Reliance Industries Ltd. And Anr. vs The Mumbai Metropolitan Region … on 8 April, 2026

    0
    65
    ADVERTISEMENT

    Bombay High Court

    Reliance Industries Ltd. And Anr. vs The Mumbai Metropolitan Region … on 8 April, 2026

    2026:BHC-OS:8906-DB
                                                                             Reliance-oswp-242-2018-J-R.doc
    
    
    
    
                                                                                                        Shephali
    
    
    
                                   IN THE HIGH COURT OF JUDICATURE AT BOMBAY
                                       ORDINARY ORIGINAL CIVIL JURISDICTION
                                           WRIT PETITION NO. 242 OF 2018
                                                       WITH
                                       INTERIM APPLICATION NO. 2172 OF 2020
                                                        IN
                                           WRIT PETITION NO. 242 OF 2018
    
    
                         1.     Reliance Industries Limited,
                                A company incorporated under the
                                Companies Act, 1956 having its
                                Registered Office at Maker Chamber IV,
                                3rd Floor, Nariman Point,
                                Mumbai 400 021
                         2.     Mr. Rajumal Nahar,
    SHEPHALI                    having his office at having his office at
    SANJAY
    MORMARE                     6th Floor, "B" Wing, Fortune 2000, "G"
     Digitally signed           Block, Bandra Kurla Complex,
     by SHEPHALI
     SANJAY
     MORMARE
                                Bandra (East), Mumbai 400 051.                             ...Petitioners
     Date: 2026.04.09
     15:15:50 +0530
    
                                  ~ versus ~
    
                         1.     Mumbai Metropolitan Region
                                Development Authority (MMRDA),
                                an authority established under the
                                Mumbai Metropolitan Region
                                Development Authority Act, 1974 and
                                having its head Office at Plot C-14 &
                                C-15, 'E' Block, Bandra Kurla Complex,
                                Bandra (East), Mumbai 400 051.
                         2.     The Metropolitan Commissioner,
                                Mumbai Metropolitan Region
                                Development Authority, having office
                                at Plot C-14 & C-15, 'E' Block, Bandra
                                Kurla Complex, Bandra (East),
                                Mumbai 400 051.
    
    
    
    
                                                         Page 1 of 65
    
    
                        ::: Uploaded on - 09/04/2026                        ::: Downloaded on - 09/04/2026 21:35:21 :::
                                                       Reliance-oswp-242-2018-J-R.doc
    
    
    
    
     3.     The Deputy Metropolitan
            Commissioner,
            Mumbai Metropolitan Region
            Development Authority, having office
            at Plot C-14 & C-15, 'E' Block, Bandra
            Kurla Complex, Bandra (East),
            Mumbai 400 051.                                      ...Respondents
    
     A PPEARANCES
     For the Petitioners               Mr.    Vikram     Nankani,    Senior
                                       Advocate, with Mr. Vikramaditya
                                       Deshmukh, Mr. Ashwin Dave,
                                       Mr. Ameya Nabar & Ms. Swati Jain,
                                       i/b A. S. Dayal & Associates.
     For Respondents-MMRDA             Dr. Birendra Saraf, Senior Advocate,
                                       with Mr. Nishant Chotani, Mr. Nivit
                                       Srivastava,   Ms.      Sneha   Patil,
                                       Ms. Aditi Sinha, Mr. Hrishikesh
                                       Joshi & Ms. Isha Vyas, i/b Maniar
                                       Srivastava Associates.
    
    
    
                           CORAM   :    SHREE CHANDRASHEKHAR, CJ &
                                        SUMAN SHYAM, J.
               RESERVED ON         :    22nd JANUARY 2026.
            PRONOUNCED ON          :    8th APRIL 2026.
    
     JUDGMENT (Per Suman Shyam, J):

    1. Rule. Rule is made returnable forthwith.

    SPONSORED

    2. By consent of the parties, the matter is taken up for final

    hearing.

    Page 2 of 65

    ::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:35:21 :::

    Reliance-oswp-242-2018-J-R.doc

    3. Assailing the demand-cum-show cause notice dated 12 th

    September 2017 (Exhibit “R”), whereby, the Respondent No.1-

    Mumbai Metropolitan Region Development Authority (“MMRDA”)

    had demanded additional premium/penalty as per statements ‘A’

    and ‘B’ annexed thereto, for the alleged delay of 7 years and 12

    days in completion of construction of a Convention & Exhibition

    Centre and Commercial Complex on Plot No. C-64, ‘G’ Block,

    Bandra-Kurla Complex, Mumbai, the Petitioners have approached

    this Court by filing this Writ Petition invoking the jurisdiction of

    this Court under Article 226 of the Constitution of India. During

    the pendency of the Writ Petition, by the communication dated

    13th June 2019 (Exhibit “X”) a further amount of

    Rs.1116,83,10,102/- was demanded from the Petitioner No. 1 as

    additional premium, along with interest, towards extension of

    time for completing the construction of the building by using the

    additional built up area of 72,500 sq mtrs. allotted under the

    Supplementary Lease Deed dated 13 th July 2007. The said Notice

    is also under challenge in this Writ Petition. The facts and

    circumstances giving rise to the filing of the present Writ Petition,

    shorn of unnecessary details, are as hereunder.

    Page 3 of 65

    ::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:35:21 :::

    Reliance-oswp-242-2018-J-R.doc

    4. The Petitioner No.1 is a company incorporated under the

    provisions of the Companies Act, 1956. As per statements made in

    the Writ Petition it is engaged inter alia in the business of

    exploration of petroleum products and allied activities. Petitioner

    No.2 is a shareholder of the Petitioner No.1 company. The

    expression “Petitioner” shall here-in-after refer to the Petitioner

    No.1 company. The Respondent No.1, MMRDA, is a statutory

    authority constituted under Section 3 of the Mumbai Metropolitan

    Region Development Authority Act, 1974. Respondent Nos.2 and 3

    are its officers.

    5. In the month of December 2005, Respondent No.1, being

    the owner of the land, had invited bids for leasing out Plot No. C-

    64 admeasuring approximately 75,000 sq. mtrs. situated in ‘G’

    Block of Bandra-Kurla Complex (BKC) for the purpose of

    construction of “Convention and Exhibition Centre and

    Commercial Complex”. The Petitioner had submitted its bid for the

    said plot and was declared successful bidder. As such, by the letter

    dated 15th February 2006, the Respondent No.1 had approved the

    proposal for leasing out the aforesaid plot of land to the Petitioner

    for a maximum permissible built-up area of 65,000 sq. mtrs. for

    Page 4 of 65

    ::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:35:21 :::
    Reliance-oswp-242-2018-J-R.doc

    the Convention and Exhibition Centre and 50,000 sq. mtrs. for the

    Commercial Complex, aggregating to 1,15,000 sq. mtrs., for a

    total premium of Rs.1104 crores. Pursuant thereto, a registered

    Lease Deed dated 1st September 2006 came to be executed by and

    in between the Petitioner and Respondent No.1 for leasing out the

    demised plot for a term of 80 years. Possession of the said plot of

    land was handed over to the Petitioner on the same day i.e. on 1 st

    September 2006.

    6. Article 2(d) of the Lease Deed dated 1st September, 2006

    stipulates that the lessee shall, within three months from receipt of

    approval of plans, commence and within a period of four years

    from the date of the lease, build and completely finish the

    construction of the Convention and Exhibition Center and

    Commercial Complex, fit for occupation. Article 2(e) lays down

    that in case of failure to adhere to the said time limit, extension of

    time may be granted upon payment of additional premium at the

    prescribed rates.

    7. On 14th October 2006 the Petitioner had applied for

    permission to start excavation and removal of earth on site by

    attaching a report of the Structural Consultants. By the said letter,

    Page 5 of 65

    ::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:35:21 :::
    Reliance-oswp-242-2018-J-R.doc

    the Petitioner had also informed the Respondents that it will not

    carry out any construction activity on the site without prior

    intimation to the MMRDA and also without obtaining the required

    statutory permissions.

    8. After the execution of the Leased Deed dated 1 st September

    2006, the FSI for the plots in block ‘G’ of BKC was increased from

    2.00 to 4.00. As such, in the month of February 2007, the

    Petitioners had applied for allotment of additional built-up area of

    72,500 sq. mtrs.. By the letter dated 7 th May 2007, the Respondent

    No.1 had approved the allotment of additional built up area of

    41,000 sq. mtrs. for the Convention Centre and 31,500 sq. mtrs.

    for the Commercial Complex, aggregating to 72,500 sq mtrs.,

    against payment of premium of a total amount of Rs.696 crores.

    Upon allotment of the additional built up area, as aforesaid, a

    Supplementary Lease Deed dated 13th July 2007 was executed by

    and between the parties in respect of the additional built-up area.

    9. It would be pertinent to note herein that after the allotment

    of the additional built up area, Reliance Communication &

    Infrastructure Ltd., along with another, had instituted Writ Petition

    No.1165 of 2007 before this Court challenging the grant of the

    Page 6 of 65

    ::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:35:21 :::
    Reliance-oswp-242-2018-J-R.doc

    additional FSI of 71,500 sq mtrs to the Petitioner for the

    Convention and Exhibition Centre (41,000 sq mtrs) and

    Commercial Complex (31,500 sq mtrs). The Petitioner was

    impleaded as Respondent No. 3 in that writ petition. By the

    interim order dated 15th October 2007 passed in the said Writ

    Petition, a Division Bench of this Court had restrained the

    Petitioner from utilizing the additional FSI of 31,500 sq. mtrs.

    allocated for the Commercial Complex.

    10. On 17/04/2008, the Petitioner submitted revised plans

    seeking necessary approvals. Based on the same, on 12 th

    June,2008, Commencement Certificate (CC), upto the plinth level,

    only in respect of the Convention & Exhibition Centre plot “A’ of

    plot C-64 in Block “G” of BKC Complex, with total permissible

    built up area of 1,06,000sq mtrs. was issued in favour of the

    Petitioner. However, no CC was issued in respect of the

    commercial complex.

