M/S. Loesche Energy Systems India … vs Ntpc Limited on 22 April, 2026

    0
    41
    ADVERTISEMENT

    Telangana High Court

    M/S. Loesche Energy Systems India … vs Ntpc Limited on 22 April, 2026

    Author: Nagesh Bheemapaka

    Bench: Nagesh Bheemapaka

    IN THE HIGH COURT OF JUDICATURE FOR THE STATE OF
                        TELANGANA
         HON'BLE SRI JUSTICE NAGESH BHEEMAPAKA
    
                 WRIT PETITION No. 13166 OF 2024
    
                             22.04.2026
    
    Between:
    
    M/s Loesche Energy Systems India Private Limited
    
                                                       ..... Petitioner
    And
    
    NTPC Limited & another
    
                                                    ..... Respondents
    
    O R D E R:

    Respondent – NTPC rejected Petitioner’s bid by way

    of e-mail dated 02.05.2024 which was questioned in this Writ

    SPONSORED

    Petition filed seeking Certiorari on the ground that the same is

    illegal, arbitrary, untenable, violative of principles of natural

    justice and fundamental rights of Petitioner.

    2. The facts of the case are: Respondent – NTPC

    invited bids from eligible bidders for the ‘Contract for Design,

    Engg, Manufacturing. Supply of New better/efficient Coal Pulv

    by replacement of existing 8.5E10 Coal Pulverizers at st-1 boiler

    of NRPC RDM’ vide its Invitation of Bids bearing NIT No.

    9900258610 (“IFB”) with respect to the Tender bearing no.

    NTPC/USSC-CPG1/9900258610 dated 21.11.2023. In terms of
    2

    the IFB, the scope of work shall include but not be limited to the

    supply, erection, testing and inspection of equipment and

    materials manufacturer’s works, packing, supply,

    transportation, transit insurance, delivery to site, unloading,

    storage and equipment erection including associated civil and

    structural works if any. Pertinently, the site of works is situated

    in Ramagundam, Telangana. The IFB mentions the term ‘NRPC

    RDM in which NRPC is inadvertently misspelt instead of ‘NTPC’

    and ‘RDM’ is short for ‘Ramagundam’.

    2.1. As per the IFB, to be eligible for participation in the

    bidding process, bidders had to meet certain Qualification

    Requirements (QR) which include both Technical and Financial

    Criteria which were made a mention in the writ affidavit, in

    detail. Hence, the same are not reiterated.

    2.2. Pursuant to the Tender, Petitioner submitted bid on

    27.02.2024, enclosing all the documents, as per the IFB.

    Thereafter, Respondent addressed e mail dated 03.04.2024 and

    sought various documents in furtherance of Petitioner’s

    technical bid. Petitioner responded vide its e mail dated

    06.04.2024 and provided all necessary documents including but

    not limited to the audited balance sheet of Loesche UK.,

    proposed coal mill GA drawing, proof that the QCMM had

    erected/supervised the erection and commissioned/supervised
    3

    the commissioning against the contract of M/s. Doosan Heavy

    Industries & Construction Co. Ltd.

    2.3. In response thereto, vide e mail dated 10.04.2024,

    Respondent inter alia sought further clarifications from

    Petitioner more particularly, as to how the Petitioner fulfilled the

    Additional Financial Criteria under Clause 6.2.2 of the IFB and

    also sought documents in support thereof. Vide its e mail dated

    13.04.2024, Petitioner issued a detailed response to

    Respondent, clarifying the queries apprising that it qualifies

    under Clause 6.3.1 as a “licensor” of QCMM and accordingly

    licensing agreement dated 31.03.2015 was submitted. Since

    Clause 6.2.2.1 only refers to “collaborator” or “associate” and

    does not prescribe any additional financial criteria for a

    “licensor”, the additional financial criteria are not required to be

    fulfilled by Petitioner. It was also informed that Petitioner by

    itself qualifies the financial criteria under the tender with an

    average annual turnover of INR 74.51 crores and a net worth of

    452.19% in the preceding financial year.

    2.4. Despite these clarifications, Respondent issued

    another e mail dated 16.04.2024 on similar lines and once

    again sought supporting documents from Petitioner regarding

    the fulfilment of additional financial criteria by the OCMM of the

    Petitioner. It is pertinent to mention here that whenever
    4

    Petitioner asked for clarifications from Respondent, its response

    was also mechanical thereby not providing necessary inputs

    regarding the bid. Petitioner immediately responded to the

    Respondent’s e mail dated 16.04.2024 vide its e mail dated

    19.04.2024 and once again, clarified the position that Clause

    6.2.2 specifies the additional qualifications only for a

    collaborator and associate and not for a licensor. In any case,

    any associate or collaborator is actively involved in the project

    bid whereas a licensor under a licensing agreement merely

    provides a license to the licensee for consideration and is not

    involved in the project actively when compared to an associate

    or collaborator. Thus, vide the said e mail, this was also brought

    to the attention of the Respondent.

