― Advertisement ―

HomeM/S. Loesche Energy Systems India ... vs Ntpc Limited on 22 April,...

M/S. Loesche Energy Systems India … vs Ntpc Limited on 22 April, 2026

ADVERTISEMENT

Telangana High Court

M/S. Loesche Energy Systems India … vs Ntpc Limited on 22 April, 2026

Author: Nagesh Bheemapaka

Bench: Nagesh Bheemapaka

IN THE HIGH COURT OF JUDICATURE FOR THE STATE OF
                    TELANGANA
     HON'BLE SRI JUSTICE NAGESH BHEEMAPAKA

             WRIT PETITION No. 13166 OF 2024

                         22.04.2026

Between:

M/s Loesche Energy Systems India Private Limited

                                                   ..... Petitioner
And

NTPC Limited & another

                                                ..... Respondents

O R D E R:

Respondent – NTPC rejected Petitioner’s bid by way

of e-mail dated 02.05.2024 which was questioned in this Writ

SPONSORED

Petition filed seeking Certiorari on the ground that the same is

illegal, arbitrary, untenable, violative of principles of natural

justice and fundamental rights of Petitioner.

2. The facts of the case are: Respondent – NTPC

invited bids from eligible bidders for the ‘Contract for Design,

Engg, Manufacturing. Supply of New better/efficient Coal Pulv

by replacement of existing 8.5E10 Coal Pulverizers at st-1 boiler

of NRPC RDM’ vide its Invitation of Bids bearing NIT No.

9900258610 (“IFB”) with respect to the Tender bearing no.

NTPC/USSC-CPG1/9900258610 dated 21.11.2023. In terms of
2

the IFB, the scope of work shall include but not be limited to the

supply, erection, testing and inspection of equipment and

materials manufacturer’s works, packing, supply,

transportation, transit insurance, delivery to site, unloading,

storage and equipment erection including associated civil and

structural works if any. Pertinently, the site of works is situated

in Ramagundam, Telangana. The IFB mentions the term ‘NRPC

RDM in which NRPC is inadvertently misspelt instead of ‘NTPC’

and ‘RDM’ is short for ‘Ramagundam’.

2.1. As per the IFB, to be eligible for participation in the

bidding process, bidders had to meet certain Qualification

Requirements (QR) which include both Technical and Financial

Criteria which were made a mention in the writ affidavit, in

detail. Hence, the same are not reiterated.

2.2. Pursuant to the Tender, Petitioner submitted bid on

27.02.2024, enclosing all the documents, as per the IFB.

Thereafter, Respondent addressed e mail dated 03.04.2024 and

sought various documents in furtherance of Petitioner’s

technical bid. Petitioner responded vide its e mail dated

06.04.2024 and provided all necessary documents including but

not limited to the audited balance sheet of Loesche UK.,

proposed coal mill GA drawing, proof that the QCMM had

erected/supervised the erection and commissioned/supervised
3

the commissioning against the contract of M/s. Doosan Heavy

Industries & Construction Co. Ltd.

2.3. In response thereto, vide e mail dated 10.04.2024,

Respondent inter alia sought further clarifications from

Petitioner more particularly, as to how the Petitioner fulfilled the

Additional Financial Criteria under Clause 6.2.2 of the IFB and

also sought documents in support thereof. Vide its e mail dated

13.04.2024, Petitioner issued a detailed response to

Respondent, clarifying the queries apprising that it qualifies

under Clause 6.3.1 as a “licensor” of QCMM and accordingly

licensing agreement dated 31.03.2015 was submitted. Since

Clause 6.2.2.1 only refers to “collaborator” or “associate” and

does not prescribe any additional financial criteria for a

“licensor”, the additional financial criteria are not required to be

fulfilled by Petitioner. It was also informed that Petitioner by

itself qualifies the financial criteria under the tender with an

average annual turnover of INR 74.51 crores and a net worth of

452.19% in the preceding financial year.

2.4. Despite these clarifications, Respondent issued

another e mail dated 16.04.2024 on similar lines and once

again sought supporting documents from Petitioner regarding

the fulfilment of additional financial criteria by the OCMM of the

Petitioner. It is pertinent to mention here that whenever
4

Petitioner asked for clarifications from Respondent, its response

was also mechanical thereby not providing necessary inputs

regarding the bid. Petitioner immediately responded to the

Respondent’s e mail dated 16.04.2024 vide its e mail dated

19.04.2024 and once again, clarified the position that Clause

6.2.2 specifies the additional qualifications only for a

collaborator and associate and not for a licensor. In any case,

any associate or collaborator is actively involved in the project

bid whereas a licensor under a licensing agreement merely

provides a license to the licensee for consideration and is not

involved in the project actively when compared to an associate

or collaborator. Thus, vide the said e mail, this was also brought

to the attention of the Respondent.

