Ssd Escatics Private Limited vs Goregaon Pearl Coopratice Housing … on 30 March, 2026

    0
    72
    ADVERTISEMENT

    Bombay High Court

    Ssd Escatics Private Limited vs Goregaon Pearl Coopratice Housing … on 30 March, 2026

    2026:BHC-OS:7691
                 Neeta Sawant                                                                        CARBP 354 of 2024
    
    
    
    
                              IN THE HIGH COURT OF JUDICATURE AT BOMBAY
                                   ORDINARY ORIGINAL CIVIL JURISDICTION
                         COMMERCIAL ARBITRATION PETITION NO. 354 OF 2024
    
    
                 SSD Escatics Private Limited                                          .....PETITIONER
                                                                                       ORIG. RESPONDENT
    
                          : VERSUS :
    
                 Goregaon Pearl Cooperative
                 Housing Society Limited                                               ....RESPONDENT
                                                                                       ORIG. CLAIMANT
    
    
                 Mr. Rajiv Narula a/w. Mr. Abhishek Bhadang and Mr. Tarang Jagtiani
                 I.b. Jhangiani Narula and Associates, for the Petitioner.
    
                 Mr. Mayur Khandeparkar i/b Mr. Tushar Gujjar a/w. Mr. Deepak Singh
                 and Mr. Lancelot Lewis i/b St. Partners, for the Respondent.
    
    
                                                             CORAM : SANDEEP V. MARNE, J.
                                                            JUDG. RESD. ON: 9 MARCH 2026.
                                                            JUDG. PRON. ON : 30 MARCH 2026
                 JUDGMENT:

    1) The Petitioner has filed this Petition under section 34 of
    Arbitration and Conciliation Act, 1996 (Arbitration Act) challenging the
    award of the learned sole arbitrator dated 24 June 2023. By the impugned
    award, the Arbitral Tribunal has declared the Termination Notice dated 9
    June 2018 terminating the Development Agreement (DA) and Power of
    Attorney (POA), both dated 26 September 2007, and of the Consent

    _______________________________________________________________________________________________________

    SPONSORED

    PAGE NO. 1 OF 78
    30 MARCH 2026

    ::: Uploaded on – 30/03/2026 ::: Downloaded on – 31/03/2026 20:32:40 :::
    Neeta Sawant CARBP 354 of 2024

    Terms dated 16 May 2017 as valid, legal and binding. The Tribunal has
    further declared that the contract of redevelopment is terminated with
    effect from 9 June 2018. The Arbitral Tribunal has restrained the
    Petitioner from interfering with possession of Respondent-Society over
    the land and building in question. Petitioner is directed to the handover
    all original documents relating to redevelopment of the Society. The
    Arbitral Tribunal has also awarded claim in the sum of
    Rs.7,08,53,695.03/- in favour of the Respondent-Society. The Arbitral
    Tribunal has awarded costs of Rs.9,65,250/- in favour of the Respondent-
    Society. The counterclaims of the Petitioner are rejected.

    FACTS

    2) Respondent is a Cooperative Housing Society registered
    under the provisions of the Maharashtra Cooperative Societies Act, 1960.
    The Society was formed by owners and occupiers of 60 flats in Buildings
    B-3, B-4 and B-5 at Survey No.7, CTS No.27 at Siddharth Nagar,
    Goregaon (West), Mumbai, which was a part of MHADA layout. The
    Respondent-Society had 60 original members, who owned and occupied
    flats in the building of the Society. The Respondent-Society decided to
    go for redevelopment of its building. By resolution adopted on 18 June
    2005, the Special General Body Meeting of the Society appointed
    Petitioner as the developer to carry out redevelopment of its building. A
    Redevelopment Agreement was executed between the Petitioner-
    Developer and Respondent-Society on 26 September 2007. A separate
    Power of Attorney was also executed in favour of the Petitioner on the

    _______________________________________________________________________________________________________

    PAGE NO. 2 OF 78
    30 MARCH 2026

    ::: Uploaded on – 30/03/2026 ::: Downloaded on – 31/03/2026 20:32:40 :::
    Neeta Sawant CARBP 354 of 2024

    same day. The Municipal Corporation issued the Intimation of
    Disapproval (IOD) on 16 August 2007. In October/November 2007, the
    members of the society vacated their respective flats and handed over
    the possession thereof to the Petitioner. On 5 January 2008, the
    Petitioner issued Bank Guarantee of Rs. 5 crores in favour of the
    Respondent-Society. Commencement Certificate for construction of a
    building having two wings – Wing-A and Wing-B was issued by the
    Municipal Corporation on 17 June 2008, which was revalidated from time
    to time. On 4 August 2011, a stop work notice was issued to the
    Petitioner alleging that it carried out construction beyond the
    permissions. According to the Respondent-Society, the construction
    activities accordingly came to a halt on 4 August 2011. In the meantime,
    MHADA issued no objection certificate for utilization of FSI 2.5 subject
    to various conditions. Petitioner purchased additional tit-bit land from
    the MHADA Authorities by paying consideration amount of
    Rs.8,18,03,435/- and by virtue of the same, the original plot area got
    increased from the original 2543 sq. mtrs to 3747.81 sq. mtrs. The
    Petitioner got the plans amended from MCGM for availing
    concessional/fungible FSI. According to the Petitioners, correspondence
    took place for execution of supplementary agreement for sharing the
    additional FSI between the Petitioner and Respondent-Society. By the
    year 2013, Petitioner had completed construction of RCC structure of ‘A’
    Wing building upto 7 floors and RCC work of ‘B’ Wing building of 21
    floors.

    _______________________________________________________________________________________________________

    PAGE NO. 3 OF 78
    30 MARCH 2026

    ::: Uploaded on – 30/03/2026 ::: Downloaded on – 31/03/2026 20:32:40 :::
    Neeta Sawant CARBP 354 of 2024

    3) On 14 March 2014, MCGM issued offer letter approving
    proposal for utilization of pro-rata FSI of 3.5 on payment of premium of
    Rs.10,54,17,300/-. It appears that the said amount was not paid by the
    Petitioner. On 12 September 2014, Petitioner issued a letter to the
    Respondent-Society seeking its consent for amalgamation of adjoining
    project of Kapil Vastu Society with Respondent-Society’s land. The
    Respondent-Society requested the Petitioner to complete the project as
    per 2.4 FSI and accommodate all 60 members by granting them
    possession by letter dated 28th January 2015. Thereafter, correspondence
    took place between the Petitioner and Respondent wherein the
    Respondent-Society complained about stoppage of entire work. The
    Petitioner cited the reason of pending issues for sanction of additional
    FSI. Apprehending that the Respondent-Society would encash the bank
    guarantee, Petitioner filed Suit (L.) No.921/2015 in this Court, which was
    withdrawn on 7 January 2016. Respondent-Society thereafter invoked
    and encashed the bank guarantee of Rs.5 crores and appropriated Rs.2.5
    crores towards arrears of tent and balance 2.5 crores towards share of
    profits and utilization of additional 1.00 FSI. The Respondent revoked
    the Power of Attorney on 16 August 2016.

    4) In the above backdrop, Respondent-Society filed Arbitration
    Petition (L) No. 160 of 2017 under Section 9 of the Arbitration Act
    seeking various interim measures. On 7 July 2017, parties arrived at an
    amicable settlement and filed Consent Terms under which the liability of
    the Petitioner was fixed at Rs.7.62 crores and it was agreed that out of
    the encashed amount of bank guarantee, Rs.2.5 crores would be adjusted

    _______________________________________________________________________________________________________

    PAGE NO. 4 OF 78
    30 MARCH 2026

    ::: Uploaded on – 30/03/2026 ::: Downloaded on – 31/03/2026 20:32:40 :::
    Neeta Sawant CARBP 354 of 2024

    towards arrears of rent and balance Rs.2.5 crores towards Society’s share
    of profits in the additional FSI. Petitioner gave commitment to clear the
    balance amount towards transit rent and issued postdated cheques.
    Petitioner agreed to complete A-Wing building with part Occupancy
    Certificate by 30 June 2018 plus grace period of 4 months. It also agreed
    to complete B-Wing building on or before 31 December 2017 with grace
    period of three months. According to the Respondent Society, Petitioner
    committed breaches of Consent Terms and all the postdated cheques
    issued towards payment of rent, etc were dishonored. The Society filed
    Contempt Petition (L) No.24 of 2018 before this Court wherein a
    direction was issued by this Court on 6 March 2018 for payment of sum
    of Rs.5,42,16,436/- in four monthly installments. According to the
    Respondent-Society, except paying sum of Rs.1,72,72,145/-, the
    Petitioner did not make the payment as directed by this Court in the
    Contempt Petition. On 3 June 2018, the Society resolved to terminate
    the Development Agreement, Consent Terms and Power of Attorney.
    The decision of termination was communicated to the Petitioner by
    notice dated 9 June 2018. The Respondent-Society filed Petition under
    Section 9 of the Arbitration Act seeking injunctive reliefs against the
    Petitioner post termination. By consent of the parties, the disputes were
    referred to arbitration by appointing a sole arbitrator by converting
    Section 9 petition into Section 17 application.

    5) After the Arbitral Tribunal comprising of the sole Arbitrator
    was constituted, the Respondent-Society pressed its application for
    interim measures. The Arbitrator passed order dated 17 September 2018

    _______________________________________________________________________________________________________

    PAGE NO. 5 OF 78
    30 MARCH 2026

    ::: Uploaded on – 30/03/2026 ::: Downloaded on – 31/03/2026 20:32:40 :::
    Neeta Sawant CARBP 354 of 2024

    under Section 17 of the Arbitration Act granting various injunctive
    reliefs in favour of Respondent-Society permitting the Society to engage
    new developer and directed Petitioner to handover possession of the
    entire project to the Society. Petitioner challenged the order of interim
    measures of the learned Arbitrator by filing Appeal before this court,
    which was dismissed by order dated 14 December 2018. The Hon’ble
    Apex Court also dismissed the SLP preferred by the Petitioner-Developer
    and this is how order of the Arbitrator making interim measures attained
    finality. The flat purchasers attempted to intervene in the arbitration but
    the learned Arbitrator rejected the intervention application by order
    dated 27 February 2019.

    6) One of the flat purchasers filed a suit seeking specific
    performance of agreement for sale executed in her favour in which City
    Civil Court passed order of temporary injunction restraining the society
    from alienating or creating third party interests in the flat allotted to her
    by the Petitioner-developer. In Appeal from Order filed by the Society,
    the order of temporary injunction was set aside by this Court on 14
    October 2019. The Special Leave Petition preferred by the developer was
    dismissed by the Apex Court on 20 January 2020 and the order passed in
    the Appeal from Order attained finality. The arbitral proceedings were
    conducted before the learned sole Arbitrator. At the conclusion of the
    proceedings, the Arbitral Tribunal has made Award dated 24 June 2023,
    upholding the termination of Petitioner-developer and restrained it from
    interfering with possession of the Society of land and building.
    Petitioner is directed to handover all original documents relating to

    _______________________________________________________________________________________________________

    PAGE NO. 6 OF 78
    30 MARCH 2026

    ::: Uploaded on – 30/03/2026 ::: Downloaded on – 31/03/2026 20:32:40 :::
    Neeta Sawant CARBP 354 of 2024

    redevelopment to the Society. The Arbitral Tribunal has also awarded
    monetary claim in the sum of Rs. 5,13,20,822.32/- in favour of the
    Respondent-society comprising amount of Rs.55,58,211/- towards costs
    incurred, Rs.3,72,24,290/- towards amount agreed to be paid under the
    Consent Terms alongwith interest of Rs.85,38,321.52/-. The Arbitral
    Tribunal has also awarded costs of Rs.9,65,250/- in favour of the
    Respondent-society. All the counterclaims of the Petitioner have been
    rejected.

    7) The Award has been corrected by the Arbitral Tribunal by
    order dated 26 June 2023 by correcting the figure of interest from
    Rs.85,38,321.52/- to Rs. 2,80,71,194.03/-. This is how the final claim
    amount has been enhanced to Rs.7,08,53,695.03/-.

    8) Aggrieved by the Award dated 24 June 2023, as corrected on
    26 June 2023, the Petitioner-developer has filed the present Petition
    under Section 34 of the Arbitration Act.

    SUBMISSIONS

    9) Mr. Narula, the learned counsel appearing for the Petitioner
    submits that the Award of the Tribunal is grossly perverse as being
    rendered contrary to the contractual terms, violates public policy
    doctrine and is patently illegal. He first attacks various findings recorded
    in the award relating to validity of the termination notice. He submits
    that the findings of the Arbitral Tribunal in para-103 of the award that

    _______________________________________________________________________________________________________

    PAGE NO. 7 OF 78
    30 MARCH 2026

    ::: Uploaded on – 30/03/2026 ::: Downloaded on – 31/03/2026 20:32:40 :::
    Neeta Sawant CARBP 354 of 2024

    the FSI was pegged at 2.4 is contrary to the Development Agreement
    dated 26 September 2007, clause-2 whereof permitted utilization of all
    available FSI and additional TDR by dividing the benefits between the
    parties. That specific admissions were made by the witness of
    Respondent-Society in answer to Question Nos.94 and 95 in this regard.
    That finding recorded in para-121 of the Award about amendment of
    plans without intimation of Society is contrary to clauses-9(a) and 9(g) of
    the Development Agreement, which did not require any prior intimation
    for amendment of the plans. That Consent Terms dated 16 May 2017
    only condoned the previous alleged breaches and therefore,
    supplemental terms were arrived at between the parties. That under
    clause 39 of the Consent Terms, Respondent was required to issue NOC
    to MHADA for grant of further FSI, but it failed to communicate the
    withdrawal of revocation of POA to MHADA. That clause 40 of the
    Consent Terms required the Society to withdraw the termination notice
    and grant unconditional NOC for additional FSI and clause 41 required
    the Respondent-Society to grant NOC for obtaining finance. That such
    NOCs were not issued by the society thereby breaching the conditions of
    the Consent Terms. That the agreement between the parties is reciprocal
    in nature and since Respondent-Society failed to adhere to its
    contractual obligations, provisions of Section 67 of the Indian Contract
    Act, 1872 (Contract Act) became applicable, thereby relieving the
    Petitioner of the consequences of any breaches on its part. He relies on
    judgment of the Apex Court in Nathulal vs. Phoolchand1.

    1

    (1969) 3 SCC 120
    _______________________________________________________________________________________________________

    PAGE NO. 8 OF 78
    30 MARCH 2026

    ::: Uploaded on – 30/03/2026 ::: Downloaded on – 31/03/2026 20:32:40 :::
    Neeta Sawant CARBP 354 of 2024

    10) Mr. Narula further submits that the findings of the Arbitral
    Tribunal in para-166 of the award about the arrangement for grant of
    NOC for additional FSI not being inflexible is contrary to the express
    conditions of the Consent Terms. That further finding of the arbitrator in
    para-169 of the award that Respondent-Society factually granted NOC is
    contrary to the record since NOC dated 28 July 2017 was delivered to the
    Petitioner only on 26 September 2017, by which date the due date to
    perform had already passed by. That the observations of the arbitrator in
    para-170 of the arbitral award about non-payment of premium is
    perverse and recorded in ignorance of payment of Rs.3,32,31,778/- which
    remained credited to the Petitioner’s account. That in view of failure to
    issue NOC by the Society, Termination Notice was illegal and contrary to
    the agreed terms. That the Arbitral Tribunal ought to have dismissed
    Society’s claim.

    11) Mr. Narula further submits that the Arbitral Tribunal has
    construed the contract in such a way that no fair-minded person would
    ever do so. He relies on judgment of the Apex Court in Associate
    Builders Versus. Delhi Development Authority2.

