Advertisement
Advertisement

― Advertisement ―

Home12.03.2026 vs Union Of India And Ors on 25 March, 2026

12.03.2026 vs Union Of India And Ors on 25 March, 2026

ADVERTISEMENT

Jammu & Kashmir High Court

Reserved On: 12.03.2026 vs Union Of India And Ors on 25 March, 2026

Author: Sanjay Dhar

Bench: Sanjay Dhar

                                                                               2026:JKLHC-JMU:836




    IN THE HIGH COURT OF JAMMU & KASHMIR AND LADAKH
                        AT JAMMU

                                     Arb P No. 98/2025
                                     CM No. 1410/2026 &
                                     Arb P No. 99/2025
                                     CM No. 1456/2026



                                                 Reserved on: 12.03.2026
                                              Pronounced on : 25.03.2026
                                                Uploaded on : 25.03.2026
                                          Whether the operative part or full
                                            judgment is pronounced: Full

M/s K.K. Enterprises
                                                                   ....Petitioners

                  Through:-           Mr. Anil Mahajan, Advocate.

                                    V/s

Union of India and Ors.
                                                                .....Respondents

                  Through:-           Mr. Sumant Sudan, Advocate vice
                                      Mr. Vishal Sharma, DSGI.
\


CORAM: HON'BLE MR. JUSTICE SANJAY DHAR, JUDGE

                                     JUDGMENT

01. By this common judgment the afore-titled two

arbitration petitions involving identical parties and common

SPONSORED

questions of law and fact are proposed to be decided together.

02. The petitioner-firm has filed the present petitions

under Section 11(6) of the Arbitration and Conciliation Act,

1996 (hereinafter to be referred to as “Act”) seeking

Arb P Nos. 98/2025 & 99/2025 Page 1 of 15
2026:JKLHC-JMU:836

appointment of an arbitrator for adjudication of disputes that

have arisen between the parties.

03. Pleadings of Arb. P No. 98 of 2025

3.1 As per case of the petitioner-firm, pursuant to

tender floated by respondent No. 1 through respondent No. 3,

its bid was declared as successful and vide letter No.

8818/68/E8 dated 23.03.2007, the contract relating to

“repair of internal electrification in certain buildings in

213 Transit Camp at Jammu” for an amount of

Rs. 4,39,311.86 was allotted in his favour. It is case of the

petitioner that an agreement came to be executed between it

and respondent No. 1 through respondent No. 3. The date of

commencement of work was 29.03.2007 with date of

completion as 28.09.2007.

3.2 According to the petitioner, the site was handed

over to it in part on 29.03.2007 whereafter the work was

completed and the building was handed over to the

respondent-department. It has been submitted that because

the respondent did not hand over all the buildings for

execution of work to the petitioner, as such, it was unable to

execute the work at old quoted rates. Accordingly, the

petitioner asked the respondents to execute fresh agreement

as it was not feasible to execute the balance work at old quoted

rates. It has been submitted that payment in respect of the

work, which was already done by the petitioner, has not been

Arb P Nos. 98/2025 & 99/2025 Page 2 of 15
2026:JKLHC-JMU:836

settled and the respondents have not performed their

contractual obligations relating to handing over of all buildings

for execution of the work.

3.3 It has been averred that vide letter/order dated

24.09.2012, respondent No. 3 constituted a Board of Officers

to ascertain the quantum of work executed by the petitioner

and the Board submitted its report dated 07.03.2013 with the

recommendation that the staff, who has made the payment, be

called and the payment made to the contractor be got recorded

in the measurement book before finalizing the case. However,

respondent No. 3 vide letter dt. 24.09.2012 cancelled the

contract w.e.f., 30.09.2012.