    11. There is no controversy in this case about the fact that the

    proposed development was composite in nature with common

    basement and foundation. As such, by the letter dated 28 th

    January 2009, the Petitioner had submitted progress report and

    Page 7 of 65

    ::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:35:21 :::
    Reliance-oswp-242-2018-J-R.doc

    informed the Respondent No.1 that commencement of

    construction at site was affected due to the interim order passed

    by the court since the basement and foundation of the Convention

    & Exhibition Centre (CEC) as well as the Commercial Complex

    (CC) was common. However, by letter dated 18 th February 2009,

    the Respondent No.1 had replied that since there was no restraint

    order in respect of the Convention & Exhibition Centre, hence,

    the Petitioner to continue with the construction of the CEC as per

    CC (1,06,000 sq mtrs) and also expedite the final hearing of the

    proceeding pending in the court. The Petitioner was also asked to

    furnish Bank Guarantee of Rs 20 crores towards liquidated

    damage and Completion Guarantee for a sum of Rs 20 crores.

    12. In response to the above, by the letter dated 16 th March

    2009, the Petitioner had highlighted the design uncertainty in

    proceeding with the construction and had sought the guidance of

    the MMRDA in the matter. Due to the uncertain circumstances

    arising in view of the pending Court proceedings, the Petitioner

    had also sought extension of time to complete the project.

    However, in the meantime, the Commencement Certificate issued

    earlier on 12th June 2008 had lapsed in June 2009.

    Page 8 of 65

    ::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:35:21 :::

    Reliance-oswp-242-2018-J-R.doc

    13. While the matter was poised as above, in the 129 th Meeting

    of the MMRDA held on 8th September 2011, the Respondent No.1

    had resolved to extend the time for allotment of additional FSI in

    ‘G’ Block till December 2012. Accordingly, by the letter dated 8 th

    November 2011, the Respondent No.1 had offered additional

    built-up area to the Petitioner by recording that there would be no

    time limit for construction of such additional built-up area.

    14. However, in view of the pendency of Writ Petition No 1165

    of 2007 and the interim order operating therein, on 14 th October

    2010, the Petitioner had offered to surrender the additional built

    up area of 72,500 sq.mtrs and sought refund of the amount of Rs

    1064 crores being the premium, along with interest, paid for the

    aforesaid built up area. The said request was followed by the

    subsequent letters dated 3rd August 2020 and 10th January 2012

    rehearing the request. In response to the above request of the

    Petitioner, by the letter dated 1st February 2012, the Respondent

    No.1 had informed the Petitioner that its request for refund of

    lease premium by surrendering the additional built up area cannot

    be considered as there is no provision in the Leased Deed as well

    the Supplementary Lease Deed permitting the same. It was,

    Page 9 of 65

    ::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:35:21 :::
    Reliance-oswp-242-2018-J-R.doc

    however, clarified that in so far as the request for extension of

    time for completion of construction on the plot under reference as

    per Article 2(d) of the Lease Deed dated 1 st September 2006, is

    concerned, the period during which the stay order of the court

    was under operation, will not be considered for computing the

    four years time period, meaning thereby, that the period, during

    which the interim order passed in Writ Petition No.1165 of 2007

    was operative, shall be excluded while computing the four-year

    period stipulated under Article 2(d) of the Lease Deed dated 1 st

    September, 2006. Be it stated here in that the Writ Petition No

    1165 of 2007 was withdrawn on 12 th March 2012 as a result of

    which, the stay order also got vacated on the same day.

    15. In the wake of the aforesaid development, the Respondent

    No.1, by letters dated 20th March 2012 and 3rd April 2012

    approved allotment of further additional built-up area of 1,00,000

    sq. mtrs. and 25,000 sq. mtrs. against payment of premiums of

    Rs.1470 crores and Rs.367.50 crores respectively. With the

    allotment of the additional built up area of 1,25,000 sq mtrs, the

    total built-up area allotted by the Respondent No.1 to the

    Petitioner for construction to be carried out on the same plot, was

    Page 10 of 65

    ::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:35:21 :::
    Reliance-oswp-242-2018-J-R.doc

    increased to 3,12,500 sq. mtrs. It is a matter of record that the

    Petitioner had paid an aggregate premium of Rs.4,005 crores to

    the Respondent No.1 for the allotment of the entire built up area

    of 3,12,500 sq. meters.

    16. In view of the allotment of additional built-up area, as

    aforesaid, the Petitioner was required to revise the development

    plans for a composite structure and also obtain various statutory

    approvals afresh including the environmental clearance under the

    EIA Notification dated 14th September 2006, height clearance from

    Civil Aviation Authorities, approval from the High Rise Committee,

    permission from the Municipal Corporation of Greater Mumbai

    and other statutory authorities. Accordingly, various approvals

    were obtained during the year 2013 and early part of the year

    2014.

    17. On 26th June 2013, Environment Clearance for the proposed

    ” Convention & Exhibition Centre and Commercial Complex” over

    plot No. C-64 in Block-G of BKC was granted to the Petitioner for

    the entire FSI of 3,12,500 Sq. Mtrs. In the said communication

    also, the CEC & CC was shown as a composite construction.

    Page 11 of 65

    ::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:35:21 :::

    Reliance-oswp-242-2018-J-R.doc

    18. After compliance of the above requisites and submission of

    the revised plans, the Respondent No.1 had issued

    Commencement Certificate dated 16th April 2014 for construction

    upto the 7th floor level of the composite building comprising

    Convention & Exhibition Centre and Commercial Complex.

    Thereafter, further Commencement Certificates were issued on

    23rd December 2016, 17th April 2017 and 19th May 2017.

    19. In the meantime, in its 131st Meeting held on 22nd October

    2012, the Respondent No.1 had considered granting extension of

    time for completion of construction by taking note of the delay

    caused in obtaining multiple statutory permissions/ clearance

    form different agencies. After considering the matter, the

    Respondent No.1, vide Resolution No.1283 adopted in the said

    meeting, had recommended extension of time from four years to

    six years for completing the construction. The said resolution was,

    however, kept in abeyance for some. Finally, in its 138 th Meeting

    held on 26th August 2015, the Respondent No.1 had resolved to

    amend Article 2(d) to provide six years time period for completion

    of construction in respect of plots leased after the date of the

    resolution and further resolved to constitute a One Man

    Page 12 of 65

    ::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:35:21 :::
    Reliance-oswp-242-2018-J-R.doc

    Committee to examine the issue of recovery of additional

    premium in the cases where delay was attributable to time

    required for obtaining statutory permissions.

    20. Notwithstanding the above developments,the Respondent

    no.1 had insisted on an undertaking from the Petitioner to pay

    the additional premium for grant of extension of time for

    completing the construction of the building. As such, on 18 th

    November 2016, the Petitioner had submitted an undertaking to

    the above effect thus, agreeing to pay the additional premium for

    extension of time for completing the construction of the building

    over Plot No- C-64 in Block “G” of the BKC before receipt of

    Occupation Certificate or decision of the Authority, which ever was

    earlier, with a further undertaking not to create any third party

    liability on the project till receipt of the Occupation Certificate.

    21. Based on such undertaking, the Respondent No 1 had issue

    further Commencement Certificate dated 19th May 2017 for the

    Fire Check floor and the 15th (part) floor.

    22. While the above process was under way, the Respondent No.

    1 had issued the impugned Notice dated 12 th September 2017,

    Page 13 of 65

    ::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:35:21 :::
    Reliance-oswp-242-2018-J-R.doc

    alleging that as per Article 2(d) of the Lease Deed dated 01 st

    September 2006, the Petitioner had the obligation to erect and

    completely finish the construction, fit for occupation, within four

    years from the date of execution of the Lease Deed. However,

    although, there was delay of 7 years and 12 days the Petitioner

    had failed to pay the penalty for the entire period of delay till

    completion of the construction, fit for occupation. It was further

    mentioned that the amount on account of delay in construction,

    along with interest, has been shown in Annexures “A” and “B”. It

    was alleged that the Petitioner had committed breach of the terms

    and conditions of the Deed of Lease. As such, the MMRDA had the

    power to recover the said amount as arrears of land revenue and

    also resume the land as per Articles 5 & 6 of the Lease Deed. The

    Petitioner was, therefore, called upon to remedy the situation

    within 30 days, failing which, the Authority will have the right to

    determine the lease and enter upon the leased premise and also

    proceed to recover the amount due as arrears of land revenue.

    23. It would be pertinent to mention here-in that the Notice

    dated 12th September, 2017 does not mention the amount claimed

    by the Respondent No. 1. The figures projected in the Statements

    Page 14 of 65

    ::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:35:21 :::
    Reliance-oswp-242-2018-J-R.doc

    “A” & “B” annexed to the Writ Petition are also not legible.

    However, it appears that upon receipt of the Notice dated 12 th

    September 2017, the Petitioner had sent reply dated 11 th October

    2017 denying its liability to pay the amount claimed with a further

    request to withdraw the show cause notice dated 12 th September,

    2017. However, no action was taken by the Respondents on such

    request made by the Petitioner.

    24. Aggrieved by the dated 12th September 2017 the Petitioner

    had instituted Writ Petition on 30 th November, 2017 which was

    originally registered as Writ Petition (L) No 3395 of 2017. On 8 th

    December 2017, this Court, while issuing notice, had recorded the

    statement made on behalf of Respondent No.1 that till next date

    of hearing no coercive steps would be taken pursuant to the

    impugned notice. Records reveal that the said ad-interim order

    was extended by the court from time to time. Subsequently, the

    said writ petition was registered as Writ Petition No.242 of 2018

    i.e. the present Writ Petition.

    25. On 06th February 2019, the Architect engaged by the

    Petitioner had applied for part Occupation Certificate for the built

    up area of 44,621 sq.mtrs. That apart, by the letter dated 18 th

    Page 15 of 65

    ::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:35:21 :::
    Reliance-oswp-242-2018-J-R.doc

    February 2019, the Petitioner had deposited a sum of

    Rs.646,77,68,594 (Rupees Six Hundred and Forty Six Crores

    Seventy Seven Lakhs Sixty Eight Thousand Five Hundred and

    Ninety Four) after deducting TDS amount of Rs.21,32,20,676/-

    and furnished a Bank Guarantee of an amount of

    Rs.13,12,54,85,287/- (Rupees Thirteen Hundred Twelve Crores

    Fifty Four Lakhs Eighty Five Thousand Two Hundred and Eighty

    Seven) based on an alternate computation treating the delay to be

    for the period from 01st September 2010 to 17th February 2019. It

    was also mentioned in that letter that the amount was being

    deposited under protest and without prejudice to the rights and

    contention of the Petitioner in the pending Writ Petition.

