M/S. Radical Bio Organics Ltd vs The Southern Power Distribution … on 24 April, 2026

    0
    31
    ADVERTISEMENT

    Telangana High Court

    M/S. Radical Bio Organics Ltd vs The Southern Power Distribution … on 24 April, 2026

    Author: Nagesh Bheemapaka

    Bench: Nagesh Bheemapaka

    IN THE HIGH COURT OF JUDICATURE FOR THE STATE OF
                        TELANGANA
         HON'BLE SRI JUSTICE NAGESH BHEEMAPAKA
    
                 WRIT PETITION No. 11626 OF 2021
    
                                24.04.2026
    
    Between:
    
    M/s Radical Bio Organics Ltd.,
    Rep. by its Director Mr. Buyyani Srinivas Reddy
                                                                ..... Petitioner
    And
    
    The Southern Power Distribution Company of
    Telangana Ltd.,
    Rep. by its Chairman and Managing Director,
    & others.
    
                                                           ..... Respondents
    
    O R D E R:

    Petitioner is a company incorporated in 2011 under

    TIN No. U74999AP2010PLCD66652 and is engaged in the

    SPONSORED

    business of distilleries manufacturing and operates a

    co-generation power plant with a capacity of 6 MW at

    Jakkepally Village, Yalal Mandal, Vikarabad District. The

    construction of the co-generation power plant commenced in the

    year 2011 and the plant was synchronized on 30.12.2012. The

    said co-generation plant supplied power to the Indian Electricity

    Exchange (IEX) from January 2013 to February 2014.

    Petitioner’s LT connection was upgraded to HT connection in
    2

    January 2013, and a High-Tension Agreement was executed on

    01.04.2013 with Respondent authorities.

    1.1. The specific case of Petitioner is that the 4th

    Respondent-Superintending Engineer, Operation Circle, Ranga

    Reddy South had issued proceedings vide Lr.

    No.SE/OP/RRS/SAO/JAO/HT/D.No. 164/14 dated

    31.05.2014, clearly stating that the HT supply to Petitioner’s

    company was disconnected on 10.02.2013 in accordance with

    the orders of the Chief General Manager (Commercial) issued for

    auxiliary consumption vide Memo No. CGM(C)/SE/DE/ADE-

    III/D.No.2691/2013 dated 08.10.2013. In the said letter, it is

    clearly mentioned that HT Agreement dated 01.04.2013 stood

    terminated with effect from 07.03.2014, as per Clause 5.9.4.2 of

    the General Terms and Conditions of Supply, and that the dues

    as on that date amounted to (-) Rs. 56,079/- i.e. no amount was

    due from Petitioner, and rather, Petitioner was entitled to a

    refundable balance after adjustment of the consumption deposit

    by Respondents. The said communication also directed that no

    fresh service, either LT or HT, should be released in Petitioner’s

    premises until a no-dues certificate was issued, thereby

    conclusively closing the account.

    1.2. It is contended by Petitioner that the aforesaid

    proceedings dated 31.05.2014 had attained finality and that
    3

    there were no pending dues or allegations of unauthorized use

    of power. However, to the utter shock of Petitioner, an

    inspection report dated 02.07.2014 was prepared by the 7th

    Respondent-Assistant Divisional Engineer, DPE/HT, Corporate

    Office, Mint Compound, Hyderabad-alleging “indicative

    unauthorized drawal of power” for the period between

    30.12.2012 and 12.06.2014, and levelling a wholly baseless

    demand of Rs.1,17,31,158/-, and that the said report was

    issued without any notice, without conducting any inspection in

    the presence of Petitioner’s authorized representatives, and

    without any reference to the earlier proceedings dated

    31.05.2014, which declared no dues. Petitioner asserts that the

    said inspection was not authorized under law and was carried

    out in contravention of Section 126 of the Electricity Act, 2003,

    which mandates that an assessment for unauthorized use of

    electricity can be made only by an authorized assessing officer

    after due notice and hearing.

    1.3. It is further stated that the HT supply having been

    disconnected in February, 2013 and the HT Agreement having

    been terminated in March 2014, the question of unauthorized

    drawl of power thereafter does not arise. Hence, the inspection

    report dated 02.07.2014 and the demand raised pursuant

    thereto is wholly without jurisdiction, fabricated, and contrary
    4

    to the factual position acknowledged by Respondents

    themselves in the earlier official records. That apart, notices

    dated 15.12.2015 and 21.03.2016 issued by Respondents under

    Form ‘A’ and Form ‘B’ respectively were issued under Section 24

    of the Indian Electricity Act, 1910, which had long been

    repealed by Section 185 of the Electricity Act, 2003. Therefore,

    the said notices are illegal and unsustainable in the eyes of law.

    1.4. It is the further case of Petitioner that during the

    period between February 2014 and November 2016, the plant

    remained non-operational owing to severe financial distress and

    internal disputes among directors. No power was drawn during

    this period and yet Respondents continued to raise fictitious

    demands. The impugned notices in Form ‘A’ and Form ‘B’,

    though dated 2015 and 2016, were served only in February

    2019, almost five years later and were followed by Form ‘C’

    dated 02.08.2019. Petitioner immediately made a representation

    dated 02.03.2019 to the 1st Respondent seeking withdrawal of

    Unscheduled Interchange (UI) charges and penalty amounts,

    explaining the entire factual background. However, without

    considering the representation or affording an opportunity of

    hearing, Respondents rejected the same vide Memo dated

    19.03.2020, confirming the illegal demands.

    5

    1.5. Petitioner submits that the impugned notices are

    barred by limitation under Section 56(2) of the 2003 Act, which

    provides that “no sum due from any consumer shall be

    recoverable after the period of two years from the date when

    such sum first became due unless such sum has been shown

    continuously as recoverable as arrears of charges.” The alleged

    dues pertain to the period 2013-2014, while the demands were

    raised and served only in 2019, without being shown

    continuously as arrears in the subsequent bills. Therefore, the

    demands are ex facie barred by limitation, illegal, and

    unenforceable.

    1.6. To substantiate this legal contention, Petitioner

    relied upon the authoritative pronouncement of the Hon’ble

    Supreme Court in Ajmer Vidyut Vitran Nigam Ltd. v.

    Rahamatullah Khan (Civil Appeal No. 1672 of 2020), wherein,

    interpreting Section 56(2) of the Act, it was held as follows:

    ” Sub-section (1) of Section 56 confers a statutory right to the
    licensee company to disconnect the supply of electricity, if the consumer
    neglects to pay the electricity dues. This statutory right is subject to the
    period of limitation of two years provided by sub-section (2) of Section 56
    of the Act. The period of limitation of two years would commence from
    the date on which the electricity charges became first due’ under sub-
    section (2) of Section 56. This provision restricts the right of the licensee
    company to disconnect electricity supply due to non-payment of dues by
    the consumer, unless such sum has been shown continuously to be
    recoverable as arrears of electricity supplied, in the bills raised for the
    past period. If the licensee company were to be allowed to disconnect
    6

    electricity supply after the expiry of the limitation period of two years
    after the sum became “first due”, it would defeat the object of Section
    56(2)
    .”

    1.7. Petitioner further relied on the judgment of the

    Hon’ble Bombay High Court in Maharashtra State Electricity

    Distribution Company Limited v. Electricity Ombudsman

    (W.P. No. 10764 of 2011), wherein it was held that:

    ” Unless and until the preconditions set out in sub-section (2)
    of Section 56 are satisfied, there is no question of the electricity supply
    being cut-off. The recovery proceedings may be initiated seeking to
    recover amounts beyond a period of two years, but the section itself
    imposes a condition that the amount sought to be recovered as arrears
    must, in fact, be reflected and shown in the bill continuously as
    recoverable as arrears, otherwise, the claim cannot succeed The
    Distribution Licensee cannot demand charges for consumption of
    electricity for a period of more than two years preceding the date of the
    first demand of such charges.”

    1.8. Respondents acted in complete violation of Section

    126 of the 2003 Act which governs cases of alleged

    unauthorized use of electricity. Under Section 126(3), an

    assessing officer must issue a provisional assessment, afford an

    opportunity of hearing, and pass a final order within thirty days.

    In the present case, no such procedure was followed; no

    provisional or final assessment order was served, and no

    hearing was afforded. Hence, the purported demand of

    Rs.1,17,31,158/- is in direct contravention of statutory

    provisions and cannot be sustained.

    7

    1.9. The letter dated 18.03.2021 issued by the 5th

    Respondent to the Sub-Registrar, directing not to allow

    registration of Petitioner’s properties in Survey Nos. 36, 38, 41,

    and 43 of Jakkepally Village, is without any legal authority or

    jurisdiction under the 2003 Act. The said letter is a coercive

    step designed to pressurize the Petitioner into paying unlawful

    and time-barred demands. It is brought to the notice of this

    Hon’ble Court that despite the pendency of the Writ Petition and

    subsistence of the interim order dated 29.04.2021 granted by

    this Court staying the impugned proceedings, Respondents, in

    utter disregard of judicial orders, continued to initiate fresh

    coercive steps by writing to the District Collector and Tahsildar,

    Yalal Mandal, to proceed under the A.P. State Electricity Board

    (Recovery of Dues) Act, 1984, thereby committing contempt of

    the interim orders of this Court.

