Advertisement
Advertisement

― Advertisement ―

HomeIndian Newspapaer Society vs Mumbai Metropolitan Region ... on 8 April, 2026

Indian Newspapaer Society vs Mumbai Metropolitan Region … on 8 April, 2026

ADVERTISEMENT

Bombay High Court

Indian Newspapaer Society vs Mumbai Metropolitan Region … on 8 April, 2026

2026:BHC-OS:8910-DB
                                                             Indian-Newspaper-oswp-864-2018-J-R.doc




                                                                                                Shephali




                               IN THE HIGH COURT OF JUDICATURE AT BOMBAY
                                   ORDINARY ORIGINAL CIVIL JURISDICTION
                                       WRIT PETITION NO. 864 OF 2018


                     Indian Newspaper Society,
                     A company registered under Section 25 of
                     the companies Act, 1956, having its
                     registered office at INS Building,
                     Rafi Marg, New Delhi 110 001.                                    ...Petitioner

                              ~ versus ~

                     1.     Mumbai Metropolitan Region
                            Development Authority,
                            a Body Corporate having its Head
                            Office at MMRDA Office Building,
SHEPHALI                    Plot Nos. C-14 & C-15, 'E' Block,
SANJAY
MORMARE                     Bandra Kurla Complex, Bandra (East),
 Digitally signed           Mumbai 400 051.
 by SHEPHALI
 SANJAY
 MORMARE
 Date: 2026.04.09
                     2.     The Metropolitan Commissioner,
 15:15:50 +0530
                            being the Chief Executive Officer of
                            the Mumbai Metropolitan Region
                            Development Authority, having his
                            office at MMRDA Office Building,
                            Plot Nos. C-14 & C-15, 'E' Block,
                            Bandra Kurla Complex, Bandra (East),
                            Mumbai 400 051.                                     ...Respondents

                     A PPEARANCES
                     For the Petitioner              Mr. Ankit Lohia, with Mr. Firoz
                                                     Patel,   Mr.   Prashant   Ghelani,
                                                     Ms. Namrata Vashist & Mr. Darshil
                                                     Desai, i/b Markand Gandhi & Co.
                     For Respondents-MMRDA           Dr. Birendra Saraf, Senior Advocate,
                                                     with Mr. Nishant Chotani, Mr. Nivit
                                                     Srivastava, Ms. Sneha Patil, Ms.
                                                     Aditi Sinha, Mr. Hrishikesh Joshi &


                                                   Page 1 of 50


                    ::: Uploaded on - 09/04/2026                    ::: Downloaded on - 09/04/2026 21:36:07 :::
                                           Indian-Newspaper-oswp-864-2018-J-R.doc




                                   Ms. Isha Vyas, i/b Maniar Srivastava
                                   Associates.



                       CORAM   :    SHREE CHANDRASHEKHAR, CJ &
                                    SUMAN SHYAM, J.
           RESERVED ON         :    22nd JANUARY 2026.
        PRONOUNCED ON          :    8th APRIL 2026.

 JUDGMENT (Per Suman Shyam, J):

1. Rule. Rule is made returnable forthwith.

SPONSORED

2. By consent of the parties, the matter is taken up for final

hearing.

3. Assailing the demand notice dated 12th September 2017

(Exhibit-N) the Writ Petitioner has approached this Court inter alia

contending that the demand for penalty/additional premium on

account of late completion of the construction, raised by the

Respondent No. 1, i.e., Mumbai Metropolitan Region Development

Authority (“MMRDA”), is contrary to the terms and conditions of

the Lease Agreement and, therefore, arbitrary and illegal. The

facts and circumstances, giving rise to the filing of the Writ

Petition, shorn of unnecessary details, are as hereunder.

Page 2 of 50

::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:36:07 :::

Indian-Newspaper-oswp-864-2018-J-R.doc

4. The Writ Petitioner is a registered company having its office

at INS Building, Rafi Marg, New Delhi 110 001. The Petitioner is a

non-profit organization and plays a central role in protecting and

promoting the interest of the Press in India. The Respondent No. 1

(MMRDA), is an authority set up under a statute viz. the Mumbai

Metropolitan Regional Development Authority Act, 1974

(hereinafter referred to as “MMRDA Act”) and the Respondent No.

2 is its Chief Executive Officer.

5. Based on an application made by the Petitioner-Company,

the Respondent No. 1 had allotted the Plot No. C-63 in ‘G’ Block at

Bandra-Kurla Complex (BKC) vide authority of approval granted

in its 120th meeting held on 24th December 2007.

6. On 17th November 2005, the Respondent No. 1 had allotted

the aforesaid plot admeasuring 10,450 sq. mtrs. to the Writ

Petitioner, on a long term lease of 80 years, for construction of

office complex, on payment of lease premium of

Rs.88,52,75,000/- (Rupees Eighty Eight crores Fifty Two lakhs and

Seventy Five thousand), calculated at the rate of Rs.42,500/- per

sq. mtr.

Page 3 of 50

::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:36:07 :::

Indian-Newspaper-oswp-864-2018-J-R.doc

7. On 1st December 2005, the Respondent No. 1 permitted the

Petitioner to transfer 40% of the built up area to third party

subject to the condition that the same shall be used only for office

purpose. Consequently, on 14th February 2008, the Petitioner had

entered into a Development Agreement with M/s. Orbit Enterprise

(“Developer”) for development of the said plot.

8. On 18th February 2008, the Petitioner paid the entire lease

premium of Rs.88,52,75,000/- (Rupees Eighty Eight Crores Fifty

Two Lakhs and Seventy Five Thousand) to the Respondent No. 1,

pursuant whereto, Lease Deed dated 9th April 2008, leasing out

the area of 10415 sq. mtrs of land, for a period of 80 years, was

executed by and between the Petitioner and the Respondent No. 1.

As per the Lease Agreement, the permissible built-up area was

20,830 sq. mtrs.

9. Article 2(c) of the Lease Deed dated 9th April 2008 stipulates

that no work shall commence till the plan is approved by the

authority; Article 2(d) lays down that the construction will be

completed within a period of four years from the date of execution

of the Lease Deed; Article 2(e) stipulates that failure to comply

with Article 2(d) would require extension of time that may be

Page 4 of 50

::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:36:07 :::
Indian-Newspaper-oswp-864-2018-J-R.doc

permitted by the Metropolitan Commissioner on payment of

additional premium, which would be 25% of the premium up to

one year; 35% of the premium between one and two years; and

40% of the premium between two and three years.

10. Pursuant to the execution of the Lease Deed dated 9 th April

2008, possession of the plot of land was handed over to the Writ

Petitioner on 10th April 2008. It would be pertinent to note herein

that when the Lease Deed dated 9th April 2008 was executed, 2.00

Floor Space Index (FSI) was available at Bandra-Kurla Complex

and, therefore, the permissible built-up area on the said plot of

land was 20,830 sq. mtrs only. Accordingly, proposal for

construction of commercial office building with two wings, viz., ‘A’

and ‘B’ wings with two level basement, constituting Ground+3

floors at ‘A’ wing (8,006 sq. mtrs.) and Ground+11 floors in ‘B’

wing (13,650 sq.mtrs) was drawn up by the Petitioner.

11. On 20th April 2008, the construction plan, along with

application for shore-piling and excavation, was submitted by the

Petitioner before the Respondent No. 1. On 30 th May 2008, the

Respondent No. 1 granted permission for excavation and shore-

piling.

Page 5 of 50

::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:36:07 :::

Indian-Newspaper-oswp-864-2018-J-R.doc

12. On 3rd November 2008, the drawings of the construction

was submitted by the Petitioner before the Respondent No. 1 for

approval. On 8th December 2008, the Respondent No. 1 had issued

deficiency letter asking the Petitioner to obtain ‘NOC’ for the

Environment Impact Assessment (EIA), which was obtained and

submitted by the Petitioner on 8th October 2009. Thereafter, the

plan upto the plinth level was approved.

