Clause 7.1 of the CLA, the

    Signature Not Verified
    Signed By:PRADEEP FAO OS (COMM) 137/2025 & 152/2025 Page 30 of 61
    SHARMA
    Signing Date:09.07.2026
    20:07:25
    lender / respondent no.1 can instruct any person who is liable to make the
    payment to the borrower to pay directly to the secured parties for the
    purpose of crediting the same into Escrow Account.

    73. According to him, the learned Tribunal has held that the Clause 5.2.2
    of the CA requires concessionaire to submit drafts of all Project agreements
    for its review and comments. CLA is a “Financing Agreement” and forms
    part of the definition of “Project Agreements” under Article 48.1 of the CAs.
    He also submitted that, the Recitals C and D to the Supplementary CLA
    dated 15.04.2011 records that the appellant had reviewed the CLA and had
    stipulated certain modifications / deletions / insertions to the same on
    account of which the SA was executed. As evident from the said SA, no
    modifications were suggested by appellant to Clauses 7.2(v) and 10.2 B (ii)
    of the CLA. Thus, the appellant had acquiesced to the said Clause 10.2 B (ii)
    which recognises that the lenders can claim Termination Payment from the
    appellant. Thus, the learned Tribunal has rightly held that the appellant had
    acquiesced to the provisions of the CLA which provide that the lenders can
    claim Termination Payment.

    74. With regard to the appellant’s submission of ‘necessary particulars’,
    Mr. Sethi submitted that this argument was not raised as a defence during
    the arbitration and it was first raised in the petition under Section 34 of the
    Act. The appellant has neither specified what “necessary particulars” were
    allegedly missing, nor does it plead or demonstrate how any absence of
    particulars caused prejudice or prevented computation/verification of the
    Termination Payment.

    Signature Not Verified
    Signed By:PRADEEP FAO OS (COMM) 137/2025 & 152/2025 Page 31 of 61
    SHARMA
    Signing Date:09.07.2026
    20:07:25

    75. On the issue of the concessionaire / respondent No. 2 raising /
    demanding Termination Payment, he submitted that the appellant has in its
    application under Section 16 of the Act stated that the concessionaire has
    invoked arbitration under the CAs; the concessionaire had raised claims
    similar to those raised by Lenders/SIB. Thus, there was clearly a demand for
    Termination Payment by the concessionaire as well.

    76. He submitted that, as per Clauses 2.1.1 and 2.1.2 of the EA, the
    Escrow Account is a trust and declares respondent No.1, respondent
    No.2/concessionaire and the appellant as the beneficiaries of the said trust.
    Therefore, the appellant is required to deposit Termination Payment in the
    Escrow Account as beneficiaries of the trust under the EA and/or as
    beneficiaries under Article 31.4.1 of the CAs. He also submitted that the
    appellant had admitted its liability to make Termination Payment to lender
    banks in such projects in a draft shelf prospectus issued by it on 07.10.2015.

    77. On the appellant’s argument that the PCC could not have been issued
    because at least 75% of the Project Highway was not completed and that the
    issuance of the PCC was therefore a patent mistake, rectified by keeping the
    PCC in abeyance, Mr. Sethi submitted that, no such contention was taken in
    the arbitration proceedings, and the same is an attempt to reargue merits
    under Section 37 of the Act. The PCC was issued by the IE under the
    authorisation of the appellant and strictly as per the contractual provisions as
    well as the circulars issued by the appellant.

    78. As per Article 10.3.5 of the CA, the issuance of the PCC shall not be
    delayed due to access not being granted to any part of the site. As per Article

    Signature Not Verified
    Signed By:PRADEEP FAO OS (COMM) 137/2025 & 152/2025 Page 32 of 61
    SHARMA
    Signing Date:09.07.2026
    20:07:25
    14.3.1 of the CA, the IE shall not withhold the PCC for the reason of any
    work remaining incomplete if the delay in completion thereof is attributable
    to appellant. He submitted that the learned Single Judge held that, it was the
    sole responsibility of the appellant to provide access to vacant land as per
    the Appendix to the respondent No. 2/ concessionaire within the 90 days
    period from the Appointed Date and if there was any delay in providing the
    same, it was to attract damages payable to the respondent No.2 by the
    appellant.

    79. He submitted that, the IE issued a recommendation for issuance of
    PCC on 07.11.2014 highlighting that, since the project began, there were
    problems in handing over ‘Right of Way’ and ‘Right to Access’ and NHAI
    Circular No. NHAI/CMC/2010/Misc./13873 dated 07.09.2010 permits
    issuance of PCC for completed stretches in such situations. The appellant
    issued a cure period notice dated 10.06.2015. After an additional portion of
    the works was completed, the IE expressed its intention to issue a PCC for
    the completed stretches vide its letter dated 30.09.2016. The appellant
    explicitly and clearly concurred with this recommendation in its letter dated
    24.10.2016, wherein, it had inspected the completed length of the Project
    Highway along with the IE and found it to be safe and reliable for
    commercial operation and conveyed its authorisation for the issuance of the
    PCC to the IE. The IE issued the PCC through its letter dated 08.12.2016
    while requiring the concessionaire to execute a SA before 25.12.2016 and
    completing the balance works by 31.10.2017.

    80. He submitted that, nine days after the issuance of the PCC, the IE
    suddenly issued a letter dated 17.12.2016 stating that the PCC is kept in

    Signature Not Verified
    Signed By:PRADEEP FAO OS (COMM) 137/2025 & 152/2025 Page 33 of 61
    SHARMA
    Signing Date:09.07.2026
    20:07:25
    abeyance. The learned Single Judge has held that the CAs nowhere provides
    that the PCC once issued can be kept in abeyance or withdrawn. The
    submission that, IE after realising its mistake, kept the PCC in abeyance, as
    75% of the total length of the Project Highway was not completed is against
    the Article, which gives IE the only right to withhold the PCC ‘before’ it is
    issued but not once the PCC is issued. The PCC was issued after inspection
    by the IE and approval by the appellant.

    81. He submitted that the learned Tribunal has held that, keeping the PCC
    in abeyance, was completely different from the letter dated 08.12.2016 in
    which it was stated that the concessionaire should complete either
    Periyakulam Bypass or Theni bypass before the first Annuity payment
    becomes due. The first annuity payment would have become due in terms of
    the said letter of the Engineer on 08.05.2017 (i.e. 6 months after the issuance
    of the PCC). He also submitted that the learned Tribunal has rightly held
    that, under Article 14.5 of the CAs relates to withholding of PCC but does
    not apply once the PCC has been issued. A series of conditions had to be
    met for the applicability of Article 14.5 which had not been met in the
    present case. He also submitted that the learned Tribunal has not altered any
    of the terms of the agreements entered into between the parties, as contended
    by the appellant.

    82. He submitted that the contention of the appellant that Debt Due are
    beyond the scope, and it was not referred in the notice under Section 21 of
    the Act and damages could not be claimed directly by the lenders are
    procedurally untenable, having neither been specifically pleaded in the
    petition under Section 34 of the Act nor raised as a ground in the present

    Signature Not Verified
    Signed By:PRADEEP FAO OS (COMM) 137/2025 & 152/2025 Page 34 of 61
    SHARMA
    Signing Date:09.07.2026
    20:07:25
    appeals. It was raised for the first time in oral arguments without pleadings
    or factual foundation, ought to be rejected.