2.5. However, without even considering the same, vide

e mail dated 02.05.2024, impugned in the Writ Petition,

Respondent has arbitrarily and unreasonably rejected the

Petitioner’s bid by merely stating the reason of “Not meeting

QR”. Due to paucity of time, considering the financial bids were

due to be opened on 03.05.2024, the Petitioner attempted to

reach out to the Respondent but there was no response. Hence,

the Writ Petition.

2.6. It is finally, stated that this Court has jurisdiction

to entertain the present Writ Petition as the cause of action in
5

respect of the IFB (Invitation for Bids) arises within the

territorial jurisdiction of this Court more so, in view of the fact

that the site of works in terms of the IFB is Ramagundam,

Telangana as indicated in the IFB as ‘NPPC RDM’ wherein RDM

stands for Ramagundam and therefore the part cause of action

is arising with in territorial jurisdiction of this Hon’ble Court.

3. In the counter filed on behalf of NTPC, it is stated,

NTPC Limited being the Central Public Sector Undertaking, the

entire bid processing is being made through the transparent

“Government e Procurement System managed by National

Informatics Centre” (hereinafter referred as “GePNIC” portal-

online system of Government E-tendering website). The tender

has been processed strictly as per the “Procurement and Work

Policy of NTPC Ltd.”. The various allegations raised by the

Petitioner is therefore, misconceived and are an afterthought

and therefore denied.

3.1. It is stated further, NTPC had floated the subject

tender and the same was called on “OPEN TENDER” by the

Central Procurement Group (CPG) of the answering Respondent

Corporation and the bidding was done “ONLINE”, at GePNIC

portal through the well detailed and established procedures

which the petitioner is well aware of it. It is submitted that since

it was an Open Tender, any agency who possess /meets
6

required Qualifying Requirements (QR) was eligible to

participate in the Bidding Process.

3.2. It is stated, petitioner’s collaborator M/s Loesche

Energy Systems Limited, United Kingdom having Negative

financial Networth, does not fulfil the individual tender financial

Networth criteria. Accordingly, Petitioner Bidder was declared to

be not meeting the Financial Qualifying requirements. During

clarification stage before tender opening, bidder’s queries with

respect to the tender requirements were replied. Accordingly,

bidder had submitted the bid. Hence it is evident that full

opportunity was afforded to the Petitioner to represent his Case.

As per Clause 4.2 of the Invitation to Bid (ITB), submission of a

bid not substantially responsive to the bidding documents in

every respect will be at the Bidder’s risk and may result in

rejection of its bid. Further as per Clause 22.3 of ITB, “An

affirmative determination of meeting the qualifying requirements

will be a prerequisite for further evaluation of Techno-

Commercial bid and holding clarification meeting, if any, with

the Bidder. A negative determination will result in rejection of

the Bidder’s Techno-Commercial Bid in which event EMPLOYER

will not open the Price Bid of the concerned bidder and his bid

security shall be returned.” Further as per clause 28.0 of ITB,

specifies the “Employer’s Right to Accept Any Bid and to Reject
7

Any or All Bids”, as Employer reserves the right to accept or

reject any bid, and to annul the bidding process and reject all

bids at any time prior to award of contract, without thereby

incurring any liability to the affected Bidder or bidders or any

obligation to inform the affected Bidder or bidders of the

grounds for Employer’s action. There is no gainsaying that

Petitioner has unequivocally accepted the terms and condition

of ITB. From the above clauses of ITB, it is clear that, it is not

obligatory on the part of the Answering Respondent to provide

any ground of rejection of the Bid. However, as petitioner failed

to meet the QR an auto-generated communication regarding his

non-qualifying for Tender was received by the petitioner.

However, the petitioner, who (also by virtue of his Deed of Joint

Undertaking), is fully aware that his Collaborator fails to meet

Financial Capability related Qualifying Criteria cannot take a

different stand in the matter.

