Yukti Construction Pvt. Ltd vs State Of Uttarakhand & Others on 20 April, 2026

    0
    34
    ADVERTISEMENT

    Uttarakhand High Court

    Yukti Construction Pvt. Ltd vs State Of Uttarakhand & Others on 20 April, 2026

    Author: Manoj Kumar Tiwari

    Bench: Manoj Kumar Tiwari

           IN THE HIGH COURT OF UTTARAKHAND AT
                         NAINITAL
             Writ Petition (M/S) No. 93 of 2024
    
    Yukti Construction Pvt. Ltd.                        ... Petitioner
                                  Versus
    
    State of Uttarakhand & Others                  ... Respondents
    
    
         Mr. Deepak Dhingra, Mr. Aditya Singh & Mr. B.S. Kathayat,
         Advocates for the petitioner.
         Mr. Pradeep Hariya, Additional Chief Standing Counsel with Mr.
         Sushil Vashistha, Standing Counsel for the State of Uttarakhand.
         Mr. Sandeep Kothari, Advocate for respondent no.4.
    
    
                                ORDER
    

    Hon’ble Manoj Kumar Tiwari, J.

    Miscellaneous Application (IA No. 19662 of 2025)

    SPONSORED

    This application has been filed by petitioner
    seeking injunction prohibiting the respondents from
    selling or parting with possession of the land in
    question or otherwise encumbering the land, which is
    subject matter of the writ petition.

    2. Learned counsel for the respondents submit
    that similar prayer for interim relief, made by
    petitioner was considered and rejected by learned
    Single Judge of this Court, vide order dated
    24.09.2014, and Special Appeal No. 571 of 2014 filed
    by appellant against the said order was also
    dismissed, therefore, subsequent application for
    identical relief would not be maintainable.

    3. Learned State counsel refers to the relief
    clause of the writ petition for contending that

    1
    petitioner has challenged the notification dated
    21.09.1987, issued under Section 4 of Land
    Acquisition Act, 1894 and also the notification dated
    30.01.1988, issued under Section 6 of the said Act
    and the Special Land Acquisition Officer, Dehradun
    gave his award on 19.02.1990, as mentioned in
    paragraph no. 3 of the writ petition, therefore, there
    is no good ground for granting the interim protection,
    as claimed by the petitioner. The reliefs sought in the
    writ petition are extracted below, for ready
    reference:-

    “(i) issue a suitable writ, order or direction in
    the nature of certiorari quashing the notifications
    under Sections 4 and 6 of the Land Acquisition Act
    were issued on 21.09.1987 and 30.01.1988
    (Annexure P-1)

    (ii) issue a suitable writ, order or direction in
    the nature of certiorari quashing the orders of the
    Collector/District Magistrate, Dehradun, dated
    11.03.2013 and 22.04.2013 (Annexure nos. 17 & 16
    respectively, to this writ petition);

    (ii) Issue a suitable writ, order or direction in
    the nature of mandamus directing the respondents
    not to dispossess the petitioner from plots bearing
    Khewat No.1 and Khasras included in it situated in
    village Rikholi, Pargana Pachwadun, Tehsil and
    District Dehradun, having total area of 187.4890
    hectares equivalent to 491 Acres.”

    4. Learned State Counsel, by referring to the
    averment made in paragraph no. 6 of the writ
    petition submits that petitioner claims to have
    purchased 491 acres land at Rikholi Village in
    Mussoorie, District Dehradun by means of separate
    sale deeds between 2007-2010. He submits that
    since the land is vested in the State Government as
    per provisions of Land Acquisition Act, 1894,
    therefore, the sale deeds executed in favour of

    2
    petitioner on subsequent dates, as mentioned in
    paragraph no. 6 of the writ petition, would not
    convey any title to the petitioner.

    5. This Court finds substance in the contention
    raised by learned counsel for the respondents. Since
    similar prayer made by petitioner earlier was rejected
    by this Court on 24.09.2014 and the rejection order
    was affirmed in appeal by Division Bench of this
    Court, vide order dated 10.03.2015, therefore,
    petitioner is not entitled to any protection, as sought
    in this application.