    12) Mr. Narula then proceeds to attack the award by contending
    that non-return of amounts spent by the Petitioner in the project which
    are benefits enjoyed by the society is contrary to the fundamental policy
    of Indian law. He submits that the award permits the Society to unjustly
    enrich itself by retaining the amounts towards rent, cost of construction,
    cost of purchased FSI, etc . That the Arbitral Tribunal has grossly erred in
    2
    (2015) 3 SCC 49
    _______________________________________________________________________________________________________

    PAGE NO. 9 OF 78
    30 MARCH 2026

    ::: Uploaded on – 30/03/2026 ::: Downloaded on – 31/03/2026 20:32:40 :::
    Neeta Sawant CARBP 354 of 2024

    not treating the various amounts spent by the Petitioner as ‘benefits’
    received by the Society. That Petitioner paid sum of Rs.8,18,03,435/- for
    acquiring additional tit-bit plot area and sum of Rs.20,61,140/- for FSI
    for R.G. area. That Petitioner also incurred huge amount of cost for
    construction of the two buildings. That additionally Respondent-Society
    appropriated amount of Rs.2.5 crores towards their share in the
    additional FSI. That all these amounts spent by the Petitioner which are
    ultimately enjoyed by the Respondent-society are erroneously not
    treated as benefits by the Society. He submits that Arbitral Tribunal’s
    refusal for restoration of benefits to the Petitioner upon termination of
    contract and non-award of damages in view of Clause-22 of the DA is
    contrary to Sections 64 and 73 of the Contract Act. He relies on judgment
    of the Madras High Court in Mundakath Mathu vs. Chalora Illath
    Vishnu Nambudripad
    and others3 in support of his contention that upon
    avoidance of the contract, a party avoiding it is under statutory
    obligation to restore the benefits. He submits that a party cannot reject
    the contract yet retain the advances derived therefrom. Mr. Narula
    further submits that Clause 22 of the DA is in the teeth of provisions of
    Section 23 of the Contract Act as it seeks to prohibit a party from
    approaching the Court for recovery of damages which is against the
    public policy of India. That this issue was specifically raised before the
    Arbitrator. He also relies on judgments of the Apex Court in Asian Techs
    Limited vs. Union of India and Ors.
    4, Board of Trustees for the Port of
    Calcutta vs. Engineers-De-Space-Age5 and of Delhi High
    Court in MBL

    3
    AIR 1932 Mad 303
    4
    (2009) 10 SCC 354
    5
    (1996) 1 SCC 516
    _______________________________________________________________________________________________________

    PAGE NO. 10 OF 78
    30 MARCH 2026

    ::: Uploaded on – 30/03/2026 ::: Downloaded on – 31/03/2026 20:32:40 :::
    Neeta Sawant CARBP 354 of 2024

    Infrastructures Ltd. vs. Delhi Metro Rail Corporation 6. In support of his
    contention that any contractual terms which denies compensation is
    void and unenforceable, Mr. Narula relies on judgments of this Court in
    Mumbai Metropolitan Region Development Authority vs. Mumbai
    Metro One Private Limited7
    and Regus South Mumbai Business Centre
    vs. Marie Gold Realtors Private Limited8.

    13) That the Arbitral Tribunal has erroneously refused to treat
    the rent paid by the Petitioner as not a benefit received by the Society
    members. That the Arbitral Tribunal has erroneously relied on mere
    interim order passed by this Court in Borivali Anamika Niwas CHSL vs.
    Aditya Developers and Ors.9
    wherein some observations are made for
    considering entitlement of parties to interim measures under Section 9
    of the Arbitration Act. That the judgment in Borivali Anamika Niwas
    CHSL cannot be read to mean an abstract principle that construction
    costs incurred by a developer can never amount to benefit received by
    the society or its members. He submits that various judgments on the
    other hand clearly lay down a law for return of benefits under Section 64
    of the Contract Act upon rescission of the contract.
    He relies on
    judgments in Chacko and Ors. vs. Sreeja and Anr.10, Mohammad
    Mumtaz Ali Khan and Anr. vs. Altaf-ul-Rahman Sheikh and Anr.11 and
    Muralidhar Chatterji vs. International Film Company Ltd. 12 That costs

    6
    2023 SCC OnLine 8044
    7
    Commercial Arbitration Petition No.427 of 2024 decided on 24 February 2026
    8
    Commercial Arbitration Petition No.439 of 2024 decided on 25 November 2026
    9
    2020 SCC OnLine Bom 10632
    10
    1990 SCC OnLine Ker 327
    11
    1922 SCC OnLine Oudh JC 87
    12
    1942 SCC OnLine PC 35
    _______________________________________________________________________________________________________

    PAGE NO. 11 OF 78
    30 MARCH 2026

    ::: Uploaded on – 30/03/2026 ::: Downloaded on – 31/03/2026 20:32:40 :::
    Neeta Sawant CARBP 354 of 2024

    of construction and payments made by the Petitioner for purchase of FSI
    and additional FSI are benefits received by the Society, which must be
    returned upon termination of the contract. That it is clearly against
    public policy to permit a party terminating the contract to retain the
    benefits arising out of it.

    14) Mr. Narula further submits that even if compensation is
    denied to the Petitioner under Section 73 of the Contract Act, the
    benefits received by the Respondent-Society must be returned under
    Section 64 of the Act. That there is no contractual prohibition between
    the parties for restoration of the benefits received by the Society. That in
    the present case, the Respondent-Society has unjustly enriched itself by
    retaining the entire construction put up by the Petitioner and also by
    utilising the FSI purchased by the Petitioner. That the learned Arbitrator
    has not considered the case of the Petitioner for restoration under
    Section 64 of the Contract Act and has conflated the same with the
    concept of compensation under Section 73 of the Act. That the
    Petitioner has made investment of over Rs.300 crores in the project and
    since the society has enjoyed the benefits of such investment, the same
    must be returned to the Petitioner upon rescission of the contract.

    15) Mr. Narula relies on the provisions of Section 27 of the
    Specific Relief Act, 1963 in support of his contention that several third
    party rights have been created during subsistence of the contract and
    that the learned arbitrator ought to have invalidated illegal rescission of

    _______________________________________________________________________________________________________

    PAGE NO. 12 OF 78
    30 MARCH 2026

    ::: Uploaded on – 30/03/2026 ::: Downloaded on – 31/03/2026 20:32:40 :::
    Neeta Sawant CARBP 354 of 2024

    the contract by the Society by taking into consideration the factum of
    third-party rights.

    16) Lastly, Mr. Narula would submit that voluminous
    documentary evidence was produced by the Petitioner in support of the
    claim for damages and benefits to the Responding-Society. That no
    cross-examination was conducted on behalf of the Respondent-Society
    in respect of the evidence so led. However, the learned Arbitrator has
    erroneously not awarded loss of profits because of insufficiency of
    evidence, which finding is contrary to the judgment of this Court in
    Harish Loyalka and Another vs. Dilip Nevatia and Others 13. On above
    broad submissions, Mr. Narula would seek invalidation of the impugned
    award.

    17) The Petition is opposed by Mr. Khandeparkar, the learned
    counsel appearing for the Respondent-Society. He submits that the
    Petitioner has failed to make out even a single valid ground of challenge
    as enumerated in Section 34 of the Arbitration Act for invalidating the
    impugned award. He submits that the Arbitral Tribunal has conducted an
    in-depth analysis of contractual provisions, correspondence between the
    parties and evidence before it and has thereafter arrived at a finding that
    the termination of the DA is legal and valid. He submits that despite
    execution of the DA on 26 September 2017, all that the Petitioner did by
    9 June 2018 by which time DA was terminated, was to merely construct a
    bare shell rehab component building. That the construction at site had
    come to an absolute halt since 2011 and Petitioner-developer had
    13
    2014 SCC OnLine 1640
    _______________________________________________________________________________________________________

    PAGE NO. 13 OF 78
    30 MARCH 2026

    ::: Uploaded on – 30/03/2026 ::: Downloaded on – 31/03/2026 20:32:40 :::
    Neeta Sawant CARBP 354 of 2024

    defaulted in payment of rent to the members. That in such
    circumstances, termination of the DA executed with the developer not
    causing any construction at the site is rightly upheld by the Arbitral
    Tribunal. That there was no construction at the site after the Municipal
    Corporation issued stop work notice on 4 August 2011. He submits that
    the Petitioner was forced to enter into Consent Terms after this Court
    noticed prima facie forgery and fabrication in the Commencement
    Certificate on 7 December 2016. However, none of the obligations under
    the Consent Terms are fulfilled by the Petitioner. That all the post-dated
    cheques issued by him towards payment of rent/ compensation were
    dishonoured. That even order passed in Contempt Petition for payment
    of sum of Rs.5.42 crores was not honoured by the Petitioner. That
    Respondent-Society, waited for more than a year for Petitioner to act in
    terms of the Consent Terms, finally was left with no other alternative but
    once again terminate the DA and POA on 9 June 2018. Mr. Khandeparkar
    places on record submissions filed before the Arbitral Tribunal and
    invites my attention to various breaches of the DA as well as of the
    Consent Terms highlighted therein.

    18) Mr Khandeparkar further submits that the Arbitral Tribunal
    has taken note of material breaches committed by the Petitioner, both of
    the DA as well as of the Consent Terms. That findings of facts recorded
    by the Arbitral Tribunal in respect of such breaches do not warrant
    interference in exercise of jurisdiction under Section 34 of the
    Arbitration Act.

    _______________________________________________________________________________________________________

    PAGE NO. 14 OF 78
    30 MARCH 2026

    ::: Uploaded on – 30/03/2026 ::: Downloaded on – 31/03/2026 20:32:40 :::
    Neeta Sawant CARBP 354 of 2024

    19) Mr. Khandeparkar then justifies the Arbitral Tribunal not
    awarding any damages and not returning the expenditure incurred by the
    Petitioner developer by inviting my attention to clauses-9(h), 22, 42 and
    47 and 53 of the D.A. wherein the developer specifically agreed not to
    claim damages or compensation in the event of breach of contract. The
    Arbitral Tribunal is justified in not awarding the same by giving effect to
    the contractual terms agreed between the parties. He relies on judgment
    of the Apex Court in Steel Authority of India Ltd. versus. J.C.
    Budharaja, Government and Mining Contractor 14 in support of his
    contention that it is not open to the arbitrator to ignore the agreed terms
    of contract which are binding on the contracting parties. He relies on
    Section 28 of the Arbitration Act in support of his contention that the
    Arbitral Tribunal was bound to render the award strictly in terms of the
    contractual stipulations agreed between the parties. He submits that in
    Borivali Anamika Niwas CHSL (supra), this Court has specifically held
    that mere investment of money into the project by the developer does
    not create any equity and the expenditure in the project is not a handout
    to the society members.
    He also relies on judgment of this Court in
    Rajawadi Arunodaya CHS Ltd. vs. Value Projects Pvt. Ltd. 15 in support
    of his contention that mere creation of third-party rights by the
    developer does not make any difference as the developer takes the risk of
    satisfying those third-party purchasers who are strangers to principal
    agreements with no obligation on the Society. He submits that the
    society ultimately is the owner of the property. Mr. Khandeparkar further
    submits that if a law is declared even while making an interim order by
    14
    (1999) 8 SCC 122
    15
    2021 SCC OnLine Bom 9572
    _______________________________________________________________________________________________________

    PAGE NO. 15 OF 78
    30 MARCH 2026

    ::: Uploaded on – 30/03/2026 ::: Downloaded on – 31/03/2026 20:32:40 :::
    Neeta Sawant CARBP 354 of 2024

    this Court, the law declared therein cannot be ignored only on the
    ground that what court decided was a mere prayer for interim injunction.
    He relies on judgment of this Court in IREP Credit Capital Pvt. Ltd. vs.
    Tapaswi Mercantile Pvt. Ltd. and Anr
    .16 That therefore, the Tribunal
    has rightly relied upon judgment of this Court in Borivali Anamika
    Niwas CHSL.

    20) Mr. Khandeparkar further submits that the development
    agreements are special types of contracts, which cannot be interpreted
    like regular commercial contracts. That consideration under Section 2(d)
    of the Contract Act can also be negative consideration. That DA is a
    negotiated document under which parties have agreed on a condition
    that the developer will not make a claim for expenses/investments made
    in case of breach/termination, which forms negative consideration for
    execution of the contract. That various clauses of the DA were never
    challenged before the learned Arbitrator nor a declaration was sought
    that the same are void or contrary to law. That therefore, arbitrator being
    a creature of contract, cannot decide the claims against the terms of the
    contract.

    21) Mr. Khandeparkar further submits that amounts allegedly
    paid by the Petitioner to MHADA/MCGM are claimed as a part of
    compensation in the counterclaim and not as restoration of benefits
    under Section 64 of the Contract Act. That therefore, Petitioner cannot
    now turn around and claim that the said amounts must be restored to it

    16
    2019 SCC OnLine Bom 5719
    _______________________________________________________________________________________________________

    PAGE NO. 16 OF 78
    30 MARCH 2026

    ::: Uploaded on – 30/03/2026 ::: Downloaded on – 31/03/2026 20:32:40 :::
    Neeta Sawant CARBP 354 of 2024

    as a part of benefit under Section 64 of the Act. He further submits that
    the learned Arbitrator has therefore rightly treated the counterclaims
    raised by the Petitioner as claim for compensation within the meaning of
    Section 73 of the Contract Act. That the view taken by the learned
    Arbitrator in treating the counterclaims as compensation is plausible
    view not warranting any interference in exercise of powers under Section
    34
    of the Arbitration Act. Without prejudice, he submits that restitution
    would otherwise form compensatory damages, as held by the Madras
    High Court in E-merge Tech Global Services P Ltd. vs. M.R.
    Vindhyasagar and Anr.17.

    22) Mr. Khandparkar relies on judgment of Division Bench of
    this Court in Vilayati Ram Mittal (P) Ltd. vs. Reserve Bank of India 18 in
    support of the contention that clauses in the contract providing for non-
    payment of compensation are enforceable in law.
    He also relies on
    judgment of the Apex Court in Associated Engineering Co. vs.
    Government of Andhra Pradesh and Anr.19 He
    relies on judgment of the
    Apex Court in Union of India and Ors. vs. Larsen & Tubro Limited20 in
    support of his contention that the Apex Court has enforced covenant in
    the contract for non-payment of interest. Mr. Khandepakar further
    submits that the any dispute about Petitioner’s entitlement to
    compensation contrary to various contractual clauses, would fall outside
    the jurisdiction of the arbitrator. That the entitlement of Petitioner to
    compensation and restoration of benefits is determined by the Tribunal
    17
    2021 SCC OnLine Mad 17022
    18
    2017 SCC OnLine Bom 8479
    19
    (1991) 4 SCC 93
    20
    2026 SCC OnLine SC 327
    _______________________________________________________________________________________________________

    PAGE NO. 17 OF 78
    30 MARCH 2026

    ::: Uploaded on – 30/03/2026 ::: Downloaded on – 31/03/2026 20:32:40 :::
    Neeta Sawant CARBP 354 of 2024

    as per the contractual terms and that therefore even if the arbitrator
    commits any mistake in interpreting the terms of the contract, it would
    be an error within its jurisdiction not warranting interference by Section
    34
    Court. He relies on judgment of this Court in Goa Shipyard Limited
    vs. Shoft Shipyard Pvt. Ltd.21
    in support of his contention that mere
    erroneous application of law by the arbitrator cannot be a ground for
    interference in the award.

    23) Mr. Khandeparkar further submits that the rights of the
    developer during the term of DA are subservient and imperfect rights
    which get perfected only upon full compliance with the terms of DA and
    upon handing over of flats to the members. That the right of the
    developer has not been perfected in the facts and circumstances of the
    present case. He relies on judgment of this Court in Vaidehi Akash
    Housing Pvt. Ltd. vs. New D.N. Nagar Co-op. Housing Society Union
    Ltd. and Others22
    in support of his contention that right of the
    Petitioner-Developer to sell flats and to earn profits does not get
    perfected until fulfilment of all obligations under the DA. That the
    developer has entered into the DA with full knowledge of non-
    entitlement for any compensation in the event of termination of
    contract on account of his breaches and therefore it cannot now be
    permitted to wriggle out of such contractual obligations.

    24) Mr. Khandeparkar further submits that what is ultimately
    taken by the arbitrator in the facts of the present case is a plausible view
    21
    Arbitration Appeal No. 38 of 2024 decided on 26 April 2024.

    22

    2014 SCC OnLine Bom 5068
    _______________________________________________________________________________________________________

    PAGE NO. 18 OF 78
    30 MARCH 2026

    ::: Uploaded on – 30/03/2026 ::: Downloaded on – 31/03/2026 20:32:41 :::
    Neeta Sawant CARBP 354 of 2024

    which cannot be interfered with by Section 34 Court. In support, he
    relies upon judgment of the Apex Court in Consolidated Construction
    Consortium Ltd. vs. Software Technology Parks of India
    23. He submits
    that even if any error is traced in construction of contractual terms by
    the Arbitral Tribunal, the same would at the highest be an error within
    the jurisdiction.
    He relies on judgment of the Apex Court in Ramesh
    Kumar Jain vs. Bharat Aluminium Company Limited ( BALCO
    ) 24 in
    support of his contention that even an award which is based on little or
    no evidence cannot be invalidated on that score and that even decisions
    taken by the arbitrator on equity which are just and fair cannot be
    overridden by Courts under Sections 34 and 37 of the Arbitration Act. He
    submits that in addition to clause 22 of the DA, the decision of the
    arbitrator not to return alleged expenses incurred by the Petitioner or
    alleged benefits received by the society is also justified on account of
    other contractual clauses in the agreement.
    He relies on judgment of the
    Apex Court in OPG Power Generation Pvt Ltd. Vs. Enexio Power
    Cooling Solutions India Pvt. Ltd. and Anr.
    25 in support of his contention
    that it is open for Section 34 Court to justify the underlying reasons in
    the arbitral award by taking into consideration the entire material
    produced before the Arbitral Tribunal. Mr. Khandeparkar further
    submits that the award of the Arbitral Tribunal results in a situation
    where the society has ultimately completed construction of the building
    and its members are put back in possession of their respective homes.
    That the Arbitral Tribunal has awarded mainly the claim for arrears of

    23
    (2025) 7 SCC 757
    24
    2025 SCC Online SC 2857
    25
    (2025) 2 SCC 417
    _______________________________________________________________________________________________________

    PAGE NO. 19 OF 78
    30 MARCH 2026

    ::: Uploaded on – 30/03/2026 ::: Downloaded on – 31/03/2026 20:32:41 :::
    Neeta Sawant CARBP 354 of 2024

    rent which are expressly agreed in the consent terms. That the issue of
    rent not representing benefit to the society Members is settled by
    judgment of this Court while rejecting Petitioner’s appeal against
    Section 17 order. He therefore submits that no case is made out by the
    Petitioner-developer for interference in the impugned award. He would
    pray for dismissal of the petition.