    2.5. However, without even considering the same, vide

    e mail dated 02.05.2024, impugned in the Writ Petition,

    Respondent has arbitrarily and unreasonably rejected the

    Petitioner’s bid by merely stating the reason of “Not meeting

    QR”. Due to paucity of time, considering the financial bids were

    due to be opened on 03.05.2024, the Petitioner attempted to

    reach out to the Respondent but there was no response. Hence,

    the Writ Petition.

    2.6. It is finally, stated that this Court has jurisdiction

    to entertain the present Writ Petition as the cause of action in
    5

    respect of the IFB (Invitation for Bids) arises within the

    territorial jurisdiction of this Court more so, in view of the fact

    that the site of works in terms of the IFB is Ramagundam,

    Telangana as indicated in the IFB as ‘NPPC RDM’ wherein RDM

    stands for Ramagundam and therefore the part cause of action

    is arising with in territorial jurisdiction of this Hon’ble Court.

    3. In the counter filed on behalf of NTPC, it is stated,

    NTPC Limited being the Central Public Sector Undertaking, the

    entire bid processing is being made through the transparent

    “Government e Procurement System managed by National

    Informatics Centre” (hereinafter referred as “GePNIC” portal-

    online system of Government E-tendering website). The tender

    has been processed strictly as per the “Procurement and Work

    Policy of NTPC Ltd.”. The various allegations raised by the

    Petitioner is therefore, misconceived and are an afterthought

    and therefore denied.

    3.1. It is stated further, NTPC had floated the subject

    tender and the same was called on “OPEN TENDER” by the

    Central Procurement Group (CPG) of the answering Respondent

    Corporation and the bidding was done “ONLINE”, at GePNIC

    portal through the well detailed and established procedures

    which the petitioner is well aware of it. It is submitted that since

    it was an Open Tender, any agency who possess /meets
    6

    required Qualifying Requirements (QR) was eligible to

    participate in the Bidding Process.

    3.2. It is stated, petitioner’s collaborator M/s Loesche

    Energy Systems Limited, United Kingdom having Negative

    financial Networth, does not fulfil the individual tender financial

    Networth criteria. Accordingly, Petitioner Bidder was declared to

    be not meeting the Financial Qualifying requirements. During

    clarification stage before tender opening, bidder’s queries with

    respect to the tender requirements were replied. Accordingly,

    bidder had submitted the bid. Hence it is evident that full

    opportunity was afforded to the Petitioner to represent his Case.

    As per Clause 4.2 of the Invitation to Bid (ITB), submission of a

    bid not substantially responsive to the bidding documents in

    every respect will be at the Bidder’s risk and may result in

    rejection of its bid. Further as per Clause 22.3 of ITB, “An

    affirmative determination of meeting the qualifying requirements

    will be a prerequisite for further evaluation of Techno-

    Commercial bid and holding clarification meeting, if any, with

    the Bidder. A negative determination will result in rejection of

    the Bidder’s Techno-Commercial Bid in which event EMPLOYER

    will not open the Price Bid of the concerned bidder and his bid

    security shall be returned.” Further as per clause 28.0 of ITB,

    specifies the “Employer’s Right to Accept Any Bid and to Reject
    7

    Any or All Bids”, as Employer reserves the right to accept or

    reject any bid, and to annul the bidding process and reject all

    bids at any time prior to award of contract, without thereby

    incurring any liability to the affected Bidder or bidders or any

    obligation to inform the affected Bidder or bidders of the

    grounds for Employer’s action. There is no gainsaying that

    Petitioner has unequivocally accepted the terms and condition

    of ITB. From the above clauses of ITB, it is clear that, it is not

    obligatory on the part of the Answering Respondent to provide

    any ground of rejection of the Bid. However, as petitioner failed

    to meet the QR an auto-generated communication regarding his

    non-qualifying for Tender was received by the petitioner.

    However, the petitioner, who (also by virtue of his Deed of Joint

    Undertaking), is fully aware that his Collaborator fails to meet

    Financial Capability related Qualifying Criteria cannot take a

    different stand in the matter.

