Union Of India vs M/S Varindera Constructions Ltd on 1 April, 2026

    0
    37
    ADVERTISEMENT

    Delhi High Court

    Union Of India vs M/S Varindera Constructions Ltd on 1 April, 2026

                      $~
                      *         IN THE HIGH COURT OF DELHI AT NEW DELHI
                      %                                   Judgment reserved on: 13.02.2026
                                                       Judgment pronounced on: 01.04.2026
                      +         O.M.P. (COMM) 73/2024 & I.A. 43484/2024 (Seeking
                                withdrawal of amount deposited by petitioner)
    
                                UNION OF INDIA                                 .....Petitioner
                                                 Through:    Mr. Vikas Kumar Sharma,
                                                             Senior Central Government
                                                             Counsel.
                                                 versus
    
                                M/S VARINDERA CONSTRUCTIONS LTD. .....Respondent
                                                 Through:    Ms. Risha Mittal and Mr. Md.
                                                             Adil Alam, Advocates.
                               CORAM:
                               HON'BLE MR. JUSTICE HARISH VAIDYANATHAN
                               SHANKAR
                                                  JUDGMENT
    

    HARISH VAIDYANATHAN SHANKAR, J.

    1. The present Petition under Section 34 of the Arbitration and
    Conciliation Act, 1996 1 has been filed impugning the Arbitral
    Award dated 27.08.2023 along with the corrigendum dated
    20.10.20232, passed by the learned Sole Arbitrator in disputes arising
    out of Contract dated 03.11.2014 executed between the parties for the
    construction of dwelling units under the Married Accommodation
    Project at Jodhpur.

    SPONSORED

    1

    A&C Act
    2
    Arbitral Award
    Signature Not Verified
    Digitally Signed
    By:NEERU O.M.P. (COMM) 73/2024 Page 1 of 48
    Signing Date:04.04.2026
    12:18:42

    2. By way of the present proceeding, the Petitioner seeks to assail
    the Impugned Arbitral Award, principally on the ground that the
    mandate of the learned Arbitrator had expired under Section 29A of
    the A&C Act, prior to the pronouncement of the Award, and that the
    grant of interest by the learned Arbitral Tribunal is legally
    unsustainable.

    BRIEF FACTS:

    3. Shorn of unnecessary details, the facts germane to the
    institution of the present Appeal are as follows:

    I. Briefly stated, the disputes between the parties arise out of a
    works contract awarded by Union of India3 to the Respondent
    for the construction of dwelling units for Officers, JCOs and
    ORs under the Married Accommodation Project at Jodhpur.
    II. The contract was awarded pursuant to a Letter of Acceptance
    dated 03.11.2014 for a total contract value of ₹138,95,30,116/-.
    The date of commencement of the work was 27.11.2014 and the
    stipulated period for completion of the project was 25 months,
    with the original date of completion being 26.12.2016. The
    work was eventually completed on 10.03.2017.
    III. Upon completion of the work, the Respondent submitted its
    final bill on 27.06.2017. The undisputed portion of the final bill
    was paid by UOI on 30.11.2019. Certain disputes thereafter
    arose between the parties, inter alia, concerning alleged delay
    in payment of the final bill, claims relating to prolonged bank
    guarantees, delayed or under payments of Running Account

    3
    UOI
    Signature Not Verified
    Digitally Signed
    By:NEERU O.M.P. (COMM) 73/2024 Page 2 of 48
    Signing Date:04.04.2026
    12:18:42
    Receipts 4 , and claims pertaining to deviation works and
    additional items.

    IV. In view of the disputes having arisen between the parties, an
    Arbitral Tribunal comprising a learned Sole Arbitrator came to
    be constituted pursuant to an Order dated 15.09.2020 passed by
    this Court in ARB.P. 378/2020.

    V. The learned Arbitrator entered upon reference and arbitral
    proceedings commenced under the provisions of the A&C Act.
    VI. During the course of the arbitral proceedings, the Respondent
    filed its Statement of Claim raising several claims, including
    interest on delayed payment of the final bill, losses on account
    of prolonged bank guarantees, losses due to delayed and
    underpayments of RARs, and claims relating to deviation works
    and additional items. UOI filed its Statement of Defence
    opposing the claims and also raised a counterclaim.
    VII. The Petitioner claims that the pleadings in the arbitral
    proceedings were completed on 24.05.2021.

    VIII. During the pendency of the arbitral proceedings, UOI filed an
    Application dated 10.04.2023 before the learned Arbitrator,
    invoking Section 29A of the A&C Act, contending that the
    mandate of the learned Arbitrator had expired and seeking
    termination of the arbitral proceedings on that ground. The said
    Application was heard by the learned Arbitrator and was
    ultimately dealt with in the Impugned Award.
    IX. The learned Sole Arbitrator thereafter rendered the Arbitral
    Award dated 27.08.2023, whereby several claims of the

    4
    RARs
    Signature Not Verified
    Digitally Signed
    By:NEERU O.M.P. (COMM) 73/2024 Page 3 of 48
    Signing Date:04.04.2026
    12:18:42
    Respondent were partly allowed. Under the Award, amounts
    were granted under different heads, including claims relating to
    delayed payment of the final bill, losses arising from delayed
    and underpayments of RARs, and certain additional works. In
    aggregate, the Respondent was awarded amounts of
    approximately ₹6 crores under various claims. The learned
    Arbitrator further directed payment of interest at the rate of 12%
    per annum on the sums awarded from 18.03.2020 till the date of
    payment.

    X. Subsequently, on the Petitioner‟s application, a corrigendum
    dated 20.10.2023 was issued by the learned Arbitrator.
    XI. Aggrieved by the said Award and the corrigendum thereto, UOI
    has preferred the present Petition under Section 34 of the A&C
    Act, contending that the Impugned Arbitral Award was
    rendered after the expiry of the mandate of the learned
    Arbitrator under Section 29A of the A&C Act and that the grant
    of interest at the rate of 12% per annum is legally unsustainable.

    CONTENTIONS ON BEHALF OF THE PETITIONER:

    4. Learned counsel appearing on behalf of UOI would contend
    that the Impugned Award is liable to be set aside primarily on the
    ground that the mandate of the learned Sole Arbitrator had expired
    under Section 29A of the A&C Act prior to the pronouncement of the
    Arbitral Award. It would be submitted that the scheme of the A&C
    Act mandates expeditious adjudication of disputes and prescribes a
    strict timeline for rendering an arbitral award. According to the
    Petitioner, once the pleadings in the arbitral proceedings stood
    completed on 24.05.2021, the learned Arbitrator was required to
    Signature Not Verified
    Digitally Signed
    By:NEERU O.M.P. (COMM) 73/2024 Page 4 of 48
    Signing Date:04.04.2026
    12:18:42
    render the Arbitral Award within a period of twelve months
    therefrom.

    5. Learned counsel for UOI would contend that the statutory
    period of twelve months for rendering the Arbitral Award expired on
    24.05.2022 and no extension of time was obtained either by mutual
    consent of the parties or from the Court as contemplated under Section
    29A
    of the A&C Act. It would thus be urged that upon expiry of the
    prescribed period, the mandate of the learned Arbitrator stood
    terminated by operation of law and the learned Arbitrator thereafter
    became functus officio, and consequently, the Award rendered on
    27.08.2023 is without jurisdiction and liable to be set aside.

    6. Learned counsel would further submit that UOI had raised the
    issue of expiry of mandate before the learned Arbitrator by filing an
    Application dated 10.04.2023, invoking Section 29A of the A&C Act.
    It would be contended that the said application was argued before the
    learned Arbitrator and the matter was reserved for orders; however,
    the learned Arbitrator did not adjudicate the said application
    independently and instead proceeded to deal with the same while
    rendering the Arbitral Award. According to the Petitioner, the
    continuation of the arbitral proceedings despite the alleged expiry of
    the mandate was contrary to the statutory framework of the A&C Act.

    7. Learned counsel for UOI would further contend that the
    reliance placed by the learned Arbitrator on the Orders passed by the
    Hon‟ble Supreme Court in Suo Motu Writ Petition (C) No. 3 of 2020
    for exclusion of the period between 15.03.2020 and 28.02.2022 is
    misconceived. It would be submitted that even if the said period is
    excluded for the purpose of computing the limitation, the learned
    Arbitrator was still required to render the Award within the
    Signature Not Verified
    Digitally Signed
    By:NEERU O.M.P. (COMM) 73/2024 Page 5 of 48
    Signing Date:04.04.2026
    12:18:42
    permissible statutory period thereafter. According to the Petitioner,
    even on such computation, the Award rendered on 27.08.2023 would
    fall beyond the permissible time limit prescribed under Section 29A of
    the A&C Act.

    8. In support of the aforesaid submission, learned counsel for UOI
    would place reliance on the judgment of the Hon‟ble Supreme Court
    in NBCC Ltd. v. J.G. Engineering Pvt. Ltd.5, wherein it was held that
    an arbitrator is required to render the award within the time prescribed
    under law or agreed between the parties and that in the absence of
    consent of the parties for enlargement of time, the authority of the
    arbitrator would cease upon expiry of the prescribed period.

    9. Learned counsel for the Petitioner would further rely upon the
    judgment of the Telangana High Court in Roop Singh Bhatty v. M/s
    Shriram City Union Finance Limited6, wherein it was held that once
    the statutory period prescribed for rendering the award expires, the
    arbitrator becomes functus officio and any award passed thereafter
    would be a nullity in the eyes of law.

    10. Reliance would also be placed on the decision of the Madras
    High Court in M/s Satyam Caterers Private Limited v. The Assistant
    Commercial Manager7
    , wherein it was held that the Arbitral Tribunal
    must complete the arbitral proceedings within the period stipulated
    under Section 29A of the A&C Act and that any award rendered
    beyond the permissible period without extension granted by the Court
    would be patently illegal and liable to be set aside.

    5

    2010 (2) SCC 385
    6
    C.R.P.NO.1354 of 2021
    7
    O.P. No.592/2018 (Decision Date: 09.08.2018)
    Signature Not Verified
    Digitally Signed
    By:NEERU O.M.P. (COMM) 73/2024 Page 6 of 48
    Signing Date:04.04.2026
    12:18:42

    11. Apart from the aforesaid jurisdictional challenge, learned
    counsel for UOI would contend that the learned Arbitrator has erred in
    awarding interest at the rate of 12% per annum on the sums awarded
    to the Respondent. It would be submitted that the rate of interest
    awarded by the learned Arbitrator is excessive and contrary to the
    prevailing bank rates in the country.

    12. Learned counsel would further contend that the learned
    Arbitrator has granted interest on certain claims despite the absence of
    any contractual stipulation entitling the Respondent to such interest. It
    would be submitted that, in terms of Section 3(b) of the Interest Act,
    19788, interest could be awarded only if a written demand notice had
    been issued by the claimant claiming such interest. According to the
    Petitioner, no such notice had been issued by the Respondent, and
    therefore, the grant of past interest is legally unsustainable.

    13. Learned counsel for UOI would also contend that the learned
    Arbitrator has erred in awarding interest on account of the alleged
    delay in payment of RARs. It would also be submitted that the learned
    Arbitrator has proceeded on the assumption that the RARs were
    required to be paid within seven days, which finding is stated to be
    contrary to the settled position of law.

    14. In this regard, reliance would be placed on the judgment of this
    Court in M/s Vascon Engineers Ltd. v. Union of India9, wherein it
    was observed that in the absence of any specific contractual
    stipulation prescribing a time period for processing of bills, a
    reasonable period of forty-five days could be taken as the benchmark
    for determining delay. It would be contended that the learned

    8
    Interest Act
    9
    2021:DHC:2828
    Signature Not Verified
    Digitally Signed
    By:NEERU O.M.P. (COMM) 73/2024 Page 7 of 48
    Signing Date:04.04.2026
    12:18:42
    Arbitrator has ignored the said principle and has erroneously
    proceeded on the basis of a seven-day period while awarding interest.

    15. Learned counsel for the Petitioner would therefore submit that
    the Impugned Award suffers from patent illegality, jurisdictional error
    and is contrary to the provisions of the A&C Act. It would
    accordingly be prayed that the Impugned Award be set aside.

    CONTENTIONS ON BEHALF OF THE RESPONDENT:

    16. Per contra, learned counsel appearing on behalf of the
    Respondent would contend that the present Petition under Section 34
    of the A&C Act is wholly misconceived and is liable to be dismissed
    in limine. It would be submitted that the grounds urged by UOI do not
    fall within the limited scope of interference permissible under Section
    34
    of the A&C Act and that the Impugned Award does not suffer from
    any patent illegality or jurisdictional error warranting interference by
    this Court.

