Chief Engineer vs Chameli Bai on 9 April, 2026

    0
    49
    ADVERTISEMENT

    Chattisgarh High Court

    Chief Engineer vs Chameli Bai on 9 April, 2026

                                                             1
    
    
    
    
                                                                              2026:CGHC:16370
    
    
           Digitally
                                                                                           NAFR
           signed by
           JYOTI
    JYOTI  SHARMA
    SHARMA Date:
           2026.04.09
           17:11:27
           +0530
                                  HIGH COURT OF CHHATTISGARH AT BILASPUR
    
                                                    ARBA No. 80 of 2025
                        Chief Engineer, Public Works Department, National Highway Zone, NH
                        Campus Pension Bada, Raipur (C.G.), Through Executive Engineer,
                        Public Works Department, National Highway Division, Bilaspur (C.G.)
                                                                             ... Appellant(s)
                                                      versus
    
                        1. Chameli Bai W/o W/o Shri Kartikram Aged About 50 Years R/o
                        Masaniyakala, Tahsil Sakti, District Janjgir-Champa, Chhattisgarh.
    
                        2. Sub Divisional Officer (Revenue)-Cum-Competent Authority Under
                        Land Acquisition, Champa, District Janjgir-Champa (C.G.)
                                                                            ... Respondent(s)

    (The cause title is as per the Memo of Appeal)
    For Appellant(s) : Mr. R.K. Mishra, DSGI

    For Respondent No. 1 : Mr. Ramakant Patel and Mr. Shubham
    Patel Advocate
    For Respondent/ State : Mr. Santosh Soni, Govt. Advocate

    SPONSORED

    Hon’ble Shri Bibhu Datta Guru, Judge

    Order on Board
    09/04/2026

    1. Heard on I.A. No. 2 of 2025, application for condonation of delay

    of 101 days in filing this arbitration appeal filed under Section 37

    of the Arbitration and Conciliation Act, 1996.

    2. The present appeal arises out of land acquisition proceedings

    initiated under the National Highways Act, 1956 for widening of
    2

    National Highway No. 200 (New 49), wherein land of the private

    respondent was acquired and an award dated 16.04.2018 was

    passed by the Competent Authority for Land Acquisition (CALA)

    determining compensation. Being dissatisfied, the private

    respondent preferred an application under Section 3G(5) of the

    Act seeking enhancement of compensation. The learned

    Arbitrator, instead of re-determining the compensation, remanded

    the matter to the CALA for passing a revised/modified award vide

    arbitral award dated 21.02.2023. The appellant challenged the

    said award under Section 34 of the Arbitration and Conciliation

    Act, 1996; however, the learned District Court, vide order dated

    27.09.2024, dismissed the application while observing that the

    Arbitrator had acted beyond the scope of Section 3G(5).

    Aggrieved thereby, the appellant has preferred the present

    appeal.

    3. Learned DSGI appearing for the appellant submits that the

    present appeal has been filed along with an application under

    Section 5 of the Limitation Act seeking condonation of delay of

    101 days in filing the appeal. He further submits that the appeal

    was filed on 02.04.2025, beyond the prescribed period of

    limitation. It is further submitted that after the impugned order

    dated 27.09.2024 was passed and the certified copy was

    obtained, the appellant sought legal opinion from its counsel, who

    advised filing an appeal under Section 37 of the Arbitration and

    Conciliation Act, 1996. The matter was thereafter placed before
    3

    the superior authority for approval and, upon approval, entrusted

    to counsel for drafting. During this period, the then Executive

    Engineer (officer-in-charge) superannuated and the post remained

    vacant for some time. Subsequently, after the new officer

    assumed charge and the winter vacation intervened, the draft was

    approved and the appeal was filed. He also submits that the delay

    occurred due to these administrative and procedural

    circumstances, and not deliberately or with malafide intention. It is

    therefore prayed that the delay may be condoned considering the

    plausible explanation offered by the appellant..

    4. Per contra, learned counsel appearing for respondents submit that

    the issue involved in the present arbitration appeal, regarding

    delay, has already been considered and decided by this Court

    vide judgment dated 02.02.2026 passed in ARBA No.62 of 2025

    (Sumitra Bai vs. Executive Engineer, PWD & Ors.) placing

    reliance upon the decisions rendered by the Supreme Court in the

    matter of Government of Maharasthra (Water Resources

    Department) vs. Borse Brothers Engineers and Contractors

    Pvt. Ltd. reported in (2021) 6 SCC 460. Learned counsel further

    submits that the delay of 219 days has not been satisfactorily

    explained and the grounds urged are vague and general in nature,

    which do not constitute sufficient cause within the meaning of

    Section 5 of the Limitation Act. It is contended that the appellant

    has been grossly negligent in prosecuting the matter and the
    4

    application has been filed only to overcome the statutory bar of

    limitation.