    3.3. It is stated, petitioner has not approached this

    Court with clean hands. In similar circumstances, when Writ

    Petition No. 16442 of 2023 was filed against the NTPC, this

    Court dismissed the same vide order dated 03.10.2023 and the

    said order applies to this case. At para 18 and 19, it has been

    observed thus:

    8

    ” The Apex Court in Jagdish Mandal v State of Orissa and
    others
    reported in 2007 (14) SCC page 517 at para 22 observed as
    under:

    ” 22…. Attempts by unsuccessful tenderers with imaginary
    grievances, wounded pride and business rivalry, to make mountains out
    of molehills of some technical/procedural violation or some prejudice to
    self, and persuade courts to interfere by exercising power of judicial
    review, should be resisted. Such interferences, either interim or final,
    may hold up public works for years, or delay relief and succour to
    thousands and millions and may increase the project cost manifold.
    Therefore, a court before interfering in tender or contractual matters in
    exercise of power of judicial review, should pose to itself the following
    questions:

    i) Whether the process adopted or decision made by the authority is
    mala fide or intended to favour someone.

    OR
    Whether the process adopted or decision made is so arbitrary and
    irrational that the court can say: ‘the decision is such that no
    responsible authority acting reasonably and in accordance with relevant
    law could have reached.;

    ii) Whether public interest is affected.

    If the answers are in the negative, there should be no interference under
    Article 226″.

    19. Taking into consideration, the aforesaid facts and
    circumstances and duly considering the averments made by the
    respondent Nos. 1 to 3 in their counter affidavit in particular, paras 13,
    14 15 and 16 and taking into consideration the law laid down by the
    Apex Court in the judgments relied upon by the learned counsel for the
    respondents (referred to above) and duly taking into consideration, the
    law laid down by the Apex Court reported in 2020 (10) SCC page 766 in
    Shanthi Devi alias Shanthi Mishra v Union of India and others (referred
    to above
    ) and the view taken by the Apex Court in the judgment dated
    12.04.1996 in State of U.P. and others v Harish Chandra and others
    reported in 1996(9) SCC 309 (referred to and extracted above) and
    applying the view taken by the Apex Court in Jagdish Mandal v State of
    Orissa and others
    reported in 2007 (14) SCC page 517 (referred to and
    extracted above) and posing the said questions, as indicated in the said
    judgment
    to this Court itself, this Court opines that the answers are in
    9

    the negative, therefore, the present writ petition is dismissed since the
    same is devoid of merits”.

    The Hon’ble Apex Court in number of cases upheld

    the said legal proposition and it has now become a well-

    established law governing Judicial interference in Tendering

    process that the Court should not ordinarily interfere in matters

    relating to tender or contract. Hence, the Writ Petition be

    dismissed on the basis of the above.

    3.4. It is also stated, since the entire tendering process

    is being done at Raipur, Chhattisgarh, on line mode, no cause of

    action has arisen within the territorial Jurisdiction of this

    Court. Further as per Deed of Joint Undertaking executed by

    Petitioner, the Courts of Raipur shall have exclusive

    jurisdiction. As per Clause 2.2 of the Special Condition of

    Contract also Court of Competent Jurisdiction at Raipur is

    having exclusive jurisdiction.

    3.5. This Court vide order dated 03.05.2024 issued

    directions as extracted under:

    “The issue, whether the petitioner has fulfilled all the
    conditions of the tender notification dated 21.11.2023 issued by the
    respondent and is eligible for financial bid, is required to be adjudicated
    after filing of the counter affidavit by the respondent. In the meanwhile,
    any further action taken by the respondent in pursuance of the tender
    notification dated 21.11.2023 shall be subject to further orders of this
    Court.”

    10

    It is stated, in compliance with the said order, PO

    No. 5500044674 dated 29.05.2024 was placed upon L1 Bidder

    M/s. Schenck Process Solutions India Pvt Ltd, Bangalore, with

    the stipulation that the Award of PO shall be subjected to the

    further/final Order (s) of this Court. Accordingly, no claim on

    account of any reason / ground whatsoever shall be admissible

    against NTPC for any rescinding/modification of the Contract

    /PO, made in compliance to the Final Judgment in this regard

    and any decision of EIC in this regard shall be final and binding

    on the parties. It is also stated, bidding conditions has the pre-

    requisite of entering DJU with the Collaborator. Further,

    Collaborator should invariably be a Holding Company of the

    bidder as well as should simultaneously comply with the

    requirement of being a ‘Qualified Coal Mill Manufacturer’ which

    has been specified under tender technical Qualifying

    Requirement at Clause 6.1.1. Thus, the bidder’s contention to

    set aside the applicability of additional financial Qualification

    Requirements for licensor, in spite of submitting the DJU on

    non-judicial stamp paper so as to fulfill the Technical

    Qualification Requirements is devoid of merit.

