Binodini Infrastructure Pvt. Ltd vs State Of Odisha on 20 May, 2026

    0
    18
    ADVERTISEMENT

    Orissa High Court

    Binodini Infrastructure Pvt. Ltd vs State Of Odisha on 20 May, 2026

                   ORISSA HIGH COURT : CUTTACK
    
                        W.P.(C) No.8589 of 2024
    
         In the matter of an Application under Articles 226 & 227
                    of the Constitution of India, 1950.
    
                                  ***
    

    Binodini Infrastructure Pvt. Ltd.

    Registered Office
    At: Bahadurbagichapada
    Bhawanipatna
    District: Kalahandi, Odisha
    Represented through
    Managing Director
    (Being authorized by Board of Directors)
    Sri Pradipta Kumar Singh
    Aged about 48 years
    Son of Late Nrusingha Charan Singh
    At: Bahadurbagichapada
    P.O./P.S.: Bhawanipatna
    District: Kalahandi, Odisha. … Petitioner

    SPONSORED

    -VERSUS-

    1. State of Odisha
    Represented through
    Commissioner-cum- Secretary
    Work Department, State Secretariat
    Bhubaneswar, District: Khurda.

    2. F.A.-cum-Special Secretary to Government
    Works Department, Government of Odisha
    State Secretariat, Bhubaneswar.

    W.P.(C) No.8589 of 2024 Page 1 of 89

    3. Engineer-in-Chief (Civil), Odisha
    Bhubaneswar, District: Khordha.

    4. Chief Engineer
    Bridge World Bank Project, Odisha
    Bhubaneswar, District: Khordha.

    5. Chief Engineer, (DPI & Roads)
    Works Department, Odisha
    Bhubaneswar, District: Khordha.

    6. Chief Construction Engineer
    Jeypore (R & B ) Circle, Jeypore

    7. Superintending Engineer
    Malkanagiri (R & B) Division
    Malkangiri. … Opposite Parties.

    Advocates appeared in this case:

    For the Petitioner : M/s. Prabodha Chandra Nayak,
    S.K. Sahoo, Advocates

    For the Opposite Parties : Mr. Saswat Das,
    Additional Government Advocate

    P R E S E N T:

    HONOURABLE CHIEF JUSTICE
    MR. HARISH TANDON

    AND

    HONOURABLE JUSTICE
    MR. MURAHARI SRI RAMAN

    Date of Hearing : 06.05.2026 :: Date of Judgment : 20.05.2026

    J UDG MENT

    W.P.(C) No.8589 of 2024 Page 2 of 89
    MURAHARI SRI RAMAN, J.–

    The petitioner, craving to question the propriety and
    legality of order dated 30.03.2024 passed by the Chief
    Engineer, Bridges (WBP), Odisha, blacklisting the
    company for six years for having failed to achieve the
    desired milestones as per agreement and complete the
    works entrusted within period stipulated in terms of
    conditions of contract, beseeches exercise of power
    conferred on this Court under the provisions of Articles
    226
    and 227 of the Constitution of India for grant of
    following relief(s):

    “It is therefore prayed that this Hon‟ble Court may be
    graciously pleased to issue rule NISI in the nature of any
    appropriate writ/writs and/or any other writ/writs
    and/or order/orders and/or direction/directions calling
    upon the opposite parties to show cause as to why:

    (i) The impugned order No.14974, dated 30.03.2024
    under Annexure-1, passed by the opposite party
    No.4 in blacklisting and debarring the petitioner to
    participate in any tender for six years without
    following due procedure shall not be declared illegal,
    arbitrary and same shall not be quashed.

    (ii) The action and decision of the opposite party No.4
    under Annexure-1 in blacklisting the petitioner shall
    not be declared illegal, arbitrary, unreasonable and
    violative of Article 14 and 19(1)(g) of the Constitution
    of India;

    W.P.(C) No.8589 of 2024 Page 3 of 89

    And may pass such other order(s)/direction(s) as this
    Hon‟ble Court deems just and proper;

    And for this act of kindness, the petitioner shall as in duty
    bound ever pray.”

    Facts:

    2. The present case emanates from two work orders,
    namely:

    i. “Construction of H.L. Bridge over river Saberi, at
    16/000 km of Mathili-Kaliguda road in Malkangiri
    district” with stipulation to commence on
    27.12.2017 and complete on 26.06.2019 vide
    Agreement No.45P-1/2017-18 (hereinafter be
    referred to as “Work No.1”).

    ii. Bid identification No.58/2016-17 for the work
    “Construction of H.L. Bridge over river Satpadhara,
    at km 2/000 of Govindapalli-Kamalapadar-
    Gajaguda road in Malkangiri district under State
    Plan” with stipulation to commence on 28.11.2017
    and complete on 27.02.2019 vide Agreement
    No.33P-1/2017-18 (hereinafter be referred to as
    “Work No.2”).

    2.1. Due to unforeseen circumstances, the petitioner could
    not complete the Work No.2 in time and upon
    consideration of request, extension of time was allowed
    up to 30.06.2020. Yet no substantial work being shown
    W.P.(C) No.8589 of 2024 Page 4 of 89
    to have been progressed, vide Letter No.3079, dated
    25.06.2021 issued by the Executive Engineer,
    Malkangiri (R&B) Division while granting period to
    complete the work by 31.03.2022, the petitioner was
    instructed to show cause failing which action would be
    initiated for rescission of the agreement.

    2.2. After furnishing replies eliciting the difficulties faced by
    the petitioner and it is brought to the notice of the Chief
    Engineer (World Bank Projects), Bhubaneswar by Letter
    dated 10.05.2023 that though super structure drawing
    was approved in Directorate of Design on 30.11.2022,
    the same was not communicated to the petitioner. In the
    said letter the authority was requested to allow the
    petitioner to execute the balance work and release the
    escalation cost up to 30.06.2020. Notwithstanding such
    reply, the Works Department intimated the Chief
    Engineer, World Bank Projects regarding approval of
    rescission proposal of contract in terms of Clause 2(b)(i)1
    of Agreement No.33P1 of 2017-18. Consequent upon
    such communication, an Office Order dated 23.08.2023
    was issued by the Superintending Engineer, Malkangiri
    (R&B) Division which reads as follows:

    “The contract bearing No.33P1/2017-18 for the work
    „Construction of HL Bridge over river Saptadhara at km

    1 “To rescind the contract (of which rescission notice in writing to the contractor
    under the hand of the Executive Engineer shall be conclusive evidence) 20% of the
    value of left-over work will be realized from the contractor as penalty.”

    W.P.(C) No.8589 of 2024 Page 5 of 89

    2/0 of Govindapalli-Kamalapadar-Gajiaguda road in
    Malkangiri District under State Plan‟ has been rescinded
    under Clause 2b(i) of the said P1 Agreement executed by
    Binodini Infrastructure Pvt. Ltd. „Super‟ Class Contractor
    vide Letter No.33086, dated 10.08.2023 of Chief Engineer
    (World Bank Projects), Odisha, Bhubaneswar.”

    2.3. Assailing such order of rescission of contract with
    respect to Work No.2, the petitioner approached this
    Court by way of filing an application registered as
    W.P.(C) No.31693 of 2023, wherein vide order dated
    29.09.2023 notice was issued and the matter was
    directed to be listed along with W.P.(C) No.29863 of 2023
    which related to Work No.1.

    2.4. While the matter was sub judice, two show cause notices
    on 18.10.2023 were issued with respect to above both
    the works.

    2.5. Show Cause Notice vide Letter No.C-II-MLK-05/2016–

    44375, dated 18.10.2023 with respect to Work No.1 was
    issued indicating as follows:

    “Please take notice that you have been entrusted with the
    work „Construction of H.L Bridge over river Saberi at
    16.000 Km. of Mathili-Kaliaguda road in the district of
    Malkangiri under state plan vide Agreement No.45-P1 of
    2017-18 of the Executive Engineer, Malkangiri (R&B)
    Division, Malkangiri with the date of commencement as
    27.12.2017 and stipulated date of completion as
    26.06.2019. You have not completed the said work till

    W.P.(C) No.8589 of 2024 Page 6 of 89
    rescission of contract by the Government in Works
    Department vide Letter No.13148, dated 08.08.2023.

    ***

    Further on the final notice of the Superintending Engineer,
    Malkangiri (R&B) Division vide Letter No.3139, dated
    30.06.2021 where he has stated that on his inspection to
    bridge site, no men and machineries were found in
    execution of the bridge project and he has again
    requested you to gear up the work in a war footing basis
    by engaging sufficient men and machineries with
    maximum working hour to complete back log quantities of
    the work by 31.03.2022 otherwise suitable action as per
    relevant clauses of the agreement will be initiated for
    rescission of the agreement. But no such initiative was
    found to be taken by you. Hence, it is apprehended that
    due to your such type of apathetic attitude and deliberate
    negligence the above work couldn‟t have been completed
    till date and could not be put to use of General Public.

    In view of the above factual matrix, you are hereby
    directed to submit your explanation within 15 days from
    the date of issue of this show cause notice why suitable
    action shall not be taken by the undersigned under
    Appendix-XXXIV of Odisha Public Works Department
    Code, Volume-II and under Clause No.121 of the DTCN,
    failing which it is to be deemed that you have nothing to
    reply against this show cause and accordingly the action
    as deemed proper will be processed against you without
    any further intimation.”

    2.6. Show Cause Notice vide Letter No.C-II-MLK-05/2016–

    44374, dated 18.10.2023 with respect to Work No.2 was
    issued indicating as follows:

    W.P.(C) No.8589 of 2024 Page 7 of 89

    “Please take notice that you have been entrusted with the
    work „Construction of HL Bridge over river Saptadhara at
    2.00km of Govindapalli-Kamalapadar-Gujiaguda road in
    the district of Malkangiri under State plan vide Agreement
    No.33P1 of 2017-18 executed by the Executive Engineer,
    Malkangiri (R&B) Division, Malkangiri with the date of
    commencement as 28.11.2017 and stipulated date of
    completion as 27.02.2019. You have not completed the
    said work till rescission of contract by the Government in
    Works Department vide Letter No.13147, dated
    08.08.2023.

    ***

    Though you have been allowed with the extension of time
    up to 30.06.2020 vide Government in Works Department
    Letter No.6805, dated 03.06.2020, the bridge work could
    not be completed within the extended period also. The
    Superintending Engineer, Malkangiri (R&B) Division vide
    Letter No.3842, dated 26.08.2020 issued another show
    cause notice to you regarding slow progress of work.
    Neither you have expedited the work nor you have
    applied for further extension of time to complete the said
    work.

    ***

    The Superintending Engineer, Malkanglri (R&B) Division
    issued final notice vide Letter No.357, dated 25.01.2021
    to you with a request to execute the back log quantities of
    the work by engaging sufficient men and machineries
    with maximum working hours as well as to achieve the
    target for completion of the above project otherwise
    suitable action as per relevant clauses of the agreement
    will be initiated for rescission of the agreement. It proves
    that due to your lack of interest and deliberate negligence

    W.P.(C) No.8589 of 2024 Page 8 of 89
    the above work couldn‟t be completed till date and could
    not be put to use of General Public.

    In view of the above factual matrix, you are hereby
    directed to submit your explanation within 15 days from
    the date of issue of this show cause notice why suitable
    action shall not be taken by the undersigned under
    Appendix-XXXIV of Odisha Public Works Department
    Code, Volume-II and under Clause No.121 of the DTCN,
    failing which it is to be deemed that you have nothing to
    reply against this show cause and accordingly the action
    as deemed proper will be processed against you without
    any further intimation.”

    2.7. Imposing penalty of Rs.74,96,518/- with respect to Work
    No.2 a demand has been raised vide Letter No.4815,
    dated 26.10.2023 by the Superintending Engineer,
    Malkangiri (R&B) Division with instruction to deposit
    balance penalty to the tune of Rs.10,52,210/- after
    adjustment of amounts due on account of earnest
    money deposit, initial security deposit, security deposit,
    withheld for extension of time and value of work
    executed as per final/joint measurement for payment.

    2.8. By Letter Nos.BIPL/283/2023-24 (Work No.1) and
    BIPL/282/2023-24 (Work No.2), dated 23.10.2023 citing
    pendency of writ petitions being W.P.(C) No.29863 of
    2023 and W.P.(C) No.31693 of 2023 the petitioner
    objected to steps taken for blacklisting/debarring
    exercising power under Appendix-XXXIV of the Odisha
    Public Works Department Code, Volume-II (“OPWD

    W.P.(C) No.8589 of 2024 Page 9 of 89
    Code”, for brevity) read with Clause No.121 of the DTCN.
    An affidavit dated 29.01.2024 was filed in W.P.(C)
    No.31693 of 2023 before this Court with the following
    undertaking:

    “That the petitioner files this affidavit with undertaking to
    complete the balance work, i.e., Construction of HL Bridge
    over river Saptadhara at km 2/000 of Govindpalli-
    Kamalapadar-Gajiaguda road in Malkangiri district under
    State plan within a period of 8 months from the date of
    order in terms of agreement and will not claim escalation
    for the said period.”

    2.9. The writ petition being W.P.(C) No.29863 of 2023
    (relating to Work No.1) came to be disposed of on
    01.03.2024 with the following observation:

    “4. In the additional affidavit filed by the petitioner
    dated 02.02.2024, at paragraph-3 the petitioner has
    stated as follows:

    „3. That, the petitioner files this present Affidavit
    with an undertaking to complete the remaining
    portion of the work “Construction of H.L. Bridge
    over river Saberi at 16/000 of Mathili-Kaliguda
    Road in Malkangiri district under State Plan”

    within a stipulated period of eight (8) months
    from the date of order in terms of agreement
    and hence shall not claim escalation for the
    said period.

    ***

    6. In view of the above, this writ petition stands
    disposed of directing the opposite parties to
    W.P.(C) No.8589 of 2024 Page 10 of 89
    permit the petitioner to complete the work
    within the period of eight months as indicated
    in paragraph-3 of the affidavit dated
    02.02.2024.”

    2.10. Assailing the order dated 01.03.2024, the State of
    Odisha moved the Hon’ble Supreme Court of India in
    S.L.P.(Civil) No.14142 of 2024 [Civil Appeal No.7085 of
    2025], wherein the following order was passed on
    14.05.2025:

    “Leave granted.

    The issue involved in the present appeal is covered by the
    decision in State of Odisha & Ors. Vrs. Binodini
    Infrastructure Pvt. Ltd.-[Civil Appeal No.5228 of 2025]2
    dated 15.04.2025, wherein the following order was
    passed:

    „After hearing learned counsel appearing for the parties,
    we find that the directions as contained in paragraph 3 of
    the impugned order could not possibly have been issued
    by the High Court as the same would fall in the domain of
    re-writing the terms of contract. The challenge before the
    High Court in the Writ Petition was to an order vide which
    the contract granted to the respondent was rescinded.
    The High Court had travelled beyond the prayer made in
    the Writ Petition. Instead of going through the validity of
    the order impugned, the High Court granted further time
    to the respondent to complete the contract, which was not

    2 Vide Special Leave to Appeal (C) No(s). 1479 of 2025 [Arising out of order dated
    12.01.2024 in WP(C) No.37679 of 2023 passed by the High Court of Orissa at
    Cuttack in the case of Binodini Infrastructre Pvt. Ltd., Kalahandi Vrs. State of
    Odisha].