    1.10. Petitioners therefore, state that the entire action of

    Respondents in issuing Forms ‘A’, ‘B’, and ‘C’ notices, rejecting

    the representation dated 02.03.2019 by Memo dated

    19.03.2020, and issuing the consequential letter dated

    18.03.2021 to the Sub-Registrar is illegal, arbitrary, without

    jurisdiction, violative of statutory provisions, and contrary to

    principles of natural justice. The demands are barred by
    8

    limitation, raised without lawful authority, and based on

    repealed statutory provisions.

    2. Respondents 1 to 4, 6, and 7 filed a detailed

    Counter Affidavit through the Superintending Engineer,

    Operation Circle, Vikarabad, opposing the Writ Petition. The 5th

    Respondent has also filed an Additional Counter Affidavit,

    bringing on record subsequent events that transpired during the

    pendency of the Writ Petition. The combined stand of the

    Respondents is set out hereunder:

    The answering Respondents in the Counter Affidavit

    submit that the present Writ Petition is devoid of merit and is

    liable to be dismissed, as the impugned demand notices were

    issued strictly in accordance with the provisions of the2003 Act,

    the A.P. State Electricity Board (Recovery of Dues) Act, 1984,

    and the A.P. State Electricity Board (Recovery of Dues) Rules,

    1985. It is asserted, Petitioner has deliberately suppressed the

    material facts regarding unauthorized withdrawal of electricity

    and failure to pay Unscheduled Interchange (UI) charges and

    other statutory dues. Petitioner originally obtained a Low

    Tension (LT) Category-III (B) connection, Service Connection No.

    2418000206, with a contracted load of 149 HP, which was

    released on 02.02.2011 for its distillery unit. Subsequently, they

    proposed a 6 MW Biomass-based Co-generation Power Project
    9

    for captive use and export under open access. The said proposal

    was sanctioned by NREDCAP vide Proceedings No.

    NREDCAP/RBOL/Biomass Co-gen/2012/2937, dated

    21.01.2012. Thereafter, Petitioner vide letter dated 23.06.2012

    requested permission to utilize 51% of the installed capacity for

    captive consumption and export the remaining capacity to the

    grid through open access on a temporary basis. It was also

    requested that the plant be synchronized with the grid. On

    06.12.2012, the Petitioner once again addressed the authorities

    stating that all synchronization works were completed.

    2.1. Subsequently, on 07.12.2012, Petitioner furnished

    a categorical undertaking stating that it would not draw any

    power for start-up or auxiliary consumption from APCPDCL

    (now TSSPDCL), and that it would shortly apply for an HT

    connection and that on 24.12.2012, while requesting

    installation of internal consumption meters, Petitioner reiterated

    that it would not draw any power from the grid during or after

    synchronization and would not claim any compensation for

    inadvertent power injected into the grid. Contrary to these

    representations, the Petitioner allegedly indulged in

    unauthorized drawal of electricity from the grid.

    10

    2.2. Respondents had stated that Petitioner’s LT service

    was disconnected on 10.02.2013 for non-payment of current

    consumption charges. As per APERC’s Tariff Order for 2013-14,

    all services above 100 HP were required to be shifted to High

    Tension (HT). Accordingly, Petitioner’s LT service was converted

    to HT Category-1, Service Connection No. VKB1630 (Old No.

    RRS1630), with a Contracted Maximum Demand (CMD) of 130

    KVA, effective 01.04.2013. Petitioner’s co-generation plant was

    synchronized on 30.12.2012. It is admitted, as per Memo No.

    CGM(C)/SE(C)/ADE-II/D.No.2691/2013 dated 08.10.2013, the

    HT supply to Petitioner’s industry was disconnected on

    10.02.2013 and the HT Agreement dated 01.04.2013 was

    terminated with effect from 07.03.2014, under Clause 5.9.4.2 of

    the General Terms and Conditions of Supply (GTCS). The dues

    as on the date of termination were recorded as (-) Rs. 56,079/-

    after adjusting the consumption deposit of Rs. 1,47,742/-

    2.3. Respondents, however, state that the said

    termination and no-dues statement pertained to the original

    LT/HT Cat-I connection and not to the co-generation plant

    operating at 33 KV under HT Category-II. Petitioner’s 33 KV line

    for evacuation of power was sanctioned vide Letter No.

    SE/OP/RRS/Comml/C.O.O.Ms.No.284/2012-13 D.No.3105/12

    dated 15.09.2012, for an estimated cost of Rs. 8,98,203/- on a
    11

    turnkey basis. Petitioner’s co-generation plant was thus

    synchronized on 30.12.2012 at 33 KV voltage level without any

    sanction for start-up or auxiliary power supply. While so, on

    12.06.2014, upon receiving a complaint from the Divisional

    Engineer (Operations), Vikarabad, Petitioner was drawing power

    unauthorisedly from the grid, the Assistant Divisional Engineer

    (DPE/HT) inspected the premises. The inspection revealed that

    Petitioner had been drawing electricity for start-up and auxiliary

    consumption without permission, contrary to its own

    undertaking. Accordingly, a case under Section 126 of the 2003

    Act was booked for unauthorized use of electricity from

    30.12.2012 to 12.06.2014, and a provisional assessment notice

    dated 19.07.2014 was issued demanding Rs. 1,17,21,158/-.

    Petitioner was called upon to file objections within 15 days or

    pay the assessed amount. They neither paid the demanded

    amount nor filed any objections. Consequently, the service

    connection was disconnected on 30.07.2014 and HT agreement

    was terminated on 30.11.2014 under Clause 5.9.4.3 of the

    GTCS.

    2.4. Respondents further contend that Petitioner

    scheduled and sold power through the Indian Electricity

    Exchange (IEX) from January 2013 to June 2014 without actual

    generation of electricity, thereby deriving wrongful gain and
    12

    violating the grid code. It is stated, Unscheduled Interchange

    (UI) charges were levied from 28.01.2013 to 01.06.2014

    amounting to Rs. 2,42,34,007/-, out of which Petitioner paid up

    to 22.12.2013 but defaulted thereafter. Several notices were

    issued between October 2013 and August 2014 demanding

    payment, but Petitioner failed to comply.

    2.5. In view of the continued non-payment, Respondents

    issued statutory Form ‘A’, Form ‘B’, and Form ‘C’ notices under

    the A.P. SEB (Recovery of Dues) Rules, 1985 demanding

    cumulative dues of Rs. 8,00,67,563/- as on 31.07.2019,

    including surcharge for delayed payment. The detailed

    calculation of arrears, surcharge, and back billing was

    furnished, showing the accumulation of total dues of

    Rs. 9,53,97,998/- as on 31.07.2021. It is therefore, contended

    that the plea of limitation under Section 56(2) of the Act is

    misconceived, as the demands were continuously raised from

    2013 onwards and reflected as recoverable arrears. Petitioner’s

    letter dated 02.03.2019 requesting waiver of UI charges and

    offering to pay the back-billing amount in installments

    constitutes a clear acknowledgment of debt.

    2.6. Respondents also assert that due to non-payment,

    letter dated 18.03.2021 was issued to the Sub-Registrar,

    Seetharampet, Tandur Village, requesting not to register or
    13

    transfer any of Petitioner’s properties in Survey Nos. 36, 38, 41,

    and 43 of Jakkepally Village, until the outstanding dues were

    cleared. The interim order of this Court dated 29.04.2021

    causes serious prejudice to the distribution company and

    should be vacated. Respondents accordingly, pray that this

    Court dismiss the Writ Petition and vacate the interim order

    dated 29.04.2021.

    3. The 5th Respondent, Superintending Engineer,

    Operation Circle, Vikarabad, filed an Additional Counter

    Affidavit narrating the subsequent developments that occurred

    after the interim orders dated 29.04.2021. It is stated that

    during the pendency of Writ Petition, Petitioner approached the

    1st Respondent seeking waiver of penal and Ul charges.

    Pursuant to this, vide Letter No.

    SE/OP/VKB/SAO/JAO/HT/D.No.1960/21 dated 23.09.2021, a

    request was made to the District Collector, Vikarabad, to initiate

    action under Section 5 of the A.P. State Electricity Board

    (Recovery of Dues) Act, 1984. The District Collector accordingly

    directed the Tahsildar, Yalal Mandal, to initiate recovery

    proceedings vide Letter No. D2/13134/2021 dated 23.11.2021,

    resulting in a Demand Notice under Section 7 of the Revenue

    Recovery Act, 1864 issued on 28.02.2023 (No. B/7/170/2023).
    14

    3.1. Subsequently, Petitioner again approached the 1st

    Respondent on 09.10.2023, expressing willingness to pay the

    total back-billing, penal, and UI charges in easy installments.

    On such request, the Chief General Manager (Commercial), vide

    Lr.No.CGM(C)/SE(C)/DE(C)-1/ADE-IV/D.No.2602/2023-24

    dated 25.10.2023, permitted Petitioner to pay a total

    outstanding of Rs. 10,95,64,096/- in twelve (12) monthly

    installments, subject to surcharge and adherence to tariff and

    GTCS conditions. It is further stated, Petitioner made payment

    of the first two installments but defaulted in the third

    installment due on 25.12.2023. Consequently, the Assistant

    Divisional Engineer (Operations), Tandur, was instructed to

    disconnect Petitioner’s linked LT service for non-payment, vide

    Lr.No.CGM(C)/SE(C)/DE(C)-1/ADE-IV/D.No.9602/2023-24

    dated 27.12.2023.

