24.04.2026 vs M/S Sew Engineering Works on 22 May, 2026

    0
    23
    ADVERTISEMENT

    Jammu & Kashmir High Court

    Reserved On: 24.04.2026 vs M/S Sew Engineering Works on 22 May, 2026

    Bench: Rajnesh Oswal, Rahul Bharti

                                                                             2026:JKLHC-JMU:1626-DB
    
    
    
    HIGH COURT OF JAMMU & KASHMIR AND LADAKH
                                      AT JAMMU
    
                                       AA No. 7/2023
    
                                       Reserved on:            24.04.2026
                                       Pronounced on:          22.05.2026
                                       Uploaded on:            26.05.2026
    
                                       Whether the operative part or full
                                       judgment is pronounced: Full
                                       judgment.
         Union of India
         Th. Chief Engineer Udhampur
         Zone, Udhampur
         Garrison Engineer (South)               .....Appellant(s)/Petitioner(s)
         Udhampur
    
    
                           Through: Mr. Sumant Sudan, Advocate vice
                                    Mr. Vishal Sharma, DSGI.
    
                      Vs
         M/S Sew Engineering Works
         Pvt. Ltd. L-333, Sarita Vihar
         New Delhi-110076                        ..... Respondent(s)
    
                           Through: Mr. M. K. Raina, Advocate.
    
    Coram: HON‟BLE MR. JUSTICE RAJNESH OSWAL, JUDGE
           HON‟BLE MR. JUSTICE RAHUL BHARTI, JUDGE
                                      JUDGMENT
    

    (Oswal-J)

    1. Present appeal under Section 37 of the Arbitration and

    SPONSORED

    Conciliation Act, 1997 (for short ‘the Act of 1997’), is aimed

    against an order dated 11.01.2023 passed by the court of

    learned Principal District Judge, Udhampur, whereby an

    application filed by the appellant for setting aside an

    AA No. 7/2023 Page 1 of 10
    2026:JKLHC-JMU:1626-DB

    arbitration award dated 08.09.2014 passed by the sole

    arbitrator-Sh. Satish Chander, Chief Engineer (Contracts) has

    been dismissed.

    2. In the memo of appeal, the appellant is coming forward with

    grounds of challenge to the order dated 11.01.2023 as

    under:-

    a. that the impugned order dated 11.01.2023 suffers from

    patent illegality, as Court of the learned Principal District

    Judge, Udhampur failed to appreciate that the underlying

    arbitral award was passed in blatant disregard of express

    provisions of the contract;

    b. that the court of learned Principal District Judge, Udhampur

    missed to consider a specific ground raised in the appellant’s

    petition under Section 34 of the Act of 1997 that the award is

    entirely non-speaking. Such an omission directly violates the

    statutory mandate of Section 31(3) of the Act of 1997 and is,

    ex-facie, opposed to Public Policy;

    c. that the court of learned Principal District Judge, Udhampur

    resorted to an irregular exercise of jurisdiction by dismissing

    the appellant’s petition by exploit of very general observations

    and mechanical recitation of judicial precedents bearing no

    relevance to the actual controversy at hand.

    AA No. 7/2023 Page 2 of 10

    2026:JKLHC-JMU:1626-DB

    3. Mr. Sumant Sudan, Advocate appearing vice Mr. Vishal

    Sharma, learned DSGI, has submitted that the court of

    learned Principal District Judge, Udhampur has not

    considered in a right and correct perspective the petition filed

    by the appellant under Section 34 of the Act of 1997, as such,

    the order impugned deserves to be set-aside.

