Telecommunications Consultants India … vs M/S Frans Global Infotech Ltd on 27 April, 2026

    0
    39
    ADVERTISEMENT

    Delhi High Court

    Telecommunications Consultants India … vs M/S Frans Global Infotech Ltd on 27 April, 2026

                        $~
                        *     IN THE HIGH COURT OF DELHI AT NEW DELHI
                        %                                     Judgment reserved on: 07.04.2026
                                                           Judgment pronounced on: 27.04.2026
    
                        +     O.M.P. (COMM) 119/2026
                              TELECOMMUNICATIONS CONSULTANTS INDIA LTD
                                                                     .....Petitioner
                                         Through: Mr. Amitesh Chandra Mishra,
                                                  Ms. Vishakha, Mr. Mrityunjai
                                                  Singh and Mr. Harshit S
                                                  Gahlot, Advocates.
                                                    versus
    
                              M/S FRANS GLOBAL INFOTECH LTD.
                                                                                 .....Respondent
                                                    Through:      Mr. Rizwan, Ms. Sachi Chopra
                                                                  and Mr. Samarth Sharma,
                                                                  Advocates.
    
                        +     O.M.P. (COMM) 555/2025
                              M/S FRANS GLOBAL INFOTECH PVT. LTD .....Petitioner
                                           Through: Mr. Rizwan, Ms. Sachi Chopra
                                                    and Mr. Samarth Sharma,
                                                    Advocates.
                                           versus
    
                              TELECOMMUNICATIONS CONSULTANTS INDIA LTD.
                                                                  .....Respondent
                                         Through: Mr. Amitesh Chandra Mishra,
                                                  Ms. Vishakha, Mr. Mrityunjai
                                                  Singh and Mr. Harshit S
                                                  Gahlot, Advocates.
    
                              CORAM:
                              HON'BLE MR. JUSTICE HARISH VAIDYANATHAN
                              SHANKAR
    
    Signature Not Verified
                      O.M.P. (COMM) 119/2026 & connected matter                       Page 1 of 42
    Digitally Signed
    By:NEERU
    Signing Date:29.04.2026
    10:27:23
                                                     JUDGMENT
    

    1. The present Petitions filed under Section 34 of the Arbitration
    and Conciliation Act, 19961, being OMP (COMM) 119/2026 filed by
    Telecommunications Consultants India Limited2 and OMP (COMM)
    555/2025 filed by Frans Global Infotech Private Limited3, arise out
    of a common Arbitral Award dated 24.09.20254 passed by the
    learned Arbitral Tribunal5, comprising a Sole Arbitrator, in disputes
    inter se the parties.

    2. It is noted that Frans was the Claimant before the learned AT,
    whereas, TCIL was the Respondent.

    SPONSORED

    3. By way of OMP (COMM) 119/2026, TCIL has laid a challenge
    to the Impugned Award insofar as it allows certain claims in favour of
    Frans and rejects the counter-claims preferred by TCIL.

    4. Conversely, by way of OMP (COMM) 555/2025, Frans has
    assailed the Impugned Award to the extent that its Claim Nos. 1, 2 and
    6 have been rejected, pertaining to damages on account of termination
    of the Purchase Order, payment under invoices dated 14.04.2023 and
    01.05.2023, and damages for loss of reputation arising from the
    blacklisting by TCIL, along with consequential claim for interest.

    5. Since both petitions emanate from the same arbitral proceedings
    and call into question different parts of the same award, involving
    overlapping factual and legal issues, they were heard together and are
    being considered by this common judgment.

    BRIEF FACTS:

    1

    A&C Act
    2
    TCIL
    3
    Frans
    4
    Impugned Award
    5
    AT
    Signature Not Verified
    O.M.P. (COMM) 119/2026 & connected matter Page 2 of 42
    Digitally Signed
    By:NEERU
    Signing Date:29.04.2026
    10:27:23

    6. The disputes between the parties arise out of a tender for the
    supply, installation, commissioning and maintenance of the Horizontal
    Extension of State Wide Area Network.

    7. A Request for Proposal dated 05.12.2022 was issued by the
    Directorate of Information Technology6, Government of Tripura,
    for the execution of the said project. In pursuance thereof, TCIL
    issued a Notice Inviting Tender dated 07.03.2023 for the selection of
    an implementing agency.

    8. Subsequently, TCIL issued a corrigendum dated 15.03.2023,
    clarifying that the timeline for commencement of the work order
    would be reckoned from 06.03.2023.

    9. Frans participated in the tender process, and its bid was
    accepted. A Letter of Intent dated 24.03.2023 was issued in its favour,
    which was accepted on 27.03.2023.

    10. Thereafter, a Purchase Order dated 28.04.20237 was issued
    for the execution of the project. And in terms of Clause 3.2 of the
    Special Conditions of Contract8, Frans also furnished a
    Performance Bank Guarantee dated 13.04.20239 in favour of TCIL
    for an amount of ₹25,75,512/-, valid for 42 months, which was
    submitted electronically on 13.04.2023 and physically on 17.04.2023.

    11. The contractual framework envisages the supply, installation,
    testing and commissioning of equipment within stipulated timelines,
    along with maintenance obligations. The timelines for delivery and
    execution formed a central component of the contractual obligations
    between the parties.

    6

    DIT
    7
    Purchase Order
    8
    SCC
    9
    PBG
    Signature Not Verified
    O.M.P. (COMM) 119/2026 & connected matter Page 3 of 42
    Digitally Signed
    By:NEERU
    Signing Date:29.04.2026
    10:27:23

    12. During the execution of the project, disputes arose between the
    parties with respect to timelines, placement of purchase orders, and
    delivery of equipment. In this context, TCIL issued a communication
    dated 11.05.2023 raising concerns of delay, followed by a Show
    Cause Notice dated 18.05.202310, which was responded to by Frans
    disputing the allegations.

    13. Thereafter, TCIL terminated the Purchase Order vide
    termination notice dated 09.06.2023 and simultaneously imposed a
    ban on Frans from participating in its future tenders for a period of
    two years.

    14. Following that, Frans approached this Court for the
    appointment of an arbitrator by filing ARB. P. 769/2023, wherein, vide
    Order dated 06.11.2023, a Sole Arbitrator came to be appointed.

    15. Before the learned AT, Frans raised claims inter alia on account
    of alleged wrongful termination, non-payment of invoices,
    encashment of the PBG, damages and challenge to blacklisting. TCIL
    contested the claims and also raised counter-claims towards penalty,
    risk purchase costs and other losses.

    16. On the basis of pleadings, the learned AT vide its Order dated
    24.05.2024 framed issues concerning, inter alia, the validity of
    termination of the Purchase Order, entitlement to payments,
    encashment of the PBG, claims for damages, legality of blacklisting,
    and entitlement to counter-claims. For the sake of clarity and ready
    reference, the issues framed by the learned AT, upon which the
    disputes between the parties came to be adjudicated, are reproduced
    herein under:

    “Issues

    10
    Show Cause Notice
    Signature Not Verified
    O.M.P. (COMM) 119/2026 & connected matter Page 4 of 42
    Digitally Signed
    By:NEERU
    Signing Date:29.04.2026
    10:27:23

    86. The following Points of Determination/Issues were framed vide
    Order dated 24.05.2024 (as revised by Order dated 10.07.2024):

    i. Whether the termination of the Purchase Order dated 28.04.2023
    by the Respondent vide its Notice dated 09.06.2023 is wrongful
    & fraudulent? If yes, then whether the Claimant is entitled to
    damages of Rs. 15,00,000/- or any other amount? OPC
    ii. Whether the Claimant is entitled to an amount of Rs.
    1,31,64,631/- against the invoice dated 14.04.2023 amounting to
    Rs. 88,03,589/- and invoice dated 01.05.2023 amounting to Rs.
    43,61,042/- raised by the Claimant? OPC
    iii. Whether the encashment of the Performance Bank Guarantee
    by the Respondent was wrongful and fraudulent? If yes, whether
    Claimant is entitled to the cost of the Performance Bank
    Guarantee amounting to Rs. 25,75,512/- or any other amount?
    OPC
    iv. Whether the Claimant is entitled to the loss of Opportunity Cost
    of Rs. 35,00,000/- or any other amount? OPC
    v. Whether the Claimant is entitled to re-imbursement of the
    expenses to the tune of Rs. 15,00,000/- or any other amount?
    OPC
    vi. Whether, the blacklisting/debarment of the Claimant by the
    Respondent from participating in future tenders/bids of the
    Respondent is arbitrary, wrong and unjust? OPC
    vii. Whether the Claimant is entitled to claim of Rs. 15,00,000/- or
    any other amount towards loss of reputation on account of
    banning and blacklisting of the Claimant by the Respondent
    from participating in future tender bids of the Respondent? OPC
    viii. Whether the Respondent is entitled to an amount of Rs. 94 72
    000/- or any other amount towards penalty as per the Client
    RFP/Tender dated 05.12.2022? OPR [Revised by Order dated
    10.07.2024 passed by the Arbitral Tribunal]
    ix. Whether the Respondent is entitled to an amount of Rs.

    12,87,756.75/- or any other amount towards risk purchase cost?
    OPR
    x. Whether the Respondent is entitled to the claim of Rs. 5,00,000/-
    or any other amount towards loss of business opportunities and
    reputation? OPR
    xi. Whether the parties are entitled to pendente lite and future
    interest on the above-mentioned claims. If yes, then at what rate
    and for what period? OPC/OPR
    xii. Whether the parties are entitled to the cost and expenses. If yes,
    then what amount? OPC/OPR”

    17. Upon consideration of the pleadings, evidence and oral
    submissions, the learned AT passed the Impugned Award, whereby
    certain claims of Frans were allowed, while others were rejected, and
    Signature Not Verified
    O.M.P. (COMM) 119/2026 & connected matter Page 5 of 42
    Digitally Signed
    By:NEERU
    Signing Date:29.04.2026
    10:27:23
    the counter-claims of TCIL were also rejected. Aggrieved thereby, the
    parties have preferred the present Petitions before this Court.
    SUBMISSIONS ON BEHALF OF PARTIES IN OMP(COMM)
    119/2026:

    TCIL’s submissions:

    18. Learned counsel for TCIL would submit that the Impugned
    Award is vitiated by patent illegality and is liable to be set aside under
    Section 34 of the A&C Act, inasmuch as the findings of the learned
    AT are perverse, based on a misreading of contractual provisions and
    non-consideration of material evidence on record. In this regard,
    reliance would be placed on OPG Power Generation Pvt. Ltd. v.

    Enexio Power Cooling Solutions (India) Pvt. Ltd.11 and Delhi
    Airport Metro Express Pvt. Ltd. v. Delhi Metro Rail Corporation
    Ltd.12
    to submit that an award which is perverse, based on no
    evidence, or ignores vital evidence, is liable to be interfered with.

    19. Learned counsel would submit that the learned AT erred in
    holding the termination of the Purchase Order to be premature, since
    the material on record demonstrated persistent defaults on the part of
    Frans, including failure to adhere to stipulated timelines and non-
    performance of contractual obligations, which entitled TCIL to
    terminate the contract in terms of Clause 2.18 of the General
    Conditions of Contract13.