    17. Learned counsel for the Respondent would first address the
    contention of UOI regarding the alleged expiry of the mandate of the
    learned Arbitrator under Section 29A of the A&C Act. It would be
    submitted that UOI had filed an Application dated 10.04.2023 before
    the learned Arbitrator, invoking Section 29A and alleging that the
    mandate of the tribunal had expired on 24.05.2022. According to the
    Respondent, the learned Arbitrator considered the said application in
    detail and rejected the same in the Impugned Award.

    18. Learned counsel would contend that the conduct of UOI itself
    demonstrates that the objection relating to the expiry of the mandate is
    an afterthought. It would be submitted that even though UOI claims
    that the mandate of the tribunal had expired on 24.05.2022, the
    Signature Not Verified
    Digitally Signed
    By:NEERU O.M.P. (COMM) 73/2024 Page 8 of 48
    Signing Date:04.04.2026
    12:18:42
    application invoking Section 29A was filed only on 10.04.2023,
    nearly one year thereafter. It is urged that during this period, UOI
    continued to participate in the arbitral proceedings without demur.

    19. It would further be submitted that even after filing the said
    application under Section 29A, UOI continued to participate in the
    arbitral proceedings and addressed arguments on merits before the
    learned Arbitrator. Learned counsel would submit that UOI
    participated in the hearings conducted on 12.04.2023 and 21.04.2023
    and also participated in the hearing conducted for the Respondent‟s
    rejoinder arguments on 08.05.2023. It would therefore be contended
    that the participation of UOI in the proceedings clearly indicates that
    the mandate of the learned Arbitrator was accepted and cannot now be
    challenged.

    20. Learned counsel for the Respondent would further submit that
    even after the Impugned Award was rendered on 27.08.2023, UOI
    filed an application under Section 33 of the A&C Act seeking
    correction in the rate of interest awarded by the learned Arbitrator.
    According to the Respondent, such conduct on the part of UOI clearly
    demonstrates that it accepted the jurisdiction and mandate of the
    learned Arbitrator and therefore cannot now be permitted to contend
    that the tribunal lacked jurisdiction.

    21. Learned counsel would further contend that the objection raised
    by UOI regarding the expiry of the mandate under Section 29A is also
    untenable in view of the orders passed by the Hon‟ble Supreme Court
    in Suo Motu Writ Petition (C) No. 3 of 2020, whereby the period
    between 15.03.2020 and 28.02.2022 was directed to be excluded for
    the purpose of computing limitation under various statutes, including
    the timelines prescribed under the A&C Act.

    Signature Not Verified
    Digitally Signed
    By:NEERU O.M.P. (COMM) 73/2024 Page 9 of 48
    Signing Date:04.04.2026
    12:18:42

    22. It would be submitted that in view of the aforesaid orders of the
    Hon‟ble Supreme Court, the period between 15.03.2020 and
    28.02.2022 stood excluded while computing the period prescribed
    under Section 23(4) and Section 29A of the A&C Act. According to
    the Respondent, the learned Arbitrator rightly applied the said
    exclusion while computing the timeline for rendering the Award.

    23. Learned counsel would further place reliance on the judgment
    of the Hon‟ble Supreme Court in Arif Azim Co. Ltd. v. Aptech Ltd.10,
    wherein it was clarified that the period between 15.03.2020 and
    28.02.2022 shall stand excluded for the purpose of computing
    timelines under Sections 23(4) and 29A of the A&C Act. It would be
    submitted that the said judgment squarely supports the computation
    adopted by the learned Arbitrator in the present case.

    24. Learned counsel for the Respondent would also rely upon the
    judgment of this Court in Chroma-Ator Energy Systems Pvt. Ltd. v.
    Indraprastha Gas Ltd. 11 , wherein this Court held that the period
    excluded by virtue of the orders passed in Suo Motu Writ Petition (C)
    No. 3 of 2020 would have to be excluded while computing the period
    of limitation.

    25. Reliance is also placed on the decision of this Court in
    Drooshba Fabricators v. Indure Pvt. Ltd.12, wherein it was held that
    the delay occurring during the period covered by the orders passed in
    Suo Motu Writ Petition (C) No. 3 of 2020 would stand excluded while
    computing limitation.

    10

    2024 SCC OnLine SC 215.

    11

    2024 SCC OnLine Del 2480
    12
    2022:DHC:3427
    Signature Not Verified
    Digitally Signed
    By:NEERU O.M.P. (COMM) 73/2024 Page 10 of 48
    Signing Date:04.04.2026
    12:18:42

    26. Learned counsel would therefore submit that once the exclusion
    of the aforesaid period is applied, the timeline for rendering the Award
    stood extended and the Award rendered on 27.08.2023 would fall well
    within the permissible period. It would thus be contended that the
    objection regarding the expiry of the mandate of the learned Arbitrator
    is wholly untenable.

    27. Learned counsel for the Respondent would next address the
    contention of UOI relating to the rate of interest awarded by the
    learned Arbitrator. According to the Respondent, the Impugned
    Award clearly reflects that interest at the rate of 12% per annum has
    been awarded on the sums found due.

    28. Learned counsel would submit that the rate of interest awarded
    by the learned Arbitrator is reasonable and is in consonance with the
    statutory framework of the A&C Act. Reliance in this regard would be
    placed on the judgment of the Hon‟ble Supreme Court in Oil and
    Natural Gas Corporation Ltd. v. G and T Beckfield Drilling Services
    Pvt. Ltd.13
    , wherein the grant of interest at the rate of 12% per annum
    was upheld as reasonable.

    29. Learned counsel would further rely upon the judgment of the
    Hon‟ble Supreme Court in Sri Lakshmi Hotel Pvt. Ltd. v. Sriram City
    Union Finance Ltd.14
    , wherein it has been held that disputes relating
    to the rate of interest awarded by an arbitral tribunal would ordinarily
    not fall within the limited scope of challenge under Section 34 of the
    A&C Act.

    30. Learned counsel for the Respondent would also place reliance
    on the judgment of the Hon‟ble Supreme Court in Consolidated

    13
    2025 INSC 1066
    14
    2025 INSC 1327
    Signature Not Verified
    Digitally Signed
    By:NEERU O.M.P. (COMM) 73/2024 Page 11 of 48
    Signing Date:04.04.2026
    12:18:42
    Construction Ltd. v. Software Technology Parks of India15, wherein
    it was reiterated that Section 34 of the A&C Act does not confer
    appellate jurisdiction upon the Court and that the Court cannot
    reappreciate evidence or substitute its own view merely because
    another view is possible.

    31. It would therefore be submitted that the Impugned Award
    represents a plausible view taken by the learned Arbitrator on the
    basis of the material placed on record and does not warrant
    interference under Section 34 of the A&C Act.

    ANALYSIS:

    32. This Court has carefully considered the submissions advanced
    on behalf of both sides and, with their able assistance, has perused the
    Arbitral Award and the material placed before this Court.

    33. At the outset, it is apposite to note that this Court remains
    conscious of the limited scope of its jurisdiction while examining an
    objection petition under Section 34 of the A&C Act. There is a
    consistent and evolving line of precedents whereby the Hon‟ble
    Supreme Court has authoritatively delineated and settled the contours
    of judicial intervention in such proceedings.

    34. In this regard, a three-Judge Bench of the Hon‟ble Supreme
    Court, after an exhaustive consideration of a catena of earlier
    judgments, in OPG Power Generation (P) Ltd. v. Enexio Power
    Cooling Solutions (India) (P) Ltd.16
    , while dealing with the grounds
    of conflict with the public policy of India and patent illegality,

    15
    (2025) 7 SCC 757
    16
    (2025) 2 SCC 417
    Signature Not Verified
    Digitally Signed
    By:NEERU O.M.P. (COMM) 73/2024 Page 12 of 48
    Signing Date:04.04.2026
    12:18:42
    grounds which have also been urged in the present case, made certain
    pertinent observations, which are reproduced hereunder:

    “Relevant legal principles governing a challenge to an arbitral
    award

    30. Before we delve into the issue/sub-issues culled out above, it
    would be useful to have a look at the relevant legal principles
    governing a challenge to an arbitral award. Recourse to a court
    against an arbitral award may be made through an application for
    setting aside such award in accordance with sub-sections (2), (2-A)
    and (3) of Section 34 of the 1996 Act. Sub-section (2) of Section 34
    has two clauses, (a) and (b). Clause (a) has five sub-clauses which
    are not relevant to the issues raised before us. Insofar as clause (b)
    is concerned, it has two sub-clauses, namely, (i) and (ii). Sub-
    clause (i) of clause (b) is not relevant to the controversy in hand.
    Sub-clause (ii) of clause (b) provides that if the Court finds that the
    arbitral award is in conflict with the public policy of India, it may
    set aside the award.

    Public policy

    31. “Public policy” is a concept not statutorily defined, though it
    has been used in statutes, rules, notification, etc. since long, and is
    also a part of common law. Section 23 of the Contract Act, 1872
    uses the expression by stating that the consideration or object of an
    agreement is lawful, unless, inter alia, opposed to public policy.
    That is, a contract which is opposed to public policy is void.

    *****

    37. What is clear from above is that for an award to be against
    public policy of India a mere infraction of the municipal laws of
    India is not enough. There must be, inter alia, infraction of
    fundamental policy of Indian law including a law meant to serve
    public interest or public good.

    *****
    The 2015 Amendment in Sections 34 and 48

    42. The aforementioned judicial pronouncements were all prior to
    the 2015 Amendment. Notably, prior to the 2015 Amendment the
    expression “in contravention with the fundamental policy of Indian
    law” was not used by the legislature in either Section 34(2)(b)(ii) or
    Section 48(2)(b). The pre-amended Section 34(2)(b)(ii) and its
    Explanation read:

    *****

    44. By the 2015 Amendment, in place of the old Explanation to
    Section 34(2)(b)(ii), Explanations 1 and 2 were added to remove
    any doubt as to when an arbitral award is in conflict with the public
    policy of India.

    45. At this stage, it would be pertinent to note that we are dealing
    with a case where the application under Section 34 of the 1996 Act
    was filed after the 2015 Amendment, therefore the newly

    Signature Not Verified
    Digitally Signed
    By:NEERU O.M.P. (COMM) 73/2024 Page 13 of 48
    Signing Date:04.04.2026
    12:18:42
    substituted/added Explanations would apply [Ssangyong Engg. &
    Construction Co. Ltd. v. NHAI
    , (2019) 15 SCC 131].

    46. The 2015 Amendment adds two Explanations to each of the
    two sections, namely, Section 34(2)(b)(ii) and Section 48(2)(b), in
    place of the earlier Explanation. The significance of the newly
    inserted Explanation 1 in both the sections is two-fold. First, it does
    away with the use of words : (a) “without prejudice to the
    generality of sub-clause (ii)” in the opening part of the pre-

    amended Explanation to Section 34(2)(b)(ii); and (b) “without
    prejudice to the generality of clause (b) of this section” in the
    opening part of the pre-amended Explanation to Section 48(2)(b);
    secondly, it limits the expanse of public policy of India to the three
    specified categories by using the words “only if”.
    Whereas, Explanation 2 lays down the standard for adjudging
    whether there is a contravention with the fundamental policy of
    Indian law by providing that a review on merits of the dispute shall
    not be done. This limits the scope of the enquiry on an application
    under either Section 34(2)(b)(ii) or Section 48(2)(b) of the 1996
    Act.

    47. The 2015 Amendment by inserting sub-section (2-A) in Section
    34
    , carves out an additional ground for annulment of an arbitral
    award arising out of arbitrations other than international
    commercial arbitrations. Sub-section (2-A) provides that the Court
    may also set aside an award if that is vitiated by patent illegality
    appearing on the face of the award. This power of the Court is,
    however, circumscribed by the proviso, which states that an award
    shall not be set aside merely on the ground of an erroneous
    application of the law or by reappreciation of evidence.

    48. Explanation 1 to Section 34(2)(b)(ii), specifies that an arbitral
    award is in conflict with the public policy of India, only if:

    (i) the making of the award was induced or affected by fraud or
    corruption or was in violation of Section 75 or Section 81; or

    (ii) it is in contravention with the fundamental policy of Indian law;

    or

    (iii) it is in conflict with the most basic notions of morality or
    justice.

    49. In the instant case, there is no allegation that the making of the
    award was induced or affected by fraud or corruption, or was in
    violation of Section 75 or Section 81. Therefore, we shall confine
    our exercise in assessing as to whether the arbitral award is in
    contravention with the fundamental policy of Indian law, and/or
    whether it conflicts with the most basic notions of morality or
    justice. Additionally, in the light of the provisions of sub-section
    (2-A) of Section 34, we shall examine whether there is any patent
    illegality on the face of the award.

    50. Before undertaking the aforesaid exercise, it would be apposite
    to consider as to how the expressions:

    (a) “in contravention with the fundamental policy of Indian law”;

    Signature Not Verified
    Digitally Signed
    By:NEERU O.M.P. (COMM) 73/2024 Page 14 of 48
    Signing Date:04.04.2026
    12:18:42

    (b) “in conflict with the most basic notions of morality or justice”;
    and

    (c) “patent illegality” have been construed.