    REASONS AND ANALYSIS

    25) The present case is an example of a tragic saga where the
    hopes of members of the Respondent-society to secure bigger, better and
    more comfortable homes through redevelopment process resulted in a
    long ordeal where they were dishoused back in the year 2007 and were
    kept waiting for newly built homes for next 11 long years. The transit
    rent was stopped by the Petitioner-developer. The society terminated
    the DA and encashed the Bank Guarantee for recovery of arrears of
    transit rent. The parties however entered into consent terms and one
    more opportunity was given to the Petitioner-developer to complete the
    project. However, Petitioner was again unable to complete construction
    of the building and the Society once again terminated the DA and
    completed the balance construction of the building on its own. The
    Arbitral Tribunal has upheld the termination and has directed the
    Petitioner-developer to pay to the Society the amounts agreed to be paid
    under the Consent Terms towards arrears of rent, etc along with interest.
    The counterclaims of the Petitioner-developer were towards return of
    amounts spent in the project and damages/compensation for loss of

    _______________________________________________________________________________________________________

    PAGE NO. 20 OF 78
    30 MARCH 2026

    ::: Uploaded on – 30/03/2026 ::: Downloaded on – 31/03/2026 20:32:41 :::
    Neeta Sawant CARBP 354 of 2024

    profit which have been rejected by the Tribunal. The Petitioner-
    developer is aggrieved by the impugned award and has filed the present
    Petition under Section 34 of the Arbitration Act.

    26) The net result of the arbitral award is that the Petitioner is
    out of the project, it has lost all investments made in the project and the
    society is relieved of the liability towards third parties to whom the
    Petitioner had sold the flats. Petitioner is also made liable to pay the
    arrears of transit rent, etc to the society members.

    VALIDITY OF TERMINATION OF DA

    27) The principal issue before the Arbitral Tribunal was about
    validity of the termination notice dated 9 June 2018 by which the DA is
    terminated. Since the DA is terminated alleging breaches by the
    Petitioner-Developer, the Society was required to prove before the
    Tribunal commission of breaches of the contractual clauses of the DA
    and of the Consent Terms by the Petitioner. The Arbitral Tribunal has
    ruled in favour of the Respondent-Society by holding Petitioner
    responsible for breaches of DA and of Consent Terms and has held the
    termination notice to be valid.

    28) It would be necessary to consider the broad contractual
    arrangement between the parties under the DA. The first recital to the
    DA indicates that MHADA had constructed the old buildings of the
    Society consisting of 60 flats and had allotted the same to various

    _______________________________________________________________________________________________________

    PAGE NO. 21 OF 78
    30 MARCH 2026

    ::: Uploaded on – 30/03/2026 ::: Downloaded on – 31/03/2026 20:32:41 :::
    Neeta Sawant CARBP 354 of 2024

    allottees who collectively formed the Respondent Society. Under clause 2
    of the DA, parties agreed that total FSI to be exploited was 2.4 and in the
    event the Developer was allowed to load any further TDR on the plot, the
    benefits accrued to it from additional/surplus construction shall be
    divided between the Developer and the Society in equal ratio. Under
    clause 9(e), Developer agreed to consult the Society in regard to the
    construction work carried out by it by providing copies of all letters and
    correspondence as well as plans/approvals without any specific request
    made by the Society. Under clause 9(f), the Developer provided
    unconditional undertaking to abide by provisions of Mumbai Municipal
    Corporation Act, 1888
    , Development Control Regulations, 1991,
    Maharashtra Housing and Area Development Act, 1976 which govern the
    use of FSI/TDR and indemnify the Society in respect of any violation
    thereof. Under clause 9(g), the Developer agreed that any
    modification/changes in the annexure attached to DA were to be
    mutually discussed with the Society and such changes made in the new
    annexure would replace the redundant annexure without modifying the
    other clauses of DA. Under clause 9(h), parties agreed that the Society
    shall have right to exploit all the rights and liberties of the Petitioner
    arbitrarily in case of any default on the part of the Developer. Under
    clause 9(k), the Society was absolved of any liability towards third party
    purchasers of flats.

    29) Under clause 10(3) of the DA, the Developer was liable to
    pay compensation or license fee/rent towards alternate accommodation
    to all 60 members till they were put in possession of new flats after

    _______________________________________________________________________________________________________

    PAGE NO. 22 OF 78
    30 MARCH 2026

    ::: Uploaded on – 30/03/2026 ::: Downloaded on – 31/03/2026 20:32:41 :::
    Neeta Sawant CARBP 354 of 2024

    obtaining full occupation certificate. Under clause 22, the Society was at
    liberty to terminate the DA in the event of Developer failing to complete
    the project even after three months extension and to appoint a new
    developer to complete the reconstruction. Most importantly, it was
    agreed between the parties that Developer will have no right to claim any
    damages or compensation from the Society and Developer would forgo
    its right to sell the commercial premises which are part of saleable
    portion of the flats. Under clause 27, an indemnity was given by the
    Developer to the Society. Under clause 42, the Developer agreed to bear
    and pay all costs of construction including all costs, charges and
    expenses for obtaining various approvals, permissions, etc. Under clause
    47, the Developer agreed not to ask for any amount or contribution from
    the Society or its members towards expenses for putting of the
    construction. Under clause 53 (iii), it was agreed that the DA was not to
    be construed as partnership or joint venture or agreement of partnership
    and that the same was be on ‘principal to principal’ basis.

    30) The Respondent-Society alleged various breaches of the DA
    by the Petitioner. The broad allegations of breaches are as under:

    a. Breach of clause (2) by using 3.5 FSI contrary to agreed cap of FSI
    2.4,

    b. Breach of clause (3) by exceeding the maximum cap of 860 sq.ft.

    carpet area by constructing flats in A Wing of 866 sq. ft. and
    Wing of 1006 sq.ft.

    _______________________________________________________________________________________________________

    PAGE NO. 23 OF 78
    30 MARCH 2026

    ::: Uploaded on – 30/03/2026 ::: Downloaded on – 31/03/2026 20:32:41 :::
    Neeta Sawant CARBP 354 of 2024

    c. Breach of clause 9(f) by committing violation of planning norms
    leading to issuance of stop work notice by MCGM on 4 August
    2011 and by executing work beyond CC,

    d. Breach of clause 9(g) by changing the plans without the consent of
    the Society,

    e. Breach of clause 10(1)(a) by committing default in payment of rent
    from 2014 onwards,

    f. Breach of clause 10(1)(b) by not increasing the rental
    compensation by 10% despite passage of period of 25 months from
    the date of issuance of CC,

    g. Breach of clause 22 by not completing construction within 25
    months of issuance of CC dated 17 August 2002,

    h. Breach of Annexure-I by not providing amenities listed therein.

    31) As observed above, though disputes arose between the
    parties in the year 2017 and the society encashed the bank guarantee, the
    parties entered into Consent Terms before this Court on 16 May 2017 in
    Petition filed under Section 9 of the Arbitration Act. The broad
    agreement executed in the Consent Terms included fixing the total
    liability of Petitioner in respect of arrears of rent of Rs.7,62,20,000/-
    which was agreed to be paid by the Petitioner under two mechanisms.
    Petitioner agreed to pay sum of Rs.5,12,20,000/- in various instalments
    upto 30 November 2017. The balance amount of Rs.2,50,00,000/- was
    agreed to be adjusted from the amount of Rs.5,00,00,000/- encashed by
    the Respondent-Society towards bank guarantee. The rest of amount of
    Rs.2,50,00,000/- from Bank Guarantee was to be adjusted against
    _______________________________________________________________________________________________________

    PAGE NO. 24 OF 78
    30 MARCH 2026

    ::: Uploaded on – 30/03/2026 ::: Downloaded on – 31/03/2026 20:32:41 :::
    Neeta Sawant CARBP 354 of 2024

    Society’s share in respect of use of additional FSI by the Petitioner-
    Developer. Petitioner agreed to complete A and B Wings buildings within
    the extended timeline of 30 June 2018 (plus four months grace period)
    and 31 December 2017 (with three months grace period) respectively.

    32) According to the Respondent-Society, Petitioner has
    committed following material breaches of the Consent Terms:

    a. Payments agreed towards transit rent due on 30 August 2017, 30

    September 2017, 30 October 2017 and 30 November 2017 are not
    paid,
    b. Seven post dated cheques issued by Petitioner for Rs.24,00,000/-

    each for rent of seven months from 1 May 2017 to 31 December
    2018 were dishonoured,
    c. Brokerage of Rs.40,000/- per member as agreed under clause 4 of

    Consent Terms was not paid. Breach of clause 5 of Consent Terms
    which provided for payment of penalties for not paying the same,
    d. Breach of clause 15 for construction of permanent wall as well as

    wall between Respondent-Society and Kapil Vastu Society, which
    was not constructed,
    e. Breach of clause 17 for providing flats to the 32 members of A-

    Wing having a carpet area of minimum 1006/1010 sq.ft.
    f. Breach of Clauses 24 (a) and (b) relating to timelines for
    completion of Wing A and Wing B.
    g. Breach of Clause 33 relating to opening of escrow account.

    _______________________________________________________________________________________________________

    PAGE NO. 25 OF 78
    30 MARCH 2026

    ::: Uploaded on – 30/03/2026 ::: Downloaded on – 31/03/2026 20:32:41 :::
    Neeta Sawant CARBP 354 of 2024

    33) The Arbitral Tribunal has done a detailed analysis of
    breaches committed by the Petitioner in respect of the Development
    Agreement. In paragraphs 102 to 111 of the Award, the Arbitral Tribunal
    has held that the Petitioner committed breach of contractual covenant of
    utilization of FSI 2.4 by carrying out construction in excess of the FSI
    cap. Mr. Narula has argued that there is perversity in this finding of
    Arbitral Tribunal since clause (2) of the DA envisaged use of FSI in excess
    of 2.4 and that the finding of the Arbitral Tribunal is contrary to the
    contractual stipulation. He has also relied upon admissions given by
    Respondent’s witness in answer to question Nos.94 and 95 in support of
    his contention that finding is contrary to the evidence on record. In my
    view, however, clause (2) of the DA provided for sharing of benefit
    arising out of loading of any further TDR on the flat in equal proportions
    between Petitioner and Respondent. The Arbitral Tribunal has construed
    clauses (2), (3), 9(h) read with Schedule-I of the DA and has thereafter
    recorded a finding that the FSI was restricted to 2.4. As a matter of fact,
    breach of clause (2) can also be inferred from the fact that Petitioner
    subsequently agreed to shell out 50% amount of encashed bank
    guarantee towards share of Respondent-Society in the additional FSI.

    The amount was agreed to be shared only after the society encashed the
    bank guarantee and was not paid to the society contemporaneously
    when Petitioner carried out construction in excess of FSI 2.4. So far as
    the admissions by Respondent’s witness are concerned, the Arbitral
    Tribunal has recorded a plausible finding that witness’ understanding of
    the clause did not make any difference and that her answers were
    required to be understood in the context of answers to other questions. I

    _______________________________________________________________________________________________________

    PAGE NO. 26 OF 78
    30 MARCH 2026

    ::: Uploaded on – 30/03/2026 ::: Downloaded on – 31/03/2026 20:32:41 :::
    Neeta Sawant CARBP 354 of 2024

    therefore do not find any perversity in the findings recorded by the
    Arbitral Tribunal qua the issue of FSI cap of 2.4. The Tribunal has
    constructed the contractual clauses of the DA and the said exercise is
    within its exclusive domain. The construction of contractual clauses by
    the Tribunal for recording findings about violation of FSI cap cannot be
    termed as so irrational that no fair-minded person would ever record the
    same. Reliance by Mr. Narula on judgment of the Apex Court in
    Associate Builders (supra) in this regard is therefore inapposite.

    34) The Arbitral Tribunal thereafter considered the events that
    occurred during subsistence of the DA, amendments effected by the
    Petitioner to the status of project from composite to non-composite as
    well as amendments in the Plans. The Tribunal has held that the Plans
    were amended without prior intimation to the Respondent-Society nor
    consent of the Society was obtained before applying for the same. Mr.
    Narula has sought to rely on clauses 9(a) and 9(g) of the Development
    Agreement in support of his contention that prior intimation to the
    Society was not required to be given. However, the Arbitral Tribunal has
    held that clauses 9(a) and 9(g) of the DA required consultation with the
    Respondent-Society and its approval to the changes effected in the
    construction plans. The Arbitral Tribunal has accordingly held Petitioner
    liable for amendment of plans during subsistence of DA without
    consultation and approval of the Respondent-Society and I again do not
    find any element of perversity in the said findings recorded by the
    Arbitral Tribunal.

    _______________________________________________________________________________________________________

    PAGE NO. 27 OF 78
    30 MARCH 2026

    ::: Uploaded on – 30/03/2026 ::: Downloaded on – 31/03/2026 20:32:41 :::
    Neeta Sawant CARBP 354 of 2024

    35) The Arbitral Tribunal thereafter considered various other
    breaches on the part of the Petitioner-Developer in paragraphs 134 to
    150 of the Award. No attempt is made to indicate an element of
    perversity in respect of other breaches in paragraphs 134 to 150 of the
    impugned Award.

    36) The factual findings recorded by the Arbitral Tribunal in
    respect of breaches committed by the Petitioner-Developer of various
    contractual obligations under the Development Agreement cannot be
    termed as perverse. It is not necessary to delve deeper into the findings
    of the Tribunal about breaches of DA by the Petitioner as commission of
    those breaches is an admitted position. This is clear from the plea is
    raised by the Petitioner before me that execution of Consent Terms
    dated 16 May 2017 condoned the previous breaches and such plea
    contains implicit admission of commission of various breaches of the DA
    by the Petitioner.

    37) The Arbitral Tribunal thereafter considered allegations
    relating to breaches of the Consent Terms committed by the Petitioner-
    Developer in paragraphs 155 to 172 of the Arbitral Award. Mr. Narula has
    contended that there were reciprocal agreements in the Consent Terms
    and that the Respondent Society committed breach of its reciprocal
    obligations under the Consent Terms. It is contended that under clause
    40 of the Consent Terms, the Society was supposed to withdraw the
    termination notice and grant unconditional NOC for additional FSI. It is
    contended that under clause 41 of the Consent Terms Respondent-

    _______________________________________________________________________________________________________

    PAGE NO. 28 OF 78
    30 MARCH 2026

    ::: Uploaded on – 30/03/2026 ::: Downloaded on – 31/03/2026 20:32:41 :::
    Neeta Sawant CARBP 354 of 2024

    Society was supposed to grant NOC for obtaining finance. Petitioner
    contends that since both the obligations under clauses 40 and 41 of the
    Consent Terms are not fulfilled by the Respondent-Society, provisions of
    Section 67 of the Contract Act are attracted in the present case and the
    Petitioner would get excused of any neglect or refusal in respect of non-
    performance of contract. Reliance is placed in this regard on judgment of
    the Apex Court in Nathulal vs. Phoolchand (supra).

    38) However, perusal of various findings recorded by the
    Arbitral Tribunal in the impugned Award would indicate that delay in
    issuance of NOCs by the Society as per clauses 40 and 41 of Consent
    Terms are raised more as pretext to escape the consequences of breaches
    of Consent Terms and that non-issuance/delay in issuance of NOC did
    not come in the way of Petitioner performing its contractual obligations
    under the Consent Terms. The Tribunal has taken note of the fact that
    while opposing Contempt Petition filed by the Society for breach of
    Consent Terms to pay various amounts, no grievance was raised by
    Petitioner about failure on the part of Respondent to issue NOC for
    additional pro-rata FSI. There is also no dispute to the factual position
    that NOC was actually issued by the Society in accordance with the
    Consent Terms. There is also nothing perverse in finding recorded in
    paragraph 166 of the Award that parties themselves understood the
    stipulation for grant of NOC for additional FSI which was not inflexible
    and that the NOC could be granted as and when needed. In any case, the
    alleged delay in issuance of NOC for additional FSI did not come in the
    way of Petitioner performing its contractual obligations.