3.3. It is stated, petitioner has not approached this

Court with clean hands. In similar circumstances, when Writ

Petition No. 16442 of 2023 was filed against the NTPC, this

Court dismissed the same vide order dated 03.10.2023 and the

said order applies to this case. At para 18 and 19, it has been

observed thus:

8

” The Apex Court in Jagdish Mandal v State of Orissa and
others
reported in 2007 (14) SCC page 517 at para 22 observed as
under:

” 22…. Attempts by unsuccessful tenderers with imaginary
grievances, wounded pride and business rivalry, to make mountains out
of molehills of some technical/procedural violation or some prejudice to
self, and persuade courts to interfere by exercising power of judicial
review, should be resisted. Such interferences, either interim or final,
may hold up public works for years, or delay relief and succour to
thousands and millions and may increase the project cost manifold.
Therefore, a court before interfering in tender or contractual matters in
exercise of power of judicial review, should pose to itself the following
questions:

i) Whether the process adopted or decision made by the authority is
mala fide or intended to favour someone.

OR
Whether the process adopted or decision made is so arbitrary and
irrational that the court can say: ‘the decision is such that no
responsible authority acting reasonably and in accordance with relevant
law could have reached.;

ii) Whether public interest is affected.

If the answers are in the negative, there should be no interference under
Article 226″.

19. Taking into consideration, the aforesaid facts and
circumstances and duly considering the averments made by the
respondent Nos. 1 to 3 in their counter affidavit in particular, paras 13,
14 15 and 16 and taking into consideration the law laid down by the
Apex Court in the judgments relied upon by the learned counsel for the
respondents (referred to above) and duly taking into consideration, the
law laid down by the Apex Court reported in 2020 (10) SCC page 766 in
Shanthi Devi alias Shanthi Mishra v Union of India and others (referred
to above
) and the view taken by the Apex Court in the judgment dated
12.04.1996 in State of U.P. and others v Harish Chandra and others
reported in 1996(9) SCC 309 (referred to and extracted above) and
applying the view taken by the Apex Court in Jagdish Mandal v State of
Orissa and others
reported in 2007 (14) SCC page 517 (referred to and
extracted above) and posing the said questions, as indicated in the said
judgment
to this Court itself, this Court opines that the answers are in
9

the negative, therefore, the present writ petition is dismissed since the
same is devoid of merits”.

The Hon’ble Apex Court in number of cases upheld

the said legal proposition and it has now become a well-

established law governing Judicial interference in Tendering

process that the Court should not ordinarily interfere in matters

relating to tender or contract. Hence, the Writ Petition be

dismissed on the basis of the above.

3.4. It is also stated, since the entire tendering process

is being done at Raipur, Chhattisgarh, on line mode, no cause of

action has arisen within the territorial Jurisdiction of this

Court. Further as per Deed of Joint Undertaking executed by

Petitioner, the Courts of Raipur shall have exclusive

jurisdiction. As per Clause 2.2 of the Special Condition of

Contract also Court of Competent Jurisdiction at Raipur is

having exclusive jurisdiction.

3.5. This Court vide order dated 03.05.2024 issued

directions as extracted under:

“The issue, whether the petitioner has fulfilled all the
conditions of the tender notification dated 21.11.2023 issued by the
respondent and is eligible for financial bid, is required to be adjudicated
after filing of the counter affidavit by the respondent. In the meanwhile,
any further action taken by the respondent in pursuance of the tender
notification dated 21.11.2023 shall be subject to further orders of this
Court.”

10

It is stated, in compliance with the said order, PO

No. 5500044674 dated 29.05.2024 was placed upon L1 Bidder

M/s. Schenck Process Solutions India Pvt Ltd, Bangalore, with

the stipulation that the Award of PO shall be subjected to the

further/final Order (s) of this Court. Accordingly, no claim on

account of any reason / ground whatsoever shall be admissible

against NTPC for any rescinding/modification of the Contract

/PO, made in compliance to the Final Judgment in this regard

and any decision of EIC in this regard shall be final and binding

on the parties. It is also stated, bidding conditions has the pre-

requisite of entering DJU with the Collaborator. Further,

Collaborator should invariably be a Holding Company of the

bidder as well as should simultaneously comply with the

requirement of being a ‘Qualified Coal Mill Manufacturer’ which

has been specified under tender technical Qualifying

Requirement at Clause 6.1.1. Thus, the bidder’s contention to

set aside the applicability of additional financial Qualification

Requirements for licensor, in spite of submitting the DJU on

non-judicial stamp paper so as to fulfill the Technical

Qualification Requirements is devoid of merit.