    In contravention with the fundamental policy of Indian law

    51. As discussed above, till the 2015 Amendment the expression
    “in contravention with the fundamental policy of Indian law” was
    not found in the 1996 Act. Yet, in Renusagar Power Co.
    Ltd. v. General Electric Co.
    , 1994 Supp (1) SCC 644, in the
    context of enforcement of a foreign award, while construing the
    phrase “contrary to the public policy”, this Court held that for a
    foreign award to be contrary to public policy mere contravention of
    law would not be enough rather it should be contrary to:

    (a) the fundamental policy of Indian law; and/or

    (b) the interest of India; and/or

    (c) justice or morality.

    *****

    55. The legal position which emerges from the aforesaid discussion
    is that after “the 2015 Amendments” in Section 34(2)(b)(ii) and
    Section 48(2)(b) of the 1996 Act, the phrase “in conflict with the
    public policy of India” must be accorded a restricted meaning in
    terms of Explanation 1. The expression “in contravention with the
    fundamental policy of Indian law” by use of the word
    “fundamental” before the phrase “policy of Indian law” makes the
    expression narrower in its application than the phrase “in
    contravention with the policy of Indian law”, which means mere
    contravention of law is not enough to make an award vulnerable.
    To bring the contravention within the fold of fundamental policy of
    Indian law, the award must contravene all or any of such
    fundamental principles that provide a basis for administration of
    justice and enforcement of law in this country.

    56. Without intending to exhaustively enumerate instances of such
    contravention, by way of illustration, it could be said that:

    (a) violation of the principles of natural justice;

    (b) disregarding orders of superior courts in India or the binding
    effect of the judgment of a superior court; and

    (c) violating law of India linked to public good or public interest,
    are considered contravention of the fundamental policy of
    Indian law.

    However, while assessing whether there has been a contravention
    of the fundamental policy of Indian law, the extent of judicial
    scrutiny must not exceed the limit as set out in Explanation 2 to
    Section 34(2)(b)(ii).

    *****
    Patent illegality

    65. Sub-section (2-A) of Section 34 of the 1996 Act, which was
    inserted by the 2015 Amendment, provides that an arbitral award
    not arising out of international commercial arbitrations, may also
    be set aside by the Court, if the Court finds that the award is visited
    Signature Not Verified
    Digitally Signed
    By:NEERU O.M.P. (COMM) 73/2024 Page 15 of 48
    Signing Date:04.04.2026
    12:18:42
    by patent illegality appearing on the face of the award. The proviso
    to sub-section (2-A) states that an award shall not be set aside
    merely on the ground of an erroneous application of the law or by
    reappreciation of evidence.

    66. In ONGC Ltd. v. Saw Pipes Ltd., (2003) 5 SCC 705, while
    dealing with the phrase “public policy of India” as used in Section
    34
    , this Court took the view that the concept of public policy
    connotes some matter which concerns public good and public
    interest. If the award, on the face of it, patently violates statutory
    provisions, it cannot be said to be in public interest. Thus, an award
    could also be set aside if it is patently illegal. It was, however,
    clarified that illegality must go to the root of the matter and if the
    illegality is of trivial nature, it cannot be held that award is against
    public policy.

    67. In Associate Builders v. DDA, (2015) 3 SCC 49, this Court
    held that an award would be patently illegal, if it is contrary to:

    (a) substantive provisions of law of India;

    (b) provisions of the 1996 Act; and

    (c) terms of the contract [See also three-Judge Bench decision of
    this Court in State of Chhattisgarh v. SAL Udyog (P) Ltd.,
    (2022) 2 SCC 275].

    The Court clarified that if an award is contrary to the substantive
    provisions of law of India, in effect, it is in contravention of
    Section 28(1)(a) of the 1996 Act. Similarly, violating terms of the
    contract, in effect, is in contravention of Section 28(3) of the 1996
    Act.

    68. In Ssangyong Engg. & Construction Co. Ltd. v. NHAI, (2019)
    15 SCC 131 this Court specifically dealt with the 2015
    Amendment which inserted sub-section (2-A) in Section 34 of the
    1996 Act. It was held that “patent illegality appearing on the face
    of the award” refers to such illegality as goes to the root of matter,
    but which does not amount to mere erroneous application of law.
    It
    was also clarified that what is not subsumed within “the
    fundamental policy of Indian law”, namely, the contravention of a
    statute not linked to “public policy” or “public interest”, cannot be
    brought in by the backdoor when it comes to setting aside an award
    on the ground of patent illegality [ See Ssangyong Engg. &
    Construction Co. Ltd. v. NHAI
    , (2019) 15 SCC 131].
    Further, it
    was observed, reappreciation of evidence is not permissible under
    this category of challenge to an arbitral award [See Ssangyong
    Engg. & Construction Co. Ltd. v. NHAI
    , (2019) 15 SCC 131].
    Perversity as a ground of challenge

    69. Perversity as a ground for setting aside an arbitral award was
    recognised in ONGC Ltd. v. Western Geco International Ltd.,
    (2014) 9 SCC 263. Therein it was observed that an arbitral decision
    must not be perverse or so irrational that no reasonable person
    would have arrived at the same. It was observed that if an award is
    perverse, it would be against the public policy of India.

    Signature Not Verified
    Digitally Signed
    By:NEERU O.M.P. (COMM) 73/2024 Page 16 of 48
    Signing Date:04.04.2026
    12:18:42

    70. In Associate Builders v. DDA, (2015) 3 SCC 49 certain tests
    were laid down to determine whether a decision of an Arbitral
    Tribunal could be considered perverse. In this context, it was
    observed that where:

    (i) a finding is based on no evidence; or

    (ii) an Arbitral Tribunal takes into account something irrelevant to
    the decision which it arrives at; or

    (iii) ignores vital evidence in arriving at its decision, such decision
    would necessarily be perverse.

    However, by way of a note of caution, it was observed that when a
    court applies these tests it does not act as a court of appeal and,
    consequently, errors of fact cannot be corrected. Though, a possible
    view by the arbitrator on facts has necessarily to pass muster as the
    arbitrator is the ultimate master of the quantity and quality of
    evidence to be relied upon. It was also observed that an award
    based on little evidence or on evidence which does not measure up
    in quality to a trained legal mind would not be held to be invalid on
    that score.

    71. In Ssangyong Engg. & Construction Co. Ltd. v. NHAI, (2019)
    15 SCC 131, which dealt with the legal position post the 2015
    Amendment in Section 34 of the 1996 Act, it was observed that a
    decision which is perverse, while no longer being a ground for
    challenge under “public policy of India”, would certainly amount to
    a patent illegality appearing on the face of the award. It was
    pointed out that an award based on no evidence, or which ignores
    vital evidence, would be perverse and thus patently illegal.
    It was
    also observed that a finding based on documents taken behind the
    back of the parties by the arbitrator would also qualify as a decision
    based on no evidence inasmuch as such decision is not based on
    evidence led by the parties, and therefore, would also have to be
    characterised as perverse [ See Ssangyong Engg. & Construction
    Co. Ltd. v. NHAI
    , (2019) 15 SCC 131].

    72. The tests laid down in Associate Builders v. DDA, (2015) 3
    SCC 49 to determine perversity were followed in Ssangyong
    Engg. & Construction Co. Ltd. v. NHAI
    , (2019) 15 SCC 131 and
    later approved by a three-Judge Bench of this Court in Patel Engg.
    Ltd. v. North Eastern Electric Power Corpn. Ltd.
    , (2020) 7 SCC

    167.

    73. In a recent three-Judge Bench decision of this Court in DMRC
    Ltd. v. Delhi Airport Metro Express (P) Ltd., (2024) 6 SCC 357,
    the ground of patent illegality/perversity was delineated in the
    following terms: (SCC p. 376, para 39)
    “39. In essence, the ground of patent illegality is available
    for setting aside a domestic award, if the decision of the
    arbitrator is found to be perverse, or so irrational that no
    reasonable person would have arrived at it; or the
    construction of the contract is such that no fair or
    reasonable person would take; or, that the view of the
    Signature Not Verified
    Digitally Signed
    By:NEERU O.M.P. (COMM) 73/2024 Page 17 of 48
    Signing Date:04.04.2026
    12:18:42
    arbitrator is not even a possible view. A finding based on
    no evidence at all or an award which ignores vital
    evidence in arriving at its decision would be perverse and
    liable to be set aside under the head of “patent illegality”.
    An award without reasons would suffer from patent
    illegality. The arbitrator commits a patent illegality by
    deciding a matter not within its jurisdiction or violating a
    fundamental principle of natural justice.”

    Scope of interference with an arbitral award

    74. The aforesaid judicial precedents make it clear that while
    exercising power under Section 34 of the 1996 Act the Court does
    not sit in appeal over the arbitral award. Interference with an
    arbitral award is only on limited grounds as set out in Section 34 of
    the 1996 Act. A possible view by the arbitrator on facts is to be
    respected as the arbitrator is the ultimate master of the quantity and
    quality of evidence to be relied upon. It is only when an arbitral
    award could be categorised as perverse, that on an error of fact an
    arbitral award may be set aside. Further, a mere erroneous
    application of the law or wrong appreciation of evidence by itself is
    not a ground to set aside an award as is clear from the provisions of
    sub-section (2-A) of Section 34 of the 1996 Act.

    75. In Dyna Technologies (P) Ltd. v. Crompton Greaves Ltd.,
    (2019) 20 SCC 1, paras 27-43, a three-Judge Bench of this Court
    held that courts need to be cognizant of the fact that arbitral awards
    are not to be interfered with in a casual and cavalier manner, unless
    the court concludes that the perversity of the award goes to the root
    of the matter and there is no possibility of an alternative
    interpretation that may sustain the arbitral award. It was observed
    that jurisdiction under Section 34 cannot be equated with the
    normal appellate jurisdiction. Rather, the approach ought to be to
    respect the finality of the arbitral award as well as party’s autonomy
    to get their dispute adjudicated by an alternative forum as provided
    under the law.”

    35. In the present case, the principal questions that arise for
    determination are, firstly, whether the mandate of the learned Sole
    Arbitrator had lapsed in terms of Section 29A of the A&C Act prior to
    the pronouncement of the Impugned Arbitral Award dated
    27.08.2023, thereby rendering the said Award without jurisdiction;
    and secondly, whether the grant of interest at the rate of 12% per
    annum by the learned Arbitral Tribunal on the amounts awarded in

    Signature Not Verified
    Digitally Signed
    By:NEERU O.M.P. (COMM) 73/2024 Page 18 of 48
    Signing Date:04.04.2026
    12:18:42
    favour of the Respondent calls for interference in the exercise of this
    Court‟s jurisdiction under Section 34 of the A&C Act.

    i. Expiry of Arbitral Tribunal’s Mandate under Section 29A

    36. Insofar as the first issue is concerned, it becomes apposite to
    examine the statutory framework governing the time limit for making
    an arbitral award. Section 29A of the A&C Act prescribes the period
    within which an arbitral tribunal is required to render its award and the
    consequences that ensue upon expiry of such period. For the sake of
    completeness, the relevant provision is extracted herein below:

    “29-A. Time limit for arbitral award. — (1) The award in
    matters other than international commercial arbitration shall be
    made by the arbitral tribunal within a period of twelve months
    from the date of completion of pleadings under sub-section (4) of
    Section 23:

    (2) If the award is made within a period of six months from the
    date the arbitral tribunal enters upon the reference, the arbitral
    tribunal shall be entitled to receive such amount of additional fees
    as the parties may agree.

    (3) The parties may, by consent, extend the period specified in sub-

    section (1) for making award for a further period not exceeding six
    months.

    (4) If the award is not made within the period specified in sub-
    section (1) or the extended period specified under sub-section (3),
    the mandate of the arbitrator(s) shall terminate unless the court has,
    either prior to or after the expiry of the period so specified,
    extended the period:

    Provided that while extending the period under this sub-
    section, if the court finds that the proceedings have been delayed
    for the reasons attributable to the arbitral tribunal, then, it may
    order reduction of fees of arbitrator(s) by not exceeding five per
    cent for each month of such delay:

    Provided further that where an application under sub-
    section (5) is pending, the mandate of the arbitrator shall continue
    till the disposal of the said application:

    Provided also that the arbitrator shall be given an opportunity of
    being heard before the fees is reduced.

    (5) The extension of period referred to in sub-section (4) may be on
    the application of any of the parties and may be granted only for
    sufficient cause and on such terms and conditions as may be
    imposed by the Court.

    Signature Not Verified
    Digitally Signed
    By:NEERU O.M.P. (COMM) 73/2024 Page 19 of 48
    Signing Date:04.04.2026
    12:18:42

    (6) While extending the period referred to in sub-section (4), it
    shall be open to the Court to substitute one or all of the arbitrators
    and if one or all of the arbitrators are substituted, the arbitral
    proceedings shall continue from the stage already reached and on
    the basis of the evidence and material already on record, and the
    arbitrator(s) appointed under this section shall be deemed to have
    received the said evidence and material.

