Rakesh Panda vs State Of Odisha And Others …. Opposite … on 20 May, 2026

    0
    34
    ADVERTISEMENT

    Orissa High Court

    Rakesh Panda vs State Of Odisha And Others …. Opposite … on 20 May, 2026

    Author: Murahari Sri Raman

    Bench: Murahari Sri Raman

       IN THE HIGH COURT OF ORISSA AT CUTTACK
    
                           W.P.(C). No. 7003 of 2026
    
    
    Rakesh Panda                                      ....                  Petitioner
    
                                        -Versus-
    State of Odisha and others                        ....         Opposite Parties
    
    
       Advocates appeared in this case:
          For Petitioner                :   Mr. Prafulla Kumar Rath,
                                            Sr. Advocate       assisted by
                                            Mr. Saibrata Rath, Advocate
    
          For Opposite Parties          :   Ms. Aishwarya Dash,
                                            Addl. Standing Counsel
    
    
                                     CORAM:
    
                HON' BLE THE CHIEF JUSTICE
                            AND
          HON'BLE MR. JUSTICE MURAHARI SRI RAMAN
    
                                JUDGMENT
    

    ———————————————————————————-

    Date of Judgment: 20th May, 2026

    SPONSORED

    ———————————————————————————-
    HARISH TANDON, CJ.

    1. The dispute raised in the instant writ petition is within the

    limited compass, more particularly on the mathematical calculation

    on the basis of a formula given in the tender document relating to

    W.P.(C) No.7003 of 2026 Page 1 of 14
    bid capacity. Both the petitioner as well as the State has submitted

    the calculation on the basis of such formula which is at variance.

    There is no dispute to the applicability of the formula provided in

    the said tender document for ascertaining the bid capacity and,

    therefore, the instant writ petition can be decided on the basis of the

    undisputed facts discerned from the record.

    2. In order to address the issue as stated hereinabove, the facts

    which led the foundation of the genesis thereof is adumbrated

    hereinafter.

    3. The petitioner is an „A‟ Class Contractor registered with

    Public Works Department, Government of Odisha and participated

    in the tender pursuant to Tender Call Notice vie e-procurement

    notice No. 3781 dated 23.10.2025 for 33 road works in the district

    of Balasore and Bhadrak. At the time of floating the Tender Call

    Notice, the last date of submission of the bid was fixed to 15 th

    November 2025, but subsequently by 1st corrigendum dated 4th

    November, 2025 the same was extended up to 24th November, 2025

    and was further extended by 2nd corrigendum dated 21st November,

    2025 up to 8th December, 2025. The petitioner along with opposite

    party no.7 submitted the bid within the said extended time and

    W.P.(C) No.7003 of 2026 Page 2 of 14
    technical bid was opened on 9th December, 2025. The tender

    summary report and technical evaluation summary dated 7 th

    February, 2026 reveals that 7 bidders including the petitioner and

    opposite party no.7 were found technically qualified and the

    financial bid was opened on 12th February, 2026 and opposite party

    no.7 was declared as L1 by quoting 14.99 % less than the estimated

    cost. The petitioner subsequently came to know that bid capacity of

    opposite party no.7 has been wrongly calculated by applying the

    formula and, therefore, challenged the declaration of opposite party

    no.7 as L1.

    4. Clause- 2.1 (7) of the General Instructions to Tenderers

    contained the exhaustive mechanism in ascertaining the bid

    capacity of each intending bidder on the basis of a formula

    provided therein. In order to avoid any ambiguity, the said Clause

    is quoted as under:

    “2.1 (7) Bid Capacity (As per Works Department L.No 6300
    Dtd 16.6.2011. Bid capacity clause as qualification criteria has
    been included). These stipulations shall apply to all works
    above Rs 3.00 Crores)
    Applicants who meet the minimum qualification criteria will
    be qualified only if their available bid capacity at the
    expected time of bidding is more than the total estimated
    cost of the works. The available bid capacity will be
    calculated as under:

    Assessed Available Bid Capacity= (A*N*2-B) where

    W.P.(C) No.7003 of 2026 Page 3 of 14
    A= Maximum value of Civil Engineering works executed in
    any one year during the last five years (updated to the
    current price level) rate of inflation may be taken as 10
    percent per year (escalation factor) which will make in to
    account the completed as well as works in progress.

    B= Value of current price level of the existing commitments
    & ongoing works to be completed during the next years
    (period of completion of works for which bids are invited).
    The information for the value of B need to be furnished in
    Format -II.