3.6. It is stated, bid of Petitioner was not rejected

unreasonably. Rather the compliance of tender technical

Qualifying Requirements, submission of DJU to fulfil technical
11

Qualification Requirements based on the Collaborator,

compliance of financial requirements for bidder and the

compliance of additional financial Requirements for Collaborator

with whom bidder/petitioner has executed the DJU as the

Executant Partner was evaluated in the tender. Accordingly, bid

of petitioner was rejected and a system generated e mail dated

02.05.2024 was sent to petitioner for rejection of bid.

4. In the counter filed on behalf of Respondent No.2, it

is stated, on 03.06.2024, they received information from the

on line portal of Respondent No. 1 that it was the L1 bidder for

the subject Tender and it was awarded the Tender vide

Purchase Order dated 29.05.2024, after having met all the

specifications under the QR as per the instructions under the

Tender. They met the QR under Invitation for Bid (“IFB”), also

qualified the financial criteria under Clause 6.2, furnished

performance securities for ten per cent (10%) of the total

contract price in compliance with Clause 31 of the Instructions

to Bidders (“ITB”).

4.1. It is also stated that the present matter pertains to

the award of tender by a Public Sector Undertaking. It is a

settled position of law upheld by the Hon’ble Apex Court in a

catena of judgments that there are inherent limitations in

exercise of the power of judicial review in matters pertaining to
12

tenders and contractual powers of Government bodies. It is

stated, the right to choose cannot be considered to be an

arbitrary power. In the present case, Petitioner did not meet the

qualification requirements under the IFB, as such, Respondent

No. 1 rightly rejected the bid of Petitioner. This respondent

draws attention to Clause 28 of the ITB stipulates as follows:

” Employer’s Right to Accept Any Bid and to Reject Any
or All Bids:

Employer reserves the right to accept or reject any bid, and to and
the bidding process and reject all bids at any time prior to award of
contract, without thereby incurring any liability to the affected Bidder or
bidders or any obligation to inform the affected Bidder or bidders of the
grounds for Employer’s action”.

Clause 28 clearly states that Respondent No. 1

reserves the right to accept or reject any bid, and to annul the

bidding process and reject all bids at any time prior to the

award of the contract, without incurring any liability to the

affected bidder or bidders or any obligation to inform the

affected bidder or bidders of the grounds for employer’s action.

4.2. It is stated, petitioner alleges to have qualified

under the technical criteria via Route 3 under Clause 6.1.3 of

the IFB viz. Subsidiary of a Qualified Coal Mill Manufacturer.

Petitioner also alleges to have filed a Deed of Joint Undertaking

with the Qualified Coal Mill Manufacturer. Here, it is to be seen,
13

as per Clause 6.2 of the IFB, there were Additional Financial

Requirements to be met by the Collaborator of Petitioner. As is

clear from the counter filed by Respondent No.1, Petitioner did

not meet the Additional Financial Requirements stipulated

under Clause 6.2 of the IFB. In fact, as per the counter of

Respondent No. 1, the net worth of the Collaborator of Petitioner

is on the negative side. Since Petitioner did not meet the QR laid

down under the IFB, Respondent No.1 rightly rejected the bid of

Petitioner. Petitioner cannot, at this point of time, take a stand

that it could change its Collaborator and enter into a fresh Deed

of Joint Undertaking to meet the aforementioned financial

requirements.

4.3. It is stated, the Hon’ble Supreme Court had

unequivocally held in a catena of decisions that it is not for the

Court to determine whether a particular policy or particular

decision taken in the fulfilment of that policy is fair. The Court

is only concerned with the manner in which those decisions

have been taken. The Court does not sit as a court of Appeal but

merely reviews the manner in which the decision was made. The

action of Respondent No.1 cannot be regarded as arbitrary

action as there was proper reasonable criteria by which

petitioner’s qualification was rejected. The terms of the
14

invitation to tender cannot be open to judicial scrutiny because

the invitation to tender is in the realm of contract.

4.4. It is further stated, this Court under Article 226 of

the Constitution would not be justified in interfering with

commercial transactions in which the State is one of the parties

except where there is substantial public interest involved and in

cases where the transaction is mala fide. The scope of judicial

review in matters pertaining to tenders and contracts by Public

Sector Undertakings is limited to cases where it is clearly

established that there was a mala fide action on the part of the

Respondent or there is substantial public interest involved. It is

respectfully submitted by the Answering Respondent that the

present case does not qualify both the parameters and s such,

the present Petition is liable to be dismissed.