    3.6. It is stated, bid of Petitioner was not rejected

    unreasonably. Rather the compliance of tender technical

    Qualifying Requirements, submission of DJU to fulfil technical
    11

    Qualification Requirements based on the Collaborator,

    compliance of financial requirements for bidder and the

    compliance of additional financial Requirements for Collaborator

    with whom bidder/petitioner has executed the DJU as the

    Executant Partner was evaluated in the tender. Accordingly, bid

    of petitioner was rejected and a system generated e mail dated

    02.05.2024 was sent to petitioner for rejection of bid.

    4. In the counter filed on behalf of Respondent No.2, it

    is stated, on 03.06.2024, they received information from the

    on line portal of Respondent No. 1 that it was the L1 bidder for

    the subject Tender and it was awarded the Tender vide

    Purchase Order dated 29.05.2024, after having met all the

    specifications under the QR as per the instructions under the

    Tender. They met the QR under Invitation for Bid (“IFB”), also

    qualified the financial criteria under Clause 6.2, furnished

    performance securities for ten per cent (10%) of the total

    contract price in compliance with Clause 31 of the Instructions

    to Bidders (“ITB”).

    4.1. It is also stated that the present matter pertains to

    the award of tender by a Public Sector Undertaking. It is a

    settled position of law upheld by the Hon’ble Apex Court in a

    catena of judgments that there are inherent limitations in

    exercise of the power of judicial review in matters pertaining to
    12

    tenders and contractual powers of Government bodies. It is

    stated, the right to choose cannot be considered to be an

    arbitrary power. In the present case, Petitioner did not meet the

    qualification requirements under the IFB, as such, Respondent

    No. 1 rightly rejected the bid of Petitioner. This respondent

    draws attention to Clause 28 of the ITB stipulates as follows:

    ” Employer’s Right to Accept Any Bid and to Reject Any
    or All Bids:

    Employer reserves the right to accept or reject any bid, and to and
    the bidding process and reject all bids at any time prior to award of
    contract, without thereby incurring any liability to the affected Bidder or
    bidders or any obligation to inform the affected Bidder or bidders of the
    grounds for Employer’s action”.

    Clause 28 clearly states that Respondent No. 1

    reserves the right to accept or reject any bid, and to annul the

    bidding process and reject all bids at any time prior to the

    award of the contract, without incurring any liability to the

    affected bidder or bidders or any obligation to inform the

    affected bidder or bidders of the grounds for employer’s action.

    4.2. It is stated, petitioner alleges to have qualified

    under the technical criteria via Route 3 under Clause 6.1.3 of

    the IFB viz. Subsidiary of a Qualified Coal Mill Manufacturer.

    Petitioner also alleges to have filed a Deed of Joint Undertaking

    with the Qualified Coal Mill Manufacturer. Here, it is to be seen,
    13

    as per Clause 6.2 of the IFB, there were Additional Financial

    Requirements to be met by the Collaborator of Petitioner. As is

    clear from the counter filed by Respondent No.1, Petitioner did

    not meet the Additional Financial Requirements stipulated

    under Clause 6.2 of the IFB. In fact, as per the counter of

    Respondent No. 1, the net worth of the Collaborator of Petitioner

    is on the negative side. Since Petitioner did not meet the QR laid

    down under the IFB, Respondent No.1 rightly rejected the bid of

    Petitioner. Petitioner cannot, at this point of time, take a stand

    that it could change its Collaborator and enter into a fresh Deed

    of Joint Undertaking to meet the aforementioned financial

    requirements.

    4.3. It is stated, the Hon’ble Supreme Court had

    unequivocally held in a catena of decisions that it is not for the

    Court to determine whether a particular policy or particular

    decision taken in the fulfilment of that policy is fair. The Court

    is only concerned with the manner in which those decisions

    have been taken. The Court does not sit as a court of Appeal but

    merely reviews the manner in which the decision was made. The

    action of Respondent No.1 cannot be regarded as arbitrary

    action as there was proper reasonable criteria by which

    petitioner’s qualification was rejected. The terms of the
    14

    invitation to tender cannot be open to judicial scrutiny because

    the invitation to tender is in the realm of contract.

    4.4. It is further stated, this Court under Article 226 of

    the Constitution would not be justified in interfering with

    commercial transactions in which the State is one of the parties

    except where there is substantial public interest involved and in

    cases where the transaction is mala fide. The scope of judicial

    review in matters pertaining to tenders and contracts by Public

    Sector Undertakings is limited to cases where it is clearly

    established that there was a mala fide action on the part of the

    Respondent or there is substantial public interest involved. It is

    respectfully submitted by the Answering Respondent that the

    present case does not qualify both the parameters and s such,

    the present Petition is liable to be dismissed.