    26. Upon receipt of the above amount, on 20 th February 2019,

    the Respondent No.1 had issued part Occupation Certificate for

    44,621 sq. mtrs. However, soon thereafter i.e. on 13 th June 2019,

    the Petitioner was served with another communication demanding

    payment of a further amount of Rs.1116,83,10,102/- as additional

    premium for the delay in completing the construction of the

    additional built up area as allotted under the Supplementary

    Lease Deed dated 13th July 2007.

    Page 16 of 65

    ::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:35:21 :::

    Reliance-oswp-242-2018-J-R.doc

    27. Despite the notice dated 13th June 2019, the Petitioner,

    through its Architect, had applied for further part Occupation

    Certificate for the built up area of 1,24,000 sq. mtrs. However, the

    Respondent No. 1 refused to process the same until the amount of

    Rs.1116,83,10,102/- was paid. Under such circumstances, the

    Petitioner had filed Interim Application No.2171 of 2020 arising

    out of this Writ Petition, seeking a direction upon the Respondent

    No.1 for issuance of Occupation Certificate without insisting upon

    payment of the additional premium. By the judgment and order

    dated 12th July 2021 passed in the Interim Application No. 2171 of

    2020, this Court had allowed the prayer made in the Interim

    Application and directed the Respondent No.1 to process the

    applications seeking Occupation Certificates including the

    application dated 3rd February 2020, without insisting on payment

    of the amount mentioned in the subsequent demand notice dated

    13th June 2019. In the said order it was also observed that when

    the court was in seisin of the matter and considering the earlier

    interim order dated 8th December 2017, the Respondents ought

    not to have issued the notice dated 13th June 2019. By carrying

    out amendments in the writ petition, the Petitioner has

    challenged the letter dated 13th June 2019.

    Page 17 of 65

    ::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:35:21 :::

    Reliance-oswp-242-2018-J-R.doc

    28. The Respondent Nos. 1 and 2 have opposed the Writ

    Petition by filing joint Reply. The plea taken by the Respondents in

    their Reply, reduced to their essence, is to effect that that the Writ

    Petition involves disputed questions of fact, which cannot be

    adjudicated in a Writ Petition; that the Writ Petitioners have an

    alternate, efficacious remedy by way of Civil Suit; that the dispute

    is purely contractual in nature involving interpretation of the

    terms and conditions of the contract, which cannot be entertained

    in a Writ Petition; that this is not a case of infringement of any

    constitutional, statutory or fundamental right of the Petitioner;

    that the Demand Notice has issued on account of breach of

    conditions of the Lease Deed and, therefore, the same does not

    involved violation of any constitutional right; that Articles 2(a)

    and 2(d) of the Lease Deed, which require completion of the

    construction within a period of four years from the date of Lease

    Deed are binding and mandatory clauses in the Lease Deed.

    Therefore, those are enforceable under the law; even if the delay

    in construction has occurred due to interim order of Court or on

    account of force majeure, even than, in view of Article 2(d), any

    extension of time could only been granted upon payment of

    additional premium. Since the MMRDA would not have any power

    Page 18 of 65

    ::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:35:21 :::
    Reliance-oswp-242-2018-J-R.doc

    to waive such amount, therefore, payment of additional

    premium/penalty was inevitable in case of delay; that the restraint

    order of the Court was limited only to the additional area of

    31,500 sq.mtrs. of commercial FSI. Therefore, the same did not

    prevent commencement and completion of construction of the

    Convention Centre; that allotment of additional built-up area was

    optional. Since the Petitioners have opted for the additional built-

    up area, therefore, the allotment of additional built up area

    cannot be a justifiable ground for the delay in completion of

    construction; that the Petitioners have issued an unconditional

    undertaking on 14th December 2016 agreeing to pay the additional

    premium/penalty for grant of extension of time. Therefore, they

    would be bound by such undertaking; that the Writ Petitioner has

    approached this Court by suppressing material facts and

    particulars pertaining to the undertaking dated 14 th December

    2016, therefore, the Writ Petition is liable to be dismissed on such

    count alone; that the decision of the MMRDA to extend the time

    period from four years to six years was applicable prospectively,

    i.e., with effect from August, 2015 and therefore, the same would

    not cover the case of lessees such as the Petitioner in respect of

    whom, the Lease Deed was executed prior to August, 2015.

    Page 19 of 65

    ::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:35:22 :::

    Reliance-oswp-242-2018-J-R.doc

    29. By filing Rejoinder, the Writ Petitioner, while denying the

    assertions made by the Respondents, has reiterated that it is a case

    of violation of fundamental right of the Petitioner guaranteed

    under Article 14 of the Constitution of India. It has further been

    asserted that even in contractual matters, unfair treatment

    extended by the State or its instrumentality would be amenable to

    writ jurisdiction of this Court; that due to the allotment of the

    additional built-up area and the integrated design of the project, it

    would be impossible to complete the original portion of the

    building within four years since it included common structures

    such as common basement and services, etc. The Petitioners have

    also denied the contention that the restraint order of the Court did

    not affect the integrated planning and common infrastructure of

    the project so as to permit bifurcation of the construction; it has

    also been alleged that the Petitioner being similarly situated

    Lessee, extension of time from four years to six years would be

    equally applicable to them as denial of such benefit would amount

    to unfair discrimination; the Petitioners have further contended

    that similarly situated entities such as Bharat Diamond Bourse &

    Indian Oil Corporation have been granted extension of time

    without levy of additional premium; it has also been contended

    Page 20 of 65

    ::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:35:22 :::
    Reliance-oswp-242-2018-J-R.doc

    that the undertaking dated 14th December 2016 was obtained

    under coercion viz. On the threat of withholding Occupation

    Certificate and, therefore, the same cannot preclude the Petitioner

    from agitating its grievance as per law; the Petitioner has also

    denied suppression of material facts.

    30. In their additional Reply, the Respondents have controverted

    the statements made in the Rejoinder Affidavit while maintaining

    their original stand justifying the demand for the additional

    premium.

    31. This Writ Petition was analogously heard along with three

    other Writ Petitions being Writ Petition No.864 of 2018, Writ

    Petition No.2377 of 2018 and Writ Petition No.3209 of 2017,

    involving similar issues wherein, identical reliefs were sought by

    the Writ Petitioner(s).

    32. We have heard the learned Senior Counsel appearing for the

    parties and have also perused the pleadings and documents placed

    on record.

    33. Mr. Vikram Nankani, learned Senior Counsel appearing for

    the Petitioners, has argued that the impugned demand notice

    Page 21 of 65

    ::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:35:22 :::
    Reliance-oswp-242-2018-J-R.doc

    dated 12th September 2017 and the subsequent communication

    dated 13th June 2019 issued by Respondent No.1 seeking recovery

    of additional premium on account of alleged delay in completion

    of construction are arbitrary, illegal and unsustainable in law.

    According to the learned Senior Counsel, the demand proceeds on

    an erroneous interpretation of Clauses 2(a), 2(c) and 2(d) of the

    Lease Deed dated 1st September 2006, in as much as under Clause

    2(c), no construction work could commence until the plans and

    specifications were approved by the planning authority. It is

    therefore submitted that the timeline for completion of

    construction cannot be computed independent of such approvals.

    34. The learned Senior Counsel further submits that the project

    contemplated construction of a Convention and Exhibition Centre

    and Commercial Complex as a composite development.

    Subsequent to the execution of the Lease Deed, Respondent No.1

    had allotted additional built-up area of 72,500 sq. mtrs. under the

    Supplementary Lease Deed dated 13 th July, 2007, and thereafter,

    further additional built-up area of 1,25,000 sq. mtrs. in the year

    2012. The allotment of such additional built-up area required

    revision of the development plans and fresh statutory approvals

    Page 22 of 65

    ::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:35:22 :::
    Reliance-oswp-242-2018-J-R.doc

    and therefore, the timelines originally contemplated under the

    Lease Deed dated 1st September 2006 cannot be strictly applied to

    such construction.

    35. The learned Senior Counsel further has submitted that the

    allotment of additional built-up area was unconditional and

    Respondent No.1 had itself clarified that there would be no time

    limit for construction of such additional built-up area. Therefore,

    by granting such additional development rights during the

    subsistence of the Lease Deed, Respondent No.1 must be deemed

    to have waived the condition relating to completion of

    construction within four years.

    36. It is also submitted that the development of the project was

    affected by the order of injunction passed by this Court in Writ

    Petition No.1165 of 2007, which restrained utilization of a portion

    of the additional built-up area until 12th March 2012. The

    Petitioners had requested Respondent No.1 to exclude the said

    period while computing the four-year period stipulated under the

    Lease Deed which was confirmed by the Respondent No. 1 vide

    communication dated 1st February 2012. As such, such time line

    cannot be enforced.

    Page 23 of 65

    ::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:35:22 :::

    Reliance-oswp-242-2018-J-R.doc

    37. The Senior Counsel has further submitted that the project

    required several statutory approvals from various authorities

    including environmental clearance, aviation height clearance,

    approval of the High-Rise Committee and permissions from the

    Municipal Corporation of Greater Mumbai. According to the

    Petitioner, these approvals were obtained over a period of time

    and the commencement certificate for the integrated project was

    eventually issued only in the year 2014. The learned Senior

    Counsel therefore submits that the period of four years

    contemplated under Clause 2(d) of the Lease Deed must be

    construed in a commercially reasonable manner and the same

    must be computed only after approval of the development plans

    and issuance of the necessary commencement certificates.

    38. The learned Senior Counsel has further argued that the

    Respondent No.1 had itself recognized the practical difficulties

    faced by developers in completing construction within four years

    and at its 138th Meeting held on 26th August 2015, resolved to

    amend the standard form of lease by extending the period for

    completion of construction from four years to six years. According

    to the Petitioner’s Counsel, restricting the benefit of the said

    Page 24 of 65

    ::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:35:22 :::
    Reliance-oswp-242-2018-J-R.doc

    decision only to leases executed after 26 th August 2015 would be

    arbitrary and discriminatory, since all developers in Bandra-Kurla

    Complex are required to obtain similar statutory approvals. It is,

    therefore, contended that the impugned action of the Respondent

    No.1 violates Article 14 of the Constitution of India.

    39. To sum up his arguments, the learned Senior Counsel has

    submitted that the present case is squarely covered by the decision

    of this Court rendered in the case of Raghuleela Builders Pvt. Ltd.

    & Anr vs. MMRDA & Ors. , whereby in identical fact situation and

    similar circumstances, this Court, by interpreting similar clauses in

    the lease deed, has held that the demand of additional premium

    on account of delay in completing the construction was arbitrary

    and illegal and, accordingly struck down such demand.