5. Petitioner filed rejoinder denying the averments of

the counter and reiterating the averments of the writ petition. It

is well-settled that constitutional courts can interfere in the

decision making process of the tender authority when the

decision is arbitrary and irrational. Reliance is placed on the

judgments in Jagdish Mandal v. State of Orissa 1, Monarch

Infrastructure (P) Ltd. v. Ulhasnagar Municipal Corpn. 2. It is

1
(2007) 14 SCC 517
2
(2000) 5 SCC 287
15

also stated, the order dated 03.10.2023 in Writ Petition No.

16442 of 2023 relied on by Respondent No.1 is in fact, in favour

of Petitioner. Although the facts in the said case are different to

the facts in the present case, the Court in the said case did

interpret the bid conditions and came to the conclusion that

petitioner therein did not fulfil the qualification requirements.

However, in the present case, Petitioner fulfilled all the

Qualifying Requirements stipulated in the IFB.

6. Sri P. Venugopal, learned Senior Counsel assisted

by Sri M. Abhinay Reddy, learned counsel for petitioner

contends that the action of Respondent No.1 in rejecting

petitioner’ bid for non-compliance with clause 6.2.2. is

arbitrary, irrational and contrary to the tender conditions. He

further argues that the entire tendering process is being done at

Raipur, Chattisgarh, on line mode, however, relying on the

judgment in Shanti Devi v. UOI 3, contends that irrespective of

the fact that seat of the authority concerned is outside the

territorial jurisdiction of the High Court, even if a small fraction

of cause of action arises within its jurisdiction, it has

jurisdiction. In that regard, reliance is also placed on the

3
(2020) 10 SCC 766
16

judgment in Gupta Freight Carrier v. Executive Director 4

and MRT Signals Ltd. V. UOI 5.

6.1. Another argument put forward by learned counsel

is that reserving rights clause in tender does not absolve the

authority from furnishing valid reasons. Based on the judgment

of the Hon’ble Delhi High Court in PKF Sridhar and

Santhanam v. Airports Economic Regulatory Authority of

India 6, learned counsel submits that such clauses do not mean

that the authority should not have valid reasons to justify its

conduct.

7. On the other hand, learned counsel for Respondent

No.1 Sri Ch. Sidharth Sharma primarily takes objection on the

maintainability of the Writ Petition as the writ of certiorari is not

maintainable against the NTPC order. He places reliance on the

judgment of the Hon’ble Apex Court in Central Council for

Research in Ayurvedic Studies v. Bikartan Das 7, Radhey

Shyam v. Chhabi Nath 8. Secondly, it is argued, this Court

does not possess the territorial jurisdiction to adjudicate the

present dispute. Reliance is placed on the judgment of the

Hon’ble Supreme Court in State of Rajasthan v. M/s Swaika

4
2022 SCC On line Bom 706
5
2024 SCC On line Cal 5593
6
2022 SC On line Del 122
7
2023 SCC On line SC 996
8
(2015) 5 SCC 423
17

Properties 9. Thirdly, learned counsel, on the scope of judicial

review in matters pertaining to tender, argued that the scope is

limited and the terms of the invitation for bids cannot be open

to judicial scrutiny and interpretation and understanding of the

tender conditions given by the Employer should be second-

guessed by courts under judicial review. Learned counsel tries

to take cue from the judgments of the Hon’ble Apex Court in

Silppi Constructions Contractors v. Union of India10,

Jagdish Mandal’s case (supra), JSW Infrastructure Ltd. v.

Kakinada Sea Port 11, and Galaxy Transport Agency v. New

J.K. Roadways 12.

8. Heard M/s King Stubb & Kasiva, learned counsel for

Respondent No.2.

9. Upon consideration of the pleadings, material on

record and the submissions, this Court finds that the primary

relief sought is issuance of a Writ of Certiorari to quash the

rejection email dated 02.05.2024 issued by Respondent No.1 in

the course of a tender process. Whereas the contention of

respondent No.1 is writ of certiorari is not maintainable.