    20. He would contend that the learned AT has failed to consider
    material evidence, including communications from Original
    Equipment Manufacturers14 indicating non-payment and

    11
    (2025) 2 SCC 417
    12
    (2024) 6 SCC 357
    13
    GCC
    14
    OEM
    Signature Not Verified
    O.M.P. (COMM) 119/2026 & connected matter Page 6 of 42
    Digitally Signed
    By:NEERU
    Signing Date:29.04.2026
    10:27:23
    consequent delays, and has misinterpreted the contractual provisions,
    including the SCC, without harmoniously construing the same.
    Reliance would be placed on I-Pay Clearing Services Pvt. Ltd. v.
    ICICI Bank Ltd.15
    , Ram Kishore Lal v. Kamal Narayan16, to submit
    that findings rendered in disregard of material evidence and based on
    an incorrect construction of contractual provisions are liable to be set
    aside.

    21. Learned counsel for TCIL would submit that the rejection of the
    counter-claims of TCIL is unsustainable, as the same were based on
    independent contractual provisions, including risk purchase and
    termination clauses, and ought to have been adjudicated
    independently.

    22. He would also submit that the learned AT erred in holding that
    Section 39 of the Indian Contract Act, 187217, was inapplicable.
    TCIL would submit that Frans’s conduct constituted an anticipatory
    breach, entitling TCIL to terminate the contract. In this regard,
    reliance would be placed on Maharashtra State Electricity
    Distribution Co. Ltd. v. Datar Switchgear Ltd.18
    .

    23. Lastly, it would be submitted that the direction to refund the
    PBG amount, along with interest and costs, is arbitrary and contrary to
    the contractual framework and the evidence on record. He would
    further contend that the Impugned Award of interest @ 12% per
    annum is excessive and unwarranted, particularly in the absence of
    any contractual stipulation justifying such a rate.
    Frans Submissions:

    15

    (2022) 3 SCC 121
    16
    AIR 1963 SC 890
    17
    IC Act
    18
    (2018) 3 SCC 133
    Signature Not Verified
    O.M.P. (COMM) 119/2026 & connected matter Page 7 of 42
    Digitally Signed
    By:NEERU
    Signing Date:29.04.2026
    10:27:23

    24. Per contra, learned counsel for Frans would submit that the
    challenge raised by TCIL proceeds on a fundamental misappreciation
    of the scope of interference under Section 34 of the A&C Act,
    inasmuch as it seeks a re-interpretation of the contractual provisions
    and a re-appreciation of evidence, which is impermissible in law.

    25. He would submit that the principal contention of TCIL pertains
    to the application of Clause 3.9 of the SCC. Learned counsel would
    contend that the learned AT has applied the said provision in the
    context of the contractual framework and the facts on record, and has
    arrived at a reasoned conclusion, which does not warrant interference
    merely because TCIL seeks to advance an alternate construction of the
    same provision.

    26. He would further submit that the entire challenge of TCIL is
    predicated on a reinterpretation of Clause 3.9 of the SCC, and once the
    interpretation adopted by the learned AT is found to be a possible and
    reasonable one, the foundation of TCIL’s challenge stands eroded.

    27. He would further submit that the reliance placed by TCIL on
    Section 39 of the IC Act is misplaced. Learned counsel would urge
    that the doctrine of anticipatory breach is not attracted in the facts of
    the present case, since there was no unequivocal refusal or conduct on
    the part of Frans which could be said to have disabled performance of
    the contract. He would contend that the learned AT has correctly
    appreciated this aspect and declined to apply Section 39 of the IC Act.

    28. Learned counsel would also submit that the findings of the
    learned AT in relation to encashment of the PBG are based on a
    proper construction of the contractual provisions and the surrounding
    circumstances, and do not suffer from any infirmity warranting
    interference.

    Signature Not Verified
    O.M.P. (COMM) 119/2026 & connected matter Page 8 of 42
    Digitally Signed
    By:NEERU
    Signing Date:29.04.2026
    10:27:23

    29. He would submit that the attempt on the part of TCIL is to read
    the contractual provisions in isolation and in a manner favourable to
    itself, whereas the learned AT has construed the contract as a whole,
    keeping in view the commercial intent and the factual matrix.

    30. Learned counsel would clarify that Frans has independently
    assailed the Impugned Award in OMP(COMM) 555/2025 to the
    limited extent certain of its claims have been rejected, and seeks
    interference only to that extent.

    31. Insofar as OMP(COMM) 119/2026 filed by TCIL is concerned,
    he would submit that the same is devoid of merit and does not disclose
    any ground warranting interference with the impugned award.

    SUBMISSIONS ON BEHALF OF PARTIES IN OMP(COMM)
    555/2025:

    Frans submissions:

    32. Learned counsel for Frans would submit that the Impugned
    Award is liable to be set aside to the limited extent that the claims of
    Frans have been rejected, despite the learned AT having returned
    findings in its favour on material issues, including wrongful
    termination and blacklisting.

    33. He would submit that the learned AT, while holding the
    termination of the Purchase Order to be wrongful and noting the
    absence of notice under Clause 3.9 of the SCC, has nevertheless
    rejected the claim for damages on the ground of lack of proof of actual
    loss. Learned counsel would contend that such an approach is contrary
    to settled principles of contract law, as once breach is established,
    compensation cannot be denied merely for want of strict proof of loss
    and for the same, the reliance would be placed by the learned counsel

    Signature Not Verified
    O.M.P. (COMM) 119/2026 & connected matter Page 9 of 42
    Digitally Signed
    By:NEERU
    Signing Date:29.04.2026
    10:27:23
    for Frans upon MSK Projects (India) (JV) Ltd. v. State of
    Rajasthan19
    .

    34. In this context, he would submit that the learned AT has failed
    to apply the aforesaid settled position of law and has erroneously
    denied damages, thereby rendering the impugned award unsustainable
    to that extent.

    35. Learned counsel would further submit that the findings of the
    learned AT in relation to rejection of claims towards payment for the
    supply of equipment are contrary to the pleadings and the material on
    record. It would be contended that the learned AT has accepted a
    “back-to-back” or “pay-when-paid” defence in favour of TCIL,
    despite the absence of any such foundational plea in the Statement of
    Defence20. It would be urged that such a defence was raised for the
    first time during oral arguments and could not have been relied upon
    in the absence of pleadings and proof.

    36. He would further submit that even otherwise, there was no
    material on record to establish that TCIL had not received payment
    from the end client, and in the absence of such proof, the denial of
    Frans’ claims on this basis is legally untenable.

    37. Learned counsel would also submit that the learned AT has
    failed to give effect to the contractual payment terms, which clearly
    provided for the release of a substantial portion of the consideration
    upon delivery of the equipment. He would contend that the delivery of
    equipment having been admitted, the rejection of claims for payment
    is contrary to the express stipulations of the contract.

    19

    (2011) 10 SCC 573
    20
    SoD
    Signature Not Verified
    O.M.P. (COMM) 119/2026 & connected matter Page 10 of 42
    Digitally Signed
    By:NEERU
    Signing Date:29.04.2026
    10:27:23

    38. Learned counsel would clarify that Frans supports the findings
    of the learned AT insofar as they relate to the issue of wrongful
    termination of the Purchase Order and the illegality of blacklisting.
    The present challenge is confined to the rejection of Claim Nos. 1, 2
    and 6, namely, (i) denial of damages on account of wrongful
    termination; (ii) non-payment of amounts under invoices dated
    14.04.2023 and 01.05.2023 for supply of equipment; and (iii) denial
    of damages towards loss of reputation arising from wrongful
    blacklisting.

    39. He would, accordingly, submit that the Impugned Award is
    liable to be set aside to the aforesaid limited extent, and the claims of
    Frans deserve to be allowed.

    TCIL Submissions:

    40. Per contra, learned counsel for TCIL would submit that the
    contention of Frans that, upon a finding of wrongful termination,
    damages must necessarily follow, is misconceived. He would submit
    that the learned AT has specifically recorded that Frans failed to lead
    any credible evidence to establish actual loss, profitability, or any
    proximate loss flowing from the alleged breach, and has, on that basis,
    rightly rejected Claim No. 1.

    41. He would contend that the challenge raised by Frans is, in
    substance, directed against the appreciation of evidence by the learned
    AT on the issue of quantum of loss, and does not disclose any
    jurisdictional or legal error warranting interference under Section 34
    of the A&C Act.

    42. He would further submit that the reliance placed by Frans on
    MSK Projects (supra) is misplaced. Learned counsel would contend

    Signature Not Verified
    O.M.P. (COMM) 119/2026 & connected matter Page 11 of 42
    Digitally Signed
    By:NEERU
    Signing Date:29.04.2026
    10:27:23
    that while the said judgment recognises that loss of expected profits
    may be awarded in appropriate cases, the same is contingent upon
    proof of breach and a rational basis for quantification.

    43. Learned counsel would also submit that the rejection of the
    claim for payment under invoices is in consonance with the
    contractual framework, which envisaged a back-to-back arrangement
    with the end client. He would contend that the so-called “pay-when-
    paid” mechanism is not an independent defence but a consequence of
    the contractual terms themselves, and the learned AT was well within
    its jurisdiction to interpret and apply the same. He would urge that
    Frans failed to establish an unconditional entitlement to payment,
    particularly in the absence of satisfaction of the conditions precedent
    under the contract.

    44. He would further contend that the reliance placed by Frans on
    Clause 3.1(i) of SCC is selective and ignores the overall contractual
    scheme, as “delivery” in the present project cannot be construed as
    mere physical supply but must be read in conjunction with
    installation, commissioning, and readiness for acceptance. He would
    submit that the findings of the learned AT in this regard are based on a
    contractual and factual appreciation and do not warrant interference.

    45. He would submit that the claim for damages towards loss of
    reputation is wholly untenable and the finding of wrongful
    blacklisting does not, by itself, entitle a party to compensatory
    damages in the absence of proof of actual loss. He would urge that
    such claims are governed by Section 73 of the IC Act and require
    cogent evidence of loss and its nexus with the alleged wrongful act,
    which is absent in the present case; thus, the learned AT has,

    Signature Not Verified
    O.M.P. (COMM) 119/2026 & connected matter Page 12 of 42
    Digitally Signed
    By:NEERU
    Signing Date:29.04.2026
    10:27:23
    therefore, rightly declined to award damages and cannot be faulted for
    refusing to engage in speculation.

    46. He would submit that the present Petition is liable to be
    dismissed as it is an attempt to re-agitate issues already adjudicated by
    the learned AT and does not disclose any ground for interference
    under Section 34 of the A&C Act.

    ANALYSIS:

    47. This Court has carefully considered the submissions advanced
    on behalf of both sides and, with their able assistance, has perused the
    Impugned Award and the material placed before this Court by the
    respective parties.

    48. At the outset, it is apposite to note that this Court remains
    conscious of the limited scope of its jurisdiction while examining an
    objection petition under Section 34 of the A&C Act. There is a
    consistent and evolving line of precedents whereby the Hon’ble
    Supreme Court has authoritatively delineated and settled the contours
    of judicial intervention in such proceedings.

