Delhi Jal Board vs M/S Metrro Waste Handling Private … on 20 April, 2026

    0
    34
    ADVERTISEMENT

    Delhi High Court

    Delhi Jal Board vs M/S Metrro Waste Handling Private … on 20 April, 2026

                       *      IN THE HIGH COURTOF DELHI AT NEW DELHI
                       %                              Judgment reserved on: 02.04.2026
                                                   Judgment pronounced on: 20.04.2026
                       +      O.M.P. (COMM) 277/2025 & I.A. 17526/2025
    
                              DELHI JAL BOARD                                .....Petitioner
                                            Through:         Mr. Jayant Mehta, Sr. Adv.
                                                             with Mr. Tushar Sannu, Mr.
                                                             Malvi Balyan, Mr. Fajallu
                                                             Rehman & Mr. Pallav Arora,
                                                             Advs.
                                                 versus
    
                              M/S METRRO WASTE HANDLING PRIVATE
                              LIMITED                          .....Respondent
                                           Through: Mr. Akshay Makhija, Sr. Adv.
                                                    with Mr. Tarang Gupta & Ms.
                                                    Shreya Sharma, Advs.
    
                              CORAM:
                              HON'BLE MR. JUSTICE AVNEESH JHINGAN
                                                 JUDGMENT
    

    1. The petition under section 34 of the Arbitration and
    Conciliation Act, 1996 (for short ‗the Act’) is filed challenging the
    arbitral award dated 08.04.2025.

    Brief Facts

    SPONSORED

    2. The brief facts are that on 26.04.2012, the petitioner/Delhi Jal
    Board (for short ‗DJB’) issued a Notice Inviting Tender (for short
    ‗NIT’) for hiring and O&M of jetting-cum-suction-cum-recycling
    sewer cleaning machines. The respondent, M/S Metrro Waste
    Handling Private Limited (for short ‗MWHPL’) along with M/s City

    Signature Not Verified
    O.M.P. (COMM) 277/2025 Page 1 of 33
    Signed By:CHANCHAL
    Signing Date:20.04.2026
    18:51:13
    Lifeline Travels Private Limited entered into a Joint Venture
    Agreement dated 30.10.2012 and bidded as a consortium. DJB on
    11.04.2013 issued a Letter of Intent (for short ‗LOI’). On 27.05.2013,
    the project was awarded for five machines as per the terms and
    conditions of the Work Order dated 06.05.2013, at the rate of
    Rs.7101/- per hour plus taxes and for a period of seven years with
    additional six months for supply of machines. The cost of the work
    was Rs.59,64,84,000/-.

    2.1 On 24.08.2017, MWHPL proposed deployment of five
    additional machines. DJB issued a LOI dated 09.10.2017 and
    MWHPL on 12.10.2017 gave a Letter of Acceptance (for short
    ‗LOA’). Work Order dated 30.10.2017 was issued and a contract
    dated 17.11.2017 was executed, adopting the earlier contractual terms.
    2.2 MWHPL on 11.05.2022 requested the DJB for enhancement of
    the budget as the amount stipulated was likely to be exhausted by
    August-September, 2022. Vide communication dated 01.11.2022,
    DJB advised MWHPL that the agreed contract price was fully utilized
    and work be carried out only within the cap. MWHPL suspended
    operations on 02.11.2022 and requested that the pending dues be
    cleared.

    2.3 On 23.01.2023, MWHPL aggrieved of delay in revision of the
    allocated budget filed writ petition (W.P. (C) No. 985 of 2023). On
    20.02.2023, DJB closed the contract stating that the scope of work
    was completed and requested for bill. The writ petition was dismissed
    as withdrawn and the parties were relegated to the Dispute
    Adjudication Board for amicable resolution. MWHPL issued a notice

    Signature Not Verified
    O.M.P. (COMM) 277/2025 Page 2 of 33
    Signed By:CHANCHAL
    Signing Date:20.04.2026
    18:51:13
    dated 24.02.2023 invoking arbitration. Petition filed by MWHPL
    under Section 9 of the Act was disposed of on 29.03.2023. The
    conciliation proceedings failed and were closed on 20.04.2023. On
    reference, the main issue before the arbitrator was whether the
    contract was an item rate contract operative for a period of seven years
    or it was till the exhaustion of the contract price of Rs.59,64,84,000.
    In view of fact that the tenure of contract had expired during pendency
    of arbitration proceedings, the declaratory reliefs (Claims No. I – VI

    (ii)) seeking declaration against DJB were not pressed by MWHPL.
    DJB aggrieved of the award dated 08.04.2025 allowing the following
    claims of MWHPL filed the present petition:

                                            Claim                          Amount Awarded
                              Alternative Claim VI                  Rs.     18,46,26,000/-       (with
                              Claim     towards        Damages interest at 10% per annum from
    

    calculated as per minimum 01.05.2025 till payment)
    assurance from Feb, 2022 to
    April, 2025
    Claim VII Rs.2,83,79,759/-

                              Claim        towards       interest
                              applicable        for     delayed
                              payments.
                              Claim VIII                            Rs.3,49,37,191/- (with interest
                              Claim     towards       escalation/ at      10%   per    annum     from
                              price variation                       28.07.2023 till payment.)
                              Claim IX                              Rs.2,36,70,000/- (with interest
    
    
    
    Signature Not Verified
                       O.M.P. (COMM) 277/2025                                          Page 3 of 33
    Signed By:CHANCHAL
    Signing Date:20.04.2026
    18:51:13
                               Claim      towards    minimum at       10%    per   annum         from
                              assured    payment    for    the 20.02.2023 till payment)
                              months     of     Nov,2022    to
                              Feb,2023
                              Claim X                            Rs.1,74,47,808/- (with interest
                              Claim     towards    additional at 10% per annum from April
                              labour deployed                    2018 till payment)
                              Claim XII                          Arbitral fee paid to DIAC along
                              Litigation Cost                    with legal fee of Rs.10,00,000/-
    
                       Submissions of the Petitioner
    

    3. Learned senior counsel for DJB contended that the contract
    documents, work order, LOI and related records reflect the total
    contract value of Rs.59,64,84,000/- which was to be paid over seven
    years and the expression ‗minimum’ was not in relation to the contract
    value in the documents. The contention is that clause II of the Special
    Conditions of the Contract (for short ‗SCC’) stipulates that the
    vehicles shall be available for at least twenty five days a month and
    will be hired for a minimum two hundred hours per month but the
    condition was not absolute and in case of deployment of the machines
    for less than eight hours a day the payment on pro-rata basis has to be
    made. MWHPL received the assured amount in four years and seven
    months instead of seven years. MWHPL suspended the work on being
    informed on 01.11.2022 that the total contract value stood exhausted
    and the work was to be done within the upper cap. The work was
    closed vide order dated 20.02.2023. The contention is that the tribunal

    Signature Not Verified
    O.M.P. (COMM) 277/2025 Page 4 of 33
    Signed By:CHANCHAL
    Signing Date:20.04.2026
    18:51:13
    erred in concluding that the contract was an item rate and not a lump
    sum contract. It is emphasised that internal departmental
    communications have no sanctity. Reliance is placed upon Konkan
    Railway Corporation Ltd. v. SRC Company Infra Pvt. Ltd.
    , 2025
    SCC OnLine Bombay 4438.