13. The FSI in the Bandra-Kurla Complex area was

subsequently, enhanced to 4.00. As such, the Respondent No. 1

had offered additional built-up area upto 4.00 FSI to the existing

Lessees. In view of the enhancement in the FSI, the Petitioner, vide

letter dated 22nd September 2009, requested the Respondent No. 1

to allot additional built-up area of 20,830 sq. mtrs. on the same

plot. Acting on such request made by the Petitioner, on 10 th

September 2009, the Respondent No. 1 had allotted additional

built-up area of 20,830 sq. mtrs to the Petitioner against payment

of Rs.204,02,98,500/- (Rupees Two Hundred Four Crores Two

Lakhs Ninety Eight Thousand Five Hundred only), which was

payable in five installments. Liberty was also granted to the

Petitioner to transfer the entire additional built-up area, subject to

Page 6 of 50

::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:36:07 :::
Indian-Newspaper-oswp-864-2018-J-R.doc

the provision of the Lease Deed. In view of the allotment of the

additional built-up area, the total built-up area allotted to the

Petitioner stood increased to 41,660 sq. mtrs.

14. On 22nd April 2013, a Supplementary Lease Deed was

executed by and between the Petitioner and the Respondent No. 1.

Article 2(c) of the Supplementary Lease Deed clearly stipulated

that there shall be no time-limit, as stipulated in Article 2(d) of

the Lease Deed dated 9th April 2008, for completion of the

construction of the building by using the additional built-up area.

It was further provided that the incremental premises would be

deemed to be the integral part of the demised premise as defined

in the Lease Deed dated 9th April 2008.

15. In the wake of the allotment of additional built-up area

(BUA), as aforesaid, the Petitioner was required to submit revised

building plan so as to consume the new built-up area within the

same plot and the same building. According to the revised plan,

both the wings, namely, ‘A’ and ‘B’ wings would now have G+14

floors. Accordingly, on 29th March 2010, the Petitioner had

submitted amended plan which was approved by Respondent No.

1 on 26th August 2011. Thereafter, on 2nd January 2012, the

Page 7 of 50

::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:36:07 :::
Indian-Newspaper-oswp-864-2018-J-R.doc

Respondent No. 1 had issued Commencement Certificate (“CC”)

for the 4th to 6th floor in Wing ‘A’ for the built-up area of 5,730.64

sq. mtrs.

16. As per the projection made in the Writ Petition, the

Petitioner had completed construction of the two basements as

well as Ground+9 floors in wing ‘B’ and Ground+6 floors in ‘A’

Wing in the month of April, 2012, thus, substantially consuming

the original built-up area of 20,830 sq. mtrs.

17. In view of the allotment of the additional built-up area, the

height of the building had to also be raised. Therefore, the

Petitioner had applied for height clearance which was granted by

the Airports Authority of India by NoC dated 2nd August 2012.

18. On 18th January 2013, the Respondent No. 1 had issued

Commencement Certificate (“CC”) for ‘A’ Wing (7 th to 12th floors)

and ‘B’ Wing (10th to 12th floors) and, thereafter, on 14th November

2013, the Respondent No. 1 had issued Commencement

Certificate for the plinth level basements as well as G+14 floors of

‘A’ and ‘B’ wings. Thus, the CC for completing the construction of

the entire building, including the basement as well as G+14 floors

Page 8 of 50

::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:36:07 :::
Indian-Newspaper-oswp-864-2018-J-R.doc

in both the wings, was eventually granted by the Respondent No.

1 only on 14th November 2013.

19. Although there was no written demand for any additional

premium/penalty for extension of time, yet, in view of Article 2(c)

of the Lease Deed dated 9 th April 2008 stipulating outer limit of

four years for completion of the construction, which period had

already expired, on 6th June, 2012, the Petitioner wrote a letter

to the Chief Town Planner of Respondent No. 1 seeking extension

of time for two years as the height clearance was yet to be

received from the Civil Aviation Authorities, New Delhi. The letter

dated 6th June 2012 was followed by another letter dated 10 th

December 2012 renewing the request for extension of time by two

years by citing the reasons for the delay. Thereafter, on 10 th

January 2013, the Petitioner had addressed another letter to the

Deputy Metropolitan Commissioner, Land & Estate Department of

the Respondent No. 1 stating that the completion of the building

would take almost six years due to various reasons and problems.

20. In view of the above request for extension of time made by

the Petitioner, the Respondent No.1 i.e. the MMRDA had proposed

Page 9 of 50

::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:36:07 :::
Indian-Newspaper-oswp-864-2018-J-R.doc

to levy penalty upon the Petitioner due to the delay in completion

of the construction beyond the time-limit of four years.

21. Although, the Petitioner did not agree with the said decision

and had clarified that the decision would be appealed against, yet,

in the interest of the project, some more time as well as facility of

payment of additional premium under protest, in four quarterly

installments, was made by the Petitioner. By the letter dated 10 th

January 2013, the Petitioner had also assured the Respondent

No.1 that the first installment would be paid on or before 31 st

March 2013 as the project did not have any provision for this

additional burden.

22. On 30th September 2013, the Deputy Metropolitan

Commissioner of the Respondent No. 1 Authority had issued a

letter to the President of the Petitioner-company, granting the

request for extension of time for completing the construction of

the building on Plot No. C-63 in ‘G’ Block of Bandra-Kurla

Complex (BKC) under Lease Deed dated 9th April 2008 for a

period of one year from 9th April 2012 to 8th April 2013, by

charging additional premium at the rate of 10% of the lease

premium payable in advance. In the said letter, it was also

Page 10 of 50

::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:36:07 :::
Indian-Newspaper-oswp-864-2018-J-R.doc

mentioned that the additional premium payable by the Petitioner,

as on that date, works out to Rs.8,85,27,500/- along with interest

payable for delayed payment, calculated at the rate of 14% per

annum. It was also conveyed that as requested by the Petitioner ,

the Respondent No. 1 was agreeable to the proposal for payment

of the additional premium in four equal quarterly installments

along with interest due thereon, at the rate of 14%, of which, the

first installment would be due on 31 st March 2013. The Petitioner

was, therefore, asked to pay the outstanding dues immediately

along with interest applicable thereon.

23. Thereafter, on 31st October 2013, the Deputy Town Planner

TN & CP Division of Respondent No. 1, had addressed a letter to

the representative of the Petitioner calling upon him to deposit the

amount of Rs.10,05,449/- as scrutiny fee in respect of the

development on Plot No. C-63 in ‘G’ Block at Bandra-Kurla

Complex for “Indian Newspaper Society”.

24. Thereafter, on 22nd August 2014, the Respondents issued a

notice to the Petitioner to pay up the outstanding dues, failing

which, the CC will be revoked and the ‘Lease’ would also be

determined. In the said notice, although reference has been made

Page 11 of 50

::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:36:07 :::
Indian-Newspaper-oswp-864-2018-J-R.doc

to breach of the terms and conditions of the Lease Deed dated 9 th

April, 2008 as well as the Supplementary Deed of Lease deed

dated 22nd April 2013, in so far as completion of the construction

as “fit for occupation” was concerned, yet, there is no mention of

any specific amount falling due and payable by the Petitioner on

account of the alleged breach of the terms of the Lease

Agreements nor was any particulars furnished as regards the

nature and extent of the breach, so alleged.

25. On 19th September 2014, the Petitioner submitted its reply

to the notice dated 22nd August 2014 as well as the letter dated

31st October 2013, forwarding a Pay Order for an amount of

Rs.73,78,07,466/- as payment of installment for the additional

built-up area. That apart, a separate pay order for an amount of

Rs.13,78,59,150/- was also forwarded towards payment of

penalty/additional premium for granting extension of time for

completion of the construction.

26. The above communication was followed by the letter 22 nd

September 2014 issued by the Petitioner to the Respondent No. 1

inter- alia stating that the payment of premium for the additional

built-up area due to delay in completing the construction has been

Page 12 of 50

::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:36:07 :::
Indian-Newspaper-oswp-864-2018-J-R.doc

made under protest. It has further been mentioned therein that at

the time of executing the Supplementary Lease Deed allotting the

additional built-up area, it was assured that due to the increase in

additional built-up area the period of completion of construction

would be increased by the MMRDA from four years to six years.