3.4 It has been submitted that vide communications

dated 15.05.2024 and 01.02.2025, the petitioner requested

respondent No. 2, the designated authority, to appoint the

arbitrator to decide the disputes that have arisen between the

parties. The petitioner has given the details of claims that,

according to it, have arisen against the respondents. It has

been submitted that as many as 14 claims have arisen and an

amount of Rs. 92,88,279.64 along with interest @ 18% per

annum is due and payable to the petitioner.

3.5 It has further been submitted that vide

communication dated 09.08.2024 issued by respondent No. 3,

the petitioner was asked to furnish an undertaking that it has

no objection for change in appointing authority so that the

Arb P Nos. 98/2025 & 99/2025 Page 3 of 15
2026:JKLHC-JMU:836

appointing authority may take a decision in the matter. This

was responded to by the petitioner vide communication dated

02.09.2024 informing that it does not agree to the same. It is

in these circumstances that the petitioner has filed the present

petition seeking appointment of arbitrator.

3.6 The respondents have filed their objections to the

petition in which it has been submitted that the petition is

hopelessly time barred, as such, liable to be dismissed. It has

been contended that the petitioner has suppressed material

facts and that it has not approached the Court with clean

hands. According to the respondents, the petitioner did not

execute the work as per the agreed time schedule and failed to

complete the entire work despite issuance of several slow

progress notices. This ultimately led to cancellation of the

contract on 24.09.2012.

3.7 It has been submitted that the petitioner issued

notice dated 20.06.2013 requesting for appointment of

arbitrator but its request was not acceded to. According to the

respondents, two more communications came to be addressed

by the petitioner to the appointing authority on 05.04.2016

and 09.06.2020 seeking appointment of arbitrator.

3.8 It has been contended that limitation period for

filing a petition under Section 11(6) of the Act would start

running against the petitioner from thirty days after the

issuance of notice dated 20.06.2013 for invocation of the

Arb P Nos. 98/2025 & 99/2025 Page 4 of 15
2026:JKLHC-JMU:836

arbitrator clause and the present petition has been filed in

November, 2025, as such, the same is hopelessly time barred.

3.9 It has been submitted that communication dated

09.08.2024 issued by respondent No. 3 is a routine official

letter and does not have any consequence and bearing upon

the limitation period for filing of the petition under Section

11(6) of the Act. It has been further submitted that

respondent No. 3 is not the appointing authority, as such, it is

not competent to appoint the arbitrator.

3.10 When the objection with regard to maintainability of

the petition on the ground of limitation was taken by the

respondents, the petitioner came up with application bearing

CM No. 1410 of 2026 and placed on record a copy of

communication dated 02.11.2023 addressed by it to

Commander Works Engineer, Jammu and also a copy of

communication dated 29.08.2023 addressed by respondent

No. 3 to the petitioner.

04. Pleadings in Arb. P No. 98 of 2025

4.1 As per case of the petitioner-firm pursuant to tender

floated by respondent No. 1 through respondent No. 3, it was

declared as successful bidder in terms of communication No.

8818/59/30/E8 dated 07.12.2006 and the contract relating to

“repair of internal electrification work and replacement of

GLS lamps at Satwari” was allotted in its favour. The cost of

the contract was Rs. 7,95,210.54/-. Pursuant to the allotment

Arb P Nos. 98/2025 & 99/2025 Page 5 of 15
2026:JKLHC-JMU:836

letter, an agreement came to be executed between the

petitioner and respondent No. 3. The date of commencement

of work was fixed as 11.12.2006 with date of completion as

10.06.2007.

4.2 It has been submitted that the site was handed over

to the petitioner only in part on 11.12.2006 and the entire site

was never handed over to it for execution of the contract. The

petitioner executed the work and informed the respondents

that all the buildings have not been handed over to it, as such,

the petitioner is unable to execute the work at old quoted

rates. Accordingly, the petitioner requested the respondents

for execution of a fresh agreement. It has been submitted that

respondent-department did not have material in store, as

such, there was delay in execution of the work. It has been

further submitted that final bill has not been settled and paid

to the petitioner as yet. It has been alleged that the

respondents have not performed their contractual obligation

relating to handing over of all buildings to the petitioner.

