HomeReserved On: 26.02.2026 vs Union Of India Through on 11 March, 2026

Reserved On: 26.02.2026 vs Union Of India Through on 11 March, 2026

ADVERTISEMENT

Through: Mr. Vishal Sharma, DGSI with
Mr. Sumant Sudan, Adv.

SPONSORED

CORAM: HON’BLE MR. JUSTICE M A CHOWDHARY, JUDGE

(JUDGMENT)

1. Applicant-M/S National Engineers, through the medium of this

Arbitration Application under Section 34 of the J&K Arbitration & Conciliation

Act, seeks setting aside of award dated 10.08.2005 and communication dated

04.10.2005 on an application moved U/S 33 of the Act, passed by the learned

Sole Arbitrator Col. Balwinder Singh, in Arbitration Application titled

“National Engineers Vs. Commander Works Engineers, HQ 138 Works

Engineeers.” to the extent of non-payment of interest as the petitioner is entitled

to recover interest @ 24 % per annum from the date of completion of contract

agreement.