    6. Learned counsel for the petitioner could not
    point out any imminent threat to the property in
    question, which may warrant passing of interim order
    for protecting it. Petitioner has challenged the
    notifications issued under Sections 4 & 6 of Land
    Acquisition Act, 1894, which indicates that the land in
    dispute was subjected to acquisition proceedings. The
    acquisition proceedings concluded in the year 1990 as
    per pleading made in the writ petition and the
    acquired land came to be vested in the State
    Government, which is now continuing in possession
    over the land in question, as held by this Court in its
    order dated 24.09.2014. It is well settled that
    injunction cannot be granted against the true owner
    of property (Premji Ratansey Shah v. Union of India,
    reported as (1994) 5 SCC 547). Petitioner is yet to
    prove his right or title over the land in question,
    therefore, at his instance, State Authorities cannot be
    prevented from using the land for a public purpose.

    3

    7. For the aforesaid reasons, Misc. Application,
    seeking injunction filed by petitioner, is rejected.

    Delay Condonation Application (IA No. 19661 of 2025)
    Review Application (IA No. 19663 of 2025)

    8. As per office report, there is delay of 6
    years, 8 months and 13 days in filing application
    seeking review of orders dated 05.12.2018 and
    06.12.2018.

    9. For the reasons indicated and in the interest
    of justice, delay condonation application is allowed
    and delay in filing the review application is condoned.

    10. Operative portion of the order dated
    05.12.2018 is reproduced below:-

    “11. Mr. S.S. Yadav shall also explain why he
    has filed such false affidavit and Mr. Deepak Dhingra,
    Advocate shall explain why he has clandestinely
    drafted the applications and projected Mr. Bharose
    Lal as retired Judge of the High Court.”

    11. Operative portion of the order dated
    06.12.2018 is reproduced below:-

    “The report submitted by Mr. Bharose Lal, Advocate
    Commissioner, who had been appointed at the
    instance of the petitioner, cannot be considered as
    an independent Advocate Commissioner. Learned
    counsel for the petitioner company would submit that
    he is not willing to place reliance on the report of Mr.
    Bharose Lal, Advocate Commissioner and the same
    may be rejected. With the consent of the parties, the
    report dated 19.08.2017 of Mr. Bharose Lal,
    Advocate Commissioner, is hereby rejected.”

    12. Perusal of the order dated 05.12.2018
    reveals that there is neither any finding nor
    observation made by the Court, which would
    prejudice claim of the petitioner/review applicant for
    title over the land in question. By the said order,
    4
    representatives of the petitioner were asked to give
    an explanation as to why they misrepresented facts
    before coordinate Bench, which led to passing of
    order dated 28.03.2016.

    13. Careful perusal of the order dated
    06.12.2018 would reveal that the report submitted by
    Mr. Bharose Lal was rejected by this Court, in view of
    submission made by learned counsel for the
    petitioner that he is not willing to place reliance on
    that report. Perusal of order dated 06.12.2018
    further reveals that report submitted by Mr. Bharose
    Lal was rejected with the consent of parties.

    14. Learned counsel for the respondents are
    therefore right in submitting that an order passed
    with consent of parties cannot be reviewed on the
    asking of a party, which had consented to passing of
    that order.

    15. Learned counsel for the review applicant
    contends that petitioner’s counsel never consented
    for setting aside the report submitted by Mr. Bharose
    Lal, therefore, the order dated 06.12.2018 is liable to
    be reviewed.

    16. Learned counsel for the respondents,
    however, submit that the application seeking review
    is filed after nearly seven years and if what the
    petitioner/review applicant states is correct, then he
    should have filed application seeking review of the
    order dated 06.12.2018 in the year 2018, but this
    application is filed in 2025.

    5

    17. Learned counsel appearing for respondent
    no. 4 refers to paragraph no. 11 of the Misc.
    Application No. 19659 of 2018 filed by petitioner,
    where it is mentioned that this Court while rejecting
    the report submitted by Mr. Bharose Lal, made
    observation regarding appointment of fresh Advocate
    Commissioner. Learned counsel for respondent no. 4
    points out that by that application, petitioner prayed
    for appointing any person as the Hon’ble Court finds
    suitable as Advocate Commissioner for submitting a
    report concerning the issues as mentioned in
    paragraph no. 9 of the application.