    3.2. The 5th Respondent thus contends that in view of

    Petitioner’s unconditional acceptance of the payment schedule

    and part-payment thereof, the cause of action in Writ Petition

    no longer survives. It is argued that Petitioner cannot now

    challenge the validity of demands it has already accepted.

    Consequently, Respondents initiated lawful recovery

    proceedings through the Revenue Department, and therefore,

    submit that Writ Petition is devoid of merit, Petitioner
    15

    suppressed material facts, and the interim orders have been

    misused to delay recovery of legitimate dues. Respondents

    therefore pray that this Court dismiss the Writ Petition, uphold

    the legality of all demand and recovery proceedings, and vacate

    the interim orders dated 29.04.2021.

    4. Heard Sri Raja Sripathi Rao, learned Senior

    Counsel assisted by Sri Rahul Kandharkar, learned counsel for

    petitioner as well as Sri N. Sreedhar Reddy, learned Standing

    Counsel for respondents.

    5. At the time of filing of Writ Petition, I.A.No. 1 of

    2021 was filed seeking stay of all further proceedings in

    pursuance of the notices dated 15.12.2015 in Form ‘A’ with

    demand of Rs.3,88,11,228/-, another notice dated 21.03.2016

    in From-B, with demand of Rs.4,70,78,020 and the subsequent

    notice dated 02.08.2019 in Form ‘C’ demanding

    Rs.8,00,67,563/- issued by the 5th Respondent against the

    Petitioner Company and consequential letter dated 18.03.2021

    addressed by the 5th Respondent to the 8th Respondent pending

    disposal of the writ petition.. This Court had passed Interim

    order on 29.04.2021 in I.A.No.1 of 2021, In view of the same,

    there shall be an interim stay, as prayed for.

    16

    6. The aforementioned interim order is in subsistence

    till date, though Respondents have filed Counter together with

    Vacate Petition. Be that as it may, as against the subsistence of

    the interim order, have approached the District Collector vide

    letter No. 6E/OP/VKB/SAO/JAO/HT/D.No.1960/21 dated

    23.09.2021 who, in turn, directed the Thasildar, Kodangal

    Tandur, Parigi and Vikarabad, Vikarabad District to initiate

    action against the Petitioner Company under Section (5) if the

    Andhra Pradesh State Electricity Board (Recovery of Dues) Act,

    1984. That apart, it is also apparent that during the subsistence

    of the interim order mentioned supra, Respondent No.5 had

    issued Memo dated 01.12.2021 to the Divisional Engineer

    (Operations), Respondent No.7 to follow-up with the concerned

    MRO/Thasildar for recovery of the amounts from Petitioner and

    the same was followed by another letter from Respondents vide

    letter dated 16.02.2022 to the effect the disconnection of the

    service connection, if the above payments are not made cleared,

    immediately. This action of Respondents is continued by the

    issuance of another letter dated 12.10.2023 requesting the

    Tahsildar, Yalal Mandal, Vikarabad District to issue auction

    notice to Petitioner Company for recovery of electricity dues at

    early date. The afore-mentioned acts of Respondents were taken

    in the back drop of the undisputed fact that the 4th
    17

    Respondent, through its official communication

    Lr.No.SE/OP/RR/S/SAO/JAO/HT/D.No.164/14, dated

    31.05.2014, had categorically recorded that the High Tension

    Agreement dated 01.04.2013 stood terminated with effect from

    07.03.2014 under Clause 5.9.4.2 of the General Terms and

    Conditions of Supply (GTCS), and further declared that

    Petitioner was not due to pay any arrears and that Rs. 56,079/-

    stood refundable after adjustment of consumption deposit. Once

    such a finding was recorded by the competent authority, the

    same is conclusive and binding upon the department. The

    subsequent issuance of Form ‘A’ notice dated 15.12.2015, Form

    ‘B’ notice dated 21.03.2016, and Form ‘C’ notice dated

    02.08.2019, demanding Rs.3,88,11,228/-, Rs. 4,70,78,020/-,

    and Rs.8,00,67,563/-respectively, stands in direct contradiction

    to the Respondents’ own official record and is ex facie arbitrary

    and unsustainable, thereby, the aforesaid acts of the

    Respondents are acts of commission and omission which are to

    be found fault with.

    7. This Court observes that Respondents violated the

    mandatory procedure contemplated under Section 126 of the

    Act, which governs the assessment for unauthorized use of

    electricity. The said provision requires that a provisional

    assessment be issued by the designated assessing officer,
    18

    followed by an opportunity to file objections and a final order to

    be passed within thirty days. In the instant case, the so-called

    inspection report dated 02.07.2014, alleging “indicative

    unauthorized drawal of power” and levying Rs.1,17,31,158/-,

    was neither preceded nor followed by any provisional

    assessment, notice, or hearing. Petitioner was never put on

    notice or afforded an opportunity to explain. Consequently, the

    alleged assessment and all proceedings based thereon are

    rendered void ab initio, being in violation of sub-sections (2) and

    (3) of Section 126 of the Act.

    8. Respondents invocation of Section 24 of the Indian

    Electricity Act, 1910, in the impugned Form ‘A’ and Form ‘B’

    notices, is patently without jurisdiction. The said Act stood

    repealed upon the enforcement of the Electricity Act, 2003, by

    virtue of Section 185 thereof, which expressly repeals the Indian

    Electricity Act, 1910, the Electricity (Supply) Act, 1948, and the

    Electricity Regulatory Commissions Act, 1998. Any reliance

    upon repealed provisions is impermissible in law and

    demonstrates total non-application of mind on the part of the

    authorities. The impugned notices, having been issued under a

    repealed enactment, are legally non est.

    9. This Court further finds that the demands raised

    are clearly barred by limitation under Section 56(2) of the Act,
    19

    which mandates that “no sum due from any consumer shall be

    recoverable after the period of two years from the date when

    such sum first became due, unless such sum has been shown

    continuously as recoverable as arrears.” The alleged period of

    consumption and assessment pertains to 2013-14, whereas the

    first demand notice was issued only in 2015, followed by further

    demands in 2016 and 2019. There is no material placed on

    record to demonstrate that the alleged dues were ever shown

    continuously as recoverable in the subsequent billing cycles.

    Therefore, the demands are ex facie time-barred and

    unenforceable.

    10. The position of law in this regard is no longer res

    integra. The Hon’ble Supreme Court in Ajmer Vidyut Vitran

    Nigam Ltd. v. Rahamatullah Khan (Civil Appeal No.1672 of

    2020) categorically held that “the period of limitation of two

    years would commence from the date on which the electricity

    charges became first due, and any disconnection or recovery

    after the expiry of that period, without showing continuous

    arrears, would defeat the very object of Section 56(2).” Similarly,

    the Hon’ble Bombay High Court in Maharashtra State

    Electricity Distribution Co. Lad. v. Electricity Ombudsman

    (W.P. No.10764 of 2011) held that “unless the amount sought to

    be recovered has been continuously shown as arrears in the
    20

    bills, the Distribution Licensee is precluded from demanding

    charges beyond two years. The ratio of these binding precedents

    squarely applies to the facts of the present case.

    11. Respondents’ subsequent action in issuing Memo

    dated 19.03.2020, rejecting Petitioner’s detailed representation

    dated 02.03.2019 without considering the factual and legal

    objections, further exhibits non-application of mind and

    procedural irregularity. The rejection is devoid of any reasoning

    and contrary to the requirement of a speaking order under

    administrative law principles. Likewise, letter dated 18.03.2021,

    addressed by the 5th Respondent to the Sub-Registrar,

    Seetharampet, Tandur, directing that no registration or transfer

    of the Petitioner’s property in Survey Nos.36, 38, 41, and 43,

    Jakkepally Village, be affected, is wholly without authority

    under the Electricity Act, 2003. No provision of the Act

    empowers Respondents to impose restrictions upon property

    transactions of consumers. Such an action, de hors any

    statutory backing, constitutes a blatant violation of Article 300-

    A of the Constitution, which guarantees protection against

    deprivation of property save by authority of law.

    12. It is further apparent, as mentioned supra, that

    during the subsistence of the interim order dated 29.04.2021,

    Respondents proceeded to request the District Collector,
    21

    Vikarabad, through Letter dated 23.09.2021, to initiate recovery

    proceedings under Section 5 of the A.P. State Electricity Board

    (Recovery of Dues) Act, 1984, culminating in the issuance of

    Demand Notice dated 28.02.2023, by the Tahsildar, Yalal

    Mandal. Such actions, undertaken during the pendency of Writ

    Petition, amount to willful disobedience of the subsisting stay

    order and are in flagrant violation of judicial discipline. The

    subsequent letter of Petitioner dated 09.10.2023, expressing

    willingness to pay the dues in installments, followed by the

    permission granted under Letter dated 25.10.2023, was

    evidently issued under coercion and pressure of unlawful

    recovery proceedings. Such consent obtained under duress

    cannot validate an otherwise illegal and time-barred demand.