9
(1985) 3 SCC 217
10
(2020) 16 SCC 489
11
(2017) 4 SCC 170
12
(2021) 16 SCC 808
18

10. It is settled position of law that a writ of certiorari is

issued to quash decisions of judicial or quasi-judicial authorities

where such authorities act without jurisdiction, exceed

jurisdiction, commit an error apparent on the face of the record,

or violate principles of natural justice. The scope of certiorari

does not ordinarily extend to purely administrative or

contractual decisions unless such decisions are shown to be

vitiated by arbitrariness, mala fides, or violation of statutory

provisions.

11. In Central Council for Research in Ayurvedic

Studies v. Bikartan Das (supra), the Hon’ble Supreme Court

held as under:

” 53. This Court explained that a court which has jurisdiction
over a subject-matter has jurisdiction to decide wrong as well as right,
and when the legislature does not choose to confer a right of appeal
against that decision, it would be defeating its purpose and policy if a
superior court were to rehear the case on the evidence and substitute its
own finding in certiorari.

54. In Yakoob v. K.S. Radhakrishnan [Yakoob v. K.S.
Radhakrishnan, 1963 SCC OnLine SC 24 : AIR 1964 SC 477] , P.B.
Gajendragadkar, C.J., speaking for the Constitution Bench, placed the
matter beyond any position of doubt by holding that a writ of certiorari
can be issued for correcting errors of jurisdiction committed by inferior
courts or tribunals. The observations of this Court in para 7 are worth
taking note of : (SCC OnLine SC para 7)
“7. The question about the limits of the
jurisdiction of High Courts in issuing a writ of certiorari
under Article 226 has been frequently considered by this
Court and the true legal position in that behalf is no longer in
doubt. A writ of certiorari can be issued for correcting errors
19

of jurisdiction committed by inferior courts or tribunals :

these are cases where orders are passed by inferior courts or
tribunals without jurisdiction, or is in excess of it, or as a
result of failure to exercise jurisdiction. A writ can similarly
be issued where in exercise of jurisdiction conferred on it, the
Court or Tribunal acts illegally or improperly, as for instance,
it decides a question without giving an opportunity to be
heard to the party affected by the order, or where the
procedure adopted in dealing with the dispute is opposed to
principles of natural justice. There is, however, no doubt that
the jurisdiction to issue a writ of certiorari is a supervisory
jurisdiction and the Court exercising it is not entitled to act
as an appellate court. This limitation necessarily means that
findings of fact reached by the inferior court or Tribunal as a
result of the appreciation of evidence cannot be reopened or
questioned in writ proceedings. An error of law which is
apparent on the face of the record can be corrected by a writ,
but not an error of fact, however grave it may appear to be. In
regard to a finding of fact recorded by the Tribunal, a writ of
certiorari can be issued if it is shown that in recording the
said finding, the Tribunal had erroneously refused to admit
admissible and material evidence, or had erroneously
admitted inadmissible evidence which has influenced the
impugned finding. Similarly, if a finding of fact is based on no
evidence, that would be regarded as an error of law which can
be corrected by a writ of certiorari. In dealing with this
category of cases, however, we must always bear in mind that
a finding of fact recorded by the Tribunal cannot be
challenged in proceedings for a writ of certiorari on the
ground that the relevant and material evidence adduced
before the Tribunal was insufficient or inadequate to sustain
the impugned finding. The adequacy or sufficiency of evidence
led on a point and the inference of fact to be drawn from the
said finding are within the exclusive jurisdiction of the
Tribunal, and the said points cannot be agitated before a writ
court. It is within these limits that the jurisdiction conferred
on the High Courts under Article 226 to issue a writ of
certiorari can be legitimately exercised….”

12. From the above, it is to be understood, while

exercising extraordinary jurisdiction under Article 226 of the

Constitution, more particularly when it comes to the issue of a

writ of certiorari, the High Court does not exercise the powers of

Appellate Tribunal and it does not review or reweigh the

evidence upon which the determination of the inferior tribunal
20

purports to be based and the writ of Certiorari can be issued if

an error of law is apparent on the face of the record and it being

a high prerogative writ, should not be issued on mere asking.

Further, the Writ of Certiorari is issued for correcting errors of

jurisdiction, as and when an inferior court or tribunal acts

without jurisdiction or in excess of it, or fails to exercise it.

13. Further, the Hon’ble Supreme Court in Silppi

Constructions Contractors v. Union of India laid down the

law that calling for a tender is purely an administrative decision

and it need not contain any reasons and that it is neither a

judicial nor a quasi-judicial order. Learned counsel for

petitioner in his Note, relied on the aforementioned judgment in

Silppi Constructions Contractors’ case (supra) wherein the

Hon’ble Supreme Court held at Para 19 that the Court being the

guardian of fundamental rights is duty bound to interfere when

there is arbitrariness, irrationality, mala fides and bias.