Therefore, the additional premium/penalty was paid without

prejudice to the right of the Petitioner to claim refund of the entire

amount, in case, the period of construction is increased from four

years to six years. Accordingly, a request was made to re-validate

the NoC etc.

27. On 23rd December 2014, the Respondent No. 1 extended the

date of completion of construction of the building to 8 th April 2015

and demanded additional penalty of Rs. 8.85 Crores for the year

2014-2015. On such basis, the Respondent No. 1 claimed that an

amount of Rs.15,44,36,039/- along with interest for delayed

payment, as on 31st October 2014, was due and payable.

28. Eventually, on 12th September 2017, the Respondent No. 1

had issued the impugned Demand Notice calling upon the

Petitioner to pay the outstanding dues, failing which, action under

Articles 5 and 6 of the Deed of Lease would be initiated for breach

Page 13 of 50

::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:36:07 :::
Indian-Newspaper-oswp-864-2018-J-R.doc

of the Agreement. The said Demand Notice is under challenge in

the present proceeding.

29. In the Reply filed on behalf of the Respondents, the

maintainability of the Writ Petition has been assailed inter-alia on

the ground that the same raises several disputed questions of facts

which cannot be adjudicated in a Writ Petition. By referring to

Section 44 of the MMRDA Act, 1974 read with Rule 5 of the

MMRDA Rules,1976, it has been alleged that alternative remedy,

in the form of an Appeal under Section 44 was available to the

Petitioner. Therefore, the Writ Petition ought to be dismissed on

such ground alone.

30. The Respondents have also alleged that the Writ Petitioner

has approached this Court by suppressing material facts and

particulars; that in the Writ Petition, challenge has been made to

the policy decision of the State without challenging the relevant

provisions of the statute which permits such action; that the Writ

Petition is hit by delay and laches and the same is also barred by

the law of limitation.

Page 14 of 50

::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:36:07 :::

Indian-Newspaper-oswp-864-2018-J-R.doc

31. The Respondents have further alleged that by failing to

produce the full ‘CC’ dated 14th November 2013, the Petitioner has

suppressed material facts. Since the Petitioner has approached this

Court with unclean hands and, hence, the Writ Petition is liable to

be dismissed on such count alone.

32. While denying and disputing the assertions made by the

Petitioner that the construction of the built-up area as per the

initial allotment of 20,830 sq. mtrs. was completed in the month

of April 2012, i.e., within the stipulated period of four years, it

was contended that such disputed questions of facts cannot be

gone into in a Writ Petition.

33. This Writ Petition was analogously heard along with three

other Writ Petitions being Writ Petition No. 2377 of 2018, Writ

Petition No. 242 of 2018 and Writ Petition No. 3209 of 2017,

involving similar issues whereby, identical reliefs were sought by

the Writ Petitioner(s).

34. Mr. Ankit Lohia Learned Counsel for the Petitioner has

adopted the arguments advanced by Mr Nakani Learned Senior

Counsel for the Writ Petitioners in the connected Writ Petitions.

Page 15 of 50

::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:36:07 :::

Indian-Newspaper-oswp-864-2018-J-R.doc

Like wise Dr. Saraf, learned Senior Counsel for the Respondents

has also advanced common arguments in this Writ Petition as well

in Writ Petition No 242 of 2018, supporting the statements made

in the Reply Affidavit.

35. We have considered the pleadings brought on record and

have also gone through the documents annexed therein.

36. At the very outset, it deserves to be mentioned herein that

although the maintainability of the Writ Petition has been assailed

on the ground that several disputed questions of facts are involved

there-in, yet, after examining the record, we find that save and

except the claim of the Petitioner as regards the date of

completion of the first phase of initial built-up area of 20,830 sq.

mtrs., all other assertions made in the Writ Petition are based on

documents annexed thereto, which are admitted documents.

Having regard to the core controversy involved in this proceeding

and considering the fact that the issues involved in this Writ

Petition would call for determination based on interpretation of

the relevant clauses of the Lease Agreement(s) as well as the

documents exchanged by and between the parties, we are of the

considered opinion that the date of completion of the first phase

Page 16 of 50

::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:36:07 :::
Indian-Newspaper-oswp-864-2018-J-R.doc

of the initial built up area would not have much of a material

bearing in the out come of the Writ Petition.

37. In the case of Joshi Technologies International IBC vs. U.O.I.

& Ors.,1 the Hon’ble Supreme Court has observed that there is no

absolute bar to the maintainability of a Writ Petition, even in

contractual matters or where there are disputed questions of fact

or even when monetory claim is raised, provided, the Court is

called upon to examine the issue which has a public law character

attached to it. Having regard to the core controversy involved in

this proceeding and considering the fact that the issues involved in

this Writ Petition would call for determination by this Court based

on interpretation of the relevant Articles of the Lease Agreement

as well as the documents exchanged by and between the parties so

as to ascertain fairness in the action of the Respondent No 1, we

are unable to agree with the stand of the Respondents that the

Writ Petition ought to be dismissed on the ground that it raises

disputed questions of facts.

38. Likewise, in Banda Development Authority, Banda vs.

Motilal Agarwal & Ors.2 the Hon’ble Supreme Court has observed

1 (2015) 7 SCC 728.

2 (2011) 5 SCC 394.

Page 17 of 50

::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:36:07 :::

Indian-Newspaper-oswp-864-2018-J-R.doc

that no limitation has been prescribed for filing a Writ Petition

under Article 226 of the Constitution of India. However, the High

Court will treat the delay in filing the Writ Petition as

unreasonable, if the same is filed beyond the period of limitation

prescribed for filing a Civil Suit for a similar cause. From the

above, it would be apparent that although un-explained delay in

instituting a Writ Petition could be a valid ground to decline relief

to the Petitioner, yet, the law of Limitation would not have strict

application in a Writ Petition.

39. There is no dispute in this case about the fact that the

Respondent No. 1 is an instrumentality of the State and, therefore,

would be an “other authority” within the meaning of Article 12 of

the Constitution of India.

40. Law is well settled that arbitrariness in the decision making

process of the State or its instrumentality is a facet of Article 14 of

the Constitution of India. In E.P..Royappa v State of Tamil Nadu,3 it

was pointed out that Article 14 would strike at arbitrariness in

State action and ensure fairness and equality of treatment.

3 (1974) 4 SCC 3.

Page 18 of 50

::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:36:08 :::

Indian-Newspaper-oswp-864-2018-J-R.doc

41. The present is not a proceeding simpliciter for enforcing a

money claim but raises significant questions pertaining to the

validity and fairness in the impugned action of the Respondent No

1, which are required to be adjudicated on the touch stone of

Article 14. As such, we are of the considered opinion that such

plea cannot be brushed aside merely on the ground of delay and

laches, more so, since such delay has evidently not given rise to

any parallel right of a third party.

42. In so far as the plea of availability of alternative remedy is

concerned, from a reading of Section 44 of the MMRDA, Act 1974,

we find that the provision for Appeal provided thereunder, is

pertaining to disputes regarding recovery of money due to the

authority as arrears of land revenue. Since the challenge made to

the impugned demand notice is on the ground that the same is

contrary to the terms of the Supplementary Lease Deed and hence,

illegal and arbitrary, we are of the opinion that the said

controversy cannot be effectively adjudicated in an Appeal filed

under Section 44. Therefore, we reject the contention of the

Respondents that the Petitioner has an effective and efficacious

alternative remedy.

Page 19 of 50

::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:36:08 :::

Indian-Newspaper-oswp-864-2018-J-R.doc

43. We also find that all material facts have been stated in the

Writ Petition. Therefore, the Writ Petition cannot also be dismissed

on account of suppression of facts.