    49. In this regard, a 3-Judge Bench of the Hon’ble Supreme Court,
    after an exhaustive consideration of a catena of earlier judgments, in
    OPG Power (supra), while dealing with the grounds of conflict with
    the public policy of India, perversity and patent illegality, grounds
    which have also been urged in the present case, made the following
    observations, which are reproduced hereunder:

    “Relevant legal principles governing a challenge to an arbitral
    award

    30. Before we delve into the issue/sub-issues culled out above, it
    would be useful to have a look at the relevant legal principles
    governing a challenge to an arbitral award. Recourse to a court
    against an arbitral award may be made through an application for
    setting aside such award in accordance with sub-sections (2), (2-A)
    and (3) of Section 34 of the 1996 Act. Sub-section (2) of Section
    Signature Not Verified
    O.M.P. (COMM) 119/2026 & connected matter Page 13 of 42
    Digitally Signed
    By:NEERU
    Signing Date:29.04.2026
    10:27:23
    34 has two clauses, (a) and (b). Clause (a) has five sub-clauses
    which are not relevant to the issues raised before us. Insofar as
    clause (b) is concerned, it has two sub-clauses, namely, (i) and (ii).
    Sub-clause (i) of clause (b) is not relevant to the controversy in
    hand. Sub-clause (ii) of clause (b) provides that if the Court finds
    that the arbitral award is in conflict with the public policy of India,
    it may set aside the award.

    Public policy

    31. “Public policy” is a concept not statutorily defined, though it
    has been used in statutes, rules, notification, etc. since long, and is
    also a part of common law. Section 23 of the Contract Act, 1872
    uses the expression by stating that the consideration or object of an
    agreement is lawful, unless, inter alia, opposed to public policy.
    That is, a contract which is opposed to public policy is void.

    *****

    37. What is clear from above is that for an award to be against
    public policy of India a mere infraction of the municipal laws of
    India is not enough. There must be, inter alia, infraction of
    fundamental policy of Indian law including a law meant to serve
    public interest or public good.

    *****
    The 2015 Amendment in Sections 34 and 48

    42. The aforementioned judicial pronouncements were all prior to
    the 2015 Amendment. Notably, prior to the 2015 Amendment the
    expression “in contravention with the fundamental policy of Indian
    law” was not used by the legislature in either Section 34(2)(b)(ii)
    or Section 48(2)(b). The pre-amended Section 34(2)(b)(ii) and its
    Explanation read:

    *****

    44. By the 2015 Amendment, in place of the old Explanation to
    Section 34(2)(b)(ii), Explanations 1 and 2 were added to remove
    any doubt as to when an arbitral award is in conflict with the public
    policy of India.

    45. At this stage, it would be pertinent to note that we are dealing
    with a case where the application under Section 34 of the 1996 Act
    was filed after the 2015 Amendment, therefore the newly
    substituted/added Explanations would apply [Ssangyong Engg. &
    Construction Co. Ltd. v. NHAI
    , (2019) 15 SCC 131].

    46. The 2015 Amendment adds two Explanations to each of the
    two sections, namely, Section 34(2)(b)(ii) and Section 48(2)(b), in
    place of the earlier Explanation. The significance of the newly
    inserted Explanation 1 in both the sections is two-fold. First, it
    does away with the use of words : (a) “without prejudice to the
    generality of sub-clause (ii)” in the opening part of the pre-

    amended Explanation to Section 34(2)(b)(ii); and (b) “without
    prejudice to the generality of clause (b) of this section” in the
    opening part of the pre-amended Explanation to Section 48(2)(b);
    secondly, it limits the expanse of public policy of India to the three

    Signature Not Verified
    O.M.P. (COMM) 119/2026 & connected matter Page 14 of 42
    Digitally Signed
    By:NEERU
    Signing Date:29.04.2026
    10:27:23
    specified categories by using the words “only if”.
    Whereas, Explanation 2 lays down the standard for adjudging
    whether there is a contravention with the fundamental policy of
    Indian law by providing that a review on merits of the dispute shall
    not be done. This limits the scope of the enquiry on an application
    under either Section 34(2)(b)(ii) or Section 48(2)(b) of the 1996
    Act.

    47. The 2015 Amendment by inserting sub-section (2-A) in
    Section 34, carves out an additional ground for annulment of an
    arbitral award arising out of arbitrations other than international
    commercial arbitrations. Sub-section (2-A) provides that the Court
    may also set aside an award if that is vitiated by patent illegality
    appearing on the face of the award. This power of the Court is,
    however, circumscribed by the proviso, which states that an award
    shall not be set aside merely on the ground of an erroneous
    application of the law or by reappreciation of evidence.

    48. Explanation 1 to Section 34(2)(b)(ii), specifies that an arbitral
    award is in conflict with the public policy of India, only if:

    (i) the making of the award was induced or affected by fraud or
    corruption or was in violation of Section 75 or Section 81; or

    (ii) it is in contravention with the fundamental policy of Indian
    law; or

    (iii) it is in conflict with the most basic notions of morality or
    justice.

    49. In the instant case, there is no allegation that the making of the
    award was induced or affected by fraud or corruption, or was in
    violation of Section 75 or Section 81. Therefore, we shall confine
    our exercise in assessing as to whether the arbitral award is in
    contravention with the fundamental policy of Indian law, and/or
    whether it conflicts with the most basic notions of morality or
    justice. Additionally, in the light of the provisions of sub-section
    (2-A) of Section 34, we shall examine whether there is any patent
    illegality on the face of the award.

    50. Before undertaking the aforesaid exercise, it would be apposite
    to consider as to how the expressions:

    (a) “in contravention with the fundamental policy of Indian law”;

    (b) “in conflict with the most basic notions of morality or justice”;
    and

    (c) “patent illegality” have been construed.

    In contravention with the fundamental policy of Indian law

    51. As discussed above, till the 2015 Amendment the expression
    “in contravention with the fundamental policy of Indian law” was
    not found in the 1996 Act. Yet, in Renusagar Power Co.
    Ltd. v. General Electric Co.
    , 1994 Supp (1) SCC 644, in the
    context of enforcement of a foreign award, while construing the
    phrase “contrary to the public policy”, this Court held that for a
    foreign award to be contrary to public policy mere contravention of
    law would not be enough rather it should be contrary to:

    Signature Not Verified
    O.M.P. (COMM) 119/2026 & connected matter Page 15 of 42
    Digitally Signed
    By:NEERU
    Signing Date:29.04.2026
    10:27:23

    (a) the fundamental policy of Indian law; and/or

    (b) the interest of India; and/or

    (c) justice or morality.

    *****

    55. The legal position which emerges from the aforesaid discussion
    is that after “the 2015 Amendments” in Section 34(2)(b)(ii) and
    Section 48(2)(b) of the 1996 Act, the phrase “in conflict with the
    public policy of India” must be accorded a restricted meaning in
    terms of Explanation 1. The expression “in contravention with the
    fundamental policy of Indian law” by use of the word
    “fundamental” before the phrase “policy of Indian law” makes the
    expression narrower in its application than the phrase “in
    contravention with the policy of Indian law”, which means mere
    contravention of law is not enough to make an award vulnerable.
    To bring the contravention within the fold of fundamental policy of
    Indian law, the award must contravene all or any of such
    fundamental principles that provide a basis for administration of
    justice and enforcement of law in this country.

    56. Without intending to exhaustively enumerate instances of such
    contravention, by way of illustration, it could be said that:

    (a) violation of the principles of natural justice;

    (b) disregarding orders of superior courts in India or the binding
    effect of the judgment of a superior court; and

    (c) violating law of India linked to public good or public interest,
    are considered contravention of the fundamental policy of Indian
    law.

    However, while assessing whether there has been a contravention
    of the fundamental policy of Indian law, the extent of judicial
    scrutiny must not exceed the limit as set out in Explanation 2 to
    Section 34(2)(b)(ii).

    *****
    Patent illegality

    65. Sub-section (2-A) of Section 34 of the 1996 Act, which was
    inserted by the 2015 Amendment, provides that an arbitral award
    not arising out of international commercial arbitrations, may also
    be set aside by the Court, if the Court finds that the award is visited
    by patent illegality appearing on the face of the award. The proviso
    to sub-section (2-A) states that an award shall not be set aside
    merely on the ground of an erroneous application of the law or by
    reappreciation of evidence.

    66. In ONGC Ltd. v. Saw Pipes Ltd., (2003) 5 SCC 705, while
    dealing with the phrase “public policy of India” as used in Section
    34
    , this Court took the view that the concept of public policy
    connotes some matter which concerns public good and public
    interest. If the award, on the face of it, patently violates statutory
    provisions, it cannot be said to be in public interest. Thus, an award
    could also be set aside if it is patently illegal. It was, however,
    clarified that illegality must go to the root of the matter and if the

    Signature Not Verified
    O.M.P. (COMM) 119/2026 & connected matter Page 16 of 42
    Digitally Signed
    By:NEERU
    Signing Date:29.04.2026
    10:27:23
    illegality is of trivial nature, it cannot be held that award is against
    public policy.

    67. In Associate Builders v. DDA, (2015) 3 SCC 49, this Court
    held that an award would be patently illegal, if it is contrary to:

    (a) substantive provisions of law of India;

    (b) provisions of the 1996 Act; and

    (c) terms of the contract [See also three-Judge Bench decision of
    this Court in State of Chhattisgarh v. SAL Udyog (P) Ltd., (2022)
    2 SCC 275].

    The Court clarified that if an award is contrary to the substantive
    provisions of law of India, in effect, it is in contravention of
    Section 28(1)(a) of the 1996 Act. Similarly, violating terms of the
    contract, in effect, is in contravention of Section 28(3) of the 1996
    Act.

    68. In Ssangyong Engg. & Construction Co. Ltd. v. NHAI, (2019)
    15 SCC 131 this Court specifically dealt with the 2015
    Amendment which inserted sub-section (2-A) in Section 34 of the
    1996 Act. It was held that “patent illegality appearing on the face
    of the award” refers to such illegality as goes to the root of matter,
    but which does not amount to mere erroneous application of law.
    It
    was also clarified that what is not subsumed within “the
    fundamental policy of Indian law”, namely, the contravention of a
    statute not linked to “public policy” or “public interest”, cannot be
    brought in by the backdoor when it comes to setting aside an award
    on the ground of patent illegality [ See Ssangyong Engg. &
    Construction Co. Ltd. v. NHAI
    , (2019) 15 SCC 131].
    Further, it
    was observed, reappreciation of evidence is not permissible under
    this category of challenge to an arbitral award [See Ssangyong
    Engg. & Construction Co. Ltd. v. NHAI
    , (2019) 15 SCC 131].
    Perversity as a ground of challenge

    69. Perversity as a ground for setting aside an arbitral award was
    recognised in ONGC Ltd. v. Western Geco International Ltd.,
    (2014) 9 SCC 263. Therein it was observed that an arbitral
    decision must not be perverse or so irrational that no reasonable
    person would have arrived at the same. It was observed that if an
    award is perverse, it would be against the public policy of India.