    40. Dr. Birendra Saraf, learned Senior Counsel appearing for the

    Respondent Nos.1 and 2,on the other hand, has opposed the

    prayer made in the Writ Petition and has also questioned the

    maintainability of the Writ Petition by contending that the dispute

    between the parties arise out of contractual obligations contained

    in the Lease Deed and the Supplementary Lease Deed and the

    same involves several disputed questions of fact which cannot be

    Page 25 of 65

    ::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:35:22 :::
    Reliance-oswp-242-2018-J-R.doc

    adjudicated in a writ petition in exercise of jurisdiction under

    Article 226 of the Constitution of India. He has further argued that

    the Writ Petition is hit by delay and laches and the relief prayed

    for is also barred by limitation. According to Dr. Saraf, , since the

    Petitioner had earlier sought extension of time for completion of

    construction and had not challenged the communications issued

    by Respondent No.1 at the relevant time, hence, the challenge

    made to such demand notices is not maintainable at this point of

    time.

    41. The learned Senior Counsel for the Respondents has further

    argued that the recovery sought by Respondent No.1 is strictly in

    accordance with the provisions of the MMRDA Act, the MMRDA

    (Disposal of Land) Regulations, 1977 as well as the terms and

    conditions of the Lease Deed executed by and between the parties.

    According to learned counsel, the clauses contained in the Lease

    Deed are statutory in nature. Therefore, under Article 2(e),

    extension of time for completion of construction can be granted

    only upon payment of additional premium at the prescribed rates

    which cannot be waived even by the MMRDA.

    Page 26 of 65

    ::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:35:22 :::

    Reliance-oswp-242-2018-J-R.doc

    42. Dr. Saraf has further argued that the Petitioner had

    furnished undertakings promising to pay the amount of additional

    premium for the delay in completing the construction. Therefore,

    the Petitioner cannot now resile from such promise.

    43. The learned Senior Counsel for the Respondents has also

    argued that the reliance placed by the Petitioner on the judgment

    in Raghuleela Builders Pvt. Ltd. & Anr. (Supra) is misplaced in as

    mush as the said decision was rendered in the peculiar facts of

    that case.

    44. To sum up his arguments, Dr. Saraf has submitted that the

    Petitioners have approached this Court without disclosing material

    facts and producing the relevant documents. Since they have

    approached this court with unclean hands, hence, the Petitioners

    are not entitled to any relief from the court of equity. As such, the

    Writ Petition be dismissed.

    45. In support of his above arguments, Dr. Saraf, has relied

    upon the following decisions:-

    (a) State of Punjab and Ors. vs. Dhanjit Singh Sandhu1

    1 (2014) 15 SCC 144.

    Page 27 of 65

    ::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:35:22 :::

    Reliance-oswp-242-2018-J-R.doc

    (b) Atur Park-4 Co operative Housing Society Ltd. vs
    State of Maharashtra2

    (c) State of Goa vs. Dr. Alvaro Alberto Mousinho3

    Plea regarding Maintainability of the Writ Petition :-

    46. Insofar as the plea regarding maintainability of the Writ

    Petition is concerned, at the very outset, it deserves to be

    mentioned herein that although the maintainability of the Writ

    Petition has been questioned inter-alia on the ground that several

    disputed questions of facts are involved there-in, yet, after

    examining the record, we find that the material assertions made in

    the Writ Petition are all based on documents annexed thereto,

    which are admitted documents. Moreover, in view of the plea

    raised by the Petitioner that the action of the Respondent No. 1 in

    levying additional premium/penalty for the delay in completion of

    construction is not only contrary to the terms and conditions of

    the Lease Deed, but also, arbitrary and illegal and hence, in

    violation of the fundamental rights guaranteed to the Petitioner

    under Article 14 of the Constitution, we are of the view that the

    2 2023 SCC Online Bom 874.

    3 (2019) 10 SCC 465.

    Page 28 of 65

    ::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:35:22 :::

    Reliance-oswp-242-2018-J-R.doc

    issues raised in the Writ Petition have an element of public law

    character.

    47. In the case of Joshi Technologies International IBC vs. U.O.I.

    & Ors. , the Hon’ble Supreme Court has observed that there is no

    absolute bar to the maintainability of a Writ Petition, even in

    contractual matters or where there are disputed questions of fact

    or even when monitory claim is raised, provided, the Court is

    called upon to examine the issue which has a public law character

    attached to it. Having regard to the core controversy involved in

    this proceeding and considering the fact that the issues involved in

    this Writ Petition would call for determination by this Court based

    on interpretation of the relevant Articles of the Lease Agreement

    as well as the documents exchanged by and between the parties so

    as to ascertain fairness in the action of the Respondent No 1, we

    are unable to agree with the stand of the Respondents that the

    Writ Petition ought to be dismissed on the ground that it raises

    disputed questions of facts.

    48. Likewise, from a reading of Section 44 of the MMRDA, Act

    1974, we find that the provision for Appeal provided thereunder,

    is available for disputes regarding recovery of money due to the

    Page 29 of 65

    ::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:35:22 :::
    Reliance-oswp-242-2018-J-R.doc

    authority as arrears of land revenue. Since the challenge made to

    the impugned demand notice is on the ground that the same is

    contrary to the terms of the Supplementary Lease Deed and hence,

    illegal and arbitrary as such, we are of the opinion that the said

    controversy cannot be effectively adjudicated in an Appeal filed

    under Section 44. Therefore, we reject the contention of the

    Respondents that the Petitioner has an effective and efficacious

    alternative remedy.

    49. We also find that all material facts necessary for

    appreciating the controversy have been disclosed in the Writ

    Petition. Therefore, we are of the view that the Writ Petition

    cannot also be dismissed on account of suppression of material

    facts as well.

    50. In so far as the grounds of delay and laches as well as the

    plea of the claim being barred by the Law of Limitations is

    concerned, save and except making a bald assertion on such count

    the Respondents have failed to mention as to on which date the

    cause of action for the petitioner to institute the proceeding had

    ceased and on what count. There is also no oral argument

    advanced to that effect.

    Page 30 of 65

    ::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:35:22 :::

    Reliance-oswp-242-2018-J-R.doc

    51. In Banda Development Authority, Banda vs. Motilal Agarwal

    & Ors.4 the Hon’ble Supreme Court has observed that no limitation

    has been prescribed for filing a Writ Petition under Article 226 of

    the Constitution of India. However, the High Court will treat the

    delay in filing the Writ Petition as unreasonable, if the same is

    filed beyond the period of limitation prescribed for filing a Civil

    Suit for a similar cause. From the above, it would be apparent that

    although un-explained delay in instituting a Writ Petition could be

    a valid ground to decline relief to the Petitioner, yet, the law of

    Limitation would not have strict application in a Writ Petition.

    52. There is no dispute in this case about the fact that the

    Respondent No. 1 is an instrumentality of the State and, therefore,

    would be an “other authority” within the meaning of Article 12 of

    the Constitution of India.

    53. Law is well settled that arbitrariness in the decision making

    process of the State or its instrumentality is a facet of Article 14 of

    the Constitution of India. In E.P..Royappa v State of Tamil Nadu,5 it

    was pointed out that Article 14 would strike at arbitrariness in

    State action and ensure fairness and equality of treatment.
    4 (2011) 5 SCC 394.

    5 (1974) 4 SCC 3.

    Page 31 of 65

    ::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:35:22 :::

    Reliance-oswp-242-2018-J-R.doc

    54. The present is not a proceeding simpliciter for enforcing a

    money claim but raises significant questions pertaining to the

    validity and fairness in the impugned action of the Respondent No

    1, which are required to be adjudicated on the touch stone of

    Article 14. As such, we are of the considered opinion that such

    plea cannot be brushed aside merely on the ground of delay and

    laches, more so, since such delay has evidently not given rise to

    any parallel right of a third party.

    55. In view of the foregoing discussions, we are of the view that

    the Writ Petition is maintainable in law as well as in the facts and

    circumstances of the case.

    56. It would be further pertinent to note herein that in an

    earlier decision rendered by a co-ordinate Bench of this Court

    dated 20th November 2019 in Raghuleela Builders Pvt. Limited

    and Anr. vs. The Mumbai Metropolitan Regional Development

    Authority & Ors. (Supra) wherein, identical issues were involved,

    this Court had entertained the Writ Petition. In that case also the

    Petitioners had challenged a similar Demand Notice dated 12 th

    September 2017 issued by the Respondent No.1, by invoking

    similar provisions of the Lease Deed as well as the Supplementary

    Page 32 of 65

    ::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:35:22 :::
    Reliance-oswp-242-2018-J-R.doc

    Lease Deed, demanding payment of a sum of Rs. 432 Crores as

    penalty for the delay in completion of construction of the building.

    That was also a case wherein, although the initial built up area

    was 30550 sq. meters, which was to be consumed by constructing

    9 (nine) floors in the building, yet, subsequently, due to the

    increase in the FSI, the Respondent No.1 had allotted additional

    built up area of 67000 sq. meters to the Petitioner resulting in

    construction of 11 additional floors in the same building. Due to

    the addition in the built up area, the construction of the building

    could not be completed within four years, as stipulated in Article

    2(d) of the original Lease Deed, as a result of which, Demand

    Notice dated 12th September 2017 was served for recovery of

    penalty/additional premium along with interest calculated

    thereon.

    57. By the Judgment and Order dated 20 th November 2019, in

    Raghuleela Builders Pvt. Ltd. & Anr. (Supra), the Division Bench

    had set aside the impugned Demand Notice dated 12 th September

    2017 by holding that such a demand was not maintainable in the

    eyes of law. That apart, it was also observed that in view of the

    change in policy of the MMRDA increasing the time limit for

    Page 33 of 65

    ::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:35:22 :::
    Reliance-oswp-242-2018-J-R.doc

    completion of the building “Fit for occupation”, from four years to

    six years, the demand for penalty/additional premium for delay in

    completion of construction within four years was ex-facie

    unreasonable, unjustified and discriminatory.

    58. The Special Leave Petition (C) No. 6411 of 2020 preferred

    by the Respondent No.1 assailing the Judgment and Order dated

    20th November 2019 was dismissed by the Hon’ble Supreme Court

    by the order dated 27 th July 2020 after taking note of the findings

    recorded in paragraphs No. 38 and 40 of the Judgment and Order

    dated 20th November 2019. However, it was clarified that since the

    judgment of the Division Bench of the Bombay High Court was

    rendered in the facts of that case, hence, it cannot influence any

    other matter in this behalf. With the above observation the Special

    Leave Petition was dismissed.