    (7) In the event of arbitrator(s) being appointed under this section,
    the arbitral tribunal thus reconstituted shall be deemed to be in
    continuation of the previously appointed arbitral tribunal.
    (8) It shall be open to the Court to impose actual or exemplary
    costs upon any of the parties under this section.
    (9) An application filed under sub-section (5) shall be disposed of
    by the Court as expeditiously as possible and endeavour shall be
    made to dispose of the matter within a period of sixty days from
    the date of service of notice on the opposite party.”

    37. Before proceeding further, this Court deems it apposite also to
    extract the findings recorded by the learned Sole Arbitrator on the
    issue concerning the subsistence of the mandate under Section 29A of
    the A&C Act. The relevant portions of the Arbitral Award read as
    under:

    “47. Respondent’s Application under S. 29A (3) of Arbitration
    Act.

    Before I embark upon the merit of the various claims, it would be
    appropriate first to deal with an application filed by the Respondent
    on 10.04.2023 under S. 29A(3) of Arbitration Act with a prayer for
    a declaration that the mandate of the Tribunal gets terminated
    w.e.f. 24.05.2022.

    Notice of the application was accepted and the non-applicant /
    Claimant preferred to argue the application without filing any
    formal reply.

    According to the learned counsel for the Claimant the issue is
    covered by a Supreme Court judgment for the Covid-19 period.
    Accordingly, the arguments were heard on 11.04.2023 and the
    order is being pronounced along with the Award.
    Having heard the arguments and perusing the record, I find that the
    application merits rejection because the application itself has been
    filed on 10.4.2023 after about one year of the claimed date of
    termination of the mandate of the Arbitrator i.e. 24.05.2022.
    Obviously it is after thought. The earlier counsel did not even raise
    any such plea and had acquiesced in extension of time. The
    Applicant – Respondent kept on participation in the arbitral

    Signature Not Verified
    Digitally Signed
    By:NEERU O.M.P. (COMM) 73/2024 Page 20 of 48
    Signing Date:04.04.2026
    12:18:42
    proceedings after 24.5.2022 and impliedly accepted the mandate of
    the arbitrator.

    48. At the stage of argument, it is not possible to accept such a
    submission because by that time parties may apprehend the results
    one way or the other from the record of the proceedings and resort
    to such type of applications at the stage of arguments which must
    be discouraged. Moreover, Hon’ble Supreme Court in Re-
    Cognizance for Extension of Limitation with Mis. Application No.
    29 of 2023 in Suo Motu Writ Petition (C) No. 3 of 2020 decided on
    10.01.2022 has expressed a categorical view that the whole Covid
    period from 15.03.2020 till 28.02.2022 is to be excluded in
    computing the period prescribed under Section 23 (4) and 29A of
    the Arbitration & Conciliation Act, 1996. Para 5(4) of the
    Judgment of the Hon’ble Supreme Court the aforesaid view finds
    its expression and the same is set out below verbatim for a ready
    reference :

    “It is further clarified that the period from 15.03.2020 till
    28.02.2022 shall also stand excluded in computing the
    periods prescribed under Sections (4) and 29A of the
    Arbitration & Conciliation Act, 1996
    . Section 12A of the
    Commercial Courts Act, 2015 and provisos (b) and (c) of
    Section 138 of the Negotiable Instruments Act, 1881 and
    another laws, which prescribe period(s) of limitation for
    instituting proceedings, outer limits (within which the
    court or tribunal can delay) termination of proceedings.”

    49. When the ratio of the judgment as expressed in the quoted para
    is applied to the facts of the present case, it becomes patent that
    there is ample time for pronouncement of award and the mandate
    of the arbitrator cannot be deemed to have been terminated on the
    claimed date of 24.5.2022. The facts in the present case are that the
    arbitrator entered reference on 8.12.2020 when Covid 19 was at its
    peak. The period up to 28.2.2022 as per the mandate of the Hon’ble
    Supreme Court has to be excluded, inter alia, for the purposes of,
    Section 23 (4) and Section 29A of the Act. The period of 1 year 6
    months would thus commence from 28.2.2022 onwards.
    Accordingly, 18 months period added to 28.2.2022 would bring the
    date for pronouncement of award as 28.8.2023.

    50. Ld. Counsel for the Respondent however, has insisted on
    applying Para 5(3) of the Covid-19 judgment of the Supreme Court
    (Supra). It is argued-that period of 90 days from 01.03.2022 should
    be taken and adopted. The argument suffers from a basic fallacy
    because in para 5(4) there is specific reference to sections 23 (4)
    and section 29A of the Arbitration Act. Moreover, in the instant
    case the limitation does not expire during the period between
    15,03.2020 to 28.2.2022 as is required by Para 5(3) of the
    Judgment. On facts, it is clear that the arbitrator entered reference
    on 8.12.2020 and in the ordinary course, he was supposed to
    pronounce the award on 8.6.2022 (6 months + 1 year) whereas the
    Signature Not Verified
    Digitally Signed
    By:NEERU O.M.P. (COMM) 73/2024 Page 21 of 48
    Signing Date:04.04.2026
    12:18:42
    limitation period as per the view of the Hon’ble Supreme Court is
    required to expire between 15.3.2020 to 28.2.2022 as per para 5(3).
    It is further appropriate to mention that in para 8 of the application
    it is conceded that the period for arbitral proceedings did not expire
    between 15.3.2020 and 28.2.2022.

    As a sequal to the above discussion the application fails and it is
    accordingly dismissed. It is held that the arbitral Tribunal would be
    well within its mandate to pronounce the award on or before
    28.08.2023.”

    (emphasis supplied)

    38. Section 29A of the A&C Act was introduced by way of the
    Arbitration and Conciliation (Amendment) Act, 2015, with the
    avowed legislative objective of ensuring expedition and efficiency in
    arbitral proceedings. The provision, in essence, prescribes that an
    arbitral tribunal shall render the award within twelve (12) months
    from the date of completion of pleadings, subject to extension by
    consent of the parties for a further period not exceeding six months,
    and thereafter only by order of the Court upon sufficient cause being
    shown. The legislative intent underlying this provision is
    unmistakably to discourage protracted arbitral proceedings and to
    instil procedural discipline in arbitration. At the same time, the
    provision cannot be construed in a manner that defeats the very
    purpose of arbitration by encouraging belated jurisdictional objections
    or tactical challenges that are raised only after the arbitral process has
    substantially progressed.

    39. The statutory architecture of Section 29A of the A&C Act must
    therefore be understood not as a rigid mechanism intended to
    invalidate arbitral proceedings upon a mere lapse of time, but as a
    supervisory framework designed to ensure timely completion of
    arbitration while preserving the continuity of the adjudicatory process.
    The scheme of the provision itself makes this position clear. While
    Signature Not Verified
    Digitally Signed
    By:NEERU O.M.P. (COMM) 73/2024 Page 22 of 48
    Signing Date:04.04.2026
    12:18:42
    sub-section (1) prescribes the initial twelve-month period and sub-
    section (3) permits extension by consent of the parties, sub-section (4)
    expressly empowers the Court to extend the mandate of the arbitral
    tribunal either prior to or after the expiry of the stipulated period.

    40. The legislature has thus consciously vested a wide discretionary
    jurisdiction in the Court so that arbitral proceedings, once
    substantially progressed, are not rendered futile merely by efflux of
    time. The law in this regard has been succinctly laid down by the
    Hon‟ble Supreme Court in the case of C. Velusamy v. K Indhera17,
    which reads as under:

    “VII. Timelines under the 1996 Act

    9. Party autonomy, coupled with minimal intervention of judicial
    authorities, has been the guiding principle for the 1996 Act. This is
    perhaps the reason for not provisioning a statutory timeline for
    delivering awards and prescribing consequences of not delivering
    them on time.

    9.1. In the event of failure of an arbitrator to act without undue
    delay, recourse was provided under Section 14 of the Act of 1996
    to dual remedies-by approaching the arbitrator first and then the
    Court8. Section 14(1)(a) states that the mandate of an arbitrator
    would stand terminated if he either becomes de jure or de
    facto unable to perform his functions or, for other reasons, fails to
    act without undue delay. Section 14(2) states that, if a controversy
    remains concerning any of the grounds referred to in Section
    14(1)(a)
    , a party may, unless otherwise agreed with by the parties,
    apply to the Court to decide on the termination of the arbitrator’s
    mandate. On the other hand, Section 34 of the 1996 Act does not
    postulate delay in the delivery of the arbitral award as a ground in
    itself, to set it aside, except, as explained in the Lancor
    Holdings (supra), where the negative effect of the delay in the
    arbitral award is explicit and adversely reflects on the findings of
    the award.

    VIII. The felt need for the prescription of timelines for making
    the award and the recommendation of the law commission

    10. The absence of a statutory time limit under the Act of 1996 had
    resulted in arbitrations remaining pending for several years, even
    without Court intervention, thereby defeating the very object of
    arbitration as a speedy dispute resolution mechanism. Accordingly,
    the Law Commission proposed the introduction of a structured
    17
    2026 SCC OnLine SC 142
    Signature Not Verified
    Digitally Signed
    By:NEERU O.M.P. (COMM) 73/2024 Page 23 of 48
    Signing Date:04.04.2026
    12:18:42
    timeline, with limited extensions by party consent and supervisory
    control by the Court thereafter, not with a view to terminating
    arbitral proceedings, but to compel their timely progress. The
    emphasis was on continuation of the arbitration, even pending
    applications for extension, so that procedural delays do not result
    in wastage of time, costs, or evidence already led. The legislative
    intent, therefore, was to ensure that an arbitral award is ultimately
    passed, with judicial intervention operating as a facilitative and
    corrective mechanism to curb delay, rather than as a means to abort
    the arbitral process. The relevant extract from the 176th Report of
    the Law Commission of India is extracted below:

    *****
    IX. Introduction of Section 29A & its interpretation:

    11. It is in the above-referred background that the Arbitration Act
    was amended with retrospective effect from 23.10.2015 to
    effectively deal with delays in arbitral proceedings by inserting
    Section 29A. The Statement of Objects and Reasons records that
    practical difficulties had arisen, necessitating amendments to make
    arbitration more user-friendly, cost-effective, and expeditious.

    Accordingly, provision was made requiring the arbitral tribunal to
    render the award within twelve months from the date it enters upon
    the reference, with liberty to the parties to extend the period by a
    further six months, any extension thereafter being permissible only
    by order of the Court on sufficient cause being shown. Thereafter,
    the Act of 1996 was further amended w.e.f. 30-8-2019 to provide,
    inter alia, that, where an application seeking extension of time
    under sub-section (5) of Section 29A is pending, the mandate of
    the arbitrator shall continue until such application is finally
    decided.

    11.1. Section 29A of the 1996 Act as amended is extracted below
    for ready reference;

    *****
    X. International perspective on the validity of the arbitral
    award rendered after the stipulated statutory time limit.

    *****
    XI. Conclusions

    13. Section 29A, as explained in recent decisions of this Court
    in Rohan Builders (supra), Lancor Holdings (Supra) and Jagdeep
    Chowgule v. Sheela Chowgule15 can be formulated as under:

    (I) Sub-section (1) of Section 29A mandates that the award shall be
    made within 12 months of the completion of pleadings before the
    Arbitral Tribunal16. While sub-section (2) incentivises expeditious
    making of the Award, proviso to sub-section (4) and sub-section
    (8) authorises the Court to impose penalty for delay in making the
    award.

    (II) Sub-section (3) enables parties, by consent, to extend the
    period of 12 months for making the award by a further period not
    exceeding 6 months.

    Signature Not Verified
    Digitally Signed
    By:NEERU O.M.P. (COMM) 73/2024 Page 24 of 48
    Signing Date:04.04.2026
    12:18:42

    (III) If the award is not made within the stipulated period of 12
    months or the extended period of 6 months, the mandate of the
    arbitrator(s) shall terminate17.

    (IV) This termination is subject to the power of the Court to extend
    the period18.

    (V) The „Court‟ under Section 29A shall be the Civil Court of
    ordinary original jurisdiction in a district and includes the High
    Court in exercise of its original civil jurisdiction under Section
    2(1)(e)
    , and shall not be the High Court or the Supreme Court
    under Section 11(6) of the Act. Section 42 of the Act relating to
    jurisdiction for applications will also not apply to Section 11 of the
    Act19.

    (VI) There is no statutory prescribed time limit for the Court to
    exercise the power under Section 29A(4) for extending the period,
    except for its own discretion. The Court can exercise the power
    before or after the expiry of the period under sub-sections 29A(1)
    or (3)20. Further, there is no prescription of an outer limit for
    extending the time for the conclusion of arbitral proceedings.

