Oil And Natural Gas Corporation Ltd vs Newton Engineering And Chemicals … on 30 April, 2026

    0
    26
    ADVERTISEMENT

    Bombay High Court

    Oil And Natural Gas Corporation Ltd vs Newton Engineering And Chemicals … on 30 April, 2026

    2026:BHC-OS:11282-DB
    
    
    
    
                      IN THE HIGH COURT OF JUDICATURE AT BOMBAY
                          ORDINARY ORIGINAL CIVIL JURISDICTION
                                            [ COMMERCIAL DIVISION ]
    
                         COMM. ARBITRATION APPEAL NO.1 OF 2026
                                          IN
                       COMM. ARBITRATION PETITION NO.648 OF 2021
    
                Oil and Natural Gas Corporation Ltd.,              ]
                A company incorporated under the                   ]
                Companies Act, 1956                                ]
                Having its registered office at :                  ]
                Pandit Deen Dayal Upadhyay                         ]
                Urja Bhavan, 5, Nelson Mandela Marg,               ]
                Vasant Kunj, New Delhi - 110 070                   ]
                            And                                    ]
                at Uran Plant, Uran - 400 702,                     ] ..Appellant/
                Maharashtra                                        ] Org. Petitioner
                                     Versus
                Newton Engineering & Chemicals Ltd.,               ]
                Being a Company incorporated under                 ]
                the Companies Act, 1956                            ]
                Having its registered office at:864/B-4            ]
                G.I.D.C., Makarpura, Baroda                        ] .. Respondent/
                Gujarat - 490 010                                  ]Org. Respondent
    
    
                Mr. Navroz Seervai, Senior Advocate, with Mr. Vishal Kanade,
                Mr. Anagh Pradhan, Ms. Aneesha Munshi, Mr. Anand Iyer,
                Ms. Palak Jain, Advocates, i/by Divya Shah Associates, for
                the Appellant-Original Petitioner.
                Mr. Mayur Khandeparkar with Mr. Bernardo Reis and
                Mr. Pratik Dixit, i/by Dr. Prem Motiramani, Advocates for the
                Respondent.
    
                        CORAM : SHREE CHANDRASHEKHAR, CJ &
                                GAUTAM A. ANKHAD, J.
    

    Judgment is reserved on : 27th March 2026
    Judgment is pronounced on : 30th April 2026

    1/35
    CARBA-1-2026-Judgment.doc
    Dixit

    SPONSORED

    ::: Uploaded on – 30/04/2026 ::: Downloaded on – 01/05/2026 05:00:53 :::
    PER, GAUTAM A. ANKHAD, J.

    This appeal impugns the judgment dated 17 th October
    2025 passed by the learned Single Judge, whereby the
    appellant’s petition under section 34 of the Arbitration and
    Conciliation Act, 1996 (“the Act”) came to be dismissed and
    the Arbitral Award dated 26th August 2021, rendered
    unanimously by a three-member Tribunal, was upheld.

    2. The respondent herein – M/s. Newton Engineering &
    Chemicals Limited was the original claimant before the
    Arbitral Tribunal, whereas the appellant – Oil & Natural Gas
    Corporation Limited (“ONGC”) was the original respondent
    before the Tribunal.

    3. The factual background in a nutshell is that the
    appellant awarded to the respondent a turnkey contract for
    modernization of the Effluent Treatment Plant (ETP) at its
    Uran Plant. The respondent submitted its bid on 7 th July
    2014, identifying M/s. UEM India Private Limited (“UEM”) as
    its technical collaborator pursuant to a Technical
    Collaboration Agreement dated 6th May 2014. The
    respondent’s bid was accepted and a Letter of Award dated
    11th May 2015 was issued, followed by execution of a contract
    on 29th March 2016 between the appellant and the
    respondent (“Contract”). The Contract expressly recorded that
    it constituted the entire agreement between the parties and
    provided for milestone-based payments along with furnishing
    of a performance bank guarantee by the respondent. UEM
    was not a party to the Contract.

    2/35

    CARBA-1-2026-Judgment.doc
    Dixit

    ::: Uploaded on – 30/04/2026 ::: Downloaded on – 01/05/2026 05:00:53 :::

    4. Disputes arose between the parties during the execution
    of the project. The appellant alleged that the respondent had
    made negligible progress and had failed to meet critical
    milestones. By a show cause notice dated 9 th May 2017, the
    appellant called upon the respondent to cure the defaults,
    complete the specified activities and demonstrate
    improvement in the execution of the project within thirty
    days, failing which the Contract would be terminated. The
    notice dated 9th May 2017 is reproduced as below:

    “WITHOUT PREJUDICE
    Oil and Natural Gas Corporation Ltd.

    MR, Uran Plant, Uran – 400 702 (India).

    MM Department – Dronagiri Bhavan,
    Navi Mumbai – 400 702.

    Tel.: 022-2723 4300 / 4302 4314
    Fax : 022 – 27222811
    No.MR/URAN/MM/L5TK/ETP/14/2013-14/UA5KC13001
    Date : 9th May 2017
    M/s. Newton Engineering and Chemicals Ltd.
    Regional Office : 504, Meadows, Sahar Plaza Complex,
    Chakala Metro Station, Andheri-Kurla Road,
    Andheri (East), Mumbai – 400 059, Maharashtra.

    Kind Attention : Shri N. Gopinath, Managing Director
    Ref. :

    1. Contract No.MR/URAN/MM/LSTK/ETP/14/2013-14/UA5KC13001
    dated 11.05.2015

    2. MOMs dated 28.02.2017, 07.03.2017, 14.03.2017, 21.03.2017,
    04.04.2017

    3. Letter no.MR/URN/ES/ETP/82/9(A) 2016-17/1159 dated 29.12.2016

    4. MOM dated 10.01.2017

    5. Letter no.MR/URN/ES/ETP/82/9(A)/2016-17/1253 dated 12.01.2017

    6. Letter no.MR/URN/ES/ETP/82/9(A)/2016-17/1357 dated 31.01.2017

    7. Letter no.MR/URN/ES/ETP/82/9(A)/2016-17/1357 dated 13.02.2017

    8. Letter no.MR/URN/ES/ETP/82/9(A)/2016-17/1545 dated 10.03.2017

    9. Letter no.PM/NECL/M-250/2017/011 dated 11.03.2017

    10. Letter no.MR/URN/ES/ETP/82/9(A)/2016-17/1561 dated 15.03.2017

    11. Letter no.MR/URN/ES/ETP/82/9(A)/2016-17/1561 dated 15.03.2017
    Subject : Termination Notice under Clause 12.4 of the Contract
    No.MR/URAN/MM/
    LSTK/ETP/14/2013-14/UA5KC13001 dated 11.05.2015.

    3/35

    CARBA-1-2026-Judgment.doc
    Dixit

    ::: Uploaded on – 30/04/2026 ::: Downloaded on – 01/05/2026 05:00:53 :::

    1. WHEREAS, Oil and Natural Gas Corporation Ltd. (hereinafter
    ONGC) entered into Contract No.MR/URAN
    MM/LSTK/ETP/14/2013-14 UA5KC13001 dated 11.05.2015
    with M/s. Newton Engineering and Chemicals Ltd. (hereinafter
    M/s.NECL) for Modernisation of ETP Plant at ONGC Uran Plant.

    2. AND WHEREAS, 23 out of total completion period of 32 months
    have passed and the overall progress in the Project is abysmally
    low at 2.01% against scheduled progress of 68.96%.

    3. AND WHEREAS, M/s. NECL has failed to resolve their dispute
    with their Technical Collaborator M/s. UEM India Pvt. Ltd.
    (hereinafter UEM) who are responsible for Basic Design &
    Engineering, Detail Engineering, Technical Collaboration
    Assistance / Services, Critical Equipment Supplies and Expert
    Supervision and which is considered as one of the reasons for
    the delay.

    4. AND WHEREAS, Execution Philosophy, Methodology and
    constructability document, overall plot plan, equipment layout
    etc. is a primary pre-requisite for execution of project which has
    not been frozen till date by NECL despite several reminders from
    ONGC/EIL.

    5. AND WHEREAS, Procurement activities, Soil testing and other
    construction activities are yet to be started.

    6. AND WHEREAS, ONGC have, during various weekly review
    meetings, expressed serious concern over slow progress of the
    Project and advised NECL to work with meticulous planning,
    mobilise full resources and sort out commercial issues with UEM
    without any more delay. (please refer Letter
    no.MR/URN/ES/ETP/82/9(A)/2016-17/1159 dated 29.12.2016
    and MOMs weekly meetings dated 28.02.2017, 07.03.2017,
    14.03.2017, 21.03.2017, 04.04.2017).