    70. In Associate Builders v. DDA, (2015) 3 SCC 49 certain tests
    were laid down to determine whether a decision of an Arbitral
    Tribunal could be considered perverse. In this context, it was
    observed that where:

    (i) a finding is based on no evidence; or

    (ii) an Arbitral Tribunal takes into account something irrelevant to
    the decision which it arrives at; or

    (iii) ignores vital evidence in arriving at its decision, such decision
    would necessarily be perverse.

    However, by way of a note of caution, it was observed that when a
    court applies these tests it does not act as a court of appeal and,
    consequently, errors of fact cannot be corrected. Though, a

    Signature Not Verified
    O.M.P. (COMM) 119/2026 & connected matter Page 17 of 42
    Digitally Signed
    By:NEERU
    Signing Date:29.04.2026
    10:27:23
    possible view by the arbitrator on facts has necessarily to pass
    muster as the arbitrator is the ultimate master of the quantity and
    quality of evidence to be relied upon. It was also observed that an
    award based on little evidence or on evidence which does not
    measure up in quality to a trained legal mind would not be held to
    be invalid on that score.

    71. In Ssangyong Engg. & Construction Co. Ltd. v. NHAI, (2019)
    15 SCC 131, which dealt with the legal position post the 2015
    Amendment in Section 34 of the 1996 Act, it was observed that a
    decision which is perverse, while no longer being a ground for
    challenge under “public policy of India”, would certainly amount
    to a patent illegality appearing on the face of the award. It was
    pointed out that an award based on no evidence, or which ignores
    vital evidence, would be perverse and thus patently illegal.
    It was
    also observed that a finding based on documents taken behind the
    back of the parties by the arbitrator would also qualify as a
    decision based on no evidence inasmuch as such decision is not
    based on evidence led by the parties, and therefore, would also
    have to be characterised as perverse [ See Ssangyong Engg. &
    Construction Co. Ltd. v. NHAI
    , (2019) 15 SCC 131].

    72. The tests laid down in Associate Builders v. DDA, (2015) 3
    SCC 49 to determine perversity were followed in Ssangyong
    Engg. & Construction Co. Ltd. v. NHAI
    , (2019) 15 SCC 131 and
    later approved by a three-Judge Bench of this Court in Patel Engg.
    Ltd. v. North Eastern Electric Power Corpn. Ltd.
    , (2020) 7 SCC

    167.

    73. In a recent three-Judge Bench decision of this Court in DMRC
    Ltd. v. Delhi Airport Metro Express (P) Ltd., (2024) 6 SCC 357,
    the ground of patent illegality/perversity was delineated in the
    following terms: (SCC p. 376, para 39)
    “39. In essence, the ground of patent illegality is available
    for setting aside a domestic award, if the decision of the
    arbitrator is found to be perverse, or so irrational that no
    reasonable person would have arrived at it; or the
    construction of the contract is such that no fair or
    reasonable person would take; or, that the view of the
    arbitrator is not even a possible view. A finding based on
    no evidence at all or an award which ignores vital
    evidence in arriving at its decision would be perverse and
    liable to be set aside under the head of “patent illegality”.
    An award without reasons would suffer from patent
    illegality. The arbitrator commits a patent illegality by
    deciding a matter not within its jurisdiction or violating a
    fundamental principle of natural justice.”

    Scope of interference with an arbitral award

    74. The aforesaid judicial precedents make it clear that while
    exercising power under Section 34 of the 1996 Act the Court does
    not sit in appeal over the arbitral award. Interference with an

    Signature Not Verified
    O.M.P. (COMM) 119/2026 & connected matter Page 18 of 42
    Digitally Signed
    By:NEERU
    Signing Date:29.04.2026
    10:27:23
    arbitral award is only on limited grounds as set out in Section 34 of
    the 1996 Act. A possible view by the arbitrator on facts is to be
    respected as the arbitrator is the ultimate master of the quantity and
    quality of evidence to be relied upon. It is only when an arbitral
    award could be categorised as perverse, that on an error of fact an
    arbitral award may be set aside. Further, a mere erroneous
    application of the law or wrong appreciation of evidence by itself
    is not a ground to set aside an award as is clear from the provisions
    of sub-section (2-A) of Section 34 of the 1996 Act.

    75. In Dyna Technologies (P) Ltd. v. Crompton Greaves Ltd.,
    (2019) 20 SCC 1, paras 27-43, a three-Judge Bench of this Court
    held that courts need to be cognizant of the fact that arbitral awards
    are not to be interfered with in a casual and cavalier manner, unless
    the court concludes that the perversity of the award goes to the root
    of the matter and there is no possibility of an alternative
    interpretation that may sustain the arbitral award. It was observed
    that jurisdiction under Section 34 cannot be equated with the
    normal appellate jurisdiction. Rather, the approach ought to be to
    respect the finality of the arbitral award as well as party’s
    autonomy to get their dispute adjudicated by an alternative forum
    as provided under the law.”

    50. It is in the aforesaid backdrop that the rival challenges in OMP
    (COMM) 119/2026 filed by TCIL and OMP (COMM) 555/2025 filed
    by Frans are required to be examined.

    I. TCIL’S CHALLENGE
    Termination of Contract

    51. At the outset, it is apposite to examine the principal challenge
    raised by TCIL, which arises in the context of Issue No. 1 framed by
    the learned AT, pertaining to the validity of the termination of the
    Purchase Order. TCIL assails the finding of the learned AT holding
    the termination to be wrongful and not in accordance with the
    contractual provisions, whereas Frans supports the said finding and
    seeks consequential relief on that basis. In the considered view of this
    Court, the determination of this issue is foundational, since the claims
    and counter-claims of the parties in both petitions are intrinsically

    Signature Not Verified
    O.M.P. (COMM) 119/2026 & connected matter Page 19 of 42
    Digitally Signed
    By:NEERU
    Signing Date:29.04.2026
    10:27:23
    dependent upon the validity of such termination. The relevant findings
    of the learned AT on Issue No. 1 are reproduced hereunder:

    “Analysis & Findings

    132. The relevant facts for adjudication of the present issue are as
    follows:

    a) Pursuant to the Client’s Tender (05.12.2022), a work order dated
    06.03.2023 was issued by the end Client in favour of the
    Respondent, subsequent to which the Respondent issued the
    Tender (07.03.2023).

    b) Subsequent to the issuance of the Tender, the Respondent issued
    the Corrigendum (15.03.2023).

    c) The Claimant submitted its bid on 20.03.2023 which was accepted
    and the LOI (24.03.2023) was issued by the Respondent in favour
    of the Claimant. The LOI was accepted by the Claimant vide email
    dated 27.03.2023.

    d) The Claimant submitted the PBG belatedly on 13.04.2023 (through
    email) and on 17.04.2023 (hardcopy).

    e) The said Purchase Order (28.04.2023) was issued by the
    Respondent in favour of the Claimant.

    f) As per the Claimant, it placed certain purchase orders on OEMs
    after issuance of the LOI. Further purchase orders were placed
    after the issuance of the said Purchase Order.

    g) The Respondent followed up the progress of the purchase orders
    placed by the Claimant on the OEMs and the Claimant provided
    timelines. Various emails were exchanged between the Claimant
    and the Respondent in this regard.

    h) The Respondent received complaints from OEMs seeking its
    intervention as the Claimant was not making payment to the OEMs
    for the purchase orders provisionally placed on the OEMs by the
    Claimant.

    i) The end Client sent an email dated 08.05.2023/letter dated
    06.05.2023 to the Respondent requesting to complete execution of
    the work without any delay by the end of May 2023, pursuant to
    which the Respondent sent emails to the Claimant, inter-alia,
    seeking information/details pertaining to the delivery schedule and
    installation timelines.

    j) The Respondent issued a notice dated 11.05.2023 to the Claimant
    with regard to the delay in the execution timelines of the project.
    The said notice was replied to by the Respondent vide its email
    dated 13.05.2023.

    k) Thereafter, the Respondent issued the Show Cause Notice
    (18.05.2023) to the Claimant, inter-alia, stating that the Claimant
    had prima facie failed to provide any tangible details regarding the
    purchase orders placed on the OEMs, the delivery schedule of the
    goods and installation timelines resulting in serious delays in the
    execution timelines of the project. By the Show Cause Notice, the
    Respondent called upon the Claimant to show cause as to why the
    Signature Not Verified
    O.M.P. (COMM) 119/2026 & connected matter Page 20 of 42
    Digitally Signed
    By:NEERU
    Signing Date:29.04.2026
    10:27:23
    Respondent should not initiate action against the Claimant as
    mentioned in the Show Cause Notice including termination of the
    Tender. The Claimant was called upon to reply to the Show Cause
    Notice within 3 days failing which necessary action would be
    taken by the Respondent.

    I) The Claimant replied to the Show Cause Notice vide its replies
    dated 20.05.2023 (also sent vide email dated 22.05.2023) and
    24.05.2023, inter-alia, stating that the Claimant is going as per the
    timelines and trying its best to complete the project within the
    stipulated timelines mentioned in the Tender. The Respondent
    issued a pointwise reply dated 30.05.2023 to the above replies of
    the Claimant. In the said letter dated 30.05.2023, the Respondent
    directed the Claimant to complete the SITC part as per the project
    requirements by 06.06.2023 (except for. Networking switches),
    failing which action would be taken as per the Show Cause Notice
    and the terms of the Tender.

    m) The Respondent issued the Termination Notice (09.06.2023),
    inter-alia, alleging that the Claimant had failed to take any tangible
    action in furtherance of the said Purchase Order inspite of
    opportunities provided to it. By the Termination Notice, the
    Respondent terminated the said Purchase Order and banned the
    Claimant for a period of 2 years from participating in future/new
    works/tenders undertaken by the Respondent. The PSG was also
    forfeited.

    n) The Claimant made a representation dated 15.06.2023 to the
    Respondent stating that the Termination Notice was issued
    wrongly and erroneously. The Claimant requested for extension in
    terms of Clause 3.14 of the Tender and also reinstatement of the
    said Purchase Order. The Claimant stated that it was keen on
    completion of the project and assured that the same shall be
    executed within 45 days.

    o) The Respondent replied to the above representation of the Claimant
    vide its letter dated 20.06.2023 denying the extension sought by
    the Claimant.

    p) Thereafter, the Respondent issued a letter dated 03.07.2023 to the
    Claimant informing that work had been awarded to a new vendor
    i.e. Orbit at an additional cost of Rs. 12,87,756.75/- (Rupees
    Twelve Lakhs Eighty-Seven Thousand Seven Hundred Fifty-Six
    and Seventy-Five Paisa Only) which would be recovered from the
    Claimant.

    133. For the adjudication of the present issue, the first aspect which
    needs to be decided is the timeline within which the Claimant was
    to deliver the equipment as per the Tender.