4.3 It has been averred that vide letter dated

24.09.2012, respondent No. 3 constituted a Board of Officers

to ascertain the quantum of work carried out by the petitioner

and the Board, vide its report dated 07.03.2013, recommended

that the staff, who has made the payment be called and the

payment made to the contractor be got recorded in the

measurement book before finalizing the case. However,

Arb P Nos. 98/2025 & 99/2025 Page 6 of 15
2026:JKLHC-JMU:836

respondent No. 3, vide its letter No. 24.09.2012, cancelled the

contract w.e.f., 30.09.2012.

4.4 It has been submitted that the petitioner vide its

communications dated 15.05.2024 and 01.02.2025, has

invoked the arbitration clause and requested respondent

No. 2, the designated authority, to appoint the arbitrator to

decide the disputes that have arisen between the parties.

According to the petitioner, as many as 15 claims are

outstanding against the respondents which amount to

Rs. 1,08, 90,547.40/- along with interest @ 18% per annum.

4.5 It has further been submitted that vide

communication dated 09.08.2024, respondent No. 3 called

upon the petitioner to furnish an undertaking that it has no

objection to change in appointing authority to which the

petitioner responded vide its communication dated 02.09.2024

informing that it does not agree to change in the designated

authority. Accordingly, the present petition seeking

appointment of arbitrator has been filed by the petitioner.

4.6 The Respondents in their reply to the petition have

raised preliminary objection to the maintainability of the

petition on the ground that the same is hopelessly time barred.

It has been further submitted that the petitioner has

suppressed material facts from this court and has not

approached the Court with clean hands. It has been alleged

that the petitioner could not complete the work within the

Arb P Nos. 98/2025 & 99/2025 Page 7 of 15
2026:JKLHC-JMU:836

agreed time schedule despite issuance of several slow progress

notices. This ultimately led to cancellation of the contract in

terms of communication dated 24.09.2012.

4.7 It has been submitted that vide notice dated

19.06.2013, the petitioner made a request for appointment of

arbitrator before the designated authority by invoking the

arbitration clause but its request was not acceded to. Another

communication to the same effect was addressed by the

petitioner on 05.04.2016. It has been contended that limitation

period for approaching the Court for appointment of arbitrator

started to run against the petitioner after one month of

issuance of notice dated 19.06.2013, as such, the present

petition is hopelessly time barred.

4.8 In so far as communication dated 09.08.2024

issued by respondent No. 3, it has been contended by the

respondents that the same is a routine official letter and

because the said communication has not been issued by the

designated authority, as such, the same does not have bearing

upon the limitation period for approaching this Court for

appointment of the arbitrator.

4.9 When the respondents raised the objection with

regard to maintainability of the petition on the ground of

limitation, the petitioner came up with application bearing CM

No. 1456 of 2026 and placed on record a copy of the

communication dated 30.10.2023 addressed by it to the

Arb P Nos. 98/2025 & 99/2025 Page 8 of 15
2026:JKLHC-JMU:836

Commander Works Engineer, Jammu. The other documents,

which have been placed on record, are copy of the

communication dt. 21.09.2023 addressed by respondent No. 3

to the petitioner, copy of communication dated 16.11.2023

addressed by the Commander Works Engineer, Jammu to the

petitioner, copy of Communication dated 02.12.2023

addressed by the Commander Works Engineer, Jammu to the

petitioner and copy of Communication dated 24.11.2023

addressed by the petitioner to the Commander Works

Engineer, Jammu.

05. Discussion and Legal Analysis

5.1 I have heard learned counsel for the parties and

perused record of the case.