    The conduct of the Petitioner is bona fide. It had made repeated

    representations requesting waiver of UI charges, and their

    requests have been rejected arbitrarily and Petitioner’s

    subsequent request for installment facility was under the

    adverse circumstances created at the instance of Respondents,

    which is made under coercion of illegal recovery proceedings

    and thereby the said act of Petitioner cannot be construed as an

    admission of liability. The alleged acceptance of installments

    was under duress and cannot extinguish Petitioner’s

    substantive legal rights or render Writ Petition infructuous. At
    22

    this juncture, this Court is bound to follow the law laid down by

    the Hon’ble Apex Court in Celir LLP v. Sumati Prasad Bafna1

    case wherein it was laid down that all the acts that are down in

    violation of the court orders are nullity and as a consequence of

    the same, said acts are liable to be set aside. Relevant Portion

    from the said order are extracted hereunder :-

    “C. ISSUES FOR DETERMINATIN DETERMINATION

    109. Having heard the learned counsel appearing for the parties and having
    gone through the materials on record, the following questions fall for our
    consideration:-

    I. Whether any act of contempt could be said to have been committed by the
    respondent nos. I to 4 respectively of the judgment and order dated
    21.09.2023 passed by this Court in Civil Appeal Nos. 5542-5543 of 2023? In
    other words, whether the respondents herein in light of the aforesaid
    decision of this Court were duty bound to cancel the Release Deed dated
    28.08.2023 and hand over the physical possession along with the original
    title deeds of the Secured Asset to the petitioner herein?

    II. Whether, the proceedings arising out of S.A. No. 46 of 2022 could have
    continued after this Court’s judgment and order dated 21.09.2023 directing
    the issuance of the Sale Certificate of the Secured Asset to the petitioner
    herein? In other words, whether the petitioner by virtue of the Sale
    Certificate dated 27.09.2023 is said to have acquired a clear title to the said
    property?

    III. Whether the transfer of the Secured Asset in favour of the Subsequent
    Transferee by way of the Assignment Agreement dated 28.08.2023 is hit by
    lis pendens? In other words, whether the absence of any registration in
    accordance with Section 52 of the TPA as amended by the State of
    Maharashtra renders the lis pendens inapplicable?

    *****
    iii. Whether any contempt is said to have been committed by the respondents
    herein?

    1
    2024 SCC On line SC 3727
    23

    182. In order to decide whether the appellants are guilty of civil contempt, it
    would be apposite to refer to Section 2(b) of the Act, 1971, which reads as
    under:-

    2.Definitions. In this Act, unless the context otherwise requires, xxx xxx xxx

    (b) “civil contempt” means wilful disobedience to any judgment, decree,
    direction, order, writ or other process of a court or wilful breach of an
    undertaking given to a court;”

    183. The Black’s Law Dictionary, Sixth Edition, at page 1599, defines
    “willful” as hereunder:-

    “Proceeding from a conscious motion of the will; voluntary; knowingly,
    deliberate. Intending the result which actually comes to pass; designed;
    intentional; purposeful; not accidental or involuntary. Premeditated;
    malicious; done with evil intent, or with a bad motive or purpose, or with
    indifference to the natural consequences; unlawful; without legal
    justification. An act or omission is “willfully” done, if done voluntarily and
    intentionally and with the specific intent to do something the law forbids, or
    with the specific intent to fail to do something the law requires to be done,
    that is to say, with bad purpose elther to disobey or to disregard the law. It is
    a word of many meanings, with its construction often influenced by its
    context. In civil actions, the word (willfully) often denotes an act which is
    intentional, or knowing, or voluntary, as distinguished from accidental. But
    when used in a stubbornly, obstinately, perversely.

    184. In Ashok Paper Kamgar Union v. Dharam Godha, (2003) 11 SCC 1, the
    expression ‘wilful disobedience in the context of Section 2 (b) of the Act, 1971
    was read to mean an act or omission done voluntarily and intentionally with
    the specific intent to do something, which the law forbids or with the specific
    intention to fail to do something which the law requires to be done.
    Wilfulness signifies deliberate action done with evil Intent and bad motive
    and purpose. It should not be an act, which requires and is dependent upon,
    either wholly or partly, any act or omission by a third party for compliance.

    185. Hence, the expression or word “wilful” means act or omission which is
    done voluntarily or intentionally and with the specific intent to do something
    which the law forbids or with the specific intent to fail to do something the
    law requires to be done, that is to say with bad purpose either to disobey or
    to disregard the law. It signifies a deliberate action done with evil intent or
    with a bad motive or purpose.

    24

    186. Article 129 of the Constitution declares this Court as a “a court of
    record” and states that it shall have all the powers of such a court including
    the power to punish for contempt of itself. The provisions of the Act, 1971
    and the Rules framed thereunder form a part of a special statutory
    Jurisdiction that is vested in courts to punish an offending party for its
    contemptuous conduct. It needs no emphasis that the power of contempt
    ought to be exercised sparingly with great care and caution. The
    contemptuous act complained of must be such that would result in
    obstruction of justice, adversely affect the majesty of law and impact the
    dignity of the courts of law.

    187. It must also be understood that contempt proceedings are sui generis
    inasmuch as the Law of Evidence and the Criminal Procedure Code, 1973
    are not to be strictly applied. At the same time, the procedure adopted during
    the contempt proceedings must be fair and just that is to say the principles
    governing the Rule of law must be extended to the party against whom
    contempt proceedings have been initiated. The party must have every
    opportunity to place its position before the Court. Such a party must not be
    left unheard under any circumstances.

    188. In Ram Kishan v. Tarun Bajaj, (2014) 16 SCC 204 it was held that the
    contempt jurisdiction conferred on to the law courts power to punish an
    offender not only for his wilful disobedience but also for contumacious
    conduct or obstruction to the majesty of law. It further observed that such
    power has been conferred for the simple reason that the respect and
    authority commanded by the courts of law are the greatest guarantee to an
    ordinary citizen that his rights shall be protected and the entire democratic
    fabric of the society will crumble down if the respect of the judiciary is
    undermined. The relevant observations read as under:-

    “11. The contempt jurisdiction conferred on to the law courts power to
    punish an offender for his wilful disobedience/contumacious conduct or
    obstruction to the majesty of law, for the reason that respect and authority
    commanded by the courts of law are the greatest quarantee to an ordinary
    citizen that his rights shall be protected and the entire democratic fabric of
    the society will crumble down if the respect of the judiciary is undermined.
    Undoubtedly, the contempt jurisdiction is a powerful weapon in the hands of
    the courts of law but that by itself operates as a string of caution and unless,
    thus, otherwise satisfied beyond reasonable doubt, it would neither be fair
    25

    nor reasonable for the law courts to exercise jurisdiction under the Act. The
    proceedings are quasi criminal in nature, and therefore, standard of proof
    required in these proceedings is beyond all reasonable doubt. It would rather
    be hazardous to impose sentence for contempt on the authorities in exercise
    of the contempt jurisdiction on mere probabilities. […]”

    (Emphasis supplied)

    189. In Murray & Co. v. Ashok Kr. Newatia, (2000) 2 SCC 367 this Court
    held that the purpose of contempt jurisdiction is to uphold the majesty and
    dignity of the courts of law since the image of such a majesty in the minds of
    the people cannot be led to be distorted, as any Indulgence which can even
    remotely be termed to affect the majesty of law would result in the society
    losing its confidence and faith in the judiciary and the law courts forfeiting
    the trust and confidence of the people in general. The relevant observations
    read as under:-

    “9 […] The purpose of contempt jurisdiction is to uphold the majesty and
    dignity of the courts of law since the image of such a majesty in the minds of
    the people cannot be led to be distorted. The respect and authority
    commanded by courts of law are the greatest guarantee to an ordinary
    citizen and the entire democratic fabric of the society will crumble down if
    the respect for the judiciary is undermined. It is true that the judiciary will
    be judged by the people for what the judiciary does, but in the event of any
    indulgence which can even remotely be termed to affect the majesty of law,
    the society is bound to lose confidence and faith in the judiciary and the law
    courts thus, would forfeit the trust and confidence of the people in general.”