    134. The Delivery/Implementation Schedule is provided in Clause
    3.6 of the SCC of the Tender which is set out hereunder:

    “3.6 DELIVERY/IMPLEMENTATION SCHEDULE
    As per Client’s tender’

    Signature Not Verified
    O.M.P. (COMM) 119/2026 & connected matter Page 21 of 42
    Digitally Signed
    By:NEERU
    Signing Date:29.04.2026
    10:27:23

    135. The Implementation Schedule in the Client’s Tender is
    provided in Clause 7 which is set out hereunder:

    “7. Implementation Schedule
    SI No. Activity Time line

    1. Issue of LoI/ Work T
    Order

    2. Delivery & (i) T+6
    installation of Months for
    equipment at networking
    identifies location Switches

    (ii) T+3
    months for
    other than
    networking
    switches
    3. Providing T+ 36
    maintenance Months
    services as
    mentioned in this
    RFP

    136. The Claimant has contended that as per Clause 7 of the
    Client’s Tender, the time period for delivery of equipment and
    installation is to commence from T, defined as the date of issuance
    of the Letter of Intent or Work Order. As the LOI in favour of the
    Claimant was issued on 24.03.2023, the commencement of the
    delivery period has to be calculated from 24.03.2023 and the
    stipulated period for delivery and installation of equipment other
    than network switches would have elapsed on 24.06.2023 (T +3
    months) and 24.09.2023 (T +6 months) for network switches.

    Accordingly, the said Purchase Order was terminated prematurely
    and wrongfully.

    137. The contention of the Claimant is misconceived. The terms
    “Service Provider/Selected Bidder/Selected Agency” and “Work
    Order/Supply Order” are defined in Clause 2.1 (Definitions) of the
    Client’s Tender. The relevant clauses are reproduced as under:

    “Service Provider/Selected Bidder/Selected
    Agency’ means “Successful Bidder’, with
    whom Govt. signs the Contract.

    “Work Order/Supply Order” means tasks/activities
    which will be assigned or scheduled to the successful ·
    Bidder’

    138. The Selected Bidder means the “Successful Bidder” with
    whom the end Client signs the Contract i.e. the Respondent herein.
    The Work Order/Supply Order is the work order executed between
    the end Client and the Respondent herein. In view of the above,
    when in Clause 7 (Implementation Schedule) of the Client’s
    Tender, the term LoI/Work Order is used, it means the work order
    Signature Not Verified
    O.M.P. (COMM) 119/2026 & connected matter Page 22 of 42
    Digitally Signed
    By:NEERU
    Signing Date:29.04.2026
    10:27:23
    executed between the end Client and the Respondent i.e. the work
    order dated 06.03.2023 (which has been referred to in the Letter
    dated 06.05.2023 sent by the end Client to the Respondent) i.e.
    Ex. RW1/S(Colly.).

    139. Accordingly, as per Clause 7 of the Client’s Tender, the
    timeline for delivery and installation of equipment was to
    commence on the date of the work order executed by the end
    Client in favour of the Respondent i.e. 06.03.2023 and not
    24.03.2023 as contended by the Claimant. Therefore,
    commencement for the delivery period was from 06.03.2023.

    140. The Respondent had issued the Corrigendum which
    stated/clarified “T” as specified in Clause 7 of the Client’s Tender
    as 06.03.2023. The relevant portion of the Corrigendum is set out
    hereunder:

    3 3.6 As per # Activity Timeline
    Delivery/ Client’
    Implementation s
    Schedule tender

    (Page-21)
    1 Issue of T=
    LoI/ Work 06/03/202
    Order 3
    2 Delivery & (i) T+6
    installation Months for
    of networkin
    equipment g Switches
    at identified
    location (ii) T+3
    months for
    other than
    networkin
    g switches
    3 Providing T+36
    maintenanc Months
    e services as
    mentioned
    in this RFP

    The Corrigendum made it clear that the date of commencement is
    06.03.2023 and that the date for delivery and installation of
    equipment other than network switches is 06.06.2023 (T +3
    months) and for the network switches is 06.09.2023 (T +6 months).

    141. The Corrigendum is dated 15.03.2023 and was issued by the
    Respondent prior to the Claimant submitting its bid on 20.03.2023.

    Signature Not Verified
    O.M.P. (COMM) 119/2026 & connected matter Page 23 of 42
    Digitally Signed
    By:NEERU
    Signing Date:29.04.2026
    10:27:23

    Further, by the Corrigendum, the Respondent also extended the last
    date of submission of bids and the Claimant submitted its bid as
    per the extended date mentioned in the Corrigendum. Accordingly,
    the Claimant cannot contend that it was unaware of the
    Corrigendum before submission of its bid. Further, the Respondent
    is correct in contending that the Corrigendum being a public
    document was readily available on the a-procurement portal and
    the Respondent’s website throughout the bidding period. The
    Corrigendum is also
    mentioned in the LOI as well as the said Purchase Order. In fact,
    CW-1 in answer to Question 11 has admitted that when the
    Corrigendum was mentioned in the LOI/said Purchase Order, the
    Claimant did not raise any objection or concern regarding the
    same. Therefore, the argument of the Claimant that no email or
    letter communication exists apprising the Claimant of a change in
    the delivery schedule cannot be accepted.

    142. The contention of the Claimant that the Corrigendum
    materially changed the Tender is misconceived. The Corrigendum
    with respect to the delivery/implementation schedule was more in
    the nature of a clarification and there was no material change in the
    Tender. The judgments in Bhanwar Lal Verma (supra) and Parvati
    Oevi (supra) do not support the case of the Claimant inasmuch as
    the Corrigendum was issued prior to the submission of the bid by
    the Claimant and there was no vested right in the Claimant that
    was withdrawn or taken away by virtue of the Corrigendum.

    143. Even as per the Claimant’s own case, the Claimant had started
    placing the purchase orders on the OEMs for procuring the
    equipment immediately after the issuance of the LOI. The
    Claimant placed the first purchase order on 29.03.2023 i.e. within
    7 days of issuance of the LOI. The Claimant therefore was aware
    and conscious of the strict timelines. The Respondent vide its email
    dated 25.04.2023 had requested the Claimant to review the
    timelines as the same were not in sync with the delivery timelines
    of the end· Client and the Tender. It is for the first time vide its
    email dated 10.05.2023 that the claimant took a stand that the “T”
    is 24.03.2023. CW-1 in his cross-examination in answer to
    Question 22 has deposed that the Claimant did not raise any issue
    of delivery schedule prior to its email dated 20.05.2025 as the
    Claimant was waiting for the OEMs to give the delivery schedule
    to the Claimant, which was received only in the last week of May
    2023

    144. Even otherwise, if the obligation of the Respondent to the end
    client is to deliver and install the equipment within. the timelines
    specified in the Client’s Tender, the Respondent cannot give a
    longer time period to the Claimant for delivery and installation of
    the equipment than what is specified in the Client’s Tender. The
    Claimant would have to comply with the timelines agreed to
    between the Respondent and the end Client which are in line with

    Signature Not Verified
    O.M.P. (COMM) 119/2026 & connected matter Page 24 of 42
    Digitally Signed
    By:NEERU
    Signing Date:29.04.2026
    10:27:23
    the timeline of the Tender. The judgment in Novartis Vaccines
    (supra) does not help the case of the Claimant.

    145. From the above discussion, it is clear that the
    commencement of the delivery period “T” has to be calculated
    from 06.03.2023. Accordingly, the Claimant was to deliver and
    install the equipment other than network switches by
    06.06.2023 and the network switches by 06.09.2023.

    146. The second issue which has to be considered is whether any
    notice period was required to be given by the Respondent to the
    Claimant prior to terminating the said Purchase Order/Tender.

    147. The Claimant has contended that termination of the said
    Purchase Order by the Respondent is wrongful as the Claimant was
    not given the contractually stipulated notice period. In this regard,
    the Claimant has relied upon Section 3 of the SCC of the Tender
    which provides that the terms and conditions of the Tender are to
    be applied on a back-to-back basis with the Client’s Tender. The
    Claimant contends that as per Clause 3.9 of the Tender, the
    termination has to be in accordance with the Client’s Tender i.e.
    Clause 3.12 of the Client’s Tender. In terms of Clause 3.12 of the
    Client’s Tender, it was entitled to a 45 day’ notice prior to
    termination of the Tender by the Respondent and as the said clause
    was not compiled. with, the termination by the Respondent is
    unlawful. The Claimant contended that Clause 3.12 of the Client’s
    Tender would have been applicable, however, the Respondent
    issued the Termination Notice in terms of Clause 2.18 of the
    Tender.

    148. The relevant clauses in the Tender regarding termination are
    Clause 2.18 and Clause 3.9, which are reproduced as under:

    “2.18 TERMINATION FOR DEFAULT

    a) TCIL may, without prejudice to any other remedy for
    breach of contract, by written notice of default, sent to the
    supplier, terminate this contract in whole or in part.

    – if the supplier fails to deliver any or all the services/goods
    within the time period specified in the contract, or any
    extension thereof granted by TCIL.

    – if the supplier fails to perform any other obligation(s)
    under the contract;

    – if the supplier, in either of the above circumstances, does
    not remedy his failure within a period of 15 days (or such
    longer period as TCIL may authorize in writing) after
    receipt of the default notice from TCIL

    – Failure of the successful bidder to comply with the
    requirement of submission of performance security shall
    constitute sufficient ground for cancellation of the award of
    work and forfeiture of the bid security.

    ………………. ………. . ….. ………………..

    “3.9 TERMINATION OF CONTRACT
    As per Client’s tender’

    Signature Not Verified
    O.M.P. (COMM) 119/2026 & connected matter Page 25 of 42
    Digitally Signed
    By:NEERU
    Signing Date:29.04.2026
    10:27:23

    149. The clause regarding termination in the Client’s Tender is
    Clause 3.12 of the Client’s Tender, which is set out hereunder:

    “3.12. Termination

    (i) Termination for Default:

    If the Selected Agency/Service Provider fails to carry out
    the award/work order in terms of this document within the
    stipulated period or any extension thereof, as may be
    allowed· by OIT, without any valid reasons acceptable to
    OIT, OIT may terminate the contract after giving 45 days’
    notice, and the decision of DIT on the matter shall be final
    and binding on the Service Provider. Upon termination of
    the contract, DIT shall be at liberty to get the work done at
    the risk and expense of the Selected Agency through any
    other
    agency, and to recover from the Service Provider’s
    compensation or damages.”

    150. The Note under Section 3 of the SCC of the Tender mentions
    that in case of any difference in the clauses in the Tender, the
    conditions mentioned in the SCC of the Tender shall prevail. The
    said Note is set out hereunder:

    “Note: In case clauses/sub clauses have any difference
    mentioned in this NIT at different places, the conditions
    mentioned in this section shall prevail. The terms and
    conditions of this section shall be on back-to-back basis
    based on client’s tender No. 22(44)/DIT/COMM/2022 for
    “Request for Proposal for Selection of Agency for supply,
    installation, commissioning & maintenance of Horizontal
    Extension of SWAN (HSWAN)”.”

    151. Accordingly, Clause 3.9 of the SCC of the Tender would
    prevail over Clause 2.18 of the GCC of the Tender and the
    applicable clause for termination of the Tender will be Clause 3.12
    of the Client’s Tender. Clause 3.12 of the Client’s Tender mandates
    that upon failure to carry out the work “within the stipulated
    period’, a “45 days notice period’ has to be given before
    termination.