    7. AND WHEREAS, ONGC vide a number of letters addressed the
    issues to the MD of NECL on the matter but they failed to sort out
    matter with their Technical Collaborator i.e. UEM and
    Engineering remained an area of concern: Letter
    no.MR/URNES/ETP/82/9(A) 2016-17/1159 dated 29.12.2016
    was issued to NECL indicating that progress of project is
    unsatisfactory.

    8. AND WHEREAS, in order to expedite the project engineering work
    a review meeting was held at EIL, Delhi office to review the
    engineering documents of the project along with UEM based on
    the request of NECL on 10.01.2017. However, no documents
    were vetted by UEM.

    9. AND WHEREAS, NECL was advised to submit catch up plan,
    construction methodology & order copies of 3 nos. of Work Orders
    placed to vendors vide letter no.MR/URN/ES/ETP/82/9(A)/
    2016-17/1253 dated 12.01.2017 and NECL submitted an
    incomplete catch up plan without indicating the activity-wise
    plan.

    4/35

    CARBA-1-2026-Judgment.doc
    Dixit

    ::: Uploaded on – 30/04/2026 ::: Downloaded on – 01/05/2026 05:00:53 :::

    10. AND WHEREAS, ONGC advised NECL, vide letter
    no.MR/URN/ES/ETP/82/9(A)/2016-17/1357 dated 31.01.2017
    and dated 13.02.2017 to expedite the progress of the project.

    11. AND WHEREAS, ONGC planned MRM on 23.02.2017 to discuss
    various issues at the level of Plant Manager but the meeting had
    to be called off as MD of NECL did not attend the meeting. This
    shows very casual approach of NECL for the project.

    12. AND WHEREAS, NECL vide letter no.MR/URN/ES/ETP/82/9(A)/
    2016-17/1545 dated 10.03.2017 NECL were also advised for
    compliance of following:

    a) Documentary evidence to substantiate that issues with UEM,
    Delhi have been resolved and there will not be any hurdle in
    this project for the jobs to be performed by UEM.

    b) Catch up plan duly endorsed by UEM to arrest further delay
    in the project.

    13. AND WHEREAS, in response to the above communication, NECL
    vide letter no.PM/NECL/M-250/2017/011 dated 11.03.2017
    claimed to have resolve their dispute with UEM through MOM
    dated 10.03.2017 between NECL and UEM. However, there is no
    evidence of the said MOM being followed in letter and spirit.

    14. AND WHEREAS, ONGC again vide letter no.MR/URN/ES/ETP/
    82/9(A)/2016-17/1561 dated 05.03.2017 advised NECL to take
    actions on the issue raised vide letters dated 28.02.2017 and
    10.03.2017 but the same was not responded by NECL.

    15. AND WHEREAS, in the 4th MRM of the project was held on
    24.03.2017 and the same was attended by Directors and other
    personnel of NECL. During the meeting, following points were
    discussed and NECL was advised to comply the same latest by
    31.03.2017. This MRM was also not attended by MD, NECL.
    15.1 Progress of the project is 2.01% against the schedule of
    68.70% which is highly unsatisfactory. NECL is to improve
    the performance.

    15.2 Progress of Design & Engineering is 21.41% against the
    schedule of 100%. Planning package yet to be submitted by
    NECL for approval under Code-1.

    15.3 The schedule of submission of documents for Surge Pond-B,
    schedule of submission of PRs, schedule for revamping jobs
    shall be submitted by NECL latest by 31.03.2017.
    15.4 NECL yet to commence soil testing in Surge Pond-B.
    15.5 NECL to commission one de-watering pump by 31.03.2017
    15.6 NECL yet to submit site execution a philosophy,
    methodology and constructability document to execute the
    project.

    15.7 NECL to submit most practical catch up plan for
    Engineering, Procurement and Construction before
    31.03.2017 along with dates for each activity, failing which
    ONGC shall take appropriate action for termination of the

    5/35
    CARBA-1-2026-Judgment.doc
    Dixit

    ::: Uploaded on – 30/04/2026 ::: Downloaded on – 01/05/2026 05:00:53 :::
    contract under Clause 12.4 of the contract for
    unsatisfactory performance.

    15.8 NECL to submit letter from M/s. UEM indicating that all
    technical and commercial issues as per agreement between
    them have been sorted out and there shall not be any delay
    hereafter for various activities of the project. The letter from
    UEM shall have to be submitted by NECL to ONGC by
    31.03.2017.

    Due to non-compliance of the above issues by the cut-off
    date of 31.03.2017, ONGC again issued letter on
    31.03.2017 and 05.04.2017 to NECL to submit the
    compliance of points raised in 4 th MRM. It may be noted that
    NECL has not complied these till date.

    16. AND WHEREAS, despite best effort of ONGC to expedite the
    project, NECL has adopted the casual approach and thereby
    failed to address any of the concern ONGC have raised which is
    evident in failure of NECL to;

    16.1 Make any noticeable progress in execution of the project.
    16.2 Resolve the dispute with their technical collaborator M/s.

    UEM.

    16.3 Start the construction activities, and
    16.4 Place purchase order for the project materials and
    equipment.

    17. AND WHEREAS, ONGC is compelled to issue this Notice of
    Termination of the referred contract on account of unsatisfactory
    performance of NECL as per provision of the Clause no.12.4 page
    22 giving a period of 30 days from the date of issue of this Notice
    for NECL to improve their performance and complete the activities
    to the satisfaction of ONGC as below;

    17.1 Commercial dispute with technical collaborator M/s. UEM,
    Delhi to be resolved.

    17.2 Execution, Philosophy, Methodology and Constructability
    document, overall plot plan, equipment layouts etc. are to be
    frozen.

    17.3 Catch up plan to be submitted.

    17.4 Engineering Documents as listed at Annexure-1, duly
    reviewed by UEM to be submitted for approval by
    ONGC/EIL.

    17.5 Procurement Balance 60 out of 80 MR/PR’s as per
    Annexure-2 to be submitted.

    17.6 Site Works : Activities enlisted in Annexure-3 to be
    completed.

    18. AND WHEREAS, after expiry of 30 days’ Notice Period, if NECL
    fails to complete the above mentioned activities and is unable to
    6/35
    CARBA-1-2026-Judgment.doc
    Dixit

    ::: Uploaded on – 30/04/2026 ::: Downloaded on – 01/05/2026 05:00:53 :::
    demonstrate improvement in execution of the project and their
    ability to complete the project, the Contract shall stand
    terminated thenceforth without any further notice and
    consequences as per clauses 12.5 and 31.0 of the Contract shall
    follow.

    (R.B. Singh)
    GM (MM)-I/c MM

    Copy to : 1. M/s. Newton Engineering and Chemicals Ltd.

    Registered Office : 864/B-4, GIDC, Markarpura,
    Baroda – 390010. Gujarat, India.

    Fax No.0265-2638564

    2. GGM-PMU

    3. GGM-HES

    4. Office Copy.

    (R.B. Singh)
    GM (MM)-I/c MM”

    5. The respondent by its reply dated 29th May 2017 denied
    these allegations and inter alia attributed the delays to the
    appellant’s inaction. It asserted that the project was delayed
    due to lack of clarity and approvals in relation to sludge
    disposal, which according to the respondent was the
    foundational activity for execution of the project. It was
    contended that the design and engineering activities were
    interdependent on inputs such as soil testing and equipment
    specifications, which in turn were contingent upon sludge
    removal. The respondent further stated that it had mobilized
    resources and undertaken preliminary activities, but its
    progress was hindered due to delay in approvals and non-
    payment of dues by the appellant. The respondent asserted
    that the commercial issues with UEM had been resolved and
    did not justify the appellant’s insistence on UEM’s
    involvement in the Contract as demanded by the appellant.
    The letter dated 29th May 2017 is reproduced as below:

    7/35

    CARBA-1-2026-Judgment.doc
    Dixit

    ::: Uploaded on – 30/04/2026 ::: Downloaded on – 01/05/2026 05:00:53 :::
    “Newton Engineering and Chemicals Ltd.
    Regd. Office : 864/B-4, GIDC, Markarpura,
    Baroda – 390010, Gujarat, India.

    Phone No.:+91 265 6672661, 6672663
    Fax : +91 265 6672662
    Email: [email protected]
    Website: www.newtonengg.com
    PM/NECL/M-251/2017/016
    Date : 29.05.2017
    To,
    The Project Coordinator,
    Modernisation of ETP Uran,
    Oil & Natural Gas Corporation Ltd.,
    Mumbai Region, Uran Plant, Uran
    Maharashtra, India.

    Ref. : Contract No. MR/URAN/MM/LSTK/ETP/14/2013-14/
    UA5KC 13001, dated 11.05.2015
    Sub. : Compliance to letter no.MR/URN/ES/ETP/9(A)/2016-
    17/1907 dated 08.05.2017.