    (Emphasis supplied)

    190. In Pushpaben v. Narandas Badiani, (1979) 2 SCC 394, it was held
    that contempt of court is a special jurisdiction to be exercised sparingly and
    with caution whenever an act adversely affects the administration of justice
    or which tends to impede its course or tends to shake public confidence in
    the judicial institutions. It further held that this jurisdiction is to be
    exercised not for the protection of the dignity of an individual judge but to
    protect the administration of justice from being maligned and ensure that the
    authority of the courts is neither imperilled nor is the administration of
    justice by it interfered with in any manner. The relevant observations read as
    under:-

    42. The contempt of court is a special jurisdiction to be exercised sparingly
    and with caution whenever an act adversely affects the administration of
    26

    justice or which tends to impede its course or tends to shake public
    confidence in the judicial institutions. This jurisdiction may also be exercised
    when the act complained of adversely affects the majesty of law or dignity of
    the courts. The purpose of contempt jurisdiction is to uphold the majesty
    and dignity of the courts of law. It is an unusual type of jurisdiction
    combining “the jury, the judge and the hangman” and it is so because the
    court is not adjudicating upon any claim between litigating parties. This
    jurisdiction is not exercised to protect the dignity of an individual judge but
    to protect the administration of justice from being maligned. In the general
    interest of the community it is imperative that the authority of courts should
    not be imperilled and there should be no unjustifiable interference in the
    administration of justice. It is a matter between the court and the contemner
    and third parties cannot intervene. It is exercised in a summary manner in
    aid of the administration of justice, the majesty of law and the dignity of the
    courts. No such act can be permitted which may have the tendency to shake
    the public confidence in the fairness and impartiality of the administration of
    justice.” (Emphasis supplied)

    191. In Reliance Petrochemicals Ltd. v. Proprietors of Indian Express
    Newspapers, Bombay Pvt. Ltd.
    (1988) 4 SCC 592 it was observed that the
    process of due course of administration of justice must remain unimpaired,
    Public interest demands that there should be no interference with judicial
    process and the effect of the judicial decision should not be pre-empted or
    circumvented. The relevant observations read as under:-

    “35. The question of contempt must be judged in a particular situation. The
    process of due course of administration of justice must remain unimpaired.
    Public interest demands that there should be no interference with judicial
    process and the effect of the judicial decision should not be pre-empted or
    circumvented by public agitation or publications. It has to be remembered
    that even at turbulent times through which the developing countries are
    passing, contempt of court means interference with the due administration of
    justice.” (Emphasis supplied)

    192. In Rita Markandey v. Surjit Singh Arora, (1996) 6 SCC 14, it was
    observed that even if parties have not filed an undertaking before the court
    but if the court was induced to sanction a particular course of action or
    inaction on the representation made by a party and the court ultimately
    finds that the party never intended to act on the said representation or such
    27

    representation was false, the party would be guilty of committing contempt.
    The relevant observations read as under:-

    12. Law is well settled that if any party gives an undertaking to the court to
    vacate the deliberate from which he is liable to be evicted underlivres an us
    of the court and there is a clear and de did n breach thereof it amounts to
    civil contempt but since, in the present case, the peling punished for file any
    undertaking as envisaged in the not but sings Court the question of his being
    punished for breach thereof does not arise. However, in our considered view
    even in a caset if the court undertaking is given, a party to a litigation may
    be held liable for such contempt if the court of induced to sanction a
    particular course of action or inaction on the basis of the representation of
    such a party and the court ultimately finds that the party never intended to
    act on such representation or such representation was false In other words,
    if on the representation of the respondent herein the Court was persuaded to
    pass the order dated 5-10-1995 extending the time for vacation of the suit
    premises, he may be held guilty of contempt of court, notwithstanding nont
    furnishing of the undertaking, if it is found that the representation was false
    and the respondent never intended to act upon it. […]” (Emphasis supplied)

    193. The Borrower and the Subsequent Transferee/the alleged contemnors
    herein placing reliance on the decision of this Court in Patel Rajnikant
    (supra) have contended that in the absence of any disobedience or wilful
    breach of a prohibitory order no contempt could be said to have been
    committed. It has been further canvased that this Court in the Main Appeals
    never issued any specific direction either to the Borrower or the Subsequent
    Transferee, & therefore no contempt could be said to have been committed.

    194. In Patel Rajnikant (supra) this Court upon examining Section 2

    (b) of the Act, 1971 held that to hold a person guilty of having committed
    contempt, there must be a judgment, order, direction etc. by a court, there
    must be disobedience of such judgment, order, direction etc and that such
    disobedience must be willful. The relevant provisions read as under:-

    “58. The provisions of the Contempt of Courts Act, 1971 have also been
    invoked. Section 2 of the Act is a definition clause. Clause (a) enacts that
    contempt of court means “civil contempt or criminal contempt. Clause (b)
    defines “civil contempt” thus.

    “2. (b) civil contempt” means wilful disobedience to any judgment, decree,
    direction, order, wit or other process of a court or wilful breach of an
    undertaking given to a court;” Reading of the above clause makes it clear
    28

    that the following conditions must be satisfied before a person can be held to
    have committed a civil contempt:

    (i) there must be a judgment, decree, direction, order, writ or other process of
    a court (or an undertaking given to a court); (ii) there must be disobedience
    to such judgment, decree, direction, order, writ or other process of a court (or
    breach of undertaking given to a court); and (iii) such disobedience of
    judgment, decree, direction, order, writ or other process of a court (or breach
    of undertaking) must be wilful.”

    195. However, the subsequent observations made by this Court in Patel
    Rajnikant (supra) are significant. It observed that the court should not
    hesitate in wielding the potent weapon of contempt, It is for the proper
    administration of justice and to ensure due compliance with the orders
    passed by it in order to uphold and maintain the dignity of courts and
    majesty of law. The relevant observations read as under:-

    “70. From the above decisions, it is clear that punishing a person for
    contempt of court is indeed a drastic step and normally such action should
    not be taken. At the same time, however, it is not only the power but the
    duty of the court to uphold and maintain the dignity of courts and majesty of
    law which may call for such extreme step. If for proper administration of
    justice and to ensure due compliance with the orders passed by a court, it is
    required to take strict view under the Act, it should not hesitate in wielding
    the potent weapon of contempt.” (Emphasis supplied)

    196. What can be discerned from the above exposition of law is that any act
    of disobedience, defiance, or any attempt to malign the authority of the court
    would amount to contempt because they undermine the respect and trust
    that the public reposes in judicial institutions. The judicial process relies on
    the confidence of society, and any act that disrupts or disrespects this
    process threatens to erode the foundation of justice and order.

    197. Contempt jurisdiction exists to preserve the majesty and sanctity of the
    law. Courts are the guardians of justice, and their decisions must command
    respect and compliance to ensure the proper functioning of society. When
    Individuals or entities challenge the authority of courts through wilful
    disobedience or obstructive behaviour, they undermine the rule of law and
    create the risk of anarchy. Contempt serves as a mechanism to protect the
    integrity of the courts, ensuring that they remain a symbol of fairness,
    impartiality, and accountability.

    29

    198. When judicial orders are openly flouted or court proceedings are
    disrespected, it sends a signal that the rule of law is ineffective, leading to a
    loss of trust in the system. Judicial decisions must remain unimpaired, free
    from external pressures, manipulation, or circumvention. Acts that attempt
    to mislead the court, obstruct its functioning or frustrate its decisions distort
    the process of justice and would amount to contempt.

    199. The contempt jurisdiction of this court cannot be construed by any
    formulaic or rigid approach. Merely because there is no prohibitory order or
    no specific direction issued the same would not mean that the parties cannot
    be held guilty of contempt. The Contempt jurisdiction of the court extends
    beyond the mere direct disobedience of explicit orders or prohibitory
    directions issued by the court. Even in the absence of such specific
    mandates, the deliberate conduct of parties aimed at frustrating court
    proceedings or circumventing its eventual decision may amount to contempt.
    This is because such actions strike at the heart of the judicial process,
    undermining its authority and obstructing its ability to deliver justice
    effectively. The authority of courts must be respected not only in the letter of
    their orders but also in the broader spirit of the proceedings before them.

    200. Any contumacious conduct of the parties to bypass or nullify the
    decision of the court or render it ineffective, or to frustrate the proceedings of
    the court, or to enure any undue advantage therefrom would amount to
    contempt. Attempts to sidestep the court’s jurisdiction or manipulate the
    course of litigation through dishonest or obstructive conduct or malign or
    distort the decision of the courts would inevitably tantamount to contempt
    sans any prohibitory order or direction to such effect.

    201. Thus, the mere conduct of parties aimed at frustrating the court
    proceedings or circumventing its decisions, even without an explicit
    prohibitory order, constitutes contempt. Such actions interfere with the
    administration of justice, undermine e the respect and authority of the
    judiciary, and threaten the rule of law.

    202. However, at the same time, the power of contempt ought to be exercised
    sparingly and with caution and care. It operates with a string of caution and
    unless otherwise satisfied beyond doubt, it would neither be fair nor
    reasonable for the courts to resort to such powers. The standard of proof
    required before a person is held guilty of committing contempt of court must
    be beyond all reasonable doubt.

    30

    203. The courts while exercising its contempt jurisdiction must remain
    circumspect, more particularly, where there exists a possibility of the order
    being amenable to more than one interpretation. In Jhareshwar Prasad Paul
    v. Tarak Nath Ganguly
    reported in (2002) 5 SCC 352 it was held that if an
    order does not contain any specific direction regarding a matter or if there is
    any ambiguity in the directions issued therein then it would be appropriate
    to direct the parties to approach the court which disposed of the matter for
    necessary clarification of the order instead of the court exercising its
    contempt jurisdiction thereby taking upon itself the power to decide the
    original proceeding in a manner not dealt with by the court passing the
    judgment or order. The relevant observations read as under:-

    “The contempt jurisdiction should be confined to the question whether there
    has been any deliberate disobedience of the order of the court and if the
    conduct of the party who is alleged to have committed such disobedience is
    contumacious. The court exercising contempt jurisdiction is not entitled to
    enter into questions which have not been dealt with and decided in the
    judgment or order… The court has to consider the direction issued in the
    judgment or order and not to consider the question as to what the judgment
    or order should have contained. At the cost of repetition, be it stated here
    that the court exercising contempt jurisdiction is primarily concerned with
    the question of contumacious conduct of the party, which is alleged to have
    committed deliberate default in complying with the directions in the
    judgment or order. If the judgment or order does not contain any specific
    direction regarding a matter or if there is any ambiguity in the directions
    issued therein then it will be better to direct the parties to approach the
    court which disposed of the matter for clarification of the order instead of the
    court exercising contempt jurisdiction taking upon itself the power to decide
    the original proceeding in a manner not dealt with by the court passing the
    judgment or order.