    3.1 Clause 11.3 of the General Conditions of Contract (for short
    ‗GCC’) is relied upon to contend that DJB had the power to cancel the
    contract wholly or in part.

    3.2 The damages awarded of Rs.18,46,26,000/- are challenged
    being contrary to Sections 73 and 74 of the Indian Contract Act, 1872
    (for short ‗Contract Act‘) having been awarded solely on the basis of
    calculations furnished by MWHPL and not substantiated by evidence
    of actual loss or injury. Reliance is placed upon the decisions of the
    Supreme Court in Kailash Nath Associates v. Delhi Development
    Authority & Anr.
    , (2015) 4 SCC 136, Unibros v. All India Radio,
    2023 SCC OnLine SC 1366 and Batliboi Environmental Engineers
    Limited v. Hindustan Petroleum Corporation Limited & Anr.
    ,
    2023 SCC OnLine SC 1208. It is canvassed that there is no discussion
    of nature and quantum of loss. Moreover, the turnover was awarded as
    damages without deducting operating costs. The findings that the
    machines used were tailor made are refuted relying upon the cross-
    examination of CW-1 wherein it was stated that the machines were
    deployed elsewhere post-termination. The grievance is that the
    evidence of GPS tracking charts to support the plea that the machines
    were being used elsewhere was brushed aside by the tribunal. It is
    submitted that MWHPL had changed the password of GPS and DJB

    Signature Not Verified
    O.M.P. (COMM) 277/2025 Page 5 of 33
    Signed By:CHANCHAL
    Signing Date:20.04.2026
    18:51:13
    was curtailed from having access to the subsequent movement.
    MWHPL continued to submit monthly bills after February, 2023 but
    withheld the GPS data or proof of zero movement of the vehicles.
    3.3 The submission is that the damages awarded for the period of
    suspension i.e. November, 2022 to February, 2023 along with interest
    at the rate of ten percent per annum are on the same pedestal as the
    damages awarded for the post-termination period.
    3.4 The amount awarded for deployment of additional labour along
    with interest at the rate of ten percent per annum is stated to be
    contrary to Section 73 of the Contract Act. MWHPL failed to prove
    actual expenditure and the tribunal relied upon self-serving extracts of
    ledger produced by MWHPL. Clause III of the SCC is relied upon to
    contend that labour in abnormal circumstances was to be provided by
    DJB. It is argued that grant of interest on the delayed payments from
    ninety-first day of issuance of invoice is contrary to the clause 12.2.2
    of the GCC wherein it is provided for interest after ninety days from
    the date of pay order. Reliance is placed upon the decision of the
    Supreme Court in Union of India & Ors. v. Larsen & Tubro Ltd.,
    2026 SCC OnLine SC 327 to contend that awards contrary to the
    terms of the contract are patently illegal.

    3.5 It is submitted that the escalation charges were ordered to be
    released without MWHPL proving the escalation of prices and interest
    awarded thereon is beyond the terms of the contract. Lastly, the
    litigation costs awarded are unsupported by evidence and contrary to
    the contract.

    Signature Not Verified
    O.M.P. (COMM) 277/2025 Page 6 of 33
    Signed By:CHANCHAL
    Signing Date:20.04.2026
    18:51:13

    Submissions of the Respondent

    4. Per contra the arbitrator rightly held the contract to be an item
    rate and not a lump sum contract. The tender notice invited item rate
    bids; the additional terms of the contract provided that the contract
    was for seven years and could be extended; there was a provision for
    increasing deployment of machines and the rate quoted was on per
    hour basis; the SCC stipulated that the contract period was for seven
    years from the deployment of machines; the nature of the work was
    such that there could not be prior calculation of the lump sum contract
    price; DJB assured in contract that machines would be hired for two
    hundred hours per month and the amount calculated on that basis was
    a mutually agreed genuine pre-estimated loss and damage; the
    contract mandated pro-rata payments based on the total number of
    actual working hours each month; the invoices were to be raised on an
    hourly basis; there was a clause providing for payment towards
    escalation charges of fuel, labour and material as per fluctuations in
    cost; and clause 12.6 of the GCC declared that the contract was not a
    lump sum contract.

    4.1 The conduct of the petitioner in enhancing the budgetary
    allocation of the initial contract and forwarding proposals to higher
    authorities for enhancement of the budget of the contract in hand is
    relied upon to emphasise that contract was an item rate and not a lump
    sum contract. The decisions of this court dated 29.03.2023 disposing
    of application under Section 9 of the Act is relied upon to substantiate
    that the contract was an item rate contract. The decision of the

    Signature Not Verified
    O.M.P. (COMM) 277/2025 Page 7 of 33
    Signed By:CHANCHAL
    Signing Date:20.04.2026
    18:51:13
    Supreme Court in Godhra Electricity Co. Ltd. & Anr. v. State of
    Gujarat & Anr.
    , (1975) 1 SCC 199 and Transmission Corporation
    of Andhra Pradesh Ltd. & Ors. v. GMR Vemagiri Power
    Generation Ltd. & Anr.
    , (2018) 3 SCC 716 are relied to submit that
    assistance in interpreting the contract can be taken from the conduct of
    the parties and their understanding of the terms. The decision of the
    Supreme Court in Haris Marine Products v. Export Credit
    Guarantee Corporation (ECGC) Limited
    , (2022) 20 SCC 776 is
    relied upon to buttress the argument that ambiguity in the terms of the
    contract is to be construed against the drafter.

    4.2 The decision of the Supreme Court in Prakash Atlanta (JV) v.
    National Highways Authority of India
    , 2026 SCC OnLine SC 98 is
    relied upon to argue that interpretation of the clauses of contract lies
    within the domain of the arbitrator and no interference is warranted
    unless the conclusion arrived at is perverse.

    4.3 The reliance on clause 11.3 of the GCC to contend that there
    was a power to wholly or partly terminate the contract is refuted
    stating that termination could have been effected only for the reasons
    mentioned in clause 11.1 of the GCC which are not applicable to the
    facts of this case.