    5. Petitioner filed rejoinder denying the averments of

    the counter and reiterating the averments of the writ petition. It

    is well-settled that constitutional courts can interfere in the

    decision making process of the tender authority when the

    decision is arbitrary and irrational. Reliance is placed on the

    judgments in Jagdish Mandal v. State of Orissa 1, Monarch

    Infrastructure (P) Ltd. v. Ulhasnagar Municipal Corpn. 2. It is

    1
    (2007) 14 SCC 517
    2
    (2000) 5 SCC 287
    15

    also stated, the order dated 03.10.2023 in Writ Petition No.

    16442 of 2023 relied on by Respondent No.1 is in fact, in favour

    of Petitioner. Although the facts in the said case are different to

    the facts in the present case, the Court in the said case did

    interpret the bid conditions and came to the conclusion that

    petitioner therein did not fulfil the qualification requirements.

    However, in the present case, Petitioner fulfilled all the

    Qualifying Requirements stipulated in the IFB.

    6. Sri P. Venugopal, learned Senior Counsel assisted

    by Sri M. Abhinay Reddy, learned counsel for petitioner

    contends that the action of Respondent No.1 in rejecting

    petitioner’ bid for non-compliance with clause 6.2.2. is

    arbitrary, irrational and contrary to the tender conditions. He

    further argues that the entire tendering process is being done at

    Raipur, Chattisgarh, on line mode, however, relying on the

    judgment in Shanti Devi v. UOI 3, contends that irrespective of

    the fact that seat of the authority concerned is outside the

    territorial jurisdiction of the High Court, even if a small fraction

    of cause of action arises within its jurisdiction, it has

    jurisdiction. In that regard, reliance is also placed on the

    3
    (2020) 10 SCC 766
    16

    judgment in Gupta Freight Carrier v. Executive Director 4

    and MRT Signals Ltd. V. UOI 5.

    6.1. Another argument put forward by learned counsel

    is that reserving rights clause in tender does not absolve the

    authority from furnishing valid reasons. Based on the judgment

    of the Hon’ble Delhi High Court in PKF Sridhar and

    Santhanam v. Airports Economic Regulatory Authority of

    India 6, learned counsel submits that such clauses do not mean

    that the authority should not have valid reasons to justify its

    conduct.

    7. On the other hand, learned counsel for Respondent

    No.1 Sri Ch. Sidharth Sharma primarily takes objection on the

    maintainability of the Writ Petition as the writ of certiorari is not

    maintainable against the NTPC order. He places reliance on the

    judgment of the Hon’ble Apex Court in Central Council for

    Research in Ayurvedic Studies v. Bikartan Das 7, Radhey

    Shyam v. Chhabi Nath 8. Secondly, it is argued, this Court

    does not possess the territorial jurisdiction to adjudicate the

    present dispute. Reliance is placed on the judgment of the

    Hon’ble Supreme Court in State of Rajasthan v. M/s Swaika

    4
    2022 SCC On line Bom 706
    5
    2024 SCC On line Cal 5593
    6
    2022 SC On line Del 122
    7
    2023 SCC On line SC 996
    8
    (2015) 5 SCC 423
    17

    Properties 9. Thirdly, learned counsel, on the scope of judicial

    review in matters pertaining to tender, argued that the scope is

    limited and the terms of the invitation for bids cannot be open

    to judicial scrutiny and interpretation and understanding of the

    tender conditions given by the Employer should be second-

    guessed by courts under judicial review. Learned counsel tries

    to take cue from the judgments of the Hon’ble Apex Court in

    Silppi Constructions Contractors v. Union of India10,

    Jagdish Mandal’s case (supra), JSW Infrastructure Ltd. v.

    Kakinada Sea Port 11, and Galaxy Transport Agency v. New

    J.K. Roadways 12.

    8. Heard M/s King Stubb & Kasiva, learned counsel for

    Respondent No.2.

    9. Upon consideration of the pleadings, material on

    record and the submissions, this Court finds that the primary

    relief sought is issuance of a Writ of Certiorari to quash the

    rejection email dated 02.05.2024 issued by Respondent No.1 in

    the course of a tender process. Whereas the contention of

    respondent No.1 is writ of certiorari is not maintainable.

    9
    (1985) 3 SCC 217
    10
    (2020) 16 SCC 489
    11
    (2017) 4 SCC 170
    12
    (2021) 16 SCC 808
    18

    10. It is settled position of law that a writ of certiorari is

    issued to quash decisions of judicial or quasi-judicial authorities

    where such authorities act without jurisdiction, exceed

    jurisdiction, commit an error apparent on the face of the record,

    or violate principles of natural justice. The scope of certiorari

    does not ordinarily extend to purely administrative or

    contractual decisions unless such decisions are shown to be

    vitiated by arbitrariness, mala fides, or violation of statutory

    provisions.