    83. He submitted that the Original Statement of Claim filed by respondent
    no.1 was limited to a prayer for specific performance of appellants
    contractual obligation to deposit the Termination Payment into the Escrow
    Account together with interest. Subsequently, by way of an amendment,
    respondent no.1 sought an alternative relief, namely damages quantified at
    90% of the Debt Due, along with interest claimed as damages for delay in
    deposit. Since the concerned projects are annuity projects, the Termination
    Payment is the discounted value of future annuities, not 90% Debt Due. This
    alternative claim and it quantification at 90% Debt Due was premised on the
    escrow waterfall under Clause 4.2 of the EA, which accords priority to 90%
    Debt Due after taxes. It was expressly pleaded as an alternative to, and not
    in substitution of, the primary relief of escrow deposit.

    84. He submitted that the learned Tribunal held that NHAI’s contractual
    obligation was not to pay damages or interest directly to the lenders, but to
    deposit the Termination Payment into the Escrow Account; and that the
    contractual consequence for delay in such deposit was expressly provided
    under Article 37.3.3 of the CAs. The learned Tribunal declined the
    alternative reliefs sought by the Lenders’ (direct payment of damages and
    interest), but simultaneously enforced the primary contractual obligation by
    directing the appellant to deposit the Termination Payment along with
    interest into the Escrow Account. The relief granted by the learned Tribunal
    is limited to a direction to deposit the Termination Payment (with interest)
    into the Escrow Account. There is no direction to discharge the lenders’

    Signature Not Verified
    Signed By:PRADEEP FAO OS (COMM) 137/2025 & 152/2025 Page 35 of 61
    SHARMA
    Signing Date:09.07.2026
    20:07:25
    outstanding debt or to make any payment directly to the lenders.

    85. On the submission of the appellant that the expression “due and
    payable” in Article 37.3.3 of the CAs permits the appellant to affect a
    unilateral set-off of its alleged claims against the Termination Payment, Mr.
    Sethi submitted that, Article 37.3.3 stipulates that the Termination Payment
    becomes due and payable upon a demand made after termination. The
    provision does not make the obligation to deposit the Termination Payment
    contingent upon: (i) adjudication or resolution of inter se disputes between
    appellant and the concessionaire, or (ii) adjustment of NHAI’s alleged
    claims against the concessionaire. The contractual scheme clearly separates
    appellant’s obligation to deposit the Termination Payment into escrow from
    its claims against the concessionaire, which are required to be pursued
    independently.

    86. He submitted that the contractual structure precludes any unilateral
    pre-deposit set-off against the Termination Payment. The claims against the
    concessionaire are not extinguished, but they are deliberately subordinated
    in the agreed priority mechanism.

    87. He submitted that the argument of the appellant that, Clause 3.2 of the
    EA entitles the appellant to appropriate Concession Fee due and payable
    from the concessionaire from the Termination Payment which means that
    there has to be an adjustment from the Termination Payment, is
    misconceived. The Concession Fee is only a nominal amount of Re. 1 per
    year during the term of the CAs. It has not been pleaded by the appellant in
    the arbitration, Section 34 petition or in the appeal that any Concession Fee

    Signature Not Verified
    Signed By:PRADEEP FAO OS (COMM) 137/2025 & 152/2025 Page 36 of 61
    SHARMA
    Signing Date:09.07.2026
    20:07:25
    is outstanding to be paid by the concessionaire which should have been
    adjusted from the Termination Payment directed to be deposited by the
    appellant in the Escrow Account in terms of the Award. Therefore, the
    appellant is not entitled to raise any such argument.

    88. Mr. Sethi submitted that the learned Tribunal had made it clear that it
    did not enter into any impermissible adjudication on jurisdictional facts, but
    merely noted that the quantification was never disputed, no alternative
    computation was provided by the appellant, and that the issue was one of
    merit, not jurisdiction. Once it is accepted that the CAs forms part of the
    EAs and SAs, the application of the pre-agreed contractual formula under
    Article 37 of the CA for computing the Termination Payment cannot be
    characterised as a jurisdictional overreach. It is, an exercise in arithmetical
    application of contractual terms, which falls squarely within the learned
    Tribunal’s remit. As recorded both in the Awards and the impugned
    judgment, the appellant has neither disputed the computation or quantum of
    the Termination Payment before the learned Tribunal nor was any
    alternative calculation placed on record. The computation of Termination
    Payment for concessionaire’s default under Article 37.3.1 of the CAs is
    based on an objective and mechanical formula.

    89. He submitted that, it is well settled that interpretation of contractual
    provisions lies squarely within the domain of the learned Tribunal, and so
    long as the interpretation adopted is a possible and plausible view, it is
    immune from interference under Sections 34 and 37 of the Act. It is well
    settled that errors of fact or even of law committed by an Arbitral Tribunal
    are not grounds for setting aside an award unless they fall within the narrow

    Signature Not Verified
    Signed By:PRADEEP FAO OS (COMM) 137/2025 & 152/2025 Page 37 of 61
    SHARMA
    Signing Date:09.07.2026
    20:07:25
    compass of Section 34(2) or Section 34(2A) of the Act.

    90. Mr. Sethi submitted that, an appeal under Section 37 of the Act is
    extremely narrow and far more circumscribed than the already limited scope
    of interference under Section 34 of the Act. The appellate court does not sit
    in appeal over the arbitral award, nor does it undertake a re-appreciation of
    facts or a re-interpretation of contractual provisions. In support of his
    submission, he has relied upon the judgment of the Supreme Court in Jan
    De Nul Dredging India Pvt. Ltd. v. Tuticorin Port Trust
    , 2026 SCC
    OnLine SCC33,

    91. He seeks dismissal of these appeals.

    ANALYSIS AND CONCLUSION

    92. Having heard the learned counsel for the parties and perused the
    record, the first and the foremost issue that needs to be decided is whether
    the CA(s) formed part of the EA(s) & the SA(s).

    93. According to Mr. Nandrajog, the CA(s) was only annexed to the
    EA(s) and SA(s) and as such the learned Tribunal could not have directed
    the appellant to deposit the Termination Payment in the Escrow Account. He
    submitted that, according to the learned Single Judge, the phraseology used
    in EA(s) and SA(s) is very clear in as much as the CA(s) is annexed and
    marked as Annex-A to form part of the agreement(s) i.e., EA and SA, is
    erroneous.

    94. He submitted that the CA(s) was annexed to the agreements so that
    the non-signatory to the CA(s) is aware of the terms of the CA(s) so as to

    Signature Not Verified
    Signed By:PRADEEP FAO OS (COMM) 137/2025 & 152/2025 Page 38 of 61
    SHARMA
    Signing Date:09.07.2026
    20:07:25
    enable the respondent no.1 exercise its rights. To support his submission,
    Mr. Nandrajog has placed reliance on Articles 2 and 3 of the SA and
    Articles 2.5 & 2.6 of the EA, which we reproduce as under:

    “2 ASSIGNMENT
    2.1 Assignment of rights and title
    The Concessionaire hereby assigns the rights, title and interest
    in the Concession to, and in favour of, the Lenders’
    Representative pursuant to and in accordance with the
    provisions of this Agreement and the Concession Agreement by
    way of security in respect of financing by the Senior Lenders
    under the Financing Agreements.

    3 SUBSTITUTION OF THE CONCESSIONAIRE
    3.1 Rights of substitution
    3.1.1 Pursuant to the rights, title and interest assigned under
    Clause 2.1, the Lenders’ Representative shall be entitled to
    substitute the Concessionaire by a Nominated Company under
    and in accordance with the provisions of this Agreement and
    the Concession Agreement.