    4. Mr. M. K. Raina, learned counsel for the respondent on the

    other hand has submitted that the scope of interference in an

    appeal under Section 37 of the Act of 1997 before this court is

    tightly circumscribed. He has argued that the essential

    conditions envisaged under Section 34 of the Act of 1997 for

    setting aside an arbitral award were completely lacking in the

    instant case and, thus, the court of learned Principal District

    Judge, Udhampur deservingly dismissed the appellant’s

    challenge and the petition. He further contends that the court

    of learned Principal District Judge, Udhampur actively

    applied its judicial mind to the matter in issue which aspect

    is clearly demonstrated by the fact that the court modified

    and reduced awarded interest rate from 12% p.a for entire

    period to 6% p.a for the pre-arbitration and pendente lite

    periods

    5. Heard thoroughly learned counsel for the parties and perused

    the record.

    AA No. 7/2023 Page 3 of 10

    2026:JKLHC-JMU:1626-DB

    6. A perusal of the record depicts that contract agreement No.

    CEUZ-03/2000-2001 for work of “Provision of OTM Accn.

    For HQ Northern Command (Phase-III) at Udhampur” was

    executed between the appellant through Chief Engineer,

    Udhampur Zone, and the respondent herein M/s Sew

    Engineer Works Pvt. Ltd., on 26.07.2000. Upon emergence of

    certain disputes between the parties to the contract, the

    matters were referred to the arbitral tribunal of Arbitrator-Sh.

    Baljit Singh, Chief Engineer but following his resignation from

    the appointment, Sh. Satish Chander, Chief Engineer

    (Contracts), was appointed as the substituted arbitrator.

    7. Conspectus of the contract in reference between the parties

    hereto is set out as under:-

    a) Contract Agreement No. : CEUZ-03 of 2000-01

    b) Name of work : Provision of OTM Accn for HQ
    Northern Command (Phase-III) at
    Udhampur.

    c) Date of acceptance of Tender : 26 Jul 2000

    d) Amount of contract : Rs. 2, 46, 56, 178.24

    e) Date of commencement of work : Sample Quarter-23 Aug 2000

    Phase-I (a)- 23 Aug 2000
    Phase-I (b)- 23 Aug 2000
    Phase-II – 07 Sep 2001

    f) Original date of completion : Sample Quarter-22 Apr 2001

    Phase-I (a)- 22 Aug 2001
    Phase-I (b)- 22 Jun 2002
    Phase-II – 22 Jun 2002

    g) Extended date of completion : Sample Quarter-07 Feb 2004

    Phase-I (a)- 28 Feb 2005
    Phase-I (b)- 31 Oct 2005
    Phase-II – 31 Dec 2005

    h) Date of cancellation contract (First) : 05 Aug 2002

    Date of revocation of cancellation : 12 Jul 2003

    AA No. 7/2023 Page 4 of 10
    2026:JKLHC-JMU:1626-DB

    i) Date of cancellation (2nd time) : 08 Nov 2005 wef 25 Nov 2005

    8. Before the learned Arbitrator, the appellant raised four claims

    while the respondent preferred nine claims. Vide award dated

    08.09.2014, the learned Arbitrator rejected all four claims of

    the appellant; out of the respondent’s nine claims, four were

    rejected altogether, while the remaining five were allowed in

    part. Both sides’ i.e., the appellant and the respondent’s

    respective statement of claims are set out herein as under

    and the decision against each claim returned by the learned

    arbitrator:

    CLAIMS OF APPELLANT-UNION OF INDIA (CLAIMANT)

    CLAIM No. 1: EXTRA EXPENDITURE INCURRED TO GET THE BALANCE WORK
    COMPLETED THROUGH OTHER AGENCY.

    Amount of claim: Rs. 1,00,19,424.64

    This claim was held and declared nil.

    CLAIM No. 2: COMPENSATION FOR DELAY.

    Amount of claim: Rs. 12,32,808.92

    This claim was held and declared nil.

    CLAIM No. 3: COST OF REFERENCE TO ARBITRATION.

    Amount of claim: Rs. 2,00,000.00

    This claim was held and declared nil.

    CLAIM No. 4: INTEREST @ 12% PER ANNUM

    This claim was held and declared nil.