    18. Learned State Counsel points out that Misc.
    Application No. 19659 of 2018 was filed by the
    petitioner in the Registry of this Court on 18.12.2018.
    Thus, he submits that petitioner had no grievance
    against rejection of report of Mr. Bharose Lal,
    consequently, instead of seeking recall/review of the
    order dated 06.12.2018, petitioner chose to file
    application for appointing another Advocate
    Commissioner. Thus, it is contended that petitioner
    cannot now be permitted to resile from the stand,
    which he took earlier, by his conduct.

    19. Learned counsel for respondent no. 4
    submits that filing of another application for
    appointing other Advocate Commissioner, after
    rejection of report submitted by Mr. Bharose Lal, vide
    order dated 06.12.2018, reveals that petitioner had
    no grievance against the order dated 06.12.2018;
    instead of seeking review of order dated 06.12.2018,

    6
    petitioner chose to file application for appointing
    another Advocate Commissioner, therefore,
    petitioner/review applicant cannot now contend that
    the order dated 06.12.2018 is erroneous, therefore,
    deserves to be reviewed. He submits that petitioner
    cannot be permitted to approbate and reprobate at
    the same time. Learned counsel for respondent no. 4
    further submits that there is no error apparent in the
    orders dated 05.12.2018 and 06.12.2018, which may
    warrant invocation of review jurisdiction by this
    Court.

    20. This Court finds substance in the
    submission made on behalf of the respondents. The
    order dated 06.12.2018 indicates that petitioner’s
    counsel stated that he is not willing to place reliance
    on the report of Mr. Bharose Lal. The said order
    reveals that the report submitted by Mr. Bharose Lal
    was rejected with the consent of parties. If
    petitioner’s concession was wrongly recorded in the
    order dated 06.12.2018, then remedy for petitioner
    was to immediately seek review of that order, but
    instead of doing so, he filed application praying for
    appointment of some other Advocate Commissioner.
    Petitioner’s conduct corroborates the submission
    made on behalf of the respondents that petitioner
    consented to rejection of report submitted by
    Mr. Bharose Lal.

    21. Review of an order can be made only when
    there is an error apparent on the face of record, but
    this Court do not find any error, which may warrant

    7
    invocation of review jurisdiction. Moreover, the order
    dated 06.12.2018 was passed with the consent given
    on behalf of the petitioner, therefore, this Court does
    not find any reason to review the said order.

    22. For the aforesaid reasons, this Court does
    not find any scope to review the order dated
    06.12.2018. Review Application (IA No. 19663 of
    2025) is rejected.

    Misc. Application ( I.A. No. 19665 of 2025

    23. Miscellaneous Application (IA No. 19665 of
    2025) stands disposed of accordingly.

    Misc. Application (CLMA No. 19659 of 2018)

    24. This application was filed on 18.12.2018
    with the following prayer:-

    “A. Pass necessary orders appointing any person as
    this Hon’ble Court may find suitable as Advocate
    Commissioner for the purpose of submitting with this
    Hon’ble Court a report concerning the issues as
    detailed in paragraph no. 9 above or such other
    issues which the Hon’ble Court may deem fit and
    proper.”

    25. Learned counsel for the petitioner submits
    that petitioner purchased 187.489 hectare land
    comprised in Khasra No. 1298-1331 in Village Rikholi,
    District Dehradun by means of different sale deeds
    executed between 2007-2010. He submits that since
    the purchased land is fragmented, therefore,
    Advocate Commissioner deserves to be appointed, for
    identifying the land purchased by the petitioner.

    26. Learned State Counsel, however, submits
    that courts cannot use their authority, such as

    8
    appointing Commissioners to collect evidence for a
    party or to bridge-gaps in a case. He submits that
    courts’ agency is intended to resolve disputes, based
    on material on record and not for phishing
    expeditions to gather evidence on behalf of a party.
    He submits that Court Commissioners can be
    appointed in appropriate cases where there is
    ambiguity on a specific aspect and the purpose of
    Commissions is not to replace the evidence that
    should be collected by the parties. He further submits
    that law is well settled that Court Commissioner
    cannot be appointed to fill-up lacuna, which might
    have been left in the evidence and since petitioner
    has not been able to bring any evidence on record in
    support of his case, therefore, he has made this
    prayer for appointing Advocate Commissioner.
    Learned State Counsel further submits that petitioner
    has challenged the notifications issued by the State
    Government under Section 4 & 6 of the Land
    Acquisition Act, therefore, there is no factual dispute
    to be resolved, for which report from Advocate
    Commissioner would be needed. He further submits
    that if Advocate Commissioner is appointed and his
    report is taken on record, then respondents will
    agitate their right of filing objection to the report and
    thereafter oral testimony of the witnesses will also
    have to be recorded. He submits that challenge
    thrown by petitioner to the notifications issued under
    Land Acquisition Act can be decided without going

    9
    into the factual disputes, which petitioner is trying to
    bring in through Advocate Commissioner’s report.