    W.P.(C) No.8589 of 2024 Page 11 of 89

    within the domain of the High Court in exercise of the
    power under Article 226 of the Constitution of India.

    For the reasons mentioned above, the impugned order
    passed by the High Court is set aside. However, the legal
    issues raised by the appellant in the Writ Petition having
    not been gone into by the High Court, we remit the matter
    to the High Court for examination thereof. All the
    arguments by both the parties are left open.‟

    In view of the above order, the impugned order stands set
    aside and the matter stands remitted to the High Court,
    for examination of the issues therein.

    The appeal stands allowed accordingly.”

    2.11. So far as writ petition being W.P.(C) No.31693 of 2023
    relating to Work No.2 is concerned, counter affidavit has
    been filed by the opposite parties, copy of which was
    served on the counsel for the petitioner on 11.03.2024.

    2.12. Thus, both the writ petitions are now pending before this
    Court.

    2.13. It is submitted by the petitioner that the blacklisting
    order dated 30.03.2024 for six years is arbitrary and
    contrary to the Codal Provisions contained in sub-rule

    (c) of Rule A of Appendix-XXXIV of the OPWD Code read
    with Works Department Office Memorandum
    No.16131/W, dated 26.11.2021. While the writ petition,
    being W.P.(C) No.31693 of 2023 relating to Work No.2 is
    pending, the opposite parties in the counter affidavit
    filed therein took a stand that the petitioner had not
    W.P.(C) No.8589 of 2024 Page 12 of 89
    assured nor applied for extension of time seeking to
    complete the balance work of the bridge. Without taking
    cognizance of the fact that the petitioner did furnish
    affidavit before this Court showing its inclination to
    complete the Work No.2 “within eight months from the
    date of order in terms of the agreement”, such stand is
    not in consonance with the order dated 02.02.2024
    passed by this Court in the said writ petition, which
    reads as follows:

    “2. An additional affidavit dated 29.01.2024 has been
    filed by the petitioner undertaking to complete the
    work in question within a period of eight months
    from the date of order in terms of the agreement. To
    that effect, Mr. P.P. Mohanty, learned Additional
    Government Advocate for the State-Opposite Parties
    seeks time to obtain instructions.”

    2.14. Further submission is made by the petitioner that
    though this Court by order dated 01.03.2024 passed in
    W.P.(C) No.29863 of 2023 relating to Work No.1 taking
    similar affidavit furnished in the said case into
    consideration directed the opposite parties to permit the
    petitioner to complete the work within the period
    mentioned therein.

    2.15. Objecting to continuance of blacklisting order, it is
    submitted that in view of order dated 02.02.2024 passed
    by this Court in the writ petition being W.P.(C) No.31693
    of 2023 relating to Work No.2 the impugned order vide
    W.P.(C) No.8589 of 2024 Page 13 of 89
    Annexure-1 is liable to be quashed being arbitrary and
    illegal.

    Counter affidavit of the opposite parties:

    3. The Superintending Engineer having issued notices on
    very many occasions requested the petitioner to
    complete the work and thereby given opportunities to
    complete the work within the period extended. On
    inspection of the site by the authority as no men and
    machineries were found, steps were taken.

    3.1. Perceiving poor performance of the petitioner, who
    showed indifference to complete the works, the authority
    rescinded the contracts, and on receiving instruction
    from the Chief Construction Engineer, Jeypore (R&B)
    Circle in Letter No.5368, dated 13.10.2023, the Chief
    Engineer (WBP) issued Show Cause Notice Nos.44374
    and 44375, dated 18.10.2023 (Annexure-11 enclosed
    with the writ petition) contemplating action as per
    Clause 121 of the DTCN in terms of Appendix-XXXIV of
    the OPWD Code.

    3.2. It is highlighted that challenging the decision to rescind
    the contracts with respect to Work Nos.1 and 2, the
    petitioner filed writ petitions being W.P.(C) Nos.29863 of
    2023 and 31693 of 2023 and requested the authority
    concerned not to take step with respect to blacklisting.
    Nonetheless, questioning the legality of order dated
    W.P.(C) No.8589 of 2024 Page 14 of 89
    01.03.2024 passed in W.P.(C) No.29863 of 2023, the
    opposite parties approached the Hon’ble Supreme Court
    of India in SLP(C) No.14142 of 2024, wherein by order
    dated 15.07.2024 stay of operation of said order of this
    Court was granted. Nevertheless, in W.P.(C) No.31693 of
    2023 counter affidavit has been filed by the opposite
    parties.

    3.3. With technical details, it is submitted by the opposite
    parties that the petitioner could have completed the
    work within the extended period as allowed by the
    authority and thereby the ground citing non-completion
    of works within the period stipulated, as sought to be
    extended by the petitioner, has been denied. Referring to
    many Show Cause Notices issued to the petitioner
    granting liberty to accomplish the works, it is asserted
    that the petitioner remained indolent and recalcitrant. It
    is pertinent to quote the following reply found place in
    the counter affidavit:

    “12. That in reply to the averments made in Paragraph
    Nos. 07 and 08 of the writ petition, it is humbly
    submitted that due to abnormal delay in progress,
    the petitioner had been requested from time to time
    to expedite the progress of work. As on 09.07.2019,
    the petitioner had left the approach road work in
    haphazard position in which it was causing
    inconvenience to the public. So, the petitioner had
    been asked in written to complete the approach road
    work. The petitioner could have completed the work
    W.P.(C) No.8589 of 2024 Page 15 of 89
    by 27.02.2019. The petitioner failed to submit the
    testing report of test pile within stipulated period of
    completion for which further drawing could not be
    obtained from the authority concerned and also, the
    petitioner had not deployed sufficient manpower
    and machineries as required for the bridge work,
    show-cause notices were issued to the Petitioner as
    to why penal action as per Clause 2(b)(i) shall not be
    initiated against it. In spite of the Show Cause
    notices, as to why the contracts in question shall not
    be terminated for causing the delay in completing
    the work, the petitioner had neither attended at
    work site of bridge properly nor responded to the
    communication made by the Executive Engineer vide
    his Letter dated 09.07.2019 and 15.07.2019 and
    failed to complete the bridge work.

    ***

    16. That the averments made in Paragraph No.12 of the
    writ petition are disputed and denied. It is humbly
    submitted that the original time period was 15
    months (01 year 03 months) to complete the total
    bridge work. Basing on Letter dated 14.12.2021 of
    the petitioner, the petitioner had already lost more
    than 04 years since date of commencement of bridge
    work i.e. 28.11.2017, but pile integrity test and pile
    dynamic test over the river had not attended to
    complete it, in which other drawings could not be
    obtained from the authority concerned in absence of
    above report. After lapses of maximum time period,
    the petitioner had able to submit the Dynamic Test
    Report in 02 (two) phases i.e on 21.12.2021 for
    Abutment and 23.03.2022 for Piers. Basing on
    above report, the final drawing and design dated

    W.P.(C) No.8589 of 2024 Page 16 of 89
    30.11.2022 was provided to the site engineer of the
    petitioner for execution of work. Still then the
    petitioner had not started that work. From time to
    time the petitioner had been reminded to start the
    work otherwise suitable action will be initiated for
    rescission of the agreement.”

    3.4. The opposite parties stuck to the action taken by the
    opposite parties and sought for dismissal of the writ
    petition.

    Hearing:

    4. As the blacklisting order poses “civil death” of the
    petitioner’s business activities and the same debars it
    from participating in tenders, urgency in the matter
    being shown, the matter is taken up for hearing.

    4.1. The pleadings being completed, heard Sri Prabodha
    Chandra Nayak, learned Advocate for the petitioner; Sri
    Saswat Das, learned Additional Government Advocate
    for the opposite parties. Written note of submissions has
    been filed by the counsel for respective parties on
    06.05.2026.

    4.2. Being directed to list the matter for “orders”, the matter
    being listed, the Judgment is pronounced.

    Rival contentions and submissions with written note of
    submissions:

    W.P.(C) No.8589 of 2024 Page 17 of 89

    5. With the above background of factual scenario, though
    the matters challenging propriety of decision taken for
    rescinding the works in question are pending
    adjudication, Sri Prabodha Chandra Nayak, learned
    Advocate, insisted for hearing of the matter relating to
    debarring the petitioner from participating in tenders by
    contending that where certain things are required to be
    done in certain way, the same must be done in that
    manner, but not otherwise as other methods are
    necessarily forbidden inasmuch as the authorities have
    not adhered to the Codal Provisions in proper
    perspective. He relied on following dictum in Avtar Singh
    Vrs. State of Punjab, (2023) 18 SCC 717:

    “15. It is a settled law that where a power is given to do
    a certain thing in a certain way, the thing must be
    done in that way or not at all. Other methods are
    necessarily forbidden. Reference can be made to
    Dharani Sugars & Chemicals Ltd. Vrs. Union of
    India, (2019) 5 SCC 480.”

    5.1. It is with vehemence argued that the reasons ascribed
    for the conclusion arrived at by the Chief Engineer,
    Bridges (WBP), Odisha, vide order dated 30.03.2024 to
    blacklist the petitioner are vague and incoherent with
    the grounds enshrined in Rule A of Appendix-XXXIV to
    the OPWD Code.

    5.2. It is canvassed before this Court that mere rescission of
    contracts does not contemplate step to be taken for
    W.P.(C) No.8589 of 2024 Page 18 of 89
    debarment/blacklisting the contractor under the said
    Code. The authority prior to taking a decision to
    blacklist the petitioner ought to have conducted enquiry
    and ought to make specific fact-finding that the
    ground(s) existed warranting order to be passed for
    blacklisting. Without granting reasonable, fair and
    meaningful opportunity of hearing to the petitioner the
    impugned order vide Annexure-1, being illegal,
    whimsical and arbitrary, is liable to be quashed”.

    5.3. The learned Advocate for the petitioner referred to and
    relied on the following decisions to countenance his
    argument that the authority prior to action proposed
    should mention specifically and unambiguously the
    grounds:

    i. Erusian Equipment and Chemicals Ltd. Vrs. State of
    West Bengal, (1975) 1 SCC 70, wherein it has been
    observed as follows:

    “12. Under Article 298 of the Constitution the
    executive power of the Union and the State
    shall extend to the carrying on of any trade
    and to the acquisition, holding and disposal of
    property and the making of contracts for any
    purpose. The State can carry on executive
    function by making a law or without making a
    law. The exercise of such powers and functions
    in trade by the State is subject to Part III of the
    Constitution. Article 14 speaks of equality

    W.P.(C) No.8589 of 2024 Page 19 of 89
    before the law and equal protection of the
    laws. Equality of opportunity should apply to
    matters of public contracts. The State has the
    right to trade. The State has there the duty to
    observe equality. An ordinary individual can
    choose not to deal with any person. The
    Government cannot choose to exclude persons
    by discrimination. The order of blacklisting
    has the effect of depriving a person of
    equality of opportunity in the matter of
    public contract. A person who is on the
    approved list is unable to enter into
    advantageous relations with the Government
    because of the order of blacklisting. A person
    who has been dealing with the Government in
    the matter of sale and purchase of materials
    has a legitimate interest or expectation. When
    the State acts to the prejudice of a person
    it has to be supported by legality.

    ***

    15. The blacklisting order does not pertain to any
    particular contract. The blacklisting order
    involves civil consequences. It casts a slur.
    It creates a barrier between the persons
    blacklisted and the Government in the
    matter of transactions. The blacklists are
    “instruments of coercion”.

    16. In passing an order of blacklisting the
    government department acts under what is
    described as a standardised Code. This is a
    code for internal instruction.

    ***

    W.P.(C) No.8589 of 2024 Page 20 of 89

    19. Where the State is dealing with individuals in
    transactions of sales and purchase of goods,
    the two important factors are that an individual
    is entitled to trade with the Government and an
    individual is entitled to a fair and equal
    treatment with others. A duty to act fairly
    can be interpreted as meaning a duty to
    observe certain aspects of rules of natural
    justice. A body may be under a duty to give
    fair consideration to the facts and to consider
    the representations but not to disclose to those
    persons details of information in its
    possession. Sometimes duty to act fairly can
    also be sustained without providing
    opportunity for an oral hearing. It will depend
    upon the nature of the interest to be affected,
    the circumstances in which a power is
    exercised and the nature of sanctions involved
    therein.

    ***

    20. Blacklisting has the effect of preventing a
    person from the privilege and advantage
    of entering into lawful relationship with
    the Government for purposes of gains. The
    fact that a disability is created by the order of
    blacklisting indicates that the relevant
    authority is to have an objective satisfaction.
    Fundamentals of fair play require that the
    person concerned should be given an
    opportunity to represent his case before
    he is put on the blacklist.”

    W.P.(C) No.8589 of 2024 Page 21 of 89

    ii. UMC Technologies Private Limited Vrs. Food
    Corporation of India, (2021) 2 SCC 551, wherein the
    following is the observation:

    “13. At the outset, it must be noted that it is
    the first principle of civilised
    jurisprudence that a person against whom
    any action is sought to be taken or whose
    right or interests are being affected
    should be given a reasonable opportunity
    to defend himself. The basic principle of
    natural justice is that before adjudication
    starts, the authority concerned should
    give to the affected party a notice of the
    case against him so that he can defend
    himself. Such notice should be adequate
    and the grounds necessitating action and
    the penalty/action proposed should be
    mentioned specifically and
    unambiguously. An order travelling
    beyond the bounds of notice is
    impermissible and without jurisdiction to
    that extent. This Court in Nasir Ahmad Vrs.
    Custodian General, Evacuee Property, (1980) 3
    SCC 1 has held that it is essential for the
    notice to specify the particular grounds on the
    basis of which an action is proposed to be
    taken so as to enable the noticee to answer the
    case against him. If these conditions are not
    satisfied, the person cannot be said to have
    been granted any reasonable opportunity of
    being heard.

    W.P.(C) No.8589 of 2024 Page 22 of 89

    14. Specifically, in the context of blacklisting
    of a person or an entity by the State or a
    State Corporation, the requirement of a
    valid, particularised and unambiguous
    show-cause notice is particularly crucial
    due to the severe consequences of
    blacklisting and the stigmatisation that
    accrues to the person/entity being
    blacklisted. Here, it may be gainful to
    describe the concept of blacklisting and the
    graveness of the consequences occasioned by
    it. Blacklisting has the effect of denying a
    person or an entity the privileged opportunity of
    entering into Government contracts. This
    privilege arises because it is the State who is
    the counterparty in Government contracts and
    as such, every eligible person is to be afforded
    an equal opportunity to participate in such
    contracts, without arbitrariness and
    discrimination. Not only does blacklisting
    take away this privilege, it also tarnishes
    the blacklisted person’s reputation and
    brings the person’s character into
    question. Blacklisting also has long-
    lasting civil consequences for the future
    business prospects of the blacklisted
    person.