    _______________________________________________________________________________________________________

    PAGE NO. 29 OF 78
    30 MARCH 2026

    ::: Uploaded on – 30/03/2026 ::: Downloaded on – 31/03/2026 20:32:41 :::
    Neeta Sawant CARBP 354 of 2024

    39) Petitioner’s reliance on provisions of Section 67 of the
    Contract Act does not cut any ice. Section 67 of the Contract Act
    provides thus:

    67. Effect of neglect of promisee to afford promisor reasonable facilities
    for performance.–

    If any promisee neglects or refuses to afford the promisor reasonable facilities
    for the performance of his promise, the promisor is excused by such neglect or
    refusal as to any non-performance caused thereby.

    40) Section 67 of the Contract Act excuses the promisor only in
    respect of non-performance caused by the neglect or refusal by the
    promisee to afford reasonable facilities for performance of the promise.
    The Petitioner has not been able to demonstrate as to how delay in
    issuance of the NOC came in his way of making various payments
    towards arrears of transit rent to the members of the Society. Therefore,
    reliance by the Petitioner on judgment of the Apex Court in Nathulal vs.
    Phoolchand
    (supra) does not assist the case of the Petitioner. There is
    nothing in the Consent Terms to infer that obligations were to be
    performed in a certain sequence and that therefore delay in issuance of
    NOC had impact on performance of contractual obligations by the
    Petitioner-Developer.

    41) The Arbitral Tribunal has held that MHADA’s offer letter for
    additional FSI dated 16 April 2018 was issued as per the Society’s NOC
    and that Petitioner was required to pay the requisite amount of premium
    to MHADA and/or to the Municipal Corporation. The Petitioner did not
    produce before the Arbitral Tribunal any documentary evidence about
    making of premium payment to MHADA and or to the Municipal
    _______________________________________________________________________________________________________

    PAGE NO. 30 OF 78
    30 MARCH 2026

    ::: Uploaded on – 30/03/2026 ::: Downloaded on – 31/03/2026 20:32:41 :::
    Neeta Sawant CARBP 354 of 2024

    Corporation. Thus, despite grant of NOC by Society for release of
    additional FSI, it is Petitioner-Developer who failed to avail the same by
    paying requisite premium to MHADA/MCGM. Therefore, even if it is
    assumed arguendo that there was any delay in issuing of NOC by the
    Society, ultimately it is an admitted position that on 16 April 2018
    MHADA did issue the offer letter for additional FSI and the Petitioner did
    not avail the same by making payment of premium.

    42) Petitioner has sought to question finding of fact recorded by
    Arbitral Tribunal in paragraph 170 of the Award about failure to pay
    premium by contending that an amount of Rs.3,32,31,778/- was already
    paid by Petitioner to MHADA, which was lying to the credit of
    Petitioner’s account and that a request was made by the Petitioner to the
    Respondent-Society to transfer the said credit.

    43) MHADA’s Offer Letter dated 16 April 2018 required
    Petitioner to pay premium of Rs.7,52,93,898/- in four instalments. The
    Offer Letter also required payment of offsite infrastructure charges to
    MCGM.

    44) I have gone through letter dated 31 May 2018 addressed by
    the Petitioner to the Society. The said letter talks of making of
    Application dated 16 April 2018 by Petitioner to MHADA for transferring
    the unutilized balance FSI in favour of Goregaon Pearls CHS Ltd which
    was earlier issued in favour of Siddharth Nagar Kapil Vastu CHS Ltd. for
    total additional BUA of 2410.75 sq.m. Thus, letter dated 31 May 2018 was
    not for transfer of the amount of Rs.3,32,31,778/- allegedly lying credited
    _______________________________________________________________________________________________________

    PAGE NO. 31 OF 78
    30 MARCH 2026

    ::: Uploaded on – 30/03/2026 ::: Downloaded on – 31/03/2026 20:32:41 :::
    Neeta Sawant CARBP 354 of 2024

    to Petitioner’s account against offer letter issued by MHADA for
    additional FSI subject to payment of premium. In any case, how amount
    allegedly paid by Petitioner for amalgamation of another plot, for its own
    benefits, can be treated as discharge of liability to pay the demanded
    premium by MHADA for completion of construction of building of
    Respondent Society is incomprehensible. The plea in this regard sought
    to be raised by the Petitioner is thus totally baseless.

    45) It is also admitted position that Petitioner-Developer did
    not comply with construction timelines as set out in clause 24 of the
    Consent Terms. In view of the above, I do not find any element of gross
    perversity in the findings recorded by the Arbitral Tribunal in paragraph
    174 of the Award that Petitioner-Developer committed consistent
    breaches not only of clauses of Consent Terms but also of undertakings
    given to this Court.

    46) In my view therefore, commission of breaches by the
    Petitioner of the DA and of the Consent Terms is rightly held to be
    proved by the Arbitral Tribunal. Termination of the DA, POA and of the
    arrangements under the Consent Terms by the Society is rightly upheld
    by the Tribunal. Petitioner has failed to make out any valid ground under
    Section 34 of the Arbitration Act for setting aside the said finding.

    _______________________________________________________________________________________________________

    PAGE NO. 32 OF 78
    30 MARCH 2026

    ::: Uploaded on – 30/03/2026 ::: Downloaded on – 31/03/2026 20:32:41 :::
    Neeta Sawant CARBP 354 of 2024

    AWARD OF MONITORY CLAIM IN FAVOUR OF THE SOCIETY

    47) As a direct consequence of holding the termination of the
    DA, POA and Consent Terms to be valid, the Arbitral Tribunal has
    awarded monitory claim in the sum of Rs. 7,08,53,695.03/ in Society’s
    favour. The amount comprises of Rs. 55,58,211/- towards legal costs,
    Architect’s fees and miscellaneous costs incurred by the Society, which
    have been duly proved by the Society before the Tribunal. Society’s claim
    for Rs.3,72,24,290/- was towards the admitted liability of the Petitioner
    under the consent terms, which sum was agreed to be paid towards
    arrears of transit rent. The Petitioner had also agreed under the consent
    terms to pay interest @15% per annum under the consent terms and
    accordingly the Tribunal has awarded interest of Rs. 2,80,71,194.03
    towards interest. Thus, award of monitory claim in the sum of Rs.
    7,08,53,695.03 cannot be faulted. Society’s claim for compensation for
    mental harassment is rejected by the Arbitral Tribunal. No submissions
    are canvassed before me about any error in award of the said amount.
    Petitioner’s main plea before me is that the termination of the DA, POA
    and the consent terms is invalid and once the said contention is rejected,
    award of monitory claim in favour of the Society will have to be
    necessarily upheld.

    _______________________________________________________________________________________________________

    PAGE NO. 33 OF 78
    30 MARCH 2026

    ::: Uploaded on – 30/03/2026 ::: Downloaded on – 31/03/2026 20:32:41 :::
    Neeta Sawant CARBP 354 of 2024

    ENFORCEABILITY OF CONTRACTUAL CLAUSE DENYING COMPENSATION
    /DAMAGES

    48) Petitioner raised a counterclaim for losses and damages
    against the Society. The damages were sought both by way of
    reimbursement of expenses incurred as well as claim for loss of profits.
    Under Clause 22 of the DA, parties agreed specifically that the developer
    will have no right to claim damages or compensation from the society.
    Under clause 22 of the DA, it was agreed thus :

    22. The Developers agree to complete the total re-construction work within a
    period of 22 months from the date of receipt of Commencement Certificate. In
    the event of the Developers failing to complete the re-construction work
    within the stipulated period of 22 months, then the Developers will have to
    pay a penalty of Rs.1,00,000/- per month of delay to the Said Society. In
    addition to this the Developers shall pay to each of the Members/allottees Rs.

    22000/- (Rupees Twenty-Two Thousand Only) per month as compensation
    towards permanent alternate accommodation, until the Member is put in
    possession of the Permanent Alternate Accommodation in the said New
    Building. However if the developers extended period permitted with penalty
    after the stipulated 22 months for completion of the reconstruction work will
    be only for 3 months. After expiry of these 3 months if the Developer has
    yet failed to complete the entire building R.C.C. work and the external
    and internal plastering work of the Building’s (that is completed with
    entire brick work), then upon such event the said Society shall be at
    liberty to terminate this agreement and take over all rights in the said
    project and appoint a new Developer of its choice to complete the
    reconstruction work. In such a case, the Developers will have no right to
    claim any damages/compensation from the said Society. The Developers
    shall also forego it’s right to sell the flats/ commercial premises which are part
    of the saleable portion of the flats after proving the existing members 60 flats
    in the new building.

    (emphasis added)

    49) Thus, clause 22 of the DA envisaged non-entitlement of the
    developer to claim any damages or compensation upon society

    _______________________________________________________________________________________________________

    PAGE NO. 34 OF 78
    30 MARCH 2026

    ::: Uploaded on – 30/03/2026 ::: Downloaded on – 31/03/2026 20:32:41 :::
    Neeta Sawant CARBP 354 of 2024

    terminating the agreement and taking over rights of the project and
    appointing a new developer to complete reconstruction in the event of
    the developer not completing the project within 3 months’ extension.
    The developer has also agreed to forego his right to sell the units falling
    in sale component in the event of termination of the DA. Thus, clause 22
    seeks to deny damages or compensation to the developer in the event
    developer committing breach of the DA. In the present case, the Arbitral
    Tribunal has upheld termination of DA by the Society by holding that
    Petitioner-developer has committed breaches, both of DA as well as of
    the Consent Terms. Therefore, the Petitioner-developer is held not
    entitled to damages or compensation by the Arbitral Tribunal as per
    clause 22 of the DA.

    50) Petitioner has sought to question enforceability of clause 22
    of the DA submitting that the contractual stipulation which bars the
    remedy of the party of seeking damages is unenforceable.

    51) The issue for consideration is whether the Arbitral Tribunal
    could have awarded damages or compensation in favour of the Petitioner
    contrary to clause 22 of the DA. Arbitrator is a creature of contract and
    cannot travel beyond the contractual terms. Under Section 28 of the
    Arbitration Act, the Tribunal needs to have regard to the contractual
    terms while making an award. For holding that it is bound by the
    contractual terms and cannot travel beyond the same, the Arbitral
    Tribunal has relied on judgment of this Court in Board of Control of

    _______________________________________________________________________________________________________

    PAGE NO. 35 OF 78
    30 MARCH 2026

    ::: Uploaded on – 30/03/2026 ::: Downloaded on – 31/03/2026 20:32:41 :::
    Neeta Sawant CARBP 354 of 2024

    Cricket India vs. Deccan Chronicle Holdings Ltd. 26. The judgment of the
    Apex Court in Steel Authority of India Ltd. versus. J.C. Budharaja
    (supra) also lays down the same proposition.

    52) In the present case, the Petitioner-developer has
    specifically agreed not to claim damages or compensation as well as to
    forego its right to sell units in sale component upon termination of
    contract due to breaches committed by it. Therefore the tribunal could
    not have awarded claim for damages/compensation in ignorance of
    clause 22. However it is Petitioner’s case that clause 22 is unenforceable
    as it puts unreasonable restrictions. Mr. Narula has relied on judgment of
    the Apex Court in Asian Techs Limited (supra) in support of his
    contention that any clause in the contract which seeks to deny damages
    to party is contrary to the provisions of Sections 64 and 73 of the
    Contract Act. In case before the Apex Court, the delay in execution of the
    contract was solely accountable to the respondents therein. Though the
    appellant therein was not willing to execute work beyond the contract
    period, the respondent therein gave assurance to the appellant to
    continue the work with a promise that rates would be decided across the
    table once the appellant went ahead with the work. It is in the light of
    these peculiar circumstances that the Apex Court held that Clause 11(C)
    of the contract did not come in the way of the arbitrator awarding
    amount for work done beyond the contract period. Reliance by Mr.
    Narula on judgment of the Apex Court in Board of Trustees for the Port
    of Calcutta is also inapposite. The issue before the Apex Court was

    26
    2021 SCC OnLine Bom 834
    _______________________________________________________________________________________________________

    PAGE NO. 36 OF 78
    30 MARCH 2026

    ::: Uploaded on – 30/03/2026 ::: Downloaded on – 31/03/2026 20:32:41 :::
    Neeta Sawant CARBP 354 of 2024

    about arbitrator’s power to award interest pendente lite in the light of
    clause in the contract prohibiting the Commissioner from granting
    interest on the amount of delayed payment to the contractor. The Apex
    Court held that the clause, upon strict construction, prohibited only the
    Department from granting interest but did not prohibit Arbitrator from
    granting interest.

    53) Mr. Narula has also strenuously relied on judgment of the
    Delhi High Court in MBL Infrastructures in support of his contention
    that clauses in the contract which restrict right of the parties in claiming
    damages is a restrictive clause defeating the provisions of Sections 55
    and 73 of the Contract Act. The case before the Delhi High Court
    involved performance of a contract for construction of Metro Station.
    Clause-8.3 of the General Conditions of Contract (GCC) provided the
    remedy of only extension of time in the event of delay. The Arbitral
    Tribunal had held that Clause 8.3 of the GCC did not provide for
    compensation to the Contractor by way of damages. The Delhi High
    Court disagreed with the arbitrator’s finding and held that there was
    delay on the part of the Respondent therein to complete the project and
    the termination of the contract was wrongful. The Delhi High Court
    further held
    that the Respondent therein did not grant extension of time
    as per Clause 8.3 of the GCC before proceeding to terminate the contract.
    It is in the light of these peculiar facts that the Delhi High Court held in
    para-46 of the judgment that a clause in the contract not providing for
    remedy of damages is against public interest as it hindered the smooth
    operation of commercial transaction.

    _______________________________________________________________________________________________________

    PAGE NO. 37 OF 78
    30 MARCH 2026

    ::: Uploaded on – 30/03/2026 ::: Downloaded on – 31/03/2026 20:32:41 :::
    Neeta Sawant CARBP 354 of 2024

    54) Reliance is also placed on behalf of the judgment of this
    Court in Regus South Mumbai Business Centre (supra) in which the
    issue was about correctness of award of damages by the arbitrator in the
    light of contractual clause in the Agreement providing for either
    termination or conversion of arrangement of running of business centre
    into a leave and license agreement. In the case before this Court there
    was no specific clause in the contract for non-payment of compensation
    or damages. Award of damages was sought to be criticised by the
    Petitioner therein contending that the clause provided for only two
    consequences of termination of Agreement and vacation of premises or
    conversion of agreement into leave and license and that directing the
    third consequence in the form of damages by the Arbitrator was like
    rewriting the terms of contract. This Court disagreed with the said
    contention and upheld award of damages. However in the present case,
    there is direct contractual clause No. 22 disentitling the Petitioner of
    damages or compensation in the event of termination of contract by the
    society.

    55) Petitioner has also relied on judgment of this Court in
    Mumbai Metropolitan Region Development Authority Vs. Mumbai
    Metro One Pvt Ltd.
    (supra) in which again this Court noticed that
    though the contract provided for extension of concession period in the
    event of delay by MMRDA to provide the Right of Way, there was no
    specific prohibition in the contract for awarding damages.

    _______________________________________________________________________________________________________

    PAGE NO. 38 OF 78
    30 MARCH 2026

    ::: Uploaded on – 30/03/2026 ::: Downloaded on – 31/03/2026 20:32:41 :::
    Neeta Sawant CARBP 354 of 2024

    56) Thus, all the judgments sought to be relied upon by the
    Petitioner can be distinguished on account of a specific clause in the DA
    disentitling the Petitioner from raising a claim for compensation or
    damages. On the other hand, judgments of the Apex Court in Associated
    Engineering Co.
    (supra) and Union of India vs. L&T (supra) hold
    contractual clauses for denial of compensation or interest to be
    enforceable.
    The judgment of Division Bench of this Court in Vilayati
    Ram Mittal
    (supra) also holds contractual clause for denial of
    compensation to be enforceable and goes a step further by holding that
    the arbitrator is bound by such clause and cannot travel beyond the
    same.

    57) In my view, a clause in the redevelopment agreement for
    denial of damages or compensation to the developer can be enforced in
    law because of the peculiarity of the contract. In a redevelopment
    agreement, the developer undertakes the responsibility of rehousing the
    society members by demolishing the old building and by constructing a
    new one. In return, the developer secures right to sell the additional
    constructed units to recoup the expenditure and to earn profits. He has
    the responsibility of praying transit rent to the society members in the
    interregnum. Developer in an agreement for redevelopment does not
    secure ownership in the land and the Society continues to remain the
    owner. He has the primary responsibility of providing new houses to the
    members. His right to earn profits in the project crystallizes only after he
    fulfills the obligations of paying transit rent and putting back the society
    members in possession of reconstructed flats. If the developer fails to

    _______________________________________________________________________________________________________

    PAGE NO. 39 OF 78
    30 MARCH 2026

    ::: Uploaded on – 30/03/2026 ::: Downloaded on – 31/03/2026 20:32:41 :::
    Neeta Sawant CARBP 354 of 2024

    perform the primary obligations, his right to earn profits by selling the
    flats remains imperfect. Therefore once the developer commits breach of
    obligation to provide constructed flats/units to the society members and
    once the DA is terminated on that count, the right of the developer to
    earn profits from the project continues to remain imperfect. In absence
    of right to make profits in the project, the developer cannot seek
    damages/compensation from the society. This is a reason why if the
    developer agrees not to claim compensation or damages in the event of
    termination of contract by the Society due to his defaults, such
    contractual clause would be enforceable in law.