    59. In the order dated 27th July 2020 the Hon’ble Supreme

    Court, while dismissing the Special Leave to Appeal (C) No(s)

    6411/2020, had observed as follows:-

    “We are not inclined to exercise our jurisdiction under Article
    136
    of the Constitution of India in the given facts of the case and
    more so as reflected from paragraphs 38 and 40 of the
    impugned judgment.

    Page 34 of 65

    ::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:35:22 :::

    Reliance-oswp-242-2018-J-R.doc

    Mr. K. K. Venugopal, learned Attorney General for India
    expresses some apprehension on account of there being other
    matters pending.

    We clarify that the present matter is in the given facts of
    the case as stated aforesaid and thus, cannot be said to influence
    any other matter in this behalf.

    The special leave petition is dismissed in terms aforesaid.
    Pending applications shall also stand disposed of.”

    60. It appears that the Respondent No. 1 had filed a Review

    Petition seeking review of the order dated 27 th July 2020, which

    was also dismissed by the Hon’ble Supreme Court vide order

    dated 29th September 2020 passed in Review Petition (Civil) No.

    1764 of 2020 arising out of SLP (C) No. 6411 of 2020.

    61. From a plain reading of the decision rendered in Raghuleela

    Builders Pvt. Ltd. & Anr. (Supra) we are of the opinion that, even

    if the said decision is treated to have been rendered in the fact

    situation of that case, even then, we can take note of the legal

    principles emanating therefrom. In that view of the matter we are

    unable to agree with the submission of the learned Counsel for the

    Respondents that the decision in the case of Raghuleela Builders

    Pvt. Ltd. & Anr. (Supra) cannot be looked into by this Court even

    for the purpose of deciding the question of maintainability of the

    Writ Petition.

    Page 35 of 65

    ::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:35:22 :::

    Reliance-oswp-242-2018-J-R.doc

    62. It is to be noted herein that the question of

    maintainability of a Writ Petition is a mixed question of law

    and facts. Therefore, such question would obviously have to

    be considered having due regard to the peculiar facts and

    circumstances of each case. Having regard to the facts and

    circumstances of this case and considering the fact that a

    similar Writ Petition, raising similar issues in Raghuleela

    Builders Pvt. Ltd. & Anr. (Supra) had earlier been entertained

    by this Court, for the sake of maintaining uniformity in

    judicial decisions, we are not inclined to non-suit the Writ

    Petitioner merely on the plea of maintainability as raised by

    the Respondents.

    On Merits:-

    63. During the Course of arguments, the learned Counsel for

    the Respondents has made it clear that the demand for additional

    penalty on account of delay in completing the construction had

    been raised by the Respondent No.1 in deference to Article 2(d) &

    (e) of the Lease Deed dated 1 st September 2006 which is as per

    Form ‘D’ of Regulation No 10 of the Mumbai Metropolitan Region

    Page 36 of 65

    ::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:35:22 :::
    Reliance-oswp-242-2018-J-R.doc

    Development Authority (Disposal of Land) Regulations, 1977.

    Therefore, the question as to whether such a claim /demand of

    the Respondent No. 1 for payment of additional premium/ penalty

    on account of delay in completing the construction was

    maintainable in the eyes of law as well as in the facts and

    circumstances of the case would undoubtedly have to be answered

    by this court in the light of materials brought on record and by

    constructing the relevant clauses of the Lease Agreement. For the

    above purpose Articles 2 (d) and (e) of the Lease Deed dated 1 st

    September 2006 would be relevant and therefore, the same are

    being reproduced herein-below for ready reference:-

    “(d) Time limits for commencement and completion of
    construction work: That the Lessee shall within three months
    from the receipt of approval of its plans and specifications of
    building or buildings intended to be erected on the said plot of
    land, commence and within a period of four years from the
    date of this lease at his own expense and in a substantial and
    workman like manner and with the sound materials and in
    compliance with the said Development Control Regulations
    and Building Regulations and all Municipal Rules, bye-laws
    and Regulations applicable hereto and in strict accordance
    with the approved plans, elevations, sections, specifications
    and details as specified in the Section 5, 6 & 8 of the said RFP
    and the said allotment letter, to the satisfaction of the
    Metropolitan Commissioner and conforming to the Bandra-

    Kurla Complex Notified Area, Development Control
    Regulations, 1979 & all other relevant Rules, Regulations &
    Acts and further as provided in Section 5 of the said RFP and
    the said allotment letter, build and completely finish fit for
    occupation a (i) “Convention & Exhibition Centre” and (ii)
    “Commercial Complex”to be used as (i) “Convention &
    Exhibition Centre” and (ii) “Commercial Complex” with all
    requisite drains and other proper conveniences thereto.

    Page 37 of 65

    ::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:35:22 :::

    Reliance-oswp-242-2018-J-R.doc

    PROVIDED THAT the construction of Convention and
    Exhibition Centre will be commenced before the
    commencement of construction of Commercial Complex and
    Occupation Certificate of Convention and Exhibition Centre
    (65000 sq. mtr. shall be obtained prior to the request for
    Occupation Certificate of Commercial Complex (50000 sq.
    mtr) as set out in the said RFP and the said allotment letter
    the Lessee shall scrupulously observe the approved Work
    Execution Plan (copy Whereof is set out in the SIXTH
    SCHEDULE hereunder written).

    PROVIDED FURTHER THAT as set out in the said
    allotment letter, the Lessee shall submit the periodic progress
    report of the Convention and Exhibition Center say in the first
    week of every third month to the Metropolitan Commissioner,
    Mumbai Metropolitan Region Development Authority. The
    Evaluation Committee appointed by the Metropolitan
    Commissioner as referred in the Proviso to clause (a)
    hereinabove, will review the progress of the development of
    Convention Center report by the Lessee and submit its report
    to the Metropolitan Commissioner. The Evaluation Committee
    as indicated above will satisfy itself regarding the development
    of the Convention and Exhibition Center which has to be of
    international standards and if necessary the Evaluation
    Committee will make suggestions in that respect to the
    Metropolitan Commissioner and the Lessee shall incorporate
    changes so directed by the Metropolitan Commissioner.’

    (e) Extension of time stipulated for construction of
    building or development of land:

    (i) If the Lessee shall not perform and observe the
    limitations of the time mentioned in clause 2 (d) above
    for construction of the intended (i) “Convention &
    Exhibition Centre” on plot of land admeasuring 55000
    sq. mtr. and (ii) “Commercial Complex” on plot of land
    admeasuring 20000 sq. mtr. or otherwise development
    of said plot of land leased to him for reasons beyond
    his control, the Metropolitan Commissioner may
    permit extension of such time on payment of additional
    premium at the following rates:

                       Up to 1 year _____               25    percent    of  the
                                                        respective premium paid
                                                        for     "Convention    &
                                                        Exhibition Centre" and
                                                        "Commercial Complex"
    
    
    
    
                                            Page 38 of 65
    
    
    ::: Uploaded on - 09/04/2026                             ::: Downloaded on - 09/04/2026 21:35:22 :::
                                                             Reliance-oswp-242-2018-J-R.doc
    
    
    
    
                       Between 1 and 2 years___      35    percent    of  the
                                                     respective premium paid
                                                     for     "Convention    &
                                                     Exhibition Centre" and
                                                     "Commercial Complex"
    
                       Between 2 and 3 years ___     40    percent    of    the
                                                     respective premium paid
                                                     for "Convention Exhibition
                                                     Centre" and "Commercial
                                                     Complex"
    
              (ii)     If the Metropolitan Commissioner shall refuse to
    

    permit such extension of time or shall find the Lessee
    of having committed breach of any condition or
    covenant during limitation of time mentioned in clause
    2(d) hereto before Metropolitan Commissioner may
    forfeit and determine the Lease: provided that in the
    event of such determination of lease 25 percent of the
    premium paid by the Lessee to the Lessor shall stand
    forfeited and the the remaining 75 percent of such
    premium shall be refunded to him; provided further
    that the power to so determine the Lease shall not be
    exercised unless and until the Metropolitan
    Commissioner shall be given to the Lessee or left on
    some part of the demised premises a nonce in writing
    of his intention to do so and of specific breach of the
    covenant or condition in respect of which forfeiture is
    intended and default shall have been made by the
    Lessee in remedying such breach within three months
    from the service of notice on him or the notice being
    left on the demised premises.”

    64. Article 2 of the Supplementary Lease Deed dated 13 th July

    2007 mentions that the incremental premises agreed to be

    constructed shall be deemed to be integral part of the demised

    premise defined in Lease Deed dated 1 st September 2006. Article 2

    reads as follows :-

    “2. It is here by agreed and declared by and
    between the parties hereto that all the conditions
    and covenants including the term of the lease as

    Page 39 of 65

    ::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:35:22 :::
    Reliance-oswp-242-2018-J-R.doc

    contained in the said Deed of Lease shall be deemed
    to be incorporated herein and shall regulate the
    lease hereby granted. It is further agreed and
    declared by the parties hereto that the incremental
    premises hereby agreed to be constructed and to be
    leased by the lessor to the lessee shall be deemed to
    be the integral part of demised premises as defined
    in the said Deed of Lease dated 1 st September 2006
    and annexed hereto as ANNEXURE.”

    65. At the very out set it must be noted here-in that as per

    Article 2(d) the lessee is required to complete the construction

    within four years from the date of execution of the lease deed.

    However, Article 2 (c) of the Lease Deed makes it clear that no

    work shall commence or be carried out contrary to the

    Development Control Regulations and the Building Regulations

    applicable to the plot of land and until the plans, elevations,

    sections, specifications and details shall have been approved.

    Therefore, in view of Article 2(c), the construction no construction

    can commence until all statutory approvals including the approval

    of building plan etc. are received. Article 2(a) of the Lease Deed

    mentions that the lessee shall, within three months, submit plans

    etc. for approval. However, there is no condition in the Lease Deed

    laying down any time line for granting of such approval by the

    Respondent No. 1.