    Dear Sir,
    With reference to the above mentioned letter received from your
    good-self kindly find below the point wise clarification:

    1. Regarding Project Progress / Design & Engineering / Disposal
    of Sludge / Soil Testing / Placement of Orders
    a. Project Progress:

    We again iterate that the clarity on the sludge issue was
    achieved only on 29th November 2016 only after which the
    work was restarted in all the areas. It is a well-known fact
    that restart of the work and reorganization of the resources
    takes its own course. Since there was no clarity on the
    sludge issue, the project’s progress was hampered due to
    this and hence now comparing the scheduled progress with
    the current progress is not at all justified.
    b. Design & Engineering:

    We again iterate that Design & Engineering is not an
    independent activity and is based on inputs received from
    the various sources. How can civil designs be started
    without having soil report in hand. It was ONGC/EIL who
    insisted that the soil report should be available from the
    area. Inside the pond which could have been done only after
    the removal of the sludge from the pond. No foundation
    drawings can be started until the availability of the soil
    report and equipment loading data which will be available
    only after the placement of the orders. Many drawings are
    interrelated and can be started only after the approval of
    former drawing like GAD of tanks can be prepared only after
    the approval of Tank Data Sheet. Hence your contention
    M/s. NECL has placed a misleading fact is not correct.

    8/35

    CARBA-1-2026-Judgment.doc
    Dixit

    ::: Uploaded on – 30/04/2026 ::: Downloaded on – 01/05/2026 05:00:53 :::
    c. Disposal of Sludge:

    It is a well established fact that we had mobilised the site in
    August 2015 and started making the efforts for sludge
    removal in the same month itself. Since the approval of
    removal for the sludge was not given and the area of the
    construction being on the sludge pond the project progress
    was hampered. It is an established fact that ONGC had been
    deposing the sludge without even categorizing it which is
    primary requirement for the disposal of the Hazardous
    waste. We having work experience in various other Oil and
    Gas Companies like IOCL, HPCL always knew that this
    sludge is fit for recycling and hence we had taken it as a
    revenue item during the bidding of the project. This can be
    seen from the cost difference between the L1 and L2 which is
    almost 23 crores. No procedure for sludge disposal is given
    in the bid document and in the contract document. ONGC
    has always been referring to a pre-bid reply which is also
    vague and not clear. Also M/s. ONGC had been forcing us to
    adopt a method for sludge disposal which was against the
    hazardous waste policy which we have been conveying from
    the start. Also now when M/s. ONGC has taken out the
    tender for the reprocessing of the sludge through the Bid
    Invitation No.UA6517002 and hence it is established that the
    procedure for sludge disposal proposed by us was correct
    and all the delay caused due to delay in the resolution of the
    sludge issue is not at all attributable to M/s. NECL.
    d. Soil Testing:

    From the letter it is agreed by you that we had carried the
    soil testing near the surge pond and not in the area where
    the sludge is kept. It was M/s. ONGC / M/s. EILs
    recommendation to do the designing only after doing the soil
    sampling from below the pond. It was only then we have re-
    initiated for the soil testing from the bottom of the surge pond
    from where the sludge has been removed. The documentary
    evidence for the same is available and hence your contention
    that M/s. NECL has placed a misleading fact is not correct.
    e. Placement of Orders:

    We again iterate that initially due to non-clarity on the
    sludge issue and later due to ONGC not making payments
    for the want of stamp and signature of the technical
    collaborator, we had delayed the placement of the orders. As
    on date, we have not received nay payment against the
    placement of the orders and on the other hand we have
    made payments to the vendors which is again putting us in
    negative cash flows impacting the project work.

    2. Resolution of Dispute with M/s. UEM:

    We again iterate that due to delay in the clarity over the sludge
    issue, we could not start the project work and due to this we
    ended up only in extra overheads and cash crunch. We had
    made a single payment of Rs.22,50,000/- after the Due to this,
    9/35
    CARBA-1-2026-Judgment.doc
    Dixit

    ::: Uploaded on – 30/04/2026 ::: Downloaded on – 01/05/2026 05:00:53 :::
    we could not honour the commercial commitments made to M/s.
    UEM completely, still we kept on paying them whatever we
    could and hence there was a commercial dispute between both
    the agencies. M/s. UEM wished to get their payment for
    technical collaboration completely without considering the
    situation. In spite of delay in the project and billing merely
    anything to ONGC, we have paid more than 80 lakh to
    M/s. UEM till date and the proof of the same can be given to
    M/s. ONGC. All the commercial issues have been resolved and
    we have started submitting documents signed by M/s. UEM to
    M/s. ONGC for approval. We are still firm on our statement that
    there is no liability given to the technical collaborator in the
    contract and M/s. NECL is held responsible for everything as
    per the contract. The entire responsibility of execution of the job,
    achieving the process parameters is responsibility of M/s.
    NECL and we have never denied or step back from our
    responsibility. However, in spite of this when it comes to
    execution, M/s. ONGC has always not reviewed the documents
    submitted by us, not made payments against the order placed
    by us for the want of signature of M/s. UEM which gave them
    full strength to dictate their terms and exploit us as they wish.

    3. Submission of MR/PR and Review of MR/PR:

    The MR/PR documents are vendor generated and it is vendor
    who takes the responsibility of the performance of the
    equipment. Hence, M/s. UEM will not sign the documents in
    MR/PR except for Data Sheets which are reviewed from process
    point of view. For TTPRO section since M/s. UEM will be
    supplying all the equipments and will be responsible for the
    warrantee and guarantee for the TTPRO section and hence for
    all the equipments coming in TTPRO section, the PS documents
    will be signed by M/s. UEM.

    4. Mobilisation of Soil Testing Agency:

    Kindly refer the mail dated 15 th April 2017 where we had
    asked for the approval of Bore Hole location and confirmed that
    the agency is ready and can mobilise the site by 19 th April
    2017. We received the approval on 24 th April 2017 by which the
    agency had deployed his rig to some other places after which
    we had searched for new agency and hence it took time. The
    documents for the gate pass approval for manpower of the new
    agency has already been submitted to the office of your good
    self.

    5. Diesel Pump:

    The diesel engine pump has been shifted to site on 15 th May
    2017. We have also ordered an additional diesel pump which
    will be delivered at site by 10th May 2017.

    6. Submission of Specific Letter from M/s. UEM:

    The commercial disputes have been resolved and M/s. UEM is
    working on this project. M/s. ONGC has also cross-verified this
    by sending an email to M/s. UEM that the documents

    10/35
    CARBA-1-2026-Judgment.doc
    Dixit

    ::: Uploaded on – 30/04/2026 ::: Downloaded on – 01/05/2026 05:00:53 :::
    submitted by M/s. NECL were really signed by them or not over
    which they have replied in positive. We feel that forcing us to
    get a particular letter from M/s. UEM is not justified.

    7. Submission of Planning Package:

    We again iterate that the MOM of the meeting may also be
    pleased to refer to this meeting which was held for discussion
    of comments on PFD, P&ID and DCI & MCI. Also planning
    package is not engineering document and hence the technical
    collaborator has no role to play in it. As confirmed earlier, there
    are only comments on the DCI and MCI in the planning
    package. Since there are several departments in EIL and we
    are also not very clear with the comments, we requested you to
    kindly arrange a joint meeting across the table with M/s. EIL
    which was denied from your end. The reply given by your good
    self on this issue is not in line with the actual facts and hence
    we do not agree with the same. We confirm you that the issues
    between us and UEM are resolved and we have expedited all
    our resources for the completion of the project at the earliest.
    We request your kind cooperation in taking this project forward.
    Regards
    Amit Datarkar
    Project Manager”

    6. Notwithstanding the reply, the appellant terminated the
    Contract on 15th June 2017 with effect from 7th June 2017.
    The letter dated 15th June 2017 is reproduced as below:
    “Oil & Natural Gas Corporation Ltd.,
    MR, Uran Plant, Uran – 400702 (India).

    MM Department-Dronagiri Bhavan,
    Navi Mumbai – 400702
    Tel.: 022-2723 4300 / 4302 4314
    Fax: 022-27222811
    No.MRJURAN/MM/LSTKJETP/14/2013-14/UASK
    Date : 15th June 2017
    M/s. Newton Engineering and Chemical Ltd.,
    Regional Office : 504, Meadows, Sahar Plaza Complex,
    Chakala Metro Station, Andheri-Kurla Road,
    Andheri (E), Mumbai – 400059, Maharashtra.

    Kind Attention : Shri N. Gopinath, Managing Director
    Ref. : 1. Contract No. MRJURAN/MM/LSTK/ETP/14/
    2013-14/UA5KC/13001 dated 11.05.2015.