    15. In the present case as well, the appellant has
    submitted that serious prejudice has been
    caused to it due to the Corporation’s order of
    blacklisting as several other government
    corporations have now terminated their
    contracts with the appellant and/or prevented
    the appellant from participating in future

    W.P.(C) No.8589 of 2024 Page 23 of 89
    tenders even though the impugned blacklisting
    order was, in fact, limited to the Corporation’s
    Madhya Pradesh regional office. This domino
    effect, which can effectively lead to the
    civil death of a person, shows that the
    consequences of blacklisting travel far
    beyond the dealings of the blacklisted
    person with one particular Government
    Corporation and in view thereof, this
    Court has consistently prescribed strict
    adherence to principles of natural justice
    whenever an entity is sought to be
    blacklisted.

    ***

    21. Thus, from the above discussion, a clear legal
    position emerges that for a Show-Cause
    Notice to constitute the valid basis of a
    blacklisting order, such notice must spell
    out clearly, or its contents be such that it
    can be clearly inferred therefrom, that
    there is intention on the part of the issuer
    of the notice to blacklist the noticee. Such
    a clear notice is essential for ensuring that the
    person against whom the penalty of
    blacklisting is intended to be imposed, has an
    adequate, informed and meaningful
    opportunity to show cause against his possible
    blacklisting.”

    5.4. Advancing further his argument, Sri Prabodha Chandra
    Nayak, learned counsel would submit that the Codal
    Provisions for blacklisting contractors in sub-rule (c) of
    Rule A of Appendix-XXXIV appended to the OPWD Code
    W.P.(C) No.8589 of 2024 Page 24 of 89
    envisages two aspects, namely (i) Constant non-
    achievement of milestones on insufficient and imaginary
    grounds; and (ii) non-adherence to quality specifications
    despite being pointed out conjoined. Both the aspects
    together would form part of one ground. In the present
    case, only first two being pointed out by the authority
    concerned, the decision taken by the Chief Engineer,
    World Bank Projects, Odisha pursuant to Show Cause
    Notices dated 18.10.2023 (Annexure-11) is inconsistent
    with the Codal Provision; as such, the same suffers vice
    of arbitrariness, caprice and fancies of the authority;
    and the decision thereon is tainted with mechanical
    application of mind. To buttress his argument that these
    circumstances as envisaged in sub-rule (c) of Rule A of
    Appendix-XXXIV do constitute single whole, he referred
    to Sk. Ahmed Vrs. State of Telangana, (2021) 9 SCC 59,
    wherein it was held that,

    “19. This Court held that when the provisos (i) and (ii) are
    separated by conjunctive word “and”, they have to
    be read conjointly. The requirement of both the
    proviso has to be satisfied to avail the benefit. Para
    8 [in Hyderabad Asbestos Cement Products Vrs.
    Union of India, (2000) 1 SCC 426] is as follows:

    „8. The language of the rule is plain and simple. It
    does not admit of any doubt in interpretation.
    Provisos (i) and (ii) are separated by the use of
    the conjunction “and”. They have to be read
    conjointly. The requirement of both the provisos

    W.P.(C) No.8589 of 2024 Page 25 of 89
    has to be satisfied to avail the benefit. Clauses

    (a) and (b) of proviso (ii) are separated by the
    use of an “or” and there the availability of one
    of the two alternatives would suffice. Inasmuch
    as cement and asbestos fibre used by the
    appellants in the manufacture of their finished
    excisable goods are liable to duty under
    different tariff items, the benefit of pro forma
    credit extended by Rule 56-A cannot be availed
    of by the appellants and has been rightly
    denied by the authorities of the Department.‟
    ***”

    5.5. Sri Prabodha Chandra Nayak, learned Advocate
    arduously submitted that mere allegation of breach of
    contractual obligations without anything more, per se,
    does not invite such punitive action. He referred to
    following observation of the Hon’ble Supreme Court of
    India made in Techno Prints Vrs. Chhattisgarh Textbook
    Corporation, (2025) 3 SCR 208:

    “34. Plainly, if a contractor is to be visited with the
    punitive measure of blacklisting on account of an
    allegation that he has committed a breach of a
    contract, the nature of his conduct must be so
    deviant or aberrant so as to warrant such a punitive
    measure. A mere allegation of breach of
    contractual obligations without anything more,
    per se, does not invite any such punitive
    action.

    35. Usually, while participating in a tender, the bidder is
    required to furnish a statement undertaking that it
    has not been blacklisted by any institution so far
    W.P.(C) No.8589 of 2024 Page 26 of 89
    and, if that is not the case, provide information of
    such blacklisting. This serves as a record of the
    bidder‟s previous experience which gives the
    purchaser a fair picture of the bidder and the
    conduct expected from it. Therefore, while the
    debarment itself may not be permanent and
    may only remain effective for a limited, pre-
    determined period, its negative effect continues
    to plague the business of the debarred entity
    for a long period of time. As a result, it is
    viewed as a punishment so grave, that it must
    follow in the wake of an action that is equally
    grave.

    36. In the overall view of the matter more particularly in
    the peculiar facts of the case, we have reached the
    conclusion that asking the appellant herein to file his
    reply to the show cause notice and then await the
    final order which may perhaps go against him,
    leaving him with no option but to challenge the same
    before the jurisdictional High Court will be nothing
    but an empty formality. Even otherwise, issuing
    of show cause notice if not always then at
    least most of the times is just an empty
    formality because at the very point of time the
    show cause notice is issued the Authority has
    made up its mind to ultimately pass the final
    order blacklisting the Contractor. In other
    words, the show cause notice in most of the
    cases is issued with a pre-determined mind. It
    has got to be issued because this Court has said
    that without giving an opportunity of hearing there
    cannot be any order of blacklisting. To meet with
    this just a formality is completed by the Authority of
    issuing a show cause notice.

    W.P.(C) No.8589 of 2024 Page 27 of 89

    5.6. It is submitted that since the petitioner pursuing his
    remedy bona fide and the propriety and legality of
    rescission of contracts being sub judice before this Court
    for adjudication in W.P.(C) Nos.29863 of 2023 and
    31693 of 2023, the authority should not have shown
    haste in taking recourse of banning the petitioner for six
    years from participating in any of the tenders
    undertaken by the Government of Odisha and
    transacting business with the Government of Odisha,
    directly or indirectly.

    5.7. Stemming on the observations made in Blue Dreamz
    Advertising (P) Ltd. Vrs. Kolkata Municipal Corporation,
    (2024) 15 SCC 264, the Codal Provisions specifying
    modalities for blacklisting/debarment requires strict
    interpretation, and non-fulfilment of any of the
    conditions thereof would render the decision of the
    authority vitiated. It is, thus, asserted that the ban order
    dated 30.03.2024 can be regarded as “civil death”3, for
    such a decision tends to “blacklisting” the petitioner
    preventing it to eke out livelihood.

    5.8. Hence, it is urged fervently for showing indulgence in the
    matter.

    6. Sri Saswat Das, learned Additional Government
    Advocate dispelling controversial contentions raised by
    3 See, Shri Artatran Bhuyan Vrs. State of Odisha, 2025 (II) ILR-CUT 1042 as
    followed in Rinabala Sethi Vrs. State of Odisha, 2025 SCC OnLine Ori 4785.

    W.P.(C) No.8589 of 2024 Page 28 of 89

    the petitioner submitted that the petitioner prior to
    passing order banning it from participating in the
    bidding process for the work undertaken by the
    Government of Odisha and entering into transactions of
    business with the Government of Odisha, issued Show
    Cause Notices and the reply of the petitioner was found
    not to have been specific or cogent. Referring to written
    note dated 21.07.2025 submitted by the opposite
    parties, he emphasised that in view of State of Odisha
    Vrs. Panda Infraproject Limited, (2022) 4 SCC 393, having
    adhered to principles of natural justice prior to taking
    decision to debar/ban, no flaw in the order dated
    30.03.2024 of the Chief Engineer, Bridges (WBP) can be
    imputed so as to warrant this Court to interfere with. He
    would submit that banning the contractor like the
    petitioner who defied to complete the works entrusted
    within the period stipulated is an effective measure to
    discipline the defiant.

    6.1. Explaining further he strenuously contended that the
    petitioner even though was granted sufficient
    opportunity and extension of period to complete the
    works in question, he remained dormant and filed
    affidavit before this Court for a direction to the opposite
    parties to extend the period so expired knowing fully well
    that such a recourse is not open for it to approach by

    W.P.(C) No.8589 of 2024 Page 29 of 89
    invoking provisions of Articles 226 and 227 of the
    Constitution of India.

    6.2. In counter reply to the interpretation of use of the word
    “and” in sub-rule (c) of Rule A of the Appendix-XXXIV,
    Sri Saswat Das, learned Additional Government
    Advocate made suave submission that the aspects
    contained therein are to be read disjunctively, but not
    conjunctively. It is one thing to hold the petitioner
    having committed offence of “Constant non-achievement
    of milestones on insufficient and imaginary grounds”

    and nevertheless, it is another to say “non-adherence to
    quality specifications despite being pointed out”. It is
    vociferously submitted that two independent aspects
    cannot be construed to be one ground. Since the Show
    Cause Notices indicated one aspect i.e., “Constant non-
    achievement of milestones on insufficient and imaginary
    grounds” out of the two aspects in the ground vide sub-
    rule (c) of Rule A of Appendix-XXXIV read with Clause
    121 of the DTCN, and the reply thereto by the petitioner
    being not found favour with, ban order debarring the
    petitioner from participating in tenders vide order dated
    30.03.2024 has been passed. Valiant attempt was made
    by the learned Additional Government Advocate to
    construe the word “and” joining two situations/
    circumstances enjoined in sub-rule (c) of Rule A of
    Appendix-XXXIV to the OPWD Code to be disjunctive.

    W.P.(C) No.8589 of 2024 Page 30 of 89

    6.3. Referring to Venkataraman Krishnamurthy Vrs. Lodha
    Crown Buildmart Pvt. Ltd., (2024) 4 SCC 230, it is
    submitted that the explicit terms contained in Clause
    2(b)(i)4 read with Clause 121 of the DTCN should be
    treated to be final word with regard to the intention of
    the parties. On the specious plea of regulatory or
    adjudicatory forum the petitioner should be discouraged
    to insist for judicial review after participation in the
    tender and being awarded with the works to accomplish
    within the periods stipulated in the guise of seeking
    equity or fairness. Such a course to draw sympathy of
    this Court is anathema to judicial approach and to insist
    for rewriting the contractual framework or superimpose
    obligations alien to the agreement.

    6.4. He, thus, prayed not to meddle with the order of
    debarment vide Annexure-1 and dismiss the writ
    petition.

    Analysis and discussion:

    7. Before this Court the rescission of contracts with respect
    to two different works awarded has been under
    challenge in W.P.(C) Nos.29863 and 31693 of 2023. In
    both the cases the petitioner filed affidavit undertaking
    that given extension of further period, it would be in a

    4 “To rescind the contract (of which rescission notice in writing to the contractor
    under the hand of the Executive Engineer shall be conclusive evidence) 20% of the
    value of left-over work will be realized from the Contractor as penalty.”

    W.P.(C) No.8589 of 2024 Page 31 of 89

    position to complete the works. While in respect of one of
    the works, being Work No.1, this Court having directed
    the opposite parties to allow the petitioner to complete
    the work in W.P.(C) No. 29863 of 2023 vide order dated
    01.03.2024, the Hon’ble Supreme Court in the case of
    State of Odisha Vrs. Binodini Infrastructure Pvt. Ltd., Civil
    Appeal No.7085 of 2025 [Arising out of S.L.P.(C) No.14142
    of 2024] vide order dated 14.05.2025 set aside the
    matter by holding that this Court could not have issued
    such direction inasmuch as such consideration would
    fall in the domain of rewriting the terms of contract. In
    the other matter being W.P.(C) No.31693 of 2023 the
    opposite parties have filed counter refuting the
    averments and contentions of the petitioner. Both the
    matters are now sub judice before this Court. Rescission
    of contracts being questioned in the said writ petitions,
    in the present the concern is for ban order clamped
    against the petitioner from participating in tenders and
    transacting business with the Government.

    8. Be that as it may, the order banning/debarring the
    petitioner has come to be passed by the Chief Engineer,
    Bridges (WBP), Odisha on 30.03.2024 which is subject
    matter of challenge in this writ petition.

    9. Perusal of Show Cause Notice dated 18.10.2023 with
    respect to Work No.1, it transpired that several requests
    were made by the authority concerned by issue of
    W.P.(C) No.8589 of 2024 Page 32 of 89
    notices to the petitioner to complete the works, which
    turned out to be futile and went unheeded. Upon
    inspection being conducted by the Superintending
    Engineer, Malkangiri (R&B) to the spot, it was found
    that there were no men or machineries at the site. Such
    negligence on the part of the petitioner invited issue of
    such notice with the caveat that failure to act with
    promptitude would invite action in terms of Clause 121
    of the DTCN read with provisions of Appendix-XXXIV of
    OPWD Code, Volume-II.

    9.1. Perusal of Show Cause Notice dated 18.10.2023 with
    respect to Work No.2 (Annexure-11) it is manifest that
    notwithstanding several notices issued to the petitioner,
    it remained indifferent and failed to complete the work
    within the period stipulated, as extended. Even a notice
    in Letter No.357 dated 25.01.2021 was issued with
    request to complete the balance work with warning that
    failure to resume work would entail step under Clause
    121 of DTCN read with relevant provisions of Appendix-
    XXXIV of OPWD Code, Volume-II.

    9.2. Separate replies dated 23.10.2023 were submitted to the
    Chief Engineer, World Bank Projects with copies to other
    authorities making them aware that the tenability of
    decision to rescind the contracts has been pending
    before this Court.

    W.P.(C) No.8589 of 2024 Page 33 of 89

    9.3. Perusal of record further revealed the fact that the
    petitioner has been imposed with penalty vide Letter
    dated 26.10.2023 issued by the Superintending
    Engineer (R&B) Division, Malkangiri (Annexure-12).

    9.4. When the material with respect to pendency of cases
    relating to the works in question was made known to the
    authority concerned, without issuing further notice
    contemplating to take drastic step against the petitioner
    and/or hearing it the order of ban/debarment has been
    passed, which is recognized akin to “blacklisting”,
    thereby affecting the fundamental right to carry
    business under Article 19(1)(g) of the Constitution of
    India. As it emanates ex facie from the reply dated
    23.10.2023, the petitioner merely made aware the
    authorities regarding pendency of cases before this
    Court as against rescission of contracts; but the reply
    does not indicate that the petitioner has disclosed the
    reasons for non-completion of the works within the
    periods stipulated.

    9.5. It cannot be gainsaid that in order to impose stringent
    condition, like ban/debarment/blacklisting which would
    have effect of impinging upon constitutional right of the
    contractor, the authority exercising such power must be
    more circumspect and such recourse preventing the
    contractor from carrying on business would have
    unreasonable restriction on the right flowing from Article
    W.P.(C) No.8589 of 2024 Page 34 of 89
    19(1)(g).
    Article 14 of the Constitution of India
    safeguards such persons being contemned without
    affording opportunity of hearing. Such is the facet is
    audi alteram partem.