5.2 The main objection that has been raised by the

respondents to the maintainability of both the afore-titled

petitions is that the same are hopelessly barred by time

inasmuch as the arbitration clause has been invoked by the

petitioner in the year 2013 whereas, the present petitions have

been filed after a lapse of more than twelve (12) years. The

petitioner, on the other hand, has contended that the matter

relating to settlement of dispute between the parties has

always remained under consideration of the respondents and

the petitioner has invoked the arbitration clause in the year

2024/2025 to which respondent No. 3 has responded in terms

of communication dated 09.08.2024 whereby the petitioner

Arb P Nos. 98/2025 & 99/2025 Page 9 of 15
2026:JKLHC-JMU:836

was asked to furnish an undertaking expressing its no

objection to the change in the designated authority, which was

not acceded to by the petitioner and conveyed vide

communication dated 02.09.2024.

5.3 Before dealing with the merits of the rival

contentions of the parties, it would be appropriate to analyze

the legal position as regards the limitation period for filing a

petition under Section 11(6) of the Act.

5.4 The issue whether Limitation Act, 1963 is

applicable to an application for appointment of an arbitrator

under Section 11(6) of the Act came up for consideration

before the Supreme Court in the case of Arif Azim Company

Ltd Vs. Aptech Limited, (2024) 5 SCC 313. The Supreme

Court observed that a petition under Section 11(6) of the Act of

1996 would be covered under Article 137 of the Limitation Act,

which prescribes a limitation period of three years from the

date when the right to apply accrues. It was further observed

by the Supreme Court that limitation period for filing an

application seeking appointment of an arbitrator was to

commence only after a valid notice, invoking arbitration, had

been issued by one of the parties to the other party and there

had been either a failure or refusal on the part of the other

party to comply with the requirement of the said notice.

5.5 The ratio laid down in the aforesaid decision was

further explained by the Supreme Court in the case of

Arb P Nos. 98/2025 & 99/2025 Page 10 of 15
2026:JKLHC-JMU:836

“Aslam Ismail Khan Deshmukh Vs. Asap Fluids Pvt. Ltd.,

(2025) 1 SCC 520″. After noticing the ratio laid down in Arif

Azim‘s case (supra), the Supreme Court observed as under:

39. Therefore, while determining the issue of limitation in the
exercise of powers under Section 11(6) of the Act, 1996, the
referral court must only conduct a limited enquiry for the
purpose of examining whether the Section 11(6) application
has been filed within the limitation period of three years or
not. At this stage, it would not be proper for the referral court
to indulge in an intricate evidentiary enquiry into the
question of whether the claims raised by the petitioner are
time barred. Such a determination must be left to the decision
of the arbitrator. After all, in a scenario where the referral
court is able to discern the frivolity in the litigation on the
basis of bare minimum pleadings, it would be incorrect to
assume or doubt that the arbitral tribunal would not be able
to arrive at the same inference, especially when they are
equipped with the power to undertake an extensive
examination of the pleadings and evidence adduced before
them.

5.6 From the foregoing analysis of the legal position, it

is clear that an application under Section 11(6) of the Act has

to be filed within three years from the date of failure or refusal

on the part of the adverse party to respond to the letter of

invocation of arbitration agreement. Thus, the breaking point,

which gives rise to commencement of cause of action in favour

of a party approaching the court under Section 11(6) of the

Act, is the refusal/neglect on the part of the adverse party or

Arb P Nos. 98/2025 & 99/2025 Page 11 of 15
2026:JKLHC-JMU:836

the designated authority to respond to the letter invoking

arbitration agreement. The cause of action would start running

against the party approaching the court from that date and

once it starts running, it would not stop running against the

party approaching the court thereafter. Section 9 of the

Limitation Act, which is applicable to the arbitration

proceedings, makes it clear that once time has begun to run,

no subsequent disability or inability to institute a suit or make

an application stops it.