    58) Also in the present case, the Petitioner has admittedly failed
    to deliver possession of new flats to the members and has failed to pay
    the transit rent. Commission of breaches by the Petitioner both of the
    DA and of the consent terms is established. The termination of the DA is
    on account of defaults committed by the Petitioner. Therefore, even
    going by the provisions of Section 73 of the Contract Act, Petitioner is
    otherwise not entitled to claim any compensation or damages due to
    termination of the DA. In my view therefore the Arbitrator has rightly
    denied the counterclaim of the Petitioner for damages. Denial of claim
    for compensation and damages is justified both on account of provisions
    of Section 28 of the Arbitration Act under which the Arbitrator is bound
    to give effect to clause 22 of the DA as well as in accordance with
    provisions of Section 73 of the Contract Act, since termination of the DA
    is attributable solely to the acts of the Petitioner.

    _______________________________________________________________________________________________________

    PAGE NO. 40 OF 78
    30 MARCH 2026

    ::: Uploaded on – 30/03/2026 ::: Downloaded on – 31/03/2026 20:32:41 :::
    Neeta Sawant CARBP 354 of 2024

    RESTORATION OF BENEFITS RECEIVED UNDER THE TERMINATED CONTRACT

    59) In addition to the claim for compensation/damages,
    Petitioner also sought return of the amounts spent by it in the project.
    As against the claim for compensation/damages under Section 73 of the
    Contract Act, the claim for restoration of benefits is traceable to
    provisions of Section 64. Under Section 64 of the Contract Act, the party
    rescinding a voidable contract is bound to restore the benefits, which he
    has received from another party to such contract. Section 64 of the
    Contract Act provides thus:

    64. Consequences of rescission of voidable contract.–

    When a person at whose option a contract is voidable rescinds it, the other
    party thereto need not perform any promise therein contained in which he is
    promisor. The party rescinding a voidable contract shall, if he have received
    any benefit thereunder from another party to such contract, restore such
    benefit, so far as may be, to the person from whom it was received.

    60) Though Section 64 of the Contract Act uses the word
    ‘voidable contract’, the law is well settled that provisions of Section 64
    apply even when a valid contract is rescinded. Section 64 of the Contract
    Act also applies to contracts that are initially valid but are rendered
    voidable at the option of the injured party due to a breach and is
    subsequently rescinded. Mr. Narula has relied on judgment of Privy
    Council in Muralidhar Chatterji (supra) in which the Privy Council has
    discussed the effect of provisions of Sections 64 and 65 of the Contract
    Act. The Privy Council has held that Section 64 applies even to cases

    _______________________________________________________________________________________________________

    PAGE NO. 41 OF 78
    30 MARCH 2026

    ::: Uploaded on – 30/03/2026 ::: Downloaded on – 31/03/2026 20:32:42 :::
    Neeta Sawant CARBP 354 of 2024

    where a valid contract is rendered voidable by wrongful act of a party
    thereto and which has been rescinded by the opposite party. Thus,
    Section 64 of the Contract Act applies even to a situation where a
    contract is valid, but is rendered voidable on account of breaches
    committed by a party to contract and the injured party terminates the
    same. Thus even if the contract is terminated on account of breaches
    committed by a party, such party is still entitled to claim restoration of
    benefits received by the injured party under Section 64 of the Contract
    Act. Since termination is due to breaches committed by a party and
    though such party may be liable to pay compensation to the injured
    party under Section 73 of the Contract Act, he can nonetheless seek
    restoration of benefits received by the injured party under part
    performance of the contract.

    61) Section 64 of the Contract Act provides for restoration of
    ‘such benefit’ which a party rescinding the contract has received from
    another party to the contract. The issue for consideration therefore is
    whether various expenses incurred by the Petitioner-developer in the
    project can be treated as ‘benefits’ received by the Respondent-Society
    which it must return under the provisions of Section 64 of the Contract
    Act. According to the Petitioner, the benefits received by the Society
    within the meaning of Section 64 of the Contract Act are as under :

             (i)     rent paid to members of the society
             (ii)    construction costs incurred by the Petitioner.
    

    (iii) amounts spent by the Petitioner for procurement of FSI.

    _______________________________________________________________________________________________________

    PAGE NO. 42 OF 78
    30 MARCH 2026

    ::: Uploaded on – 30/03/2026 ::: Downloaded on – 31/03/2026 20:32:42 :::
    Neeta Sawant CARBP 354 of 2024

    (iv) amount of Rs.2,50,00,000/-adjusted by the Society out of
    amount encashed under the bank guarantee towards benefit
    of extra FSI.

    62) In its counterclaim, the Petitioner-developer claimed from
    the Society three amounts of Rs. 30,68,54,552/- (Exh.2), Rs.
    118,39,97,856/- (Exh.3) and Rs. 29,09,70,826/-(Exh.4). The amount of
    Rs.30,68,54,552/- were branded ‘restoration of benefits’ in para-20 of the
    counterclaim, which reads thus :

    20) The Respondent submits that Claimant Society and its members have
    received various monetary benefits which are enumerated at Exhibit-2 herein
    under the subject Development Agreement and Consent Terms. The Claimant
    Society is bound to return the various amounts to the tune of Rs.30,68,54,552/-

    as mentioned in Exhibit-2 hereto under the relevant provisions of the Contract
    Act
    governing restoration of Benefit given by one party to another party under
    a Contract.

    63) The breakup of the amount of Rs. 30,68,54,552/- in Exhibit-
    2 to the counterclaim was set out by the Petitioner as under:

    SR No Particulars of Claim Amount

    1. Monetary Benefits Received under the Subject
    Development Agreement by the Claimant Society and
    Members from the Respondent
    (A) Benefit received under Clause 10.1.a,c,d Agreement -of Rs. 20,43,52,985/-

    Development Agreement- i.e. Rent, l.e Corpus and
    Brokerage(paid from 2006 till execution of Consent Term)
    (This Includes the increased rent paid)
    TOTAL Rs Rs. 20,43,52,985/-

    2. Monetary Benefits received under the Subject Consent
    Terms by the Claimant Society and Members from the
    Respondent.

    Benefit received under Clause 7 of Consent Terms (Amount Rs. 2,50,00,000/-
    of bank -guarantee adjusted towards arrears of rent)
    Benefit received under Clause 8A of Consent Terms. Rs. 1,00,00,000/-

    _______________________________________________________________________________________________________

    PAGE NO. 43 OF 78
    30 MARCH 2026

    ::: Uploaded on – 30/03/2026 ::: Downloaded on – 31/03/2026 20:32:42 :::
    Neeta Sawant CARBP 354 of 2024

    Benefit received under Clause 8 of Consent Terms. Rs. 24,00,000/-

    Benefit received under Clause 8 of Consent Terms. Rs. 7,00,000/-
    Benefit received under Clause 8 of Consent Terms. Rs. 17,00,000/-
    Benefit received under Clause 8B of Consent Terms. Rs. 1,00,00,000/-
    Benefit received under Clause 8F of Consent Terms. Rs. 16,39,422/-
    Benefit received under Clause 44A and C of Consent Terms Rs. 29,30,000/-
    and Minutes of order dated 6th March, 2018
    Benefit received under Clause 44A and C of Consent Terms Rs. 29,30,000/-
    and Minutes of order dated 6th March, 2018
    Benefit received-under Clause 8C and. D of Consent Terms Rs. 1,72,72,145/-
    and Minutes of order dated 6th March, 2018
    Benefit received under Clause 44A and C of Consent Terms Rs. 29,30,000/-
    and Minutes of order dated 6th March, 2018
    Benefit received under Clause 9 of Consent Terms Rs. 2,50,00,000/-

      B.        TOTAL Rs.                                                             Rs. 9,95,71,567/-
                Total Monetary Benefits (A) plus (B)                                  Rs. 30,68,54,552/-
                                                                                      (Rupees Thirty Crores
                                                                                      Sixty Eight Lakhs, Fifty
                                                                                      Four Thousand, Five
                                                                                      Hundred and Fifty Two
                                                                                      Only)
                ALONGWITH
    

    Further interest @ 12% per annum from 1st November,
    2018, till payment and/or realization on the above amount.

    64) The amount of Rs. 118,39,97,856/- was indicated in Exhibit 3
    to the counterclaim as the expenses incurred by the Petitioner, whereas
    the amount of Rs.29,09,70,826/- was indicated in Exhibit-4 as the loss of
    profits on sale of 75 flats. Para-21 of the counterclaim in this regard
    reads thus:

    21) In addition to the above, the Respondent further submits that the
    Respondent has suffered various losses/damages on account of the Purported
    Termination of the subject Development Agreement and Consent Terms as
    enumerated in Exhibit-3 and 4 hereto on account of expenses incurred for the
    development of the subject property till date, loss of profit and loss of
    reputation. The Claimant Society is hence bound and liable to pay to the
    Respondent the aforesaid Amount of Rs.118,39,97,856.- as damages in lieu of
    specific performance in the event the Arbitral Tribunal upholds the
    _______________________________________________________________________________________________________

    PAGE NO. 44 OF 78
    30 MARCH 2026

    ::: Uploaded on – 30/03/2026 ::: Downloaded on – 31/03/2026 20:32:42 :::
    Neeta Sawant CARBP 354 of 2024

    Termination of the Subject documents alongwith damages for Loss of
    Reputation.

    65) So far as the counterclaim for Rs. 29,09,70,826/- towards
    loss of profits on sale of 75 flats is concerned the same was clearly in the
    nature of compensation within the meaning of Section 73 of the
    Contract Act and I have already upheld denial of any compensation to
    the Petitioner both on account of clause 22 of the DA as well as on
    account of termination being attributable to breaches committed by the
    Petitioner. So far as the counterclaim for expenses of Rs. 118,39,97,856/-
    is concerned, the breakup of the same was provided by the Petitioner in
    Exhibit-3 as under:

    SR No Particulars of Claim Amount
    Expenses incurred on Construction Till Date Rs. 18,09,57,496/-
    Expenses Incurred on Project – Payment to Rs. 14,37,35,485/-

              MHADA, MCGM, Stamp Duty
              Onsite Exp (Admin and Sales)                               Rs. 30,40,09,774/
              Surrender of tenements                                     Rs. 24,24,40,549/-
    

    Expenses incurred for Litigation Proceedings Rs. 60,00,000/-

              Rent and Corpus                                            Rs. 30,68,54,552/-
              Total                                                      Rs. 118,39,97,856/-
                                                                         Rupees One Hundred
                                                                         and Eighteen Crores,
                                                                         Thirty Nine Lakhs,
                                                                         Ninety Seven
                                                                         Thousand, Eight
                                                                         Hundred and Fifty Six
                                                                         Only)
                                                                         ALONGWITH
                                                                         Further interest @ 12%
                                                                         per snnum from 1st
                                                                         November, 2018 till
                                                                         payment and/or
                                                                         realization on the above
                                                                         amount.
    

    _______________________________________________________________________________________________________

    PAGE NO. 45 OF 78
    30 MARCH 2026

    ::: Uploaded on – 30/03/2026 ::: Downloaded on – 31/03/2026 20:32:42 :::
    Neeta Sawant CARBP 354 of 2024

    66) By relying on pleadings in Para 20 and 21 of the
    counterclaim, Mr. Khandeparkar has contended that only the claim for
    Rs. 30,68,54,552/- in Exhibit-2 was for ‘restoration of benefits’, whereas
    the Petitioner itself chose to claim the expenditure of Rs. 118,39,97,856/-
    incurred in the costs of construction and purchase of FSI as
    ‘compensation’ in para 21 of the counterclaim. I have already
    reproduced paras-20 and 21 of the counterclaim and Exhibits-2 and 3
    relating to particulars of claim for Rs.30,68,54,552/- and Rs.
    118,39,97,856/-. In para-20 of the counterclaim, the Petitioner claimed
    amount of Rs.30,68,54,552/- towards ‘restoration of benefits’. As against
    this, two amounts of Rs.118,39,97,856/- indicated in Exhibit-3 and Rs.
    29,09,70,826/- indicated in Exhibit-4 to the counterclaim were pleaded
    jointly as ‘expenses incurred for development of the subject property till
    date, loss of profits and loss of reputation’. In para 21 of the counterclaim,
    the amount of Rs. 118,39,97,856/- was also pleaded as ‘damages in lieu of
    specific performance’. It is on account of these pleadings that Mr.
    Khandeparkar has contended that none of the amounts indicated in Para
    21 or in Exhibit-3 can be treated as amounts towards claim for return of
    ‘benefit’ under Section 64 of the Contract Act. I am unable to agree.
    Merely because the Petitioner split the two amounts in Exhibits 2 and 3
    and in Para 20 and 21 of the counterclaim, the same would not mean that
    the claim for return of expenditure incurred in the project can be treated
    as a claim for compensation. Even in Para 21 of the counterclaim, the
    Petitioner has described the amount of Rs. 118,39,97,856/- as ‘expenses
    incurred’. If any of those expenses allegedly incurred by the Petitioner in

    _______________________________________________________________________________________________________

    PAGE NO. 46 OF 78
    30 MARCH 2026

    ::: Uploaded on – 30/03/2026 ::: Downloaded on – 31/03/2026 20:32:42 :::
    Neeta Sawant CARBP 354 of 2024

    the project forms part of the ‘benefit’ received by the society, it would be
    unfair to treat such claim as the one for compensation, when in law the
    claim is actually for return of benefits under Section 64. I would
    therefore prefer to go by the contents of the claim rather than giving
    importance to the form or nomenclature. Therefore the contention of
    Mr. Khandeparkar that none of the amounts under Para 21 and Exhibit-3
    to the counterclaim could have been adjudicated as ‘benefits’ deserves
    rejection.

    67) I now proceed to consider whether the claim of the
    Petitioner for restoration of benefits under Section 64 of the Contract
    Act could have been awarded. Petitioner’s claim for restoration of
    benefits is essentially in three parts as under :

    (i) restoration of the amount of transit rent paid to the members
    of the society.

    (ii) restoration of expenses incurred in construction of the
    building.

    (iii) restoration of amounts paid to MHADA and MCGM for
    purchase of additional FSI and TDR.

    68) Before considering the claim of the Petitioner for
    restoration of benefits under each head, it is first necessary to decide
    whether Petitioner’s claim for restoration of benefits can at all be
    considered in the light of the contractual stipulations agreed between
    the parties. I have already held that a contractual stipulation in the
    redevelopment agreement denying compensation/damages to the

    _______________________________________________________________________________________________________

    PAGE NO. 47 OF 78
    30 MARCH 2026

    ::: Uploaded on – 30/03/2026 ::: Downloaded on – 31/03/2026 20:32:42 :::
    Neeta Sawant CARBP 354 of 2024

    developer upon termination of contract by the society is enforceable in
    law. The Petitioner however contends that its claim for restoration of
    benefits under Section 64 of the Contract Act is different and distinct
    than the claim for compensation under Section 73. I am inclined to
    accept the contention. Under Section 73 of the Contract Act, when a
    contract is broken, the insured party is entitled to receive from the party
    who has broken the contract, compensation for such loss or damage
    caused to him. What is payable under Section 73 of the Act is
    ‘compensation for such loss or damage caused’. On the other hand, what
    is contemplated under Section 64 of the Contract Act is restoration of
    ‘such benefits’ which are received by the party rescinding the contract
    from the opposite party. No doubt, provisions of Sections 73 and 64 may
    concurrently apply in relation to termination of the contract. When a
    party to contract commits breach thereof, the opposite party can rescind
    the contract and claim compensation under Section 73. At the same
    time, if a party rescinding the contract has received any benefit under
    the contract, such party is liable to restore the benefit under Section 64.

    In a given case, therefore the claim for restoration of benefit can be set
    off against the claim for compensation under Section 73 of the Act.