    152. The Respondent contended that due to the Claimant’s failure
    to fulfill its obligations and abide by the stipulated timelines, The
    Respondent reasonably apprehended that the Claimant would
    default on the project execution schedule. Such delay would have
    adversely impacted the end Client. Accordingly, in order to
    safeguard its interests, the Respondent initially warned the
    Claimant vide its email dated 01 .05.2023 to act urgently in the
    interest of the project and thereafter issued a notice dated
    11.05.2023 for rectification of the delivery timeline and expediting
    the completion of work. The Claimant was also served with the
    Show Cause Notice whereby the Claimant was given 3 days time
    to respond with details on its plans to meet the delivery timelines.
    Upon receiving an unsatisfactory response and being unconvinced

    Signature Not Verified
    O.M.P. (COMM) 119/2026 & connected matter Page 26 of 42
    Digitally Signed
    By:NEERU
    Signing Date:29.04.2026
    10:27:23
    by the· Claimant’s proposed delivery schedule and lack of delivery
    and execution on ground, the Respondent terminated the said
    Purchase Order only after the timeline of 06.06.2023.

    153. The contention of the Respondent is without any merit. The
    Claimant could have issued the notice under Clause 3.12 only upon
    the failure of the Claimant to deliver and install the equipment
    within the stipulated time period i.e. other than networking
    switches by 06.06.2023. Till 06.06.2023, the Claimant had not
    defaulted in its obligations under the said Purchase Order/Tender.
    Accordingly, no notice could have been issued by the Respondent
    before the actual default on the Claimant’s part.

    154. Even upon the failure of the Claimant to delivery and install
    the said equipment by 06.06.2023, the Respondent had to give 45
    days notice to the Claimant as envisaged in Clause 3.12 of the
    Client’s Tender before terminating the said Purchase Order/Tender.
    On the date the Show Cause Notice was issued, the stipulated
    period had not expired. The Show Cause Notice is also not a notice
    as envisaged under Clause 3.12 of the Client’s Tender. In fact, no
    notice as envisaged under Clause 3.12 of the Client’s Tender was
    issued by the Respondent to the Claimant. A notice under Clause
    3.12 of the Client’s Tender could only have been given after the
    expiry of the term provided for performance of the contract. The
    Respondent did not give the Claimant the contractually stipulated
    notice period to execute the said Purchase Order in terms of the
    Tender.

    155. Accordingly, there is merit in the contention of the Claimant
    that the termination of the said Purchase Order by the Respondent
    is wrongful as the Claimant was not given adequate notice in terms
    of Clause 3.12 of the Client’s Tender.

    156. The Respondent contended that delivery timelines shared by
    the Claimant created an apprehension that the Claimant will not be
    able to complete the delivery and installation by 06.06.2023 and
    would eventually fail to meet its obligations as per the Tender. The
    Respondent placed reliance on Section 39 of the Contract Act and
    illustration (a) therein to contend that a non-defaulting party is not
    required to wait till the last date of the contract if it can anticipate
    that the defaulting party is not going to perform its obligations
    under contract. In the present case, the Claimant had neither
    refused to perform nor disabled itself from performing the said
    Purchase Order/Tender. In fact, by its emails dated 20.05.2023 and
    24.05.2023, the Claimant stated that it was trying to its best to
    complete the project within the stipulated period mentioned in the
    Tender. Subsequent to the Termination Notice, the Claimant by its
    letter dated 15.06.2023 stated that it was keen on completion of the
    project and assured that the same shall be executed within 45 days
    and the Cisco Switches would be delivered by 30.09.2023. The
    Claimant also sought extension and reinstatement of the said
    Purchase Order to enable it to execute the project. The judgments

    Signature Not Verified
    O.M.P. (COMM) 119/2026 & connected matter Page 27 of 42
    Digitally Signed
    By:NEERU
    Signing Date:29.04.2026
    10:27:23
    relied upon by the Respondent with regard to anticipatory breach
    i.e. HFCL Beze Telecom (supra), Air India Limited (supra) and
    Deva Builders (supra) do not help the case of the Respondent.
    Section 39 of the Contract Act is not applicable in the facts of the
    present case. There was no repudiation of the said Purchase
    Order/Tender by the Claimant.

    157. The reliance of the Respondent on the complaints ·by the
    OEMs do not help the Respondent as admittedly there was no
    privity of contract between the Respondent and the OEMs. Further,
    though the PSG was admittedly delayed by the Claimant, however,
    the same cannot be a ground for termination after the Respondent
    accepted”‘1he same and issued the said Purchase Order in favour of
    the Claimant.

    158. The Respondent contended that the Claimant did not plead in
    its reply to the Termination Notice or in the Statement of Claim
    that the Termination Notice was not in terms of the Client’s Tender
    and it was for the first time during arguments that the Respondent
    contended as an afterthought that the notice period of 45 days was
    not given. The contention of the Respondent is misconceived. The
    Claimant in Para 6 of its Statement of Claim has referred to,
    reproduced and relied upon various clauses of the Tender and the
    Client’s Tender including Clause 3.12 of the Client’s Tender.
    Further, the Claimant has stated that the termination of the Tender
    is to be in accordance with the Client’s Tender. Therefore, it cannot
    be said that this argument was only raised by the Claimant during
    the final arguments or is an afterthought. The judgments in Ibrahim
    Uddin (supra), Bajrang Lal (supra), Susaka Private Limited
    (supra) and Mohammed Abdul Wahid (supra) relied upon by the
    Respondent are not applicable in the facts of the present case.

    159. The Arbitral Tribunal is of the view that the termination
    of the said Purchase Order/Tender vide the Termination
    Notice was not in terms of the ‘Client’s Tender or the Tender
    as the 45 days’ notice was not given by the Respondent to the
    Claimant before termination. Accordingly, it is held that the
    termination of the said Purchase Order by the Respondent vide
    the Termination Notice is wrongful.

    ………”

    52. Insofar as the first limb of challenge by TCIL is concerned, it
    was held that the termination of the Purchase Order was not preceded
    by a notice in terms of Clause 3.9 of the SCC, which, being a back-to-
    back agreement, corresponds to Clause 3.12 of the Client’s Tender,
    and such notice was a condition precedent to a valid termination;
    further, the communications on record, including Frans’ letters dated
    Signature Not Verified
    O.M.P. (COMM) 119/2026 & connected matter Page 28 of 42
    Digitally Signed
    By:NEERU
    Signing Date:29.04.2026
    10:27:23
    20.05.2023 and 24.05.2023, disclosed a continued willingness to
    perform the contract, thereby negating any inference of anticipatory
    breach; consequently, the contention of TCIL under Section 39 of the
    IC Act was rejected.

    53. With respect to the second limb of Issue No. 1, the learned AT,
    while holding the termination to be wrongful, declined to award
    damages on the ground that Frans failed to lead any evidence to
    establish the nature and quantum of loss. This Court proceeds to
    examine the challenge to the aforesaid findings.

    54. TCIL contends that the learned AT has misconstrued the SCC,
    particularly Clause 3.9 thereof, and has failed to give due weight to
    material evidence, including communications from the OEM, which,
    it is urged, demonstrate delay and non-performance disentitling Frans
    from any relief.

    55. In this context, this Court finds that TCIL’s challenge to the
    interpretation of the SCC is selective and lacks consistency. The
    learned AT, while adjudicating the same issue relating to the date of
    commencement of the work order, interpreted the relevant provisions
    of the SCC and returned a finding which has not been disputed by
    TCIL. However, insofar as the finding on termination is concerned,
    TCIL seeks to challenge the award on the ground of an alleged
    erroneous construction of the very same contractual framework.

    56. Such a selective challenge to a unified contractual scheme
    cannot be sustained. The doctrine of quod approbo non reprobo, that a
    party cannot approbate and reprobate the same instrument, is well-
    settled in Indian law. As held by the Hon’ble Supreme Court in
    Rajasthan State Industrial Development & Investment Corpn. v.

    Signature Not Verified
    O.M.P. (COMM) 119/2026 & connected matter Page 29 of 42
    Digitally Signed
    By:NEERU
    Signing Date:29.04.2026
    10:27:23

    Diamond & Gem Development Corpn. Ltd.21, a party cannot “blow
    hot and cold” or “approbate and reprobate” where it has knowingly
    accepted the benefits of a contractual framework; it is estopped from
    denying its validity or binding effect when the same framework
    operates against it.

    57. TCIL, having accepted the learned AT’s interpretation of the
    SCC with respect to the commencement timeline and other findings,
    cannot now resist the application of the same contractual scheme in
    the context of termination.

    58. Insofar as Clause 3.9 of SCC is concerned, which, as discussed
    earlier, corresponds to Clause 3.12 of the client’s tender given the
    back-to-back nature of the agreement, the contention of TCIL that the
    termination was justified under Clause 2.18 of GCC cannot be
    sustained. Clause 3.9 of SCC, read with Clause 3.12 of the client’s
    tender, prevails over Clause 2.18 of the GCC and mandates a 45-day
    notice period upon failure to perform within the stipulated period, as a
    condition precedent to a valid termination.

    59. It is an admitted position that no such notice was issued prior to
    the termination dated 09.06.2023, and the Show Cause Notice does
    not qualify as a notice under Clause 3.9 of SCC vis-à-vis Clause 3.12
    of the client’s tender, since the mandatory period for performance had
    not even expired on the date of its issuance.

    60. The learned AT has interpreted and applied the said provision
    in the context of the contractual scheme and the conduct of the parties.
    The contention of TCIL essentially seeks an alternate interpretation of
    the said clause. The judgments relied upon by TCIL, including OPG
    Power
    (supra) and Delhi Airport Metro Express Pvt. Ltd. (supra), do
    21
    (2013) 5 SCC 470
    Signature Not Verified
    O.M.P. (COMM) 119/2026 & connected matter Page 30 of 42
    Digitally Signed
    By:NEERU
    Signing Date:29.04.2026
    10:27:23
    not advance its case, as the present case is not one of absence of
    evidence or perversity, but one of interpretation of contractual terms.

    61. The contention that the OEM communications constituted
    material evidence that has been wholly ignored is not borne out from a
    reading of the impugned award. The learned AT has adverted to the
    correspondence between the parties and assessed the same in its
    totality. The mere fact that the learned AT did not assign to such
    communications the probative weight sought to be ascribed by TCIL
    does not amount to non-consideration of material evidence within the
    meaning of I-Pay Clearing Services Pvt. Ltd. (supra).
    As clarified
    therein, and in OPG Power (supra), interference is warranted where
    material evidence is completely ignored, and not where it has been
    considered but found insufficient or unpersuasive.

    62. In the present case, the learned AT has also recorded that there
    was no privity of contract between the OEM and Frans. The
    evidentiary value of such communications has thus been assessed in
    the context of the contractual relationship between the parties. The
    challenge of TCIL, in substance, seeks a re-appreciation of the
    evidentiary weight assigned by the learned AT, which falls within its
    exclusive domain and does not warrant interference.

    63. The reliance on principles of contractual interpretation in Ram
    Kishore Lal
    (supra) also does not aid TCIL, as the learned AT has
    construed the contract as a whole and has not adopted an
    interpretation contrary to the contractual scheme.

    64. Consequently, this Court finds that the said conclusion flows
    logically from the findings of the learned AT on termination and does
    not warrant any interference by this Court.