    9.6. This Court in Sumitra Sethy Vrs. The Indian Railways,
    W.P.(C) No.6182 of 2025, vide Judgment dated
    06.05.2026 observed thus:

    “7. It is no gainsaying that the blacklisting or
    debarment has an effect of eliminating a person
    from participating in any contract with the
    Government nor will have any such privilege and
    advantage of entering into the contract with the
    Government agencies. It is, in effect, deprived a
    person from having any commercial
    relationship with the Government or its
    agencies and has an impact on the right to
    trade or profession as provided under Article
    19(1)(g)
    of the Constitution of India. Such
    fundamental right is always subject to the
    established procedure of law and in the event
    it is found that the person has committed a
    gross error or violated the terms and
    conditions of the contract, there is no fetter in
    debarring such person to participate in any
    tender, nor will be entitled to establish a
    contractual relationship with the public
    authority. In such sense, it is time and again
    regarded as a “civil death” and therefore, it is
    a paramount duty of the authorities to adhere
    the principles of natural justice before it

    W.P.(C) No.8589 of 2024 Page 35 of 89
    proceeds to inflict an order of debarment
    and/or blacklisting on the person.

    8. The aforesaid concept/notion is further fortified in
    the judgment rendered by the Apex Court in case of
    Raghunath Thakur Vrs. State of Bihar; (1989) 1 SCC
    229 in the following:

    „4. Indisputably, no notice had been given to the
    appellant of the proposal of blacklisting the
    appellant. It was contended on behalf of the
    State Government that there was no
    requirement in the rule of giving any prior
    notice before blacklisting any person. Insofar
    as the contention that there is no requirement
    specifically of giving any notice is concerned,
    the respondent is right. But it is an implied
    principle of the rule of law that any order
    having civil consequence should be passed
    only after following the principles of natural
    justice. It has to be realised that blacklisting
    any person in respect of business ventures has
    civil consequence for the future business of the
    person concerned in any event. Even if the
    rules do not express so, it is an elementary
    principle of natural justice that parties affected
    by any order should have right of being heard
    and making representations against the order.
    In that view of the matter, the last portion of
    the order insofar as it directs blacklisting of the
    appellant in respect of future contracts, cannot
    be sustained in law. In the premises, that
    portion of the order directing that the appellant
    be placed in the blacklist in respect of future
    contracts under the Collector is set aside. So

    W.P.(C) No.8589 of 2024 Page 36 of 89
    far as the cancellation of the bid of the
    appellant is concerned, that is not affected.
    This order will, however, not prevent the State
    Government or the appropriate authorities from
    taking any future steps for blacklisting the
    appellant if the Government is so entitled to do
    in accordance with law i.e. after giving the
    appellant due notice and an opportunity of
    making representation. After hearing the
    appellant, the State Government will be at
    liberty to pass any order in accordance with
    law indicating the reasons therefor. We,
    however, make it quite clear that we are not
    expressing any opinion on the correctness or
    otherwise of the allegations made against the
    appellant. The appeal is thus disposed of.‟

    ***

    10. It is manifest from the ratio of law enunciated in the
    above report that the order of blacklisting and/or
    debarment not only prevents and/or excludes a
    person from participating in any contractual
    relationship with the Government or its agencies but
    is also deprived of his livelihood as a stigma would
    be attached to him which cannot be inflicted without
    giving ample opportunity to defend. Even if the terms
    and conditions embodied in the tender document
    does not contain an express provision relating to
    issuance of a show cause preceding the order of
    blacklisting, yet the rule of natural justice being
    paramount cannot be abridged and/or whittled
    down which is one of the ethos of the constitutional
    rights guaranteed in the Constitution of India. The
    maxim audi alteram partem is ingrained and

    W.P.(C) No.8589 of 2024 Page 37 of 89
    inhered into the legal system and even a
    person cannot be penalised and/or condemned
    without giving an opportunity of hearing. As
    indicated hereinabove the debarment/blacklisting
    has the blend of a civil death, such order cannot be
    passed without affording an opportunity to defend
    and for such reason the issuance of show cause
    becomes inevitable.

    11. In a recent judgment rendered by the Hon‟ble
    Supreme Court in M/s. A.K.G. Construction and
    Developers Pvt. Ltd. Vrs. State of Jharkhand and
    others; (2026) 4 SCR 331, the Apex Court was
    considering a case where a show cause notice was
    issued to the contractor with regard to the
    termination of a contract for the reasons reflected in
    the said show cause notice but the authorities while
    terminating the contract proceeded to pass an order
    of blacklisting and/or debarment. The Apex Court
    did not interfere with the order of termination
    of a contract but set aside the order of the
    debarment as both the circumstances relating
    to a termination of a contract and imposition
    of a blacklisting and/or debarment are
    distinct, different and separate. It is held that
    the show cause notice which was restricted to a
    termination of contract cannot be stretched to mean
    that it is also for the debarment in the following:

    „3. Upon careful consideration of the impugned
    State action, which terminates the contract and
    blacklists the appellant without meaningful
    distinction, we hold that the termination order
    is substantiated and justified. However, the
    blacklisting order suffers from patent

    W.P.(C) No.8589 of 2024 Page 38 of 89
    infirmities: it evinces no application of
    mind, disregards the mandatory precept
    of audi alteram partem, and fails to
    precede with a show-cause notice
    requiring the contractor to demonstrate
    why such drastic action should not be
    taken. Blacklisting, being stigmatic and
    exclusionary in nature, cannot be imposed
    mechanistically but must comport with
    principles of natural justice and
    reasonableness.

    ***

    22. Returning to the facts of the present case, at
    the outset, it is apparent that the show cause
    notice dated 04.06.2024 does not purport to be
    a show cause notice for blacklisting at all. It
    perhaps expects the contractor to assume that
    it is for termination as well as for blacklisting.

    Even if we accept the submissions of Mr.
    Kumar Anurag Singh that, as there is no
    provision for prior notice before termination,
    this show cause notice must be taken to be for
    blacklisting, we are of the opinion that it still
    falls short of the requirement of a proper show
    cause notice for blacklisting. This is for the
    reason that as the decision to blacklist is
    independent of the decision to terminate, the
    Department must demonstrate application of
    mind before it takes the next step of
    blacklisting the contractor, over an order of
    termination. Upon taking such a decision, it
    must also issue a show cause notice calling
    upon the contractor to explain why a

    W.P.(C) No.8589 of 2024 Page 39 of 89
    consequential order of blacklisting should also
    not be passed. The letter must be indicative of
    the proposed decision to blacklist and the
    requirement of the contractor to respond to it.
    The show cause notice dated 04.06.2024 falls
    short of these requirements. Similarly, the final
    order of blacklisting, dated 23.08.2024, also
    does not list the reasons as to why an order of
    blacklisting has become necessary.‟ ***”

    9.7. There is no cavil that the order of banning/blacklisting/
    debarment would be akin to “civil death”, this Court in
    Kwick Soft Solutions Pvt. Ltd., Tamilnadu Vrs. State of
    Odisha, W.P.(C) No.24026 of 2024 vide order dated
    21.08.20255 observed as follows:

    “3. It is no doubt true that the debarment or blacklisting
    of any individual or an entity to participate in a
    tender process is akin to a “civil death” as a person
    is deprived of entering into any commercial
    relationship with the public or the Government. Any
    order of debarment or blacklisting is always
    regarded as a stigma attached to the commercial
    dealing with the Government and in effect debars
    from a person to have the award of the Government
    contracts. The debarment or blacklisting has an
    effect of bringing a person from the privilege
    and advantage of entering into a lawful
    relationship with the Government or its
    instrumentalities and above all impacts the
    livelihood. In effect such debarment has a far-
    reaching consequence in public contracts and,

    5 Referred to in Rinabala Sethi Vrs. State of Odisha, W.P.(C) No.21309 of 2024,
    vide Judgment dated 22.12.2025.

    W.P.(C) No.8589 of 2024 Page 40 of 89

    therefore, the authority must view the misconduct
    more scrupulously before taking a decision of
    debarment/blacklisting. The misdeed must be of
    such magnitude which in ordinary sense is not
    expected from a reasonable man. It may at times
    should be judged on the parameter of unfair means
    or illegal gain. The minimal or accidental omission or
    mistake, which was subsequently rectified, if it does
    not, cause any prejudice or hinders in its invocation
    as the Bank remain committed to the person, in
    whose favour the Bank Guarantee is issued to
    honour the same, the authority must view the
    mistake in such perspective. Mere non-incorporation
    of UIN of the Odisha Police and incorporation of the
    PAN number of one of the Directors of the petitioner-
    Company mistakenly neither invalidates the said
    Bank Guarantee nor put any invasion into its
    invocation by the Odisha Police in the event the
    same is warranted from the conduct of the
    petitioner. Apart from the same, the said ministerial
    mistake was rectified by the Bank issuing the Bank
    Guarantee, which does not in our view invites the
    civil death as held by the Apex Court in the case of
    Gorkha Security Services Vrs. Government (NCT of
    Delhi) and others, (2014) 9 SCC 105 in the following:

    „16. It is a common case of the parties that the
    blacklisting has to be preceded by a show-
    cause notice. Law in this regard is firmly
    grounded and does not even demand much
    amplification. The necessity of compliance with
    the principles of natural justice by giving the
    opportunity to the person against whom action
    of blacklisting is sought to be taken has a valid
    and solid rationale behind it. With

    W.P.(C) No.8589 of 2024 Page 41 of 89
    blacklisting, many civil and/or evil
    consequences follow. It is described as
    “civil death” of a person who is foisted
    with the order of blacklisting. Such an
    order is stigmatic in nature and debars
    such a person from participating in
    government tenders which means
    precluding him from the award of
    government contracts.‟ ***”

    9.8. At this juncture careful reading of Show Cause Notices
    dated 18.10.2023 would depict that except for slow pace
    of work being flagged, nothing is emanated with specific
    terms with regard to the grounds on which the action for
    banning was contemplated.

    9.9. It may be necessary to have regard to Clause 121 of the
    DTCN, which is reproduced hereunder [vide Counter
    affidavit, paragraph 6]:

    “121.A contractor may be blacklisted as per amendment
    made to Appendix XXXIV to OPWD Code, Volume-II
    on rules for blacklisting of contractors vide Letter No.
    3365 dated 01.03.2007 of Works Department,
    Odisha.

    (a) Misbehavior/threatening of departmental
    supervisory officers during work/tendeiing
    process,

    (b) Involvement in any sort of tender fixing,

    (c) Constant non-achievement of milestones
    insufficient and imaginary grounds and non-

    W.P.(C) No.8589 of 2024 Page 42 of 89

    adherence to quality specifications despite
    being pointed out.

    (d) Persistent and intentional violation of important
    conditions of contract.

    (e) Security consideration of the State, i.e., any
    action that jeopardizes the security of the
    State.

    (f) Submission of false/fabricated/forged
    documents for consideration of a tender.”

    9.10. Relevant portion of Appendix XXXIV is quoted
    hereunder:

    “Appendix-XXXIV
    Codal provisions for blacklisting
    Contractors

    A. The Chief Engineer of a department may blacklist a
    contractor with the approval of concerned
    Administrative Department on the following grounds:

    (a) Misbehaviour/threatening of departmental and
    supervisory officers during execution of
    work/tendering process.

    (b) Involvement in any sort of tender fixing.

    (c) Constant non-achievement of milestones
    on insufficient and imaginary grounds
    and non-adherence to quality
    specifications despite being pointed out.

    (d) Persistent and intentional violation of important
    conditions of contract.

    W.P.(C) No.8589 of 2024 Page 43 of 89

    (e) Security consideration of the State i.e., any
    action that jeopardizes the security of the
    State.

    (f) Submission of false/fabricated/forged
    documents for consideration of a tender.

    (g) Non submission of Additional Performance
    Security (APS) within stipulated period
    inpursuance to Works Department Office
    memorandum No 14299/W, dated 03.10.2017.

    The Divisional Officer shall report to the Chief
    Engineer if in his opinion any of the above wrong
    has/have been committed by any contractor. On
    receipt of such a report from the Divisional Officer
    the Chief Engineer shall make due enquiry and if
    considered necessary, issue show cause notice to
    the concerned contractor who in turn shall furnish
    his reply, if any, within a fortnight from the date of
    receipt of the show cause notice. Therefore, if the
    Chief Engineer is satisfied that there is sufficient
    ground, he shall blacklist the concerned contractor
    with the approval of the Administrative Department.
    After issue of the order of blacklisting of the said
    contractor, the Chief Engineer shall intimate to all
    Chief Engineers of other Administrative
    Departments, the Registering Authority as provided
    under Rule 4 of PWD Contractor‟s Registration
    Rules, 1967 and Department of Information &
    Technology for publication in web site of State
    Government.

    B. The registration certificate of blacklisted contractor
    shall remain automatically suspended while
    allowing him to complete all his ongoing work(s)

    W.P.(C) No.8589 of 2024 Page 44 of 89
    unless otherwise rescinded by the competent
    authority on grounds of breach of conditions of
    agreement.

    C. The name(s) of partners and allied concerns of the
    blacklisted contractors shall also be communicated
    to all concerned. Care shall be taken to see that the
    contractor blacklisted and his partners do not
    transact any business with Government under a
    different name or title.

    D. Once the blacklisting order is issued it shall not be
    revoked ordinarily unless:

    (i) On review in later date, the Chief Engineer is of
    the opinion that there is sufficient justification
    to revoke the order of blacklisting, or

    (ii) In respect of the same offense, the accused has
    been honourably acquitted by court of law.

    The concerned Chief Engineer will obtain order from
    the concerned Administrative Department before
    revoking the order of blacklisting. The order of
    revocation shall also be communicated to all
    concerned.

    6[The blacklisting period per offence shall be limited

    to 03 (three) years subject to an overall maximum

    6 This clause has been introduced by virtue of Office Memorandum File
    No.07180200982020/16131/W, dated 26.11.2021:

    “Sub.: Codal provisions for blacklisting of contractor
    Government after careful consideration have been pleased to make the
    following provision under Rule-D of Appendix-XXXIV of OPWD Code,
    Volume-II:

    „The blacklisting period per offence shall be limited to 03 (three) years
    subject to an overall maximum cumulative period of 10 (ten) years for
    multiple offences‟.

    This shall form a part of the Appendix-XXXIV of OPWD Code, Volume-II.”

    W.P.(C) No.8589 of 2024 Page 45 of 89

    cumulative period of 10 (ten) years for multiple
    offences.]

    E. The Chief Engineer and Administrative Department
    shall maintain a list of blacklisted contractor.
    Updated list of blacklisted contractors shall be
    communicated to all concerned by the Chief
    Engineers on a quarterly basis.

    F. Checklist as per Annexure-I, shall be furnished by
    the concerned Chief Engineer for blacklisting the
    contractor.

    G. Checklist as per Annexure-II, shall be furnished by
    the concerned Chief Engineer for revoking
    blacklisting order.