    2. Letter No.MR/URAN/MM/LSTK/ETP/14/
    2013-14/UA5KC13001 dated 9th May 2017.

    11/35

    CARBA-1-2026-Judgment.doc
    Dixit

    ::: Uploaded on – 30/04/2026 ::: Downloaded on – 01/05/2026 05:00:53 :::
    Sub. : Intimation of termination of the Contract
    No.MR/URAN/
    MM/LSTK/ETP/14/2013-14/UA5KCd1a3t0e0d1
    11.05.2015 under Clause 12.4.

    1. WHEREAS, Oil & Natural Gas Corporation Ltd. (hereinafter ONGC)
    entered into Contract No.MR/URAN/MMILSTK/ETP/14/2013-14/
    U1A350KOC1 dated 11.05.2015 with M/s. Newton Engineering and
    Chemicals Ltd. (hereinafter M/s. NECL) for modernization of ETP
    Plant at ONGC Uran Plant.

    2. AND WHEREAS, ONGC served Termination Notice to M/s. Newton
    Engineering and Chemical Ltd. vide letter reference no.2 above where
    M/s. Newton Engineering and Chemicals Ltd. was allowed 30 days’
    Notice Period to complete activities listed therein and demonstrate
    improvement in execution of the project and ability to complete the
    project.

    3. AND WHEREAS, notwithstanding this termination, M/s. Newton
    Engineering and Chemicals Ltd. failed to complete the activities listed
    in the letter reference no.2 above and failed to demonstrate
    improvement in execution of the project and their ability to complete
    the project. Therefore, the said Contract No.MR/URAN/MM/LSTK/
    ETP/14/2013-14/UA5KdC 13001 dated 11.05.2015 got terminated
    on 7th June 2017 in terms of the said Termination Notice dated 9 th
    May 2017.

    4. AND WHEREAS, notwithstanding this termination, M/s. Newton
    Engineering and Chemicals Ltd. and ONGC are bound by the
    provisions of the Contract No.MRJURANIMM/LSTK/ETP/14/2013-
    14/UASKC10031 dated 11.05.2015 that reasonably requires some
    action or forbearance after such termination as per clause 12.5 of the
    Contract.

    5. AND WHEREAS, ONGC shall initiate necessary action as
    consequences of this termination as per clauses 12.5 and 31.0 of the
    Contract or any other clause elsewhere in the said Contract.

    (R.B. Singh)
    GM (MM)-I/C MM
    Copy to : M/s. Newton Engineering and Chemicals Ltd.

    Registered Office : 864/B-4, GIDC, Makarpura,
    Baroda – 390010, Gujarat, India
    Fax No.0265-2638564
    (R.B. Singh)
    GM (MM)-I/C MM”

    7. The respondent invoked arbitration and also filed
    Arbitration Petition (Lodging) no.289 of 2017 under section 9
    of the Act seeking to restrain the appellant from invoking the

    12/35
    CARBA-1-2026-Judgment.doc
    Dixit

    ::: Uploaded on – 30/04/2026 ::: Downloaded on – 01/05/2026 05:00:53 :::
    bank guarantees. As the respondent did not obtain any order
    of injunction, the appellant encashed the bank guarantees.
    All these disputes were referred to arbitration. Before the
    Tribunal, the parties led voluminous documentary and oral
    evidence. On the basis of the pleadings, a wide range of
    issues, including questions relating to delay, the role of UEM,
    the scope of work for sludge disposal, the validity of
    termination and on several claims and counterclaims, were
    framed. The same are extracted and quoted:

    i. Whether the Respondent has performed its contractual
    obligations under the subject Agreement/Contract dated
    11th May, 2015?

    ii. Whether the Respondent and/or the Claimant
    committed breaches of the subject Agreement/Contract?
    iii. Whether the disposal of the sludge was within the
    Claimant’s scope of work under the subject Contract?
    iv. Whether the Respondent’s insistence that the Claimant
    dispose of the sludge only, and only at MWML, Taloja,
    was as per subject Contract?

    v. Whether the MWML Taloja was approved Agency for
    disposal of sludge / scrap?

    vi. Whether the Contract provides or holds UEM as
    primarily responsible for overall execution of work?
    vii. Whether Claimant’s offer in the subject Contract was
    based on Consent dated 23.01.2013? If yes then
    whether Claimant is bound by MPCB Consent dated
    21.10.2014?

    viii. Whether the Claimant was entitled to the scrap under
    the subject Contract?

    ix. Whether the termination of the subject
    Agreement/Contract dated 29th March, 2017 was
    correct and justified of was wrongful?

    x. Whether the encashment of Performance Bank
    Guarantee was wrongful and if so, the Claimant is
    entitled to the refund of Rs.9,42,99,150/-?
    xi. Whether the Claimant is entitled to Rs.60,00,000/- as
    Commission charges/ expenses towards extension of
    Bank Guarantee?

    xii. Whether the Claimant is entitled to Rs.20,00,000/- for
    loss due to mobilization and demobilization of site
    infrastructure?

    13/35

    CARBA-1-2026-Judgment.doc
    Dixit

    ::: Uploaded on – 30/04/2026 ::: Downloaded on – 01/05/2026 05:00:53 :::
    xiii. Whether the Claimant is entitled to Rs.30,00,000/- for
    expenses incurred towards Insurance Policies?
    xiv. Whether the Claimant is entitled to Rs.35,00,000/- for
    loss of tools, tackles and machineries?

    xv. Whether the Claimant is entitled to the sum of
    Rs.11,36,86,818/-for Work Done but not paid?
    xvi. Whether the Claimant is entitled to Rs.2,75,00,000/- as
    loss of revenue against sludge recycling?
    xvii. Whether the Claimant is entitled to Rs.15,42,44,427/-

    as loss of profit?

    xviii. Whether the Claimant is entitled to Rs.11,08,18,621/-

    for underutilization of overheads?

    xix. Whether the Claimant is entitled to Rs.13,45,65,451/-

    for underutilization of labour force?

    xx. Whether the Claimant is entitled to Rs.7,12,40,534/- for
    underutilization of machinery?

    xxi. Whether the contract provides that property in the crude
    oil mixed in the sludge was the property of the
    Respondent?

    xxii. Whether the Respondent was entitled to reprocess the
    sludge through the 3rd Party Contractor and extract the
    crude oil therefrom before sending it for disposal by
    way of incineration?

    xxiii. Whether due to the Claimant’s failure to execute the
    subject Contract in accordance with the terms thereof,
    the Respondent has suffered a loss and is titled to an
    award for an aggregate amount of Rs.133.8 Crores
    payable by the Claimant?

    xxiv. Whether the Respondent is entitled to reimbursement of
    an amount aggregating to Rs.1,00,66,732/- incurred by
    the Respondent on maintenance of existing ETP, which
    was the scope of work of the Claimant under the subject
    Contract?

    xxv. Whether the Respondent is entitled to the aggregate
    amount of Rs.1,22,60,09,000/- being the escalated cost
    of the ETP Modernization Project occurring due to the
    inordinate delay in execution of the subject Contract by
    the Claimant?

    xxvi. Whether the Respondent is entitled to the aggregate
    amount of Rs.1,12,00,000/- on account of having
    incurred extra infructuous expenditure on manpower
    under the subject Contract?

    xxvii. Whether the Respondent is entitled to the sum of
    Rs.5,00,00,000/- as compensation for the defamatory
    and false imputations made by the Claimant against
    the officers of the Respondent?

    14/35

    CARBA-1-2026-Judgment.doc
    Dixit

    ::: Uploaded on – 30/04/2026 ::: Downloaded on – 01/05/2026 05:00:53 :::
    xxviii. Whether the Respondent is entitled to an amount of
    Rs.2.69 Crores for infructuous expenditure incurred by
    the Respondent on account of Project Managing
    Consultancy costs under the subject Contract?
    xxix. Whether the Respondent is entitled to an aggregate
    amount of Rs.12,67,240/- incurred on wasteful
    expenditure on engineering RA Bills Nos. I and 2 paid to
    the Claimant under the subject Contract?
    xxx. Whether the Respondent is entitled to the sum of
    Rs.28,00,000.00/- being the value of scrap
    appropriated by the Claimant under the subject contract
    without fulfilling all the of the Claimant’s Obligations
    under the subject contract?

    xxxi. Whether the Respondent is entitled to interest of @ 24%
    p.a. on the aggregate sum of Rs.133.8 Crores claimed in
    the present Counter Claim?

    xxxii. Whether the Claimant is entitled to interest @ 24% p.a.
    on the amounts claimed by the Claimant?

    xxxiii. What Award?

    xxxiv. What Costs?

