M/S Sharma Construction Company vs General Manager, North Western Railway … on 24 April, 2026

    0
    39
    ADVERTISEMENT

    Rajasthan High Court – Jaipur

    M/S Sharma Construction Company vs General Manager, North Western Railway … on 24 April, 2026

    [2026:RJ-JP:17545]
    
             HIGH COURT OF JUDICATURE FOR RAJASTHAN
                         BENCH AT JAIPUR
    
                     S.B. Arbitration Application No. 10/2024
    
    M/s Sharma Construction Company, Through Its Proprietors,
    Village And Post Sabalpura, District Sikar, Rajasthan-332001.
                                                                           ----Petitioner
                                           Versus
    1.       General Manager, North Western Railway, Jawahar Cirlce,
             Jaipur.
    2.       Divisional Rail Manager, North Western Railway, Jaipur.
                                                                        ----Respondents

    Connected With
    S.B. Arbitration Application No. 11/2024
    M/s Sharma Construction Company, Through Its Proprietors,
    Village And Post Sawalpura, District Sikar, Rajasthan-332001.

    —-Petitioner
    Versus

    SPONSORED

    1. General Manager, North Western Railway, Jawahar Circle,
    Jaipur.

    2. Divisional Rail Manager, North Western Railway, Jaipur.

    —-Respondents

    For Petitioner(s) : Mr. Dharmendra Jain
    For Respondent(s) : Mr. Heemanshu Meena

    HON’BLE THE ACTING CHIEF JUSTICE MR. SANJEEV PRAKASH SHARMA

    Order

    24/04/2026

    1. The petitioner(s) has invoked Clause 64 of the Agreement

    seeking appointment of an Arbitrator in relation to the dispute

    which has arisen between the parties, for which

    notice/representation dated 20.07.2022 was also served on the

    respondents. The respondents in reply have raised certain issues

    (Uploaded on 29/04/2026 at 07:58:03 AM)
    (Downloaded on 30/04/2026 at 11:06:44 PM)
    [2026:RJ-JP:17545] (2 of 3) [ARBAP-10/2024]

    relating to the dispute, which reflect that the dispute is actually

    arisen between the parties.

    2. This Court in D.B. Civil Reference No.1/2024 titled M/s

    Devender Singh Contractor vs. Union of India, decided on

    14.11.2025, has held as under:

    “2. It is not in dispute between the parties that there exist an
    arbitration clause. The arbitration clause is an independent
    clause which has to be read independently of the other
    clauses of the Arbitrator and Conciliation Act, 1996 (for short
    ‘the Act’) and unless there is an embargo in the said
    arbitration clause merely because in some other clauses of
    the agreement, certain parts are excluded would not create
    embargo for appointment of arbitrator. In, Interplay between
    Arbitration Agreements (2024) 6 SCC 1, the Supreme Court
    held that if the arbitration clause exist then the question of
    arbitrability or non-arbitrability will have to be examined by
    the concerned arbitrator who is to be appointed by the Court
    in terms of Section 11(6) of the Act. Leaving it open to the
    concerned arbitrator to exercise his powers in terms of
    Section16 of the Act.”

    3. This Court notices that a dispute has arisen between the

    parties and there is an arbitration clause, which provides for

    adjudication. Owing to the said event having arisen, this Court

    deems it appropriate to appoint Hon’ble Mr. Justice Satish Kumar

    Sharma (Retd.), R/o-1, Bhagwan Path, Kings Road, Rail Nagar,

    Jaipur, as Sole Arbitrator.

    4. The sole Arbitrator shall be paid fee in accordance with the

    Fourth Schedule of the Arbitration and Conciliation Act, 1996 (for

    short ‘the Act’), as amended. The fee of the Arbitrator will be

    equally borne by both the parties.

    5. The Arbitrator is requested to complete the proceedings as

    per time limit specified under Section 29A of the Act.

    (Uploaded on 29/04/2026 at 07:58:03 AM)
    (Downloaded on 30/04/2026 at 11:06:44 PM)
    [2026:RJ-JP:17545] (3 of 3) [ARBAP-10/2024]

    6. The arbitration applications are allowed accordingly.

    7. Copy of this order be sent to the appointed Arbitrator.

    8. A copy of this order be placed in the connected file.

    (SANJEEV PRAKASH SHARMA),ACTING CJ

    SANJAY KUMAWAT/RAJAT/33-34

    (Uploaded on 29/04/2026 at 07:58:03 AM)
    (Downloaded on 30/04/2026 at 11:06:44 PM)

    Powered by TCPDF (www.tcpdf.org)



    Source link

    LEAVE A REPLY

    Please enter your comment!
    Please enter your name here