    3.1.2 The Authority hereby agrees to substitute the
    Concessionaire by endorsement on the Concession Agreement
    in favour of the Nominated Company selected by the Lenders’
    Representative in accordance with this Agreement. (For the
    avoidance of doubt, the Senior Lenders or the Lenders’
    Representative shall not be entitled to operate and maintain the
    Project Highway as Concessionaire either individually or
    collectively)..

    —————————————————————————-
    2.5 Rights of the parties
    The rights of the Authority, the Lenders’ Representative and the
    Concessionaire in the monies held in the Escrow Account are
    set forth in their entirety in this Agreement and the Authority,
    the Lenders’ Representative and the Concessionaire shall have
    no other rights against or to the monies in the Escrow Account.
    2.6 Substitution of the Concessionaire
    The Parties hereto acknowledge and agree that upon
    substitution of the Concessionaire with the Nominated
    Company, pursuant to the Substitution Agreement, it shall be

    Signature Not Verified
    Signed By:PRADEEP FAO OS (COMM) 137/2025 & 152/2025 Page 39 of 61
    SHARMA
    Signing Date:09.07.2026
    20:07:25
    deemed for the purposes of this Agreement that the Nominated
    Company is a Party hereto and the Nominated Company shall
    accordingly be deemed to have succeeded to the rights and
    obligations of the Concessionaire under this Agreement on and
    with effect from the date of substitution of the Concessionaire
    with the Nominated Company.”

    95. Suffice to state that there is nothing in Clauses 2 and 3 of the SA and
    Clauses 2.5 and 2.6 of the EA to show that the CA was only annexed for
    information of the respondent no.1 to enable respondent no.1 to exercise its
    rights. If the intention of the parties was only to annex the CA(s) in the
    agreements for the knowledge of the non-signatory/respondent no.1 herein,
    the wordings would have been “a copy of the CA(s) is annexed hereto” but
    the express wording in the EAs & SAs, ‘to form part of this agreement’,
    would surely mean that the intention of the parties was to make CA(s) to
    form part of the said agreement(s).

    96. As per Clause 3.2 of the EA, the appellant being signatory to the said
    agreement had agreed to make deposit in the Escrow Account the
    Termination Payment. Even the interpretation under Clause 1.2.2 and 1.2.4
    of the EA, gives a clear indication that the CA is not merely annexed for the
    knowledge of the respondent no.1 but to form part of the agreements. In this
    regard, we shall reproduce Clauses 1.2.2, 1.2.4 and 3.2 of EA, as under:

    “1.2.2 The words and expressions beginning with capital
    letters and defined in this Agreement shall have the meaning
    ascribed thereto herein, and the words and expressions used in
    this Agreement and not defined herein but defined in the
    Concession Agreement shall, unless repugnant to the context,
    have the meaning ascribed thereto in the Concession
    Agreement.

    1.2.4 The rules of interpretation stated in Clauses 1.2, 1.3 and

    Signature Not Verified
    Signed By:PRADEEP FAO OS (COMM) 137/2025 & 152/2025 Page 40 of 61
    SHARMA
    Signing Date:09.07.2026
    20:07:25
    1.4 of the Concession Agreement shall apply, mutatis mutandis,
    to this Agreement.

    3.2 : Deposits by the Authority
    The Authority agrees and undertakes that, as and when due and
    payable, it shall deposit into and/or credit the Escrow Account
    with:

    (a) Annuity and any other monies disbursed by the Authority to
    the Concessionaire;

    (b) Deleted;

    (c) Deleted and

    (d) Termination Payments:

    Provided that Authority shall be entitled to appropriate from
    the aforesaid amounts, any Concession Fee due and payable to
    it by the Concessionaire, and the balance remaining shall be
    deposited into the Escrow Account.”

    97. The learned Single Judge by referring to paragraphs 96, 126, 132 and
    184 of the award has drawn his conclusion in paragraphs 46, 47 and 49 of
    the impugned judgment, which we reproduce as under:

    “46. On perusal of the above, the parties to the Agreements i.e.
    EA and SA have clearly mentioned that the Concession
    Agreement “forms part of this Agreement” which leaves no
    manner of doubt that the Concession Agreement was an
    integral part of these Agreements. Both EA and SA are
    tripartite agreements wherein all the parties herein were
    parties to the EA and the SA. Also, EA and SA are subsequent
    agreements to the Concession Agreement meaning thereby both
    these agreements were executed mainly for the purpose of the
    smooth functioning of the Project Highway.

    47. The argument of the learned senior counsel for the
    petitioner that mere annexing does not make the Concession
    Agreement part and parcel of the EA and SA in the absence of a
    clear and unambiguous/declaration is devoid of merit as the
    wordings of the Recital quoted above clearly indicates that the
    Concession Agreement has been made part of EA and SA which
    is a clear indication in itself.

    xxxx xxxx xxxx xxxx

    Signature Not Verified
    Signed By:PRADEEP FAO OS (COMM) 137/2025 & 152/2025 Page 41 of 61
    SHARMA
    Signing Date:09.07.2026
    20:07:25

    49. Reliance on the said judgment is misplaced as the same
    deals with the incorporation of an arbitral clause when a
    document is merely referred to in a Contract whereas the
    present case does not deal with the incorporation of an
    arbitration clause. The EA and SA by clear phraseology
    incorporates the Concession Agreement in both the EA as well
    as the SA. When the recitals of EA and SA are clear and
    unambiguous, there is no need for any external aid. A perusal
    of the Recitals quoted above show that the Concession
    Agreement was not merely a reference or a statement in the
    passing but the parties expressly agreed to it forming and
    becoming a part of the two Agreements i.e. EA and SA. Reading
    anything else would be counter productive to the clear terms
    agreed upon between the parties and would in effect be
    rewriting the terms of the Contract.”

    98. We may at this stage reproduce paragraphs 96, 126, 132 and 184 of
    the Award, as under:-

    “96. There are as many as four agreements that are relevant to
    the present matter. The first is a Concession Agreement entered
    into between the Concessionaire (Respondent No. 1) and NHAI
    (Respondent No. 2). Next, there is a Common Loan Agreement
    between the lenders and the Concessionaire, whereby the
    lenders (the Claimant) advanced loans to the Concessionaire
    for the execution of the Project. Importantly, this Common Loan
    Agreement was vetted / approved by NHAI. There are also
    Supplementary Loan Agreements. There are also two
    agreements between the Claimant, Respondent No.1 and
    Respondent No.2, i.e., an Escrow Agreement and a Substitution
    Agreement. The present arbitration is invoked under these two
    agreements. It is important to note that, as per the recitals of
    both these agreements, the parties have agreed that the
    Concession Agreement form part and parcel of these
    agreements as well. All these agreements are interlinked and
    define the rights and obligations of the parties, and relevant
    provisions from these are discussed in more detail in the
    following paragraphs.

    Signature Not Verified
    Signed By:PRADEEP FAO OS (COMM) 137/2025 & 152/2025 Page 42 of 61
    SHARMA
    Signing Date:09.07.2026
    20:07:25

    xxxx xxxx xxxx xxxx

    126. It may be noted that as per Recital (A) of the Escrow
    Agreement, the Concession Agreement now forms a part of the
    Escrow Agreement.

    xxxx xxxx xxxx xxxx

    132. It is noted that, as per Recital (A), it is clear that the
    Concession Agreement, which is annexed to this agreement,
    forms a part of the Substitution Agreement as well, in a manner
    similar to that which is provided in the Escrow Agreement.

    xxxx xxxx xxxx xxxx

    184. Recital A of both the Escrow Agreement and Substitution
    Agreement are identically worded and, among other things,
    states that a copy of the Concession Agreement is “annexed
    hereto and marked as Annex-A to form part of this Agreement.”