44. In view of the above discussions, we hold that the Writ

Petition is maintainable in law as well as in the facts and

circumstances of the case.

45. Having held as above, it would be pertinent to mention

herein that our attention has been invited to an earlier decision

rendered by a co-ordinate Bench of this Court (Coram: Ranjeet

More & Bharati Dangre, JJ) dated 20 th November 2019 passed in

Raghuleela Builders Pvt. Limited and Anr. vs. The Mumbai

Metropolitan Regional Development Authority & Ors. 4 wherein

issues of similar nature were involved. In that case also the Writ

Petitioners had challenged a similar Demand Notice dated 12 th

September 2017 issued by the Respondent No.1 by invoking

identical Articles in the Lease Deed as well as the Supplementary

Lease Deed, thus demanding payment of a sum of Rs. 432 Crores

as penalty for the delay in completion of construction of the

building. In that case also, the initial built up area was 30550 sq.

4 (2020) (1) ABR 397: 2019 SCC OnLine Bom 4529.

Page 20 of 50

::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:36:08 :::

Indian-Newspaper-oswp-864-2018-J-R.doc

meters, which was to be consumed by constructing 9 floors in the

building, yet, subsequently, due to the increase in the FSI, the

Respondent No.1 had allotted additional built up area of 67000

sq. meters to the Petitioner resulting into construction of 11

additional floors in the same building. Due to addition in the built

up area, the construction of the building could not be completed

within four years, as a result of which, Demand Notice dated 12 th

September, 2017 was served on the Lessees for recovery of

penalty/additional premium along with interest calculated

thereon.

46. By the Judgment and Order dated 20th November 2019,

rendered in Raghuleela Builders Pvt. Ltd. & Anr . (Supra), a

Division Bench of this Court had set aside the impugned Demand

Notice dated 12th September 2017 by holding that such a demand

was not maintainable in the eyes of law. That apart, it was also

observed that in view of the change in policy of the MMRDA

increasing the time for completion of the building “Fit for

occupation”, from four years to six years, the demand for

penalty/additional premium for delay in completion of

Page 21 of 50

::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:36:08 :::
Indian-Newspaper-oswp-864-2018-J-R.doc

construction within four years was ex-facie unreasonable,

unjustified and discriminatory.

47. The Special Leave Petition (C) No. 6411 of 2020 preferred

by the Respondent No.1 assailing the Judgment and Order dated

20th November 2019 was dismissed by the Hon’ble Supreme Court

by the order dated 27th July 2020 by taking note of the findings

recorded in paragraphs No. 39 and 41 of the Judgment and Order

dated 20th November 2019. However, it was clarified that since the

judgment of the Division Bench of Bombay High Court in

Raghuleela Builders Pvt. Ltd. & Anr. (Supra) was rendered in the

facts of that case, hence, it cannot influence any other matter in

this behalf. With the above observation the Special Leave Petition

was dismissed by the following order:-

“We are not inclined to exercise our jurisdiction under Article
136
of the Constitution of India in the given facts of the case and
more so as reflected from paragraphs 38 and 40 of the
impugned judgment.

Mr. K. K. Venugopal, learned Attorney General for India
expresses some apprehension on account of there being other
matters pending.

We clarify that the present matter is in the given facts of
the case as stated aforesaid and thus, cannot be said to influence
any other matter in this behalf.

The special leave petition is dismissed in terms aforesaid.
Pending applications shall also stand disposed of.”

Page 22 of 50

::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:36:08 :::

Indian-Newspaper-oswp-864-2018-J-R.doc

48. It appears that the Respondent No. 1 had filed a Review

Petition seeking review of the order dated 27 th July 2020, which

was also dismissed by the Hon’ble Supreme Court vide order

dated 29th September 2020 passed in Review Petition (Civil) No.

1764 of 2020 arising out of SLP (C) No. 6411 of 2020.

49. From the plain reading of order dated 27th July 2020, what

transpires is that the Hon’ble Supreme Court had observed that

the decision in Raghuleela Builders Pvt. Ltd. & Anr . (Supra) was

passed in the facts of that case. However, in our considered

opinion, we can take note of the legal principles, if any, emanating

from the said decision. In that view of the matter we are unable to

agree with the submission of learned Counsel for the Respondent

that the decision in the case of Raghuleela Builders Pvt. Ltd. &

Anr. (Supra) cannot be looked into by this Court even for the

purpose of deciding the question of maintainability of the Writ

Petition.

50. The question of maintainability of a Writ Petition is mixed

question of law and facts. Therefore, such question has to be

answered by taking note of the facts and circumstances of each

case. Having regard to the peculiar facts and circumstances of this

Page 23 of 50

::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:36:08 :::
Indian-Newspaper-oswp-864-2018-J-R.doc

case and also considering the fact that a similar Writ Petition,

raising similar issues, in Raghuleela Builders Pvt. Ltd. & Anr .

(Supra) had earlier been entertained by this court, we are not

inclined to non-suit the Petitioner merely on the plea of

maintainability raised by the Respondents.

On Merit :-

51. By referring to the materials available on record the

learned Counsel for the Petitioner has argued that after the

allotment of the additional built-up area of 20,830 sq. meters,

which was required to be used on the same plot and the same

building, it was impossible to segregate the construction and

complete the construction of initial built-up area of 20,830 sq.

meters “fit for occupation”, inasmuch as, various services, such as,

cooling tower, air cool chillers, exhaust fans for toilet exhaust, DG

exhaust, pipes, fresh air fans for AHU, pressurization fans for

staircase, etc. were common facilities for the entire building and

therefore, were required to be located on top of 14 th floor of the

building, which would not be possible until the entire construction

is completed. As a result of the same, the Building cannot be

completed “fit for occupation” without such facilities. Likewise,

Page 24 of 50

::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:36:08 :::
Indian-Newspaper-oswp-864-2018-J-R.doc

submits the learned counsel, it would not be possible to obtain fire

NOC, storm-water drainage completion certificate, service lift /

fire lift approval, etc. from the Statutory Authorities until the

construction of the entire building was completed. It is also the

submission of learned Counsel for the Petitioner that the demand

for penalty for delay in construction was unsustainable in law, as

the ‘No Time Limit’ clause would be applicable to the entire

building after the additional built-up area was allotted.

52. By referring to the subsequent decision of the MMRDA to

grant six years time for completion of construction of the buildings

but keeping it confined only to those leases which were granted

after 25th August 2015, the learned counsel has argued that such

differentia is wholly arbitrary, illegal, discriminatory and devoid of

any rational basis. The learned counsel for the Petitioner further

submits that the Respondent No.1 has not disclosed any

reasonable basis for making a distinction between pre-August

2015 and post-August 2015 lease agreement for granting

additional period of time for completion of construction without

levying any penalty, notwithstanding the fact that the lessees of

both the categories were similarly situated and were facing similar

Page 25 of 50

::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:36:08 :::
Indian-Newspaper-oswp-864-2018-J-R.doc

nature of challenges in completing the construction, which facts

were well within the knowledge and understanding of the

Respondent No.1. Therefore, he submits that the impugned

Demand Notice is illegal and hence, liable to be set aside by this

court.

53. Dr. Birendra Saraf, learned Senior Counsel appearing for the

Respondents, on the other hand, has submitted that the

Petitioners, having executed a Lease Deed which contains a

specific stipulation in the form of Article 2(c) permitting levy of

penalty due to delay in completion of construction beyond four

years, cannot now turn back and question such decision of the

authority. It is also his submission that the Petitioner cannot be

permitted to question the policy decision of the Respondent No.1,

which has the backing of a statute. On such count, the learned

senior counsel has submitted that the Writ Petition deserves to be

dismissed with cost.

54. At the very out set it must be noted here-in that as per

Article 2(d) the lessee is required to complete the construction

within four years from the date of execution of the lease deed.

However, Article 2 (c) of the Lease Deed makes it clear that no

Page 26 of 50

::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:36:08 :::
Indian-Newspaper-oswp-864-2018-J-R.doc

work shall commence or be carried out contrary to the

Development Control Regulations and the Building Regulations

applicable to the plot of land and until the plans, elevations,

sections, specifications and details shall have been approved.