    Page 40 of 65

    ::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:35:22 :::

    Reliance-oswp-242-2018-J-R.doc

    66. In a construction of this nature, permission of multiple

    statutory authorities including the Municipal Corporation, Fire

    department, Environment clearance, height clearance etc. will be

    necessary, without which even the Commencement Certificate

    cannot be issued. Unless the Commencement Certificate is issued,

    the construction work cannot commence. These statutory

    authorities are not bound by the terms and conditions of the Lease

    Agreement. Notwithstanding the same, the Lease Agreement is

    completely silent as to who will be responsible in case of delay in

    granting approval by these Statutory Authorities, coming in the

    way of early commencement and completion of the construction.

    67. Not only that, the Lease Deed is also silent as to what would

    be the effect on the time line of four years for completion of the

    construction, as laid down in Article 2(d) in case, there is delay in

    granting of statutory approvals. As such, if there is delay in

    granting permissions/ approval by the statutory authorities for any

    reason whatsoever, leading to delay in commencement of

    construction, then in that event, the Lessee will be left with no

    scope to complete the construction within the stipulated time, that

    too, for no fault on its part. Notwithstanding the same, as per

    Page 41 of 65

    ::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:35:22 :::
    Reliance-oswp-242-2018-J-R.doc

    Article 2(d), as interpreted by the Respondent No 1, the lessee

    would still be liable to pay penalty for the delay in completing the

    construction beyond the period of four years from the date of

    execution of the Lease Deed. Viewed from that perspective, Article

    2(d) of the Lease Deed appears to be ex-facie unfair, unreasonable

    and hence, unconscionable. However, since the Articles of the

    Lease Deed are not under challenge, hence, the said aspect of the

    matter need not detain this Court.

    68. As has been noted hereinabove, the initial built-up area,

    which is the subject matter of Lease Deed dated 1 st September

    2006, was only 65,000 sq. mtrs. for the Convention & Exhibition

    Centre and 50,000 sq.mtrs for the Commercial Complex, totaling

    to 1,15,000 sq.mtrs. Article 2(d) of the Lease Deed providing four

    years’ time limit for completing the construction would, therefore,

    apply to the 1,15,000 sq. mtrs of built up area.

    69. Subsequent to the execution of the Lease Deed dated 1st

    September 2006, there was increase in the FSI leading to

    allotment of additional built-up area of 72,500 sq. mtrs to the

    Petitioner. This 72,500 sq. mtrs was not within the ambit of the

    original Lease Deed dated 1st September 2006. As such, the

    Page 42 of 65

    ::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:35:22 :::
    Reliance-oswp-242-2018-J-R.doc

    Supplementary Lease Deed 13th July 2007 had to be executed.

    However, as had been noted above, soon thereafter, i.e. on 15 th

    October 2007, an interim order was passed by this High Court in

    Writ Petition No. 1165 of 2007 which had affected the

    construction work, at least in sofar as 31,500 sq. mtrs pertaining

    to the Commercial Complex is concerned. The aforesaid stay order

    remained in force until 12th March 2012. Therefore, although a

    plinth Commencement Certificate (CC) was issued on 12 th June

    2008 permitting construction upto the plinth level, yet, in view of

    the composite design of the Convention & Exhibition Centre as

    well as the Commercial Complex, having common foundation and

    basement, the Petitioner could not commence construction due to

    the operation of the stay order. The said fact was also informed to

    the Respondent No. 1 vide communication dated 28th January

    2009.

    70. From the statements made in the Writ Petition and from the

    examination of various documents on record, including EIA

    Certificate dated 26th June 2013 as well as Article 2 of the

    Supplementary Lease Deed dated 13 th July 2007, it is evident that

    although the area of 72,500 sq. mtrs was allotted subsequently,

    Page 43 of 65

    ::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:35:22 :::
    Reliance-oswp-242-2018-J-R.doc

    yet, it was treated as an integral part of the construction to be

    carried out with the original built up area.

    71. The Writ Petition No. 1165 of 2007 was withdrawn on 12 th

    March 2012. As such, on 20th Mach 2012, i.e., after the

    withdrawal of the Writ Petition No. 1165 of 2007, the Respondent

    No. 1 had approved the allotment of additional 1,00,000 sq. mtrs

    to the Petitioner and, thereafter, on 3 rd April 2012, another 25,000

    sq. mtrs was allotted thus, increasing the total allotment of built-

    up area upto 3,12,500 sq. mtrs. The Commencement Certificate

    upto the seventh floor level pertaining to the 3,12,500 sq. mtrs

    was issued only on 16th April 2014.

    72. In a composite construction of this nature involving complex

    layouts, warranting multiple Commencement Certificates to be

    issued by the Respondent No. 1, it is inconceivable that the Lessee

    would adhered to two different timelines for construction of the

    original allotment and the additional built-up area, the

    construction whereof is to be carried out over the same plot and in

    respect of the same construction. Since the construction in this

    case was evidently and admittedly not severeable in nature,

    Page 44 of 65

    ::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:35:22 :::
    Reliance-oswp-242-2018-J-R.doc

    therefore, we cannot but hold that there could only be one date of

    completion of the entire building “fit for occupation”.

    73. In view of the above discussion, we are also of the opinion

    that although a plinth Commencement Certificate was issued on

    12th June 2008 granting permission to complete the construction

    only upto the plinth level, yet, in view of the pending Court

    proceeding, and operation of the interim order dated 15 th October

    2007 such certificate was not capable of being acted upon and,

    accordingly, was also not acted upon by the Petitioner. Thereafter,

    the Commencement Certificate for the entire building came to be

    issued on 16th April 2014. Therefore, commencement of

    construction only took place pursuant to the issuance of the

    Commencement Certificate dated 16th April 2014.

    74. We also find from the materials on record that in view of

    the long continuation of the interim order dated 15 th October

    2007, the Petitioner wanted to surrender the additional built-up

    area of 72,500 sq. mtrs under the Supplementary Lease Deed

    dated 13th July 2007 but the said proposal was declined by the

    Respondent No. 1. On the contrary, on 8 th November 2011, the

    Respondent No. 1 had issued a communication categorically

    Page 45 of 65

    ::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:35:22 :::
    Reliance-oswp-242-2018-J-R.doc

    representing that there would be “no time-limit” for construction

    of the additional built-up area.

    75. Further, by the communication dated 1 st February 2012, the

    Respondent No. 1 had also confirmed that the period, during

    which, the stay order passed by the Court was in force, shall not

    be counted for computing the time-limit of four years.

    76. The reflections made in the communication dated 8 th

    November 2011 as well as 1st February 2012, in our opinion,

    clearly holds out a promise to the Petitioner by the Respondent No

    1, based on which, the Petitioner had altered its position. Under

    such circumstance, the Respondent No. 1 cannot subsequently

    resile from such promise. Therefore, any action on the part of the

    Respondents to act contrary to the reflection made in the letters

    dated 8th November 2011 and 1st February 2012 prejudicially

    affecting the interest of the Petitioner would be hit by the doctrine

    of promissory estoppel and hence, would be liable to be interfered

    with by this court. (See Motilal Padampat Sugar Mills Co. Ltd. vs.

    State of Uttar Pradesh & Ors).6

    6 (1979) 2 SCC 409.

    Page 46 of 65

    ::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:35:22 :::

    Reliance-oswp-242-2018-J-R.doc

    77. It would be significant to note here-in that it is not a case

    where the construction was delayed due to negligence on the part

    of the Lessee. On the contrary, it appears from the materials on

    record that the construction was delayed due to delay in issuance

    of statutory approvals including environment clearance. Since

    even as per the terms and conditions of the Lease Deed, the

    construction cannot commence without the approval of the plan

    and issuance of the Commencement Certificate, hence, by a

    reasonable and harmonious construction of the Articles of the

    Lease Deed, we hold that, in such a case, the time line of four

    years for completing the construction under Article 2(d) ought to

    be computed from the date of issuance of the Commencement

    Certificate and not from any prior date.

    78. Having regard to the facts and circumstances of this case,

    we find that even the condition precedent for invoking the Article

    2(d) of the Lease Deed dated 1 st September 2006 was not met in

    this case in as much as the construction of the original built-up

    area was evidently completed by the Petitioner within the period

    of four years from the date of issuance of the Commencement

    Certificate i.e. 14th April 2014 by the Respondent No. 1 after

    Page 47 of 65

    ::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:35:22 :::
    Reliance-oswp-242-2018-J-R.doc

    excluding the period during which the interim order passed by the

    High Court was in force. As such, viewed from that angle also, in

    our opinion, there was no legal justification for the Respondent

    No.1 to insist on additional premium/penalty from the Petitioner

    under Article 2(d) on account of alleged delay in completing of

    the construction beyond the period of four years.

    79. In the above context, it would be relevant to note here-in

    that, even if the provision of Article 2(d) of the Lease Deed dated

    1st September 2006 is given full weightage, even then, the four

    years period for completing the construction reckoned from the

    date of executions of the Lease Deed would expire on 30 th August

    2010. The interim order passed by the Court on 15 th October 2007

    was vacated on 12th March 2012. Therefore, the said order had

    remained in force for a period of 4 (four) years 4(four) months

    and 26 (twenty six) days, i.e. 1610 days’ in total. If the said period

    is added to the completion period, then in that event, even under

    Article 2(d), the Petitioner would be entitled for 8 years, 4

    months, 226 days’, with effect from 1st September 2006, to

    complete the construction without seeking extension of time. In

    view of the determination made here-in above, such period of 8

    Page 48 of 65

    ::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:35:22 :::
    Reliance-oswp-242-2018-J-R.doc

    years 4 months 26 days will have to be counted from 14 th

    April,2014 i.e the date on which the first effective Commencement

    Certificate facilitating the commencement of construction of the

    building was issued. If that be so, by such interpretation of the

    Clauses of the Contract, we are of the view that the time available

    to the Petitioner to complete the construction of the initial built up

    area, without seeking extension of time, would be till August

    2022. In so far as the additional built up area is concerned, in

    view of the communication dated 8th November 2011, there would

    be no time restriction applicable for completing the construction

    of the additional built up area. As such, the question of seeking

    time extension for completing the construction of the additional

    built up area would not at all arise in the eyes of law.

    80. After a careful examination of the documents brought on

    record, we find that there is no clarity as to on which date the

    construction of the entire built-up area of 3,12,500 sq. mtrs was

    actually completed by the Petitioner. The impugned Notice dated

    12th September 2017 which had imposed additional premium/

    penalty upon the Petitioner for delay of 7 years 12 days in

    completing the construction also does not furnish any relevant

    Page 49 of 65

    ::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:35:22 :::
    Reliance-oswp-242-2018-J-R.doc

    particulars in support of the above allegation. The said notice also

    appears to be totally vague as regards basis for arriving at the

    conclusion that there was 7 years 12 days delay. It is also not

    clear, if the penalty was applied for the alleged delay in

    completing the construction of the total built-up area including

    the Additional Built-up Area or any part thereof.