    8. Upon a detailed consideration of the material on record,
    the Tribunal unanimously held that the termination of the
    contract by ONGC was wrongful. The Tribunal found that the
    delay in execution was not attributable to the respondent and
    that the appellant’s own conduct, particularly in relation to
    sludge disposal and approvals had materially contributed to
    the lack of progress. The Tribunal further held that the
    contract did not mandate UEM’s approval or signature on all
    engineering documents and that the respondent could not be
    faulted on that basis. Consequently, the Tribunal partly
    allowed the respondent’s claims and out of total claims for
    Rs.111.04 crores, it awarded Rs.27.43 crores under various
    heads, including refund of the performance bank guarantee,
    value of work done, loss of revenue from sludge disposal, and
    loss of profit. The Tribunal also awarded interest and costs to
    the respondent and rejected all counterclaims of the

    15/35
    CARBA-1-2026-Judgment.doc
    Dixit

    ::: Uploaded on – 30/04/2026 ::: Downloaded on – 01/05/2026 05:00:53 :::
    appellant. In a nutshell, the following claims were awarded:

    (i) Under Issue no.10, Rs.9,42,99,150/- was awarded to
    the respondent towards refund of the performance
    bank guarantee, as the Tribunal held that the
    encashment thereof was unjustified in view of the
    wrongful termination;

    (ii) Under Issue no.15, Rs.1,06,91,238/- was awarded to
    the respondent towards the value of work done and
    payments made by it to UEM and other third-party
    vendors;

    (iii) Under Issue no.16, Rs.2 crores was awarded to the
    respondent towards loss of revenue as the Tribunal
    held that the appellant had unjustifiably insisted on
    incineration and considering that the respondent
    would have received from recycling of sludge;

    (iv) Under Issue no.17, Rs.14,93,79,332/- was awarded to
    the respondent towards the loss of profits consequent
    upon wrongful termination of the Contract by the
    appellant;

    (v) Interest and costs were also awarded to the
    respondent; and

    (vi) All counterclaims of the appellant were rejected.

    9. The appellant challenged the Award under section 34 of
    the Act before the learned Single Judge contending inter alia
    that the findings of the Tribunal were perverse, unsupported
    by evidence and had internal contradictions in the Award. The
    learned Single Judge, upon examining the Award within the
    16/35
    CARBA-1-2026-Judgment.doc
    Dixit

    ::: Uploaded on – 30/04/2026 ::: Downloaded on – 01/05/2026 05:00:53 :::
    limited scope of interference under section 34, rejected the
    challenge and held that the view taken by the Tribunal was a
    plausible one based on the material on record. Aggrieved
    thereby, the appellant has preferred the present appeal under
    section 37 of the Act.

    Submissions of the appellant:

    10. Mr. Navroz Seervai, learned senior counsel appearing for
    the appellant submitted that the Tribunal has rendered
    contradictory findings regarding the role of UEM. He
    contended that while the Tribunal has acknowledged that the
    respondent lacked the requisite technical expertise and UEM
    was its Technical Collaborator, it has simultaneously held
    that the Contract did not mandate UEM’s approval/ signature
    on all drawings for continuation of the work. It was urged
    that, but for UEM, the respondent would not have been
    awarded the tender in the first place. He invited our attention
    to paragraphs 107, 111, 124 and 163 of the Award and
    submitted that the Tribunal recorded that it was incumbent
    upon the respondent to satisfy the appellant regarding UEM’s
    involvement and to demonstrate that the plans were duly
    approved by UEM. However, in subsequent portions of the
    Award, particularly paragraphs 163, 181 and 192, the
    Tribunal has held that the Contract did not require any
    involvement of UEM and the appellant could not insist on
    UEM signing all the drawings. These mutually inconsistent
    findings render the Award perverse. The learned senior
    counsel further submitted that the issue of non-involvement
    of UEM was repeatedly raised by the appellant in its

    17/35
    CARBA-1-2026-Judgment.doc
    Dixit

    ::: Uploaded on – 30/04/2026 ::: Downloaded on – 01/05/2026 05:00:53 :::
    correspondence, including the communications forming part
    of the termination notice. It was submitted that the learned
    Single Judge not only failed to consider these fundamental
    inconsistencies at paragraph 71 of the impugned judgment
    but travelled beyond the Award, rendering the impugned
    judgment patently illegal under section 37 of the Act.

    11. Mr. Seervai next contended that the Tribunal wrongly
    held that the submission of basic engineering drawings by the
    respondent constituted less than 5% of the Contract value
    and that removal of the sludge was the major work. It was
    urged that the submission of UEM-approved drawings
    constituted a fundamental precondition for execution of the
    project. The commercial weightage assigned to the drawings
    cannot be determinative of its importance for the project. The
    Tribunal as well as the learned Single Judge failed to
    appreciate that without duly approved engineering drawings,
    no further work on the ETP could have proceeded. Mr. Seervai
    submitted that the respondent’s admission of its inability to
    furnish UEM-approved drawings amounted to the breach of a
    fundamental contractual obligation, justifying the termination
    of the Contract. It was contended that despite the Tribunal
    recording findings acknowledging the necessity of UEM’s
    involvement, it failed to appreciate the legal consequences
    thereof.

    12. As regards Rs.1,06,91,238/- granted towards work done
    and payments made to UEM and third-party vendors,
    Mr. Seervai submitted that the Award is not supported by

    18/35
    CARBA-1-2026-Judgment.doc
    Dixit

    ::: Uploaded on – 30/04/2026 ::: Downloaded on – 01/05/2026 05:00:53 :::
    evidence and suffers from material discrepancies in the
    vendors’ statements. He contended that the bank statements
    relied upon by the respondent do not satisfy the requirements
    of the Bankers’ Books Evidence Act, 1891 and the same could
    not have been relied upon by the Tribunal. The learned senior
    counsel also challenged the award of loss of profit amounting
    to Rs.14,93,79,332/-, contending that the same is premised
    on an erroneous finding of wrongful termination. He
    submitted that both the Tribunal and the learned Single
    Judge have wrongly concluded that disposal of sludge was a
    primary or foundational activity for execution of the project.
    According to him, such a conclusion is not borne out from the
    contractual framework. It was submitted that the
    quantification of loss of profit at 15% is arbitrary, without
    proof of actual loss and based solely on the ipse dixit of the
    respondent. Equally, the award of Rs.2 crores towards loss of
    revenue from sludge disposal was assailed as being wholly
    unsupported by record, without evidence and is vitiated by
    patent illegality.

    13. In support of these submissions, Mr. Seervai relied on
    following judgments to contend that where an Award is
    vitiated by internal contradictions or is unsupported by
    evidence, the Court in exercise of jurisdiction under section
    37
    of the Act is empowered to set aside the Award or in the
    alternative, remand the matter to the learned Single Judge for
    reconsideration:

    19/35

    CARBA-1-2026-Judgment.doc
    Dixit

    ::: Uploaded on – 30/04/2026 ::: Downloaded on – 01/05/2026 05:00:54 :::

    (i) “Morgan Securities & Credits Pvt. Ltd. v.

    Samtel Display Systems Ltd.”1

    (ii) “Mcdermott International Inc. v. Burn
    Standard Ltd. & Ors.
    “2

    (iii) “National Agricultural Co-operative Marketing
    Federation of India Limited (Nafed) v. Roj
    Enterprises (P) Limited & Ors.
    “3

    Submissions of the respondent:

    14. On the other hand, Mr. Mayur Khandeparkar, the
    learned counsel appearing on behalf of the respondent
    supported the findings recorded in the Award as well as the
    judgment of the learned Single Judge. Mr. Khandeparkar
    invited our attention to various portions of the Award and
    submitted that the Tribunal has correctly held that the
    termination of the Contract by the appellant was wrongful
    and that the consequences thereof necessarily follow. He
    contended that the issue relating to disposal of sludge was
    fundamental to the progress of the project and has been
    determined by the Tribunal as a question of fact on the basis
    of the materials on record. The appellant delayed the
    decision-making process in relation to sludge disposal, which
    constituted a preliminary and essential activity and further
    insisted on incineration of sludge, despite material indicating
    that the sludge was capable of being recycled. The Tribunal
    has rightly concluded that the appellant failed to grant timely
    approvals and that the delay was attributable to the
    appellant. It was submitted that the learned Single Judge has

    1
    2023 SCC OnLine Del 8018
    2
    (2006) 11 SCC 181
    3
    2025 SCC OnLine Bom 541
    20/35
    CARBA-1-2026-Judgment.doc
    Dixit

    ::: Uploaded on – 30/04/2026 ::: Downloaded on – 01/05/2026 05:00:54 :::
    correctly held that a plausible view is taken by the Tribunal
    and that this Court ought not to re-appreciate the evidence
    which has been extensively considered by the Tribunal.