    Given this power, the Court will exercise it with circumspection,
    balancing the remedy with the rights of other stakeholders.
    (VII) The power of the Court to extend the time under sub-section
    (4) may be exercised on an application by any of the parties. Once
    such an application for extension of time is pending, the mandate
    of the arbitrator shall continue till the disposal of such application
    under sub-section (9). The Court shall endeavour to dispose of
    such an application within 60 days21.

    (VIII) Delay in the delivery of an arbitral award, by itself, is not
    sufficient to set aside that award. It is only when the effect of the
    undue delay in the delivery of an arbitral award is explicit and
    adversely reflects on the findings therein, such delay and, more so,
    if it remains unexplained, can be construed to result in the award
    being in conflict with the public policy of India.22
    (IX) Under Section 29A(6), while exercising the power of
    extension, it shall be open to the Court to substitute one or all the
    arbitrators. This is a discretionary power that the Court would
    exercise in the facts and circumstances of the case. Upon
    substitution, the reconstituted tribunal shall be deemed to be in
    continuation of the previously appointed tribunal as per Section
    29A(7)
    and shall continue from the stage already reached and on
    the basis of evidence already on record. The newly appointed
    arbitrators shall be deemed to have received the evidence and
    materials.

    (X) Vesting of the power of substitution, under Section 29A(6), is
    on the “Court” and this Court is the “Court” as defined in Section
    2(1)(e)
    . The text, as well as the context for identifying the Court in
    Section 29A(6), as well as in Section 29A(4), is the Court in
    Section 2(1)(e). The expression „Court‟ in other provisions must be
    guided by the meaning given in Section 2(1)(e)23.

    Signature Not Verified
    Digitally Signed
    By:NEERU O.M.P. (COMM) 73/2024 Page 25 of 48
    Signing Date:04.04.2026
    12:18:42

    14. Section 29A of the Act does not, in terms, bar an application
    for extension of the mandate of an arbitrator in the event of the
    delivery of an award. There is no such prescription anywhere in the
    section. In the first place, if an award is made after expiry of the
    mandate, then there is no doubt about the fact that such an award
    is non est. A better expression would be to hold that such an award
    would be unenforceable under Section 36. Such an award need not
    be challenged under Section 34.

    15. Naturally, a unilateral act or the indiscretion of the arbitrator in
    making such an award will have no bearing on the power and
    jurisdiction vested in the Court under Section 29A. We have more
    hesitation in concluding that the Parliament has never intended that
    the act of an arbitrator in delivering an award when the mandate
    had expired would denude the power and jurisdiction vested in the
    Court. This power and jurisdiction stand on its own footing and is
    uninfluenced by the act of the arbitrator in passing an award
    without mandate.

    16. Secondly, the expression, “if an award is not made” in sub-
    section (4) is employed in the context of enabling the Court to
    extend the mandate of the arbitrator. The context in which the
    phrase is used makes it clear that the sub-section is not addressing
    a situation where an arbitral award has been rendered after the
    mandate of the arbitrator has expired, but rather to declare that the
    Court can extend the period before or after the expiry of the
    mandate. This is clearly explained in Rohan Builders (supra).

    17. Rohan Builders (Supra) also clarifies the context in which the
    expression „terminates‟ has been used in the section. It is explained
    that it is transitory and is subject to the exercise of power by the
    Court.

    “14. Accordingly, the termination of the arbitral mandate
    is conditional upon the non-filing of an extension
    application and cannot be treated as termination stricto
    sensu. The word “terminate” in the contextual form does
    not reflect termination as if the proceedings have come to
    a legal and final end, and cannot continue even on filing
    of an application for extension of time. Therefore,
    termination under Section 29A(4) is not set in stone or
    absolutistic in character.

    20. Lastly, Section 29A(6) does not support the narrow
    interpretation of the expression “terminate”. It states that
    the court – while deciding an extension application under
    Section 29A(4) – may substitute one or all the arbitrators.
    Section 29A(7) states that if a new arbitrator(s) is
    appointed, the reconstituted Arbitral Tribunal shall be
    deemed to be in continuation of the previously appointed
    Arbitral Tribunal. This obliterates the need to file a fresh
    application under Section 11 of the A & C Act for the
    appointment of an arbitrator. In the event of substitution
    Signature Not Verified
    Digitally Signed
    By:NEERU O.M.P. (COMM) 73/2024 Page 26 of 48
    Signing Date:04.04.2026
    12:18:42
    of arbitrator(s), the arbitral proceedings will commence
    from the stage already reached. Evidence or material
    already on record is deemed to be received by the newly
    constituted tribunal. The aforesaid deeming provisions
    underscore the legislative intent to effectuate efficiency
    and expediency in the arbitral process. This intent is also
    demonstrated in Sections 29A(8) and 29A(9). The court in
    terms of Section 29A(8) has the power to impose actual or
    exemplary costs upon the parties. Lastly, Section 29A(9)
    stipulates that an application for extension under sub-
    section (5) must be disposed of expeditiously, with the
    endeavour of doing so within sixty days from the date of
    filing.”

    18. Intention of the Parliament to secure the arbitral proceedings
    and to ensure that they are taken to their logical conclusion of a
    binding award is evident from provisions such as, enabling Courts
    to exercise the power of extension before or after the expiry of the
    18 month period [Section 29A(4)], declaring continuation of the
    proceedings till the application for extension is pending [proviso to
    29A(4)], declaring that upon extension, the existing proceedings
    would continue uninterruptedly [Section 29A(6) & (7)]. These
    provisions make it evident that the intention of the Parliament is to
    safeguard the conduct and conclusion of arbitral proceedings.

    19. Though the fact situation that has arisen in our case was not
    available in Rohan Builders (Supra) in the sense that the arbitrator
    had not passed an award after expiry of the mandate, the following
    observation in Rohan Builders is relevant for our consideration;

    “21. …The power to extend time period for making of the
    award vests with the court, and not with the Arbitral
    Tribunal. Therefore, the Arbitral Tribunal may not
    pronounce the award till an application under Section
    29A(5) of the A & C Act is sub-judice before the court. In
    a given case, where an award is pronounced during the
    pendency of an application for extension of period of the
    Arbitral Tribunal, the court must still decide the
    application under sub-section (5), and may even, where an
    award has been pronounced, invoke, when required and
    justified, sub-sections (6) to (8), or the first and third
    proviso to Section 29A(4) of the A & C Act.”

    (emphasis supplied)

    20. Vesting of power and jurisdiction in the Court, in our opinion,
    is a complete answer to any apprehension that extension of time,
    even in cases where an „award‟ is passed, could introduce a culture
    of indiscipline, as arbitrator(s) and/or counsels could become
    indifferent to the mandatory timelines. This apprehension is not
    true. There is no automatic extension of time. The Court will and
    must exercise its discretion only after evaluating the facts and
    circumstances after close scrutiny. Section 29A, in terms, enables
    Signature Not Verified
    Digitally Signed
    By:NEERU O.M.P. (COMM) 73/2024 Page 27 of 48
    Signing Date:04.04.2026
    12:18:42
    the court to adopt distinct measures to ensure dynamic and efficient
    conduct of arbitral proceedings with integrity and expedition. The
    following empowerments are in the nature of instruments in the
    toolkit of Section 29A, enabling the courts to deploy them as and
    when the factual matrix demands:

    i. Court has the power to extend the time before or after
    the expiry of the statutorily stipulated period. [Section
    29A(4)
    ]
    ii. Court is empowered to take measures to reduce the fee
    of the arbitrators if the Court is of the opinion that the
    proceedings are delayed for the reasons attributable to the
    Arbitrators. [Proviso to Section 29A(4)]
    iii. Court can grant an extension of the time period upon a
    finding that there is sufficient cause for such extension.
    [Section 29A(5)]
    iv. Court, while extending the mandate even when there is
    sufficient cause, is empowered to impose such terms and
    conditions as it thinks fit for efficiency and integrity of the
    arbitral proceedings. [Section 29A(5)]
    v. Courts are specifically empowered to substitute any one
    or all the arbitrators, if in the opinion of the Court the facts
    demand. This is a discretion that the Court would exercise
    with caution and circumspection24. [Section 29A(6)]
    vi. The Court is empowered not only to grant costs but
    also to impose exemplary and actual costs upon any of the
    parties, if the situation so demands. [Section 29A(8)]

    21. In view of the above analysis, we are of the opinion that
    provisions of the Act, particularly Section 29A, must not be
    interpreted to infer a threshold bar for an application under Section
    29A(5)
    for extension of the mandate of the arbitrator even when an
    award is passed, though after the expiry of the mandate.

    22. While interpreting an enactment providing legal remedies for
    the resolution of disputes, a constitutional court has the obligation
    to ensure that the provision is: (a) accessible, (b) affordable, (c)
    expeditious and (d) cohesive. Accessibility requires the remedy to
    be easily available25. Affordability is an aspect that is related to
    the cost of availing the remedy, it must be at a reasonable price.
    Expeditious nature of a remedy is concerned with the quick
    disposal and abhors unreasonable delays. Yet another facet of
    effective remedy is in its cohesiveness.

    23. In conclusion, we hold that an application under Section
    29A(5)
    for extension of the mandate of the arbitrator is
    maintainable even after the expiry of the time under Sections
    29A(1)
    and (3) and even after rendering of an award during that
    time. Such an award is ineffective and unenforceable. But the
    power of the court to consider extension is not impaired by such an
    indiscretion of the arbitrator. While considering the application, the
    Court will examine if there is sufficient cause for extending the
    Signature Not Verified
    Digitally Signed
    By:NEERU O.M.P. (COMM) 73/2024 Page 28 of 48
    Signing Date:04.04.2026
    12:18:42
    mandate, and in the process, it may impose such terms and
    conditions as the situation demands. The Court will also take into
    account other factors such as reduction of the fee of the arbitrator
    under proviso to Section 29A(4) and also impose costs on parties if
    the fact situation so demands. Substitution is an option for the
    Court as the provision itself says, “it shall be open for the Court to
    substitute”, and it will be exercised carefully. If the mandate is
    extended, the arbitral tribunal will pick up the thread from where it
    was left, and seamlessly continue the proceeding from the stage at
    which the mandate had expired, and conclude within the time
    granted.

    (emphasis supplied)

    41. The nature of such “termination” of mandate under Section 29A
    of the A&C Act has been authoritatively clarified in various judicial
    precedents. In Rohan Builders (India) Pvt Ltd v. Berger Paints India
    Limited18
    , the Hon‟ble Supreme Court observed that the termination
    of mandate under Section 29A is not absolutistic in character but is
    conditional and transitory, being subject to the power of the Court to
    extend the mandate.
    The Hon‟ble Supreme Court in Rohan Builders
    (supra) has held that an Application for extension of mandate under
    Section 29A(4) read with 29A(5) is maintainable even after the expiry
    of the 12-month or 6-month extended period.

    42. The legislative intent underlying the provision is thus to ensure
    that arbitral proceedings culminate in a binding adjudication rather
    than being aborted on technical grounds. The same principle has been
    reiterated by the Hon‟ble Supreme Court in Lancor Holdings Ltd v.
    Prem Kumar Menon
    19 and more recently in Jagdeep Chowgule v.
    Sheela Chowgule20.

    43. Tested against this statutory and doctrinal framework, the
    challenge mounted by the Petitioner on the ground of expiry of the

    18
    2024 SCC OnLine SC 2494
    19
    2025 SCC OnLine SC 2319
    20
    2026 INSC 92
    Signature Not Verified
    Digitally Signed
    By:NEERU O.M.P. (COMM) 73/2024 Page 29 of 48
    Signing Date:04.04.2026
    12:18:42
    mandate of the learned Sole Arbitrator cannot be sustained. The
    Petitioner has contended that the pleadings in the arbitral proceedings
    stood completed on 24.05.2021 and, therefore, the learned Arbitrator
    was required to render the award within twelve months therefrom.
    According to the Petitioner, the mandate of the learned Arbitrator
    expired on 24.05.2022 and, in the absence of any extension obtained
    from the Court, the learned Arbitrator became functus officio
    thereafter. On this basis, it is urged that the Arbitral Award rendered
    on 27.08.2023 is without jurisdiction.

    44. The aforesaid contention, however, cannot be accepted for more
    than one reason. At the outset, the computation of time under Section
    29A
    cannot be undertaken in isolation from the extraordinary
    directions issued by the Hon‟ble Supreme Court in wake of the
    COVID-19 pandemic in Suo Moto Writ (Civil) No. 3 of 2020. By
    virtue of the Order(s) passed therein, the period between 15.03.2020
    and 28.02.2022 stood excluded for the purpose of computing
    limitation across various statutory regimes, including the timelines
    prescribed under Sections 23(4) and 29A of the A&C Act. The
    applicability of this exclusion to arbitral timelines has also been
    authoritatively reiterated by the Hon‟ble Supreme Court in Arif Azim
    Co. Ltd. v. Aptech Ltd.
    21 . The relevant portion of the Order dated
    10.01.2022 passed in Suo Moto Writ (Civil) No. 3 of 2020 is
    reproduced herein below:

    “5. …….