    Explanation:

    (i) Action taken under this rule shall be in
    addition to any action taken under Rule 11 of
    PWD Contractor‟s Registration Rules,1967
    (Appendix-VIII of OPWD Code, Vol.-II). On
    revocation of order of blacklisting, registration
    certificate of the contractor shall valid
    automatically, if not otherwise become invalid
    which shall be recorded in the registration
    certificate by the revoking authority.

    (ii) The ground mentioned above for blacklisting of
    contractor shall be deemed to be deleted from
    the grounds for cancellation/suspension of
    registration certificate under Rule 11(a) of PWD
    Contractor‟s Registration Rules, 1967
    (AppendixVIII of OPWD Code, Vol.-II).”

    W.P.(C) No.8589 of 2024 Page 46 of 89

    9.11. Ground on which the authority concerned proceeded to
    ban the petitioner is sub-rule (c) of Rule A of the
    Appendix-XXXIV. Having glance at the provisions as
    referred to above read with order dated 30.03.2024
    (Annexure-1), it emerges that “Even after several notices
    and persuations, the contractor constantly failed to
    achieve the desired milestones as per agreement and did
    not complete the above works within the time stipulated
    violating the conditions of contract and Codal
    Provisions.”

    9.12. It is apparent that the ground for jumping to conclusion
    to debar the petitioner from participating in Government
    tenders falls within the ambit of sub-rule (c) of Rule A of
    Appendix-XXXIV. Rule A consists of seven grounds
    stemming on which the competent authority can invoke
    power to blacklist/debar a contractor. Minute reading of
    the order impugned would suggest that the ground on
    which the Chief Engineer, Bridges (WBP) proceeded was
    sub-rule (c) thereof. As debarment is stated to be for “six
    years”, it does not emanate from said order the reason
    for invocation of introduced clause by virtue of Office
    Memorandum dated 26.11.2021.

    9.13. Sub-rule (c) of Rule A comprehends two aspects, namely:

    i. Constant non-achievement of milestones on
    insufficient and imaginary grounds; “and”

    W.P.(C) No.8589 of 2024 Page 47 of 89

    ii. non-adherence to quality specifications despite
    being pointed out.

    9.14. Both the situations are placed under one entry as a
    composite ground. However, unless the deficiencies are
    put to notice of the petitioner in specific terms with
    respect to both the situations, it may not possibly
    appropriate for the authority to jump to conclusion that
    the contract invites stringent restriction.

    9.15. At this stage Show Cause Notices vide Annexure-11 are
    required to be taken into consideration. Meaningful
    reading of the tenor and texture of such notices would
    only indicate that notices were issued to the petitioner
    requesting it to complete the balance work. However, it
    does not emerge therefrom that the contemplated action
    for blacklisting was intimated in specific terms and
    ground(s) specified in sub-rule (c) of Rule A. It is only the
    Show Cause Notices dated 18.10.2023 which depict that
    failure to resume both the works would attract steps as
    per Clause 121 of the DTCN read with Rule A of the
    Appendix-XXXIV of the OPWD Code.

    9.16. It is interesting to note that Show Cause Notices dated
    18.10.2023 does not indicate whether there was any
    “insufficient and imaginary ground” that led to “constant
    non-achievement of milestones”. In the Show Cause
    Notice dated 18.10.2023 with respect to Work No.2 it is

    W.P.(C) No.8589 of 2024 Page 48 of 89
    stated that “The Superintending Engineer, Malkangiri,
    Malkangiri (R&B) Division again issued another show
    cause notice vide Letter No.5823, dated 11.11.2020
    where he has stated that even though you have
    committed during contract management meeting held on
    06.07.2020 in his office to start the bridge work by 2 nd
    week of September, 2020, till November, 2020 you did
    not taken any initiative.” It is further revealed therefrom
    that “the Superintending Engineer, Malkangiri (R&B)
    Division issued final notice vide Letter No.357, dated
    25.01.2021 to you with a request to execute the backlog
    quantities of the work by engaging sufficient me and
    machineries with maximum working hours as well as
    achieve the target for completion of the above project”.

    Similar facts are also found place in Show Cause Notice
    dated 18.10.2023 with respect to Work No.1.

    9.17. Above recitals emanating from the Show Cause Notices
    would indicate that the extensions granted for
    completion of works were during the period of pandemic.
    There is no iota of indication found in said Show Cause
    Notices with respect to “non-adherence to quality
    specifications”. Had the authority wanted real reason for
    the delay and non-accomplishment of the works
    entrusted to the petitioner, it should have issued notice
    to submit explanation for the delay and affording
    opportunity of hearing. Failure to give such an

    W.P.(C) No.8589 of 2024 Page 49 of 89
    opportunity would render the order legally fragile not on
    the ground of lack of jurisdiction on the part of the
    authority concerned but on the ground of violation of
    principles of natural justice. There can be no dispute
    that while the authority is free to exercise his
    jurisdiction on consideration of all relevant facts, a full
    opportunity to controvert the same and to explain the
    circumstances surrounding such facts, as may be
    considered relevant by the contractor, must be afforded
    to him prior to the finalization of the decision. See,
    Commissioner of Income Tax Vrs. Amitabh Bachchan,
    (2016) 3 SCR 516.

    9.18. In Oryx Fisheries Pvt. Ltd. Vrs. Union of India, (2010) 13
    Addl. SCR 234 it has been stated thus:

    “22. Relying on the underlined portions in the show
    cause notice, learned counsel for the appellant urged
    that even at the stage of the show cause notice the
    third respondent has completely made up his mind
    and reached definite conclusion about the alleged
    guilt of the appellant. This has rendered the
    subsequent proceedings an empty ritual and an idle
    formality.

    23. This Court finds that there is a lot of substance in
    the aforesaid contention.

    24. It is well settled that a quasi-judicial authority, while
    acting in exercise of its statutory power must act
    fairly and must act with an open mind while
    initiating a show cause proceeding. A show cause
    W.P.(C) No.8589 of 2024 Page 50 of 89
    proceeding is meant to give the person·proceeded
    against a reasonable opportunity of making his
    objection against the proposed charges indicated in
    the notice.

    25. Expressions like „a reasonable opportunity of
    making objection‟ or „a reasonable opportunity of
    defence‟ have come up for consideration before this
    Court in the context of several statutes.

    26. A Constitution Bench of this Court in Khem Chand
    Vrs. Union of India and others, reported in AIR 1958
    SC 300, of course in the context of service
    jurisprudence, reiterated certain principles which are
    applicable in the present case also.

    27. Chief Justice S.R. Das speaking for the unanimous
    Constitution Bench in Khem Chand (supra) held that
    the concept of „reasonable opportunity‟ includes
    various safeguards and one of them, in the words of
    the learned Chief Justice, is:

    „(a) An opportunity to deny his guilt and
    establish his innocence, which he can only
    do if he is told what the charges leveled
    against him are and the allegations on
    which such charges are based;‟

    28. It is no doubt true that at the stage of show cause,
    the person proceeded against must be told the
    charges against him so that he can take his defence
    and prove his innocence. It is obvious that at that
    stage the authority issuing the chargesheet, cannot,
    instead of telling him the charges, confront him with
    definite conclusions of his alleged guilt. If that is
    done, as has been done in this instant case, the

    W.P.(C) No.8589 of 2024 Page 51 of 89
    entire proceeding initiated by the show cause notice
    gets vitiated by unfairness and bias and the
    subsequent proceeding become an idle ceremony.

    29. Justice is rooted in confidence and justice is the goal
    of a quasi-judicial proceeding also. If the functioning
    of a quasi-judicial authority has to inspire
    confidence in the minds of those subjected to its
    jurisdiction, such authority must act with utmost
    fairness. Its fairness is obviously to be manifested
    by the language in which charges are couched and
    conveyed to the person proceeded against. In the
    instant case from the underlined portion of the show
    cause notice it is clear that the third respondent has
    demonstrated a totally close mind at the stage of
    show cause notice itself. Such a close mind is
    inconsistent with the scheme of Rule 43 which is set
    out below. The aforesaid rule has been framed in
    exercise of the power conferred under Section 33 of
    The Marine Products Export Development Authority
    Act, 1972 and as such that Rule is statutory in
    nature.

    ***

    31. It is of course true that the show cause notice cannot
    be read hyper-technically and it is well settled that it
    is to be read reasonably. But one thing is clear that
    while reading a show-cause notice the person who
    is subject to it must get an impression that he will
    get an effective opportunity to rebut the allegations
    contained in the show cause notice and prove his
    innocence. If on a reasonable reading of a show-
    cause notice a person of ordinary prudence gets the
    feeling that his reply to the show cause notice will
    be an empty ceremony and he will merely knock his
    W.P.(C) No.8589 of 2024 Page 52 of 89
    head against the impenetrable wall of prejudged
    opinion, such a show cause notice does not
    commence a fair procedure especially when it is
    issued in a quasi-judicial proceeding under a
    statutory regulation which promises to give the
    person proceeded against a reasonable opportunity
    of defence.

    32. Therefore, while issuing a show-cause notice, the
    authorities must take care to manifestly keep an
    open mind as they are to act fairly in adjudging the
    guilt or otherwise of the person proceeded against
    and specially when he has the power to take a
    punitive step against the person after giving him a
    show cause notice.

    33. The principle that justice must not only be
    done but it must eminently appear to be done
    as well is equally applicable to quasi judicial
    proceeding if such a proceeding has to inspire
    confidence in the mind of those who are subject
    to it.

    34. A somewhat similar observation was made by this
    Court in the case of Kumaon Mandal Vikas Nigam
    Limited Vrs. Girja Shankar Pant & others, (2001) 1
    SCC 182. In that case, this court was dealing with a
    show cause notice cum charge sheet issued to an
    employee. While dealing with the same, this Court in
    paragraph 25 (page 198 of the report) by referring to
    the language in the show cause notice observed as
    follows:

    „25. Upon consideration of the language in the
    show-cause notice-cum-charge-sheet, it has
    been very strongly contended that it is clear

    W.P.(C) No.8589 of 2024 Page 53 of 89
    that the Officer concerned has a mindset even
    at the stage of framing of charges and we also
    do find some justification in such a submission
    since the chain is otherwise complete.‟

    35. After paragraph 25, this Court discussed in detail
    the emerging law of bias in different jurisdictions
    and ultimately held in paragraph 35 (page 201 of
    the report), the true test of bias is:

    „35. The test, therefore, is as to whether a mere
    apprehension of bias or there being a real
    danger of bias and it is on this score that the
    surrounding circumstances must and ought to
    be collated and necessary conclusion drawn
    therefrom– in the event however the
    conclusion is otherwise inescapable that there
    is existing a real danger of bias, the
    administrative action cannot be sustained.‟

    36. Going by the aforesaid test any man of ordinary
    prudence would come to a conclusion that in the
    instant case the alleged guilt of the appellant has
    been prejudged at the stage of show cause notice
    itself.”

    9.19. In Commissioner of Central Excise, Bhubaneswar Vrs.

    Champdany Industries Limited, (2009) 14 (Addl.) SCR
    211 it is unequivocally laid down as follows:

    “50. Apart from that, the point on Rule 3 which has been
    argued by the learned counsel for the Revenue was
    not part of its case in the show-cause notice. It is
    well settled that unless the foundation of the case is
    made out in the show-cause notice, Revenue cannot

    W.P.(C) No.8589 of 2024 Page 54 of 89
    in Court argue a case not made out in its show-
    cause notice. [See: Commissioner of Customs,
    Mumbai Vrs. Toyo Engineering India Limited, (2006)
    7 SCC 592, para 16].

    51. Similar view was expressed by this Court in the
    case of Commissioner of Central Excise, Nagpur Vrs.
    Ballarpur Industries Ltd., (2007) 8 SCC 9. In
    paragraph 27 of the said report, learned Judges
    made it clear that if there is no invocation of the
    concerned rules in the show-cause notice, it would
    not be open to the, Commissioner to invoke the said
    Rule.”

    9.20. The Supreme Court in case of Commissioner of Customs,
    Mumbai Vrs. Toyo Engineering India Limited, (2006)
    Supp.5 SCR 657 noted that the Department cannot be
    allowed travel beyond the show cause notice and,
    therefore, it would be against the principles of natural
    justice that a person who has not been confronted with
    any ground is saddled with liability thereof. Since the
    issue did not form the basis of the show cause notice
    and was not even confronted to the order passed beyond
    show cause notice is to be quashed. In the instant case,
    the Show Cause Notices do not with specificity spelt out
    with regard to twin conditions envisioned in sub-rule (c)
    of Rule A of Appendix-XXXIV appended to the OPWD
    Code. The Show Cause Notices dated 18.10.2023 and
    the impugned order dated 30.03.2024 are silent about
    the circumstances/aspects which led to construe that

    W.P.(C) No.8589 of 2024 Page 55 of 89
    the explanation of the petitioner was “insufficient and
    imaginary grounds”. Neither the Show Cause Notices nor
    did the order demonstrate that there was “non-
    adherence to quality specifications despite being pointed
    out”.

    9.21. Numerous grounds are found mentioned in Rule A. Each
    ground is placed separately as item (a) through (g). Had
    both the aspects in Ground contained in sub-rule (c) of
    Rule A “Constant non-achievement of milestones on
    insufficient an imaginary grounds” “and” “non-
    adherence to quality specifications despite being pointed
    out” were to be treated as separate grounds, then there
    was no difficulty in formulating each of them in separate
    items. Before analyzing the nuance of grounds found
    enumerated under Rule A, OPWD Code, a doctrinaire
    principle ingrained in noscitur-a-sociis may be referred to
    as reflected in State Vrs. Hospital Mazdoor Sabha, (1960)
    2 SCR 866 may be regarded as relevant for the present
    purpose. The Hon’ble Supreme Court of India held,

    “This rule, according to Maxwell, means that, when two or
    more words which are susceptible of analogous meaning
    are coupled together they are understood to be used in
    their cognate sense. They take as it were their colour from
    each other, that is, the more general is restricted to a
    sense analogous to a less general.

    The same rule is thus interpreted in “Words and Phrases”

    (Vo. XIV, p. 207):

    W.P.(C) No.8589 of 2024 Page 56 of 89

    „Associated words take their meaning from one another
    under the doctrine of noscitur-a-sociis, the philosophy of
    which is that the meaning of a doubtful word may be
    ascertained by reference to the meaning of words
    associated with it; such doctrine is broader than the
    maxim Ejusdem Generis.‟

    In fact the latter maxim „is only an illustration or specific
    application of the broader maxim noscuntur-a-sociis‟.”

    9.22. In Parle Agro Private Limited Vrs. CCT, (2017) 7 SCC 540
    it has been said that it must be borne in mind that
    noscitur-a-sociis is merely a rule of construction and it
    cannot prevail in cases where it is clear that the wider
    words have been deliberately used in order to make the
    scope of the defined word correspondingly wider. It is
    only where the intention of the Legislature in associating
    wider words with words of narrower significance is
    doubtful, or otherwise not clear that the present rule of
    construction can be usefully applied.