    Signature Not Verified
    O.M.P. (COMM) 119/2026 & connected matter Page 31 of 42
    Digitally Signed
    By:NEERU
    Signing Date:29.04.2026
    10:27:23

    Section 39 of the IC Act

    65. As regards Section 39 of the IC Act, it provides that where a
    party to a contract refuses to perform or has disabled himself from
    performing his promise in its entirety, the other party may put an end
    to the contract, unless it has signified by words or conduct,
    acquiescence in the contract’s continuance. The learned AT has
    recorded a reasoned finding that there was no repudiation or disabling
    conduct on the part of Frans.

    66. The learned AT, in its finding, has noted that Frans, through its
    communications dated 20.05.2023 and 24.05.2023, expressed its
    willingness to perform and sought to complete the project, and even
    thereafter sought extension and reinstatement. The reliance placed by
    TCIL on Maharashtra State Electricity Distribution Co. Ltd. (supra)
    is misplaced, as the said judgment applies where the conduct of a
    party clearly demonstrates an unwillingness or inability to perform,
    which is not borne out in the facts of the present case; the conclusion
    that anticipatory breach is not attracted cannot be said to be erroneous.

    67. For the aforesaid reasons, this Court finds no ground to interfere
    with the finding of the learned AT that the termination of the Purchase
    Order was wrongful. The finding of the learned AT on this aspect is
    cogent and based on the material on record, and does not warrant any
    interference. Accordingly, the challenge laid by TCIL to this finding
    in OMP (COMM) 119/2026 fails.

    Refund of PBG

    68. The challenge to the direction regarding refund of the PBG
    arises in the context of Issue No.3 framed by the learned AT and is
    intrinsically linked to the aforesaid finding on termination. TCIL has
    Signature Not Verified
    O.M.P. (COMM) 119/2026 & connected matter Page 32 of 42
    Digitally Signed
    By:NEERU
    Signing Date:29.04.2026
    10:27:23
    also assailed the said direction, contending that the encashment was
    justified on account of the breach committed by Frans. The finding of
    the learned AT on Issue No.3 in this regard is extracted herein below:

    “Analysis & Findings

    191. As per the Respondent, the encashment of the PBG was due
    to the Claimant’s breach of the Tender, particularly its failure to
    deliver and install the required equipment within the stipulated
    timeline. The decision to encash the PBG was due to the
    Claimant’s repeated non-performance and failure to adhere to the
    terms of the Tender. The Arbitral Tribunal while deciding Issue
    No. 1 above has held that the termination of the said Purchase
    Order/Tender by the Respondent by the Termination Notice was
    wrongful and premature and a breach of the terms of the Tender.
    As the termination of the said Purchase Order was wrongful and
    premature and a breach of the terms of the Tender, the encashment
    of the PBG by the Respondent was also wrongful.

    192. Accordingly, the Claimant is entitled to an amount of Rs.
    25,75,512/- (Rupees Twenty-Five Lakhs Seventy-Five
    Thousand Five Hundred and Twelve Only) from the
    Respondent for the wrongful encashment of the PBG being the
    cost of the PBG. Issue No. 3 is accordingly decided in favour of
    the Claimant and against the Respondent.”

    69. A perusal of the above-extracted finding indicates that the
    learned AT has examined this contention in light of its finding on
    Issue No. 1 and has held that the termination of the Purchase Order
    was wrongful and not in accordance with the contractual provisions.
    On that basis, the learned AT has concluded that the alleged breach
    attributed to Frans could not be sustained.

    70. In view of the above finding, the very premise on which TCIL
    sought to justify the encashment of the PBG stands displaced. It was
    the specific case of TCIL that such encashment was consequent upon
    the alleged breach by Frans; however, the foundation of that
    contention having been found to be unsustainable, the justification for
    the invocation of the PBG does not survive. The learned AT has thus

    Signature Not Verified
    O.M.P. (COMM) 119/2026 & connected matter Page 33 of 42
    Digitally Signed
    By:NEERU
    Signing Date:29.04.2026
    10:27:23
    treated the encashment as a direct consequence of the wrongful
    termination and has directed the refund of the said amount.

    Interest

    71. On the issue of interest, the Impugned Award also does not
    warrant any interference. It is trite that the grant of interest falls within
    the discretion of the learned AT under Section 31(7) of the A&C Act,
    which empowers the learned AT to award interest at such rate as it
    deems reasonable, in the absence of any agreement to the contrary.
    The relevant finding of the learned AT at Paragraph Nos. 239 and 240
    of the Impugned Award are reproduced herein below:

    “239. While deciding Issue No.3, the Arbitral Tribunal has held
    that the Claimant is entitled. to an amount of Rs. 25,75,512/-
    (Rupees Twenty-Five Lakhs Seventy-Five Thousand Five Hundred
    and Twelve Only) from the Respondent for wrongful encashment
    of the PSG being the cost of the PBG. Therefore, the Claimant is
    granted interest @ 12% per annum on the amount of Rs.
    25,75,512/- (Rupees Twenty-Five Lakhs Seventy-Five Thousand
    Five Hundred and Twelve Only) from the date of encashment of
    the PSG till the date of the Award.

    240. Accordingly, the Claimant is entitled to and is granted
    simple interest on the amount of Rs. 25,75,512/- (Rupees
    Twenty-Five Lakhs Seventy-Five Thousand Five Hundred and
    Twelve Only) @ 12% per annum from the date of encashment
    of the PBG till the date of Award. Issue No. 11 is decided
    accordingly.”

    72. In light of the above-stated finding, no contractual bar or
    restriction on the grant of such interest has been demonstrated. The
    learned AT has awarded simple interest @ 12%, which cannot be said
    to be unreasonable or excessive so as to warrant interference under
    Section 34 of the A&C Act, the determination thereof being within the
    domain of the learned AT.

    Signature Not Verified
    O.M.P. (COMM) 119/2026 & connected matter Page 34 of 42
    Digitally Signed
    By:NEERU
    Signing Date:29.04.2026
    10:27:23

    73. Consequently, this Court finds that the said conclusion flows
    logically from the findings on termination and does not warrant
    interference.

    II. FRANS’S CHALLENGE:

    Issue no.1

    74. Having upheld the finding of wrongful termination under the
    first limb, this Court now turns to the second limb, being Frans’ cross-
    challenge against the rejection of its claim for damages flowing
    therefrom. Frans has assailed the rejection of its claim for damages
    despite a finding of wrongful termination, contending that once breach
    is established, damages must follow. In this regard, reliance is placed
    upon MSK Projects (supra). The relevant finding of the learned AT at
    Paragraph Nos. 160, 161 & 162 of the impugned award are
    reproduced herein below:

    “160. However, the Claimant has not led any evidence to prove
    that it suffered any damages on account of the wrongful
    termination of the said Purchase Order by the Respondent.

    161. The annexure to the said Purchase Order contains the list of
    the items/equipment that were to be supplied. As per the Claimant’s
    own case, it had delivered only the NGF and the NMS, however, as
    per the Respondent only the NGF was delivered to the end Client,
    and even that was not installed. Assuming the Claimant is correct
    in contending that it had supplied the NGF and the NMS, even then
    the Claimant has delivered only 2 items (out of 21 items)
    amounting to Rs. 1,31,64,631/- (Rupees One Crore Thirty One
    Lakhs Sixty-Four Thousand Six Hundred and Thirty-One Only)
    out of the contract value of Rs. 8,58,50,387.06/- (Rupees Eight
    Crores Fifty-Eight Lakhs Fifty Thousand Three Hundred Eighty-
    Seven and Six Paise Only). The said 2 items were not even
    installed or commissioned till the 06.06.2023. As till the stipulated
    date, the Claimant had, even as per its own case, only delivered 2
    items which were not installed or commissioned, amounting to
    around 15% of the total value of the said Purchase Order, the
    Claimant is not even entitled to nominal damages. The judgments
    relied upon by the Claimant in A. T. Brij Paul Singh (supra) and
    Bungo ·Steel Furniture (supra) do not support the case of the

    Signature Not Verified
    O.M.P. (COMM) 119/2026 & connected matter Page 35 of 42
    Digitally Signed
    By:NEERU
    Signing Date:29.04.2026
    10:27:23
    Claimant. Accordingly, the Claimant is not entitled to any
    damages.

    162. It is held that the termination of the said Purchase
    Order/Tender by the Respondent vide the Termination Notice
    is wrongful and premature and a breach of the terms of the
    Tender. However, the Claimant is not entitled to any damages
    as the Claimant has failed to prove that it suffered any the
    damages in this regard. Issue No. 1 is decided accordingly.”

    75. As is evident from the findings extracted hereinabove, the
    learned AT has rejected the claim for damages on the ground that
    Frans failed to establish any actual loss, and has supported the said
    conclusion with cogent reasoning. The learned AT has recorded that,
    even as per the case of Frans, only a limited portion of the contractual
    work was performed, with delivery of merely two items out of the
    total scope of twenty-one items under the Purchase Order, which
    themselves were neither installed nor commissioned within the
    stipulated timeline. The value of such partial performance constituted
    only a fraction of the overall contract value. In this factual backdrop,
    the learned AT has concluded that no basis existed for awarding
    damages, even in the nature of loss of profits.

    76. While it is true that in appropriate cases loss of expected profits
    may be awarded, the same is neither automatic nor can it be granted in
    the absence of material enabling its quantification. The ruling in MSK
    Projects
    (supra) does not dispense with the requirement of
    establishing the foundational facts necessary for such a claim.

    77. The finding of the learned AT that no such material was placed
    on record, being based on an appreciation of evidence, cannot be said
    to suffer from any perversity warranting interference.

    Issue No. 2

    78. Frans further challenges the rejection of its claim for payment
    under invoices dated 14.04.2023 and 01.05.2023, which fell for
    Signature Not Verified
    O.M.P. (COMM) 119/2026 & connected matter Page 36 of 42
    Digitally Signed
    By:NEERU
    Signing Date:29.04.2026
    10:27:23
    consideration before the learned AT under Issue No. 2. It is contended
    that the learned AT has effectively sustained a “back-to-back”

    payment defence, i.e., that TCIL’s obligation to pay Frans was
    contingent upon receipt of corresponding payments from the DIT,
    without TCIL having expressly pleaded such a contractual
    arrangement. The relevant findings returned by the learned AT on
    Issue No. 2, which bear upon the present challenge, are extracted
    hereunder:

    “Analysis & Findings

    178. The Claimant relied upon Clause 3.1 (i) of Section 3 of the
    Tender to claim the amounts of the invoices raised in respect of the
    NGF and the NMS. Clause 3.1 of the SCC of the Tender provides
    for the payment terms which is reproduced hereunder:
    “3. 1 PAYMENT TERMS

    (i) 80% of CAPEX amount will be paid after delivery of
    equipment.

    (ii) 10% ·of CAP EX amount will be paid after completion of
    installation, commissioning, Testing & Final acceptance.

    (iii) Remaining 10% of the CAP EX amount will be released
    @3% per year at the end of 151 & 2’Jd year and remaining
    4% will be release after end of 3rd year.