    N= Number of years prescribed for completion of the works
    for which the bids are invited. (For work completion period
    less than one year the value may be taken as one year)

    The statement showing the value of existing commitments & on-
    going works as well as stipulated period of completion
    remaining for each of the works listed should be duly signed by
    the bidders only.”

    5. The entire stand of the petitioner in relation to the

    aforementioned Clause is vividly and explicitly pleaded in

    paragraphs-8 to 11 of the writ petition. It is the specific stand of the

    petitioner that said opposite party no.7 disclosed the existing

    ongoing works valued at Rs.210.00 Lakhs which in fact has been

    taken by the authority while ascertaining the bid capacity.

    According to the petitioner, the opposite party no.7 was further

    awarded contracts for an amount of Rs. 3,48,38,115/- and the letter

    of acceptance was issued on 17th January, 2026 and for

    Rs.7,00,39,847 on the basis of the letter of acceptance dated 7th

    February, 2026 and, therefore, the authorities while evaluating the

    W.P.(C) No.7003 of 2026 Page 4 of 14
    bids at the technical bid stage ought to have taken into

    consideration the same and if those figures are taken into account, it

    would bring a negative bid capacity of the opposite party no.7,

    which is not in conformity with Clause 2.1 (7) of the Detailed

    Tender Call Notice.

    6. On the other hand, the State has taken a stand that the

    authorities have correctly calculated the bid capacity on the basis of

    the formula provided in the said clause and found the bid capacity

    higher than the required bid capacity in relation to the work

    awarded to opposite party no.7

    7. Before we proceed on such factual matrix, the law relating

    to interference by the Writ Court in relation to a government

    contract or a tender matter is required to be recapitulated.

    8. In Vidarbha Irrigation Development Corporation and

    others v Anoj Kumar Agarwala and others, reported in (2020) 17

    SCC 577 the apex Court reiterated and restated the principles that

    the author of the tender document is the best person to give a

    meaning to the expressions or words used therein in the following:

    W.P.(C) No.7003 of 2026 Page 5 of 14

    “15. However, the learned counsel appearing on behalf of the
    appellant strongly relied upon Afcons Infrastructure
    Ltd. v. Nagpur Metro Rail Corpn. Ltd. [Afcons Infrastructure
    Ltd.
    v. Nagpur Metro Rail Corpn. Ltd., (2016) 16 SCC 818] ,
    and paras 14 and 15 in particular, which state: (SCC p. 825)
    “14.
    We must reiterate the words of caution that this
    Court has stated right from the time when Ramana Dayaram
    Shetty v. International Airport Authority of India [Ramana
    Dayaram Shetty
    v. International Airport Authority of India,
    (1979) 3 SCC 489] was decided almost 40 years ago, namely,
    that the words used in the tender documents cannot be
    ignored or treated as redundant or superfluous — they must
    be given meaning and their necessary significance. In this
    context, the use of the word “metro” in Clause 4.2(a) of
    Section III of the bid documents and its connotation in
    ordinary parlance cannot be overlooked.

    15. We may add that the owner or the employer of a
    project, having authored the tender documents, is the best
    person to understand and appreciate its requirements and
    interpret its documents. The constitutional courts must defer
    to this understanding and appreciation of the tender
    documents, unless there is mala fide or perversity in the
    understanding or appreciation or in the application of the
    terms of the tender conditions. It is possible that the owner
    or employer of a project may give an interpretation to the
    tender documents that is not acceptable to the constitutional
    courts but that by itself is not a reason for interfering with
    the interpretation given.”

    It is further held therein that the moment the essential conditions

    are incorporated in the tender document, those should be given

    credence and its strict compliance should be ensured by the

    tendering authority in the following:

    “16. It is clear even on a reading of this judgment that the
    words used in the tender document cannot be ignored or treated
    as redundant or superfluous–they must be given meaning and
    their necessary significance. Given the fact that in the present
    case, an essential tender condition which had to be strictly
    complied with was not so complied with, the appellant would

    W.P.(C) No.7003 of 2026 Page 6 of 14
    have no power to condone lack of such strict compliance. Any
    such condonation, as has been done in the present case, would
    amount to perversity in the understanding or appreciation of the
    terms of the tender conditions, which must be interfered with by
    a constitutional court.”