Therefore, in view of Article 2(c), the construction cannot

commence until all statutory approvals including the approval of

building plan etc is received by the Lessee. Article 2(a) of the

Lease Deed mentions that the lessee shall within three months

submit plans etc. for approval. However, there is no condition in

the Lease Deed laying down any time line for granting of such

approval by the authority.

55. In a construction of this nature, permission of multiple

statutory authorities including the Municipal Corporation, Fire

department, Environment clearance, height clearance etc. will be

necessary, without which also the Commencement Certificate

cannot be issued. Unless the Commencement Certificate is issued

by the Authority, the construction work cannot commence. These

statutory authorities are not bound by the terms and conditions of

the Lease Agreement. Notwithstanding the same, the Lease

Agreement is completely silent as to who will be responsible in

Page 27 of 50

::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:36:08 :::
Indian-Newspaper-oswp-864-2018-J-R.doc

case of delay in granting approval by these statutory authorities

coming in the way of early commencement and completion of the

construction.

56. Not only that, the Lease Deed is also silent as to what would

be the effect on the time line of four years for completion of the

construction as laid down in Article 2(d) in case, there is delay in

granting of statutory approvals. Therefore, if there is delay in

granting permissions/ approval by the statutory authorities for any

reason whatsoever, leading to delay in commencement of

construction, then even in that event, the Lessee will be left with

no option but to complete the construction within the stipulated

time for no fault on its part. Yet, as per Article 2(d), as interpreted

by the Respondent No 1, the lessee would still be liable to pay

penalty for the delay in completing the construction beyond the

period of four years from the date of execution of the Lease Deed.

Viewed from that perspective, Article 2(d) of the lease deed

appears to be ex-facie unfair, unreasonable and hence,

unconscionable. However, since the Articles of the Lease Deed are

not under challenge, hence, the said aspect of the matter need not

detain this Court.

Page 28 of 50

::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:36:08 :::

Indian-Newspaper-oswp-864-2018-J-R.doc

57. From a plain reading of the documents brought on record,

more particularly, the Deed of Lease dated 9 th April 2008, it is

apparent that in view of the applicability of 2.00 FSI, the

Respondent No.1 had initially granted built-up area 20,830 sq.

mtrs only to the Petitioner by realizing the agreed premium.

However, subsequently, after the FSI was increased for the Bandra-

Kurla Complex area to 4.00, additional built-up area of 20,830 sq.

meters was allotted to the Petitioner. Consequently, a

supplementary Lease Deed dated 22 nd April 2013, was executed.

In Article 2(c) of the Supplementary Agreement, the time

restriction for completion of the building within four years was,

however, dispensed with and in its place, the time period for

completing the construction was made unlimited. Since the entire

controversy in this proceeding revolves around the pertinent

clauses of the two Lease Deeds, hence , we deem it appropriate to

reproduce the relevant clauses of the lease deeds as hereunder :-

58. Article 2 of the Lease Deed Dated 9 th April 2008 reads as

follows:-

“2. The Lessee hereby agrees to observe and perform the
following conditions that is to say:

Page 29 of 50

::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:36:08 :::

Indian-Newspaper-oswp-864-2018-J-R.doc

(c) No work to begin until plans are approved: No work
shall be commenced or carried on which infringes any of the
Development Control Regulations and Building Regulations set
out in the THIRD SCHEDULE hereto as also Municipal or any
other Regulations so far as the same are applicable to the said
land or to the use to which the said land and/or building there
upon is going to be put to, being the subject of these presents,
or until the said plans, elevations, sections, specifications and
details shall have been to approved as aforesaid and thereafter
shall not make any alterations or additions there to unless
such alternations and additions shall have been previously, in
like manner, approved.

(d) Time limits for commencement and completion of
construction work: That the Lessee shall within three months
from the receipt of approval of his plans and specifications of
building or buildings intended to be erected on the land,
commence and within a period of four years from the date of
this lease at his own expense and in a substantial and
workman-like manner and with the sound materials and in
compliance with the said Development Control Regulations
and Building Regulations and all Municipal Rules, bye-laws
and Regulations applicable hereto and in strict accordance
with the approved plans, elevations, sections, specifications
and details, to the satisfactions of the Metropolitan
Commissioner and confirming to the building lines marked on
the plan hereto annexed, and the Development Control
Regulations and Building Regulations, build and completely
finish, fit for occupation a building to be used as building with
all requisite drains and other proper convenience thereto.

(e) Extension of time stipulated for construction of
building or development of land:

(i) If the Lessee shall not perform and observe the
limitations of the time mentioned in clause 2(d) above for
construction of the intended building or otherwise
development of land leased to him for reasons beyond his
control, the Metropolitan Commissioner may permit extension
of such time on payment of additional premium at the
following rates:

Up to 1 year ______ 25 percent of the premium
Between 1 and 2 years ______ 35 percent of the premium
Between 2 and 3 years ______ 40 percent of the premium

(ii) If the Metropolitan Commissioner shall refuse to permit
such extension of time or shall find the Lessee of having
committed breach of any condition or covenant during

Page 30 of 50

::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:36:08 :::
Indian-Newspaper-oswp-864-2018-J-R.doc

limitation of time mentioned in clause 2(d) hereinbefore, the
Metropolitan Commissioner may forfeit and determine the
Lease; provided that in the event of such determination of
lease 25 percent of the premium paid by the Lessee to the
Lessor shall stand forfeited and the remaining 75 percent of
such premium shall be refunded to him; provided further that
the power to so determine the Lease shall not be exercised
unless and until the Metropolitan Commissioner shall have
given to the Lessee or left on some part of the demised
premises a notice in writing of his intention to do so and of
specific breach of the covenant or condition in respect of
which forfeiture is intended and default shall have been made
by the Lessee in remedying such breach within three months
from the service of a notice on him on the notice being left on
the demised premises.”

59. Thereafter, a Supplementary Lease Agreement was entered

by and between the parties on 22 nd April 2013 covering the

additional built up area. Articles 2(c), 2(d) and 2(e) of the

Supplementary Lease Deed are reproduced as hereunder:-

“2. It is hereby agreed and declared by and between the
parties hereto that–

(b) The Lessee shall use the said additional build up area
on the plot allotted to them and shall be at liberty to assign
the said constructed build up area subject to the terms &
conditions and covenants as setout in the said Lease Deed.

(c) All the conditions and covenants including the terms
of the lease and except the condition in Article 2(d) as
contained in the said Deed of Lease shall be deemed to be
incorporated herein and shall regulate the lease hereby
granted. It is further agreed and declared by the parties
hereto that the incremental premises hereby permitted to be
constructed and to be leased by the Lesor to the Lessee shall
be deemed to be the integral part of demised premises as
defined in the said Deed of Lease dated 9 th April 2008,
annexed hereto as ANNEXURE-I. There shall be no time limit
as contained in the Article 2(d) of the said Deed of Lease for
completion of construction of the building by using the said
additional built up area.

Page 31 of 50

::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:36:08 :::

Indian-Newspaper-oswp-864-2018-J-R.doc

(d) The Lessee shall not apply and Lessor shall not grant
Occupation Certificate in respect of the premises
constructed by using the said additional built up area as
required under the Development Control Regulations and
Building Regulations as also Municipal or any other
regulations so far as the same are applicable to the said plot
of land or to the use for which the said plot of land and/or
building there upon is going to be put to, unless Lessee pays
to the Lessor the balance lease premium of the said additional
built up area with interest due thereon or any other amount
due to the Lessor.”

60. The use of expressions such as “the incremental premises”

which shall be deemed to be “integral part of the demised

premises as defined in Deed of Lease dated 9th April 2008,” used in

Article 2(c) of the Supplementary Lease Deed makes it abundantly

clear that it was a case of composite construction meant to be

carried out over the same plot of land and in the same building.