    Note: Payment terms between the TCIL and vendor shall be
    on back to back basis except in cases of advance payment
    i.e. TCIL will release the payment of each stage only if
    received from the client. Client payment terms will supersede
    terms mentioned in this document’
    (Emphasis Supplied)

    179. The said Purchase Order also mentions the payment terms,
    which are set out hereunder:

    “5. PAYMENT TERMS

    (i) 80% of CAPEX amount will be paid after delivery of
    equipment.

    (ii) 10% of CAPEX amount will be paid after completion of
    installation, commissioning, Testing & Final acceptance.

    (iii) Remaining 10% of the CAPEX amount will be released
    @3% per year at the end of 1st & 2nd year and remaining
    4% will be release after end of 3’d year.

    Note: Payment terms between the TCIL and vendor shall
    be on back to back basis except in cases of advance
    payment i.e. TCIL will release the payment of each stage
    only if received from the client.”

    (Emphasis Supplied)

    Signature Not Verified
    O.M.P. (COMM) 119/2026 & connected matter Page 37 of 42
    Digitally Signed
    By:NEERU
    Signing Date:29.04.2026
    10:27:23

    180. In terms of Clause 3.1 of the Tender and Clause 5 of the said
    Purchase Order, the payment terms between the Respondent and
    the Claimant are on back-to-back basis except in cases of advance
    payment i.e. the Respondent was to make payment to the Claimant
    only upon receipt of payment from the end Client.

    181. The Respondent has disputed delivery of the NMS and also
    contended that the Claimant had not provided the license key for
    installation of the NGF. Even otherwise, it was the understanding
    of the Claimant that the payments were on back to back basis.’

    182. In the letter dated 13.05.2023, the Claimant stated that it had
    “placed all back to back POs to the concerned OEMs”. This shows
    that the Claimant was aware that the payments to be made to the
    Claimant under the Tender were on back to back basis and the
    payment would be made only after the Respondent is paid by the
    end Client. In fact, the Invoice dated 01.05.2023 raised by the
    Claimant for the NMS also mentions the Terms’ as “Back to Back’.
    This is also the reason the Claimant never sought payment for the
    delivery of the equipment till termination of the said Purchase
    Order/Tender. There is also nothing on record to show that the
    Respondent has received payment from the end Client with respect
    to the NGF and the NMS.

    183. The contention of the Claimant that the Respondent failed to
    raise the argument of existence of back-to-back contract in its
    pleadings is misconceived. In Para 17 of the Statement of Defence,
    the Respondent has referred to, reproduced and relied upon Clause
    3.1 of the SCC of the Tender which refers to the payment terms
    being on back to back basis and therefore it cannot be said that the
    “Respondent did not raise this point in its pleadings. The judgment
    in Prakash Rattan La/ (Supra) does not support the case of the
    Claimant.

    184. It is pertinent to note that the Claimant has not disputed that it
    did not make payment to the OEMs in respect of either the NGF or
    the NMS. In answer to Questions 25 to 28, CW-1 deposed that the
    payment to the OEMs for the NGF and the NMS had been made in
    form of credit notes after filing of the Statement of Claim. On the
    other hand, the Respondent has stated that it had purchased the
    NMS from Orbit. The Respondent has placed on record an invoice
    dated 21.08.2023 of Orbit with regard to purchase of the NMS. If
    the end Client or the Respondent had received the NMS from the
    Claimant, there would have been no occasion for the Respondent
    to order the same product again.

    185. In the judgment in Kingston Enterprises (supra) relied upon
    by the Respondent, it was held that
    “24. Judicial precedents consistently uphold the ·
    enforceability of ‘pay-when-paid’ clauses in back-to-back
    contracts, provided these clauses are clear and

    Signature Not Verified
    O.M.P. (COMM) 119/2026 & connected matter Page 38 of 42
    Digitally Signed
    By:NEERU
    Signing Date:29.04.2026
    10:27:23
    unambiguous. Courts only intervene where there is gross
    unfairness or ambiguity. In this case, the language of the
    ‘pay-when paid’ clause leaves no
    room for interpretation : NBCC’s obligation to pay the
    Petitioner is strictly contingent upon receiving payment
    from NSG.

    25. Clause 24.2 of the GCC explicitly stipulates that
    NBCC’s liability to pay the Petitioner arises on its receipt
    of funds from NSG. The NBCC, in its counter affidavit,
    acknowledges an outstanding sum of INR 88,47,080/-, but
    it is clear that this payment is contingent on receipt of
    funds from NSG. Given the unambiguous terms of the
    contract, the Court finds no basis to interfere, and the
    Petitioner’s right to payment is accordingly tied to
    NBCC’s receipt of funds from NSG.

    26. It is a well-established principle of contract law that
    parties are bound by the terms to which they voluntarily
    agree. Once a contract is executed, neither party can
    contest its terms unless they are arbitrary or violate public
    policy. In this case, the Petitioner was fully aware of the
    ‘contractual condition linking their payment to NBCC’s
    receipt of funds from NSG and willingly entered into the
    agreement. There is no challenge to the terms of the
    impugned agreement. Moreover, the Petitioner cannot
    challenge the enforcement of the impugned contractual
    stipulation under Article 226 of the Constitution. The
    Court finds no merit in the Petitioner’s claim for direct
    payment from NBCC when NBCC’s obligation to pay is
    dependent on receiving funds from NSG.”

    Pertinently, in Para 14 of the said judgment, the Delhi High Court
    has also dealt with the judgment in Harvinder Singh & Company
    (supra) which has been relied upon by the Claimant.

    186. It is accordingly held that the Respondent was to pay the
    Claimant for the equipment delivered by it on back to back
    basis i.e. upon receipt of payment from the end Client. It is not
    the case of the Claimant that the Respondent had received the
    amounts for the said items from the end Client. Accordingly,
    the Claimant is not entitled to the amount of Rs. 1,31,64,631/-
    (Rupees One Crore Thirty-One Lakhs SixtyFour Thousand Six
    Hundred and Thirty-One Only) against the invoice dated
    14.04.2023 amounting to Rs. 88,03,589 (Rupees Eighty-Eight
    Lakhs Three Thousand Five Hundred and Eighty-Nine Only)
    and the invoice dated 01 .05.2023 amounting to Rs. 43,61,042/-
    (Rupees Forty-Three Lakhs Sixty-One Thousand and Forty-
    Two Only) raised by the Claimant. Issue No.2 is decided
    accordingly.”

    Signature Not Verified
    O.M.P. (COMM) 119/2026 & connected matter Page 39 of 42
    Digitally Signed
    By:NEERU
    Signing Date:29.04.2026
    10:27:23

    79. A perusal of the above finding indicates that the learned AT has
    undertaken a detailed examination of the contractual framework
    governing payments, including Clause 3.1 of the SCC and Clause 5 of
    the Purchase Order, and has recorded a categorical finding that the
    payment mechanism between the parties was on a “back-to-back”

    basis, i.e., payments to Frans were contingent upon receipt of
    corresponding payments from the end client.

    80. The learned AT has further noted that Frans was itself aware of
    and acted in accordance with such arrangement, including by placing
    back-to-back purchase orders and reflecting the same understanding in
    its own correspondence and invoices. It has also been recorded that
    there was no material to show that TCIL had received payment from
    the end client in respect of the equipment in question.

    81. In this backdrop, the learned AT has rejected the claim for
    invoices on the ground that the contractual condition precedent for
    payment was not satisfied. The contention of Frans that such a defence
    was not pleaded has also been specifically addressed and rejected by
    the learned AT on the basis of the pleadings on record.

    82. In view of the aforesaid, the finding so returned is based on a
    reasoned interpretation of the contractual terms and appreciation of
    evidence, and does not warrant interference merely because an
    alternate view is sought to be advanced.

    Issue No. 6

    83. Frans has also assailed the rejection of its claim for damages
    towards loss of reputation consequent upon the two-year ban imposed
    by TCIL. While the wrongfulness of the blacklisting was decided in
    favour of Frans under Issue No. 6, the core of the present challenge is
    Signature Not Verified
    O.M.P. (COMM) 119/2026 & connected matter Page 40 of 42
    Digitally Signed
    By:NEERU
    Signing Date:29.04.2026
    10:27:23
    to the finding under Issue No. 7, whereby the learned AT, despite
    holding the blacklisting to be wrongful, declined to grant damages for
    the reputation and commercial loss following therefrom.

    84. In this regard, it is submitted that the learned AT, having held
    the blacklisting itself to be wrongful, the legal consequences of such
    wrongful act must necessarily include compensation for reputational
    and commercial damage.

    85. The principles governing such claims are instructive. Damages
    for injury to reputation or goodwill, in a commercial context, are not
    awardable on the basis of assertion alone and, as reiterated in M/s
    Unibros v. All India Radio22, must be supported by cogent evidence,
    which may include, inter alia, demonstration of lost business
    opportunities, cancellation of contracts, denial of future tenders, or
    other concrete and quantifiable consequences flowing from the
    blacklisting. In the absence of such material, the learned AT is neither
    required nor empowered to award damages by speculation or
    inference.

    86. Considering the aforesaid principles, the learned AT, while
    holding the blacklisting to be wrongful, has rightfully declined to
    award any damages in the absence of any material produced by Frans
    to establish such loss.

    87. Accordingly, this Court finds no infirmity in the said approach,
    as a claim for damages of such nature necessarily requires cogent
    evidence, which was not forthcoming in the present case.

    CONCLUSION:

    88. In view of the aforesaid discussion, this Court finds that the
    Impugned Award does not suffer from any infirmity falling within the
    22
    2023 SCC OnLine SC 1366
    Signature Not Verified
    O.M.P. (COMM) 119/2026 & connected matter Page 41 of 42
    Digitally Signed
    By:NEERU
    Signing Date:29.04.2026
    10:27:23
    limited scope of interference under Section 34 of the A&C Act. The
    findings returned by the learned AT are based on a reasonable
    interpretation of the contractual framework and an appreciation of the
    material on record, and cannot be said to be perverse, patently illegal,
    or in conflict with the fundamental policy of Indian law.

    89. The challenge laid by TCIL in OMP(COMM) 119/2026, insofar
    as it assails the findings on wrongful termination, rejection of counter-
    claims, and consequential directions including refund of the PBG with
    interest, is found to be devoid of merit and is accordingly rejected.

    90. Likewise, the challenge raised by Frans in OMP(COMM)
    555/2025, insofar as it assails the rejection of its claims for damages,
    payment under invoices, and damages for loss of reputation, also does
    not disclose any ground warranting interference under Section 34 of
    the A&C Act, and is accordingly rejected.

    91. In view thereof, both Petitions, being OMP (COMM) 119/2026
    and OMP (COMM) 555/2025, along with pending applications, if any,
    stand dismissed.

    92. No order as to costs.

    HARISH VAIDYANATHAN SHANKAR, J.

    APRIL 27, 2026/jk

    Signature Not Verified
    O.M.P. (COMM) 119/2026 & connected matter Page 42 of 42
    Digitally Signed
    By:NEERU
    Signing Date:29.04.2026
    10:27:23



    Source link

    LEAVE A REPLY

    Please enter your comment!
    Please enter your name here