    69) Mr. Khandeparkar has sought to question the distinction
    between claims for ‘compensation’ and for ‘restoration of benefits’ and
    contends that both ultimately are the same. He contends that the claim
    for restoration of benefits under Section 64 of the Contract Act is in the
    nature of restitutionary compensation. I am unable to agree, for the
    reasons indicated above. The claim under Section 73 of the Contract Act

    _______________________________________________________________________________________________________

    PAGE NO. 48 OF 78
    30 MARCH 2026

    ::: Uploaded on – 30/03/2026 ::: Downloaded on – 31/03/2026 20:32:42 :::
    Neeta Sawant CARBP 354 of 2024

    is by an injured party whereas the claim under Section 64 is by the party
    who is responsible for termination of the contract. In what form the
    return of benefits is granted is immaterial since the concepts under
    Sections 64 and 73 of the Act are entirely different. However, Mr.
    Khandeparkar has essentially attempted to fit the claim for restoration of
    benefits under Section 64 into ‘compensation’ so that the same can be
    denied under clause 22 of the DA. The attempt is however misplaced.
    Developer suffering losses and claiming compensation due to wrongful
    termination is a different concept than claim for return of benefits
    received by the society. Claim for compensatory damages may comprise
    of several components such as every penny spent in the project, loss of
    opportunity to make profits, claim for idling of manpower/machinery,
    etc. However, every amount spent by the developer may not necessarily
    be the benefit revoiced by the society. To illustrate, the amounts spent
    by the developer on his advocates fees, stamp duty, registration charges,
    running of sales office, security, etc would not enure to the benefit of the
    society. On the other hand if the developer spends amount of anything
    which is enjoyable and is enjoyed by the society fully, that thing would
    constitute a benefit for the society. Thus, the claim for return of benefits
    enjoyed by the society cannot be treated as the claim for compensation.
    Mr. Khandeparkar’s reliance on judgment of the Single Judge of Madras
    High Court in E-merge Tech Global Services P Ltd. (supra) in support of
    contention of claim for restoration of benefits being claim for
    compensation is inapposite. The Madaras High Court has held in paras-
    24 and 25 of the judgment as under:

    _______________________________________________________________________________________________________

    PAGE NO. 49 OF 78
    30 MARCH 2026

    ::: Uploaded on – 30/03/2026 ::: Downloaded on – 31/03/2026 20:32:42 :::
    Neeta Sawant CARBP 354 of 2024

    24. The learned counsel for the Plaintiff submitted that the Plaintiff is entitled
    to damages under the head of compensatory damages as also under the head of
    restitutionary damages by way of an account of profits. To test this contention,
    it is necessary to examine the concepts of compensatory and restitutionary
    damages.

    25. Compensatory damages are awarded to redress the loss suffered by an
    aggrieved party. The restitutionary damages are more in the nature of
    directing the Defendants to disgorge the benefit accrued in his favour due to
    unjust enrichment at the expense of the Plaintiff. Compensatory damages
    normally present themselves with difficulties associated in computing a
    reliable assessment of the loss caused to the plaintiff. Sometimes, the loss is of
    such nature that an accurate assessment may well be out of the question.

    70) The Madras High Court in E-merge Tech Global Services P
    Ltd. has thus considered the difference between the concepts of
    compensatory and restitutionary damages and has held that a party
    cannot be entitled to claim both compensatory damages, as well as
    restitutionary damages in ordinary circumstances. In case before the
    Madras High Court, the defendant therein was employed with the
    plaintiff. The defendant tendered his resignation but the plaintiff
    continued his services on consultancy basis. The defendant thereafter
    requested the plaintiff to relieve him from consultancy assignment, and
    this is how parties parted ways. The defendant thereafter floated a new
    company in which a client of the plaintiff was a subscriber. It was
    plaintiff’s case that defendant was running the business of the company
    on identical business model as that of the plaintiff and plaintiff’s main
    customer had become part of defendant’s company. Plaintiff filed a Suit
    based on non-solicit, non-compete and confidentiality clauses. The High
    Court found that the Defendant committed breach of non-solicit, non-
    compete and confidentiality clauses and then proceeded to consider
    _______________________________________________________________________________________________________

    PAGE NO. 50 OF 78
    30 MARCH 2026

    ::: Uploaded on – 30/03/2026 ::: Downloaded on – 31/03/2026 20:32:42 :::
    Neeta Sawant CARBP 354 of 2024

    plaintiff’s claim for damages. Plaintiff had raised a claim for damages to
    the tune of Rs.2 crores on the ground of unjust enrichment and had also
    sought restitution of disgorgement of gains unlawfully made by the
    Defendants. In the context of the above factual situation, the Single
    Judge of the Madras High Court held that ordinarily plaintiff cannot
    claim both compensatory damages as well as restitutionary damages
    unless an exceptional case is made out. While doing so, the Madras High
    Court distinguished the concepts of restitutionary damages and
    compensatory damages. Thus, before the Madras High Court, there was
    no claim for restitution under Section 64 of the Contract Act. The case
    did not involve rescission of the contract by one party, nor raising of a
    claim by opposite party for restoration of the benefits. The judgment of
    Madras High Court rendered in the peculiar facts of that case cannot be
    read to mean that in every case a claim for restoration of benefits under
    Section 64 of the Contract Act would be a claim for compensation under
    Section 73 of the Act.

    71) The Madras High Court in Mundakath Mathu (supra), on
    which reliance is placed by Mr. Narula, has held, by referring to the
    English Judgment in Clough Vs. London and North Western Rail Co.27
    and to the commentary in Pollock and Mulla’s Contract Act that the
    rule of restitution under Section 64 and 65 of the Contract Act is based
    on the rule of equity and good conscience as no man can treat at once
    the contract as avoided and retain the monies or other advantages
    received by it under the contract.
    Reliance by Mr. Narula on judgment of

    27
    (1871) LR 7 Exch 26
    _______________________________________________________________________________________________________

    PAGE NO. 51 OF 78
    30 MARCH 2026

    ::: Uploaded on – 30/03/2026 ::: Downloaded on – 31/03/2026 20:32:42 :::
    Neeta Sawant CARBP 354 of 2024

    Kerala High Court in Chacko & Ors. (supra) is also apposite in which it is
    held that the ‘benefit’ envisaged under Section 64 of the Contract Act
    means only the benefit received under the transaction directly
    contemplated by it and not any future benefits by any speculative or
    non-speculative investment of that benefit.

    72) Thus, this Court is unable to treat the Petitioner’s
    counterclaim for return of benefits as a claim for compensation which
    can be covered by Clause 22 of the DA. Clause 22 of the DA applies only
    to the right of the Petitioner to claim damages or compensation when
    the DA is terminated on account of commission of breaches by it. Thus,
    what can be denied under Clause 22 is only damages or compensation for
    breaches under Section 73 of the Contract Act. The same would not
    apply to Society’s obligation to return the benefits under Section 64 of
    the Act.

    73) Mr. Khandeparkar has contended that various clauses of the
    DA, when read together, disentitles the Petitioner from raising a claim
    for restoration of benefits under Section 64 of the Contract Act. It would
    therefore be apposite to reproduce the relevant clauses of the DA relied
    upon by him. Under Clause 9(h) of the DA, it was agreed between the
    parties that the Society shall have the right to exploit all the rights of the
    Petitioner arbitrarily in case of default on its part. Clause 9(h) of the DA
    reads thus :

    The Developers shall execute the entire redevelopment project as
    contemplated herein solely in the name of the society including and not
    limited to obtaining permissions for purchasing T.D.R. and/or tit-bit land,
    _______________________________________________________________________________________________________

    PAGE NO. 52 OF 78
    30 MARCH 2026

    ::: Uploaded on – 30/03/2026 ::: Downloaded on – 31/03/2026 20:32:42 :::
    Neeta Sawant CARBP 354 of 2024

    payment of premium etc. or any other right to give full effect to this
    agreement. The society shall have the right to exploit these rights and
    liberties arbitrarily in case default on the part of the Developer.

    (emphasis added)

    74) Clause 10(8) of the DA provided for termination of the
    contract and for forfeiture of amounts spent by the developer in the
    event of failure to procure commencement certificate within 3 months of
    handing over possession of flats by the society members. Clause 10(8) of
    the DA reads thus:

    Notwithstanding anything contained herein if, within three months of handing
    over vacant possession by the Members of the flats in the Original Building to
    the Developers, the Commencement Certificate is not received by the
    Developers, then this agreement for re-development shall stand terminated
    and whatever amounts spent by the Developers towards obtaining F.S.I., T’D.R
    and advance payments towards Corpus Fund will be forfeited by the Said
    Society. The Society will then be at liberty to enter into agreement for re-
    development with any other Developer of its choice.

    75) Clause 22 of the DA has already been reproduced above.

    However, in the context of submission of Mr. Khandeparkar that parties
    have agreed for denial of even restitutionary benefits under Section 64,
    only relevant part of clause 22 of the DA is reproduced once again:

    22. … After expiry of these 3 months if the Developer has yet failed to
    complete the entire building R.C.C. work and the external and internal
    plastering work of the Building’s (that is completed with entire brick
    work), then upon such event the said Society shall be at liberty to
    terminate this agreement and take over all rights in the said project and
    appoint a new Developer of its choice to complete the reconstruction
    work. In such a case, the Developers will have no right to claim any
    damages/compensation from the said Society. The Developers shall also
    forego it’s right to sell the flats/ commercial premises which are part of the
    saleable portion of the flats after proving the existing members 60 flats in the
    new building.

    (emphasis added)
    _______________________________________________________________________________________________________

    PAGE NO. 53 OF 78
    30 MARCH 2026

    ::: Uploaded on – 30/03/2026 ::: Downloaded on – 31/03/2026 20:32:42 :::
    Neeta Sawant CARBP 354 of 2024

    76) Under Clause 42, the Petitioner has agreed to bear and pay
    all costs of construction, as well as of securing approvals, costs of
    acquiring additional TDR etc. Clause 42 of the DA reads thus:

    42. The Developers shall bear and pay all costs of construction including costs,
    charges and expenses of obtaining all permissions, approvals, sanctions, or
    otherwise, N.A. orders, I.O.D. and Commencement Certificate and also
    payments to the M.C.G.M. by way of deposits, security deposits, scrutiny fees,
    development charges, debris deposit, or any other charges,
    payments/remuneration to architects, engineers, contractors, labour
    contractors, suppliers of building materials, workmen, employees, security
    staff and cost of acquiring additional T.D.R. and other expenses relating to the
    development of the said plot of land.

    77) Under Clause 47, it was specifically agreed between the
    parties that under no circumstances, the Petitioner would ask for any
    amount for contribution from the society or from its members towards
    expenses for putting up the construction. Clause 47 of the DA reads thus:

    47. Under no circumstances, the Developers shall ask for any amount or
    contribution from the Society or any of its members towards expenses for
    putting up such construction.

    78) Under clause 53(iii) of the DA, parties agreed that the
    Agreement was not to be construed as partnership or joint venture and
    that the same was on Principal-to- Principal basis. Clause 53(iii) reads as
    under:

    iii. This Agreement shall not be construed as a Partnership or Joint Venture or
    Agreement of Partnership and the same shall be on Principal-to-Principal
    basis.

    _______________________________________________________________________________________________________

    PAGE NO. 54 OF 78
    30 MARCH 2026

    ::: Uploaded on – 30/03/2026 ::: Downloaded on – 31/03/2026 20:32:42 :::
    Neeta Sawant CARBP 354 of 2024

    79) After going through the above clauses relied upon by Mr.
    Khandeparkar, I am unable to read any prohibition for the Petitioner-

    Developer from claiming restoration of benefits admissible under Section
    64
    of the Contract Act. Reliance by the Respondent-Society on Clause
    9(h) of the DA does not inure to its benefit. Under Clause 9(h) of the DA,
    the Petitioner-developer agreed to execute redevelopment project solely
    in the name of the Society and Society was to become owner of all the
    purchased TDR and/or tit-bit land etc. In the event of default on the part
    of the Petitioner, Respondent-Society became entitled to ‘exploit’ those
    rights and liberties arbitrarily. The exact purport of Clause 9(h) is that in
    the event of commission of any default by the Petitioner-developer
    resulting in termination of the DA, the Society was entitled to ‘exploit’
    (meaning consume) the purchased TDR and/or the tit-bit land. This
    would essentially mean that termination of agreement would not result
    in invalidation of permissions or invalidation of the purchased TDR or
    tit-bit land. Tit-bit lands refer to non-buildable lands, often adjoining,
    which MHADA sells to the societies for increasing the total layout size.
    Thus, under clause 9(h) of the DA, the purchases of the TDR and of tit-
    bit lands was to be made by the Petitioner-developer in the name of the
    society and in the event of termination of the DA, the society was free to
    exploit the same arbitrarily. This would mean that termination of DA
    would not automatically result in loosing of title in the purchased TDR
    or tit-bit land. Vesting of the purchased TDR and tit-bit land in the
    society is a concept distinct from the concept of returning the purchase
    price of such TDR or tit-bit land. Clause 9(h) does not walk a step further

    _______________________________________________________________________________________________________

    PAGE NO. 55 OF 78
    30 MARCH 2026

    ::: Uploaded on – 30/03/2026 ::: Downloaded on – 31/03/2026 20:32:42 :::
    Neeta Sawant CARBP 354 of 2024

    and stipulate that the society shall not be liable to refund the price of
    purchased TDR or of tit-bit land.

    80) Plans are approved and construction is effected by taking
    into consideration the purchased TDR, FSI and tit-bit land. Absent
    clause 9(h), the purchased TDR and tit-bit land would have reverted to
    the Petitioner-developer upon termination of the DA rendering the
    construction illegal. Clause 9(h) would therefore protect the
    construction carried out on the basis of permissions and TDR/tit-bit land
    purchased by the Petitioner-developer and Society does not have to
    scout in the market for securing fresh permissions or to procure the TDR
    or tit-bit land once again. Clause 9(h) cannot be read to mean an
    exception to Section 64 of the Contract Act. Clause 9(h) does not provide
    that if Society terminates the contract, Petitioner-developer shall not be
    entitled to claim return of any benefits received by the Society.

    81) Clause 22 of the DA has the effect of denial of only
    compensation and does not provide for forfeiture of the expenditure
    incurred or denial of restoration of benefits received by the society.
    Clause 22 of the DA provides that ‘In such a case, the Developers will have
    no right to claim any damages/compensation from the said Society’. I have
    rejected the submission of Mr. Khandeparkar that restoration of benefits
    under Section 64 of the Contract Act is a species of
    compensation/damages as contemplated under clause 22 of the DA. Thus
    clause 22 of the DA cannot be read to mean as if the parties agreed that

    _______________________________________________________________________________________________________

    PAGE NO. 56 OF 78
    30 MARCH 2026

    ::: Uploaded on – 30/03/2026 ::: Downloaded on – 31/03/2026 20:32:43 :::
    Neeta Sawant CARBP 354 of 2024

    upon termination of the DA, the society shall be entitled to retain all the
    benefits received by it from the Petitioner.

    82) So far as reliance by the Society on clause 42 of the DA is
    concerned, the same merely poses a responsibility on the Petitioner-
    developer to bear all costs of acquiring additional TDR. This would mean
    that Petitioner was not to demand any monies from the Society or
    members for carrying out any construction or for purchase of the TDR.
    During performance of the DA, clause 42 put the responsibility of
    incurring all the expenditure inter alia for purchase of TDR, etc. on the
    developer. This does mean that after termination of the DA, Petitioner
    was prohibited from seeking return of amounts spent by him, which
    would fit in the expression ‘benefit’ used in Section 64 of the Contract
    Act. Thus clause 42 of the DA has no application in relation to
    Petitioner’s demand for restoration of benefits under Section 64 of the
    Contract Act.

    83) The Respondent-Society has also relied on clause 47 of the
    DA which prohibited the Petitioner-developer from demanding any
    money or contribution from the society or its members towards expenses
    for putting up such construction. In my view, Clause 47 is continuation
    of contractual arrangement under Clause 42 under which the Developer
    was not supposed to demand any monies or contributions from the
    Society or its members and was to bear all the costs by itself. Therefore,
    there is nothing in clause 42 or 47 which disentitles the developer from
    seeking return of benefits under Section 64 of the Contract Act.

    _______________________________________________________________________________________________________

    PAGE NO. 57 OF 78
    30 MARCH 2026

    ::: Uploaded on – 30/03/2026 ::: Downloaded on – 31/03/2026 20:32:43 :::
    Neeta Sawant CARBP 354 of 2024

    84) Society’s reliance on Clause 53(iii) of the DA again does not
    cut any ice. The said clause only provides for construction of the
    agreement as on principal-to-principal basis and not a partnership, joint
    venture or agreement of partnership. The clause only dissociates the
    Society from the business venture undertaken by the Petitioner-
    developer so as to safeguard the Society in respect of any claims made
    against the developer by third parties such as flat purchasers, financial
    institutions, Municipal Corporation etc. Clause-53 again does not
    impose any prohibition on Petitioner’s right to seek restoration of
    benefits under Section 64 of the Contract Act.