Article 2(c) of the Supplementary Lease Deed dated 22 nd April

2013, also makes it amply clear that there shall be “no time limit”

for completion of construction of the building by using the

additional built-up area. It is, therefore, evident that after the

signing of the Supplementary Lease Deed dated 22 nd April 2013, in

view of Article 2(c), time was no longer the essence of the

contract for development of the land.

61. The unambiguous expressions used in Article 2(c) of the

Supplementary Lease Deed had clearly displaced the time

Page 32 of 50

::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:36:08 :::
Indian-Newspaper-oswp-864-2018-J-R.doc

restriction imposed under Article 2(d) of the Lease Deed dated 9 th

April, 2008 for completing the construction as long as the

construction is carried out by using the additional BUA. Had it

been the intention of the parties to still continue with time

restriction clause, as envisaged in Article 2 (d) of Lease Deed

even after allotment of the additional Built up Area and signing of

the Supplementary Lease Deed, then in that event, the said aspect

of the matter would have been clarified in the subsequent

agreement. However, the same was not done. If that be so, the

irresistible conclusion that would follow is that in view of Article

2(c) of the Supplementary Lease Deed dated 22 nd April 2013,

Article 2(d) of the original Lease Deed dated 9 th April 2008

imposing the time restriction for completing the construction was

no longer enforceable. We are, therefore, of the unhesitant

opinion that, in view of Article 2(c) of the Supplementary Lease

Deed, the Respondent No.1 did not have any right under the Lease

Agreement to insist on the time restriction clause of four years for

completing the construction by using the additional built up area.

62. It would be further pertinent to note herein that even

assuming that Article 2(d) of the Lease Deed dated 9 th April 2008,

Page 33 of 50

::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:36:08 :::
Indian-Newspaper-oswp-864-2018-J-R.doc

had any relevance after the allotment of the additional built-up

area, even then, it is apparent after the expiry of the four years

time from the Date of execution of the Lease Deed, although the

construction of the building was still incomplete, no default notice

was served upon the Petitioner. As a matter of fact, until 22 nd

August 2014, the Respondent No.1 had never raised any demand

seeking penalty nor did it threaten to determine the lease for any

reason whatsoever. The demand for payment of additional

payment/ penalty was also raised, under the circumstances noted

above, without calling for any explanation from the Petitioner as

to why such demand should not be raised, thus acting in clear

violation of the principles of the natural justice and administrative

fair play.

63. Although, there is no written communication from the

Respondent No. 1 available on record intimating the Petitioner

regarding expiry of the time limit for completing the construction,

yet, it appears that the Petitioner had, on its own volition, issued

communications dated 6th June 2012 (Exh.F) seeking extension of

time, which was followed up by the subsequent communications

dated 10th December 2012 (Exh.G) and 10th January 2013

Page 34 of 50

::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:36:08 :::
Indian-Newspaper-oswp-864-2018-J-R.doc

(Exh.H), whereby, it had deposited the amount of penalty for

delay but under protest. In all probability, such demand was made

by the Petitioner on the projection made by the Respondent No.1

threatening to determine the lease, thus, jeopardizing the entire

construction. However, since the payment was made under protest

and by reserving the right of the Petitioner to seek refund and

considering the fact that such demand was in conflict with Article

2(c) of the Supplementary Lease Deed dated 22 nd April 2013,

hence, we are of the view that the mere fact that the amount had

been deposited by the Petitioner would not be prejudicial to its

interest in any manner.

64. We also note herein that in the Demand Notice dated 22 nd

August 2014, although a threat was held out to determine the

lease until the outstanding dues were cleared by the Petitioner, the

Respondent No.1 did not specify any amount nor referred to the

specific articles of the Lease Deed which had allegedly been

violated by the Petitioner. Even in the subsequent Notice dated

12th September 2017, there is no mention as to in what manner,

the Petitioner had acted in violation of any specific Article of the

Lease Deed or for that matter, the exact amount which was found

Page 35 of 50

::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:36:08 :::
Indian-Newspaper-oswp-864-2018-J-R.doc

to be due and recoverable from the Petitioner. Considering the

nature of controversy involved in this Writ Petition, we deem it

appropriate to reproduce the Demand Notice dated 12 th

September 2017, as hereinunder:-

EXHIBIT = ‘N’
MUMBAI METROPOLITAN REGION DEVELOPMENT AUTHORITY
eqacbZ egkuxj izns’k fodkl izkf/kdj.k
_________________________________________________________
No.LEC/BKC (G)/INS(C-63)/1792/2017 Date: 12th September 2017
NOTICE
WHEREAS the Mumbai Metropolitan Region Development
Authority issued a Show Cause Notice dated 22/08/2014 for
non-payment of requisite dues and non-performance of the Lease
Deed conditions as stated therein.

WHEREAS you have submitted your say along with
explanation vide your letter dated 19/09/2014 & 22/09/2014.

WHEREAS your representation/explanation is examined
thoroughly and no merit was found in the submission/
explanation given by you.

AND WHEREAS the explanation submitted vide your
letter 19/09/2014 & 22/09/2014 dated with reference to the
Show Cause Notice is unsatisfactory and hence was summarily
rejected vide our letter dated 23/12/2014.

WHEREAS you were instructed to pay the outstanding
dues as stated in the Notice under reference within a period of 30
days. However, till date you did not pay the requisite dues to
MMRDA and thus failed to comply with your obligations.

AND WHEREAS the amount due to the Authority along
with the interest due thereon is as shown in the statement
annexed hereto as Annexure- A & B. An amount due to Authority
is un-paid till date & thus you have therefore committed breach
of the terms and conditions of the said Deed of Lease and
therefore, the Authority has power to recover the said due
amount as stated hereinbefore as arrears of land revenue and
also resume the said land as per the Article 5 and 6 of the said
Deed of Lease.

NOW THEREFORE, in exercise of the powers conferred by
Articles 5 and 6 of the said Deed of Lease, I, the Dy. Metropolitan
Commissioner for and on behalf of the Metropolitan

Page 36 of 50

::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:36:08 :::
Indian-Newspaper-oswp-864-2018-J-R.doc

Commissioner of the Authority hereby call upon you to remedy or
cause to be remedied within 30 days from the date of this notice.
Please take further notice that in the event of the default to
comply with this requisition, the Authority will have the right to
determine the Lease and enter upon the premises and proceed
further to recover the due amount stated hereinbefore as arrears
of land revenue.”

Sd/-

(A.R. Wankhade)
Dy. Metropolitan Commissioner,
M.M.R.D.A.
To,
The President,
Indian Newspaper Society,
INS Building,
Rafi Marg, New Delhi -110 001.

65. From a plain reading of the impugned Demand Notice, it is

clear that the same is devoid of any specific particulars as to the

head on which the amount was sought to be recovered. Rather, it

appears to be a completely vague and unsubstantiated notice

which did not refer to violation of any specific article of the Lease

Deed. Moreover, although the demand was admittedly a penal

action, no prior Show Cause was served upon the Petitioner

calling for any explanation. As such, impugned demand notice, in

the opinion of this Court, is liable to be declared illegal on the

ground of violation of the principles of natural justice alone.

66. There is no controversy in this case about the fact that the

Lease Deed(s) are contract agreements within the meaning of

Page 37 of 50

::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:36:08 :::
Indian-Newspaper-oswp-864-2018-J-R.doc

Section 10 of the India Contract Act,1872. Law is well settled that

while constructing the terms of a contract, the documents must be

read as a whole so as to ascertain the true intent of the parties.

67. In the case of Bank of India & Anr. Vs K. Mohandas, 5 the

Hon’ble Supreme Court has held that it is well recognized

principle of construction of contract that it must be read as a

whole in order to ascertain the true meaning of its several clauses

and the words of each clause should be interpreted so as to bring

them into harmony with the other provisions if that interpretation

does no violence to the meaning of which they are entirely

susceptible to. The observations made in paragraph 28 would be

relevant in the present case and, therefore, are being reproduced

herein-below for ready reference:-

“28. The true construction of a contract must depend upon the
import of the words used and not upon what the parties choose
to say afterwards. Nor does subsequent conduct of the parties in
the performance of the contract affect the true effect of the clear
and unambiguous words used in the contract. The intention of
the parties must be ascertained from the language they have
used, considered in the light of the surrounding circumstances
and the object of the contract. The nature and purpose of the
contract is an important guide in ascertaining the intention of the
parties.”