    5. I have heard learned counsel for the parties and perused the

    material available on record.

    6. In the case at hand, the appellant has failed to demonstrate any

    sufficient cause for not filing the appeal within the stipulated

    period prescribed under the provisions of the Arbitration and

    Conciliation Act, 1996, except citing certain administrative and

    procedural circumstances, which themselves do not constitute a

    satisfactory explanation for condonation of delay. In fact, there

    was a long delay of 101 days beyond the prescribed period. The

    explanation feel woefully short of making out any sufficient cause.

    It is also noteworthy to mention here that merely because

    sufficient cause has been made out in the facts of a given case,

    there is no vested right in the appellant to have delay condoned.

    7. The Supreme Court in the matter of Borse Brothers Engineers

    and Contractors Pvt. Ltd. (supra) held thus at para 62, 63 & 68 :

    “62. Also, it must be remembered that merely because

    sufficient cause has been made out in the facts of a given

    case, there is no right in the appellant to have delay

    condoned. This was felicitously put in Ramlal v. Rewa

    Coalfields Ltd. as follows: (SCR p. 771: AIR p. 365, para

    12)–

    5

    “12. It is, however, necessary to emphasise that even

    after sufficient cause has been shown a party is not

    entitled to the condonation of delay in question as a

    matter of right. The proof of a sufficient cause is a

    condition precedent for the exercise of the

    discretionary jurisdiction vested in the court by Section

    5. If sufficient cause is not proved nothing further has

    to be done; the application for condoning delay has to

    be dismissed on that ground alone. If sufficient cause

    is shown then the Court has to enquire whether in its

    discretion it should condone the delay. This aspect of

    the matter naturally introduces the consideration of all

    relevant facts and it is at this stage that diligence of

    the party or its bona fides may fall for consideration;

    but the scope of the enquiry while exercising the

    discretionary power after sufficient cause is shown

    would naturally be limited only to such facts as the

    Court may regard as relevant. It cannot justify an

    enquiry as to why the party was sitting idle during all

    the time available to it. In this connection we may point

    out that considerations of bona fides or due diligence

    are always material and relevant when the Court is

    dealing with applications made under Section 14 of

    the Limitation Act. In dealing with such applications the

    Court is called upon to consider the effect of the
    6

    combined provisions of Sections 5 and 14. Therefore,

    in our opinion, considerations which have been

    expressly made material and relevant by the

    provisions of Section 14 cannot to the same extent

    and in the same manner be invoked in dealing with

    applications which fall to be decided only under

    Section 5 without reference to Section 14.”

    63. Given the aforesaid and the object of speedy disposal

    sought to be achieved both under the Arbitration Act and

    the Commercial Courts Act, for appeals filed under Section

    37 of the Arbitration Act that are governed by Articles 116

    and 117 of the Limitation Act or Section 13(1-A) of

    the Commercial Courts Act, a delay beyond 90 days, 30

    days or 60 days, respectively, is to be condoned by way of

    exception and not by way of rule. In a fit case in which a

    party has otherwise acted bona fide and not in a negligent

    manner, a short delay beyond such period can, in the

    discretion of the court, be condoned, always bearing in

    mind that the other side of the picture is that the opposite

    party may have acquired both in equity and justice, what

    may now be lost by the first party’s inaction, negligence or

    laches.

    68. This explanation falls woefully short of making out any

    sufficient cause. This appeal is therefore allowed and the

    condonation of delay is set aside on this score also.”
    7

    8. In the absence of any sufficient cause and explanations, the

    application under Section 5 of the Limitation Act cannot be

    entertained as a matter of routine, particularly, when the delay in

    filing of the instant appeal is for a period of 101 days.

    9. Applying the well settled principles of law laid down by the Apex

    Court in the matter of Borse Brothers Engineers and

    Contractors Pvt. Ltd. (supra) and further considering the fact

    that the identical issue has already been considered and decided

    by this Court in Sumitra Bai (supra); and for the reasons

    mentioned in the application, I.A. No.2, for condonation of delay of

    101 days in filing the appeal is hereby rejected.

    10. Consequently, the instant arbitration appeal is also dismissed on

    this score alone. Sd/-

    (Bibhu Datta Guru)
    JUDGE

    Jyoti



    Source link

    LEAVE A REPLY

    Please enter your comment!
    Please enter your name here