    9.23. Rule A begins with expression– “The Chief Engineer of a
    department may blacklist a contractor with the approval
    of concerned Administrative Department on the following
    grounds”. Said expression is followed by seven categories
    of grounds enumerated in sub-rules (a) through (g). The
    setting of said Rule inculcates in mind only one thing
    that the Chief Engineer is empowered to take decision to
    blacklist a contractor subject to approval of the
    Administrative Department on the grounds mentioned in

    W.P.(C) No.8589 of 2024 Page 57 of 89
    sub-rules (a) to (g) on any one ground or combination of
    grounds; nonetheless, each sub-rule is a ground to be
    construed independently. Twin condition is specified in
    sub-rule (c) of Rule A. The languages employed in Clause
    121 of the DTCN and sub-rule (c) of Rule A of Appendix-
    XXXIV appended to the OPWD Code, Volume-II are
    identically worded. Rule A read as a whole indicates that
    the blacklisting of the contractor can be done on the
    grounds enumerated therein. Seven independent
    grounds are reflected in said Rule A. As has already
    been observed above each ground is separately
    enumerated from sub-rule (a) to sub-rule (g). Sub-rule

    (c) is one of the grounds contained in Rule A. Therefore,
    the suggestion of the learned Additional Government
    Advocate to read the word “and” between two
    expressions, i.e., “Constant non-achievement of
    milestones on insufficient an imaginary grounds” “and”

    “non-adherence to quality specifications despite being
    pointed out” disjunctively cannot be acceded to for the
    simple reason that while enumerating different grounds
    the OPWD Code specified separately each ground; then
    there was no difficulty in placing two disjunctive
    situations/aspects, as pleaded by the opposite parties
    through the learned Additional Government Advocate, in
    different segment. The intent of the Government to treat
    both the conditions as one ground for the purpose of

    W.P.(C) No.8589 of 2024 Page 58 of 89
    taking step to blacklist a contractor is loud and clear
    and no ambiguity can be imputed.

    9.24. It is well-established principle of statutory interpretation
    that the word “or” is normally disjunctive and the word
    “and” is normally conjunctive. Both of them can be read
    as vice-versa, but that interpretation is adopted only
    where the intention of the legislature is manifest. See,
    Central Council for Research in Ayurvedic Sciences Vrs.
    Bikartan Das, (2023) 11 SCR 731.

    9.25. In Bhavnagar University Vrs. Palitana Sugar Mill (P) Ltd.,
    (2003) 2 SCC 111 it has been enunciated as follows:

    “It is the basic principle of construction of statute that the
    same should be read as a whole, then chapter by chapter,
    section by section and words by words. Recourse to
    construction or interpretation of statute is necessary when
    there is ambiguity, obscurity, or inconsistency therein and
    not otherwise. An effort must be made to give effect to all
    parts of the statute and unless absolutely necessary, no
    part thereof shall be rendered surplusage or redundant.”

    9.26. In Renaissance Hotel Holdings Inc. Vrs. B. Vijaya Sai,
    (2022) 5 SCC 1, it has been emphasized as follows:

    “66. It is thus trite law that while interpreting the
    provisions of a statute, it is necessary that the
    textual interpretation should be matched with the
    contextual one. The Act must be looked at as a
    whole and it must be discovered what each section,
    each clause, each phrase and each word is meant

    W.P.(C) No.8589 of 2024 Page 59 of 89
    and designed to say as to fit into the scheme of the
    entire Act. No part of a statute and no word of a
    statute can be construed in isolation. Statutes
    have to be construed so that every word has a
    place and everything is in its place. ***

    67. Another principle that the High Court has failed to
    notice is that a part of a section cannot be read in
    isolation. This Court, speaking through A.P. Sen, J.,
    in Balasinor Nagrik Coop. Bank Ltd. Vrs. Babubhai
    Shankerlal Pandya, (1987) 1 SCC 606, observed
    thus:

    „4. *** It is an elementary rule that
    construction of a section is to be made of
    all parts together. It is not permissible to
    omit any part of it. For, the principle that
    the statute must be read as a whole is
    equally applicable to different parts of the
    same section.‟

    This principle was reiterated by this Court in
    Kalawatibai Vrs. Soiryabai, (1991) 3 SCC 410:

    „6. *** It is well settled that a section has to
    be read in its entirety as one composite
    unit without bifurcating it or ignoring any
    part of it.‟ ***”

    9.27. On the basis of said principle, when Rule A of the
    Appendix-XXXIV of the OPWD Code, Volume-II is
    studied, it manifests that from sub-rules (a) to (g) of Rule
    A contains independent ground mentioned in each sub-
    rule. Each ground contained in each sub-rule is distinct
    from one and the other. Sub-rules (a) to (g) comprehend
    W.P.(C) No.8589 of 2024 Page 60 of 89
    different identifiable circumstance/event/ground in each
    sub-rule. In that sense, sub-rule (c) of Rule A is to be
    read as one composite whole.

    9.28. The Show Cause Notice and the order impugned do not
    contain reason as to why the reply of the petitioner did
    contain “insufficient and imaginary ground”. Cursory
    glance at replies at Annexure-13 would show that the
    petitioner has simply intimated the authority concerned
    regarding challenge being made before this Court
    against the rescission of contract; but such replies do
    not reflect that the petitioner has proffered cause of
    delay in completion of the works. If the authority
    concerned decided to discard such replies and wished to
    proceed with the matter on merit in the context of
    blacklisting the petitioner, he should have shown
    deference by issuing further intimation with more details
    eliciting the circumstances that the petitioner was
    required to explain as to its “constant non-achievement
    of milestone on insufficient and imaginary ground and
    non-adherence to quality specifications despite being
    pointed out”. If the replies dated 23.10.2023 does not
    reveal that the petitioner has offered specific explanation
    indicating both the aspects on the ground vide sub-rule

    (c) of Rule A of the Appendix-XXXIV, OPWD Code,
    Volume-II, the authority should have shown alacrity by
    issuing further notice by mentioning specific instance/

    W.P.(C) No.8589 of 2024 Page 61 of 89
    ground to which the petitioner was required to place his
    defence/explanation.

    9.29. In A.K.G. Construction and Developers Pvt. Ltd. Vrs. State
    of Jharkhand, (2026) 4 SCR 331 it has been highlighted
    as follows:

    “23. The contractual relationship between the parties is
    governed by two legal regimes. While GCC governs
    termination, the 2012 Rules govern blacklisting.
    Proceedings for termination should not be conflated
    with proceedings for blacklisting. In the latter action,
    what is at stake is the future of the contractor. A
    blacklisting order assumes that the contractor is an
    incorrigible entity, at least for some time to come, in
    this case such an assumption was intended to
    operate for five years. For giving effect to such a
    premise, there has to be sufficient evidence, clear
    application of mind and stronger adherence to
    principles of natural justice7. The blacklisting order
    dated 23.08.2004 falls short of this requirement and
    is liable to be set aside.”

    9.30. Hence, the order dated 30.03.2024 passed by the Chief
    Engineer, Bridges (WBP), Odisha cannot withstand
    judicial scrutiny.

    10. Reading of order dated 30.03.2024 of the Chief
    Engineer, Bridges (WBP), Odisha debarring the
    petitioner for six years manifests that he has invoked

    7 Kulja Industries Ltd. Vrs. Chief General Manager, Western Telecom Project BSNL,
    (2014) 14 SCC 731; Blue Dreamz Advertising (P) Ltd. Vrs. Kolkata Municipal
    Corporation, (2024) 15 SCC 264, Techno Prints Vrs. Chhattisgarh Textbook
    Corporation, (2025) 3 SCR 208.

    W.P.(C) No.8589 of 2024 Page 62 of 89

    Rule D of Appendix-XXXIV as amended by virtue of
    Office Memorandum, dated 26.11.2021. As per such
    amended provision, the blacklisting period per offence
    shall be limited to three years subject to an overall
    maximum cumulative period of ten years for multiple
    offences. Neither Show Cause Notices nor does the order
    impugned reveal that there was any proposition to
    initiate proceeding to impose punishment for cumulative
    period with respect to multiple “offences” attracting
    Codal Provisions for banning/blacklisting contractor.

    10.1. The term “offence” as found place in Rule D of Appendix-

    XXXIV has not been defined in the OPWD Code. The
    Hon’ble Supreme Court of India in the case of Standard
    Chartered Bank Vrs. Directorate of Enforcement, (2006) 4
    SCC 278 laid down the interpretation of “offence” in
    absence of definition in the following manner:

    “29. Both, Section 50 providing for imposition of penalty
    and Section 56 providing for prosecution, speak of
    contravention of the provisions of the Act.
    Contravention is the basic element. The
    contravention makes a person liable both for penalty
    and for prosecution. Even though the heading to
    Section 56 refers to offences and prosecutions, what
    is made punishable by the section is the
    contravention of the provisions of the Act and the
    prosecution is without prejudice to any award of
    penalty. The award of penalty is also based on the
    same contravention. Section 63 confers the power of

    W.P.(C) No.8589 of 2024 Page 63 of 89
    confiscation of currency, security or any other money
    or property in respect of which a contravention of the
    provisions of the Act has taken place conferred
    equally on the adjudicating authority and the court,
    whether it be during an adjudication of the penalty
    or during a prosecution. Whereas Section 64(1)
    relating to preparation or attempt at contravention is
    confined to Section 56, the provision for prosecution,
    sub-section (2) of Section 64 makes the attempt to
    contravene or abetment of contravention, itself a
    contravention, for the purposes of the Act including
    an adjudication of penalty under the Act. Section 68
    relating to offences by companies, by sub-section (1)
    introduces a deeming provision that the person who
    was in charge of and was responsible to the
    company for the conduct of the business of the
    company, shall also be deemed to be guilty along
    with the company of the contravention of the
    provisions of the Act and liable to be proceeded
    against and punished accordingly. The proviso, no
    doubt, indicates that a person liable to punishment
    could prove that the contravention took place without
    his knowledge or that he exercised all due diligence
    to prevent such contravention. Sub-section (2) again
    speaks only of a contravention of the provisions of
    the Act and the persons referred to in that sub-
    section are also to be deemed to be guilty of the
    contravention and liable to be proceeded against
    and punished accordingly.

    The word “offence” is not defined in the Act.
    According to Concise Oxford English Dictionary, it
    means, “an act or instance of offending”. Offend
    means, “commit an illegal act” and illegal means,
    “contrary to or forbidden by law”. According to New

    W.P.(C) No.8589 of 2024 Page 64 of 89
    Shorter Oxford English Dictionary, an offence is “a
    breach of law, rules, duty, propriety, etiquette, an
    illegal act, a transgression, sin, wrong,
    misdemeanour, misdeed, fault”. Thus, an offence
    only means the commission of an act contrary to or
    forbidden by law. It is not confined to the
    commission of a crime alone. It is an act committed
    against law or omitted where the law requires it and
    punishable by it. In its legal signification, an offence
    is the transgression of a law; a breach of the laws
    established for the protection of the public as
    distinguished from an infringement of mere private
    rights; a punishable violation of law, a crime, the
    doing that which a penal law forbids to be done or
    omitting to do what it commands (see P. Ramanatha
    Aiyar‟s Advanced Law Lexicon, 3rd Edn., 2005, p.
    3302).

    This Court in Depot Manager, Andhra Pradesh State
    Road Transport Corporation Vrs. Mohd. Yousuf
    Miya, (1997) 2 SCC 699 stated that the word
    “offence” generally implies infringement of a public
    duty, as distinguished from mere private rights
    punishable under criminal law.

    In Brown Vrs. Allweather Mechanical Co., (1954) 2
    QB 443 = (1953) 1 All ER 474 = (1953) 2 WLR 402
    (DC) it was described as: (All ER p. 476 A-B)

    A failure to do something prescribed by a statute
    may be described as an offence, though no criminal
    sanction is imposed but merely a pecuniary sanction
    recoverable as a civil debt.

    The expression “offence” as defined in Section 3(38)
    of the General Clauses Act means an act or omission

    W.P.(C) No.8589 of 2024 Page 65 of 89
    made punishable by any law for the time being in
    force.

    “Punishable” as noticed by this Court in Sube Singh
    Vrs. State of Haryana, (1989) 1 SCC 235 is
    ordinarily defined as deserving of, or capable or
    liable to punishment. According to Concise Oxford
    English Dictionary, “punish” means, “inflict a
    penalty on as retribution for an offence, inflict a
    penalty on someone for (an offence)”.

    In New Shorter Oxford English Dictionary (Vol. 2, 3rd
    Edn., reprint 1993), the meaning of “punishment” is
    given as, “infliction of a penalty in retribution for an
    offence; penalty imposed to ensure application and
    enforcement of a law”.

    Going by Black‟s Law Dictionary (8th Edn.) it is:

    “A sanction– such as a fine, penalty, confinement,
    or loss of property, right, or privilege– assessed
    against a person who has violated the law.”

    According to Jowitts Dictionary of English Law, Vol.
    2, (2nd Edn. by John Burke), punishment is the
    penalty for transgressing the law.

    It is significant to notice that Section 68, both in sub-
    section (1) and in sub-section (2) uses the
    expression, shall be liable to be proceeded against
    and punished accordingly. There does not appear to
    be any reason to confine the operation of Section 68
    only to a prosecution and to exclude its operation
    from a penalty proceeding under Section 50 of the
    Act, since the essential ingredient of both is the
    contravention of the provisions of the Act. A
    company is liable to be proceeded against under
    W.P.(C) No.8589 of 2024 Page 66 of 89
    both the provisions. Section 68 is only a provision
    indicating who all in addition can be proceeded
    against when the contravention is by a company or
    who all should or could be roped in, in a
    contravention by a company. Section 68 only
    clarifies the nature and mode of proceeding when
    the contravention of any of the provisions of the Act
    is by a company, whether it be by way of
    adjudication to impose a penalty or by way of
    prosecution leading to imprisonment and a fine.”

    10.2. In Black‟s Law Dictionary by Henry Campbell Black,
    Revised Fourth Edition [St. Paul, Minn., West Publishing
    Co., 1968] the meaning of the terms “cumulative”,
    “cumulative punishment” and “cumulative sentences”

    have been described as follows:

    “Cumulative.– Additional; heaping up; increasing;
    forming an aggregate. The word signifies that two things
    are to be added together, instead of one being a repetition
    or in substitution of the other. People Vrs. Superior Court,
    10 Wend., N.Y., 285; Regina Vrs. Eastern Archipelago,
    Co., 18 Eng. Law & Eq. 183.

    Cumulative punishment.–

    An increased punishment inflicted for a second or third
    conviction of the same offense, under the statutes relating
    to habitual criminals. State Vrs. Hambly, 126 N.C. 1066,
    35 S.E. 614.

    Cumulative sentences.– Separate sentences (each
    additional to the others) imposed upon a defendant who
    has been convicted upon an indictment containing several
    counts, each of such counts charging a distinct offense, or
    W.P.(C) No.8589 of 2024 Page 67 of 89
    who is under conviction at the same time for several
    distinct offenses; one of such sentences being made to
    begin at the expiration of another. Carter Vrs. Mc-
    Claughry, 22 S.Ct. 181, 183 U.S. 365, 46 L.Ed. 236.”