5.7 Coming to the facts of the present case, according

to the petitioner, it has invoked the arbitration clause only on

15.05.2024 read with communication dated 01.02.2025 in

both the cases. However, the respondents, in their reply, have

pleaded and placed on record communications dated

19.06.2013/20.06.2013 addressed by the petitioner to the

designated authority, namely, Chief Engineer, Pathankot Zone

praying for reference of disputes to sole arbitration. The

respondents have also placed on record communication dated

05.04.2016 whereby the petitioner has repeated its request for

reference of disputes to the arbitration. Both these

communications have been suppressed by the petitioner while

filing the petitions. It is not the case of the petitioner that

these communications were not addressed by it to the

designated authority, therefore, it can safely be stated that the

petitioner has invoked the arbitration clause in both the cases

Arb P Nos. 98/2025 & 99/2025 Page 12 of 15
2026:JKLHC-JMU:836

in June, 2013 itself. The present petitions have been filed in

November, 2025, which is more than twelve and a half years

after invocation of the arbitration clause by the petitioner.

5.8 Learned counsel for the petitioner has laid much

emphasis on the subsequent correspondence, which has been

exchanged by the parties after the invocation of the arbitration

clause by the petitioner in the year 2013. Much emphasis has

been laid on communication dated 09.08.2024 addressed by

respondent No. 3 to the petitioner whereby the petitioner was

asked to file an undertaking that it has no objection to the

change in the designated authority so that arbitrator can be

appointed. The said communication in the opinion of this

Court does not extend the period of limitation, firstly, because

the said communication has not been addressed by the

appointing authority and secondly because the time for

commencement of the limitation period against the petitioner

had started to run immediately upon service of notice of

invocation of arbitration clause upon the designated authority

and the same would not stop in any circumstances

whatsoever. All the subsequent developments that have taken

place after the invocation of arbitration clause would not save

the period of limitation from running against the petitioner.

Mere reiteration and repetition of letters, invoking arbitration

agreement emanating from the petitioner, would not extend

Arb P Nos. 98/2025 & 99/2025 Page 13 of 15
2026:JKLHC-JMU:836

the period of limitation for approaching this Court in

connection with appointment of arbitrator.

5.9 Merely because the respondents may not have

taken any action or responded to the request of the petitioner

for appointment of arbitrator made in June, 2013, would not

defer the date from which the cause of action would arise in

favour of the petitioner. Once the petitioner had asserted its

claim and the respondents had failed to respond to the claim

relating to appointment of an arbitrator, such failure has to be

treated as denial of request of the petitioner and, therefore, the

cause of action for filing petition under Section 11(6) of the Act

would arise after waiting for a reasonable time which, in the

circumstances, cannot be more than one month of service of

notice of invocation of letter upon the respondents.

5.10 Apart from the above, the petitioner is guilty of

suppression of material facts from this Court and it has

conveniently suppressed the previous invocation letters of

June, 2013 and April, 2016 so as to give an impression to the

Court that it was only in the year 2024/2025 that arbitration

clause was invoked by it. Even when the respondents brought

the invocation letters of June, 2013 and April, 2016 to the

notice of this Court, the petitioner did not amend the petition

so as to explain the circumstances under which the aforesaid

letters and events were suppressed by it from this Court.

Unless it is pleaded as to in what circumstances and on what

Arb P Nos. 98/2025 & 99/2025 Page 14 of 15
2026:JKLHC-JMU:836

facts period of limitation is sought to be extended from the

date on which the cause of action originally arose, there

cannot be any basis to save the period of limitation from

running against the petitioner. In the present cases, the

petitioner, instead of pleading anything to this effect, has

suppressed the material facts from the Court.

06. Conclusion:

6.1 From the foregoing discussion, it is clear that the

present petitions are hopelessly barred by time and as such,

the same are liable to be dismissed on that ground alone.

6.2 Accordingly, both the petitions are dismissed being

barred by limitation.

(SANJAY DHAR)
JUDGE
JAMMU
25.03.2026
Naresh/Secy.

Whether the judgment is speaking: Yes
Whether the judgment is reportable: Yes

Arb P Nos. 98/2025 & 99/2025 Page 15 of 15



Source link