    4.4 It is submitted that damages of Rs.18,46,26,000/- were based on
    a genuine pre-estimate of loss agreed between the parties based upon
    assurance of hiring each machine for two hundred hours per month
    and considering that machines were tailor made. Submission is that
    the vehicles compliant with BS-IV norms were procured after
    obtaining special permission from the National Green tribunal but

    Signature Not Verified
    O.M.P. (COMM) 277/2025 Page 8 of 33
    Signed By:CHANCHAL
    Signing Date:20.04.2026
    18:51:13
    w.e.f. 01.04.2020 the emission norms were revised to BS-VI rendering
    the vehicles unfit for use. DJB failed to prove that the machines could
    be deployed elsewhere in Delhi. The argument is damages were
    rightly awarded by tribunal. Reliance is placed upon the decisions in
    Desh Raj & Ors. v. Rohtash Singh, 2023 (3) SCC 714, M/s Pawan
    Hans Helicopters Ltd. v. M/s Maritime Energy Heli Air Services
    Pvt. Ltd., 2017 (164) DRJ 703 and XL Energy Limited v.
    Mahanagar Telehpone Nigam Limited, 2018 SCC Online Del 9109
    in support of the proposition that in case of an agreed pre-estimate loss
    the actual damages need not be proved. The award of the damages for
    the suspension period is defended by similar arguments.
    4.5 Clause III of the SCC is pressed into service to contend that
    MWHPL was to deploy a driver, helper and supervisor and DJB had
    to provide staff for other activities such as removing the manholes,
    desilting of the manholes (in abnormal circumstances). The
    submission is that conclusion of the tribunal allowing claim for
    additional deployment of labour is reasonable and calls for no
    interference. It is canvassed that the deployment of additional labour
    was supported by log sheets counter-signed by the parties though the
    tribunal inadvertently recorded them as undisputed invoices. The
    contention is that the ledger along with the certificate dated
    30.07.2024 issued by the Chartered Accountant (for short ‗CA’)
    proved payment of salaries yet the tribunal allowed the claim relying
    onminimum wages and not on the amount claimed.

    Signature Not Verified
    O.M.P. (COMM) 277/2025 Page 9 of 33
    Signed By:CHANCHAL
    Signing Date:20.04.2026
    18:51:13

    4.6 Clause 12.2.2 of the GCC providing interest at the rate of ten
    percent per annum payable from ninety first day of the pay order is
    relied upon to defend the award of interest.

    4.7 The submission is that the principal amount of escalation bills
    was not challenged before the tribunal and only the award of interest
    at the rate of ten percent per annum was contested. It is submitted that
    clause 12.2.2 of the GCC provides for ten percent interest on running
    monthly invoices and that very rate has been applied by the tribunal.
    Reliance is on Section 31A (2) of the Act to defend the award of costs.

    5. Heard learned counsel for the parties. Albeit, the written
    submissions were filed but the matter was argued at length and no
    issue other than those noted above was pressed.

    Issues for Consideration
    i. Whether the contract between the parties was an item rate
    contract for a period of seven years or was limited to the total
    contract value of Rs.59,64,84,000/-.

    ii. Whether the termination of the contract by the petitioner was in
    accordance with the terms of the contract.

    iii. Whether the respondent was entitled to damages for the period
    of suspension and for the remaining tenure of the contract.
    iv. Whether the claims for deployment of additional labour and
    interest awarded thereon and also on delayed payments and
    escalation charges call for interference under Section 34 of the
    Act.

    Signature Not Verified
    O.M.P. (COMM) 277/2025 Page 10 of 33
    Signed By:CHANCHAL
    Signing Date:20.04.2026
    18:51:13

    Analysis

    6. MWHPL after termination of the contract invoked the
    arbitration. Apart from the issues now raised declaratory reliefs were
    sought however, at the time of final arguments considering that the
    tenure of the contract had expired the declaratory reliefs were not
    pressed and only alternative reliefs were prayed for. The tribunal
    decided that the contract was an item rate contract and not a lump sum
    contract. The termination of the contract was held to be illegal.

    7. Before proceeding further, it would be relevant to note the
    clauses and relevant portions of the documents relied upon by both
    sides.

    7.1 Work orders dated 06.05.2013 and 30.10.2017 are reproduced
    below:

    ―The earlier work order dated 06.05.2013 reads as under:

    M/s Metrro Waste Handling Pvt. Ltd. & M/S City Life
    Line Travels Pvt. Ltd. (JV) 8551/2, Roshanara Road,
    Delhi- 110007
    Sub: Hiring and O & M of 5 Nos. jetting cum suction
    recycling sewer cleaning machines to operate in the streets
    including narrow lanes of Delhi
    Amount put the tender
    O/o Age Item Rate
    Above/below/item rate
    Total Cost Rs. 59,64,84,000/-

                                Completion Period           6 months for supply of
                                                            machines plus 7 Yrs. For
                                                            hiring of machine
                                Head f Account              Trunk Peripheral Sewer &
                                                            Gravity duct.
    
    
    
    Signature Not Verified
                       O.M.P. (COMM) 277/2025                                      Page 11 of 33
    Signed By:CHANCHAL
    Signing Date:20.04.2026
    18:51:13
    

    With reference to your letter dated 30.10.12 and
    negotiation held on 20.03.13 for the above said work. Your
    rates has been accepted by the Competent Authority. You
    are therefore requested to start the work under the
    instructions of Assistant Engineer (E&M)- III incharge of
    this work and complete the same as per completion period
    stated above. The date of start of work shall be reckoned
    from 7 day of issue of work order.

    It should be noted that as and when orders are given for the
    execution of extra items, such orders be got confirmed in
    writing subsequently, so that extra items and rates be got
    settled & approved by the Competent Authority.‖
    xxx xxx xxx
    ―The work order of the instant case is dated 30.10.2017. The
    relevant extract of this document reads as under:
    ―NO: /DJB/2017-18//EE (West)-l/680 to 93
    Dated 30.10.2017
    Ms. Metrro Waste Handling Pvt. Ltd.

    & M/S City Life Line Travels Pvt. Ltd. (JV) 8551/2,
    Roshanara Road, Delhi-110007
    Name of work: Hiring and O&M of 5 Nos. jetting cum
    suction recycling sewer cleaning
    machines to operate in the streets
    including narrow lanes of Delhi
    Amount put together: Item rate
    Awarded Rate: Item rate
    Total contractual cost: Rs. 59,64,84,000/- plus GST as
    applicable

    Signature Not Verified
    O.M.P. (COMM) 277/2025 Page 12 of 33
    Signed By:CHANCHAL
    Signing Date:20.04.2026
    18:51:13
    Completion period: 06 Month for supply of machine
    Plus 7 years for hiring of
    machine
    Budget Head: Trunk Peripheral Sewer &
    Gravity Duct

    Performance Bank
    Guarantee @ 5%: Bearing B.G. 0301-BG-0017-17
    amounting to Rs. 85,21,200/-

    Dated 12.10.2017 validity Dt.