    85) Mr. Khandeparkar has also strenuously relied on clause 8 of
    the DA under which, if Commencement Certificate was not to be
    procured within 3 months of handing over possession by members, the
    DA was to stand terminated and the entire amount spent by the
    Petitioner-developer towards obtaining FSI/TDR and advance payments
    towards corpus funds was to be forfeited by the Society. However, this
    clause applies only for a period of 3 months from the date of vacation of
    possession of flats by the Society-members. No doubt, Clause 8 restricts
    the right of the developer to seek restoration of benefits under Section
    64
    of the Contract Act. Such restriction however applies only upto the
    stage of securing the Commencement Certificate. Parties thus
    consciously restricted prohibition on seeking restoration of benefits
    under Section 64 of the Contract Act only till a particular stage. This
    means that parties have consciously agreed not to restrict the right of
    the Petitioner-developer to seek restoration of benefits under Section 64

    _______________________________________________________________________________________________________

    PAGE NO. 58 OF 78
    30 MARCH 2026

    ::: Uploaded on – 30/03/2026 ::: Downloaded on – 31/03/2026 20:32:43 :::
    Neeta Sawant CARBP 354 of 2024

    after the stage of procuring Commencement Certificate. In fact, clause 8
    of the DA clearly indicates the conscious choice made by the
    Respondent-Society to restrict the prohibition on restoration of benefit
    under Section 64 only till the stage of securing the commencement
    certificate. There is no similar restriction in the DA after crossing the
    stage of commencement certificate.

    86) In fact, the above quoted clause 8 of the DA clearly destroys
    Mr. Khandeparkar’s contention that Clauses-9(h), 22, 27, 42, 47 and
    53(iii) impose prohibition on restoration of benefits. If Clauses-9(h), 22,
    27, 42, 47 and 53(iii) were sufficient to deny the restoration of benefits,
    there was no necessity to incorporate clause 8 in the DA. Therefore, the
    very factum of incorporation of clause 8 in the DA would clearly indicate
    a conscious choice made by the Society to restrict denial of restoration
    benefits only till the stage of procuring Commencement Certificate and
    not thereafter.

    87) I am therefore of the view that there is no clause in the DA
    which imposes any restriction or prohibition on Petitioner-developer
    exercising right of restoration of benefits under Section 64 of the
    Contract Act.

    88) Now I proceed to decide as to which of the claims of the
    Petitioner-developer would fit into the ambit of the expression ‘benefit’
    appearing in Section 64 of the Contract Act.

    _______________________________________________________________________________________________________

    PAGE NO. 59 OF 78
    30 MARCH 2026

    ::: Uploaded on – 30/03/2026 ::: Downloaded on – 31/03/2026 20:32:43 :::
    Neeta Sawant CARBP 354 of 2024

    WHETHER RENT PAID TO SOCIETY MEMBERS IS A ‘BENEFIT’

    89) Petitioner claimed amounts of Rs. 20,43,52,985/- towards
    rent, corpus and brokerage till execution of consent terms, Rs.
    2,50,00,000/- towards adjustment for rent made under consent terms as
    well as various other amounts payable under the consent terms. However
    since several cheques towards those amounts are dishonoured, the claim
    towards rent in Exhibit-2 is essentially of Rs. 20,43,52,985/- and Rs.
    2,50,00,000/-. However, Petitioner once again claimed amount of Rs.
    30,68,54,552/- in Exhibit-3 to counterclaim and the Arbitral Tribunal has
    criticised it for double counting of the claims towards rent.

    90) The Tribunal has considered and decided the issue as to
    whether the rent paid by the Petitioner to the members of the society
    could be treated as ‘benefit’ received under the performance of DA. The
    Tribunal had, in order dated 17 September 2018, taken a prima facie view
    while deciding the issue of interim measures that rent paid to members
    of Society could not be treated as a ‘benefit’. That interim order was
    upheld by this Court while dismissing the Appeal of the Petitioner.
    Tribunal took note of the order of this Court dated 14 December 2018
    upholding Section 17 order, in which this Court had held in para 27 as
    under :

    27. In my view, this submission of Mr. Narula overlooks the fact that the
    respondent members had agreed to redevelopment in the hope of better
    prospects and payment was made only in inducement for the members of the
    society who agreed to redevelop and vacating their homes rather than
    continue in the premises during repairs that would have to be undertaken.

    Payment of rent cannot be in any manner considered to be a “benefit”. It only

    _______________________________________________________________________________________________________

    PAGE NO. 60 OF 78
    30 MARCH 2026

    ::: Uploaded on – 30/03/2026 ::: Downloaded on – 31/03/2026 20:32:43 :::
    Neeta Sawant CARBP 354 of 2024

    facilitated the members to be housed in different premises. There is
    substantial collateral hardship that is associated shifting from one own home
    to rented premises and during the period that is to be taken for the new and
    permanent home to be constructed. The respondents are out of their homes for
    about 11 years. When they vacated their premises they were expecting to be
    back in their new homes within a reasonable period of time. Although shifting
    to rented premises may appear to be a formality to facilitate redevelopment, in
    fact it is a commitment made in anticipation of performance of the petitioners
    promises to rehouse them in permanent accommodation. While resolving to
    enter into such agreement, the members of the society, for that matter no
    home owner, would expect or tolerate delay of this nature.

    91) Though the observations made by this Court in order dated
    14 December 2018 were in the context of deciding the interim measures,
    the learned Arbitrator took note of ratio of the judgment of this Court in
    IREP Credit Capital (supra) in which it is held that the view expressed by
    a Court on legal position is binding and the stage at which the same is
    expressed is immaterial.

    92) However, independent of the observations made by this
    Court in order dated 14 December 2018, I am also of the view that the
    rent paid by the developer to the members of a cooperative society
    during the period they are made to vacate their homes for reconstruction
    of the building cannot be treated as a benefit within the meaning of
    Section 64 of the Contract Act. The vacation of flats is required to be
    undertaken by the members for the purpose of enabling the developer to
    demolish the building and to reconstruct the same. For facilitating
    demolition and reconstruction, the developer makes a commitment to
    the members to provide them transit rent for making temporary
    arrangements during the redevelopment process. It is the cost paid by
    the developer to the member for denying him opportunity to reside in
    _______________________________________________________________________________________________________

    PAGE NO. 61 OF 78
    30 MARCH 2026

    ::: Uploaded on – 30/03/2026 ::: Downloaded on – 31/03/2026 20:32:43 :::
    Neeta Sawant CARBP 354 of 2024

    his own house. The ‘benefit’ contemplated under Section 64 of the
    Contract Act must be the real benefit that accrues to the injured party
    terminating the contract, which, if retained, would constitute unjust
    enrichment for him. To illustrate, in a land sale transaction, if the
    agreement is terminated on account of delay by the purchaser in
    completing the transaction, the seller cannot retain the part
    consideration received under the Agreement and also retain ownership
    in the land. Retaining both would result in unjust enrichment for the
    seller. However, in a redevelopment contract, rent paid to the flat owners
    cannot be treated as ‘benefit’ received by them and retaining the same
    upon termination of the DA does not result in unjust enrichment for
    them. The new developer appointed to complete construction of the
    building undertakes the liability for rent from the date of execution of
    new DA and the members would not ordinarily receive rent twice for the
    same period. Therefore, in a case where the society members are not
    paid rent twice for the same period, the rent paid by the outgoing
    developer cannot constitute benefit received by them under Section 64 of
    the Contract Act. It may be an expenditure incurred by the developer,
    but the same would not constitute restitutionary benefit under Section
    64
    of the Act. If the rent is directed to be refunded to the developer
    whose DA is terminated due to defaults committed by him, it would
    tantamount to rewarding the developer for the breaches while putting
    already troubled society members into further difficulties, which is not
    the objective behind Section 64 of the Contract Act. Hence, rent paid by
    a developer to members of the society cannot be treated as a ‘benefit’
    received within the meaning of Section 64 of the Contract Act.

    _______________________________________________________________________________________________________

    PAGE NO. 62 OF 78
    30 MARCH 2026

    ::: Uploaded on – 30/03/2026 ::: Downloaded on – 31/03/2026 20:32:43 :::
    Neeta Sawant CARBP 354 of 2024

    Therefore, the Petitioner is not entitled to seek return or restoration of
    the transit rent or displacement compensation paid to the members. The
    Arbitral Tribunal has rightly rejected the counterclaim of the Petitioner
    for return of rent, corpus, brokerage etc.

    WHETHER PURCHASED FSI CAN BE TREATED AS ‘BENEFIT’ UNDER SECTION
    64 OF CONTRACT ACT

    93) Petitioner has contended that it has paid following amounts
    to the Respondent-society towards purchased FSI which is utilised and
    enjoyed by the Society:

    (i) Rs.8,18,03,435/- paid to MHADA for acquiring tit-bit land.

    (ii) Rs.20,61,150/- paid to MHADA for acquiring FSI of R.G. area.

    (iii) Rs.2,50,00,000/- adjusted by the Society against encashed bank
    guarantee towards FSI benefit.

    94) According to the Petitioner-Developer, these three amounts
    spent towards purchase of FSI must be refunded to it under Section 64 of
    the Contract Act.

    95) In my view, the counterclaim for return of all the three
    amounts of Rs.8,18,03,435/-, Rs.20,61,150/- and Rs.2,50,00,000/- would
    clearly be covered by the term ‘benefit’ under Section 64 of the Contract
    Act. The Respondent has undoubtedly utilised the FSI purchased by the
    developer. The purchase of FSI by the Petitioner was towards
    performance of the DA. As agreed in Clause 9(h) of the DA, the FSI

    _______________________________________________________________________________________________________

    PAGE NO. 63 OF 78
    30 MARCH 2026

    ::: Uploaded on – 30/03/2026 ::: Downloaded on – 31/03/2026 20:32:43 :::
    Neeta Sawant CARBP 354 of 2024

    purchased by the Petitioner is not only in the name of the Respondent-

    Society, but has become a property owned by the Respondent-Society. In
    my view therefore, the entire FSI purchased by the Petitioner-developer
    for carrying out redevelopment work of society’s building would clearly
    be a ‘benefit’ within the meaning of Section 64 of the Contract Act. Since
    the Society has decided to rescind the contract and even though
    rescission of contract by the Petitioner is found to be valid, the Society
    cannot retain the benefit of purchased FSI received under the rescinded
    contract and must return the same. Clause 9(h) ensures that the Society
    does not have to actually or physically return the FSI and can consume
    the same since the same is purchased in the name of the society. The
    clause also ensures that the construction already put up is not rendered
    illegal on account of termination of the DA. However the concept of
    ‘non-return of FSI’ is different and distinct from the concept of ‘return of
    purchase price of FSI’. While the former would be protected under clause
    9(h) of the DA, the latter is liable to be returned under Section 64 of the
    Contract Act.

    96) In my view therefore, part of the Award which rejects the
    counterclaim for return of the amounts of Rs.8,18,03,435/-,
    Rs.20,61,150/- and Rs.2,50,00,000/- is in conflict with the fundamental
    policy of Indian law. The learned Arbitrator has erroneously conflated
    the issue of return of benefits received by the Respondent-Society under
    the terminated contract with the claim for compensation for the purpose
    of application of Clause 22 of the DA. It has erroneously relied on
    judgment of Division Bench of this Court in Vilayti Ram Mittal which

    _______________________________________________________________________________________________________

    PAGE NO. 64 OF 78
    30 MARCH 2026

    ::: Uploaded on – 30/03/2026 ::: Downloaded on – 31/03/2026 20:32:43 :::
    Neeta Sawant CARBP 354 of 2024

    deals with the issue of compensation under Section 73 of the Contract
    Act and not with the issue of restoration of benefits under Section 64.
    For the same reason, reliance by Mr. Khandeparkar on judgment of the
    Apex Court in Associated Engineering Company is also inapposite as the
    said judgment
    also deals with the concept of validity of a clause in the
    contract denying compensation. Even the judgment of the Apex Court in
    Union of India vs. L & T relied on by Mr. Khandeparkar dealt with the
    issue of enforceability of a term in the contract which prohibited
    payment of interest.
    The judgment in Steel Authority of India vs. J. C.
    Budharaja
    (supra) is also an authority on the proposition of
    impermissibility for arbitrator to travel beyond the contractual clauses
    for awarding claims expressly prohibited in contractual clauses. However
    in the present case there is no prohibition of return of benefits received
    by the society in the DA. The prohibition on return of FSI was limited
    only upto the stage of procuring the commencement certificate, beyond
    which stage, there is no such prohibition. The prohibition in clause 22 is
    restricted only to claim for damages/compensation, which does not
    extend to return for benefits. Thus, part of the award which treats the
    prayer for restoration of costs of FSI purchased by the Petitioner as claim
    for damages or compensation and which denies the same is
    unsustainable.

    97) It is sought to be contended on behalf of the Respondent-
    Society that the Petitioner never raised the issue of claim of restoration
    not being covered by Clause 22 of the DA. However, perusal of written
    submissions before the Arbitral Tribunal would indicate that the

    _______________________________________________________________________________________________________

    PAGE NO. 65 OF 78
    30 MARCH 2026

    ::: Uploaded on – 30/03/2026 ::: Downloaded on – 31/03/2026 20:32:43 :::
    Neeta Sawant CARBP 354 of 2024

    Petitioner specifically urged before the Arbitral Tribunal that ‘please note
    at this juncture that at any event the Respondent has not agreed to not claim
    restitution/restoration of benefits received by the Society under the DA in
    cl.22 of the DA. Thus, the right to seek restitution under Sections 64 and 65
    of the Contract Act cannot be disallowed by the Tribunal in any
    circumstances’. Though the issue of non-applicability of clause 22 of the
    DA to claim of restitution of benefits was specifically raised by the
    Petitioner, it appears that the Arbitral Tribunal has failed to consider
    claim for restoration of benefits under Section 64 of the Contract Act on
    an independent footing and unnecessarily confused the said claim as a
    claim for compensation by applying Clause-22 of the DA.

    98) While the Arbitral Tribunal has conflated the claim for
    restoration of benefits with the claim for compensation, it has made
    certain observations in the Award as to why the cost of construction
    incurred by the Petitioner cannot be treated as ‘benefit’. The Tribunal
    has refused to treat the same as benefit by relying on the judgment of
    this Court in Borivali Anamika Niwas CHSL. The reasons for rejection of
    claim for restoration of benefits are to be found only in paras-215 and
    216 of the impugned Award, which read thus:

    215. Insofar as the restoration of the construction costs incurred by the
    Respondent Developer in putting up the building are concerned, the same also
    cannot be said to be a “benefit”. I find Mr. Khandeparkar to be justified in his
    reliance on Borivali Anamika Niwas CHSL (supra), paragraph 19 whereof reads
    as under:-

    _______________________________________________________________________________________________________

    PAGE NO. 66 OF 78
    30 MARCH 2026

    ::: Uploaded on – 30/03/2026 ::: Downloaded on – 31/03/2026 20:32:43 :::
    Neeta Sawant CARBP 354 of 2024

    “19. The mere fact that the developer has put money into the project
    cannot and does not create equity in and of itself. After all, the
    objective of the developer is not to do this for a charitable purpose. It is
    to make large financial gains. The expenditure on the project is not,
    therefore, a handout to the society members. It is very much in the
    nature of an investment. But that investment is clearly coupled with a
    contractual obligation that the developer is bound to discharge.

    Without discharging this obligation, it can claim no rights in equity or
    in law.”

    216. In view of the aforesaid, all the contentions of the Respondent Developer
    insofar as the restoration of its expenses are concerned, are wholly without any
    substance. In any event, at Exhibit 3 of the Counter Claim, the Respondent
    Developer has double counted the sum of Rs. 30,68,54,552/- despite the same
    having been prayed for in Exhibit 2. Insofar as the other expenses mentioned
    in Exhibit 3 are concerned, in view of the legal position discussed above, the
    same cannot be granted.

    99) Thus, by merely relying on judgment of this Court in
    Borivali Anamika Niwas CHSL, the Arbitral Tribunal has proceeded to
    reject the claim for restoration of benefit by holding that construction
    costs cannot be treated as a benefit. Here, the Arbitral Tribunal has
    failed to distinguish the claim for restoration of price paid for purchase
    of FSI and claim for restoration of cost of construction. Both are treated
    as ‘cost of construction’ by the Arbitral Tribunal. This Court has used the
    expression ‘expenditure on the project’ in Borivali Anamika Niwas
    CHSL for holding that the same is not a handout to the society members.
    However, it must be observed that the observations made by this Court
    in Borivali Anamika Niwas CHSL are in the context of entitlement of
    Society to seek interim measures against the developer under Section 9
    of the Arbitration Act. The observations made in the judgment cannot
    be used for holding that a developer can never claim any expenditure
    _______________________________________________________________________________________________________

    PAGE NO. 67 OF 78
    30 MARCH 2026

    ::: Uploaded on – 30/03/2026 ::: Downloaded on – 31/03/2026 20:32:43 :::
    Neeta Sawant CARBP 354 of 2024

    incurred by him in execution of the project from the society after
    termination of the contract. At the stage when the judgment in Borivali
    Anamika Niwas CHSL was delivered, the issue of validity of termination
    of the DA was yet to be determined since the arbitral proceedings had
    not even commenced. This Court was considering the issue whether
    mere incurring of expenditure by the outgoing developer in the project
    was a reason enough for permitting the society to complete construction
    of building through another developer. In Borivali Anamika Niwas
    CHSL this Court ultimately made interim measures appointing Court
    Receiver in respect of the property and took away possession thereof
    from the outgoing developer. In my view therefore, the observations
    made by this Court in the judgment in Borivali Anamika Niwas CHSL,
    while deciding the issue of interim measures, are of little relevance while
    adjudicating the claim of the developer for return of benefits under
    Section 64 of the Contract Act.