    AA No. 7/2023 Page 5 of 10

    2026:JKLHC-JMU:1626-DB

    9. CLAIMS OF RESPONDENT-M/S SEW ENGINEERING WORKS PVT.

    LTD.

    CLAIM No. 1: PAYMENT OF FINAL BILL INCLUDING RELEASE OF BANK
    GUARANTEES AND LOSS DUE TO EXTENSION OF BGBs

    Amount of claim: Rs. 78,56,066.00

    Claim No. 1 was awarded for Rs. 27,22,679/-

    Claim: Further the UOI shall also release the BGBs No. SEW/G/8/01/F dated
    16 Jul 2001 for Rs. 2,20,000.00 and No. SWE/G/8/01/F dated 09 May 2001
    for Rs. 1,58,300.00 within 30 days of date of publication of award.

    CLAIM No. 2: LOSS OF PROFIT DUE TO WRONG CANCELLATION OF THE
    CONTRACT.

    Amount of claim: Rs. 14,56,000.00

    Claim No. 2 awarded for Rs. 7,28,000/-

    CLAIM No. 3: LOSS DUE TO UNDERPAYMENT OF WORK OF INTERNAL
    ELECTRIFICATION (SCH „A‟ PART-IV) AND EXCESS RECOVERY OF
    CREDIT

    Amount of claim: Rs. 5,21,608.00

    This claim was held nil.

    CLAIM No. 4: NON PAYMENT OF WORKS OVER AND ABOVE CONTRACT
    PROVISION AND REIMBURSEMENT OF AMOUNT WRONGFULLY
    DEDUCTED.

    Amount of claim: Rs. 21,07,000.00

    This claim was awarded nil.

    CLAIM No. 5: LOSSES DUE TO DELAY/NON PAYMENT OF RARs.

    Amount of claim: Rs. 18,72,000.00

    This claim was awarded to Rs. 2,60,000/-

    CLAIM No. 6: LOSS ON ACCOUNT OF VARIOUS BREACHES ON THE PART OF THE
    RESPONDENTS.

    Amount of claim: Rs. 36,98,000.00

    This claim was held nil.

    AA No. 7/2023 Page 6 of 10

    2026:JKLHC-JMU:1626-DB

    CLAIM No. 7: LOSS OF REPUTATION AND LOSS DUE TO NON ISSUE OF
    TENDERS.

    Amount of claim: Rs. 1,00,00,000.00

    This claim was held nil.

    CLAIM No. 8: PAST, PENDENTE LITE AND FUTURE INTEREST @18%.

    (a) Past interest is awarded on amount awarded under Claim No. 1
    minus amount awarded against Claim No. 1 (e) and the interest shall
    be simple interest at the rate of 9% (Nine Percent) per annum and
    shall be calculated from 26 Aug 2006 to 20 Apr 2010.

    (b) Past and Pendente lite interest is awarded on amount awarded
    under Claim No. 1 minus amount awarded against Claim No. 1 (e)
    and the interest shall be simple interest at the rate of 6% (Six
    percent) per annum and shall be calculated from 21 Apr 2010 to date
    of award.

    (c) Future interest: A period of three months from the date of award is
    allowed to the UOI for making payments in terms of this award. If
    the payment is not made by this date, then the awarded amount
    shall carry simple interest at 12% (Twelve percent) per annum from
    10 Dec 2014 to date of actual payment. There shall be no future
    interest on the amount of past and pendente lite interest calculated
    as per Para (a) and (b) above.

    CLAIM No. 9: COST OF REFERENCE TO ARBITRATION

    Amount of claim: Rs. 3,00,000.00

    Rs. 50,000/- to contractor/respondent.