    11. In Central Council for Research in Ayurvedic

    Studies v. Bikartan Das (supra), the Hon’ble Supreme Court

    held as under:

    ” 53. This Court explained that a court which has jurisdiction
    over a subject-matter has jurisdiction to decide wrong as well as right,
    and when the legislature does not choose to confer a right of appeal
    against that decision, it would be defeating its purpose and policy if a
    superior court were to rehear the case on the evidence and substitute its
    own finding in certiorari.

    54. In Yakoob v. K.S. Radhakrishnan [Yakoob v. K.S.
    Radhakrishnan, 1963 SCC OnLine SC 24 : AIR 1964 SC 477] , P.B.
    Gajendragadkar, C.J., speaking for the Constitution Bench, placed the
    matter beyond any position of doubt by holding that a writ of certiorari
    can be issued for correcting errors of jurisdiction committed by inferior
    courts or tribunals. The observations of this Court in para 7 are worth
    taking note of : (SCC OnLine SC para 7)
    “7. The question about the limits of the
    jurisdiction of High Courts in issuing a writ of certiorari
    under Article 226 has been frequently considered by this
    Court and the true legal position in that behalf is no longer in
    doubt. A writ of certiorari can be issued for correcting errors
    19

    of jurisdiction committed by inferior courts or tribunals :

    these are cases where orders are passed by inferior courts or
    tribunals without jurisdiction, or is in excess of it, or as a
    result of failure to exercise jurisdiction. A writ can similarly
    be issued where in exercise of jurisdiction conferred on it, the
    Court or Tribunal acts illegally or improperly, as for instance,
    it decides a question without giving an opportunity to be
    heard to the party affected by the order, or where the
    procedure adopted in dealing with the dispute is opposed to
    principles of natural justice. There is, however, no doubt that
    the jurisdiction to issue a writ of certiorari is a supervisory
    jurisdiction and the Court exercising it is not entitled to act
    as an appellate court. This limitation necessarily means that
    findings of fact reached by the inferior court or Tribunal as a
    result of the appreciation of evidence cannot be reopened or
    questioned in writ proceedings. An error of law which is
    apparent on the face of the record can be corrected by a writ,
    but not an error of fact, however grave it may appear to be. In
    regard to a finding of fact recorded by the Tribunal, a writ of
    certiorari can be issued if it is shown that in recording the
    said finding, the Tribunal had erroneously refused to admit
    admissible and material evidence, or had erroneously
    admitted inadmissible evidence which has influenced the
    impugned finding. Similarly, if a finding of fact is based on no
    evidence, that would be regarded as an error of law which can
    be corrected by a writ of certiorari. In dealing with this
    category of cases, however, we must always bear in mind that
    a finding of fact recorded by the Tribunal cannot be
    challenged in proceedings for a writ of certiorari on the
    ground that the relevant and material evidence adduced
    before the Tribunal was insufficient or inadequate to sustain
    the impugned finding. The adequacy or sufficiency of evidence
    led on a point and the inference of fact to be drawn from the
    said finding are within the exclusive jurisdiction of the
    Tribunal, and the said points cannot be agitated before a writ
    court. It is within these limits that the jurisdiction conferred
    on the High Courts under Article 226 to issue a writ of
    certiorari can be legitimately exercised….”

    12. From the above, it is to be understood, while

    exercising extraordinary jurisdiction under Article 226 of the

    Constitution, more particularly when it comes to the issue of a

    writ of certiorari, the High Court does not exercise the powers of

    Appellate Tribunal and it does not review or reweigh the

    evidence upon which the determination of the inferior tribunal
    20

    purports to be based and the writ of Certiorari can be issued if

    an error of law is apparent on the face of the record and it being

    a high prerogative writ, should not be issued on mere asking.

    Further, the Writ of Certiorari is issued for correcting errors of

    jurisdiction, as and when an inferior court or tribunal acts

    without jurisdiction or in excess of it, or fails to exercise it.

    13. Further, the Hon’ble Supreme Court in Silppi

    Constructions Contractors v. Union of India laid down the

    law that calling for a tender is purely an administrative decision

    and it need not contain any reasons and that it is neither a

    judicial nor a quasi-judicial order. Learned counsel for

    petitioner in his Note, relied on the aforementioned judgment in

    Silppi Constructions Contractors’ case (supra) wherein the

    Hon’ble Supreme Court held at Para 19 that the Court being the

    guardian of fundamental rights is duty bound to interfere when

    there is arbitrariness, irrationality, mala fides and bias.