    81. Be that as it may, if the projection made by the Respondent

    No. 1 in the impugned notice dated 12 th September 2017 is taken

    into account on their face value, even then, if such delay has been

    computed with effect from 30th August 2010 i.e. on expiry of 4

    years from the date of execution of the Lease Deed dated 1 st

    September 2006, the question of delay of seven years twelve days

    by excluding the period during which the interim order of the

    court was operating, would not arise in this case. We say so

    because there was substantial delay in granting statutory

    approvals and Commencement Certificate which period, in our

    view, would also have to be added to the time available to the

    Petitioner to complete the construction.

    82. It is pertinent to note herein that the Respondent No. 1 had

    made recovery of substantial amount from the Petitioner as

    Page 50 of 65

    ::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:35:22 :::
    Reliance-oswp-242-2018-J-R.doc

    additional premium/penalty for delay in completion of

    construction. However, a transparent procedure valid in the eyes

    of law has not been followed in the matter. This we say so because

    the Respondent No. 1 had never served any default notice to the

    Petitioner intimating that it would be liable to pay penalty due to

    delay and completion of construction. There was also no notice

    ever served upon the Petitioner indicating as to on which date, the

    four years period mentioned in Article 2(d) of the Lease Deed

    dated 1st September 2006, would come to an end. Such prior

    notice, in our opinion, was sine- qua- non in view of the

    intervening developments in the matter , particularly the

    operation of the interim order passed by this Court. Before

    demanding and/or recovering the amount of penalty, no Show

    Cause Notice was also required to be served upon the Petitioner

    giving it an opportunity to show cause as to why such penalty

    should not be recovered by the Respondents. However, no such

    notice was served. Therefore, the entire process of recovery, in our

    view, was not only conducted in a completely arbitrary, whimsical

    and capricious manner but the same was also in violation of the

    principles of natural justice.

    Page 51 of 65

    ::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:35:22 :::

    Reliance-oswp-242-2018-J-R.doc

    83. It must be borne in mind then that in a matter of this nature

    where penalty is sought to be levied alleging default committed by

    a party, unless allegation is admitted, the recovery of penalty

    cannot be based on mere ipse dixit of the authority more so, if the

    controversy arises out of implementation of terms and conditions

    of a contract wherein the authority itself is a party. In such

    matters, the recovery would be permissible only after that

    controversy is resolved in accordance with the law.

    84. In the above context, it would be pertinent to mention

    herein that even as per Rule 11(A) of the MMRDA (Disposal of

    Lands) Regulations 1977, no action to determine the lease could

    be initiated by the Metropolitan Commissioner without serving

    prior notice as regards specific breach of the covenants and

    conditions in respect of which, default has been alleged.

    85. In so far as the undertaking given by the Petitioner to pay

    the additional premium/penalty and the consequent deposit of the

    amount of Rs 646,77,68,594 /- is concerned, it must be noted

    herein that the Writ Petitioner had not only objected to the

    demand for payment of additional premium/penalty for the

    alleged delay in completing the construction but had also

    Page 52 of 65

    ::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:35:23 :::
    Reliance-oswp-242-2018-J-R.doc

    deposited the amount under protest, thereby, categorically

    conveying that the deposit was not made voluntarily or in

    discharge of its contractual obligation. Such protest was not only

    raised contemporaneously but the same was also in writing and

    unambiguous in nature, thus, putting the Respondent No. 1 on

    clear notice that the Petitioner has not accepted the decision in

    principle.

    86. It also appears from the materials on record that apparently

    due to the pressure mounted by the Respondent No. 1 demanding

    payment of additional premium/penalty, the Petitioner was

    compelled to deposit the penalty as otherwise the Petitioner would

    not only be prevented from obtaining the Occupation Certificate

    thus, causing serious economical prejudice to its interest but the

    same would also expose the Petitioner to the risk of termination of

    the Lease. Since the Petitioner had evidently made the deposit of

    penalty under duress and under compelling circumstances, hence,

    the principles of waiver, estoppel and acquiescence would not

    operate against the Petitioner in this case. From the protest raised

    by the Petitioner, it was apparent that the Petitioner had reserved

    its right to agitate the matter at an appropriate time, thus, keeping

    Page 53 of 65

    ::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:35:23 :::
    Reliance-oswp-242-2018-J-R.doc

    the cause alive. Therefore, we hold that the claim for refund of the

    amount made by the Petitioner would not be barred under the law

    merely on account of the undertaking given by it.

    87. Section 72 of the Indian Contract Act provides that a person

    who receives payment made by the payee under coercion must

    repay or return the same.

    88. In Fatima Khatoon Chowdrain vs. Mahmoed Jan Chowdhury

    (1868) 12 Moo Ind App 65, the Privy Council has held that

    payment made not voluntarily but under species of compulsion

    would be liable to be returned.

    89. In Valpy vs Manley (1845) 1 CP 594, the Court of England

    & Wales has held that money paid under the constraint of threats

    to interfere with the legal right is sufficient to make it recoverable.

    90. In Ram Kishen Singh vs. Dooli Chand (1881) 8 IA 93 before

    the Privy Council, it was held that if a person pays money to save

    his property which has been wrongly attached in execution, he is

    entitled to recover it.

    Page 54 of 65

    ::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:35:23 :::

    Reliance-oswp-242-2018-J-R.doc

    91. Relying upon the case of Ram Kishen Singh (Supra), the

    Privy Council in the case of Kanhaya Lal vs The National Bank of

    India Limited7 has held that if a payment is made under protest

    and involuntarily, under coercion, the party making such payment

    would be entitled to claim refund of the same.

    92. Materials on record unequivocally go to show that the

    deposit of penalty was dehors any proper demand raised in

    writing but was forced under the circumstances created by the

    Respondent No. 1, as noted above. Hence, by any stretch of

    reasonable reckoning, the deposit of the penalty as well as the

    undertaking, cannot be treated as voluntarily so as to prevent the

    Petitioner to seek refund of the amount in accordance with law.

    93. In view of the foregoing discussion, we are of the un-

    hesitant opinion that the demand for payment of the

    penalty/additional premium for alleged delay in completing the

    construction was not maintainable under Article 2(d) & (e) of the

    Lease Deed. Moreover, such amount was realized by the

    Respondent No. 1 in a most arbitrary, high handed, unfair, and

    unreasonable manner by subjecting the Petitioner to undue

    7 1913 SCC Online PC 4.

    Page 55 of 65

    ::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:35:23 :::

    Reliance-oswp-242-2018-J-R.doc

    pressure and threat of termination of the Lease, thus putting its

    business interest in peril. The Petitioner was made to deposit the

    amount of penalty under coercion. The imposition of the penalty

    was also not preceded by proper Show Cause notice thus, acting in

    clear contravention of the principle of natural justice. Therefore,

    consequences under the law on such counts must follow.

    94. In the case of State of Punjab and Ors. vs. Dhanjit Singh

    Sandhu (Supra) relied upon by Dr. Saraf, the allottees of the land

    had accepted the terms and conditions of the allotment letter and

    also took possession but they did not raise any construction within

    the specified time, as a result of which, due to violation of specific

    condition, the authority wanted to go for resumption of the plot.

    In that case, the allottees, after availing the benefit of extension,

    had later on demanded refund. It was in such context that the

    Apex Court has held that as per the doctrine of “approbate and

    reprobate” a party cannot be permitted to “blow hot and cold” at

    the same time. In Atur Park-4 Co operative Housing Society Ltd. vs

    State of Maharashtra (Supra), the core question, as projected in

    paragraph 30, was as to whether, the Petitioner there-in could be

    the permitted to seek compensation and seek acquisition under

    Page 56 of 65

    ::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:35:23 :::
    Reliance-oswp-242-2018-J-R.doc

    Fair Compensation Act for the land belonging to it which was

    affected by an adjoining road.In Dr Alvaro Alberto Mousinho De

    Noronha Ferreira (Supra), the controversy was as regards

    conversion of land from agricultural to non-agricultural land and

    the applicability of rates there-in. Therefore, the above decisions

    relied upon by Dr. Saraf in our view, are distinguishable on facts

    and as such, the same would not be of any assistance to the

    Respondents in the facts and circumstances of this case.

    95. Having held as above, we deem it appropriate to record

    here-in that although the learned Counsel for the Petitioner has

    argued that this case is squarely covered by the decision rendered

    in Raghuleela Builders Pvt. Ltd. & Anr . (Supra),yet, the said

    assertion has been strongly contested by the Respondent’s Counsel

    by submitting that in view of the observations made by the

    Hon’ble Supreme Court in the order dated 27 th July 2020, no

    reliance can be placed on the said judgment on any count for the

    purpose of deciding the present Writ Petition. On a careful

    examination of the decision in Raghuleela Builders Pvt. Ltd. &

    Anr. (Supra) we also find that the said decision was rendered in

    the facts of that case. However, it is important to note here-in that

    Page 57 of 65

    ::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:35:23 :::
    Reliance-oswp-242-2018-J-R.doc

    one of the question raised in the said proceedings was pertaining

    to the question as to whether, the decision of the MMRDA to apply

    the extension of time from 4 years to 6 years for completing the

    construction only to the post August 2015 was valid in the eyes of

    law, is also a question raised in the present proceeding. While

    answering the said question, it was held in Raghuleela Builders

    Pvt. Ltd. & Anr. (Supra), as follows:-

    “38. The MMRDA constituted a single member committee of
    retired Judge of the Supreme Court to decide whether the
    MMRDA should give concession in recovery of premium
    considering the time required for plot owner to obtain
    permissions from various authorities for construction of building
    thereon. It is contended that one member committee has
    concluded that the charging of premium for extension of time
    for completing construction in Bandra-Kurla Complex area,
    specifically in case where additional built up area has been
    allotted by the MMRDA, was illegal. In its 138th meeting held
    on 26th August 2015, the MMRDA had acknowledged the
    difficulties faced by the lessees and that the condition of
    completion of construction within 4 years of the execution of the
    lease was adversely affecting the tendering process. The
    MMRDA had appointed an expert one man committee of retired
    Supreme Court Judge in that regard. The single member
    committee has advised that the period of 6 to 7 years be granted
    for completion of construction.