    IV. It is further clarified that the period from 15.03.2020 till
    28.02.2022 shall also stand excluded in computing the periods
    prescribed under Sections 23 (4) and 29A of the Arbitration and
    Conciliation Act, 1996, Section 12A of the Commercial Courts
    Act, 2015 and provisos (b) and (c) of Section 138 of the Negotiable

    21
    2024 SCC OnLine SC 215
    Signature Not Verified
    Digitally Signed
    By:NEERU O.M.P. (COMM) 73/2024 Page 30 of 48
    Signing Date:04.04.2026
    12:18:42
    Instruments Act, 1881 and any other laws, which prescribe
    period(s) of limitation for instituting proceedings, outer limits
    (within which the court or tribunal can condone delay) and
    termination of proceedings.”

    45. When the aforesaid exclusion is applied to the facts of the
    present case, the timeline for completion of the arbitral proceedings
    necessarily shifts. The arbitral proceedings commenced on
    08.12.2020, a date which itself falls squarely within the period
    excluded by the Hon‟ble Supreme Court. Consequently, the statutory
    timeline for rendering the award must necessarily be computed by
    excluding the pandemic period. Once the said exclusion is applied, the
    award rendered on 27.08.2023 cannot be said to have been delivered
    beyond the permissible statutory timeframe.

    46. This interpretation also finds support from decisions of this
    Court which have consistently applied the exclusion directed in Suo
    Motu Writ Petition (C) No. 3 of 2020 to arbitration-related timelines.
    In Chroma-Ator Energy Systems Pvt Ltd (supra), this Court held that
    the limitation period would recommence after excluding the pandemic
    period in accordance with the Hon‟ble Supreme Court‟s directions.
    Similarly, in Drooshba Fabricators (supra), it was reiterated that
    delays occurring during the excluded period would stand condoned in
    view of the extraordinary directions issued by the Hon‟ble Supreme
    Court.

    47. Even otherwise, the conduct of the Petitioner during the arbitral
    proceedings renders the present challenge wholly untenable. The
    Petitioner asserts that the mandate of the learned Arbitrator expired on
    24.05.2022. Yet, the Application invoking Section 29A of the A&C
    Act was filed only on 10.04.2023, nearly eleven months thereafter.

    Signature Not Verified
    Digitally Signed
    By:NEERU O.M.P. (COMM) 73/2024 Page 31 of 48
    Signing Date:04.04.2026
    12:18:42

    48. The chronology of the proceedings, which emerges from the
    record, may be summarised as under:

                                  Event                    Date             Observation
                       Commencement of arbitral        08.12.2020    Arbitrator entered upon
                       proceedings                                   reference
                       Completion of pleadings         24.05.2021    Petitioner‟s computation
                       (as alleged by Petitioner)                    of the timeline
                       Alleged expiry of mandate       24.05.2022    No objection raised
                       (as per Petitioner)                           contemporaneously
                       Application under Section       10.04.2023    Filed nearly one year
                       29A of the A&C Act filed                      after the alleged expiry
                       by Petitioner
                       (Objection to the mandate
                       under Section 29A)
                       Arguments       on    merits    April-May     Petitioner         actively
                       continued      before    the    2023          participated
                       Tribunal
                       Award pronounced                27.08.2023    Impugned Award
                       Application under Section       Post-award    Seeking correction of
                       33 of the A&C Act filed by                    the interest component
                       Petitioner
    
    

    49. The above chronology clearly demonstrates that, despite having
    raised an objection under Section 29A of the A&C Act, the Petitioner
    continued to actively participate in the arbitral proceedings without
    pursuing any further remedial steps in that regard. Notably, the
    Petitioner advanced substantive arguments on merits before the
    learned Arbitrator on 12.04.2023 and 21.04.2023, and thereafter also
    participated in the hearing held on 08.05.2023 concerning the
    Respondent‟s rejoinder submissions. Such conduct clearly
    demonstrates that the Petitioner continued to recognise the authority

    Signature Not Verified
    Digitally Signed
    By:NEERU O.M.P. (COMM) 73/2024 Page 32 of 48
    Signing Date:04.04.2026
    12:18:42
    of the learned Arbitrator and elected to participate in the adjudicatory
    process without reservation.

    50. The position becomes even more significant when it is noticed
    that, subsequent to the pronouncement of the Arbitral Award on
    27.08.2023, the Petitioner itself invoked the jurisdiction of the tribunal
    under Section 33 of the A&C Act, seeking correction of the interest
    awarded. The filing of such an application necessarily proceeds on the
    premise that the Arbitral Award is valid and that the tribunal
    possessed the authority to render it. Having availed of the statutory
    remedy available under Section 33 of the A&C Act, the Petitioner
    cannot now be permitted to approbate and reprobate by
    simultaneously contending that the tribunal lacked mandate to
    pronounce the Arbitral Award.

    51. In this regard, reference may also be made to the judgment of
    the Himachal Pradesh High Court in Balak Ram v. National
    Highways Authority of India
    22 , wherein it was observed that
    continued participation in arbitral proceedings without raising a timely
    objection may, in appropriate circumstances, amount to an extension
    of the mandate by conduct of the parties. The relevant portions of the
    said judgment
    read as follows:

    “20. As per Section 29A(1) of the Arbitration and Conciliation Act,
    the award has to be made within a period of 12 months from the
    date the Arbitral Tribunal enters upon the reference. Section
    29A(3)
    provides for extension of the period specified in sub section
    (1) for a further period not exceeding six months by the consent of
    the parties.

    21. An arbitral award, therefore, can be made within a period of 12
    months from the date the Arbitrator enters upon the reference. The
    parties can extend this period by consent for a further period not
    exceeding six months. An award made beyond 12 months under

    22
    2023 SCC OnLine HP 944
    Signature Not Verified
    Digitally Signed
    By:NEERU O.M.P. (COMM) 73/2024 Page 33 of 48
    Signing Date:04.04.2026
    12:18:42
    Section 29A(1) or 18 months under Section 29A(3) shall not be
    valid.

    22. The court can extend the mandate of the Arbitral Tribunal as
    per Section 29A(4). In the instant case, the Arbitrator entered upon
    the reference on 08.07.2016. Permissible period of 12 months
    within which the award could have been validly pronounced under
    Section 29A(1) lapsed on 07.07.2017. However, both the
    contesting parties continued with the proceedings. None of the
    parties objected to the arbitration proceedings conducted by the
    Arbitrator beyond 07.07.2017. From the conduct of the parties, a
    tacit consent on their part for extending the period of arbitration
    can be inferred. Under Section 29A(3), parties by consent can
    extend the period of arbitration not exceeding six months. In the
    instant case, the Arbitral Tribunal passed the award within 2
    months after the expiry of 12 months. The fact that respondent-

    NHAI had consented to the continuation of proceedings beyond 12
    months is apparent from the fact that even while agitating against
    the award passed by the Arbitrator, it had not taken any such
    ground before the learned District Judge that the award passed by
    the Arbitrator was bad in the eyes of law on the count that mandate
    of the Arbitral Tribunal had lapsed on 07.07.2017. It was a case of
    implied consent on part of respondent-NHAI. In this regard, it
    would be appropriate to refer to (2002) 3 SCC 175 : AIR 2002 SC
    1157 (Inder Sain Mittal v. Housing Board, Haryana). Relevant
    para from the judgment is as follows:–

    “13. In the case on hand, it cannot be said that
    continuance of the proceedings and rendering of awards
    therein by the Arbitrator after his transfer was in
    disregard of any provision of law much less mandatory
    one but, at the highest, in breach of agreement. Therefore,
    by their conduct by participating in the arbitration
    proceedings without any protest the parties would be
    deemed to have waived their right to challenge validity of
    the proceedings and the awards, consequently, the
    objections taken to this effect did not merit any
    consideration and the High Court was not justified in
    allowing the same and setting aside the award.”

    *****

    24. In view of above discussion on facts & law, it has to be held
    that consent of the parties envisaged under Section 29A(3) of the
    2015 Arbitration & Conciliation Act for extending the arbitral
    period need not necessarily be either express or in writing. There
    can be a deemed consent, an implied consent of the parties, which
    can be gathered from their acts and conduct. Their acquiescence in
    proceeding with the arbitration case beyond twelve months without
    raising any objection to the continuation of proceeding does
    amount to consent. On the basis of such consent, the arbitral award
    if passed within a further period of six months would be a valid
    Signature Not Verified
    Digitally Signed
    By:NEERU O.M.P. (COMM) 73/2024 Page 34 of 48
    Signing Date:04.04.2026
    12:18:42
    award. In the given facts, consent of the parties to continue the
    arbitral proceedings beyond the period of one year (12 months)
    from the date the Arbitrator entered upon the reference, is writ
    large. The award was passed by the Arbitrator within further period
    of two months. The award was thus saved by Section 29A(3) of the
    Act as it was passed within the period permitted under Section 29A
    (3)
    of the Act. The conclusion drawn by learned District Judge
    about the award being illegal having been passed beyond the
    mandated period, therefore, being illegal, cannot be justified.
    Under Section 29A(3) of the Arbitration and Conciliation Act,
    there is no requirement that consent of the parties has to be
    expressed and that too, in writing.”

    (emphasis added)

    52. Arbitration rests fundamentally upon principles of party
    autonomy, procedural fairness and good faith participation in the
    adjudicatory process. A party cannot be permitted to participate in
    arbitral proceedings, invite adjudication on merits, and thereafter
    challenge the very jurisdiction of the tribunal only after the outcome
    proves unfavourable. To permit such conduct would undermine the
    finality, efficiency and credibility that the arbitral process seeks to
    achieve.

    53. In this context, it also merits emphasis that once the exclusion
    directed by the Hon‟ble Supreme Court in the Suo Motu proceedings
    concerning extension of limitation during the COVID-19 pandemic is
    applied, the statutory timeline under Section 29A of the A&C Act
    must necessarily be reckoned only from 01.03.2022, i.e., upon the
    expiry of the period directed to be excluded. In terms of Section
    29A(1)
    read with Section 29A(3) of the A&C Act, the Arbitral
    Tribunal is permitted to render the award within twelve months, with a
    further six months‟ extension by consent of the parties, thereby
    permitting a cumulative period of eighteen months for completion of
    the arbitral proceedings. When the statutory timeline is computed
    from 01.03.2022, the outer limit of the permissible period would
    Signature Not Verified
    Digitally Signed
    By:NEERU O.M.P. (COMM) 73/2024 Page 35 of 48
    Signing Date:04.04.2026
    12:18:42
    extend to 31.08.2023. The Impugned Arbitral Award, having been
    pronounced on 27.08.2023, unmistakably falls within the said period
    of one and a half years from the expiry of the pandemic exclusion
    period. Consequently, the contention advanced by the Petitioner that
    the mandate of the learned Arbitrator had lapsed prior to the
    pronouncement of the Arbitral Award is devoid of merit and cannot be
    sustained.

    54. It must also be borne in mind that the jurisdiction of this Court
    under Section 34 of the A&C Act is supervisory and not appellate in
    nature. The Hon‟ble Supreme Court in catena of judgments has
    reiterated that a court exercising jurisdiction under Section 34 of the
    A&C Act cannot re-appreciate evidence or substitute its own view
    merely because another interpretation may appear possible. So long as
    the arbitral tribunal has adopted a plausible view based on the material
    placed before it, judicial interference would be wholly unwarranted.

    55. In the present case, the learned Arbitrator has considered the
    objection raised by the Petitioner under Section 29A of the A&C Act
    and has rejected the same upon examining the statutory framework
    and the chronology of events. The reasoning adopted by the learned
    Arbitrator is both plausible and legally sustainable. No prejudice
    whatsoever has been demonstrated by the Petitioner arising from the
    alleged delay in rendering the Arbitral Award, nor has it been shown
    that such delay has in any manner affected the reasoning or findings
    recorded in the award.

    56. Viewed in the aforesaid perspective, this Court is unable to
    accept the contention that the mandate of the learned Sole Arbitrator
    had expired prior to the pronouncement of the Impugned Arbitral
    Award. The interpretation urged by the Petitioner would defeat the
    Signature Not Verified
    Digitally Signed
    By:NEERU O.M.P. (COMM) 73/2024 Page 36 of 48
    Signing Date:04.04.2026
    12:18:42
    legislative purpose underlying Section 29A of the A&C Act and
    would encourage belated technical challenges aimed at frustrating the
    arbitral process.

    57. Consequently, the challenge mounted by the Petitioner on the
    ground of alleged expiry of the mandate of the learned Arbitrator is
    devoid of merit and stands rejected.

    ii. Validity of Interest Awarded by the Tribunal

    58. The second limb of challenge raised by the Petitioner pertains to
    the grant of interest by the learned Arbitral Tribunal on the sums
    awarded in favour of the Respondent.