    15. Mr. Khandeparkar further submitted that the monetary
    claims awarded are duly supported by reasons and evidence,
    including invoices, work orders and bank statements, all of
    which have been considered by the Tribunal. He submitted
    that it is well settled that in cases of wrongful termination,
    loss of profit can be awarded on a reasonable basis and the
    quantification adopted by the Tribunal at 15% cannot be said
    to be arbitrary or contrary to law. The direction for refund of
    the performance bank guarantee is a direct consequence of
    the finding that the termination itself was wrongful. It was
    contended that neither any ground of patent illegality or
    perversity is made out before this Court, nor is there any
    exceptional circumstance warranting interference or remand
    of the matter to the learned Single Judge. In support of his
    submissions, the learned counsel relied upon the following
    judgments:

    (i) “OPG Power Generation Private Limited v.

    Enexio Power Cooling Solutions India Private
    Limited & Anr.”4

    (ii) “Ramesh Kumar Jain v. Bharat Aluminium
    Company Limited (BALCO
    )”5

    (iii) “M/s. A.T. Brij Paul Singh & Ors. v. State of
    Gujarat
    “6

    4
    2024 SCC OnLine SC 2600
    5
    2025 SCC OnLine SC 2857
    6
    (1984) 4 SCC 59
    21/35
    CARBA-1-2026-Judgment.doc
    Dixit

    ::: Uploaded on – 30/04/2026 ::: Downloaded on – 01/05/2026 05:00:54 :::

    (iv) “Mohd. Salamatullah & Ors. v. Government of
    Andhra Pradesh
    “7

    (v) “Bombay Slum Redevelopment Corporation
    Private Limited v. Samir Narain Bhojwani
    “8

    Findings and reasons:

    16. Having heard the learned counsel for the parties and
    upon perusal of the record, we find no merit in the present
    appeal. The appellant has failed to make out any case
    warranting interference within the limited scope of
    jurisdiction under section 37 of the Act against the
    unanimous findings of the Tribunal. The legal position in this
    regard after the Arbitration and Conciliation (Amendment)
    Act, 2015
    stands well settled by the judgments of the Hon’ble
    Supreme Court in “OPG Power Generation, Ramesh Kumar
    Jain” and “National Highways Authority of India v. Hindustan
    Construction Co. Ltd”9. In “OPG Power Generation”, the Hon’ble
    Supreme Court held as follows:

    “80. We find ourselves in agreement with the view taken in Dyna
    Technologies [Dyna Technologies (P) Ltd. v. Crompton
    Greaves Ltd.
    , (2019) 20 SCC 1, paras 27-43] , as extracted
    above. Therefore, in our view, for the purposes of addressing
    an application to set aside an arbitral award on the ground of
    improper or inadequate reasons, or lack of reasons, awards
    can broadly be placed in three categories:
    (1) where no reasons are recorded, or the reasons recorded
    are unintelligible;

                   (2)     where reasons are improper, that is, they reveal a flaw
                           in the decision-making process; and
                   (3)     where reasons appear inadequate.
    

    81. Awards falling in Category (1) are vulnerable as they would
    be in conflict with the provisions of Section 31(3) of the 1996
    7
    (1977) 3 SCC 590
    8
    (2024) 7 SCC 218
    9
    (2024) 6 SCC 809
    22/35
    CARBA-1-2026-Judgment.doc
    Dixit

    ::: Uploaded on – 30/04/2026 ::: Downloaded on – 01/05/2026 05:00:54 :::
    Act. Therefore, such awards are liable to be set aside under
    Section 34, unless:

    (a) the parties have agreed that no reasons are to be given,
    or

    (b) the award is an arbitral award on agreed terms under
    Section 30.

    82. Awards falling in Category (2) are amenable to a challenge on
    ground of impropriety or perversity, strictly in accordance
    with the grounds set out in Section 34 of the 1996 Act.

    83. Awards falling in Category (3) require to be dealt with care.

    In a challenge to such award, before taking a decision the
    Court must take into consideration the nature of the issues
    arising between the parties in the arbitral proceedings and
    the degree of reasoning required to address them. The Court
    must thereafter carefully peruse the award, and the
    documents referred to therein. If reasons are intelligible and
    adequate on a fair reading of the award and, in appropriate
    cases, implicit in the documents referred to therein, the
    award is not to be set aside for inadequacy of reasons.
    However, if gaps are such that they render the reasoning in
    support of the award unintelligible, or lacking, the Court
    exercising power under Section 34 may set aside the award.

    167. Before closing discussion on the issue, it would be necessary
    to address an alternative submission raised on behalf of the
    appellants. It was argued that the learned Single Judge [OPG
    Power Generation (P) Ltd. v. Enexio Power Cooling Solutions
    India (P) Ltd.
    , 2020 SCC OnLine Mad 27362] and the Division
    Bench [Enexio Power Cooling Solutions India (P) Ltd. v. Gita
    Power & Infrastructure (P) Ltd., 2021 SCC OnLine Mad 5035]
    of the High Court, admittedly, were exercising jurisdiction
    under Sections 34 and 37, respectively, of the 1996 Act. As,
    while exercising jurisdiction under Section 34, the Court does
    not sit in appeal over the award, it cannot substitute the
    reasoning in the award with its own. Likewise, the appellate
    court exercising power under Section 37 cannot have greater
    power than what a court possesses under Section 34.
    Consequently, it was argued, the appellate court (i.e. the
    Division Bench of the High Court) exceeded its jurisdiction
    while providing its own reasons to support the conclusion in
    the award. It was also urged that in the absence of proper
    reasons in the award, the only course available was to set
    aside the award with liberty to the parties to undertake fresh
    arbitration.

    168. We have given due consideration to the above submission. In
    our view, a distinction would have to be drawn between an
    arbitral award where reasons are either
    lacking/unintelligible or perverse and an arbitral award

    23/35
    CARBA-1-2026-Judgment.doc
    Dixit

    ::: Uploaded on – 30/04/2026 ::: Downloaded on – 01/05/2026 05:00:54 :::
    where reasons are there but appear inadequate or
    insufficient [ See paras 79 to 83 of this judgment.] . In a case
    where reasons appear insufficient or inadequate, if, on a
    careful reading of the entire award, coupled with documents
    recited/relied therein, the underlying reason, factual or legal,
    that forms the basis of the award, is discernible/intelligible,
    and the same exhibits no perversity, the Court need not set
    aside the award while exercising powers under Section 34 or
    Section 37 of the 1996 Act, rather it may explain the
    existence of that underlying reason while dealing with a
    challenge laid to the award. In doing so, the Court does not
    supplant the reasons of the Arbitral Tribunal but only
    explains it for a better and clearer understanding of the
    award.”

    17. It is now well settled that the narrow scope of
    jurisdiction under section 37 of the Act does not permit re-
    appreciation of evidence or substitution of the arbitrator’s
    view merely because another view is possible. The evidence
    and interpretation of contractual terms squarely falls within
    the domain of the arbitrator. An arbitral award can be
    interfered with only where it is vitiated by patent illegality
    appearing on the face of the award or where the findings are
    so perverse that they go to the root of the matter and are
    incapable of being sustained on any reasonable
    interpretation. Tested on the above principles, the core finding
    of the Tribunal that the termination of the Contract by the
    appellant was wrongful is a finding of fact. This finding of
    wrongful termination by the appellant at Issue no.9 of the
    Award is founded upon a detailed evaluation of
    contemporaneous correspondence, contractual provisions and
    the conduct of the parties. The Tribunal has specifically
    examined the grounds cited in the termination notice, namely

    (i) delay in execution by the respondent and (ii) internal
    disputes of the respondent with UEM and the alleged non-

    24/35

    CARBA-1-2026-Judgment.doc
    Dixit

    ::: Uploaded on – 30/04/2026 ::: Downloaded on – 01/05/2026 05:00:54 :::
    involvement of UEM, and has rejected both on cogent and
    well-reasoned grounds.

    18. On the aspect of delay, the Tribunal has, upon detailed
    consideration, held at paragraphs 198 to 226 of the Award
    that the delay was attributable to the appellant. The Tribunal
    assessed the performance in the context of delays caused by
    the appellant itself, including its indecision regarding sludge
    disposal and the appellant’s insistence on incineration despite
    viable alternatives. Under the Contract, sludge was the
    property of the bidder and removal/disposal of the sludge was
    within respondent’s scope of work. The Tribunal has also
    noted that the termination notice dated 15 th June 2017 does
    not deal with any of the explanations furnished by the
    respondent in its letter of 29 th May 2017. These findings of the
    Tribunal are supported by the record before it and are not
    amenable to reappreciation in our appellate jurisdiction.

    19. The principal submission of the appellant is that the
    Award is vitiated by internal contradictions, particularly in
    relation to the role of UEM. In particular, our attention is
    drawn to paragraphs 124 and 163 of the Award which read as
    follows:

    “124. It must be mentioned at this stage that the Contract does not
    contain any provision for signature of UEM on all documents
    and the Contract only makes the Claimant responsible for
    execution. However the Respondent insisted on involvement
    of UEM in the fields, where under the MOU, UEM had the
    primary role. It may be that the Respondent were not
    absolutely correct in insisting that UEM sign all documents
    but the fact remains that Claimant had to satisfy Respondent
    that UEM was involved and had approved what was
    submitted.