    30.09.2018
    Punjab & Sind Bank Roshanara
    Road, Delhi 110007.

    Sir
    With reference to your letter dated 24.08.2017 for the
    above said work. Your rate has been accepted by the
    Competent Authority. You are therefore requested to start
    the work under the instructions of Zonal Engineer VIII
    West in charge of this work and complete the same as per
    completion period stated above The date of start of work
    shall be reckoned from 30.04.2018 or date of actual supply
    of machine, whichever earlier.

    It should he noted that and when orders are given for the
    execution of extra items, such orders be got confirmed in
    writing subsequently, so that extra item and rates be got
    settled & approved by the competent Authority‖
    xxx xxx xxx
    7.2 Clauses 12.2.1, 12.2.2, 12.6 and 14.1 of the GCC are
    reproduced as follows:-

    Signature Not Verified
    O.M.P. (COMM) 277/2025 Page 13 of 33
    Signed By:CHANCHAL
    Signing Date:20.04.2026
    18:51:13

    ―12.2.1 The payment of the monthly running bill for the
    Works shall be released in 90 days from the date of
    recording of pay order. No excuse for delay in completion
    of work/prolongation of the Contract shall however be
    entertained on account of the reason of delay in payment.
    The bidder therefore, must take into consideration of its
    financial capability to carry out and to continue the work
    without any hindrances.‖
    ―12.2.2 In the event of the failure of Employer to release
    payment as per clause 12.2.1, the Employer shall be liable
    to pay interest @ 10% per annum computed for period
    beyond 90 days. Provided always, that no interest shall be
    payable on any amount disallowed or disputed by the
    Engineer-in- Charge or the Employer, even if such amount
    is later on determined to be payable to the Contractor, as a
    result of any process resorted to for the settlement of the
    dispute as per Contract.‖
    ―12.6 Lump sum provisions in a composite tender
    This Clause is not Applicable.‖
    ―14.0 Changes in Contract Price
    14.1 Payments due to variation in prices of material, POL
    and labour after receipt of tender
    If during the operative period of the Contract, there shall
    be any variation in the prices of material (not being the
    material supplied by Employer as under clause 9.1 and/or
    services rendered at fixed prices as under clause 9.5 and
    the material for which the price variation is being
    calculated for actual quantities used as under clause
    14.1.3) and/or in the wages of labour required for
    execution of.

    Works and/or in POL (fuel); the Contract Price shall be
    adjusted as per the provisions detailed below‖
    7.3 Clauses II, III and VI of the SCC are reproduced below:-

    ―II. Functional Duties:

    Signature Not Verified
    O.M.P. (COMM) 277/2025 Page 14 of 33
    Signed By:CHANCHAL
    Signing Date:20.04.2026
    18:51:13

    xxx xxx xxx
     The vehicle shall be available and fit for work for minimum
    25 days in a month. Delhi Jal Board will hire each machine
    for minimum total 200 hours per month (and minimum total

    8 hours per day normally) for the duration of the contract.
    200 hours includes time towards transportation & setting up
    and actual operation. Lunch hours (1-2 PM) will not be
    included in 200 hours. The time of operation will be decided
    by the Engineer-in-charge. However if due to any
    extraordinary requirement of Delhi Jal Board, a machine is
    deployed for less than 8 hours, the payment will still be
    done on pro-rata basis.‖
    ―III. Staff:

     The firm will engage the required staff for operation
    and maintenance of each machine. The vehicle Driver
    operator should be well trained, well behaved, free
    from intoxication and have proper driving licence (as
    per RTA requirement).

     DJB will provide the labour/staff for other activities
    e.g. removal of the manhole, de-siliting of manhole
    (for abnormal circumstances e.g. if filled-up with
    heavy construction material which can’t be removed by
    the machine) if required. The location of the site will
    be decided by the DJB staff. The tenderer shall depute
    the machines at various zones as per the directions of
    the Engineer-in-charge.

     Minimum Manpower deployment are as follows:

    Operation Crew:

                                     Trained Driver                   1 Nos./Machine
                                     Operator                         1 Nos./Machine
                                     1 Supervisor for entire fleet‖
    
                               ―VI. Payment:
    
    
    
    Signature Not Verified
                       O.M.P. (COMM) 277/2025                                     Page 15 of 33
    Signed By:CHANCHAL
    Signing Date:20.04.2026
    18:51:13
                                      xxx                  xxx              xxx
    

    o The payment will be made as per actual hours (transport
    hours + operation hours) obtained from log sheets. The
    working hours will also be confirmed by the GPS system/
    tele-metering record (hour meter) / log-sheet etc. The
    decision of the concerned EE (Civil) will be final.

    xxx xxx xxx
    o The payment will be made on pro-rata basis based on the
    total no. or working hours (or fraction of hour upto minutes)
    of machine @ per hour rate quoted/accepted by the
    contractor/department.‖
    Nature Of Contract

    8. The tribunal noted that the contract was executed on 17.11.2017
    but the LOI and the work order were integral parts of it. The
    ‗completion date’ mentioned in the Work Order stipulated a period of
    seven years. The terms and conditions of the present contract were
    verbatim with the earlier Work Order dated 06.05.2013 and that
    contract was an ‗item rate’. The work detailed in the NIT indicated the
    contract period to be seven years after actual deployment of machines.

    Clause 12.6 of the GCC states that lump sum provisions were not
    applicable. Clause 14 of the GCC provides for payment of escalation
    in prices. The definitions of ‗stipulated date of completion’ and
    ‗contract price’ were relied upon to conclude that the contract was an
    item rate contract for a period of seven years.

    9. The minutes of meetings dated 29.09.2012, 19.03.2012,
    20.03.2013, 01.04.2013 and 11.04.2013 and communications
    exchanged inter se the officials of DJB were relied upon that as per
    the understanding of the petitioner the contract was an item rate. It

    Signature Not Verified
    O.M.P. (COMM) 277/2025 Page 16 of 33
    Signed By:CHANCHAL
    Signing Date:20.04.2026
    18:51:13
    was further considered that in the earlier contract of 2013, the budget
    allocation was revised and in the present contract proposals were
    submitted to higher authorities for revision of the budget. The prima
    facie findings recorded by this court while deciding application under
    Section 9 of the Act that the contract was an item rate and not a lump
    sum contract were noted though rightly considered not to be
    conclusive. It was held that the contract was for a fixed period of
    seven years and it was an item rate and not a lump sum contract.

    10. It is an undisputed fact that the tender was invited on an item
    rate basis. The completion period was stated to be of seven years
    which could have been extended. The bid was quoted on per working
    hour basis. There was an assurance of minimum hiring of the
    machines for two hundred hours per month. The payments were to be
    made on actual working hours and SCC provided for payment on a
    pro-rata basis in case the deployment are less than eight hours a day.