    9. In Agmatel India Private Limited v. Resoursys Telecom

    and others, reported in (2022) 5 SCC 362, the apex Court had an

    occasion to consider the scope of judicial review in contract

    matters, more particularly in relation to the interpretation of tender

    document and held that the authority who has drafted or is the

    author of the tender document is the most suited person to

    understand and appreciate the meaning of the “words” and

    “expressions” as well as “clauses” incorporated therein, in

    juxtaposition with the object sought to be achieved and the Court

    should not ordinarily interfere in this regard. Even if the Court finds

    that the interpretation given by the maker of the tender document is

    not acceptable that itself cannot be a ground to discard the same, in

    the following:

    “25. This Court referred to various decisions on the subject
    and stated the legal principles as follows : (Galaxy Transport
    Agencies case [Galaxy Transport Agencies v. New J.K.
    Roadways, Fleet Owners & Transport Contractors
    , (2021) 16
    SCC 808 : 2020 SCC OnLine SC 1035] , SCC paras 14-20)
    “14. In a series of judgments, this Court has held that the
    authority that authors the tender document is the best person
    to understand and appreciate its requirements, and thus, its
    interpretation should not be second-guessed by a court in
    judicial review proceedings.
    In Afcons Infrastructure

    W.P.(C) No.7003 of 2026 Page 7 of 14
    Ltd. v. Nagpur Metro Rail Corpn. Ltd. [Afcons Infrastructure
    Ltd.
    v. Nagpur Metro Rail Corpn. Ltd., (2016) 16 SCC 818] ,
    this Court held : (SCC p. 825, para 15)
    „15. We may add that the owner or the employer of a
    project, having authored the tender documents, is the best
    person to understand and appreciate its requirements and
    interpret its documents. The constitutional courts must defer to
    this understanding and appreciation of the tender documents,
    unless there is mala fide or perversity in the understanding or
    appreciation or in the application of the terms of the tender
    conditions. It is possible that the owner or employer of a
    project may give an interpretation to the tender documents that
    is not acceptable to the constitutional courts but that by itself is
    not a reason for interfering with the interpretation given.‟

    15. In the judgment in Bharat Coking Coal Ltd. v. AMR Dev
    Prabha [Bharat Coking Coal Ltd.
    v. AMR Dev Prabha, (2020)
    16 SCC 759] , under the heading “Deference to authority’s
    interpretation”, this Court stated : (SCC p. 776, paras 50-52)
    „50. Lastly, we deem it necessary to deal with another
    fundamental problem. It is obvious that Respondent 1 seeks to
    only enforce terms of NIT. Inherent in such exercise is
    interpretation of contractual terms. However, it must be noted
    that judicial interpretation of contracts in the sphere of
    commerce stands on a distinct footing than while interpreting
    statutes.

    51. In the present facts, it is clear that BCCL and C1-India
    have laid recourse to clauses of NIT, whether it be to justify
    condonation of delay of Respondent 6 in submitting
    performance bank guarantees or their decision to resume auction
    on grounds of technical failure. BCCL having authored these
    documents, is better placed to appreciate their requirements and
    interpret them. [Afcons Infrastructure Ltd. v. Nagpur Metro Rail
    Corpn. Ltd.
    , (2016) 16 SCC 818]

    52. The High Court ought to have deferred to this
    understanding, unless it was patently perverse or mala fide.
    Given how BCCL’s interpretation of these clauses was plausible
    and not absurd, solely differences in opinion of contractual
    interpretation ought not to have been grounds for the High Court
    to come to a finding that the appellant committed illegality.‟

    16. Further, in the recent judgment in Silppi Constructions
    Contractors v. Union of India [Silppi Constructions
    Contractors v. Union of India, (2020) 16 SCC 489] , this Court
    held as follows : (SCC pp. 501-02, para 20)
    „20. The essence of the law laid down in the judgments
    referred to above is the exercise of restraint and caution; the
    need for overwhelming public interest to justify judicial

    W.P.(C) No.7003 of 2026 Page 8 of 14
    intervention in matters of contract involving the state
    instrumentalities; the courts should give way to the opinion of
    the experts unless the decision is totally arbitrary or
    unreasonable; the court does not sit like a court of appeal over
    the appropriate authority; the court must realise that the
    authority floating the tender is the best judge of its requirements
    and, therefore, the court’s interference should be minimal. The
    authority which floats the contract or tender, and has authored
    the tender documents is the best judge as to how the documents
    have to be interpreted. If two interpretations are possible then
    the interpretation of the author must be accepted. The courts
    will only interfere to prevent arbitrariness, irrationality, bias,
    mala fides or perversity. With this approach in mind we shall
    deal with the present case.‟

    17. In accordance with these judgments and noting that the
    interpretation of the tendering authority in this case cannot be
    said to be a perverse one, the Division Bench ought not to have
    interfered with it by giving its own interpretation and not giving
    proper credence to the word “both” appearing in Condition No.
    31 of the NIT For this reason, the Division Bench’s conclusion
    [New JK Roadways v. State (UT of J&K), 2020 SCC OnLine
    J&K 733] that JK Roadways was wrongly declared to be
    ineligible, is set aside.