    Thus, the Concession Agreement forms a part of both the
    Escrow Agreement and the Substitution Agreement as per the
    express words used in those agreements.”

    99. So, it follows, the conclusion drawn by the learned Tribunal and the
    learned Single Judge is justified. It is a settled law in terms of the judgments
    of the Supreme Court that, if a plausible view is taken by Arbitral Tribunal,
    the same need not be interfered with under Section 34 and Section 37 of the
    Act unless it shocks the conscious of the Court.

    100. Insofar as the judgment in the case of M.R. Engineers & Contractors
    (P) Limited
    (supra) relied upon by Mr. Nandrajog is concerned, the same
    judgment was also relied upon by the appellant before the learned Single
    Judge. The learned Single Judge did not find the same to be applicable to the
    facts of these cases. In paragraph 49 of the impugned judgment which we
    have already reproduced above, the learned Single Judge holds that the
    recitals in EA and SA are clear in as much as the CA is not merely referred
    to, but the parties expressly agreed to form part of the agreement(s). Hence
    for parity of reasons, it need to be held that the said judgment is not

    Signature Not Verified
    Signed By:PRADEEP FAO OS (COMM) 137/2025 & 152/2025 Page 43 of 61
    SHARMA
    Signing Date:09.07.2026
    20:07:25
    applicable to the facts of this case. Hence, first plea of Mr. Nandrajog is
    rejected.

    101. Coming to the second submission of Mr. Nandrajog that the learned
    Tribunal erred in holding that the PCC could not have been kept in
    abeyance, suffice to state, the learned Single Judge agreed with the
    conclusion drawn by the learned Tribunal in paragraphs 257 to 263, wherein
    the learned Tribunal has held as under:

    “257. The Tribunal has thoroughly examined the Concession
    Agreement, and is of the view that the said agreement does not
    contain any provision which provides that a PCC, once issued,
    can be either kept in abeyance or withdrawn.

    258. It is the Tribunal’s considered view that once the I.E.
    issued the PCC, further to its letter of 08.12.2016, after being
    satisfied that the tests were successful, and the requisite portion
    of the highway was complete, the PCC remained validly issued,
    and it could not be withdrawn or kept in abeyance for any
    reason. The Tribunal also notes that the decision of the I.E. to
    keep the issuance of the PCC in abeyance on grounds
    mentioned in its letter of 17.12.2016 was invalid, as the PCC
    had already been issued. Additionally, the letter issuing the
    PCC of 08.12.2016 stated certain conditions that had to be met,
    but the Concessionaire was never given the opportunity to meet
    these requirements at all. In the circumstances, not only was
    the decision to keep the PCC in abeyance invalid, it was also
    contradictory to the position taken by the authority previously.

    259. A case was made out that the PCC was withheld under the
    terms of Article 14.5 of the Concession Agreement. The
    Tribunal has considered the provision, and finds that several
    conditions need to be met in order for Article 14.5 to operate.
    Pertinently, the provision specifically relates to withholding of
    PCC, but does not apply once the PCC has been issued.
    Therefore, in the present case, as the PCC was already issued,
    this provision would not come into operation.

    260. Even if one persists with examining the applicability of

    Signature Not Verified
    Signed By:PRADEEP FAO OS (COMM) 137/2025 & 152/2025 Page 44 of 61
    SHARMA
    Signing Date:09.07.2026
    20:07:25
    Article 14.5 further, it becomes clear that the facts of the case
    do not allow for such applicability. For Article 14.5 to apply, a
    series of conditions must be met. At the outset, the I.E. ought to
    have determined that the Project Highway or any part thereof
    did not conform to the provisions of the Concession Agreement
    and could not be safely placed in commercial operation, and
    made a report to such effect. The conditions in Article 14.5
    further require that upon receipt of such a report, Respondent
    No. 2 would inspect the Project Highway, and notify
    Respondent No. 1 of such defects and deficiencies in the Project
    Highway and direct the I.E. to withhold issuance of the PCC.

    261. On the contrary, what transpired was in fact quite
    different. The Tribunal notes that the I.E. initially
    recommended issuance of PCC, stating that delays were caused
    due to Respondent No. 2. After a series of communications,
    Respondent No. 2, the I.E., the Project Director and
    Respondent No. 1, jointly conducted an inspection, in which it
    was concluded that the portion of the highway that had been
    completed was indeed fit for commercial operation. No report
    suggesting that it was not fit was made, and none of the
    subsequent requirements (as under Article 14.5) were met.
    I.E.’s letter dated 17.12.2016 which stated that the PCC was
    being kept in abeyance, said that this decision was to stand
    until completion of the Theni Bypass which was supposedly
    agreed by Respondent No. 1 in terms of a “draft supplementary
    agreement”. The Tribunal notes that the earlier letter issued by
    the I.E., dated 08.12.2016, in which it had issued the PCC, had
    clearly stated that the Theni bypass was to be completed before
    the first annuity payment date, i.e., 6 months after PCC date
    (para 24 of the letter dated 08.12.2016). The decision to keep
    the PCC in abeyance for reason of not completing the Theni
    bypass, went against the earlier decision granting the
    Concessionaire time to do so till 6 months thereafter. This was
    a clearly contradictory exercise of authority, and cannot be
    held to be valid.

    262. In the Tribunal’s view, therefore, the PCC has remained
    validly issued by the I.E. It follows that, after the Concession
    Agreement was terminated, the Claimant’s request for
    Termination Payment is also valid, and ought to be fulfilled.

    Signature Not Verified
    Signed By:PRADEEP FAO OS (COMM) 137/2025 & 152/2025 Page 45 of 61
    SHARMA
    Signing Date:09.07.2026
    20:07:25

    263. Accordingly, Issue No. 5 is answered as follows: Answer
    to Issue No. 5. The letter dated 17.12.2016 issued by I.E.
    purportedly keeping the PCC dated 08.12.2016 in abeyance
    was non est, void ab-initio and beyond the scope and powers of
    I.E and Respondent No. 2″

    (emphasis supplied)

    102. The submission of Mr. Nandrajog is that the IE has corrected its
    error/mistake by keeping the PCC in abeyance. According to him, if the
    contrary is held to be correct, every mistake of IE will necessarily have to be
    litigated in the Courts and Arbitral Tribunal for it to be set aside and this will
    entail unnecessary litigation as such when a party has an administrative duty
    to act in execution of its duty, the same authority is duty bound and
    obligated to correct it as soon as it is brought to its knowledge.

    103. His other submission is that the learned Tribunal had failed to
    consider Article 14.3.2 of CA(s) i.e., PCC could have only been issued after
    75% of the total length of Project Highway has been completed. Whereas, it
    has only completed 90.61 km, which is less than 75% and the IE has rightly
    corrected its mistake and kept the PCC in abeyance till 75% of the total
    length of the project Highway is completed. In other words, it is his
    submission that, IE was obligated under the contractual provision to ensure
    compliance thereto.