    11. The mentioning of total contract value and usage of the
    expression ‗minimum’ for assuring deployment of the machines for
    two hundred hours per month and availability for at least twenty five
    days a month shall not be the only factors to determine the nature of
    the contract. There cannot be quarrel with the proposition that contract
    is to be read as whole and moreover, in case in hand the work order
    and LOI are integral part of the contract.

    12. The internal communications of the petitioner are not binding
    but supports that the view taken by the tribunal to be plausible one.
    The possibility of another view is not a ground under Section 34 of the
    Act for setting aside the impugned award. The NIT, LOI, GCC and

    Signature Not Verified
    O.M.P. (COMM) 277/2025 Page 17 of 33
    Signed By:CHANCHAL
    Signing Date:20.04.2026
    18:51:13
    SCC were considered for holding that the work awarded was an item
    rate. The interpretation of clauses of contract by the arbitrator cannot
    be interfered with under Section 34 of the Act unless the relevant
    clauses have been ignored, the contractual terms are rewritten or the
    conclusion arrived at is perverse and it is not so in case in hand
    making no case for interference under Section 34 of the Act.
    Termination of Contract

    13. The tribunal rightly concluded that the eventualities mentioned
    in clause 11.1 of the GCC for termination of the contract never existed
    and the termination of the contract was illegal. The contention of the
    learned senior counsel for the petitioner that under clause 11.3 of the
    GCC there was a power to terminate the contract is ill-founded.
    Clauses 11.1 and 11.3 of the GCC are to be read in conjunction and
    clause 11.3 of the GCC empowers DJB to wholly or in part terminate
    the contract applies only if the circumstances mentioned in clause 11.1
    of the GCC occur.

    Scope under Section 34 of the Act

    14. The scope of interference under Section 34 of the Act is well
    settled that interpretation of the clauses of the contract falls within the
    domain of the arbitrator and no interference is to be made if the
    conclusion arrived at is plausible and interference is to be made only
    in case of perversity. Reference is made to the following decisions of
    the Supreme Court.

    14.1 In Prakash Atlanta (JV) (Supra) it was held as under:

    ―52. ……Having considered the arbitral awards passed by
    the arbitral tribunals in the five appeals filed by NHAI, we

    Signature Not Verified
    O.M.P. (COMM) 277/2025 Page 18 of 33
    Signed By:CHANCHAL
    Signing Date:20.04.2026
    18:51:13
    find that the interpretation and construction of those terms
    and clauses by the arbitral tribunals cannot be said to be
    arbitrary, perverse or patently illegal. Given the situation
    obtaining in relation to the two Acts at the relevant time,
    the arbitral awards cannot be said to have violated the
    public policy of India or be in breach of Section 28(1)(a)
    of the Arbitration Act. Once the view taken by the arbitral
    tribunal is found to be a plausible and possible one on facts
    and not an unreasonable one, it is not for the Courts, under
    Sections 34 or 37 of the Arbitration Act, or for this Court
    to sit in appeal or substitute its view for that of the arbitral
    tribunal.‖
    14.2 The Supreme Court in Ramesh Kumar Jain vs. Bharat
    Aluminium Company Limited
    , 2025 SCC OnLine SC 2857 held as
    under:

    ―28. The bare perusal of section 34 mandates a narrow lens
    of supervisory jurisdiction to set aside the arbitral award
    strictly on the grounds and parameters enumerated in sub-
    section (2) & (3) thereof. The interference is permitted
    where the award is found to be in contravention to public
    policy of India; is contrary to the fundamental policy of
    Indian Law; or offends the most basic notions of morality
    or justice. Hence, a plain and purposive reading of the
    section 34 makes it abundantly clear that the scope of
    interference by a judicial body is extremely narrow. It is a
    settled proposition of law as has been constantly observed
    by this court and we reiterate, the courts exercising
    jurisdiction under section 34 do not sit in appeal over the
    arbitral award hence they are not expected to examine the
    legality, reasonableness or correctness of findings on facts
    or law unless they come under any of grounds mandated in
    the said provision. In ONGC Limited. v. Saw Pipes
    Limited14, this court held that an award can be set aside
    under Section 34 on the following grounds: ―(a)
    contravention of fundamental policy of Indian law; or (b)

    Signature Not Verified
    O.M.P. (COMM) 277/2025 Page 19 of 33
    Signed By:CHANCHAL
    Signing Date:20.04.2026
    18:51:13
    the interest of India; or (c) justice or morality, or (d) in
    addition, if it is patently illegal.‖
    14.3 In Consolidated Construction Consortium Limited vs.
    Software Technology Parks of India
    , (2025) 7 SCC 757 it was held
    as under:

    ―46. Scope of Section 34 of the 1996 Act is now well
    crystallized by a plethora of judgments of this Court.
    Section 34 is not in the nature of an appellate provision. It
    provides for setting aside an arbitral award that too only on
    very limited grounds i.e. as those contained in Sub-
    sections (2) and (2-A) of Section 34. It is the only remedy
    for setting aside an arbitral award. An arbitral award is not
    liable to be interfered with only on the ground that the
    award is illegal or is erroneous in law which would require
    re-appraisal of the evidence adduced before the arbitral
    tribunal. If two views are possible, there is no scope for the
    court to re-appraise the evidence and to take the view other
    than the one taken by the arbitrator. The view taken by the
    arbitral tribunal is ordinarily to be accepted and allowed to
    prevail. Thus, the scope of interference in arbitral matters
    is only confined to the extent envisaged Under Section 34
    of the Act. The court exercising powers Under Section 34
    has perforce to limit its jurisdiction within the four corners
    of Section 34. It cannot travel beyond Section 34. Thus,
    proceedings Under Section 34 are summary in nature and
    not like a full-fledged civil suit or a civil appeal. The
    award as such cannot be touched unless it is contrary to the
    substantive provisions of law or Section 34 of the 1996
    Act or the terms of the agreement.‖
    Damages for Period of Suspension and Balance Period of Contract

    15. The contract having been held to be an item rate contract and
    the termination to be illegal, the question surviving is as to whether
    MWHPL was entitled to damages for the remaining period of the term

    Signature Not Verified
    O.M.P. (COMM) 277/2025 Page 20 of 33
    Signed By:CHANCHAL
    Signing Date:20.04.2026
    18:51:13
    of the contract i.e. approximately twenty six months and the
    quantification of damages.

    16. From the reading of the terms of the contract dated 17.11.2017,
    SCC, LOI and work order it is evident that the contract was for the
    total cost of Rs.59,64,84,000/-. Clause II of the SCC stipulates that the
    vehicles shall remain available for a minimum of twenty-five days a
    month and DJB will hire each machine for a minimum of two hundred
    hours per month for the duration of the contract. The calculation of the
    total cost of the contract which was extendable by DJB has been made
    taking into account the minimum two hundred hiring hours per month
    for seven years and for five machines. In mathematical terms: 7101
    (minimum rate per hour per machine) x 25 (minimum days per month)
    x 8 (minimum hours per day) x 84 (duration of the contract in month)
    x 5 (number of vehicles).