    (Emphasis supplied)

    204. It is true that this Court in its decision rendered in the Main Appeals
    had not issued any specific direction either to the Borrower or the
    Subsequent Transferee as regards the handing over of physical possession
    and the original title deed to the Secured Asset, or the proceedings pending
    before the DRT in S.A. No. 46 of 2022. However, the same would not mean
    that the decision of this Court in the Main Appeal was bereft of any direction
    as to the outcome of its findings. This Court in the operative portion of the
    31

    Main Appeals stated in unequivocal terms that the confirmation of the sale
    by Bank under Rule 9(2) of the SARFAESI Rules had vested the petitioner
    herein with a right to obtain the certificate of sale of the Secured Asset. It
    further held categorically that the Borrower herein could not have redeemed
    the mortgage upon publication of the 9th auction notice. Furthermore, this
    Court explicitly directed the Bank to not only issue the Sale Certificate to the
    petitioner herein in accordance with Rule 9(6) of the SARFAESI Rules but
    also directed the refund of the amount of Rs. 129 crore paid by the Borrower.
    Moreover, the impugned order of the High Court had been set aside by this
    Court in toto. As already discussed in paragraph 154, the natural corollary
    to the aforesaid was that the judgment and order dated 21.09.2023 of this
    Court in Civil Appeals Nos. 5542-5543 of 2023 had held as under:-

    (i) The auction proceedings and the sale conducted thereto in favour of the
    petitioner herein pursuant to the 9th auction notice dated 12.06.2023 had
    been categorically affirmed and upheld. (ii) After having directed the issuance
    of the Sale Certificate in terms of Rule 9(6) of the SARFAESI Rules, nothing
    remained thereafter, as issuance of sale certificate is absolute and as such
    the proceedings before the DRT had been rendered infructuous. (iii) Having
    directed not only the issuance of the Sale Certificate to the Secured Asset but
    also the refund of the amount paid by the Borrower, towards redemption of
    mortgage, necessarily entailed that the Borrower was duty bound to return
    the possession and title deeds of the secured asset to the Bank for the
    purpose of handing the same over to (iv) Having set aside the impugned order
    passed by the High Court the petitioner in toto rendered any and all acts
    done pursuant thereto as null and void, and the Borrower and the
    Subsequent Transferee herein were required to get the Release Deed and the
    Assignment Agreement dated 28.08.2023 cancelled.

    (v) Having expressly directed the issuance of the Sale Certificate it
    necessarily excluded all other inconsistent and contrary rights and reliefs
    including the right to pursue the DRT proceedings in view of the maxim
    Expressio Unius Est Exclusio Alterius.

    205. Where a decision is rendered and the impugned order is set aside, it
    behoves any logic that an express direction to act must be given in respect of
    every aspect of the decision. The parties are duty bound to act in accordance
    with common sense. It is axiomatic that a party should obey both the letter
    and the spirit of a court order, and it is neither open for the parties to adopt
    a myopic and blinkered view of such decision nor any such interpretation or
    32

    view that sub-serves their own interests. It is ultimately the purpose for
    which the order was granted that will be the lodestar in guiding the parties
    as to the true effect of the order and determination of the court.

    206. If at all the parties are in doubts over the judgment and order of a court,
    the correct approach is to prefer a miscellaneous application for seeking
    clarification rather than proceeding to presume a self-serving interpretation
    of the decision. At this stage, we may also explain the correct approach to be
    adopted by the other courts and forums where a party seeks to espouse a
    cause based on its own understanding or interpretation of a decision of an
    higher authority. In such situations, the courts or forums should neither aid
    the parties in their attempt to reinterpret the decision of a higher court nor
    should they embark on an inquisitorial exercise of their own in order to
    derive the scope or intent of the order in question. The courts and tribunals
    should not conflate a decision of a higher court that declares a law with a
    decision that declares the inter-se rights of a parties, the former only
    operates as a precedent and thus, it is open for the lower courts to apply
    their minds to assess whether the same is applicable to the issues before it
    or what law has been laid down therein. However, the latter not only has
    precedential value but also carries with it the weight of determination of the
    issues directly involved between the very parties before it, the subject-matter
    itself and by extension the entire cause of action. Since such decisions have
    directly decided or given a finding on the inter-se rights and issues of the
    same parties that are before it and as such has to a certain extent a direct
    and palpable effect on the cause of action before it, in such circumstances,
    the courts and tribunals should refrain from interpreting or examining the
    scope or effect of such decisions on their own as the same would amount to
    relitigating the very same issues and rather should relegate the parties to
    seek clarification from the court that passed the order and adjourn further
    proceedings sine die.

    207. We further take note of the fact that both the Borrower and the
    Subsequent Transferee made several attempts to prevent the effective
    implementation of the judgment and order dated 21.09.2023 passed by this
    Court and thereby thwart the attempts of the Bank to hand over the physical
    possession and the original title deeds of the Secured Asset to the petitioner.

    (i) First, both the Borrower and the Subsequent Transferee addressed a letter
    to the MIDC in whose industrial area the Secured Asset was situated asking
    them not to entertain any request from the Bank or the petitioner regarding
    33

    the transfer of the leasehold rights of the Secured Asset in favour of the
    petitioner.

    (ii) Secondly, the Subsequent Transferee vide its letter dated 05.10.2023 even
    asked the Sub-Registrar Office, Nerul Thane not to entertain any request of
    the petitioner regarding the transfer of the Secured Asset

    (iii) The self-serving stance of the Borrower to initially contend that it no
    longer had any role or authority over the secured asset in view of its transfer
    and thus, cannot handover the physical possession and the original title
    deeds to the same, yet in the same breath filing an application seeking stay
    of the notice for obtaining physical possession of the Secured Asset.

    (iv) The police complaint lodged by the Subsequent Transferee against the
    Bank by distorting the decision of this Court in the Main Appeals and to
    thwart the attempts for its implementation.

    (v) The patently false contention of the Subsequent Transferee that it
    instituted the suit to prevent its unlawful dispossession of the Secured Asset
    due to the alleged illegal attempts of the petitioner to take the same forcefully
    yet, in the said suit instead of seeking permanent injunction, the Subsequent
    Transferee not only sought the relief of declaration of title in its favour but
    also the Invalidation of the Sale Certificate issued to the petitioner, contrary
    to the decision of this Court in the Main Appeals.

    208. In the facts of the case, we are convinced that both the Borrower and
    the Subsequent Transferee have committed contempt of this Court’s
    judgment and order dated 21.09.2023 in the Main Appeals. The
    aforementioned acts of the contemnors are nothing more than a gamble on
    their part to circumvent and undermine the findings and directions passed
    by this Court in the Main Appeals. Similarly, the lame excuses offered by
    them for explaining their conduct are also nothing more than a calculated
    attempt in the hope that they would get away with legitimizing the illegal
    Assignment Agreement even after the decision of this Court, and is equally
    contemptuous.

    209. However, on an overall conspectus of the facts of the present case, while
    the initial acts of the Borrower and the Subsequent Transferee are in
    violation of this Court’s judgment and order dated 21.09.2023, yet the efforts
    on their part to take steps and make amends by withdrawing the Special
    Civil Suit No. 5 of 2024 along with their belated unconditional undertaking to
    comply with any further order that this Court may deem fit and proper to
    pass, demonstrates their effort and willingness to purge themselves of their
    34

    contemptuous conducts. Thus, we are inclined to provide one last order
    dated 21.09.2023 passed by this Court and further comply with the
    directions issued in the present contempt petition, and thus, deem it fit not
    to hold them guilty of contempt for the present moment.
    iv. Circumstances when a sale of property by auction or other means under
    the SARFAESI Act may be set-aside after its confirmation.

    210. We must also address one very important aspect as regards when the
    sale of secured asset either by auction or any other method under the
    SARFAESI Act may be challenged or set-aside after its confirmation.

    211. In B. Arvind Kumar v. Govt of India, (2007) 5 SCC 745 this Court whilst
    dealing with a plea to set aside the sale of the property therein by way of
    public auction by the official receiver, it was held that when the sale is
    confirmed by the court, the sale becomes absolute and therefrom the title
    vests in the auction purchaser. The relevant observations read as under:-

    “12. […] When a property is sold by public auction in pursuance of an
    order of the court and the bid is accepted and the sale is confirmed by the
    court in favour of the purchaser, the sale becomes absolute and the title
    vests in the purchaser. A sale certificate is issued to the purchaser only
    when the sale becomes absolute. The sale certificate is merely the evidence of
    such title. It is well settled that when an auction purchaser derives title on
    confirmation of sale in his favour, and a sale certificate is issued evidencing
    such sale and title, no further deed of transfer from the court is
    contemplated or required. In this case, the sale certificate itself was
    registered, though such a sale certificate issued by a court or an officer
    authorised by the court, does not require registration. Section 17(2)(xii) of the
    Registration Act, 1908 specifically provides that a certificate of sale granted
    to any purchaser of any property sold by a public auction by a Civil or
    Revenue Officer does not fall under the category of non-testamentary
    documents which require registration under subsections (b) and (c) of
    Section 17(1) of the said Act. We therefore hold that the High Court
    committed a serious error in holding that the sale certificate did not convey
    any right, title or interest to plaintiff’s father for want of a registered deed of
    transfer.”