    27. Learned State Counsel further submits that
    petitioner has challenged the notifications issued
    under Land Acquisition Act, 1894, whereby
    proceedings for acquisition of land were set in
    motion. He submits that from the relief claimed by
    the petitioner, it is apparent that petitioner is clear
    about identity of the land purchased by him, as no
    one would challenge notifications issued under
    Section 4 & 6 of Land Acquisition Act in respect of
    land belonging to some other person. He further
    submits that every litigant approaching Court for
    relief has to stand on his own feet, therefore, the
    prayer made by petitioner deserves to be rejected.
    Learned State Counsel further submits that petitioner
    cannot be permitted to enlarge scope of writ petition
    by bringing in unnecessary factual disputes. Learned
    State Counsel further submits that petitioner is trying
    to convert this writ petition to a title suit, as he wants
    to establish his title over a land, which was acquired
    by the State Government between 1987-1990.
    Learned State Counsel further submits that if
    petitioner wants declaration of his title over the land
    in question, then, the only remedy available to him,
    is by way of approaching a civil court.

    28. Learned counsel for the petitioner, per
    contra, submits that the land in question was
    purchased by petitioner after demarcation under
    Section 41 of the Land Revenue Act and petitioner’s

    10
    name is mutated in revenue record, therefore, State
    Government cannot now claim any right or title over
    that land. He further submits that in reply to an
    application under Right to Information Act, Land
    Record Officer has informed that land comprised in
    Khasra No. 1298-1331 in Village Rikholi is outside the
    limits of Municipality Mussoorie and there is no
    notification issued under Municipalities Act, bringing
    village Rikholi or part thereof within limits of Nagar
    Palika Parishad, Mussoorie. He further submits that
    respondent no. 4 has stated in his reply that the
    property purchased by petitioner was not the subject
    matter of land acquisition.

    29. Per contra, learned counsel for respondents
    submit that the locality where Khasra No. 1298-1331
    are situate, is part of Park-Estate, which is within
    limits of Nagar Palika Parishad, Mussoorie ever since
    it was constituted in the year 1933. He further
    submits that District Magistrate informed the
    petitioner, vide order dated 22.04.2013 that the land
    in question was acquired by the State for a public
    purpose and that land has been recorded in revenue
    record in the name of Tourism Department of State
    Government. Thus, it is contended by learned counsel
    for respondents that the prayer for appointing
    Advocate Commissioner is misconceived and having
    regard to the issue involved in the writ petition,
    appointment of Advocate Commissioner would be
    unwarranted.

    11

    30. This Court is of the considered opinion that
    having regard to the issues raised and relief claimed
    in the writ petition, appointment of Advocate
    Commissioner would be unwarranted. Petitioner
    claims to have purchased land comprised in different
    khasra numbers by separate sale deeds; the
    description of the khasra numbers and sale deeds is
    given in paragraph no. 6 of the writ petition. Since
    there is no confusion or ambiguity in the mind of the
    petitioner regarding identity of the land purchased by
    him, therefore, issuing Commission to get a report
    would not be warranted. For deciding the issues
    raised in the writ petition, report of the Advocate
    Commissioner would not be needed.

    31. Learned counsel for the respondents are
    right in submitting that Advocate Commissioner
    cannot be appointed in order to collect evidence.
    Since there is no ambiguity regarding identity of the
    land in question and other issues can be decided by
    this Court based on documentary evidence available
    on record, therefore, the prayer for appointing
    Advocate Commissioner is liable to be rejected and is
    hereby rejected. Miscellaneous Application (IA No.
    19659 of 2018) is rejected.

    32. List on 28.05.2026.

    (Manoj Kumar Tiwari, J.)
    20.04.2026

    Navin

    12



    Source link

    LEAVE A REPLY

    Please enter your comment!
    Please enter your name here