68. In the present case, if the intent of the parties was to

continue with the original time restriction clause as per Article

5 (2009) 5 SCC 313.

Page 38 of 50

::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:36:08 :::

Indian-Newspaper-oswp-864-2018-J-R.doc

2(d) of the Lease Deed dated 9th April 2008 notwithstanding the

allotment of the additional built up area, then in that event, there

was nothing preventing the Respondent No 1 to clarify the same in

the Supplementary Leased Deed. The same was, however, not

done. On the contrary, as has been noted above, a specific

stipulation in the form of Article 2(c), completely dispensing with

the time restriction, was inserted in the Supplementary Lease

Deed, thus signifying a clear policy shift as regards the time

restriction for completing the construction.

68. Law is well settled that the onus to remove ambiguity in a

contract would always be on the party drafting the contract.

Therefore, if there is any ambiguity in the contract, the benefit of

the same must be resolved in favour of the party which is not

responsible for creating the ambiguity.

69. The legal maxim “Contra Proferentum” means, ambiguity to

be resolved against the party which had drafted the contract.

While dealing with the maxim “Contra Proferentum”, the Hon’ble

Supreme Court, in case of Industrial Promotion and Investments

Page 39 of 50

::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:36:08 :::
Indian-Newspaper-oswp-864-2018-J-R.doc

Corporation of Orissa Ltd., vs New India Assurance Co. Ltd. &

Anr.,6 has made the following observations:-

“We proceed to deal with the submission made by the counsel
for the appellant regarding the rule of contra proferentem. The
Common Law rule of construction “verba chartarum fortius
accipiuntur contra proferentem” means that ambiguity in the
wording of the policy is to be resolved against the party who
prepared it. MacGillivray on Insurance Law deals with the rule
of contra proferentem as follows:

“The contra proferentem rule of construction
arises only where there is a wording employed by those
drafting the clause which leaves the court unable to
decide by ordinary principles of interpretation which of
two meanings is the right one. ‘One must not use the
rule to create the ambiguity — one must find the
ambiguity first.’ The words should receive their
ordinary and natural meaning unless that is displaced
by a real ambiguity either appearing on the face of the
policy or, possibly, by extrinsic evidence of surrounding
circumstances.”

70. From a careful analysis of Articles 2(d) of the Lease Deed

dated 9th April,2008 and Article 2(c) of the Supplementary Lease

Deed dated 22nd April,2013, we are of the opinion that both the

Articles cannot be simultaneously enforced in the respect of the

same construction since the construction is composite in nature.

We, therefore, find force in the submission of the learned counsel

for the Petitioner that it would be impossible to implement Articles

2(d) of the Lease Deed and 2(c) of the Supplementary Lease Deed

referred to above, on the same construction and at the same time.

6 (2016) 15 SCC 315

Page 40 of 50

::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:36:08 :::
Indian-Newspaper-oswp-864-2018-J-R.doc

71. We have taken note of the stand of the Respondents that

Clause 2(d) of the Lease Deed dated 9 th April 2008 puts in place a

policy decision of the authority and, therefore, the same is not

amenable to challenge by one of the contracting parties by

invoking the writ jurisdiction of the Writ Court under Article 226

of the Constitution of India. However, we are of the view that such

arguments of the Respondents cannot be countenance in view of

the law laid down in the case of Industrial Promotion and

Investments Corporation of Orissa Ltd., vs New India Assurance

Co. Ltd. & Anr. (Supra), which categorically lays down that the

principle of “Contra Proferentum” would apply even in a case

where there is ambiguity in the wording of the policy.

72. It would be apparent from the observations made above

that the Petitioner did not deposit the amount of Penalty

voluntarily but the same was done under pressure and on the face

of the threat issued by the Respondent No. 1 to terminate the

Lease and also cancel the CC. Therefore, it is apparent that the

amount of penalty deposited by the Petitioner was obtained under

duress and / or coercion.

Page 41 of 50

::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:36:08 :::

Indian-Newspaper-oswp-864-2018-J-R.doc

73. Section 72 of the Indian Contract Act provides that a person

who receives payment made by the payee under coercion must

repay or return the same.

74. In Fatima Khatoon Chowdrain vs. Mahmoed Jan

Chowdhury,7 the Privy Council has held that payment made not

voluntarily but under species of compulsion would be liable to be

returned.

75. In Valpy vs Manley,8 the Court of England & Wales has held

that money paid under the constraint of threats to interfere with

the legal right is sufficient to make it recoverable.

76. In Ram Kishen Singh vs. Dooli Chand9 before the Privy

Council, it was held that if a person pays money to save his

property which has been wrongly attached in execution, he is

entitled to recover it.

77. Relying upon the case of Ram Kishen Singh (Supra), the

Privy Council in the case of Kanhaya Lal vs The National Bank of

India Limited10 has held that if a payment is made under protest
7 (1868) 12 Moo Ind App 65.

8 (1845) 1 CP 594.

9 (1881) 8 IA 93.

10 1913 SCC Online PC 4.

Page 42 of 50

::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:36:08 :::

Indian-Newspaper-oswp-864-2018-J-R.doc

and involuntarily, under coercion, the party making such payment

would be entitled to claim refund of the same.

78. In view of the discussions in the foregoing paragraphs, we

are of the considered opinion that the demand for additional

premium/penalty raised by the Respondent No. 1 on account of

delay in completing the construction was dehors the terms of the

Lease Deed and hence, was not authorized under the law. The

Respondents have acted in a highly arbitrary and high handed

manner by realizing such amount from the Petitioner under duress

and coercion.

79. It is to be noted here that in a matter of this nature, where

the Authority is seeking to recover penalty for default on grounds

which are not admitted, the recovery cannot be based on mere

ipse dixit, but upon proper resolution of the controversy in

accordance with law, more so, when such claim arises out of a

contract wherein the Authority itself is a party.

80. Having held as above, we deem it appropriate to record

here-in that although the learned Counsel for the Petitioner has

argued that this case is squarely covered by the decision rendered

Page 43 of 50

::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:36:08 :::
Indian-Newspaper-oswp-864-2018-J-R.doc

in Raghuleela Builders Pvt. Ltd. & Anr . (Supra),yet, the said

assertion has been strongly contested by the Respondent’s Counsel

by submitting that in view of the observations made by the

Hon’ble Supreme Court in the order dated 27 th July 2020, no

reliance can be placed on the said judgment on any count for the

purpose of deciding the present Writ Petition. On a careful

examination of the decision in Raghuleela Builders Pvt. Ltd. &

Anr. (Supra) we also find that the said decision was rendered in

the facts of that case. However, it is important to note here-in that

one of the question raised in the said proceedings was pertaining

to the question as to whether, the decision of the MMRDA to apply

the extension of time from 4 years to 6 years for completing the

construction only to the post August 2015 was valid in the eyes of

law, is also a question raised in the present proceeding. While

answering the said question, it was held in Raghuleela Builders

Pvt. Ltd. & Anr. (Supra), as follows:-

“38. The MMRDA constituted a single member committee of
retired Judge of the Supreme Court to decide whether the
MMRDA should give concession in recovery of premium
considering the time required for plot owner to obtain
permissions from various authorities for construction of building
thereon. It is contended that one member committee has
concluded that the charging of premium for extension of time
for completing construction in Bandra-Kurla Complex area,
specifically in case where additional built up area has been
allotted by the MMRDA, was illegal. In its 138th meeting held

Page 44 of 50

::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:36:08 :::
Indian-Newspaper-oswp-864-2018-J-R.doc

on 26th August 2015, the MMRDA had acknowledged the
difficulties faced by the lessees and that the condition of
completion of construction within 4 years of the execution of the
lease was adversely affecting the tendering process. The
MMRDA had appointed an expert one man committee of retired
Supreme Court Judge in that regard. The single member
committee has advised that the period of 6 to 7 years be granted
for completion of construction.