    104. Suffice to state, the reasons for the learned Tribunal to answer the
    issue relatable to PCC in the context of the facts has been noted by the
    learned Tribunal under Issue no.5, which can be seen from paragraphs 248
    to 256, of the award, in the following manner:

    “248. It is clear that the terms of the Concession Agreement 579
    provided that it was the responsibility of Respondent No. 2 to

    Signature Not Verified
    Signed By:PRADEEP FAO OS (COMM) 137/2025 & 152/2025 Page 46 of 61
    SHARMA
    Signing Date:09.07.2026
    20:07:25
    provide the vacant land and access to the project site (Article
    10.3.2580), and any delays in such provision of land and right of
    way would invite a daily sum of damages proportional to the
    area, payable by Respondent No. 2 to the Concessionaire
    (Article 10.3.4581). The Concession Agreement582 also
    specifically provides that once the Concessionaire receives
    such right of way, it shall complete the works within a
    reasonable period of time, and also that the issuance of the
    PCC shall not be delayed due to access not being granted to
    any part of the site (Article 10.3.5583). The Tribunal notes, in
    pertinent part, that Article 14.3.1584 clearly provides that the
    I.E. shall not withhold the PCC for reason of any work
    remaining incomplete if the delay in completion thereof is
    attributable to Respondent No. 2.

    249. Critically, the Tribunal notes that the Concessionaire’s
    obligation to complete the affected works subsists only if
    Respondent No. 2 has paid the damages as specified (Article
    10.3.5585), and if Respondent No. 2 stops paying such damages,
    the Concessionaire is no longer obliged to complete such works
    on such part of the Site.

    250. In the present case, it is recorded (Respondent No. 1’s
    letter dated 22.09.2014586 ) that Respondent No. 1 had
    completed all works in the land handed over by Respondent No.
    2 within 90 days from the Appointed Date, following which, as
    per due process, it requested the I.E. to issue the PCC. This
    was in accordance with Article 14.3587 of the Concession
    Agreement.588 The I.E. recommended onwards that the PCC be
    issued for a length of 80.561 km vide its letter No. ICT 654
    TPV:2911 dated 13.03.2014 had recommended the issuance of
    PCC to the Project Director of Respondent No. 2 for a length of
    80.561 km. However, in a subsequent letter no. ICT:654 TPV:

    4302 dated 17.04.2014, the I.E. informed the Concessionaire
    that its recommendation for issuance of PCC was rejected by
    Respondent No. 2 as the completed stretches of the Project
    Highway (i.e., 80.561 km) was less than 75% of the Project
    Highway. Upon a request for reconsideration by the
    Concessionaire, it was invited by the NHAI vide letter dated
    01.09.2014 to submit a proposal for issuance of PCC to the I.E.
    for further action, which it duly did by letter dated 22.09.2014.

    Signature Not Verified
    Signed By:PRADEEP FAO OS (COMM) 137/2025 & 152/2025 Page 47 of 61
    SHARMA
    Signing Date:09.07.2026
    20:07:25

    251. Thereafter, the I.E., in its letter dated 07.11.2014 589 to the
    Project Director of Respondent No. 2, categorically
    recommending the issue of PCC for the completed stretches of
    80.561 kms, highlighting that:

    i. since the project began, there were problems in handing over
    ‘Right of Way’ and ‘Right to Access’ for highway construction;
    ii. Respondent No. 1 had substantially completed the works in
    the length of the hindrance free highway available to it;
    iii. As per Article 14.2590 of the Concession Agreement,591 on
    completion of the construction works and the I.E. determining
    the Tests to be successful, the I.E. must issue a PCC. These
    required tests had already been carried out in March 2014;
    iv. Once a PCC is issued, it cannot be withheld, if reasons for
    delay in completion of the whole Highway is attributable to
    Respondent No. 2 for delay in handing over of land and State
    Government Authorities for delay in shifting of utilities as per
    Articles 10.3.5,592 14.3.1593 and 11.2594 of the Concession
    Agreement;595
    v. NHAI Circular No. NHAI/CMC/2010/Misc./13873 dated
    07.09.2010596 permits issuance of PCC for completed stretches
    in such situations; vi. Respondent No. 1 is entitled to receive
    full Annuity Payment of Rs. 20.5 crore on completion of the
    first six months after the date of issue of PCC since the delay in
    completion of the Project within the Scheduled Two-Laning
    Completion Date of 31.08.2013 was due to the delay in handing
    over of encumbrance free and vacant access to the
    Concessionaire.

    252. The Tribunal notes that the response of Respondent No. 2,
    to issue a cure period notice dated 10.06.2015 instead, in which
    it blamed Respondent No. 1 for the delays, according to the
    Claimant, was contradictory to the position taken by the I.E.

    253. The Tribunal also notes that in the intervening period,
    Respondent No. 1 had had to resort to seeking additional loans
    and raising additional funds. However, according to the
    Claimant, if Respondent No. 2 had approved the PCC upon the
    recommendation of the I.E., the annuity payments would have
    started flowing to Respondent No. 1, and it would not have had
    to resort to any loans or additional funding, and would have
    been able to continue its works without any financial

    Signature Not Verified
    Signed By:PRADEEP FAO OS (COMM) 137/2025 & 152/2025 Page 48 of 61
    SHARMA
    Signing Date:09.07.2026
    20:07:25
    impediments.

    254. The Tribunal notes that after an additional portion of the
    works was completed, the I.E. wrote, in a letter of
    30.09.2016,597 to the Chief General Manger cum RO of
    Respondent No. 2, expressing its intention to issue a PCC for
    the completed stretches. Respondent No. 2, in its letter dated
    24.10.2016,598 also explicitly and clearly concurred with this
    recommendation, stating as much in the said letter, after
    recording that it had inspected the completed length of 90.671
    km of the Project Highway, along with the I.E., the Project
    Director and Respondent No. 1, and found it to be safe and
    reliable for commercial operation. Respondent No. 2, besides
    confirming its concurrence with I.E.’s recommendation to issue
    the PCC, conveyed its authorization for the issuance as well, as
    is clear from the language of the letter, which states that
    “Undersigned therefore concurs with your recommendation for
    issuance of PCC…. and accordingly authorization is hereby
    conveyed for issue of Provisional Completion Certificate for
    the completed length of 90.671 km.”

    255. The Tribunal notes that thereafter, the I.E. issued the PCC
    for the completed stretch of 90.671 Km by its letter
    08.12.2016,599 but also required the Concessionaire to execute
    a Supplementary Agreement before 25.12.2016, and completion
    of balance works by 31.10.2017. However, before either of
    these requirements could be fulfilled, the I.E. issued another
    letter, on 17.12.2016,600 that the PCC is kept in abeyance until
    “completion of Theni Bypass as agreed by the Concessionaire
    in the draft Supplementary Agreement and signing of the
    Supplementary Agreement as mentioned in paras 24 and 26
    respectively of our aforesaid letter dated 08.12.2016.”

    256. The Tribunal notes the Claimant’s position that this was
    completely different from the I.E.’s previous letter dated
    08.12.2016,601 in which it was stated that the Concessionaire
    should complete either Periyakulam Bypass or Theni bypass
    before the first Annuity payment becomes due. Had the terms of
    the 08.12.2016 been followed, the first annuity payment would
    have become on 08.05.2017 (i.e., 6 months after the issuance of
    the PCC).”

    (emphasis supplied)

    Signature Not Verified
    Signed By:PRADEEP FAO OS (COMM) 137/2025 & 152/2025 Page 49 of 61
    SHARMA
    Signing Date:09.07.2026
    20:07:25

    105. If the aforesaid paragraphs are read along with paragraphs 257 to 263
    of the Award, it is clear that the PCC was issued, pursuant to a letter written
    by the IE dated 30.09.2016 to the Chief General Manager (of the appellant)
    expressing his intention to issue a PCC for the completed stretches. The
    appellant in its letter dated 24.10.2016 concurred with the recommendation
    in as much as the appellant in the said letter has stated that, it had inspected
    the completed length of 90.671 KM of the project Highway along with the
    IE, the project director and respondent no.1, wherein it is found to be safe
    and feasible for commercial operation. The appellant confirming its
    concurrence, authorised the IE to issue the PCC. So, it follows that the
    conclusion drawn by the learned Tribunal as upheld by the learned Single
    Judge is justified and needs no interference under section 37 of the Act.