    17. The contract was an item rate contract yet from reading of
    contract in entirety, an assurance to MWHPL emerges that by hiring
    of the five machines for seven years there would be a minimum
    turnover of Rs.59,64,84,000/-. It is an undisputed fact that this amount
    was paid to MWHPL prior to termination i.e. on completion of four
    years and seven months. Clause II of the SCC provided that in case of
    hiring of the machines for less than eight hour a day the payment
    would be made on pro-rata basis. Further clause VI of the SCC
    provided that the payment was to be made on actual usage. The
    conclusion of the arbitrator that in spite of the additional working
    hours in the four years seven months period, MWHPL was entitled to
    a minimum of two hundred hiring hours per month per machine for

    Signature Not Verified
    O.M.P. (COMM) 277/2025 Page 21 of 33
    Signed By:CHANCHAL
    Signing Date:20.04.2026
    18:51:13
    seven years renders the clause of pro-rata payment and payment on
    actual usage otiose.

    18. Another angle to be considered is that in the absence of proof of
    actual loss suffered MWHPL cannot claim damages due to premature
    termination of the contract by DJB, more so, when the minimum
    assured turnover to MWHPL upon completion of the contract was
    paid prior to termination.

    19. There is a dispute raised with regard to whether the machines
    where tailor-made; the machines could have been put to use for
    cleaning other sewers; and one of the machines was actually put to
    usage after the termination of the contract but for claiming damages
    under Sections 73 and 74 of the Contract Act, actual loss or damage
    suffered has to be proved. The contention of the learned senior
    counsel for the respondent that damages have been calculated on the
    basis of a formula of genuine pre-estimate of loss provided in the
    contract lacks merit. There is neither pre-determination of liquidated
    damages nor a formula has been provided for doing so. The clause for
    minimum hiring hours was only to ensure the bidder that minimum
    business that would accrue on making an investment. At this stage, it
    must be added albeit, the total contract value could have been
    extended by the petitioner but that the respondent had no right to
    claim enhancement of the contract amount.

    20. The law is well settled that for claiming damages under
    Sections 73 and 74 of the Contract Act the claimant has to prove
    actual loss suffered and in case it is not possible to prove loss, a

    Signature Not Verified
    O.M.P. (COMM) 277/2025 Page 22 of 33
    Signed By:CHANCHAL
    Signing Date:20.04.2026
    18:51:13
    reasonable amount of damages is to be assessed. Reference in this
    regard be made to the following judgments:

    20.1 The Supreme Court in Unibros (supra) while dealing with a
    claim for redressal of loss of profit made under Section 73 of the
    Contract Act arising from prolongation of the contract held:

    ―19. The law, as it should stand thus, is that for claims
    related to loss of profit, profitability or opportunities to
    succeed, one would be required to establish the
    following conditions : first, there was a delay in the
    completion of the contract; second, such delay is not
    attributable to the claimant; third, the claimant’s status
    as an established contractor, handling substantial
    projects; and fourth, credible evidence to substantiate
    the claim of loss of profitability. On perusal of the
    records, we are satisfied that the fourth condition,
    namely, the evidence to substantiate the claim of loss
    of profitability remains unfulfilled in the present case.‖
    20.2. The Supreme Court in Kailash Nath Associates (supra) held:

    ―43.6. The expression ―whether or not actual damage
    or loss is proved to have been caused thereby‖ means
    that where it is possible to prove actual damage or loss,
    such proof is not dispensed with. It is only in cases
    where damage or loss is difficult or impossible to
    prove that the liquidated amount named in the contract,
    if a genuine pre-estimate of damage or loss, can be
    awarded.‖
    20.3 The Supreme Court in State of Rajasthan v. Ferro Concrete
    Construction (P) Ltd.
    , (2009) 12 SCC 1 held:

    ―55.While the quantum of evidence required to accept
    a claim may be a matter within the exclusive
    jurisdiction of the arbitrator to decide, if there was no
    evidence at all and if the arbitrator makes an award of
    the amount claimed in the claim statement, merely on

    Signature Not Verified
    O.M.P. (COMM) 277/2025 Page 23 of 33
    Signed By:CHANCHAL
    Signing Date:20.04.2026
    18:51:13
    the basis of the claim statement without anything more,
    it has to be held that the award on that account would
    be invalid. Suffice it to say that the entire award under
    this head is wholly illegal and beyond the jurisdiction
    of the arbitrator, and wholly unsustainable.‖
    20.4 The Division Bench of this court in Tower Vision India (P)
    Ltd. v. Procall (P) Ltd.
    , 2012 SCC OnLine Del 4396 held:

    ―16. Consequence for breach of the contract are
    provided in Chapter VI of the Indian Contract Act,
    1872
    , which contains three sections, namely, section
    73
    to section 75. As per section 73 of the Indian
    Contract Act, the party who suffers by the breach of
    contract is entitled to receive from the defaulting party,
    compensation for any loss or damage caused to him by
    such breach, which naturally arose in usual course of
    things from such breach, or which the two parties knew
    when they make the contract to be likely the result of
    the breach of contract. This provision makes it clear
    that such compensation is not to be given for any
    remote or indirect loss or damage sustained by reason
    of the breach. The underlying principle enshrined in
    this section is that a mere breach of contract by a
    defaulting party would not entitle the other side to
    claim damages unless the said party has in fact suffered
    damages because of such breach. Loss or damage
    which is actually suffered as a result of breach has to
    be proved and the plaintiff is to be compensated to the
    extent of actual loss or damage suffered. When there is
    a breach of contract, the party who commits the breach
    does not eo instanti, i.e., at the instant incur any
    pecuniary obligation, nor does the party complaining
    of the breach becomes entitled to a debt due from the
    other party. The only right which the party aggrieved
    by the breach of the contract has is the right to sue for
    damages. No pecuniary liability thus arises till the
    court has determined that the party complaining of the
    breach is entitled to damages. The court in the first

    Signature Not Verified
    O.M.P. (COMM) 277/2025 Page 24 of 33
    Signed By:CHANCHAL
    Signing Date:20.04.2026
    18:51:13
    place must decide that the defendant is liable and then
    it should proceed to assess what the liability is. But, till
    that determination, there is no liability at all upon the
    defendant. The courts will give damages for breach of
    contract only by way of compensation for loss suffered
    and not by way of punishment. The rule applicable for
    determining the amount of damages for the breach of
    contract to perform a specified work is that the
    damages are to be assessed at the pecuniary amount of
    difference between the state of the plaintiff upon the
    breach of the contract and what it would have been if
    the contract had been performed and not the sum which
    it would cost to perform the contract, though in
    particular cases the result of either mode of calculation
    may be the same. The measure of compensation
    depends upon the circumstances of the case. The
    complained loss or claimed damage must be fairly
    attributed to the breach as a natural result or
    consequence of the same. The loss must be a real loss
    or actual damage and not merely a probable or a
    possible one. When it is not possible to calculate
    accurately or in a reasonable manner, the actual
    amount of loss incurred or when the plaintiff has not
    been able to prove the actual loss suffered, he will be,
    all the same, entitled to recover nominal damages for
    breach of contract. Where nominal damages only are to
    be awarded, the extent of the same should be estimated
    with reference to the facts and circumstances involved.