    100) Mr. Khandeparkar has relied on judgment of this Court in
    Rajawadi Arunodaya CHS Ltd. which again is a judgment relevant for
    deciding grant of interim measures and cannot be relied on in support of
    contention that no part of investment made or expenditure incurred by
    the developer can ever be a benefit to the society or to its members
    under Section 64 of the Contract Act.

    101) Whether the expenditure incurred by a developer in the
    project can be treated as a benefit within the meaning of Section 64 of
    the Contract Act and whether the developer is entitled to claim

    _______________________________________________________________________________________________________

    PAGE NO. 68 OF 78
    30 MARCH 2026

    ::: Uploaded on – 30/03/2026 ::: Downloaded on – 31/03/2026 20:32:43 :::
    Neeta Sawant CARBP 354 of 2024

    restoration thereof would depend on facts of each case, particularly the
    contractual clauses. There cannot be an abstract proposition of law that
    no part of the expenditure incurred by the developer can ever be treated
    as a ‘benefit’ or that in every case, a society would be entitled to retain
    all the benefits it has received from the developer after termination of
    the contract. The facts of each case would decide as to which part of
    expenditure incurred by the developer would be a benefit to the society
    and the contractual arrangement between the parties would decide if
    such benefit needs to be returned by the society to the developer or not.
    In a given case, parties may agree that a particular benefit received by
    the society shall not be returned to the developer.

    102) As held above, the purchase price paid by the Petitioner-
    developer to MHADA for securing tit-bit land, RG FSI as well as the
    amount of Rs. 2.5 crores adjusted by the society towards FSI benefit
    would be covered by the expression ‘benefit’ appearing in Section 64 of
    the Contract Act. There is no contractual prohibition in the DA for return
    of price of FSI purchased by the developer which is utilised by the
    Society. In that view of the matter, the Society is liable to return the
    price of purchased FSI to the developer.

    103) When FSI is transferred to another party, it can give rise to
    actual and speculative benefits Actual benefit is the price that the buyer
    paid for purchase of FSI. On the other hand, speculative benefit is the
    profit potential of that FSI. After securing the FSI, the party to whom the
    same is handed over can utilise the same to construct additional area and

    _______________________________________________________________________________________________________

    PAGE NO. 69 OF 78
    30 MARCH 2026

    ::: Uploaded on – 30/03/2026 ::: Downloaded on – 31/03/2026 20:32:43 :::
    Neeta Sawant CARBP 354 of 2024

    earn profits. The profit potential of such FSI would be speculative
    benefit. Under Section 64 of the Contract Act, what is required to be
    returned is the actual benefit and not the speculative benefit.

    104) The conflict with public policy of India is writ large in the
    impugned award so far as rejection of claim for return of purchase price
    of FSI is concerned. The effect of the impugned award is that the
    Respondent-Society has retained and enjoyed the benefit of FSI
    purchased by the Petitioner. It is entitled to encash the same by
    completing construction of sale component building and by selling about
    75 flats, construction of which can be completed by the society. If the
    additional FSI is transferable, the society can alternatively sell and
    monetize the same as TDR in the market. However since some part of
    construction of A wing (sale component) building is already constructed,
    the society can engage another developer/contractor and get the
    construction completed by utilizing the additional FSI purchased by the
    Petitioner. The society is thus in a position to enrich itself by using the
    FSI purchased by the Petitioner. Therefore, if restoration of purchase
    price of FSI is not directed, this would be a pure case of unjust
    enrichment for the Society. This exactly is the objective behind Section
    64
    of the Contract Act. Public policy of India requires that the party
    terminating the contract shall not enrich itself through such
    termination. In the present case, the Respondent-society has already
    enjoyed some fruits of redevelopment process since (i) the society has
    utilised the construction put up by the Petitioner-developer (and I have
    refused to uphold the claim for return of construction cost in latter part of

    _______________________________________________________________________________________________________

    PAGE NO. 70 OF 78
    30 MARCH 2026

    ::: Uploaded on – 30/03/2026 ::: Downloaded on – 31/03/2026 20:32:43 :::
    Neeta Sawant CARBP 354 of 2024

    the judgment), (ii) society has received the arrears of transit rent with
    15% interest, (iii) society has secured return of expenditure with interest,

    (iv) the society members are owners of bigger homes envisaged in the
    DA. On the top of all these, if the society is also permitted to utilize the
    additional FSI purchased by the Petitioner and to monetize the same by
    constructing and selling more flats, the same would tantamount to
    unjust enrichment. The delay in construction of the building would
    entail losses for the developer in the form of loss of opportunity to earn
    profits and non-return of most of the investments made by it in the
    project. However, this would not mean that the society can unjustly
    enrich itself by forfeiting the amount of purchased FSI, especially when
    there is no contract to that effect.

    105) The Arbitral Tribunal has committed patent illegality in
    conflating the claim for return of FSI price with the claim for
    compensation. The award conflicts public policy of India as it enables the
    society to unjustly enrich itself in total contravention of Section 64 of
    the Contract Act. The view taken by the Tribunal does not pass the
    muster of ‘plausible view’. Permitting the society to retain purchased FSI
    and to encash the same by unjustly enriching itself is something which
    no fair-minded person would ever permit. Reliance by Mr. Khandeparkar
    on judgment of Ramesh Kumar Jain (supra) would not save this part of
    the award. In my view therefore, the part of the Award which seeks to
    deny the counterclaim of the Petitioner for return of benefit of purchase
    price of FSI is in conflict with public policy, and also patently illegal.
    Only this part of the Award is liable to be set aside.

    _______________________________________________________________________________________________________

    PAGE NO. 71 OF 78
    30 MARCH 2026

    ::: Uploaded on – 30/03/2026 ::: Downloaded on – 31/03/2026 20:32:43 :::
    Neeta Sawant CARBP 354 of 2024

    CLAIM FOR COST OF CONSTRUCTION

    106) Petitioner had also claimed amount of Rs.18,09,57,496/-
    towards cost of construction from the Respondent-Society. The learned
    Arbitrator has denied the claim for return of cost of construction by
    referring to the judgment of this Court in Borivali Anamika Niwas
    CHSL. As observed above, the observations made by this Court in
    Borivali Anamika Niwas CHSL are only in the context of society’s
    entitlement to interim measures under Section 9 of the Arbitration Act
    and the same cannot be used for concluding that in every case, the
    Developer is not entitled to seek any part of expenditure incurred by it in
    the project. As observed above, it would all depend on facts of each case
    and particularly the nature of contractual arrangement between the
    parties. The Arbitrator has also denied the claim for return of cost of
    construction on account of absence of credible proof in respect of proof
    of costs presented by the developer.

    107) Having held that Developer’s entitlement to seek return of
    costs of construction from the Society would depend on facts and
    circumstances of each case and the nature of contractual arrangement
    between the parties, I proceed to examine whether the Petitioner’s
    counterclaim for return of costs of construction could have been allowed
    in the facts and circumstances of the present case. Before proceeding to
    do so, it must be observed that the Arbitral Tribunal has once again
    conflated the issue of costs of construction with the concept of
    compensation/damages by applying Clause 22 of the D.A. Here again,

    _______________________________________________________________________________________________________

    PAGE NO. 72 OF 78
    30 MARCH 2026

    ::: Uploaded on – 30/03/2026 ::: Downloaded on – 31/03/2026 20:32:43 :::
    Neeta Sawant CARBP 354 of 2024

    the claim for return of costs of construction incurred by a developer
    cannot be a claim for compensation under Section 73 of the Contract
    Act. In a given case, costs of construction incurred by a developer can fit
    into the term ‘benefit’ used under Section 64 of the Contract Act.
    However, it depends on facts of each case.

    108) In the present case, the contract of redevelopment awarded
    to the Petitioner-Developer has been terminated by the Society. I have
    already upheld part of the Award which validates the termination
    effected by the Society. Petitioner admittedly did not complete
    construction of the building within the period stipulated in the DA or
    even within the extended period under the consent terms. During the
    period from 26 June 2007 till 9 June 2018 (11 long years), the Petitioner
    was able to construct a mere bare shell RCC structure of 21 floors in
    wing and 7 floors in A wing, which was incapable of being used for
    residence by any of the members. The issue for consideration is whether
    expenditure incurred on construction of such bare shell RCC structure
    can be treated as a benefit received by the society within the meaning of
    Section 64 of the Contract Act? In my view, the answer to the question,
    in the facts and circumstances of the present case, will have to be
    necessarily in the negative. In a given case, where the construction of the
    building is virtually complete but the occupancy certificate is not issued
    and at that stage, if the DA is terminated and the society is in a position
    to secure the occupancy certificate without any modifications in the
    construction already erected, such construction by the developer may
    tantamount of benefit for the society. However, in the present case,

    _______________________________________________________________________________________________________

    PAGE NO. 73 OF 78
    30 MARCH 2026

    ::: Uploaded on – 30/03/2026 ::: Downloaded on – 31/03/2026 20:32:43 :::
    Neeta Sawant CARBP 354 of 2024

    where the structure erected by the Petitioner-developer was not of use
    for the members of the society, such structure cannot be treated as
    benefit for the society. Thus, the key is to find out whether the
    constructed structure can be put to use by the society or by its members.
    In the facts of the present case, construction put up by the Petitioner
    cannot be treated as benefit for the members of the society. For the
    purpose of application of provisions of Section 64 of the Contract Act,
    the thing passed on to the opposite party must be complete in all
    respects, capable of being enjoyed by the opposite party. Consequently,
    the thing delivered to the other party which is incapable of being utilised
    in its delivered state, cannot be treated as a benefit received. In the
    present case, the Society and its members are required to further build
    upon the bare shell structure erected by the Petitioner which was not
    capable of being put to any use by the Society members. In the facts and
    circumstances of the present case therefore, the construction so erected
    by the Petitioner would not form a benefit to the Society within the
    meaning of Section 64 of the Contract Act and therefore Petitioner’s
    claim for return of cost of construction is rightly rejected by the
    Tribunal.

    109) Also, the arbitrator has rightly evaluated the evidence on
    record for holding that the Petitioner could not produce credible
    evidence of exact costs of construction incurred in respect of the project.
    The Petitioner is a professional developer undertaking several projects.
    It was incumbent for it to prove that a particular expenditure was
    incurred for the project in question. Mere presentation of invoices for

    _______________________________________________________________________________________________________

    PAGE NO. 74 OF 78
    30 MARCH 2026

    ::: Uploaded on – 30/03/2026 ::: Downloaded on – 31/03/2026 20:32:43 :::
    Neeta Sawant CARBP 354 of 2024

    purchase of cement, steel etc cannot be a reason for inferring that the
    purchases was utilised for the project in the question. Thus, there is
    absence of any credible and reliable evidence for accepting the claim of
    the Petitioner that it incurred expenditure of Rs.18,09,57,496/ towards
    construction costs. Reliance by Petitioner on judgment of this Court in
    Harish Loyalka (supra) is inapposite. When there is no correlation
    between invoices and amount spent in particular project, mere absence
    of cross-examination is not sufficient to hold that every amount covered
    by invoices is spent on present project. Also failure to lead evidence is
    just an additional ground for rejection of counterclaim for return of cost
    of construction, which is otherwise not covered under Section 64 of the
    Contract Act.

    110) Considering the facts of the case, the view taken by the
    Tribunal rejecting claim for return of cost of construction is a plausible
    view. Though the tribunal has essentially based the rejection of claim for
    returning the cost of construction by relying on observations made by
    this Court in Borivali Anamika Niwas CHSL , the conclusion can
    otherwise be justified on the basis of the material on record of the
    Tribunal and this Court can accordingly explain the reasons for the
    conclusion as per judgment of the Apex Court in OPG Power Generation
    (supra). In the facts of the present case therefore, rejection of
    counterclaim by the learned arbitrator in respect of return of cost of
    construction cannot be treated as patently illegal for this Court to
    interfere in exercise of jurisdiction under Section 34 of the Arbitration
    Act.

    _______________________________________________________________________________________________________

    PAGE NO. 75 OF 78
    30 MARCH 2026

    ::: Uploaded on – 30/03/2026 ::: Downloaded on – 31/03/2026 20:32:43 :::
    Neeta Sawant CARBP 354 of 2024

    CONCLUSIONS

    111) Considering the overall conspectus of the case, I am of the
    view that the Award upholding the Termination Notice dated 9 June
    2018 and restraining the Petitioner from interfering with possession of
    the concerned land and the building by the Society does not warrant
    interference under Section 34 of the Arbitration Act. Similarly the award
    directing handing over of original documents, awarding monetary claim
    in the sum of Rs.7,08,53,695.03/- in favour of the Respondent-Society
    also passes muster under Section 34 of the Act. Rejection of
    counterclaims of Petitioner towards compensation (loss of profit), return
    of rent, return of cost of construction etc is also found to be in order.
    Petitioner has failed to make out a valid ground of challenge to the
    Award in respect of the above findings, and this part of the Award can be
    sustained.

    112) While most of the Award is being upheld, only a small part
    thereof relating to rejection of counterclaim for return of cost of
    purchased FSI by the Petitioner-developer is found to be unsustainable
    for the reasons indicated above. The part of the Award rejecting the
    claim for return of purchase price of FSI is not inseparably intertwined
    with the other parts of the award. This Court has upheld Petitioner’s
    right for restoration of benefits under Section 64 of the Contract Act. But
    only amount spent for purchase of TDR / tit-bit land can be treated as
    benefit and the amount of rent and cost of construction cannot be
    tretaed ass benefit. Therefore part of the award rejecting counterclaim

    _______________________________________________________________________________________________________

    PAGE NO. 76 OF 78
    30 MARCH 2026

    ::: Uploaded on – 30/03/2026 ::: Downloaded on – 31/03/2026 20:32:44 :::
    Neeta Sawant CARBP 354 of 2024

    for return of price of purchased TDR/FSI/tit-bit land is easily separable
    without causing violence to the other part of the impugned award.
    Therefore, following the principles of Constitution Bench judgment in
    Gayatri Balasamy vs. ISG Novasoft Technologies Limited 28, it is possible
    to severe bad part of the Award from the good part. Therefore while
    upholding the rest of the Award, only the part thereof which rejects
    Petitioner’s counterclaim for return of Rs.8,18,03,435/- spent by it for
    purchase of tit-bit land, Rs.20,61,150/- spent by it for purchase of RG FSI
    and Rs.2,50,00,000/- adjusted by Society towards FSI benefit is liable to
    be set aside.

    ORDER

    113) I accordingly proceed to pass the following order:

    (i) The Award of the learned Arbitrator dated 24 June 2023, except
    to the limited extent as indicated in para (ii) below, is upheld.

    (ii) The Award is set aside only to the extent it rejects Petitioner’s
    counterclaim for return of benefit received by the Respondent-

    society in the sum of Rs. 8,18,03,435/- for purchase of tit-bit
    land, Rs. 20,61,150/- for purchase of RG FSI and Rs.
    2,50,00,000/- adjusted towards FSI benefit from bank guarantee
    amount.

    28

    (2025) 7 SCC 1
    _______________________________________________________________________________________________________

    PAGE NO. 77 OF 78
    30 MARCH 2026

    ::: Uploaded on – 30/03/2026 ::: Downloaded on – 31/03/2026 20:32:44 :::
    Neeta Sawant CARBP 354 of 2024

    114) With the above directions, the Petition is partly allowed
    and disposed of. Considering the facts and circumstances of the present
    case, I deem it appropriate not to make any further order as to costs.

    
    
    
    
                                                                              [SANDEEP V. MARNE, J.]
    
             Digitally
             signed by
             NEETA
    NEETA    SHAILESH
    SHAILESH SAWANT
    SAWANT Date:
             2026.03.30
             20:38:01
             +0530
    
    
    
    
    

    _______________________________________________________________________________________________________

    PAGE NO. 78 OF 78
    30 MARCH 2026

    ::: Uploaded on – 30/03/2026 ::: Downloaded on – 31/03/2026 20:32:44 :::



    Source link

    LEAVE A REPLY

    Please enter your comment!
    Please enter your name here