    59. Before adverting to the merits of the rival submissions, it would
    be appropriate to extract the findings recorded by the learned Sole
    Arbitrator on the question of interest. The relevant observations
    forming part of the Impugned Arbitral Award, wherein the learned
    Arbitrator determined the entitlement of the Respondent to interest
    and the rate thereof, are reproduced hereinbelow for ready reference:

    “51. Issue No. 1

    Whether the Claimant is entitled to interest on the delayed
    payment of the final bill @ 12% per annum.

    *****

    56. It is true that the final bill was required to be submitted within
    3 months of the date of completion of work. The work was
    completed on 31.3.2017 and the final bill was actually submitted
    on 28.6.2017. It is also clear from Condition No. 56 of GCC that
    from the date of submission of the final bill the undisputed part
    was required to be paid within 6 months i.e. on or before
    28.12.2017. Therefore, the delay is patent from the fact that
    approval to D.Os was granted between 16.11.2017 and 04.10.2019
    as depicted in the above table.

    57. The claim of the Claimant is sought to be defeated on the
    ground that the accompanying documents were not submitted and
    there was no notice in terms of Section 3(b) of the Interest Act,
    1978. Respondent submitted that Claimant caused delay in the
    processing of various D.Os. In that regard reliance has been placed
    Signature Not Verified
    Digitally Signed
    By:NEERU O.M.P. (COMM) 73/2024 Page 37 of 48
    Signing Date:04.04.2026
    12:18:42
    on the correspondence between the parties. Annexure R-29, 30, 33
    to 44 and 44 to 46. A casual glance at Annexure 29 dated 20th
    July, 2017 would reveal that Respondent sought modification of
    bill by reducing the amount of disputed D.O. in respect of RCC
    Solar Water Heater Platform which is a separate claim in these
    proceedings. Likewise a perusal of Annexure R-31 dated 19th
    March, 2018 would show that either the measurements were
    awaited or approved D.Os. was not received by the Respondent.

    Vide Annexure R-35 dated 10th January 2019 some defects of
    leakage / seepage were pointed out. Similar position obtain in other
    documents Clause 56 of GCC (Supra) in categorical terms state
    that undisputed amount of final bill must be paid within six months
    from the date of receipt. by the Project Manager. The period for
    removal of defects is separately provided which was to expire on
    31.03.2019 (sub clause 40 GCC) and the amount of the Claimant is
    retained to ensure that Defendants are removed. The Respondent
    has thus remained unsuccessful to show that there was any serious
    deficiency in submitting the final bill in Form F as per the
    provisions of Condition No. 55 of GCC. I am in agreement with
    the Ld. Counsel for the Claimant that on these excuses payment of
    undisputed amount could not be withheld nor the delay in
    approving the D.Os. was justified. Likewise measurement did not
    need to even wait for association of the Claimant or its
    representative as last para of clause 52 of GCC provides that
    Respondent was fully within its right to have measurement done in
    his absence. The cost could be recovered from the Claimant. The
    preponderance of evidence indicates to the casual dealing with the
    approval concerning D.Os. and measurement which caused
    abnormal delay. Therefore, I find that extraordinary delay in
    approving D.Os. and measurement has been caused by Respondent
    which resulted in delay of payment of final bill. Regarding other
    argument it is not mandatory that a notice under Section 3(b) of the
    Interest Act is a sine qua non for awarding the amount of interest.
    There is ample power with the Arbitrator to award interest in the
    form of compensation given by Section 31 of the Arbitration Act
    for which no notice is required. Once a person is legitimately
    entitled to payment of final bill, any delay in making payment
    would make him entitled for compensation for deprevation of the
    use of money due to him. In the detailed cross-examination, the
    witness of the Claimant has stated that the claim of 12% interest
    has been fixed in respect of Claim No. 1 on the basis of market rate
    of interest. The interest has been claimed as compensation because
    of loss of use of money in other business on time, although nothing
    has been placed on record to prove any such loss. In that regard
    Shri Parveen Chauhan Ld. Counsel for the – Claimant has rightly
    placed reliance on para 47 of a judgment of the Supreme Court by
    5-Judge Bench in the case of Secretary Irrigation Deptt. V. G.C.
    Roy & others. It has been held that if a person is deprived of use of
    Signature Not Verified
    Digitally Signed
    By:NEERU O.M.P. (COMM) 73/2024 Page 38 of 48
    Signing Date:04.04.2026
    12:18:42
    money to which he is legitimately entitled then he has a right to be
    compensated for deprivation, call it by any name like interest,
    damages or compensation. The observations have also been quoted
    verbatim in the other part of this Award (infra). The witness denied
    the suggestion that Claim No. 1 was unnecessary excessive.
    However, on checking Commercial Rate of Interest of SBI I find
    that there is substance in the argument of Shri Parveen Jain Ld.
    Counsel for the Respondent. The rate of interest claimed by
    Claimant at 12% needs to be reduced. However, the sum total has
    not been disputed Accordingly, I am inclined to award interest
    from 01.01.2018 to 30.11.2019 i.e. for a period of 23 months on
    the sum of Rs.2,04,36889.00 @ 10% P.A. which works out to be
    Rs.39,17,071.30. Issue No. 1 related to claim No. 1 is accordingly
    decided.

    58. It is true that during cross-examination CW-1 Shri Sanjay
    Kumar Katare admitted the contents of document Ex.CW-1/R-48
    (R-5) and similar other documents making claim for extra work.
    The claim made through D.Os. was rejected but it cannot be
    termed as a sole reason for delay. Moreover rejection of all such
    D.Os. is also subject matter of claim in these proceedings.

    59. Another argument based on clause 52 of the GCC (at P. 576) is
    that the Contractor is to assist in measurement of the work
    executed. He is also expected to assist PM/DEPMC for preparation
    of D.Os. As far as measurement etc. are concerned the Respondent
    is free to move forward in case the Claimant fails to turn up as per
    clause. Regarding D.Os. the Claimant tried to project that it was
    extra work which was not included in the lump sum part yet its
    claim was rejected which is also subject matter of one of the claim.
    Therefore, I do not find any merit in submissions advanced by the
    Ld. Counsel for the Respondent and the same is rejected.”

    60. Upon perusal of the extracted findings, this Court finds that the
    learned Arbitral Tribunal has arrived at its conclusion on the question
    of interest only after undertaking a detailed scrutiny of the contractual
    framework and the evidentiary material placed on record. The tribunal
    examined the relevant clauses of the contract governing submission
    and payment of the final bill and thereafter analysed the documentary
    exhibits and oral testimony adduced by the parties. The Arbitral
    Award reflects that the Ld. Arbitral Ttribunal considered the sequence
    of events, the approvals of deviation orders, and the explanations
    offered by the parties before determining that the delay in payment
    Signature Not Verified
    Digitally Signed
    By:NEERU O.M.P. (COMM) 73/2024 Page 39 of 48
    Signing Date:04.04.2026
    12:18:42
    was not attributable to the contractor. Such an appreciation of
    contractual stipulations and evidence lies squarely within the
    adjudicatory domain of the Arbitral Tribunal.

    61. The learned Tribunal has also correctly addressed the legal
    basis for awarding interest by invoking the statutory power conferred
    under Section 31(7) of the A&C Act, which empowers an arbitral
    tribunal to grant interest as compensation for the deprivation of
    monies lawfully due. The reasoning recorded in the Arbitral Award
    demonstrates that the learned Arbitrator did not grant interest
    mechanically but evaluated the commercial context and moderated the
    rate claimed by the contractor, thereby exercising a measured and
    judicious discretion.

    62. A perusal of the Arbitral Award reveals that the learned
    Arbitrator has granted interest at the rate of 12% per annum on the
    sums found due and payable to the Respondent, commencing from
    18.03.2020 until the date of payment. The learned Arbitrator has
    recorded detailed reasons for awarding such interest, taking into
    account the fact that the Respondent had been deprived of the use of
    monies legitimately due under the contract and that the delay in
    payment was attributable to the Petitioner.

    63. The power of an arbitral tribunal to award interest is firmly
    embedded in the statutory framework of the A&C Act. Section 31(7)
    expressly recognises the authority of the tribunal to grant interest for
    the pre-award as well as post-award period unless the parties have
    agreed otherwise. The provision embodies the well-settled principle
    that a party who has been unjustifiably deprived of the use of money
    to which it is legitimately entitled must be compensated by way of

    Signature Not Verified
    Digitally Signed
    By:NEERU O.M.P. (COMM) 73/2024 Page 40 of 48
    Signing Date:04.04.2026
    12:18:42
    interest. Interest, in such circumstances, is not punitive in nature but
    compensatory, representing the time value of money.

    64. The jurisprudence governing the grant of interest in arbitral
    proceedings consistently emphasises that the determination of the
    appropriate rate of interest lies primarily within the domain of the
    arbitral tribunal. Courts exercising jurisdiction under Section 34 of the
    A&C Act do not ordinarily interfere with such determination unless
    the rate awarded is demonstrably arbitrary, unconscionable or in
    conflict with the fundamental policy of Indian law.

    65. At this stage, this Court considers it appropriate to advert to the
    judgment of a Co-ordinate Bench of this Court in M.A. Zahid v.
    Jindal SAW Ltd.23
    wherein the grant of interest at the rate of 12% by
    an arbitral tribunal was examined in the context of the statutory
    framework governing arbitral interest both prior to and subsequent to
    the 2015 amendment to the A&C Act. The Court, upon undertaking
    such analysis, upheld the grant of interest as falling squarely within
    the powers conferred upon an arbitral tribunal under Section 31(7) of
    the A&C Act. The relevant observations from the said judgment are
    reproduced herein below:

    “16. Under the 1996 Act, power of the Arbitrator to grant interest
    is governed by Section 31(7). This provision is in two parts. Under
    Clause (a), in the absence of an agreement between the parties to
    the contrary, an Arbitrator can award interest for the period
    between the date of cause of action to the date of the award, either
    for the whole or part of the said period. Clause (b) provides that
    unless the award otherwise directs, the sum directed to be paid by
    the Arbitrator shall carry interest @ 2% higher than current rate of
    interest from the date of the award to the date of payment. This
    amendment was brought about from 23.10.2015 by virtue of
    Amendment Act No. 3 of 2016. Be it noted that this Court is not
    delving into the pre-reference and pendente lite interest as the

    23
    2025 SCC OnLine Del 5227
    Signature Not Verified
    Digitally Signed
    By:NEERU O.M.P. (COMM) 73/2024 Page 41 of 48
    Signing Date:04.04.2026
    12:18:42
    contest in the present case is only with respect to post-award
    interest.

    17. Read simply and as observed by the Supreme Court in Morgan
    Securities and Credits Private Limited v. Videocon Industries
    Limited
    , 2022 SCC OnLine SC 1127, both clauses (a) and (b) of
    Section 31(7) are qualified. While clause (a) is qualified by the
    arbitration agreement, clause (b) is qualified by the arbitration
    award and placement of the phrases is crucial to their
    interpretation. As can be seen from the amended Section, the
    phrase „unless otherwise agreed by the parties’, occurs at the
    beginning of clause (a) qualifying the entire provision while phrase
    „unless the award otherwise directs‟, occurs after the words „a sum
    directed to be paid by an arbitral award shall‟ and before the words
    „carry interest at the rate of two per cent‟, and therefore, the phrase
    qualifies the rate of post-award interest. It is settled that the
    Arbitrator has a wide discretion to grant: (a) pre-reference;

    (b) pendente lite; and (c) post-award interest. In North Delhi
    Municipal Corporation v. S.A. Builders Ltd.
    , 2024 SCC OnLine
    SC 3768, the Supreme Court held that grant of post award interest
    serves a salutary purpose and primarily acts as a disincentive to the
    award-debtor not to delay payment of arbitral amount to the award-

    holder.

    18. In Morgan Securities (supra), albeit the Supreme Court was
    dealing with unamended Section 31(7)(b), it was held that Section
    31(7)(a)
    confers a wide discretion on the Arbitrator to grant pre-
    award interest and determine the rate of interest, the sum on which
    it is to be paid and the period and when a discretion has been
    conferred in regard to grant of pre-award interest, it would be
    against the grain of statutory interpretation to presuppose that
    legislative intent was to reduce the discretionary power of the
    Arbitrator for grant of post-award interest under clause (b). It was
    observed that clause (b) only contemplates a situation where the
    arbitral award is silent on the post-award interest, in which event
    the award-holder is entitled to the post-award interest @ 18%
    stipulated in Section 31(7)(b), the unamended provision. It was
    held that the Arbitrator has the discretion to grant post-award
    interest and this discretion is not fettered by clause (b) albeit it is
    open to the Arbitrator to decline interest in its discretion. It was
    highlighted that purpose of granting post-award interest is to
    ensure that the award-debtor does not delay the payment of the
    awarded amount. With proliferation of arbitration, issues involving
    both high and low financial implications are referred to arbitration
    and Arbitrator takes note of various factors such as financial
    standing of the award-debtor and circumstances of the parties in
    dispute before awarding interest. No provision under the 1996 Act
    restricts the exercise of discretion to grant post-award interest by
    the Arbitrator though Arbitrator must exercise the discretion in
    good faith taking into account relevant considerations and must act
    Signature Not Verified
    Digitally Signed
    By:NEERU O.M.P. (COMM) 73/2024 Page 42 of 48
    Signing Date:04.04.2026
    12:18:42
    reasonably and rationally. It was concluded by the Supreme Court
    that according to Section 31(7)(b) only where the Arbitrator does
    not grant post-award interest, provisions of second part of sub-
    clause (b) will come into play.