    18. Insofar as Condition No. 27 of the NIT prescribing work
    experience of at least 5 years of not less than the value of Rs 2
    crores is concerned, suffice it to say that the expert body, being
    the Tender Opening Committee, consisting of four members,
    clearly found that this eligibility condition had been satisfied by
    the appellant before us. Without therefore going into the
    assessment of the documents that have been supplied to this
    Court, it is well settled that unless arbitrariness or mala fide on
    the part of the tendering authority is alleged, the expert
    evaluation of a particular tender, particularly when it comes to
    technical evaluation, is not to be second-guessed by a writ
    court. Thus, in Jagdish Mandal v. State of Orissa [Jagdish
    Mandal v. State of Orissa, (2007) 14 SCC 517] , this Court
    noted : (SCC pp. 531-32, para 22)
    „22. Judicial review of administrative action is intended to
    prevent arbitrariness, irrationality, unreasonableness, bias and
    mala fides. Its purpose is to check whether choice or decision is
    made “lawfully” and not to check whether choice or decision is
    “sound”. When the power of judicial review is invoked in
    matters relating to tenders or award of contracts, certain special
    features should be borne in mind. A contract is a commercial
    transaction. Evaluating tenders and awarding contracts are
    essentially commercial functions. Principles of equity and
    natural justice stay at a distance. If the decision relating to

    W.P.(C) No.7003 of 2026 Page 9 of 14
    award of contract is bona fide and is in public interest, courts
    will not, in exercise of power of judicial review, interfere even if
    a procedural aberration or error in assessment or prejudice to a
    tenderer, is made out. The power of judicial review will not be
    permitted to be invoked to protect private interest at the cost of
    public interest, or to decide contractual disputes. The tenderer
    or contractor with a grievance can always seek damages in a
    civil court. Attempts by unsuccessful tenderers with imaginary
    grievances, wounded pride and business rivalry, to make
    mountains out of molehills of some technical/procedural
    violation or some prejudice to self, and persuade courts to
    interfere by exercising power of judicial review, should be
    resisted. Such interferences, either interim or final, may hold up
    public works for years, or delay relief and succour to thousands
    and millions and may increase the project cost manifold.
    Therefore, a court before interfering in tender or contractual
    matters in exercise of power of judicial review, should pose to
    itself the following questions:

    (i) Whether the process adopted or decision made by the
    authority is mala fide or intended to favour someone;

    OR
    Whether the process adopted or decision made is so arbitrary
    and irrational that the court can say:”the decision is such that no
    responsible authority acting reasonably and in accordance with
    relevant law could have reached”;

    (ii) Whether public interest is affected.

    If the answers are in the negative, there should be no
    interference under Article 226. Cases involving blacklisting or
    imposition of penal consequences on a tenderer/contractor or
    distribution of State largesse (allotment of sites/shops, grant of
    licences, dealerships and franchises) stand on a different footing
    as they may require a higher degree of fairness in action.‟

    19. Similarly, in Montecarlo Ltd. v. NTPC Ltd. [Montecarlo
    Ltd.
    v. NTPC Ltd., (2016) 15 SCC 272] , this Court stated as
    follows : (SCC p. 288, para 26)
    „26. We respectfully concur with the aforesaid statement of
    law. We have reasons to do so. In the present scenario, tenders
    are floated and offers are invited for highly complex technical
    subjects. It requires understanding and appreciation of the nature
    of work and the purpose it is going to serve. It is common
    knowledge in the competitive commercial field that technical
    bids pursuant to the notice inviting tenders are scrutinised by the
    technical experts and sometimes third-party assistance from
    those unconnected with the owner’s organisation is taken. This
    ensures objectivity. Bidder’s expertise and technical capability
    and capacity must be assessed by the experts. In the matters of