    106. The plea of Mr. Nandrajog that, it was a mistake on the part of the IE
    to issue the PCC cannot be accepted in the facts which have been noted by
    the learned Tribunal. The learned Single Judge has in paragraphs 54, 55, 56,
    57, 59, 60,61 and 62 of the impugned judgment has held as under:

    “54. On conjoint reading of Clauses 10.3.2, 10.3.4 and 10.3.5,
    it was the sole responsibility of the Authority (in the present
    case, the petitioner) to provide access and vacant land as per
    the Appendix to the respondent No. 2 within the 90 days period
    from the date of Appointed Date and if there was any delay in
    providing the same, it was to attract damages payable to the
    respondent No. 2 by the petitioner. Further, the construction
    work on the land provided was to be completed within 90 days
    and the issuance of PCC was not be delayed due to access
    being not granted to any part of the site. It is necessary to
    highlight the said clauses as in the present case as it is a case
    where the project site was not fully handed over by the
    petitioner to the respondent No. 2.

    55. As per Clause 14.3.1 and 14.3.2, upon the request of the

    Signature Not Verified
    Signed By:PRADEEP FAO OS (COMM) 137/2025 & 152/2025 Page 50 of 61
    SHARMA
    Signing Date:09.07.2026
    20:07:25
    Concessionaire (in the present case, the respondent No. 2), the
    IE may issue PCC subject to tests being successful and if the
    Project Highway could be safely and reliably placed in
    commercial operation. Further, the IE was not to withhold the
    PCC if the work was incomplete due to delay attributable to the
    petitioner. Also, PCC was only to be issued if the 75% of the
    total length of the project highway was completed. Clause 14.5
    states that if the IE determined that Project Highway was not in
    conformity with the provisions of the Concession Agreement
    and could not be safely placed in commercial operation, IE
    should forthwith send a report to the petitioner and respondent
    No. 2. If the petitioner was also of the same opinion, then the
    petitioner could direct the IE to withhold the PCC.

    56. The respondent No. 2, after completion of the construction
    work within 90 days from the appointed date, issued a letter
    dated 22.09.2014 to IE requesting grant of PCC. IE responded
    to the said letter of the petitioner, vide letter dated 07.11.2014
    by stating that respondent No. 2 had completed the work in the
    length available and there were major problems at the
    petitioner’s end in handing over the “Right of Way” and
    “Right to access” for construction meaning thereby that the
    respondent No. 2 was entitled to Annuity Payment as there was
    delay in handing over of encumbrance free and vacant access
    to the respondent No. 2 by the petitioner. Vide letter dated
    17.04.2014, IE informed the respondent No. 2 that PCC request
    has been rejected by the petitioner on the ground that 75% of
    the Project Highway was not completed.

    57. IE again wrote a letter dated 07.11.2014 to the petitioner
    by reiterating the above grounds. In the meanwhile, the
    petitioner issued Cure Period Notice on 10.06.2015. Again,
    after the additional work was completed, IE vide letter dated
    30.09.2016 expressed its intention to issue PCC. The petitioner
    vide letter dated 24.10.2016 confirmed the request of the IE
    after inspecting the 90.671 km of the Project Highway.
    Thereafter, the IE vide letter dated 08.12.2016 issued PCC for
    the completed stretch of 90.671 KM of the Project Highway and
    further stated that the respondent No. 2 shall complete the
    Periyakulam Bypass or Theni Bypass before the first annuity
    payment falls due i.e. 08.05.2017 (6 months after issuance of

    Signature Not Verified
    Signed By:PRADEEP FAO OS (COMM) 137/2025 & 152/2025 Page 51 of 61
    SHARMA
    Signing Date:09.07.2026
    20:07:25
    PCC) and the remaining bypasses before 31.10.2017 and to
    execute SA.

    xxxx xxxx xxxx xxxx

    59. IE again issued a letter dated 17.12.2016 informing the
    respondent No. 2 that PCC had been kept in abeyance by
    stating that “until completion of the Theni Bypass as agreed by
    the Concessionaire in the draft Supplementary Agreement and
    signing of the Supplementary Agreement as mentioned in paras
    24 and 26 respectively of our aforesaid letter dated
    08.12.2016”.The operative part of letter dated 17.12.2016 is
    extracted below:-

    “Ref: ICT letter no.ICT:654:TPV:10532 dt. 08.12.2016
    Dear Sir, In continuation to our letter no.10532 dated
    08.12.2016, it is hereby notified that Provisional
    Certificate dated 08.12.2016 enclosed herewith for the
    above mentioned project is kept in abeyance, until
    completion of the Theni Bypass as agreed by the
    Concessionaire in the draft Supplementary Agreement
    and signing of the Supplementary Agreement as
    mentioned in paras 24 and 26 respectively of our
    aforesaid letter dated 08.12.2016.”

    60. To my mind, the letter dated 17.12.2016 is contrary to the
    letter dated 08.12.2016 as the former is against the
    deadlines/instructions provided in the latter.

    61. A perusal of the letter dated 17.12.2016 show that the PCC
    was kept in abeyance till Theni bypass is completed and the SA
    is signed. However, the letter dated 08.12.2016, while issuing
    PCC, the IE himself had granted time to complete the bypasses
    and signing of the SA. Respondent No. 2 was not given time to
    complete the requirements as mentioned in the letter of
    08.12.2016. Further, clause 14.5 of Concession Agreement only
    gives the liberty to withhold the PCC before it is issued by the
    IE but does not give any liberty to withhold the PCC once it is
    issued.

    62. Keeping the PCC in abeyance by the IE vide letter dated
    17.12.2016 was beyond the terms of the said clause i.e. 14.5.
    The fact that the PCC was granted after the petitioner
    confirmed its concurrence and recommended its authorization
    then its issuance cannot be ignored. The Concession Agreement

    Signature Not Verified
    Signed By:PRADEEP FAO OS (COMM) 137/2025 & 152/2025 Page 52 of 61
    SHARMA
    Signing Date:09.07.2026
    20:07:25
    nowhere provides that the PCC once issued can be kept in
    abeyance or withdrawn. The interpretation given by the learned
    senior counsel for the petitioner that IE after realizing its
    mistake, kept the PCC in abeyance as 75% of the total length of
    the Project Highway was not completed is against the clause
    quoted above which gives IE the only right to withhold the PCC
    „before‟ it is issued but not once the PCC is issued.

    Additionally, the PCC was issued after inspection by the IE and
    approval by the petitioner. If the interpretation propounded by
    the petitioner is accepted then the said clause will lead to
    absurdity.”

    (emphasis supplied)

    107. At this stage, we may refer to the finding of the learned Tribunal in
    paragraph 259 of the Award on the interpretation of Article 14.5 of the CA.
    The paragraph 259 is already reproduced in paragraph 101 above.

    108. The aforesaid conclusion of the learned Tribunal and the learned
    Single Judge is justified and cannot be said to be perverse in law. It is a
    plausible interpretation, which cannot be interfered with. Hence, this
    submission of Mr. Nandrajog is liable to be rejected.