However, the Counsel for the Petitioner is only relying on the

judgment in part and the entire para 19 wherein the Hon’ble

Apex Court clearly held that Government Contracts must not be

easily interfered with is extracted herein below:

“This Court being the guardian of fundamental rights is
duty bound to interfere when there is arbitrariness, irrationality, mala
fides and bias. However, this Court in all the aforesaid decisions has
cautioned time and again that courts should exercise a lot of restraint
21

while exercising their powers of judicial review in contractual or
commercial matters. This Court is normally loathe to interfere in
contractual matters unless a clearcut case of arbitrariness or mala fides
or bias or irrationality is made out. One must remember that today
many public sector undertakings compete with the private industry. The
contracts entered into between private parties are not subject to
scrutiny under writ jurisdiction. No doubt, the bodies which are State
within the meaning of Article 12 of the Constitution are bound to act
fairly and are amenable to the writ jurisdiction of superior courts but
this discretionary power must be exercised with a great deal of restraint
and caution. The Courts must realise their limitations and the havoc
which needless interference in commercial matters can cause. In
contracts involving technical issues the courts should be even more
reluctant because most of us in judges’ robes do not have the necessary
expertise to adjudicate upon technical issues beyond our domain. As
laid down in the judgments cited above the courts should not use a
magnifying glass while scanning the tenders and make every small
mistake appear like a big blunder. In fact, the courts must give “fair play
in the joints” to the government and public sector undertakings.”

14. In the present case, the impugned action arises out

of a tender process initiated by Respondent No.1 – NTPC Limited,

a Public Sector Undertaking, under NIT No. NTPC/USSC-

CGP1/9900258610 dated 21.11.2023. The process of evaluation

of bids, determination of technical and financial eligibility, and

rejection of non-responsive bids is essentially a contractual and

administrative function carried out in terms of the Invitation for

Bids and Instructions to Bidders. The rejection e mail dated

02.05.2024, which is sought to be quashed, is not an

adjudicatory order passed by a judicial or quasi-judicial
22

authority after hearing parties, but is an outcome of evaluation

of bids in a commercial tender process governed by contractual

terms such as Clause 6.1, Clause 6.2.2, Clause 28 of the ITB

and other provisions of the bidding documents. The said action

does not involve determination of rights in a lis between parties

in a judicial manner, but is a decision taken by the tendering

authority in exercise of its contractual discretion. In the light of

the same, as rightly contended by learned Counsel for

Respondent No.1, writ of certiorari cannot be entertained against

the impugned order.

15. Secondly, the question is whether the High Court

possesses territorial jurisdiction to adjudicate the present

dispute. Admittedly, The Tender was floated at Raipur in the

State of Chattisgarh; petitioner is a resident of Chennai, Tamil

Nadu; they submitted Tender, in respect of a work at

Ramagundam in the State of Telangana, hence, they cannot file

this Writ before Telangana High Court in as much as, no “fact”

has yet arisen in Telangana to give rise to cause of action in

Telangana. The Hon’ble Supreme Court in M/s Swaika

Properties (supra) has categorically held that once the Hon’ble

High Court lacks territorial jurisdiction, the High Court cannot

entertain the Writ Petition. In the said Judgment, the property
23

which was the subject matter of litigation was situated in

Rajasthan. Merely because a Notice of acquisition of the said

property was served at Kolkata, it was held, that per se does not

enable the Kolkata High Court to assume jurisdiction and

entertain the Writ Petition. In this case also, no fact per-se has

arisen in the State of Telangana so that Petitioner can seek the

indulgence of this Court to entertain the Writ Petition.

16. Though learned counsel for petitioner sought to

place reliance on the judgment of this Court in Writ Petition No.

16442 of 2023, the ratio laid down therein is inapplicable

inasmuch as petitioner therein who participated in the tender

floated by NTPC is an entity based in State of Telangana itself,

whereas petitioner herein is a Chennai-based entity. Further,

learned counsel for Respondent No.1 filed a memo enclosing

thereto the Special Conditions of the Contract, Condition No.

2.2 of which stipulates that ‘the contract shall be governed by

and interpreted in accordance with the Laws in force in India.