    39. The lease deed entered into by the MMRDA with the
    lessees are as per form D, prescribed under the MMRDA
    (Disposal of Lands) Regulations 1977. Clause 2(a) of the lease
    deed provides that for building plans to be submitted to country
    and town planing division for approval within 3 months from
    the date of lease. Clause 2(c) of the lease deed provides that no
    work is to be carried out until all plans, elevations, specifications
    are approved by the concerned authorities. Clause 2(d) provides
    that within 3 months of the approval of plans, the lessee is to
    commence construction which is to be completed within four
    years of the lease. Clause 2(e) provided for extension of time.
    Clause 2(e) contemplates a situation when the time for
    completion of construction can be extended, parties to the

    Page 58 of 65

    ::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:35:23 :::
    Reliance-oswp-242-2018-J-R.doc

    contract contemplated that certain uncertainties or situations
    may arise which may require more time for completion of the
    construction. In view of this, time is not essence of the contract
    between the parties and rightly so since construction of any
    building in Bandra Kurla Complex, several permissions are
    required from the various authorities and not only from the
    MMRDA who is planning authority for the Bandra Kurla area,
    namely,
    (1) The environmental clearance under the
    Environmental Impact Notification from the Ministry of
    Environment and Forest.

    (2) Building height clearance from the Ministry of
    Civil Aviation because of the close proximity to Airport.

                    (3)        Clearance from the high rise committee.
                    (4)        Permission from the the MCGM.
                    (5)        Permission from the traffic police.
    

    Each of these authorities is required to be approached
    separately since there is no single window clearance / nodal
    agency which would co-ordinate with the aforesaid authorities
    for granting of all necessary permissions. In view of the delay in
    obtaining permissions which are beyond the control of lessee, no
    work could be carried out as per clause 2(d) of the lease deed.

    40. The MMRDA had issued a letter of allotment dated 20th
    March 2012 allotting additional 67,000 sq. meters at
    consideration of 984 crore. Part payment of Rs.196 crore was
    received on 20th March 2012. The supplementary lease deed
    was executed for additional built up area of 67,000 sq. meters.

    The letter of allotment dated 20th March 2012, the acceptance
    of part payment of consideration for additional built up area
    allotted, diluted the time period of four years and there was no
    question of application of condition of occupation certificate for
    built up area within 4 years when additional built up area was
    allotted for raising additional 11 floors on the same building.

    41. The resolution passed by MMRDA for extending the time
    period for completing construction from 4 years to 6 years only
    for leases executed after 26th August 2015 also appears to be
    arbitrary, discriminatory, without basis and justification. The said
    set of circumstances are prevailing for the construction being
    carried out under the leases executed prior to 26th August 2015.
    Therefore, not extending this benefit of this extension of time
    from 4 years to 6 years to the prior leases in respect of other
    plots in the BKC, is completely arbitrary, discriminatory,
    capricious and violative of Article 14 of the Constitution of

    Page 59 of 65

    ::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:35:23 :::
    Reliance-oswp-242-2018-J-R.doc

    India. There is no reasonable basis or justification for this
    decision. The classification sought to be made between the
    leases prior and subsequent to 26th August 2015 is not founded
    on intelligible differentia and neither does this differentia has
    any logic, rational, nexus to the object sought to be achieved.
    The MMRDA has sought to treat equals as unequal. The lessees
    of plots are being discriminated on the basis of their date of
    execution of their leases. The lessees who are placed in similar
    circumstances prevailing for construction in Bandra Kurla area
    are entitled to equal treatment guaranteed under Article 14 of
    the Constitution of India.”.

    96. It is not in dispute that the Lease Deed involved in

    Raghuleela Builders Pvt. Ltd. & Anr. (Supra) was also in Form ‘D’

    of the Regulations of 1977 wherein the same Articles 2 (d) and (e)

    were involved. The Writ Petitioner there-in was also a similarly

    situated lessee, from whom, penalty for delay in completing the

    construction beyond the period of 4 years was raised by the

    Respondent No 1. The Petitioner in that case had also raised

    identical plea as regards the applicability of the time extension

    Clause. The Lease Deed in that case was also executed prior to 26 th

    August 2015. If that be so there can be no doubt about the fact

    that the legal principles discussed and the findings & observations

    recorded in paragraphs 38 and 41 of Raghuleela Builders, in so

    far as uniform applicability of the 6 years time extension clause is

    concerned, would be applicable to the facts of the present case as

    well. Therefore, we hold that by applying the principles parity, the

    Respondent No. 1 would be duty-bound to extend the same

    Page 60 of 65

    ::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:35:23 :::
    Reliance-oswp-242-2018-J-R.doc

    benefit of extension of time for completion of construction to six

    years to the present Petitioner as well.

    97. In the facts and circumstances of this case, we are also of

    the opinion that there is no legal justification for the Respondent

    No. 1 to confine the benefit of the time extension clause only to

    those Lease Agreements which were executed after 26 th August

    2015 as such an approach would be highly arbitrary and

    discriminatory in nature. Therefore, having regard to the peculiar

    facts and circumstances of this case, we do not find any justifiable

    ground to take a different view on the aforesaid issue.

    98. Law is well settled that for maintaining judicial discipline

    and propriety, a decision rendered by a Coordinate Bench on the

    same issue must be respected and followed by a Coordinate

    Bench. In the case of Mary Pushpam vs. Televi Curusumary & Ors.8

    the Hon’ble Supreme Court has observed that when a decision of a

    Coordinate Bench of the same High Court is brought to the notice

    of the Bench, it is to be respected and would be binding, subject to

    the right of the Bench of such co-equal forum to take a different

    view and refer the question to a larger Bench. In other words, any

    8 (2024) 1 SCR 11.

    Page 61 of 65

    ::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:35:23 :::

    Reliance-oswp-242-2018-J-R.doc

    decision of a Coordinate Bench would be binding on a Bench of

    equal strength subject to the condition that if a different view is

    sought to be taken in the matter, then the issue would have to be

    referred to a larger Bench.

    99. The above legal principle has taken a firm footing in the

    Indian Jurisprudence by a long line of judicial pronouncements.

    We do not deem it necessary to burden this judgment by referring

    to all those decisions. However, suffice it to mention here-in that

    unless there are justifiable grounds to take a different view in the

    matter warranting reference to a larger Bench, the previous

    decision of a coordinate Bench would be binding on a Bench of

    equal strength.

    100. Consequently, it is held that notwithstanding Article 2(d) of

    the Lease Deed dated 1 st September 2006, in view of the decision

    taken by the Respondent No 1 to extend the period of construction

    from four years to six years, the Petitioner, being a similarly

    situated Lessee, would also be entitled to six years’ time for

    completion of the construction. Since, the Commencement

    Certificate for the entire built up area of 3,12,500 sq. mtrs. was

    issued by the Respondent No.1 only on 16 th April 2014, as such,

    Page 62 of 65

    ::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:35:23 :::
    Reliance-oswp-242-2018-J-R.doc

    we are of the opinion that the Petitioner would be entitled to six

    years’ time period, with effect from 16th April 2014, for completing

    the construction for the simple reason that in view of the built-up

    area subsequently allotted to the Petitioner, there was no scope to

    commence construction of the composite construction prior to 14 th

    April 2014. Therefore, adding the period of 4 years 4 month and

    26 days, during which period, the interim order dated 15 th

    October 2007 was in force, the Petitioner, in our opinion, would

    be entitled to total time period of 10 years 4 months 26 days with

    effect from 14th April 2014. Alternately, even if the period of 10

    years 4 months 26 days is counted from 1 st September 2006, i.e.,

    the date of the Lease Deed, even then, the Petitioner would be

    entitled to such period of time for completing the construction of

    the initial built-up area without seeking extension of time. In so

    far as the additional built up area is concerned, in view of the

    communication dated 08/11/2011, as noted above, no time limit

    would at all be applicable for the construction of such built up

    area.

    101. Therefore, we are constrained to hold that the condition

    precedent so as to invoke Articles 2(d) & (e) of the Lease Deed

    Page 63 of 65

    ::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:35:23 :::
    Reliance-oswp-242-2018-J-R.doc

    Dated 1st September, 2006 was not met in this case. As such, we

    are also of the view that no additional premium/ penalty was

    either payable or recoverable from the Petitioner on account of

    delay in completing the construction.

    102. For the reasons stated above, this Writ Petition succeeds

    and the same is hereby allowed in terms of payer clauses(a),(a)

    (i),(a)(ii)(a)&(b). The impugned Demand Notices dated

    12/09/2017 and 13th June 2019 are accordingly, set aside.

    103. Consequently, we hold that the Petitioner would be entitled

    for refund of the amount of Rs.646,77,68,594 (Rupees Six

    Hundred and Forty Six Crores Seventy Seven Lakhs Sixty Eight

    Thousand Five Hundred and Ninety Four) deposited as additional

    premium/ penalty for the alleged delay in completion of the

    construction. The Respondent No 1 is, therefore, directed to

    refund the aforesaid amount to the Petitioner within a period of

    90 (ninety) days from the date of receipt of the Certified Copy of

    this order, failing which, the amount would carry interest at the

    same rate at which, interest was payable by the Petitioner under

    the Lease Agreement due to delay in paying premium, to be

    calculated from the date of this order till the date of the refund.

    Page 64 of 65

    ::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:35:23 :::

    Reliance-oswp-242-2018-J-R.doc

    104. In so far as the Bank Guarantee(s) furnished by the

    Petitioner including that for an amount of Rs.13,12,54,85,287/-

    (Rupees Thirteen Hundred Twelve Crores Fifty Four Lakhs Eighty

    Five Thousand Two Hundred and Eighty Seven ) the same shall be

    kept valid for a period of 90 (Ninety) days from the date of this

    order.

    105. With the above observations, the Rule is made absolute.

    106. The Writ Petition stands disposed of.

    107. Parties to bear their own cost.

    108. In view of disposal of the Writ Petition, nothing survives in

    the Interim Application and the same is disposed of accordingly.

    (SUMAN SHYAM, J)                                         (CHIEF JUSTICE)
    
    
    
    
                                   Page 65 of 65
    
    
    ::: Uploaded on - 09/04/2026                   ::: Downloaded on - 09/04/2026 21:35:23 :::
     



    Source link

    LEAVE A REPLY

    Please enter your comment!
    Please enter your name here