    25/35

    CARBA-1-2026-Judgment.doc
    Dixit

    ::: Uploaded on – 30/04/2026 ::: Downloaded on – 01/05/2026 05:00:54 :::

    163. Now let us see who was responsible for Contract work not
    progressing. Facts are not in dispute and thus detailed facts
    need not be set out. Brief facts, which clearly indicate what
    happened, are sufficient. As set out above the Tender (Exhibit
    C-174) was issued on 6th December 2013. At that time MPCB
    Consent dated 23rd January 2013 was in force. Thereafter
    the Consent to Operate dated 21st October 2014 was issued.
    Even though Claimant had entered into Technical
    Collaboration Agreement with UEM and got the Contract
    because of this Agreement, at the Project Kick-off Meeting
    dated 1st June 2015 the Claimant introduced M/s. R. P.
    Engineers (RPE) as their Consultants. Most of the drawings
    submitted by Claimant were not approved by Respondent on
    the ground that UEM had not signed them. Claimant relies on
    fact that UEM is not a party to the Contract and the Contract
    does not provide for drawings to be signed by UEM. Claimant
    is right in this respect. The Contract does not provide that
    UEM should sign all drawings. UEM has no role in the
    Contract. The Contract only makes Claimant liable and
    responsible. But the fact that admittedly the Claimant only
    got the contract because of Technical Collaboration with UEM
    cannot be lost sight of……”

    20. We are unable to accept the appellant’s contention that
    while the Tribunal acknowledged the importance of UEM’s
    involvement in the technical aspects of the matter, in
    contradiction it held that the Contract did not mandate UEM-
    approved drawings as a precondition for continuation of work.
    We find that a holistic reading of the Award indicates that the
    Tribunal has not rendered inconsistent findings, but has
    instead drawn a distinction between (i) the contractual
    arrangement inter se between the respondent and UEM, and

    (ii) the contractual obligations inter se between the
    respondent and the appellant. At paragraphs 163 and 181 of
    the Award, the Tribunal has on appreciation of evidence
    concluded that while UEM was the technical collaborator, the
    Contract executed between the parties did not require UEM’s
    approval as a condition precedent for performance. This
    26/35
    CARBA-1-2026-Judgment.doc
    Dixit

    ::: Uploaded on – 30/04/2026 ::: Downloaded on – 01/05/2026 05:00:54 :::
    finding is based on a detailed analysis and supported by
    cogent reasons. Paragraph 181 of the Award read as follows:

    “181.It has been very seriously submitted that Claimant failed in
    its duty to furnish drawings. It was submitted that Claimant
    were to furnish 399 drawings before removal of sludge. It
    was submitted that Claimant supplied only 29 drawings
    approved/signed by UEM. On the other hand on behalf of
    Claimant it is submitted that all drawings required to be
    submitted were submitted but that Respondent refused to
    consider them as most of them were not signed by UEM. As
    set out in paragraph 140 above nothing much turns on the
    fact of UEM signing or not signing. This was only Basic
    Drawings which admittedly constituted, at the highest, 5% of
    the Contract. The major work had to start after removal of
    sludge. We find that Claimant is right. Evidence shows that
    they had submitted all required drawings. Respondent was
    not accepting or reviewing them as they were not signed by
    UEM. UEM is not a party to the contract. There is no provision
    in the Contract which requires Claimant to get signature of
    UEM on all drawings. Under the Contract only Claimant is
    responsible for performance. If UEM had refused to perform
    Respondent could not have forced UEM to perform. While we
    understand Respondent wanting UEM to be involved
    Respondent themselves are to blame for not having a proper
    Contract. It must not be forgotten that the Contract has been
    drafted by Respondent and Claimant had no say in any of its
    provisions. At this stage it must be mentioned that the aspect
    of failure of Claimant to submit drawings has been dealt with
    in greater detail under issue No.9.”

    21. The above conclusion is based on the express terms of
    the Contract, which places the entire responsibility of
    performance upon the respondent. There is a difference
    between the expectations of the appellant and the obligations
    of the respondent under the Contract. The reasons in the
    Award do not exhibit any perversity. It is evident from
    Recitals “B” and “C” of the Contract dated 29th March 2016
    between the appellant and the respondent which record the
    various documents that formed an integral part of the
    Contract between the parties. It is expressly stated that the

    27/35
    CARBA-1-2026-Judgment.doc
    Dixit

    ::: Uploaded on – 30/04/2026 ::: Downloaded on – 01/05/2026 05:00:54 :::
    said Contract constitutes the entire agreement between the
    parties and supersedes all communications, negotiations and
    agreements made prior to the date of the said Contract.
    Mr. Khandeparkar has rightly submitted that UEM is not a
    party to the Contract between the appellant and the
    respondent. Further as per Clause B.1.2.4(C), though UEM
    was identified as a technical collaborator, the respondent was
    primarily responsible for execution and completion of the
    project. The evidence on record, including the admission of
    the appellant’s witness Mr. Sushil Kumar Gupta in cross-
    examination, supports the Tribunal’s finding that neither the
    agreement dated 19th June 2014 nor the Contract required all
    documents to be reviewed, signed or approved by UEM. The
    Tribunal has concluded at paragraphs 198 to 200 and 219 to
    226 that the Contract did not mandate any role for UEM in
    the manner contended by the appellant. The Tribunal has
    held that there is no denial that the appellant was aware that
    prior to termination, the disputes between the respondent
    and UEM had been resolved. The observations in the Award
    that are relied upon by the appellant do not disclose any
    contradiction. The learned Single Judge has considered the
    Appellant’s submission at paragraph 71 of the impugned
    judgment. We do not find any contradiction in the Award or
    the findings of the learned Single Judge. In any case, we also
    find that the Tribunal’s interpretation is a plausible view
    arising from the contractual scheme and does not warrant
    interference.

    28/35

    CARBA-1-2026-Judgment.doc
    Dixit

    ::: Uploaded on – 30/04/2026 ::: Downloaded on – 01/05/2026 05:00:54 :::

    22. The appellant’s contention that the Tribunal erred in
    correlating the milestone payment for drawings at 5% with
    their contractual significance is also without merit. As per the
    Final Revised Planning Package dated 7 th January 2016, the
    work breakdown structures in weightages was Engineering –
    5%; Material Procurement – 55%; and Construction – 40%.
    The Tribunal has examined the contractual framework in
    detail which apportions the weightage across engineering,
    procurement, and construction with the payments. While the
    appellant contends that the approval by UEM was critical
    irrespective of its monetary weightage, the Tribunal has taken
    a plausible view that the contractual scheme did not support
    the appellant’s position that submission of UEM-approved
    drawings was an absolute precondition to further execution.
    This interpretation is reasonable and does not warrant
    interference. It is settled law that where two interpretations of
    a contract are possible, the arbitrator’s view must prevail so
    long as it is a reasonable one.

    23. Mr. Seervai then contended that the Tribunal attached
    undue significance to the issue of removal of sludge,
    particularly when the show cause notice preceding
    termination dated 9th May 2017 was confined to delays by the
    respondent in submitting drawings. According to him, the
    appellant had not raised the issue of sludge removal in the
    show cause notice and the entire dispute pertained to non-
    performance by the respondent. We are unable to accept this
    submission. The respondent in its reply dated 29 th May 2017
    to the show cause notice specifically identified the removal of

    29/35
    CARBA-1-2026-Judgment.doc
    Dixit

    ::: Uploaded on – 30/04/2026 ::: Downloaded on – 01/05/2026 05:00:54 :::
    sludge as a key hindrance to the performance of the contract
    and attributed the delays in the project to the appellant.
    Inexplicably, the appellant does not deal with this issue at all
    in the termination notice dated 15 th June 2017. The issue was
    thereafter pursued as a main issue by the respondent in its
    Statement of Claim before the Tribunal, as recorded in
    paragraphs 10 to 39 of the Award. The Tribunal has noted
    that sludge removal was treated by the respondent as a
    primary activity. The execution of civil, mechanical, piping,
    electrical and instrumentation works, for which drawings
    were required was contingent upon the handing over of an
    unhindered site. In that context, the removal of sludge
    assumed foundational importance. The Tribunal has taken
    into account the extensive correspondence between the
    parties on this issue and has considered it along with
    contractual clauses in detail while dealing with Issue no. 2,
    read with Issue nos. 3 and 22 of the Award. The appellant has
    failed to demonstrate the factual findings in this regard are
    perverse or which go to the root of the matter so as to set
    aside the Award. In the exercise of our limited jurisdiction
    under Section 37 of the Act, no interference with the
    Tribunal’s factual conclusions is warranted.