    10.3. Thus being conspectus of the terms “offence”,
    “cumulative”, “cumulative offence”, and “cumulative
    sentences”, there can be no confusion rests in mind that
    there must first be a recording of finding that the
    various offences are charged and proved/established by
    clear evidence vis-à-vis explanation by the defender and
    such offences warrants imposition of punishments/
    penalties to be treated cumulatively. Ground contained
    in sub-rule (c) of Rule A of Appendix-XXXIV of the OPWD
    Code, Volume-II is clear indication that the twin
    conditions enumerated therein are required to be
    fulfilled before taking action for banning/blacklisting/
    debarring for more than one offence contemplated in the
    introduced provision by virtue of Office Memorandum
    dated 26.11.2021.

    10.4. It may be pertinent to have regard to the interpretation
    of penal provisions as reiterated in Fuleshwar Gope Vrs.
    Union of India, (2024) 10 SCR 315:

    “31. It is well understood that penal statutes are statutes
    to be interpreted strictly. This canon of construction
    has been reiterated time and again. It is apposite
    here to refer to certain authorities in this context.

    W.P.(C) No.8589 of 2024 Page 68 of 89

    31.1 Maxwell in The Interpretation of Statutes (11th Edn.)
    has observed:

    „The effect of the rule of strict construction might
    almost be summed up in the remark that, where an
    equivocal word or ambiguous sentence leaves a
    reasonable doubt of its meaning which the cannons
    of interpretation failed to solve, the benefit of the
    doubt should be given to the subject and against the
    legislature which has failed to explain itself. But it
    yields to the paramount rule that every statute is to
    be expounded according to its expressed or manifest
    intention and that all cases within the mischief
    aimed at our, if the language permits, to be held to
    fall within its remedial influence‟

    Observations in the twelfth edition, in this context,
    are also educative:

    „The strict construction of penal statutes seems
    to manifest itself in four ways: In the
    requirement of express language for the creation of
    an offence; in interpreting strictly words setting out
    the elements of an offence; in requiring the
    fulfillment to the letter of statutory conditions
    precedent to the infliction of punishment; and in
    insisting on the strict observance of technical
    provisions concerning criminal procedure and
    jurisdiction.‟ ***”

    10.5. Show Cause Notices dated 18.10.2023 (Annexure-11)
    and consequent order dated 30.03.2024 (Annexure-1) do
    not transpire that the authority has returned any finding
    as to “offence” being committed by the petitioner and
    there was scope in the circumstances to impose
    W.P.(C) No.8589 of 2024 Page 69 of 89
    penalties/punishments like debarment/blacklisting to
    have cumulative effect. In absence of such finding being
    recorded on the material available on record, this Court
    is of the opinion that the circumstances did not exist
    warranting the petitioner to ban “from participating or
    bidding for any work to be undertaken by the
    Government of Odisha” and “from transacting business
    with the Government of Odisha directly, in the name of
    proprietary bidder or indirectly under different name or
    title” for a period of “six years”.

    10.6. In absence of proper, clear, unequivocal and specific
    charge being stated in the Show Cause Notices
    (Annexure-11) as indicated in the foregoing paragraphs,
    with reference to the Office Memorandum dated
    26.11.2021 the Chief Engineer proceeded on an
    erroneous approach as if the blacklisting could be
    clamped consecutively for six years (limited to three
    years per offence) at the drop of the hat. As is already
    observed that the petitioner had had no opportunity to
    justify the reasons for not being able to complete the
    works within the period stipulated, the instruction to
    complete the works by the authority concerned appears
    to be during the pandemic, i.e., 2020-21 or 2021-22. The
    reply dated 23.10.2023 cannot be construed to be
    explanation on the merit; rather it is only intimation
    regarding pendency of cases before this Court against

    W.P.(C) No.8589 of 2024 Page 70 of 89
    rescission of contract(s) by way of filing writ petitions. Be
    that be. In view of A.K.G. Construction and Developers
    Pvt. Ltd. Vrs. State of Jharkhand, (2026) 4 SCR 331 since
    it is not forthcoming that the petitioner is incorrigible
    entity upon analysis of sufficient evidence, clear
    application of mind and stronger adherence to principles
    of natural justice, it is entitled to the benefit of audi
    alteram partem and right to reason with respect to
    banning/blacklisting/debarment having impact on its
    future transactions which in the considered view of this
    Court falls within the connotation of “civil death” and
    “civil consequences”.

    10.7. In this respect the decision of the Hon’ble Supreme
    Court of India rendered in ASP Traders Vrs. State of
    Uttar Pradesh, (2025) 7 SCR 1462 may be pertinent to
    derive guidelines for the administrative authorities to
    proceed with the Show Cause Notice. The following
    summation of principles as propounded in the said
    reported case may be taken as guidelines in the present
    matter:

    “18. The principles of natural justice mandate that when
    a taxpayer submits a response to a show cause
    notice, the adjudicating authority is required to
    consider such response and render a reasoned,
    speaking order. This is not a mere procedural
    formality, but a substantive safeguard ensuring
    fairness in quasi-judicial proceedings. The right to

    W.P.(C) No.8589 of 2024 Page 71 of 89
    appeal under Section 107 of the CGST Act, 2017, is
    predicated upon the existence of a formal
    adjudication. An appeal can lie only against an
    „order‟, and in the absence of a reasoned order
    passed under Section 129(3) of the Act, the taxpayer
    is effectively deprived of the statutory remedy of
    appeal. Such a deprivation undermines the
    foundational principles of fairness, due process, and
    access to justice, rendering the right of appeal
    illusory or nugatory. It is now settled law that failure
    to issue a speaking order in response to a show
    cause notice creates a legal vacuum. Any
    consequential action including imposition of tax or
    penalty, would then be unsupported by authority of
    law, thereby potentially violating Article 265 of the
    Constitution of India, which prohibits the levy or
    collection of tax except by authority of law.

    18.1. In this context, useful guidance may be drawn from
    the decision in M/s. Kranti Associates (P) Ltd & Anr.
    Vrs. Masood Ahmed Khan & Ors., (2010) 9 SCC 496,
    wherein, this Court emphasized that fairness,
    transparency, and accountability are inseparable
    from the duty to provide reasons. The Court held
    that failure to furnish reasons violates the principles
    of natural justice and renders the right of appeal or
    judicial review illusory. In paragraph 51 of the
    judgment, the Court distilled the following key
    principles:

    „a. In India the judicial trend has always been to
    record reasons, even in administrative
    decisions, if such decisions affect anyone
    prejudicially.

    W.P.(C) No.8589 of 2024 Page 72 of 89

    b. A quasi-judicial authority must record reasons
    in support of its conclusions.

    c. Insistence on recording of reasons is meant to
    serve the wider principle of justice that justice
    must not only be done it must also appear to be
    done as well.

    d. Recording of reasons also operates as a valid
    restraint on any possible arbitrary exercise of
    judicial and quasi-judicial or even
    administrative power.

    e. Reasons reassure that discretion has been
    exercised by the decision maker on relevant
    grounds and by disregarding extraneous
    considerations.

    f. Reasons have virtually become as
    indispensable a component of a decision
    making process as observing principles of
    natural justice by judicial, quasi-judicial and
    even by administrative bodies.

    g. Reasons facilitate the process of judicial review
    by superior Courts.

    h. The ongoing judicial trend in all countries
    committed to rule of law and constitutional
    governance is in favour of reasoned decisions
    based on relevant facts. This is virtually the life
    blood of judicial decision making justifying the
    principle that reason is the soul of justice.

    i. Judicial or even quasi-judicial opinions these
    days can be as different as the judges and
    authorities who deliver them. All these

    W.P.(C) No.8589 of 2024 Page 73 of 89
    decisions serve one common purpose which is
    to demonstrate by reason that the relevant
    factors have been objectively considered. This
    is important for sustaining the litigants‟ faith in
    the justice delivery system.

    j. Insistence on reason is a requirement for both
    judicial accountability and transparency.

    k. If a Judge or a quasi-judicial authority is not
    candid enough about his/her decision making
    process then it is impossible to know whether
    the person deciding is faithful to the doctrine of
    precedent or to principles of incrementalism.

    l. Reasons in support of decisions must be
    cogent, clear and succinct. A pretence of
    reasons or „rubber-stamp reasons‟ is not to be
    equated with a valid decision making process.

    m. It cannot be doubted that transparency is the
    sine qua non of restraint on abuse of judicial
    powers. Transparency in decision making not
    only makes the judges and decision makers
    less prone to errors but also makes them
    subject to broader scrutiny. (See David Shapiro
    in Defence of Judicial Candor (1987) 100
    Harward Law Review 731-737).

    n. Since the requirement to record reasons
    emanates from the broad doctrine of fairness in
    decision making, the said requirement is now
    virtually a component of human rights and was
    considered part of Strasbourg Jurisprudence.
    See (1994) 19 EHRR 553, at 562 para 29 and
    Anya vs. University of Oxford, 2001 EWCA Civ

    W.P.(C) No.8589 of 2024 Page 74 of 89
    405, wherein the Court referred to Article 6 of
    European Convention of Human Rights which
    requires, “adequate and intelligent reasons
    must be given for judicial decisions”.

    o. In all common law jurisdictions judgments play
    a vital role in setting up precedents for the
    future. Therefore, for development of law,
    requirement of giving reasons for the decision
    is of the essence and is virtually a part of “Due
    Process”.”

    19. Therefore, even assuming that the payment was
    made by the appellant, voluntarily or otherwise, the
    proper officer could not be absolved of the statutory
    obligation to pass a reasoned order in Form GST
    MOV-09 and upload the corresponding summary in
    Form GST DRC-07. Compliance with these
    procedural requirements is essential not only for
    ensuring transparency and accountability in tax
    administration, but also for safeguarding the
    taxpayer‟s appellate rights under the CGST Act,
    2017
    . Such adherence is in consonance with the
    constitutional mandate under Article 265 of the
    Constitution of India.”

    Conclusion:

    11. As discussed supra neither the order dated 30.03.2024
    (Annexure-1) nor the Show Cause Notices dated
    18.10.2023 (Annexure-11) indicate the grounds for
    blacklisting in terms of Rule A of Appendix-XXXIV of
    OPWD Code in clear and unequivocal terms. The Show
    Cause Notices are silent about existence of twin

    W.P.(C) No.8589 of 2024 Page 75 of 89
    conditions as a ground envisaged in sub-rule (a) of Rule
    A for blacklisting nor is there any finding of fact
    returned in the impugned order to show such ground
    (twin conditions) established. Therefore, this matter
    deserves intervention.

    11.1. The ban/debarment/blacklisting is construed as “civil
    death” having substantial impact on the fundamental
    right to carry on business as envisioned under Article
    19(1)(g)
    of the Constitution of India, and as such penal
    action leads to civil or evil consequence, the provisions
    vesting power on the authority to impose penalties are
    required to be conceived strictly.

    11.2. It is true that penal provisions must be strictly
    construed; but having regard to the nature of the offence
    involved, such strict construction may be refused to be
    adopted. Looking to the gravity of offence, narrow and
    pedantic, literal and lexical construction of penal
    provisions can be eschewed. Reference may be had to
    Murlidhar Meghraj Loya Vrs. State of Maharashtra, (1976)
    3 SCC 684 and Kisan Trimbak Kothula Vrs. State of
    Maharashtra, (1977) 1 SCC 300. Having regard to the
    intent of the OPWD Code, harmonious construction may
    be adhered to while invoking the provisions of Appendix-

    XXXIV so as to strike a balance between the right of the
    contractee-Government and the right of the contractor.

    W.P.(C) No.8589 of 2024 Page 76 of 89

    11.3. This apart, one must bear in mind that Codal Provisions
    in Appendix-XXXVI is part of the OPWD Code, which are
    executive instructions and mere procedures facilitating
    smooth functioning of works entrusted to the
    contractors. It is well settled that procedural laws must
    be liberally construed to serve as handmaid of justice
    and not as its mistress. [See, Sardar Amarjit Singh Kalra
    Vrs. Pramod Gupta, (2003) 3 SCC 272, N. Balaji Vrs.
    Virendra Singh, (2004) 8 SCC 312 and Kailash Vrs.
    Nanhku, (2005) 4 SCC 480].

    11.4. In G.J. Fernandez Vrs. State of Mysore, (1967) 3 SCR 636
    = AIR 1967 SC 1753 it has been observed thus:

    “12. Taking first the contention with respect to the Code
    not being followed in the matter of tenders, the
    question that arises is whether this Code consists of
    statutory rules or not. The High Court has observed
    that the so-called rules in the Code are not framed
    either under any statutory enactment or under any
    provision of the Constitution. They are merely in the
    nature of administrative instructions for the
    guidance of the department and have been issued
    under the executive power of the State. Even after
    having said so, the High Court has considered
    whether the instructions in the Code were followed
    in the present case or not. Before however we
    consider the question whether instructions in the
    Code have been followed or not, we have to decide
    whether these instructions have any statutory force.
    If they have no statutory force, they confer no right
    on any body and a tenderer cannot claim any rights
    W.P.(C) No.8589 of 2024 Page 77 of 89
    on the basis of these administrative instructions. If
    these are mere administrative instructions it may be
    open to Government to take disciplinary action
    against its servants who do not follow these
    instructions but non-observance of such
    administrative instructions does not in our opinion
    confer any right on any member of the public like a
    tenderer to ask for a writ against Government by a
    petition under Article 226. The matter may be
    different if the instructions contained in the Code are
    statutory rules. Learned counsel for the appellant is
    unable to point out any statute under which these
    instructions in the Code were framed. He also
    admits that they are administrative instructions by
    Government to its servants relating to the Public
    Works Department. But his contention is that they
    are rules issued under Article 162 of the
    Constitution. Now Article 162 provides that
    “executive power of a State shall extend to the
    matters with respect to which the legislature of the
    State has power to make laws”. This Article in our
    opinion merely indicates the scope of the executive
    power of the State; it does not confer any power on
    the State Government to issue rules thereunder. As
    a matter of fact wherever the Constitution envisages
    issue of rules it has so provided in specific terms.
    We may for example, refer to Article 309, the proviso
    to which lays down in specific terms that the
    President or the Governor of a State may make rules
    regulating the recruitment and the conditions of
    service of persons appointed to services and posts
    under the Union or the State. We are therefore of
    opinion that Article 162 does not confer any power
    on the State Government to frame rules and it only
    indicates the scope of the executive power of the
    W.P.(C) No.8589 of 2024 Page 78 of 89
    State. Of course, under such executive power, the
    State can give administrative instructions to its
    servants how to act in certain circumstances; but
    that will not make such instructions statutory rules
    which are justiciable in certain circumstances. In
    order that such executive instructions have the force
    of statutory rules it must be shown that they have
    been issued either under the authority conferred on
    the State Government by some statute or under
    some provision of the Constitution providing therefor.
    It is not in dispute that there is no statute which
    confers any authority on the State Government to
    issue rules in matters with which the Code is
    concerned; nor has any provision of the Constitution
    been pointed out to us under which these
    instructions can be issued as statutory rules except
    Article 162. But as we have already indicated,
    Article 162 does not confer any authority on the
    State Government to issue statutory rules. It only
    provides for the extent and scope of the executive
    power of the State Government, and that coincides
    with the legislative power of the State Legislature.
    Thus under Article 162, the State Government can
    take executive action in all matters in which the
    legislature of the State can pass laws. But Article
    162
    itself does not confer any rule making power on
    the State Government in that behalf. We are
    therefore of opinion that instructions contained in the
    Code are mere administrative instructions and are
    not statutory rules. Therefore even if there has been
    any breach of such executive instructions that does
    not confer any right on the appellant to apply to the
    court for quashing orders in breach of such
    instructions. It is unnecessary for us to decide
    whether there has been in fact a breach of any
    W.P.(C) No.8589 of 2024 Page 79 of 89
    instruction contained in the Code with respect to
    tenders and we do not therefore so decide. But
    assuming that there has been any breach that is a
    matter between the State Government and its
    servant, and the State Government may take
    disciplinary action against the servant concerned
    who disobeyed these instructions. But such
    disobedience did not confer any right on a person
    like the appellant, to come to court for any relief
    based on the breach of these instructions. It is for
    this reason that we are not referring to the Code,
    though the High Court did consider whether there
    was any breach of these administrative instructions
    and came to the conclusion that there was no
    breach. In the view we take it is unnecessary for us
    to consider this, for we are of opinion that no claim
    for any relief before a court of law can be founded
    by a member of the public, like the appellant, on the
    breach of mere administrative instructions.”