    109. Insofar as the submission of Mr. Nandrajog that the learned Tribunal
    has directed the deposit of Termination Payment is erroneous as according
    to him, the Termination Payment under the CAs is not payable if termination
    happens due to concessionaire’s default. He has heavily relied upon the
    Article 37.3.1 of the CA(s) which stipulates that, concessionaire
    acknowledges that no Termination Payment shall be due or payable on
    account of a concessionaire default occurred prior to COD. He also
    submitted that the COD is achieved upon issuance of Completion Certificate
    / PCC which is issued by the IE. Since the COD was not achieved as the

    Signature Not Verified
    Signed By:PRADEEP FAO OS (COMM) 137/2025 & 152/2025 Page 53 of 61
    SHARMA
    Signing Date:09.07.2026
    20:07:25
    PCC issued by IE was kept in abeyance, the Termination Payment is not
    payable. He has also submitted that the Termination Payment becomes only
    payable when the concessionaire raises the demand for the same. According
    to him, only the parties to the contract can enforce their rights and liabilities
    under such contract, as such, respondent no.1 is precluded from seeking
    enforcement of CA(s)/ Termination Payment

    110. According to the learned Tribunal, the PCC was validly issued on
    08.12.2016. Therefore, COD was achieved on the date of issuance of PCC
    as per Article 15 of the CA. In this regard, the learned Single Judge has in
    paragraphs 73 to 84 of the impugned judgment has held as under:

    “73. Clause 40 of the Concession Agreement reads as under:-

    “40.3 Substitution Agreement
    40.3.1 The Lenders’ Representative, on behalf of Senior
    Lenders, may exercise the right to substitute the
    Concessionaire pursuant to the agreement for
    substitution of the Concessionaire(the “Substitution
    Agreement”) to be entered into amongst the
    Concessionaire, the Authority and the Lenders’
    Representative, on behalf of Senior Lenders,
    substantially in the form set forth in Schedule – V.”

    74. A perusal of the said clause makes it evident that the parties
    herein were obligated to enter into SA. Pursuant to the said
    clause, the parties herein entered into the SA on 31.05.2013.

    75. Clause 2 of the SA reads as under:-

    “2. ASSIGNMENT

    2.1 Assignment of rights and title The Concessionaire
    hereby assigns the rights, title and interest in the
    Concession to, and in favour of, the Lenders’

    Signature Not Verified
    Signed By:PRADEEP FAO OS (COMM) 137/2025 & 152/2025 Page 54 of 61
    SHARMA
    Signing Date:09.07.2026
    20:07:25
    Representative pursuant to and in accordance with the
    provisions of this Agreement and the Concession
    Agreement by way of security in respect of financing by
    the Senior Lenders under the Financing Agreements.”

    76. On perusal, it is clear that the Concessionaire has assigned
    its rights, title and interest in favour of the Lenders
    Representative, pursuant to execution of the SA, i.e. the
    respondent No. 1. Furthermore, the respondent No. 2 under the
    Concession Agreement has been described as
    “Concessionaire” which includes its successors and permitted
    assigns and substitutes. On conjoint reading, it is clear that
    there is a conscious and deliberate intent on the part of the
    contracting parties to transfer and assign all rights, title, and
    interest held by the Concessionaire to the Lenders
    Representative i.e. the respondent No. 1. Consequently, the
    respondent No. 1 after execution of the SA, steps into the shoes
    of the Concessionaire. Hence, the respondent No. 1 acting in
    the capacity of the respondent No. 2 is entitled to make such
    demands.

    77. Assuming for the sake of argument that the Concessionaire
    can only demand the Termination Payment, such a contention
    completely ignores the plain language and “commercial
    purpose” of the Agreements and if it is implemented, it will
    render effective the carefully crafted substitution mechanism.
    This interpretation would disregard the intent of the parties,
    who clearly intended that the lender, upon substitution, would
    possess all the rights necessary to recover its dues including
    the Termination Payment.

    78. In somewhat similar circumstances, a coordinate bench of
    this Court in PNB II observed as under:-

    “36. Besides, the debt had been extended, by the
    lenders, led by PNB, to JST, for the project forming
    subject matter of the Concession Agreement. Once the
    Concession Agreement itself stood terminated, the
    loaned amount was required to be returned. The
    lenders, led by PNB, had no concern with the inter se

    Signature Not Verified
    Signed By:PRADEEP FAO OS (COMM) 137/2025 & 152/2025 Page 55 of 61
    SHARMA
    Signing Date:09.07.2026
    20:07:25
    disputes between NHAI and JST. It is for this reason
    that the Concession Agreement, rightly, made deposit by
    NHAI, into the Escrow Account, as well as the
    withdrawal, thereby, by the lenders, the inevitable
    sequitur to termination of the Concession Agreement.
    The amounts claimed by NHAI from JST were subject
    matter of the inter se dispute between NHAI and JST.
    The right of NHAI to claim these amounts from JST
    cannot be gainsaid. That, however, was rightly made
    subject matter of a separate arbitral proceeding, which
    is presently pending. Whatever be the outcome of the
    arbitral proceeding, the fact that the Concession
    Agreement stands terminated and that, thereby, NHAI
    became liable to deposit, into the Escrow Account, at
    least 90 of the Debt Due, is an undeniable, even if
    uncomfortable (to NHAI), contractual reality. The
    attempt of NHAI to “adjust”, from the said figure, the
    amounts which, according to it, are liable to be paid by
    JST, amounts to taking, from Peter, what is due from
    Paul. NHAI and Paul may be at loggerheads in the first
    arbitral proceeding; that cannot delegate from the right
    of Peter, to the return of the debt extended by it.”

    (Emphasis added)

    79. The AT in paragraph 275 of the Arbitral Award in this
    regard has observed as under:-

    “275. Respondent No. 2 maintains that the demand for
    Termination Payment should and could have been made
    only by the Concessionaire in order for the Termination
    Payment to become due and payable. However, this
    argument, as discussed earlier, has no merits. The
    Tribunal is of the view that the Concessionaire need not
    request for the Termination Payment at all; making
    such a request mandatory would nullify and effectively
    defeat the entire purpose of the scheme laid out in
    Article 37.3 of the Concession Agreement read with the
    Escrow Agreement and the Substitution Agreement”

    Signature Not Verified
    Signed By:PRADEEP FAO OS (COMM) 137/2025 & 152/2025 Page 56 of 61
    SHARMA
    Signing Date:09.07.2026
    20:07:25

    80. Hence, the contention of the petitioner that the demand of
    the Termination Payment can only be made by respondent No.
    2 is rejected.

    81. It is also argued that if the Concession Agreement is
    terminated due to the defaults committed by the respondent No.
    2 before achieving COD, the Termination Payment shall not be
    due and payable.

    82. Clause 37.3 of the Concession Agreement reads as under:-

    “37.3 Termination Payment
    37.3.1 Upon Termination on account of a
    Concessionaire Default during the Operation Period,
    the Authority shall pay to the Concessionaire, by way of
    Termination Payment, an amount equal to the
    discounted value of future Annuity payments, the
    discounting factor applied being the then SBI PLR +
    (plus) 3% less Insurance Cover; provided that if any
    insurance claims forming part of the Insurance Cover
    are not admitted and paid, then 80%(eight per cent) of
    such unpaid claims shall be deducted from the
    Termination Payment so assessed. For the avoidance of
    doubt, the Concessionaire hereby acknowledges that no
    Termination Payment shall be due or payable on
    account of a Concessionaire Default occurring prior to
    COD.