    (Emphasis supplied)

    212. In LICA (P) Ltd. v. Official Liquidator, (1996) 85 Comp Cas 788 (SC)
    this Court held that the purpose of an open auction is to get the most
    remunerative price with the highest possible public participation, and as
    35

    such the courts shall exercise their discretion to interfere where the auction
    suffers from any fraud or inadequate pricing or underbidding that too with
    circumspection, keeping in view the facts of each case. The relevant
    observations read as under:-

    “The purpose of an open auction is to get the most remunerative price and it
    is the duty of the court to keep openness of the auction so that the intending
    bidders would be free to participate and offer higher value. If that path is cut
    down or closed the possibility of fraud or to secure inadequate price or
    underbidding would loom large. The court would, therefore, have to exercise
    its discretion wisely and with circumspection and keeping in view the facts
    and circumstances in each case.” (Emphasis supplied)

    213. This Court in Valji Khimji (supra) held that once an auction is
    confirmed the objections to the same should not ordinarily be allowed, except
    on very limited grounds like fraud as otherwise no auction would ever be
    complete. The relevant observations read as under:-

    “11. It may be noted that the auction-sale was done after adequate publicity
    in well-known newspapers. Hence, if any one wanted to make a bid in the
    auction he should have participated in the said auction and made his bid.
    Moreover, even after the auction the sale was confirmed by the High Court
    only on 30-7-2003, and any objection to the sale could have been filed prior
    to that date However, in our opinion, entertaining objections after the sale is
    confirmed should not ordinarily be allowed, except on very limited grounds
    like fraud, otherwise no auction-sale will ever be complete.
    xxx 29. […] It may be mentioned that auctions are fuctiolypesub(1) where the
    auction is not subject to subsequent confirmation, and (2) where the auction
    is subject to subsequent confirmation by some authority after the auction
    held. 30. In the first case mentioned above, le. where the auction is not
    subject to confirmation by any authority, the auction is complete on the fall
    of the hammer, and certain rights accrue in favour of the auction-purchaser.
    However, where the auction is subject to subsequent confirmation by some
    authority (under a statute or terms of the auction) the auction is not
    complete and no rights accrue until the sale is confirmed by the said
    authority. Once, however, the sale is confirmed by that authority, certain
    rights accrue in favour of the auction-purchaser, and these rights cannot be
    extinguished except in exceptional cases such as fraud.” (Emphasis supplied)

    214. In Ram Kishun v. State of Uttar Pradesh reported in (2012) 11 SCC 511
    this Court although held that where public money is to be recovered such
    36

    recovery should be done expeditiously, yet the same must be done strictly in
    accordance with the procedure prescribed by law. However, this Court after
    examining a plethora of other decisions further held that once the sale has
    been confirmed it cannot be set aside unless a fundamental procedural error
    has occurred or sale certificate had been obtained by misrepresentation or
    fraud. The relevant observations read as under:-

    “13. Undoubtedly, public money should be recovered and recovery should be
    made expeditiously. But it does not mean that the financial institutions
    which are concerned only with the recovery of their loans, may be permitted
    to behave like property dealers and be permitted further to dispose of the
    secured assets in any unreasonable or arbitrary manner in flagrant violation
    of the statutory provisions.

    28. In view of the above, the law can be summarised to the effect that the
    recovery of the public dues must be made strictly in accordance with the
    procedure prescribed by law. The liability of a surety is coextensive with that
    of the principal debtor. In case there are more than one surety the liability is
    to be divided equally among the sureties for unpaid amount of loan. Once the
    sale has been confirmed it cannot be set aside unless a fundamental
    procedural error has occurred or sale certificate had been obtained by
    misrepresentation or fraud.” (Emphasis supplied)

    215. In PHR Invent Educational Society v. UCO Bank, (2024) 6 SCC 579 it
    was again reiterated that an auction-sale which stands confirmed can only
    be interfered with when there was any fraud or collusion, and entertaining of
    issues regarding the validity of such auction would amount to reopening
    issues which have achieved finality. The relevant observations read as
    under:-

    “34. In our view, the High Court ought to have taken into consideration that
    the confirmed auction-sale could have been interfered with only when there
    was a fraud or collusion. The present case was not a case of fraud or
    collusion. The effect of the order of the High Court would be again reopening
    the issues which have achieved finality.

    216. In V.S. Palanivel v. P. Sriram, 2024 INSC 659 this Court again
    reiterated unless there are some serious flaws in the conduct of the auction
    as for example perpetration of a fraud/collusion, grave irregularities that go
    to the root of such an auction, courts must ordinarily refrain from setting
    them aside keeping in mind the domino effect such an order would have. The
    relevant observations read as under:-

    37

    “36.14. This Court must underscore the well settled legal position
    that once an auction is confirmed, it ought to be interfered with on fairly
    limited grounds. (Refer: Valji Khimji and Co. v. Hindustan Nitro Product
    (Gujarat) Ltd. (Official Liquidator) (2008) 9 SCC 299: 2008: INSC: 925 and
    Celir LLP v. Bafna Motors (Mumbai) Private Limited (2024) 2 SCC 1: 2023:

    INSC: 838). Repeated interferences in public auction also results in causing
    uncertainty and frustrates the very purpose of holding auctions. (Refer: K.
    Kumara Gupta v. Sri Markendaya and Sri Omkareswara Swamy Temple

    (2022) 5 SCC 710: 2022: INSC: 207). Unless there are some serious flaws in
    the conduct of the auction as for example perpetration of a fraud/collusion,
    grave irregularities that go to the root of such an auction, courts must
    ordinarily refrain from setting them aside keeping in mind the domino effect
    such an order would have. Given the facts noted above, we shall refrain from
    cancelling the sale or declaring the Sale Deed as vold. Instead, it is deemed
    appropriate to balance the equities by directing the Auction Purchaser to pay
    an additional amount in respect of the subject property.”

    (Emphasis supplied)

    217. In the present lis, it is not the case of the Borrower herein that the 9th
    auction conducted by the Bank was a result of any collusion or fraud either
    at the behest of the Bank or the Successful Auction Purchaser herein. Aside
    from the lack of any 15-days gap between the notice of sale and the notice of
    auction, no other illegality has been imputed to the aforesaid auction
    proceedings. It is also not the case of the Borrower that due to the absence of
    the aforesaid statutory period, any prejudice was caused or that it was
    prevented from effectively exercising its rights due to such procedural
    infirmity. Despite a total of eight auctions being conducted by the Bank from
    April, 2022 to June, 2023, not once did the Borrower express its desire to
    redeem the mortgage. Even when the auction notice came to be issued on
    12.06.2023, the Borrower never intimated that it was in process of
    redeeming the mortgage with the aid of the Subsequent Transferee and that
    the auction be delayed even though, as per the parties own submissions,
    they started exploring the possibility of redeeming the mortgage and
    thereafter transferring in June, 2023 itself. In such circumstances, given the
    fact that although the S.A. No. 46 of 2022 was still pending, yet since there
    was nothing before this Court to doubt the validity of the 9th auction, this
    Court in the Main Appeals confirmed the sale in favour of the petitioner and
    brought the auction proceedings to its logical conclusion by directing the
    38

    issuance of the sale certificate. The Borrower never raised the issue of the
    validity of the 9th auction notice despite having sufficient opportunities to do
    so even after the pronouncement of the decision in the Main Appeals, and
    that such pleas are being raised only after the auction was confirmed in
    favour of the petitioner, we find no good reason to interfere with the 9th
    auction conducted by the Bank.

    218. Any sale by auction or other public procurement methods once already
    confirmed or concluded ought not to be set aside or interfered with lightly
    except on grounds that go to the core of such sale process, such as either
    being collusive, fraudulent or vitiated by inadequate pricing or underbidding.
    Mere irregularity or deviation from a rule which does not have any
    fundamental procedural error does not take away the foundation of authority
    for such proceeding. In such cases, courts in particular should be mindful to
    refrain entertaining any ground for challenging an auction which either could
    have been taken earlier before the sale was conducted and confirmed or
    where no substantial injury has been caused on account of such irregularity.

    219. In the present lis, apart from the want of statutory notice period, no
    other challenge has been laid to the 9th auction proceedings on the ground
    of it being either collusive, fraudulent or vitlated by inadequate pricing or
    underbidding, thus, the auction cannot be said to suffer from any
    fundamental procedural error, and as such does not warrant the interference
    of this Court, particularly when the plea sought to be raised to challenge the
    same could have been raised earlier.