    However, the Counsel for the Petitioner is only relying on the

    judgment in part and the entire para 19 wherein the Hon’ble

    Apex Court clearly held that Government Contracts must not be

    easily interfered with is extracted herein below:

    “This Court being the guardian of fundamental rights is
    duty bound to interfere when there is arbitrariness, irrationality, mala
    fides and bias. However, this Court in all the aforesaid decisions has
    cautioned time and again that courts should exercise a lot of restraint
    21

    while exercising their powers of judicial review in contractual or
    commercial matters. This Court is normally loathe to interfere in
    contractual matters unless a clearcut case of arbitrariness or mala fides
    or bias or irrationality is made out. One must remember that today
    many public sector undertakings compete with the private industry. The
    contracts entered into between private parties are not subject to
    scrutiny under writ jurisdiction. No doubt, the bodies which are State
    within the meaning of Article 12 of the Constitution are bound to act
    fairly and are amenable to the writ jurisdiction of superior courts but
    this discretionary power must be exercised with a great deal of restraint
    and caution. The Courts must realise their limitations and the havoc
    which needless interference in commercial matters can cause. In
    contracts involving technical issues the courts should be even more
    reluctant because most of us in judges’ robes do not have the necessary
    expertise to adjudicate upon technical issues beyond our domain. As
    laid down in the judgments cited above the courts should not use a
    magnifying glass while scanning the tenders and make every small
    mistake appear like a big blunder. In fact, the courts must give “fair play
    in the joints” to the government and public sector undertakings.”

    14. In the present case, the impugned action arises out

    of a tender process initiated by Respondent No.1 – NTPC Limited,

    a Public Sector Undertaking, under NIT No. NTPC/USSC-

    CGP1/9900258610 dated 21.11.2023. The process of evaluation

    of bids, determination of technical and financial eligibility, and

    rejection of non-responsive bids is essentially a contractual and

    administrative function carried out in terms of the Invitation for

    Bids and Instructions to Bidders. The rejection e mail dated

    02.05.2024, which is sought to be quashed, is not an

    adjudicatory order passed by a judicial or quasi-judicial
    22

    authority after hearing parties, but is an outcome of evaluation

    of bids in a commercial tender process governed by contractual

    terms such as Clause 6.1, Clause 6.2.2, Clause 28 of the ITB

    and other provisions of the bidding documents. The said action

    does not involve determination of rights in a lis between parties

    in a judicial manner, but is a decision taken by the tendering

    authority in exercise of its contractual discretion. In the light of

    the same, as rightly contended by learned Counsel for

    Respondent No.1, writ of certiorari cannot be entertained against

    the impugned order.

    15. Secondly, the question is whether the High Court

    possesses territorial jurisdiction to adjudicate the present

    dispute. Admittedly, The Tender was floated at Raipur in the

    State of Chattisgarh; petitioner is a resident of Chennai, Tamil

    Nadu; they submitted Tender, in respect of a work at

    Ramagundam in the State of Telangana, hence, they cannot file

    this Writ before Telangana High Court in as much as, no “fact”

    has yet arisen in Telangana to give rise to cause of action in

    Telangana. The Hon’ble Supreme Court in M/s Swaika

    Properties (supra) has categorically held that once the Hon’ble

    High Court lacks territorial jurisdiction, the High Court cannot

    entertain the Writ Petition. In the said Judgment, the property
    23

    which was the subject matter of litigation was situated in

    Rajasthan. Merely because a Notice of acquisition of the said

    property was served at Kolkata, it was held, that per se does not

    enable the Kolkata High Court to assume jurisdiction and

    entertain the Writ Petition. In this case also, no fact per-se has

    arisen in the State of Telangana so that Petitioner can seek the

    indulgence of this Court to entertain the Writ Petition.

    16. Though learned counsel for petitioner sought to

    place reliance on the judgment of this Court in Writ Petition No.

    16442 of 2023, the ratio laid down therein is inapplicable

    inasmuch as petitioner therein who participated in the tender

    floated by NTPC is an entity based in State of Telangana itself,

    whereas petitioner herein is a Chennai-based entity. Further,

    learned counsel for Respondent No.1 filed a memo enclosing

    thereto the Special Conditions of the Contract, Condition No.

    2.2 of which stipulates that ‘the contract shall be governed by

    and interpreted in accordance with the Laws in force in India.