    The general principle to be borne in mind is that the
    injured party may be put in the same position as that he
    would have been if he had not sustained the wrong.‖
    (emphasis supplied)

    21. The arbitrator erred in awarding damages of the entire turnover
    for remaining period of contract, calculating it by minimum assured
    hiring of the machines. The amount to be received by MWHPL was
    the gross turnover and would include operational expenses,

    Signature Not Verified
    O.M.P. (COMM) 277/2025 Page 25 of 33
    Signed By:CHANCHAL
    Signing Date:20.04.2026
    18:51:13
    consumables and other overheads and does not denote the loss
    suffered.

    22. Another aspect is that making of a payment on actual usage
    basis and on pro-rata basis in case of hiring of the machine for less
    than eight hours a day makes the contract flexible enough to adjust
    according to the situations arising at ground level, with the only
    condition that MWHPL shall get minimum Rs.59,64,84,000/- during
    the tenure of the contract. The award of damages in absence of
    evidence on record of actual loss suffered or a finding recorded that
    the loss suffered cannot be proved is in violation of Sections 73 and
    74 of the Contract Act and against public policy. The tribunal awarded
    damages without considering the value of the machines, the usage
    these were put to, loss of business and other factors. The gross amount
    to be received by MWHPL for remaining period of the contract,
    calculated with minimum hiring guarantee of two hundred working
    hours per month per machine in itself is not actual loss suffered by the
    respondent as only a percentage of turnover can be regarded as profit.

    23. It is trite law that, in case of termination of contract the
    aggrieved party is to be awarded damages to put it in the same
    position that it would have been in if the contract had been executed.
    However, the damages must be reasonable and the parties should not
    be allowed to make a windfall profit. The Supreme Court in Batliboi
    Environmental Engineers Ltd.
    (supra) held:

    ―16. This is without doubt, a sound legal and correct
    proposition. However, the computation of damages
    should not be whimsical and absurd resulting in a
    windfall and bounty for one party at the expense of the

    Signature Not Verified
    O.M.P. (COMM) 277/2025 Page 26 of 33
    Signed By:CHANCHAL
    Signing Date:20.04.2026
    18:51:13
    other. The computation of damages should not be
    disingenuous. The damages should commensurate with
    the loss sustained. In a claim for loss on account of delay
    in work attributable to the employer, the contractor is
    entitled to the loss sustained by the breach of contract to
    the extent and so far as money can compensate. The party
    should to be placed in the same situation, with the
    damages, as if the contract had been performed. The
    principle is that the sum of money awarded to the party
    who has suffered the injury, should be the same quantum
    as s/he would have earned or made, if s/he had not
    sustained the wrong for which s/he is getting
    compensated. [Robinson v. Harman, (1848) 1 Ex 850, at
    p. 855 and Livingstone v. Rawyards Coal Co., (1880) LR
    5 AC 25 (HL)]‖
    [emphasis supplied]

    23.1 Contrary to the settled principles governing the award of
    damages, the gross turnover for the remaining period of the contract
    was taken to be loss suffered by MWHPL. The awarding of damages
    without deducting expenses puts MWHPL in position of having a
    windfall gain rather than reimbursing the loss suffered. At cost of
    repetition MWHPL has already achieved the assured minimum
    business.

    24. The damages for the period the contract was suspended were
    awarded on the same basis and hence meet the same fate. The
    awarding of the damages is set aside.

    Grant of Interest on Delayed Payment

    25. Clauses 12.2.1 and 12.2.2 of the GCC provide that payment of
    interest at the rate of ten percent per annum is to be computed after
    ninety days of the pay order. The petitioner though set up a case that

    Signature Not Verified
    O.M.P. (COMM) 277/2025 Page 27 of 33
    Signed By:CHANCHAL
    Signing Date:20.04.2026
    18:51:13
    the ninety days is to be counted from the date of the issuance of the
    pay order but the information exclusively in the possession of the
    petitioner i.e. the date of pay order was not disclosed. Moreover, it
    was not substantiated that for payments made to MWHPL, pay orders
    were being issued. The emails exchanged between the parties were
    also relied upon by tribunal wherein the amounts calculated were
    inclusive of interest at the rate of ten percent per annum. The tribunal
    rightly granted interest at the rate of ten percent per annum from the
    ninety-first day of submission of the bills. The grant of interest is in
    consonance with clause 12.2.2 of the GCC and calls for no
    interference.

    Deployment of Additional Labour and Interest Thereon

    26. Clause III of the SCC provides for deployment of one trained
    driver, operator and supervisor. DJB had to provide labour for other
    activities such as removal of manhole and desilting of manhole (only
    in abnormal circumstances). The contention of learned senior counsel
    of the petitioner that the staff was to be deployed only in abnormal
    circumstances as evident from clause III of the SCC, is ill-founded.

    The arbitrator rightly held that the abnormal circumstances applied
    only to de-silting of the manholes and not for other activities to be
    done for example removal of manholes. The contention that the
    deployment of additional labour itself shall not entitle the respondent
    for payment unless actual wages paid are proved, is of no avail. SCC
    provides for the log sheets were to be maintained for deployment of
    labour and these were to be counter-signed by the parties. The
    respondent produced the counter signed log sheets, extracts of the

    Signature Not Verified
    O.M.P. (COMM) 277/2025 Page 28 of 33
    Signed By:CHANCHAL
    Signing Date:20.04.2026
    18:51:13
    ledger and a certificate of the CA to prove deployment of additional
    labour and wages paid. The counter-signatures on the log sheets for
    deployment of additional labour were not disputed by the petitioner.
    The extracts of ledger produced by the respondent were backed by
    certificate issued by the CA and the entries in the log sheets. The
    quality of evidence to be considered is in the domain of the tribunal.
    Supreme Court in Parsa Kente Collieries Limited v. Rajasthan
    Rajya Vidyut Utpadan Nigam Limited
    , (2019) 7 SCC 236 held that
    quality of evidence to be relied upon is a matter for consideration of
    arbitrator only. Relevant part is quoted below:

    ―9.1 ……… it is observed and held that an Arbitral Tribunal
    must decide in accordance with the terms of the contract,
    but if an Arbitrator construes a term of the contract in a
    reasonable manner, it will not mean that the award can be
    set aside on this ground. It is further observed and held that
    construction of the terms of a contract is primarily for an
    Arbitrator to decide unless the Arbitrator construes the
    contract in such a way that it could be said to be something
    that no fair-minded or reasonable person could do. It is
    further observed by this Court in the aforesaid decision in
    para 33 that when a court is applying the ―public policy‖
    test to an arbitration award, it does not act as a court of
    appeal and consequently errors of fact cannot be corrected.
    A possible view by the Arbitrator on facts has necessarily
    to pass muster as the Arbitrator is the ultimate master of
    the quantity and quality of evidence to be relied upon
    when he delivers his arbitral award. It is further observed
    that thus an award based on little evidence or on evidence
    which does not measure up in quality to a trained legal
    mind would not be held to be invalid on this score.‖
    (emphasis supplied)

    Signature Not Verified
    O.M.P. (COMM) 277/2025 Page 29 of 33
    Signed By:CHANCHAL
    Signing Date:20.04.2026
    18:51:13

    27. It would be relevant to note that the tribunal has not awarded
    the entire claim made for additional deployment of labour but
    considered the undisputed number of additional labour deployed and
    the minimum wages statutorily prescribed. Conclusion arrived at by
    the tribunal suffers from no legal error much less perversity. The
    claim awarded is upheld.

    28. The challenge to the grant of interest on the amount awarded for
    deployment of additional labour on the ground that there is no clause
    for grant of interest is noted to be rejected. The tribunal has given the
    basis of awarding interest at the rate of ten percent per annum which is
    equivalent to the rate agreed between the parties under clause 12.2.2
    of the GCC in case of delay in payment of bills. Moreover, there is no
    clause in the contract barring the grant of interest.
    Escalation Charges

    29. Clause 14.1 of the GCC read with Clause VII of the SCC
    provides for payment of escalation charges in case of price fluctuation
    in labour component, material and fuel. The claim for escalation of
    prices and the fact that fifty-six bills on account of price variation
    were submitted by the respondent from April 2018 to December 2022
    were not disputed before the tribunal. The only defence pressed was
    that there was deficiency in the documents submitted. The tribunal in
    the facts and circumstances of the case rightly held the respondent to
    be entitled to payment for the escalation bills submitted. For the grant
    of interest at the rate of ten percent per annum on the delayed payment
    of the escalation bills the tribunal relied upon clause 12.2.2 of the
    GCC wherein the parties agreed for grant of interest at the rate of ten

    Signature Not Verified
    O.M.P. (COMM) 277/2025 Page 30 of 33
    Signed By:CHANCHAL
    Signing Date:20.04.2026
    18:51:13
    percent per annum on delayed payment of bills. It would be apposite
    to mention that there is no clause in the contract that no interest would
    be awarded for delay in payment due to escalation of prices. A
    plausible conclusion arrived at by the tribunal backed by the reasons
    cannot be tinkered with under Section 34 of the Act.

    30. The tribunal under Section 31A(2) of the Act has the discretion
    to award costs. The discretion was exercised by the tribunal
    considering the expenditure incurred by the respondent in litigation,
    the certificate of costs submitted and the fact and circumstance of the
    case. The discretion exercised having a sound basis needs no
    interference.

    31. The Supreme Court in Gayatri Balasamy v. ISG Novasoft
    Technologies Ltd.
    , (2025) 7 SCC 1 held that while an arbitral award
    cannot be modified under Section 34 of the Act, a severable part of the
    award may be set aside. The relevant paragraphs are quoted below:

    ―32. In the present controversy, the proviso to Section
    34(2)(a)(iv)
    is particularly relevant. It states that if the
    decisions on matters submitted to arbitration can be
    separated from those not submitted, only that part of the
    arbitral award which contains decisions on matters non-
    submitted may be set aside. The proviso, therefore,
    permits courts to sever the non-arbitrable portions of an
    award from arbitrable ones. This serves a twofold
    purpose. First, it aligns with Section 16 of the 1996 Act,
    which affirms the principle of kompetenzkompetenz, that
    is, the arbitrators’ competence to determine their own
    jurisdiction. Secondly, it enables the Court to sever and
    preserve the ―valid‖ part(s) of the award while setting
    aside the ―invalid‖ ones. [The ―validity‖ and ―invalidity‖,
    as used here, does not refer to legal validity or merits
    examination, but validity in terms of the proviso to

    Signature Not Verified
    O.M.P. (COMM) 277/2025 Page 31 of 33
    Signed By:CHANCHAL
    Signing Date:20.04.2026
    18:51:13
    Section 34(2)(a)(iv) of the 1996 Act.] Indeed, before us,
    none of the parties have argued that the Court is not
    empowered to undertake such a segregation.

    33. We hold that the power conferred under the proviso
    to Section 34(2)(a)(iv) is clarificatory in nature. The
    authority to sever the ―invalid‖ portion of an arbitral
    award from the ―valid‖ portion, while remaining within
    the narrow confines of Section 34, is inherent in the
    Court’s jurisdiction when setting aside an award.

    34. To this extent, the doctrine of omne majus continet in
    se minus–the greater power includes the lesser–

    applies squarely. The authority to set aside an arbitral
    award necessarily encompasses the power to set it aside
    in part, rather than in its entirety. This interpretation is
    practical and pragmatic. It would be incongruous to hold
    that power to set aside would only mean power to set
    aside the award in its entirety and not in part. A contrary
    interpretation would not only be inconsistent with the
    statutory framework but may also result in valid
    determinations being unnecessarily nullified.

    (emphasis supplied)

    32. The quashing of awarding of damages for the period of
    suspension and for the balance period of the contract along with the
    interest thereon are separable, not dependant on other claims awarded
    and are not intricately connected with each other.
    Conclusion

    33. In view of the above, it is concluded:-

    i. The conclusion of the tribunal holding the contract to be an item
    rate contract and the termination of the contract to be illegal is
    upheld.

    ii. The award of damages for the period of suspension and for the

    Signature Not Verified
    O.M.P. (COMM) 277/2025 Page 32 of 33
    Signed By:CHANCHAL
    Signing Date:20.04.2026
    18:51:13
    remaining tenure of the contract alongwith the interest thereon
    is set aside.

    iii. The award of escalation charges, amount towards deployment
    of additional labour, grant of interest and costs awarded does
    not call for interference and are upheld.

    34. The petition is partly allowed. Pending application stands
    disposed of.

    AVNEESH JHINGAN, J.

    APRIL 20, 2026
    Ch
    Reportable:-Yes

    Signature Not Verified
    O.M.P. (COMM) 277/2025 Page 33 of 33
    Signed By:CHANCHAL
    Signing Date:20.04.2026
    18:51:13



    Source link

    LEAVE A REPLY

    Please enter your comment!
    Please enter your name here