    24. The appellant has assailed the award of
    Rs.1,06,91,238/- under Issue no.15 towards payments made
    to UEM and third-party vendors on the ground of
    insufficiency of evidence. However, we find that the Tribunal
    has considered documentary material including invoices,
    work orders and bank statements which were on record and

    30/35
    CARBA-1-2026-Judgment.doc
    Dixit

    ::: Uploaded on – 30/04/2026 ::: Downloaded on – 01/05/2026 05:00:54 :::
    awarded only some of the vendors-related claims that were
    proved by the respondent through its witness. The sufficiency
    and adequacy of evidence falls squarely within the domain of
    the Tribunal. The finding in the Award on this Issue cannot
    be termed as based on “no evidence”. The technical objection
    regarding the non-compliance with the Bankers’ Books
    Evidence Act
    as argued by Mr. Seervai is misconceived, as the
    Tribunal is not bound by strict rules of evidence. The
    payments made by the respondent to third-party vendors are
    supported with corresponding entries in its bank statements.
    This has not been disputed by the appellant. Hence, the
    Award does not warrant any interference on this ground.

    25. Similarly, the appellant’s objection under Issue no.16 for
    the award of Rs.2 crores towards loss of revenue from sludge
    disposal is also untenable. The Tribunal has returned a
    factual finding that the disposal and treatment of sludge
    formed an integral part of the project and that the appellant’s
    insistence on a particular mode of disposal contributed to the
    delays and losses to the respondent. The loss has been
    quantified on a quantity of 5000 MT and at a rate of
    Rs.4,000/- per MT. This factual determination is based on
    documents, surrounding circumstances and does not call for
    any interference.

    26. The appellant’s challenge to the award of loss of profit of
    Rs.14,93,79,332/- under Issue no.17 is equally without
    merit. Once the Tribunal found that there was wrongful
    termination of the Contract, the grant of loss of profit is a

    31/35
    CARBA-1-2026-Judgment.doc
    Dixit

    ::: Uploaded on – 30/04/2026 ::: Downloaded on – 01/05/2026 05:00:54 :::
    recognized head of damages. The Tribunal has adopted a
    percentage-based approach, supported by settled legal
    principles, to place the respondent in the position it would
    have occupied had the Contract been performed. The
    quantification by its very nature is an exercise of estimation,
    cannot be faulted unless it is shown to be arbitrary or without
    reasons, which is not the case here. Based on the judgments
    of the Hon’ble Supreme Court in “M/s. A.T. Brij Paul Singh &
    Ors.” and “Mohd. Salamatullah”, the Tribunal has adopted a
    percentage basis (15%) on the premise that the innocent party
    should be put in the same position as if the contract had been
    performed. The Tribunal has considered certain deductions
    before awarding this claim and this quantification exercise
    cannot be said to be arbitrary or without foundation. The
    appellant has not demonstrated that the methodology
    adopted is so unreasonable as to shock the conscience of the
    section 34 Court or of this Court to warrant interference on
    the ground of patent illegality. Equally, once the termination
    has been held to be wrongful, as a direct consequence, the
    respondent is entitled to the refund of amounts encashed by
    invoking the performance bank guarantees. The reasons in
    the Award are intelligible, adequate and no infirmity has been
    demonstrated in this regard.

    27. In the present case, we find that at paragraphs 65 to 79
    of the impugned judgment, the learned Single Judge has
    applied the correct test, namely, whether the view taken by
    the Tribunal is a plausible one. The appellant has failed to
    demonstrate any patent illegality apparent on the face of the

    32/35
    CARBA-1-2026-Judgment.doc
    Dixit

    ::: Uploaded on – 30/04/2026 ::: Downloaded on – 01/05/2026 05:00:54 :::
    Award. At paragraph 65 of “McDermott International Inc.” on
    which Mr. Seervai relies upon, the Hon’ble Supreme Court
    identifies key grounds on which the challenge to the award
    can be considered, one of them being whether it suffers from
    internal inconsistencies. The Hon’ble Supreme Court was
    considering a challenge to the award, where claims were made
    on account of delays, variations and additional work
    delineated the scope of judicial interference with arbitral
    awards under the Act. The Court clarified that mere errors in
    appreciation of evidence, or even erroneous conclusions on
    facts or law, do not by themselves furnish a ground for setting
    aside an award unless such findings are perverse, based on
    no evidence, or in conflict with the fundamental policy of
    Indian law. Since, we find no internal inconsistency or
    contradiction in the Award, the judgment in “McDermott
    International Inc.” is of no assistance to the appellant.

    28. We also find that the judgment of a learned Single Judge
    of the Delhi High Court in “Morgan Securities” is of no
    assistance to the appellant. The facts in “Morgan Securities”

    were entirely different as the Court held that there was a
    contradiction in the findings of the arbitrator while dealing
    with claim nos.2 and 3. In that judgment, the Court noted
    that while adjudicating claim no.2, the arbitrator had
    expressly rejected the claimant’s valuation of the pledged
    shares at Rs.21/- per share as on 26 th April 2007 and Rs.17/-
    per share at the time of filing the statement of claim. However,
    in contradiction to this finding, the arbitrator proceeded to
    adopt a value of Rs.17/- per share for the purpose of deciding

    33/35
    CARBA-1-2026-Judgment.doc
    Dixit

    ::: Uploaded on – 30/04/2026 ::: Downloaded on – 01/05/2026 05:00:54 :::
    claim no.3, without indicating the relevant date for such
    valuation. It was in this context that the Delhi High Court
    held that the award suffered from a contradiction and since it
    travelled beyond the claimant’s pleaded case, set it aside
    insofar as claim no.3 was concerned. No such inconsistency
    or patent infirmity exists in the present case. Hence this
    judgment is also of no assistance to the appellant.

    29. The appellant’s reliance on “National Agricultural Co-
    operative Marketing Federation of India Ltd. (NAFED)” is
    equally misconceived. In “NAFED”, a co-ordinate Bench of this
    Court held that the District Judge failed to specifically
    consider various grounds raised in the Section 34 petition
    and the written notes of arguments challenging the award.
    The Court set aside the order passed by the District Judge
    under Section 34 of the Act and directed that the same be
    considered afresh in accordance with law. The relevant
    portion reads as follows:

    “10. It can thus be seen that the conclusion recorded by the
    learned Arbitrator that the Tie Up Agreements were in the
    nature of joint enterprise was the subject-matter of contest
    before the learned Judge in the application filed under
    section 34 of the Act of 1996. In paragraph 18, the learned
    Judge has observed that he had gone through the written
    note of arguments submitted by NAFED below Exhibit-31.
    Perusal of the impugned judgment thereafter indicates that
    this challenge as raised by NAFED as to the nature of the
    Tie Up Agreements has not been dealt with at all. Except
    for observing that the findings rendered by the learned
    Arbitrator were by appreciating the evidence on record and
    applying certain legal provisions, the learned Judge has
    disposed of that challenge. The parties being at issue on
    this aspect, it was necessary for the learned Judge to have
    considered the rival contentions and expressed his opinion
    so as to reflect its judicial consideration, albeit within the
    scope permissible under section 34 of the Act of 1996. The
    same has however not been done.”

    34/35

    CARBA-1-2026-Judgment.doc
    Dixit

    ::: Uploaded on – 30/04/2026 ::: Downloaded on – 01/05/2026 05:00:54 :::

    30. No such infirmity arises here as the learned Single
    Judge has duly considered the submissions advanced by the
    appellant and thereafter rightly rejected the challenge in its
    entirety on the ground that the Tribunal has taken a plausible
    view. We also find that no exceptional case for remand, as
    contemplated in paragraph 29 of the judgment of the Hon’ble
    Supreme Court in Bombay Slum Redevelopment Corporation,
    has been made out by the appellant. The submissions of the
    appellant, in substance, invites this Court to undertake a re-
    appreciation of evidence and to substitute its own
    interpretation of the Contract. Such an exercise is
    impermissible within the limited jurisdiction under section 37
    of the Act. For all the above reasons, Commercial
    Arbitration Appeal no.1 of 2026 is dismissed. There shall
    be no order as to costs.

                          [ GAUTAM A. ANKHAD, J. ]                                    [ CHIEF JUSTICE ]
    
    
    BHARAT
    DASHARATH
    PANDIT
    
    Digitally signed by
    BHARAT
    DASHARATH
    PANDIT
    Date: 2026.04.30
    21:04:42 +0530
    
    
    
    
                                                                      35/35
                          CARBA-1-2026-Judgment.doc
                                                                                                                       Dixit
    
    
    
                                ::: Uploaded on - 30/04/2026                           ::: Downloaded on - 01/05/2026 05:00:54 :::
     



    Source link

    LEAVE A REPLY

    Please enter your comment!
    Please enter your name here