    W.P.(C) No.7003 of 2026 Page 10 of 14
    financial assessment, consultants are appointed. It is because to
    check and ascertain that technical ability and the financial
    feasibility have sanguinity and are workable and realistic. There
    is a multi-prong complex approach; highly technical in nature.
    The tenders where public largesse is put to auction stand on a
    different compartment. Tender with which we are concerned, is
    not comparable to any scheme for allotment. This arena which
    we have referred requires technical expertise. Parameters
    applied are different. Its aim is to achieve high degree of
    perfection in execution and adherence to the time schedule. But,
    that does not mean, these tenders will escape scrutiny of judicial
    review. Exercise of power of judicial review would be called for
    if the approach is arbitrary or mala fide or procedure adopted is
    meant to favour one. The decision-making process should
    clearly show that the said maladies are kept at bay. But where a
    decision is taken that is manifestly in consonance with the
    language of the tender document or subserves the purpose for
    which the tender is floated, the Court should follow the
    principle of restraint. Technical evaluation or comparison by
    the Court would be impermissible. The principle that is applied
    to scan and understand an ordinary instrument relatable to
    contract in other spheres has to be treated differently than
    interpreting and appreciating tender documents relating to
    technical works and projects requiring special skills. The owner
    should be allowed to carry out the purpose and there has to be
    allowance of free play in the joints.‟

    20. This being the case, we are unable to fathom how the
    Division Bench, on its own appraisal, arrived at the conclusion
    that the appellant held work experience of only 1 year,
    substituting the appraisal of the expert four-member Tender
    Opening Committee with its own.”

    (italicised matter emphasised in the original;

    emphasis in bold italics supplied)

    10. In Vedika Resources v. National Aluminium Company

    Ltd. reported in 2025 SCC OnLine Ori 4148, this Bench had an

    occasion to consider the similar aspect when the parties were at

    variance in interpreting the words used in the tender document. It

    was held that every words and expressions which are used in the

    W.P.(C) No.7003 of 2026 Page 11 of 14
    tender document carries a meaning and/or significance as the author

    shall not use any words or expressions which are either redundant

    or surplusage and, therefore, the interference by the Writ Court is

    minimal.

    11. The law enunciated in the above reports have laid down a

    uniform principle relating to the interpretation of the tender

    document to the effect that the Court must accept the interpretation

    given by the draftsman/author of the said tender document to the

    words and the expressions used therein if they do not frustrate the

    purpose for which the tender is floated. The writ Court should not

    substitute its own interpretation unless the interpretation given by

    the author of the tender document is unreasonable, irrationally and

    beyond comprehension in the ordinary circumstances. The Writ

    Court should be slow and circumspect in interfering on the premise

    of giving a meaning to a tender document if those appears to be

    clear and unambiguous and used to subserve the purpose for which

    the tender is floated.

    12. Reverting to the merit of the said case, the said clause 2.1

    (7) relating to a bid capacity, appears to have been understood by

    the petitioner and the State authorities in the different manner. The

    W.P.(C) No.7003 of 2026 Page 12 of 14
    dispute, in effect, hovers around the value to be given to “Be”,

    which is relatable to the existing commitments & on-going works

    to be completed during the next year. The petitioner has taken into

    account even the works subsequently awarded and/or allotted to the

    opposite party no.7 after the last date of submission of the bid,

    whereas the authorities have taken the value of the existing work as

    disclosed by opposite party no.7 in its bid document. The

    contention of the petitioner is unacceptable for the reason that the

    said clause mandates the bid capacity to be ascertained at the

    expected time of bidding. It further postulates that the said bid

    capacity must be more than the total estimated cost of the work.

    The expressions “available bid capacity at the expected time of

    bidding” has to be understood as the capacity of a bidder as on the

    last date of submission of the bid. If any work awarded subsequent

    to the last date of submission of the bid is taken into consideration,

    it would frustrate the purpose of an expression “expected time of

    bidding”. The intending contractors bids on or before the last date

    of the submission and, therefore, the capacity has to be evaluated

    on the said date and not the date posterior thereto.

    W.P.(C) No.7003 of 2026 Page 13 of 14

    13. The opposite party no.7 was awarded a work valued at Rs.

    7,00,39,847/- on 7th February, 2026 and Rs.3,48,38,115/- on 17th

    January, 2026, much after the last date of submission of the bid

    and, therefore, the contention of the petitioner with regard to

    inclusion of the said work as an ongoing work by the petitioner is

    unacceptable and, therefore, the relief claimed in the instant writ

    petition cannot be granted. Accordingly the writ petition sans merit

    and the same is, therefore, dismissed.

    (Harish Tandon)
    Chief Justice

    (M.S. Raman)
    Judge

    Arun Mishra

    Signature Not Verified
    Digitally Signed
    Signed by: ARUN KUMAR MISHRA
    Designation: ADR-cum-Addl. Principal Secretary
    Reason: Authentication
    Location: High Court of Orissa, Cuttack
    Date: 20-May-2026 19:01:26

    W.P.(C) No.7003 of 2026 Page 14 of 14



    Source link

    LEAVE A REPLY

    Please enter your comment!
    Please enter your name here