    37.3.2 Upon Termination on account of any Authority
    Default, the Authority shall pay to the Concessionaire,
    by way of Termination Payment, an amount equal to the
    discounted value of future Annuity payments, the
    discounting factor applied being the then SBI PLR –

    (minus) 3%.

    37.3.3 Termination Payment shall become due and
    payable to the Concessionaire within 15 (fifteen) days
    of a demand being made by the Concessionaire to the
    Authority with the necessary particulars, and in the

    Signature Not Verified
    Signed By:PRADEEP FAO OS (COMM) 137/2025 & 152/2025 Page 57 of 61
    SHARMA
    Signing Date:09.07.2026
    20:07:25
    event of any delay, the Authority shall pay interest at a
    rate equal to 3% (three per cent) above the Bank Rate
    on the amount of Termination Payment remaining
    unpaid; provided that such delay shall not exceed 90
    (ninety) days. For the avoidance of doubt, it is expressly
    agreed that Termination Payment shall constitute full
    discharge by the Authority of its payment obligations in
    respect thereof hereunder.

    37.3.4 The Concessionaire expressly agrees that
    Termination Payment under this Article 37 shall
    constitute a full and final settlement of all claims of the
    Concessionaire on account of Termination of this
    Agreement for any reason whatsoever and that the
    Concessionaire or any shareholder thereof shall not
    have any further right or claim under any law, treaty,
    convention, contract or otherwise.”

    83. On perusal, Clause 37.3.1 states that the if the Agreement is
    terminated on account of the Concessionaire default during the
    operation period then the Authority i.e. the petitioner would
    pay as per the clause quoted above. Further, if the Agreement
    terminated prior to COD on the Concessionaire default, no
    amount shall be due or payable. Clause 37.3.2 and 37.3.3
    states the formula to be applied for Termination Payment
    alongwith the interest component.

    84. I have already observed that the letter dated 17.12.2016 is
    contrary to the letter dated 08.12.20216 and once PCC is
    issued in terms of the Concession Agreement, the same cannot
    be kept in abeyance and/or withdrawn. PCC was validly issued
    on 08.12.2016. Therefore, COD was achieved on the date of
    issuance of PCC as per Article 15 of the Concession Agreement
    and the demand made by the respondent No. 1 for Termination
    Payment was valid. Further the Concession Agreement was
    terminated vide Termination Notice dated 22.05.2019 w.e.f.
    09.04.2019. The argument of the petitioner that the Agreement
    was terminated prior to COD is devoid of merit as PCC
    (08.12.2016) was issued before the Termination Notice dated

    Signature Not Verified
    Signed By:PRADEEP FAO OS (COMM) 137/2025 & 152/2025 Page 58 of 61
    SHARMA
    Signing Date:09.07.2026
    20:07:25
    22.05.2019 w.e.f. 09.04.2019.”

    (emphasis supplied)

    111. Suffice to state that this plea of Mr. Nandrajog is also unmerited in
    view of our conclusion on his previous submission, based on the
    interpretation of Article 14.5 of the CA and the same has been rightly dealt
    with by the learned Single Judge in paragraph 84 of the impugned judgment.
    So, we find no reason to interfere with the conclusion drawn by the learned
    Single Judge. Hence, the plea of Termination Payment not becoming due
    and payable is not sustainable.

    112. One of the pleas of Mr. Nandrajog is that the learned Tribunal has
    erred in arriving at figures of Rs.229.50 and Rs.181.81 Crores as
    Termination Payment is erroneous, as according to him, adjudication of
    quantum of Termination Payment is beyond the scope of reference as there
    is no provision in the EA or SA that enables the learned Tribunal to
    calculate Termination Payment. To put it straight, he stated that Termination
    Payment can only be calculated while entertaining disputes/claims arising
    out of CA(s) which are/shall be subject matter of Arbitral proceedings
    between the concessionaire and the appellant. We note the learned Single
    Judge has decided identical plea by stating in paragraph 87 of the impugned
    judgment, in the following manner: –

    “87. I have already observed above that the Concession
    Agreement forms part of the EA and SA. Hence, there is no
    question that the AT exceeded its jurisdiction. Also, the
    calculation of the Termination Payment is a question of fact not
    a question of jurisdiction. The answer to the said contention i.e.
    calculation of Termination Payment, clearly lies in Clause 37
    of the Concession Agreement and more particularly in Clause

    Signature Not Verified
    Signed By:PRADEEP FAO OS (COMM) 137/2025 & 152/2025 Page 59 of 61
    SHARMA
    Signing Date:09.07.2026
    20:07:25
    37.3.2 and 37.3.3. Further, the petitioner has not argued that
    the amount of Rs. 229.50 crores suffer from any errors or that
    extra amounts have been added instead of this, only a mere
    averment has been made without any evidence. On perusing the
    SOD filed by the petitioner, the calculation of Termination
    Payment has not been disputed.”

    (emphasis supplied)

    113. We agree that the said conclusion drawn by the Learned Single
    Judge, which is a factual finding. Hence, this plea of Mr. Nandrajog is also
    liable to be rejected. We order so.

    114. In so far as judgments relied upon by Mr. Nandrajog in the cases of
    Associated Engineering Co. (supra), Rajasthan State Mine and Minerals
    Ltd.
    (supra), Food Corporation of India (supra) & Indian Oil Corporation
    Limited
    (supra) are concerned, they have no applicability to the facts of the
    case, as the aspect of calculation of Termination Payment was never
    disputed before the learned Tribunal. The learned Single Judge has reiterated
    the finding of the learned Tribunal in paragraph 87 of the impugned
    judgment, which we have reproduced above. Hence, the contention of the
    appellant that the learned Tribunal exercised jurisdiction beyond the
    provisions of the contract, is devoid of any merit.

    115. In so far as judgments in the case of Visa International Ltd. (supra)
    & Nandram Hanutram (supra) are concerned, Mr. Nandrajog submitted
    that the application for arbitration can be made only when a dispute arises
    between the parties to the arbitration agreement. It is the finding of the
    learned Tribunal on facts that the arbitration has been invoked by the
    respondent no.1 under EA & SA for the Termination Payment to be

    Signature Not Verified
    Signed By:PRADEEP FAO OS (COMM) 137/2025 & 152/2025 Page 60 of 61
    SHARMA
    Signing Date:09.07.2026
    20:07:25
    deposited in the Escrow Account. The submission that the dispute is
    between the appellant and the concessionaire, and whether the
    lender/respondent no.1 can step into the shoes of the concessionaire is
    settled by the learned Single Judge in paragraph 76 of the impugned
    judgment as reproduced by us in paragraph 110 and no interference is called
    for. This answers the submission made by Mr. Nandrajog, as noted by us in
    paragraph 52 above.

    116. In so far as judgment in the case of Transstroy Tirupati Tiruthani
    Chennai Tollways Pvt. Ltd.
    (supra) is concerned, the issue before the Court
    was with regard to the Bank’s right to substitution upon the occurrence of
    concessionaire’s default. The said judgment has no applicability to the facts
    of this case and in view of our findings above.

    117. In view of our above discussion, these appeals being devoid of
    merits are dismissed. Pending applications are dismissed as infructuous.

    V. KAMESWAR RAO, J

    VINOD KUMAR, J
    JULY 09, 2026
    rt

    Signature Not Verified
    Signed By:PRADEEP FAO OS (COMM) 137/2025 & 152/2025 Page 61 of 61
    SHARMA
    Signing Date:09.07.2026
    20:07:25



    Source link

    LEAVE A REPLY

    Please enter your comment!
    Please enter your name here