39. The lease deed entered into by the MMRDA with the
lessees are as per form D, prescribed under the MMRDA
(Disposal of Lands) Regulations 1977. Clause 2(a) of the lease
deed provides that for building plans to be submitted to country
and town planing division for approval within 3 months from
the date of lease. Clause 2(c) of the lease deed provides that no
work is to be carried out until all plans, elevations, specifications
are approved by the concerned authorities. Clause 2(d) provides
that within 3 months of the approval of plans, the lessee is to
commence construction which is to be completed within four
years of the lease. Clause 2(e) provided for extension of time.
Clause 2(e) contemplates a situation when the time for
completion of construction can be extended, parties to the
contract contemplated that certain uncertainties or situations
may arise which may require more time for completion of the
construction. In view of this, time is not essence of the contract
between the parties and rightly so since construction of any
building in Bandra Kurla Complex, several permissions are
required from the various authorities and not only from the
MMRDA who is planning authority for the Bandra Kurla area,
namely,
(1) The environmental clearance under the
Environmental Impact Notification from the Ministry of
Environment and Forest.

(2) Building height clearance from the Ministry of
Civil Aviation because of the close proximity to Airport.

                (3)        Clearance from the high rise committee.
                (4)        Permission from the the MCGM.
                (5)        Permission from the traffic police.

Each of these authorities is required to be approached
separately since there is no single window clearance / nodal
agency which would co-ordinate with the aforesaid authorities
for granting of all necessary permissions. In view of the delay in
obtaining permissions which are beyond the control of lessee, no
work could be carried out as per clause 2(d) of the lease deed.

Page 45 of 50

::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:36:08 :::

Indian-Newspaper-oswp-864-2018-J-R.doc

40. The MMRDA had issued a letter of allotment dated 20th
March 2012 allotting additional 67,000 sq. meters at
consideration of 984 crore. Part payment of Rs.196 crore was
received on 20th March 2012. The supplementary lease deed
was executed for additional built up area of 67,000 sq. meters.
The letter of allotment dated 20th March 2012, the acceptance
of part payment of consideration for additional built up area
allotted, diluted the time period of four years and there was no
question of application of condition of occupation certificate for
built up area within 4 years when additional built up area was
allotted for raising additional 11 floors on the same building.

41. The resolution passed by MMRDA for extending the time
period for completing construction from 4 years to 6 years only
for leases executed after 26th August 2015 also appears to be
arbitrary, discriminatory, without basis and justification. The
same set of circumstances are prevailing for the construction
being carried out under the leases executed prior to 26th August
2015. Therefore, not extending this benefit of this extension of
time from 4 years to 6 years to the prior leases in respect of
other plots in the BKC, is completely arbitrary, discriminatory,
capricious and violative of Article 14 of the Constitution of
India. There is no reasonable basis or justification for this
decision. The classification sought to be made between the
leases prior and subsequent to 26th August 2015 is not founded
on intelligible differentia and neither does this differentia has
any logic, rational, nexus to the object sought to be achieved.
The MMRDA has sought to treat equals as unequal. The lessees
of plots are being discriminated on the basis of their date of
execution of their leases. The lessees who are placed in similar
circumstances prevailing for construction in Bandra Kurla area
are entitled to equal treatment guaranteed under Article 14 of
the Constitution of India.”.

81. It is not in dispute that the Lease Deed involved in

Raghuleela Builders Pvt. Ltd. & Anr. (Supra) was also in Form ‘D’

of the Regulations of 1977 wherein the same Articles 2 (d) and (e)

were involved. The Writ Petitioner there-in was also a similarly

situated lessee, from whom, penalty for delay in completing the

construction beyond the period of 4 years was raised by the

Respondent No 1. The Petitioner in that case had also raised

Page 46 of 50

::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:36:08 :::
Indian-Newspaper-oswp-864-2018-J-R.doc

identical plea as regards the applicability of the time extension

Clause. The Lease Deed in that case was also executed prior to 26 th

August, 2015. If that be so there can be no doubt about the fact

that the legal principles discussed and the findings & observations

recorded in paragraphs 38 and 41 of Raghuleela Builders, in so

far as uniform applicability of the 6 years time extension clause is

concerned, would be applicable to the facts of the present case as

well. Therefore, we hold that by applying the principles parity, the

Respondent No. 1 would be duty-bound to extend the same

benefit of extension of time for completion of construction to six

years to the present Petitioner as well.

82. In the facts and circumstances of this case, we are also of

the opinion that there is no legal justification for the Respondent

No. 1 to confine the benefit of the time extension clause only to

those Lease Agreements which were executed after 26 th August

2015 as such an approach would be highly arbitrary and

discriminatory in nature. Therefore, having regard to the peculiar

facts and circumstances of this case, we do not find any justifiable

ground to take a different view on the aforesaid issue.

Page 47 of 50

::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:36:08 :::

Indian-Newspaper-oswp-864-2018-J-R.doc

83. Law is well settled that for maintaining judicial discipline

and propriety, a decision rendered by a Coordinate Bench on the

same issue must be respected and followed by a Coordinate

Bench. In the case of Mary Pushpam vs. Televi Curusumary &

Ors.11 the Hon’ble Supreme Court has observed that when a

decision of a Coordinate Bench of the same High Court is brought

to the notice of the Bench, it is to be respected and would be

binding, subject to the right of the Bench of such co-equal forum

to take a different view and refer the question to a larger Bench.

In other words, any decision of a Coordinate Bench would be

binding on a Bench of equal strength subject to the condition that

if a different view is sought to be taken in the matter, then the

issue would have to be referred to a larger Bench.

84. The above legal principle has taken a firm footing in the

Indian Jurisprudence by a long line of judicial pronouncements.

We do not deem it necessary to burden this judgment by referring

to all those decisions. However, suffice it to mention here-in that

unless there are justifiable grounds to take a different view in the

matter warranting reference to a larger Bench, the previous

11 (2024) 1 SCR 11.

Page 48 of 50

::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:36:08 :::

Indian-Newspaper-oswp-864-2018-J-R.doc

decision of a coordinate Bench would be binding on a Bench of

equal strength.

85. For the reasons stated above we hold that the Demand

Notices dated 22nd August 2014 as well as 12 th September 2017

are illegal, dehors the terms and conditions of the Lease Deeds as

well as the authority of law. Therefore, the same are hereby set

aside.

86. The Writ Petition stands allowed in terms of prayer clauses

(A) and (B).

87. From the statements made in the Writ Petition it appears

that the Petitioner had deposited an amount of Rs 13,78,59,150/-

as penalty by the letter dated 19/09/2014 and thereafter, a

further amount of Rs. 8.85 crores on 23/12/2014, totaling to Rs

22,63,59,150/-. In view of the determination made above, the

Respondent No. 1 is directed to verify and refund the entire

amount paid by the Petitioner on additional premium/penalty,

within a period of 90 (ninety) days from the date of receipt of a

Certified Copy of this order, failing which, the amount would carry

interest at the rate of 14% per annum i.e. the same rate at which,

Page 49 of 50

::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:36:08 :::
Indian-Newspaper-oswp-864-2018-J-R.doc

interest was payable by the Petitioner under the Lease Agreement

due to delay in payment of outstanding dues, to be calculated

from the date of this order till the amount is refunded.

88. With the above observations, Rule is made absolute.

89. The Writ Petition is disposed of accordingly.

90. Parties to bear their own costs.

(SUMAN SHYAM, J)                                              (CHIEF JUSTICE)




                                Page 50 of 50


::: Uploaded on - 09/04/2026                        ::: Downloaded on - 09/04/2026 21:36:08 :::
 



Source link