    11.5. In P. Tulsi Das Vrs. Government of Andhra Pradesh,
    (2002) Supp.3 SCR 306 it has been laid down as follows:

    “On a careful consideration of the principles laid down in
    the above decisions in the light of the fact situation in
    these appeals we are of the view that they squarely apply
    on all fours to the cases on hand in favour of the
    appellants. The submissions on behalf of the respondent-
    State that the rights derived and claimed by the
    appellants must be under any statutory enactment or
    Rules made under Article 309 of the Constitution of India
    and that in other respects there could not be any
    acquisition of rights validly, so as to disentitle the State to
    enact the law of the nature under challenge to set right
    serious anomalies which crept in and deserved to
    W.P.(C) No.8589 of 2024 Page 80 of 89
    undone, does not merit our acceptance. It is by now well
    settled that in the absence of Rules under Article 309 of
    the Constitution in respect of a particular area, aspect or
    subject, it was permissible for the State to make
    provisions in exercise of its executive powers under Article
    162
    which is co-extensive with its Legislative powers
    laying conditions of service and rights accrued to or
    acquired by a citizen would be as much rights acquired
    under law and protected to that extent. The orders passed
    by the Government, from time to time beginning from
    February 1967 till 1985 and at any rate upto the passing
    of the Act, to meet the administrative exigencies and cater
    to the needs of public interest really and effectively
    provided sufficient legal basis for the acquisition of rights
    during the period when they were in full force and effect.
    The orders of the High Court as well as the Tribunal also
    recognised and upheld such rights and those orders
    attained finality without being further challenged by the
    Government, in the manner known to law. Such rights,
    benefits and perquisites acquired by the Teachers
    concerned cannot be said to be rights acquired otherwise
    than in accordance with law or brushed aside and
    trampled at the sweet will and pleasure of the
    Government, with impunity. Consequently we are unable
    to agree that the Legislature could have validly denied
    those rights acquired by the appellants retrospectively,
    not only depriving them of such rights but also enact a
    provision to repay and restore the amounts paid to them
    to State. The provisions of the Act, though can be valid in
    its operation „in futuro‟ cannot be held valid in so far as it
    purports to restore status quo ante for the past period
    taking away the benefits already available, accrued and
    acquired by them. For all the reasons stated above the
    reasons assigned by the majority opinion of the Tribunal
    could not be approved in our hands. The provisions of
    W.P.(C) No.8589 of 2024 Page 81 of 89
    Section 2 and 3(a) insofar as they purport to take away
    the rights from 10.02.1967 and obligates those who had
    them to repay or restore it back to the State is hereby
    struck down as arbitrary, unreasonable and
    expropriatory and as such is violative of Articles 14 and
    16 of the Constitution of India. No exception could be
    taken, in our view, to the prospective exercise of powers
    thereunder without infringing the rights already acquired
    by the appellants and the category of the persons
    similarly situated whether approached courts or not
    seeking relief individually. The provisions contained in
    Section 2 have to be read down so as to make it only
    prospective, to save the same from the unconstitutionality
    arising out of its retrospective application.”

    11.6. In the case of R. Sai Bharathi Vrs. J. Jayalalitha, (2003)
    Supp.6 SCR 85, the Hon’ble Supreme Court held:

    “Even if the Government order is traced to have been
    issued under executive power of the State under
    Article 162, such a Code will not be enforceable
    when the language used is not in mandatory terms
    and they are intended to be mere guidelines or
    instructions to the concerned persons in authority.
    Therefore, as long as such a Code of Conduct is not
    enforceable in any court of law and does not even provide
    what action could possibly be taken in case of breach by
    the Chief Minister, the prohibition contained therein is
    only having ethical or moral effect and any breach thereof
    cannot be treated to be unlawful or even illegal within the
    meaning of Section 43 IPC. To constitute a ground for civil
    action under Section 43, there must be a right in a party
    which can be enforced. It may be a breach of contract or a
    claim for damages or some such similar right accruing
    under any law. There is no law which debars the Chief
    W.P.(C) No.8589 of 2024 Page 82 of 89
    Minister from participating in a sale conducted by any
    Department of the Government or any of the Corporations
    or any public sector undertaking affording a cause for civil
    action especially when no fraud or illegal gain .is
    involved. Therefore, we are constrained to hold that the
    offence under the aforesaid provision has not been
    established. In fact, there is nothing in the charge to
    indicate nor did the prosecution take a specific stand at
    any stage of the trial that the purchase of T ANSI foundry
    property by A-I from the Government would furnish a
    ground for a particular civil action. The nature of civil
    action that could be initiated cannot be left to the guess
    work and the accused cannot be expected to meet such
    case at this stage.”

    11.7. Thus, with the above conspectus of legal position with
    respect to executive instructions compiled in the form of
    a Code (here OPWD Code), they are construed to be
    guidelines to the authorities of the Departments of the
    Government and the language of any of such
    instructions is in the nature of mandatory character, the
    authority is obligated to strictly adhere to the same.
    While the provisions dealing with procedural aspect
    conferring power to invoke authority and arrive at the
    conclusion are procedural in nature which can be
    construed liberally, the provision enabling the authority
    to impose penalty like banning/blacklisting/debarring is
    to be interpreted strictly as the same would involve civil
    or evil consequence having restrictive impact on the
    business of the contractor offending Article 14 read with

    W.P.(C) No.8589 of 2024 Page 83 of 89
    Article 19(1)(g) of the Constitution of India. Any decision
    to blacklist/debar a contractor from participating in
    tenders need to be taken strictly within the parameters
    of law and has to comport with the principle of
    proportionality.

    11.8. Such view has explicitly been stated in Blue Dreamz
    Advertising (P) Ltd. Vrs. Kolkata Municipal Corporation,
    (2024) 15 SCC 264 with the following observations:

    “24. What is significant is that while setting out the
    guidelines prescribed in USA, the Court noticed that
    comprehensive guidelines for debarment were
    issued there for protecting public interest from those
    contractors and recipients who are non-responsible,
    lack business integrity or engage in dishonest or
    illegal conduct or are otherwise unable to perform
    satisfactorily. The illustrative cases set out also
    demonstrate that debarment as a remedy is to be
    invoked in cases where there is harm or potential
    harm for public interest particularly in cases where
    the person‟s conduct has demonstrated that
    debarment as a penalty alone will protect public
    interest and deter the person from repeating his
    actions which have a tendency to put public interest
    in jeopardy. In fact, it is common knowledge that in
    notice inviting tenders, any person blacklisted is
    rendered ineligible. Hence, blacklisting will not only
    debar the person concerned from dealing with the
    employer concerned, but because of the
    disqualification, their dealings with other entities
    also is proscribed. Even in the terms and conditions
    of tender in the present case, one of the conditions of
    W.P.(C) No.8589 of 2024 Page 84 of 89
    eligibility is that the agency should not be
    blacklisted from anywhere.

    25. In other words, where the case is of an ordinary
    breach of contract and the explanation offered by
    the person concerned raises a bona fide dispute,
    blacklisting/debarment as a penalty ought not to be
    resorted to. Debarring a person albeit for a certain
    number of years tantamounts to civil death
    inasmuch as the said person is commercially
    ostracised resulting in serious consequences for the
    person and those who are employed by him.

    26. Too readily invoking the debarment for ordinary
    cases of breach of contract where there is a bona
    fide dispute, is not permissible. Each case, no doubt,
    would turn on the facts and circumstances thereto.

    27. Examining the facts of this case from that
    perspective, we find that the appellant, after the
    award of the tender, has admittedly paid an amount
    of Rs.3,71,96,265, though, according to the
    Corporation, the outstanding amount as on the date
    of the debarment was Rs.14,63,24,727. However,
    as would be clear from the facts discussed
    hereinabove, right from the inception there have
    been issues between the appellant and the
    Corporation with regard to the fulfilment of the
    reciprocal obligations in the bid document. There has
    been exchange of correspondence between the
    parties with each side blaming the other for not
    performing the reciprocal obligations. While the
    appellant had a case with regard to the non-
    issuance of work orders; non-receipt of formal format
    of bank guarantee; refusal of no-objection certificate
    for obtaining connection from Calcutta Electric
    W.P.(C) No.8589 of 2024 Page 85 of 89
    Supply Corporation Ltd.; existence of only 200 out of
    250 allotted street hoardings and so on
    demonstrating breach of obligations by the
    Corporation, the Corporation had a case that bank
    guarantee was not the mode of payment and as
    such there was no reason to insist on bank
    guarantee; that in the joint inspection the appellant’s
    men failed to cover all the areas and thereafter
    when the appellant was asked to submit a list of
    allotted location, the appellant failed to furnish the
    same and further there was huge default on the part
    of the appellant.

    28. Even in the order dated 02.03.2016 by which the
    appellant was debarred for a period of five years,
    the reason given is that the tender notice had clearly
    stated that the street hoardings in the annexures
    would be allotted on “as is where is” basis; that the
    company having understood the scope and effect of
    the terms and conditions of the notice accepted the
    award; that “no-objection certificate” is not required
    in respect of the existing hoardings; that there was
    no document to show that the company had applied
    to Calcutta Electric Supply Corporation Ltd. for
    connection and that it appeared to the Corporation
    that the company did not have the financial capacity
    to pay and as such the company was creating
    problems on one pretext or the other since obtaining
    the allotment of sites. The order also stated that the
    appellant had set up a bad example to others having
    interest to enjoy the advertisement rights.

    29. All these reasons fall far short of rendering the
    conduct of the appellant in the present case, so
    abhorrent as to justify the invocation of the drastic

    W.P.(C) No.8589 of 2024 Page 86 of 89
    remedy of blacklisting/debarment. The appellant
    very clearly has been subjected to a
    disproportionate penalty. The Corporation has lifted
    a sledgehammer to crack a nut. We disapprove of
    the said course of action on the facts of this case.

    ***

    34. The Division Bench has, in our opinion, not
    appreciated the case in its proper perspective.
    Merely saying that the blacklisting order carried
    reasons is not good enough. Do the reasons justify
    the invocation of the penalty of blacklisting and is
    the penalty proportionate, was the real question.

    35. The Division Bench has observed that blacklisting is
    a business decision by which the party affected by
    the breach decides not to enter into any contractual
    relationship with the party committing the breach. It
    also observed that between two private parties the
    right to take any such decision is absolute and
    untrammelled by any constraints whatsoever. The
    observations are too sweeping in their ambit and
    wholly overlook the fact that the respondent
    Corporation is a statutory body vested with the duty
    to discharge public functions. It is not a private
    party. Any decision to blacklist should be strictly
    within the parameters of law and has to comport
    with the principle of proportionality.

    36. The Division Bench having noticed the fact that any
    decision to blacklist will be open to scrutiny on the
    anvil of the doctrine of proportionality has failed to
    apply the principle to the facts of the case in the
    correct perspective. The Division Bench has also
    failed to correctly appreciate the ratio of the decision

    W.P.(C) No.8589 of 2024 Page 87 of 89
    in B.S.N. Joshi & Sons Ltd. Vrs. Nair Coal Services
    Ltd., (2006) 11 SCC 548.

    37. There has been no enquiry by the Division Bench as
    to whether the conduct of the appellant was part of
    the normal vicissitudes in business and common
    place hazards in commerce or whether the appellant
    had crossed the rubicon warranting a banishment
    order, albeit for a temporary period in larger public
    interest.”

    11.9. In the wake of the above the order dated 30.03.2024
    passed by the Chief Engineer, Bridges (WBP), Odisha
    (Annexure-1) cannot be held to be tenable in the eye of
    law and hence, the same is hereby quashed and set
    aside. The matter is thus reverted to the stage of Show
    Cause Notices dated 18.10.2023. However, liberty is
    reserved to the petitioner to file reply to Show Cause
    Notices and the authority may take this opportunity to
    intimate the petitioner about existence of twin
    conditions in clear, unambiguous and specific terms, if
    such material is available on record, so that proper
    defence/explanation can be prepared and reasons
    explaining the ground suggested by the opposite parties
    for banning/blacklisting/debarring can be cited.

    11.10. In such event the authority concerned would be
    required to consider such explanation and afford the
    petitioner opportunity of hearing. After adhering to
    formalities required for adhering to the principles of

    W.P.(C) No.8589 of 2024 Page 88 of 89
    natural justice, appropriate action may be taken by the
    authority assigning reason for such decision.

    11.11. Needless to observe that the decision taken thereon
    shall be communicated to the petitioner forthwith. It is
    clarified that until the ground(s) are examined in the
    light of discussions made above and appropriate finding
    is recorded thereon, the order of banning/blacklisting/
    debarment ceases to operate.

    12. In the result, finding merit in the writ petition the same
    is allowed to the above extent and pending Interlocutory
    Application(s), if any, shall stand disposed of, but in the
    circumstances, there shall be no order as to costs.

    
    
                                        I agree
    
    
    
                                         (HARISH TANDON)                         (MURAHARI SRI RAMAN)
                                          CHIEF JUSTICE                                JUDGE
    
    
    
    
    Signature Not
    Verified
    Digitally Signed
    Signed by: ASWINI KUMAR
    SETHY
    Designation: PERSONAL
    ASSISTANT (SECY I/C)
    Reason: Authentication
                                 High Court of Orissa, Cuttack
    Location: ORISSA HIGH
    COURT, CUTTACK
    

    The 20th May, 2026/Aswini/Bichi/MRS/Laxmikant
    Date: 20-May-2026 19:29:08

    W.P.(C) No.8589 of 2024 Page 89 of 89



    Source link

    LEAVE A REPLY

    Please enter your comment!
    Please enter your name here