    10. The appellant then preferred a petition under Section 34 of

    the Act of 1997 seeking to set aside arbitral award dated

    08.09.2014. It was contended that the learned Arbitrator

    erroneously disallowed the appellant’s claims by failing to

    properly appreciate both the evidence and the supporting

    submissions and in doing so the learned Arbitrator

    overlooked a vital aspect of the dispute that the respondent

    AA No. 7/2023 Page 7 of 10
    2026:JKLHC-JMU:1626-DB

    had committed breach of fundamental contractual provisions,

    constraining not only cancellation of the contract but given

    the time-sensitive nature and urgency of the project, the

    remaining work had to be re-allotted to a 3rd party contractor

    for timely completion. By misinterpreting the appellant’s

    arguments, the learned Arbitrator wrongfully rejected the

    appellant’s claims while erroneously awarding claims in

    favour of the respondent.

    11. After considering the rival contentions of the parties, the

    learned Principal District Judge, Udhampur arrived at the

    following conclusion:

    “12. Nevertheless, a careful perusal of the award
    passed by the Arbitrator would leave in no manner
    any doubt that Arbitrator has acted well within the
    limits of terms of reference and has given sufficient
    reasons for allowing/disallowing the claims/counter-
    claims in part or full after taking into consideration
    the documents produced by both the parties as well
    as arguments advanced in support of each of the
    individual claims/counter-claims.”

    12. It is now a well established position of law that an arbitral

    award can be set aside upon being challenged only within the

    narrow confines of the grounds stipulated under Section 34 of

    the Act of 1997. Even before this Court, the appellant has

    fallen short of submissions, legal as well as factual, to

    demonstrate any such basis and grounds that would warrant

    judicial intervention from our end.

    AA No. 7/2023 Page 8 of 10

    2026:JKLHC-JMU:1626-DB

    13. In „Ramesh Kumar Jain vs. Bharat Aluminum Company

    Ltd.(Balco)‟, 2025 INSC 1457, the Hon’ble Supreme Court of

    India has held that “It is a settled proposition of law as has

    been constantly observed by this court and we reiterate, the

    courts exercising jurisdiction under section 34 do not sit in

    appeal over the arbitral award hence they are not expected to

    examine the legality, reasonableness or correctness of findings

    on facts or law unless they come under any of grounds

    mandated in the said provision.”

    14. We find ourselves in cordial and in complete agreement with

    the court of learned Principal District Judge, Udhampur that

    the appellant failed to plead and point much less prove any

    perversity and perforation in the arbitral award.

    15. The submissions made vehemently before us lack legal

    substance and sagacity and fail to align with the stringent

    statutory parameters of Section 34 of the Act of 1997.

    16. In Ramesh Kumar Jain‟s case ibid, the Hon’ble Supreme

    Court of India has reinforced that “When it comes to Section

    37 of the A&C Act, it provides for a limited appellate remedy

    against an order either setting aside or refusing to set aside an

    arbitral award passed by civil court in exercise of its power

    under section 34. This court in MMTC Ltd. v. Vedanta Ltd.15, at

    Paragraph 14 observed that interference with an order made

    AA No. 7/2023 Page 9 of 10
    2026:JKLHC-JMU:1626-DB

    under section 37 cannot travel beyond the restrictions laid

    down in section 34“.

    17. Having perused the order passed by the court of learned

    Principal District Judge, Udhampur, we find it to be well-

    reasoned and self-sustainable in law. Consequently, we find

    no ground to interfere.

    18. The present appeal is dismissed as misconceived, along with

    all connected applications.

    19. Amount deposited by the appellant be released in favour of

    the respondent after due verification and in accordance and

    compliance with rules.

                          (RAHUL BHARTI)                      (RAJNESH OSWAL)
                              JUDGE                                JUDGE
    Jammu
    22.05.2026
    Sahil Padha
                           Whether the order is speaking:        Yes.
                           Whether the order is reportable:      Yes.
    
    
    
    
          AA No. 7/2023                                                 Page 10 of 10
     



    Source link

    LEAVE A REPLY

    Please enter your comment!
    Please enter your name here