    220. The aforesaid may be looked at from one another angle. Even if the 9th
    auction were to be held illegal and bad in law by virtue of the aforesaid S.A.
    No. 46 of 2022, it would not mean that the auction purchaser would by
    virtue of such finding lose all its rights to the secured asset, even after
    having the sale confirmed in its favour. In this regard we may refer to the
    decision of this Court in Janak Raj v. Gurdilal Singh, AIR 1967 SC 608
    wherein it was held that even if a decree pursuant to which auction was
    previously conducted was later set aside, the successful auction purchaser’s
    rights will remain unaffected and he would still be entitled to confirmation of
    sale in its favour. The relevant observations read as under:-

    “27. For the reasons already given and the decisions noticed, it must be held
    that the appellant auction purchaser was entitled to a confirmation of the
    sale notwithstanding the fact that after the holding of the sale the decree had
    been set aside. The policy of the Legislature seems to be that unless a
    39

    stranger auction-purchaser is protected against the vicissitudes of the
    fortunes of the suit, sales in execution would not attract customers and it
    would be to the detriment of the interest of the borrower and the creditor
    alike if sales were allowed to be impugned merely because the decree was
    ultimately set aside or modified. The Code of Civil Procedure of 1908 makes
    ample provision for the protection of the interest of the judgment-debtor who
    feels that the decree ought not to have been passed against him. On the facts
    of this case, it is difficult to see why the judgment-debtor did not take resort
    to the provisions of O. XXI r. 89. The decree was for a small amount and he
    could have easily deposited the decretal amount besides 5 per cent of the
    purchase money and thus have the sale set aside. For reasons which are not
    known to us he did not do so.

    (Emphasis supplied)
    E. FINALORDER

    221. Before we close this judgment, we may address yet another submission
    canvassed on behalf of the respondents herein. It was contended by the
    Borrower and the Subsequent Transferee that the petitioner herein having
    not prayed for the relief of physical possession in the original proceedings
    cannot be permitted to expand the scope of the said proceedings and now
    seek the relief which it previously did not. In this regard, we may only refer to
    the decision of this Court in Baranagore Jute Factory Plc. Mazdoor v.
    Baranagore Jute Factory Plc.
    , AIR 2017 OnLine SC 410 wherein it was held
    the court not only has a duty to issue appropriate directions for remedying or
    rectifying the things done in violation of its orders but also the power to take
    restitutive measures at any stage of the proceedings. The relevant
    observations read as under:-

    “… As held by this Court in Delhi Development Authority v. Skipper
    Construction Co. (P) Ltd.
    , and going a step further, the Court has a duty to
    issue appropriate directions for remedying or rectifying the things done in
    violation of the orders. In that regard, the Court may even take restitutive
    measures at any stage of the proceedings. […]”

    (Emphasis supplied) 222. Similarly, a Three-Judge Bench of this Court in the
    case of State Bank of India v. Dr. Vijay Mallya, 2022 SCC OnLine SC SC 826,
    in clear terms said that apart from punishing the contemnor for his
    contumacious conduct, the majesty of law may demand that appropriate
    40

    directions be issued by the Court so that any advantage secured as a result
    of such contumacious conduct is completely nullified. The approach may
    require the Court to issue directions either for reversal of the transactions in
    question by declaring said transactions to be void or passing appropriate
    directions to the concerned authorities to see that the contumacious conduct
    on the part of the contemnor does not continue to enure to the advantage of
    the contemnor or anyone claiming under him

    223. In view of the aforesaid, we pass the following orders and directions:-

    (1) The legality and validity of the 9th auction proceedings conducted
    pursuant to the notice of sale dated 12.06.2022 is upheld. The sale of the
    Secured Asset to the petitioner is hereby confirmed and the title conferred
    through the Sale Certificate dated 27.09.2023 is declared to be absolute.

    (ii) The Borrower and the Bank shall immediately take steps for the
    cancellation of the Release Deed dated 28.08.2023 within a period of one
    week from the date of pronouncement.

    (iii) The Borrower shall also unconditionally withdraw the S.A. No. 46 of 2022
    pending before the DRT within a period of one week from the date of
    pronouncement.

    (iv) The Assignment Agreement dated 28.08.2023 is hit by lis pendens and
    hereby declared void. The Subsequent Transferee shall hand over the
    peaceful physical possession of the Secured Asset along with its original title
    deeds to the Bank within a period of one week from the date of
    pronouncement of this judgment. In the event of any further hinderance or
    any obstruction that may be caused by the Borrower or the Subsequent
    Transferee while taking over the possession of the property then in such
    circumstances the Bank shall take the assistance of police.

    (v) The Subsequent Transferee shall also withdraw the police complaint dated
    17.01.2024 lodged by it within a period of one week from the date of
    pronouncement of this judgment.

    (vi) We clarify that the Subsequent Transferee is not entitled to recover the
    amount paid by it towards redeeming the second charge over the Secured
    Asset or any other dues or amount paid in respect of the same from the
    petitioner herein.

    vii) The Bank shall refund the amount of Rs. 129 crore paid by the Borrower
    towards the redemption of mortgage without any interest only after the
    aforesaid directions have been compiled to the letter and spirit.
    41

    (viii) The Subsequent Transferee is at liberty to recover the amount paid by it
    towards the Assignment Agreement dated 28.06.2023 and any other amount
    from the Borrower by availing appropriate legal remedy as may be available
    under the law.

    224. Let this matter be notified once again before this Bench after a period of
    two weeks to report compliance of the aforesaid directions.

    225. There shall be no order as to costs.”

    13. The ratio laid down by the Hon’ble Apex Court is

    directly applicable to the present lis inter alia, issuance of the

    money recovery proceedings as against Petitioner and issuance

    of notices for putting the properties of Petitioner to auction.

    Under the compulsive and adverse circumstances created at the

    instance/s of Respondents, Petitioner was left no option to give

    a letter requesting payments to be made in installments and to

    prove his bona fides had paid part of the amounts. This conduct

    of Petitioner cannot be viewed and projected by Respondents

    that Petitioner having accepted the payment of money under

    installments cannot now turn around and contest this Writ

    Petition. This argument of Respondents is to be received only to

    be rejected, as the acts of commission of the Respondents is/are

    during the continuation of the Interim Orders and thus are

    illegal.

    14. Respondents’ actions also violate Clauses 5.9.4.2

    and 5.9.4.3 of the GTCS, which mandate that upon termination

    of the HT Agreement, the licensee must issue a final statement
    42

    of account, and no further claim can be raised unless based on

    fresh cause and lawful assessment. The reopening of a

    terminated agreement, without statutory authority or notice,

    amounts to procedural impropriety and administrative

    arbitrariness.

    15. The ratio laid down in the decisions, supra,

    squarely applies to the present case and the impugned demands

    are wholly time-barred. The invocation of Section 24 of the

    repealed Indian Electricity Act, 1910, in the impugned notices is

    patently illegal, as that Act stood repealed by virtue of Section

    185 of the Electricity Act, 2003, which specifically provides that

    the earlier enactments shall stand repealed, thereby the

    impugned notices, having been issued under a repealed statute,

    are void ab initio and non est in the eye of law and as a

    consequence of the same are liable to be set aside.

    16. Upon careful consideration of the pleadings of both

    the parties, the documents placed on record and the

    submissions advanced and in view of the above discussion, this

    Court finds that the impugned proceedings of Respondents

    suffer from serious legal infirmities, arbitrariness, and violation

    of statutory provisions and principles of natural justice. The

    entire action of Respondents, commencing from the alleged

    inspection of Petitioner’s premises and culminating in the
    43

    impugned notices and recovery proceedings, is unsustainable in

    law.

    17. For all the reasons and discussions made supra,

    this Court holds that the impugned notices dated 15.12.2015,

    21.03.2016 and 02.08.2019, the consequential Memo dated

    19.03.2020, and the letter dated 18.03.2021 issued by the 5th

    Respondent to the Sub-Registrar are illegal, arbitrary, violative

    of Sections 56(2), 126, and 185 of the Electricity Act, 2003, and

    Clauses 5.9.4.2 and 5.9.4.3 of the GTCS, and contrary to the

    law laid down by the Hon’ble Supreme Court and High Courts.

    The same are accordingly set aside and quashed. Further,

    Respondents are directed to refrain from taking any coercive

    steps, including recovery proceedings under the A.P. State

    Electricity Board (Recovery of Dues) Act, 1984 or

    communication with revenue or registration authorities, in

    respect of the subject matter of this Writ Petition. It is further

    directed that any future demand or assessment, if warranted,

    shall be made strictly in accordance with the Electricity Act,

    2003, after issuance of a lawful notice and granting of an

    opportunity of hearing to Petitioner.

    18. This Court, therefore, concludes that Respondents

    have acted in excess of their jurisdiction, in violation of
    44

    statutory provisions, and in contravention of the principles of

    natural justice. The writ petition deserves to be allowed.

    19. Accordingly, the Writ Petition is allowed. The

    impugned notices dated 15.12.2015, 21.03.2016, and

    02.08.2019, Memo dated 19.03.2020, and letter dated

    18.03.2021 issued by the 5th Respondent are hereby quashed

    and set aside. All consequential proceedings initiated pursuant

    thereto, including those under the A.P. State Electricity Board

    (Recovery of Dues) Act, 1984, are declared void. It is needless to

    say that the contesting Respondents can avail the remedies

    available to them in accordance with law. No costs.

    20. Consequently, the miscellaneous Applications, if

    any shall stand closed.

    ————————————-

    NAGESH BHEEMAPAKA, J
    24th April 2026

    ksld
    45



    Source link

    LEAVE A REPLY

    Please enter your comment!
    Please enter your name here