    19. In the present case, the learned Arbitrator has exercised his
    discretion to grant post-award interest @ 12% per annum for 90
    days from 23.05.2016 and 16% per annum from expiry of 90 days
    till actual payment. The post-award interest is based on a sound
    reasoning which precedes the grant. Arbitrator has observed that in
    the various documents executed on 22.07.2013 between the parties,
    there was acknowledgement of liability by the Petitioner and there
    was no mention of interest. Parties entered into settlement in the
    spirit of goodwill, bonhomie and to maintain long term business
    relations. Respondent was satisfied with the Petitioner paying the
    principal amount on lifting of the attachment by Income Tax
    Authorities and/or selling properties. There was no intent of
    charging interest in the settlement. On this ground, Arbitrator
    declined interest from 01.06.2011, as sought by the Respondent.
    Thereafter, the Arbitrator refers to the legal notice dated
    23.05.2016 from which date Respondent started demanding the
    admitted payment expressing its intention to the Petitioner to
    charge interest. Admittedly, Petitioner made no effort to pay the
    admitted amount and constrained by circumstances, Respondent
    invoked arbitration. Arbitrator notes the provisions of the 1996 Act
    and judgments relating to grant of interest cited by the Respondent
    as also the fact that the transaction between the parties was
    undoubtedly a commercial one and the Petitioner though not
    denying its liability to pay the principal sum even in the reply dated
    07.08.2016 to Respondent’s legal notice, did not make good his
    obligation and commitment to pay. In light of the fact that
    Respondent was denied of the amount admittedly due to the
    Respondent for several years, Arbitrator in his discretion awarded
    interest. The question is whether any interference is warranted in
    the award to the extent of grant of dual rate of interest for two
    separate periods.

    20. It needs no reiteration that jurisdiction of the Court under
    Section 34 of the 1996 Act is extremely circumscribed and is
    limited to the grounds enumerated therein. Petitioner urges that by
    awarding exorbitant and dual interest, the award is vitiated by
    „patent illegality appearing on the face of the award‟. The Supreme
    Court and High Courts have time and again affirmed that „patent
    illegality‟ is an illegality which goes to the root of the matter and
    cannot be of a trivial nature. [Ref.: Associate Builders v. Delhi
    Development Authority
    , (2015) 3 SCC 49 and Larsen Air
    Conditioning and Refrigeration Company v. Union of
    India
    , (2023) 15 SCC 472]. Proviso to Section 34(2A) itself
    stipulates that an award shall not be set aside merely on erroneous
    application of law.
    Division Bench of this Court in Aksh Optifibre
    Signature Not Verified
    Digitally Signed
    By:NEERU O.M.P. (COMM) 73/2024 Page 43 of 48
    Signing Date:04.04.2026
    12:18:42
    Limited v. Nantong Siber Communication Co. Ltd.
    , 2024 SCC
    OnLine Del 4011, has held that it is well-settled that fundamental
    policy of Indian law does not refer to violation of any Statute but
    fundamental principles on which Indian law is founded. Any
    difference or controversy as to rate of interest clearly falls outside
    the scope of challenge on the ground of conflict with the public
    policy of India unless it is evident that the rate of interest awarded
    is so perverse and so unreasonable so as to shock the conscience of
    the Court sans which no interference is warranted in the award,
    whereby interest is awarded by the Arbitrator. Against the said
    judgment
    , the Supreme Court dismissed the SLP (C) No.
    22495/2024 on 21.10.2024.

    21. On a plain reading of the impugned award in the instant case
    and applying the settled law, the reasoning adopted by the learned
    Arbitrator for awarding the rate of interest cannot be faulted with.
    Arbitrator has considered all relevant factors such as: (a)
    Petitioner’s admission of his liability to pay the principal amount to
    the Respondent; (b) violation of the terms of settlement in the Deed
    of Settlement and related documents executed on the same day; (c)
    financial loss caused to the Respondent; and (d) the admitted fact
    of the Respondent being deprived of its right to enjoy the monies
    due to it for several years, etc. Arbitrator has exercised the
    discretion vested in him judiciously, taking into consideration
    relevant facts/factors and eschewing irrelevant considerations.

    22. It is a settled law that in the absence of an express bar in the
    contract between the parties, it is the Arbitrator who enjoys
    absolute discretion and has the jurisdiction to award interest
    including post-award interest. [Ref.: State of Rajasthan v. Ferro
    Concrete Construction Private Limited
    , (2009) 12 SCC 1;
    and Indian Railway Construction Company Limited v. National
    Buildings Construction Corporation Limited
    , (2023) 7 SCC 390].
    Clearly, the Deed of Settlement contains no express bar regarding
    interest and it was thus open to the Arbitrator to award the interest.
    Once interest is awarded by the Arbitrator, Section 37(1)(b) comes
    into play where the phrase „unless the award otherwise
    directs‟, qualifies the rate of post-award interest, which means that
    once the award grants interest, award-debtor cannot claim any
    other rate of interest, save and except, where the rate of interest is
    so excessive or unreasonable that it shocks the conscience of the
    Court, which is not the case here.

    23. Counsel for the Petitioner laid much stress on the judgment of
    the Supreme Court in Vedanta Limited (supra), to argue that
    awarding dual interest and that too at an exorbitant rate of 15% was
    held to be unjustified by the Supreme Court.
    In my view, this
    argument is misconceived and need not detain this Court in light of
    the judgment of the Supreme Court in Reliance Infrastructure
    Limited v. State of Goa
    , 2023 SCC OnLine SC 604, as also
    judgments of the Bombay High Court and this Court, to which I
    Signature Not Verified
    Digitally Signed
    By:NEERU O.M.P. (COMM) 73/2024 Page 44 of 48
    Signing Date:04.04.2026
    12:18:42
    shall advert later.
    In Reliance Infrastructure (supra), the Supreme
    Court was examining the legality of the award including the issue
    of grant of pre-reference and post-award interest.
    Insofar as the
    post-award interest is concerned, the High Court had reduced the
    rate of interest from 15 to 10% following the decision in Vedanta
    Limited
    (supra) and principle of proportionality. The Supreme
    Court observed that the reduction of rate of interest by the High
    Court was unjustified.
    Referring to provisions of Section 31(7)(b),
    more particularly, the phrase „unless the award otherwise
    directs‟, and distinguishing the decision in Vedanta
    Limited
    (supra), the Supreme Court held that the observation of the
    High Court that Court may reduce interest awarded by the
    Arbitrator when such interest does not reflect the prevailing
    economic condition or where it is not found reasonable or where it
    promotes interest of justice, based on the decision in Vedanta
    Limited
    (supra), was without any basis since in the case
    of Vedanta Limited (supra), the Supreme Court was dealing with
    an International Commercial Arbitration involving Rupee as well
    Euro components and moreover, the rate of interest was reduced in
    respect of foreign currency component to bring the interest rate in
    line with international rate on the ground that rate of interest
    prevailing on the rupee debt in India and on international currency
    in abroad were different and international rates were lower, which
    was not the case before the Supreme Court in Reliance
    Infrastructure
    (supra). It was further held that the Arbitral Tribunal
    was well within its jurisdiction under Section 31 to award interest
    at the rate of 15% per annum and no justification was found to
    reduce the same. Significantly, it was also observed that the High
    Court was not exercising any equity jurisdiction to re-settle the rate
    of interest as deemed fit by it as this was a matter relating to an
    award made by an Arbitral Tribunal in a commercial dispute. ***
    *****

    27. For all the aforesaid reasons, I am of the view that the
    impugned award calls for no interference in exercise of jurisdiction
    under Section 34 of the 1996 Act.

    (emphasis added)

    66. To augment, the Hon‟ble Supreme Court has repeatedly
    underscored the limited scope of judicial review in matters relating to
    interest awarded by arbitral tribunals. In Sri Lakshmi Hotel Pvt. Ltd.
    (supra), the Hon‟ble Supreme Court reiterated that disputes
    concerning the rate of interest ordinarily fall outside the narrow
    confines of judicial review under Section 34 of the A&C Act. The

    Signature Not Verified
    Digitally Signed
    By:NEERU O.M.P. (COMM) 73/2024 Page 45 of 48
    Signing Date:04.04.2026
    12:18:42
    Court held that a difference of opinion regarding the appropriate rate
    of interest does not, by itself, constitute a ground to interfere with an
    arbitral award on the touchstone of public policy.

    67. It is also pertinent to note that arbitral tribunals, while
    determining the rate of interest, are entitled to take into account the
    commercial nature of the transaction, the conduct of the parties, and
    the period for which the successful party has been deprived of monies
    legitimately due to it. The grant of interest thus serves as a
    restitutionary mechanism ensuring that the party wrongfully
    withholding payment does not derive an undue advantage from the
    delay.

    68. In the present case, as noted earlier, the learned Arbitrator has
    carefully considered the factual matrix and has recorded a categorical
    finding that the Respondent was deprived of the legitimate use of
    monies due under the contract for a considerable period of time. The
    award of interest at the rate of 12% per annum is therefore intended to
    compensate the Respondent for the financial detriment suffered on
    account of such delay.

    69. This Court is therefore of the considered opinion that the rate of
    12% per annum awarded in the present case cannot, by any stretch of
    imagination, be described as exorbitant or unconscionable. On the
    contrary, it falls well within the range of rates that have been
    repeatedly upheld by courts in arbitral matters. The rate awarded is
    thus neither arbitrary nor disproportionate and does not warrant
    interference in the exercise of jurisdiction under Section 34 of the
    A&C Act.

    70. It must also be emphasised that the Court, while exercising
    jurisdiction under Section 34, does not sit in appeal over the
    Signature Not Verified
    Digitally Signed
    By:NEERU O.M.P. (COMM) 73/2024 Page 46 of 48
    Signing Date:04.04.2026
    12:18:42
    conclusions of the arbitral tribunal. As reiterated by the Supreme
    Court in OPG Power Generation (supra) and Consolidated
    Construction Limited (supra), the Court cannot substitute its own
    view merely because another interpretation of facts or law may appear
    possible. So long as the arbitral tribunal has adopted a plausible view
    based on the material before it, the award must be allowed to stand.

    71. Applying the aforesaid principles to the present case, this Court
    finds that the determination of interest by the learned Arbitrator
    represents a reasoned exercise of discretion grounded in the
    contractual relationship between the parties and the factual
    circumstances of the dispute. The Petitioner has failed to demonstrate
    that the award of interest suffers from any illegality, perversity or
    violation of public policy.

    72. Consequently, this Court finds no justification to interfere with
    the award of interest granted by the learned Arbitral Tribunal. The
    challenge raised by the Petitioner on this ground is therefore devoid of
    merit and stands rejected.

    CONCLUSION:

    73. In view of the foregoing discussion and the findings returned
    hereinabove, this Court finds no merit in the challenge mounted by the
    Petitioner to the Impugned Arbitral Award, passed by the learned Sole
    Arbitrator. Consequently, the present Petition, being O.M.P. (COMM)
    73/2024, stands dismissed.

    74. Insofar as I.A. 43484/2024, filed by the Respondent seeking
    withdrawal of the amount deposited by the Petitioner pursuant to the
    Order dated 07.02.2024, is concerned, the same is allowed. The
    Registry is directed to release the amount of ₹3,44,13,536/-, along
    Signature Not Verified
    Digitally Signed
    By:NEERU O.M.P. (COMM) 73/2024 Page 47 of 48
    Signing Date:04.04.2026
    12:18:42
    with accrued interest, to the Respondent, subject to the Corporate
    Guarantee furnished on behalf of the Respondent being taken on
    record.

    75. Pending Application(s), if any, stands disposed of.

    76. No order as to costs.

    HARISH VAIDYANATHAN SHANKAR, J.

    APRIL 01, 2026/kr

    Signature Not Verified
    Digitally Signed
    By:NEERU O.M.P. (COMM) 73/2024 Page 48 of 48
    Signing Date:04.04.2026
    12:18:42



    Source link

    LEAVE A REPLY

    Please enter your comment!
    Please enter your name here