The Courts at Raipur shall have exclusive jurisdiction in all

matters arising under the contract. Also, Clause 9 in Deed of

Joint Undertaking says that any dispute that may arise in

connection with the Deed of Joint Undertaking shall be settled

as per arbitration procedure / rules mentioned in the contract

documents. This Deed shall be construed and interpreted in
24

accordance with the Laws of India and the Courts of Raipur

shall have exclusive jurisdiction. This clause again reiterates

that the Courts at Raipur shall have exclusive jurisdiction in the

mater. In that view of the matter, it is to be concluded that this

Court lacks territorial jurisdiction to entertain the Writ Petition.

17. Thirdly, it is to be seen, the scope of judicial review

in matters pertaining to tender is limited and the terms of the

invitation for bids cannot be open to judicial scrutiny and

interpretation and understanding of the tender documents given

by the employer should be second-guessed by courts under

judicial review. In Jagdish Mandal‘s case, the Hon’ble Apex

Court held that a Court before interfering in tender or

contractual maters in exercise of power of judicial review,

should pose to itself the following questions:

(i) Whether the process adopted or the decision taken by the authority is
mala fide or intended to favour some one;

Or
Whether the process adopted or decision made is so arbitrary and irrational
that the Court can say: “the decision is such that no responsible authority
acting reasonably and in accordance with relevant law could have reached”.

(ii) Whether public interest is affected?

18. It has been held by the Hon’ble Supreme Court in

JSW Infrastructure Ltd. and New J.K. Roadways (supra) that

interest of the person who issued the tender has to be protected

and nothing beyond. In matters of contract, the Courts must
25

also not interfere where such interference will cause

unnecessary loss to the public exchequer. No doubt, the tender

in question arises out of contractual domain involving

commercial decision of a Public Sector Undertaking. The scope

of judicial review in such matters is limited to examining the

decision-making process and not the merits of the decision. The

law laid down in Jagdish Mandal‘s case clearly holds that

interference is warranted only when the decision is mala fide,

arbitrary to the extent that no reasonable authority

would have taken such decision, or where public interest is

affected. Even in TATA Cellular v. Union of India 13, the

Hon’ble Supreme Court have laid down the parameters of

interpretation and the one stated by petitioner does not fit in

those parameters.

19. In the present case, petitioner, admittedly,

participated under Route-3 under Clause 6.1.3 and submitted

Deed of Joint Undertaking dated 24.11.2023. The DJU, which

forms part of the tender documents, specifically treats the

associated entity as Collaborator and binds both the parties

jointly and severally. Respondent No. 1 has evaluated the bid on

the basis of the DJU submitted by petitioner. The contention of

Petitioner that its QCMM is a ‘licensor’ and not a ‘collaborator’

13
(1994) 6 SCC 651
26

cannot be accepted in view of the fact that Petitioner has itself

executed DJU in prescribed format and relied upon such

document for qualification. The attempt to re-characterize the

relationship after submission of bid is clearly untenable and

amounts to altering the basis of qualification after participation.

20. Further, Clauses 6.2.2.1 and 6.2.2.2 clearly

stipulate Additional Financial Criteria for Collaborator/Associate

for bidders under Clause 6.1.3. Once Petitioner has submitted

DJU and projected its QCMM as Collaborator for the purpose of

qualification, compliance with Clause 6.2.2 becomes mandatory.

The material on record establishes that Collaborator’s net worth

is negative and does not meet the requirement of not less than

100% or even 75% of paid-up share capital. The plea of

Petitioner that it independently satisfies financial criteria is also

of no assistance, as the tender conditions specifically require

compliance with criteria applicable to Route-3 including

collaborator requirements. The terms of the tender cannot be

rewritten by the Court.

21. It is also relevant to note that contract has already

been awarded to Respondent No.2 vide Purchase Order dated

29.05.2024 and Contract Agreement dated 11.07.2024, and

substantial steps have been taken including furnishing of bank
27

guarantees. Interference, at this stage, would cause prejudice,

delay in execution of a project of national importance and

adversely affect public interest. In view of the above, this Court

is of the considered opinion that petitioner failed to establish any

arbitrariness, mala fide or illegality in the decision-making

process of Respondent No.1.

22. Accordingly, the Writ Petition is dismissed. No costs.

23. Consequently, the miscellaneous Applications, if

any shall stand closed.

——– —————————–

NAGESH BHEEMAPAKA, J

22nd April 2026

ksld



Source link