    The Courts at Raipur shall have exclusive jurisdiction in all

    matters arising under the contract. Also, Clause 9 in Deed of

    Joint Undertaking says that any dispute that may arise in

    connection with the Deed of Joint Undertaking shall be settled

    as per arbitration procedure / rules mentioned in the contract

    documents. This Deed shall be construed and interpreted in
    24

    accordance with the Laws of India and the Courts of Raipur

    shall have exclusive jurisdiction. This clause again reiterates

    that the Courts at Raipur shall have exclusive jurisdiction in the

    mater. In that view of the matter, it is to be concluded that this

    Court lacks territorial jurisdiction to entertain the Writ Petition.

    17. Thirdly, it is to be seen, the scope of judicial review

    in matters pertaining to tender is limited and the terms of the

    invitation for bids cannot be open to judicial scrutiny and

    interpretation and understanding of the tender documents given

    by the employer should be second-guessed by courts under

    judicial review. In Jagdish Mandal‘s case, the Hon’ble Apex

    Court held that a Court before interfering in tender or

    contractual maters in exercise of power of judicial review,

    should pose to itself the following questions:

    (i) Whether the process adopted or the decision taken by the authority is
    mala fide or intended to favour some one;

    Or
    Whether the process adopted or decision made is so arbitrary and irrational
    that the Court can say: “the decision is such that no responsible authority
    acting reasonably and in accordance with relevant law could have reached”.

    (ii) Whether public interest is affected?

    18. It has been held by the Hon’ble Supreme Court in

    JSW Infrastructure Ltd. and New J.K. Roadways (supra) that

    interest of the person who issued the tender has to be protected

    and nothing beyond. In matters of contract, the Courts must
    25

    also not interfere where such interference will cause

    unnecessary loss to the public exchequer. No doubt, the tender

    in question arises out of contractual domain involving

    commercial decision of a Public Sector Undertaking. The scope

    of judicial review in such matters is limited to examining the

    decision-making process and not the merits of the decision. The

    law laid down in Jagdish Mandal‘s case clearly holds that

    interference is warranted only when the decision is mala fide,

    arbitrary to the extent that no reasonable authority

    would have taken such decision, or where public interest is

    affected. Even in TATA Cellular v. Union of India 13, the

    Hon’ble Supreme Court have laid down the parameters of

    interpretation and the one stated by petitioner does not fit in

    those parameters.

    19. In the present case, petitioner, admittedly,

    participated under Route-3 under Clause 6.1.3 and submitted

    Deed of Joint Undertaking dated 24.11.2023. The DJU, which

    forms part of the tender documents, specifically treats the

    associated entity as Collaborator and binds both the parties

    jointly and severally. Respondent No. 1 has evaluated the bid on

    the basis of the DJU submitted by petitioner. The contention of

    Petitioner that its QCMM is a ‘licensor’ and not a ‘collaborator’

    13
    (1994) 6 SCC 651
    26

    cannot be accepted in view of the fact that Petitioner has itself

    executed DJU in prescribed format and relied upon such

    document for qualification. The attempt to re-characterize the

    relationship after submission of bid is clearly untenable and

    amounts to altering the basis of qualification after participation.

    20. Further, Clauses 6.2.2.1 and 6.2.2.2 clearly

    stipulate Additional Financial Criteria for Collaborator/Associate

    for bidders under Clause 6.1.3. Once Petitioner has submitted

    DJU and projected its QCMM as Collaborator for the purpose of

    qualification, compliance with Clause 6.2.2 becomes mandatory.

    The material on record establishes that Collaborator’s net worth

    is negative and does not meet the requirement of not less than

    100% or even 75% of paid-up share capital. The plea of

    Petitioner that it independently satisfies financial criteria is also

    of no assistance, as the tender conditions specifically require

    compliance with criteria applicable to Route-3 including

    collaborator requirements. The terms of the tender cannot be

    rewritten by the Court.

    21. It is also relevant to note that contract has already

    been awarded to Respondent No.2 vide Purchase Order dated

    29.05.2024 and Contract Agreement dated 11.07.2024, and

    substantial steps have been taken including furnishing of bank
    27

    guarantees. Interference, at this stage, would cause prejudice,

    delay in execution of a project of national importance and

    adversely affect public interest. In view of the above, this Court

    is of the considered opinion that petitioner failed to establish any

    arbitrariness, mala fide or illegality in the decision-making

    process of Respondent No.1.

    22. Accordingly, the Writ Petition is dismissed. No costs.

    23. Consequently, the miscellaneous Applications, if

    any shall stand closed.

    ——– —————————–

    NAGESH BHEEMAPAKA, J

    22nd April 2026

    ksld



    Source link

    LEAVE A REPLY

    Please enter your comment!
    Please enter your name here