M/S Cosco Blossoms Pvt Ltd vs Oriental Insurance Company Ltd on 12 March, 2026

    0
    53
    ADVERTISEMENT

    Delhi High Court

    M/S Cosco Blossoms Pvt Ltd vs Oriental Insurance Company Ltd on 12 March, 2026

    Author: Jasmeet Singh

    Bench: Jasmeet Singh

                              $~J
                              *      IN THE HIGH COURT OF DELHI AT NEW DELHI
    
                                                                      Judgment reserved on: 06.11.2025
                                                                   Judgment pronounced on: 12.03.2026
    
                              +      O.M.P. (COMM) 568/2016
    
                                     M/S COSCO BLOSSOMS PVT LTD                        .....Petitioner
    
                                                        Through:    Mr. Raman Kapur, Sr. Adv. with Mr
                                                                    Rajinder Wali, Adv.
                                                        versus
    
                                     ORIENTAL INSURANCE COMPANY LTD          .....Respondent
                                                  Through: Mr. Pradeep Gaur, Mr. Amit Gaur,
                                                           Ms. Sweta Sinha, Advs.
                                     CORAM:
                                     HON'BLE MR. JUSTICE JASMEET SINGH
    
                                                           JUDGMENT
    

    1. This is a petition filed under Section 34 of the Arbitration and
    Conciliation Act, 1996 (“the Act”), seeking to challenge the Arbitral
    Award dated 17.03.2012 (“Award”) passed by the learned Sole
    Arbitrator.

    FACTUAL MATRIX AS PER THE PETITIONER

    SPONSORED

    2. The petitioner, namely M/s Cosco Blossoms Pvt. Ltd., is a registered
    private limited company engaged in the business of floriculture. The
    company at the relevant time was primarily a 100% export oriented
    company exporting its flowers in foreign markets in Europe, Japan,
    etc.

    Digitally Signed
    By:MAYANK
    Signing Date:12.03.2026 O.M.P. (COMM) 568/2016 Page 1 of 37
    19:10:21

    3. For the purpose of operating its floriculture business, the petitioner
    maintained several greenhouses built on area measuring 15 acres
    situated at Village Goyla, Sub-Tehsil Tauru, Gurgaon, Haryana.

    4. The company catered to the demands of the high-end flowers market
    abroad, and to ensure high quality standards, the process/technique of
    production, cultivation and all other necessary equipment were
    imported from various countries, primarily the UK, Holland and
    Israel.

    5. Greenhouses were the essential component for the cultivation process.

    The structure of each greenhouse was made of galvanized steel
    (imported from Israel) containing 17 bays. Each bay measured 7.5
    meters wide, 40 meters long, and 3.5 meters in height. The top portion
    of each bay was made up of UVA Stabilized polyethylene sheets
    measuring 8.5 meters wide and 46 meters long, which were also
    imported from Israel.

    6. The entire setup of greenhouse structure consisted of 131 high quality
    polyethylene sheets imported from Azrom Metal Industries Ltd., Israel
    and other foreign companies. Each such sheet was designed to
    withstand any high speed winds up to 60km/hr and to allow only a
    specific measured amount of sunshine exposure to the plants. The
    nature of plantations in this business required maintenance of
    appropriate temperature and humidity.

    7. The respondent, namely Oriental Insurance Company Ltd., is an
    Insurance Company from which the petitioner had availed two
    insurance policies bearing Policy No. 211300/47/98/00002 (“Policy
    1”) and Policy No. 211300/000/00000/11/13/98/05088 (“Policy 2”).

    Digitally Signed
    By:MAYANK
    Signing Date:12.03.2026 O.M.P. (COMM) 568/2016 Page 2 of 37
    19:10:21
    These policies were operative for the period of 12 months, i.e.
    07.08.1997 to 06.08.1998.

    8. The Policy 1 covered items such as plants, saplings, roses, and inputs,
    while the Policy 2 covered other physical assets such as equipment in
    the greenhouses. The present dispute emanates from policy 2, namely
    the fire and miscellaneous insurance policy.

    9. On the evening of 02.06.1998, severe high winds and rainfall struck
    the greenhouses of the petitioner. The directors of the company were
    informed, and they reached the site immediately. They discovered that
    a substantial number of polyethylene sheets had suffered serious
    damage, were either torn or blown away, thereby also damaging the
    plants.

    10. The directors of the company made several efforts to repair the
    damaged sheets to reduce the resultant damage to the plants with the
    help of the villagers, however a second wave of high winds and rain
    struck the greenhouse of the petitioner again on 04.06.1998. The
    directors again organised their efforts to repair the damage done on
    04.06.1998.

    11. The respondent was informed by the petitioner company vide letter
    dated 05.06.1998 about the loss and damage suffered by them and
    their greenhouses. On 5.06.1998, some more sheets were replaced.

    12. Pursuant thereto, the surveyor deputed by the respondent namely Mr.
    J.K. Sharma visited the site on 06.06.1998 to assess the damage done
    to the material of the greenhouses. The repair work of the said
    greenhouses continued on 06.06.1998, whereby 90 sheets were

    Digitally Signed
    By:MAYANK
    Signing Date:12.03.2026 O.M.P. (COMM) 568/2016 Page 3 of 37
    19:10:21
    replaced because of damage and 41 old sheets were found to be in fit
    condition.

    13. Since the surveyor did not visit again, the petitioner repeatedly
    requested and addressed numerous communications and finally the
    survey was conducted on 19.09.1998, whereby the surveyor was
    shown the damaged sheets, damaged plants and also the new sheets,
    90 in number which were replaced in order to fix the greenhouses.
    The stock registers also recorded the said facts, that the petitioner
    company had 91 sheets in stock and substantial numbers of them were
    utilised. The surveyor tried on several occasions to get the damaged
    sheets counted but the same could not be done.

    14. The surveyor addressed a letter dated 05.10.1998 to the petitioner
    stating that it was not possible to measure the heaps of damaged
    polyethylene sheets because of lack of labour and that the same fact
    was also informed to one of the directors of the company. The
    surveyor through this letter allowed a last opportunity to the petitioner
    to submit their response by 15.10.1998. The petitioner vide letter
    dated 02.11.1998 submitted a statement of measurement and counting,
    and informed the surveyor that the damaged sheets are lying in pieces
    and heaps because of extensive damage due to high speed wind and
    rain.

    15. On 09.11.1998, the surveyor submitted his report to the respondent,
    which as per the petitioner was based on misrepresentation of facts
    and was without any application of mind.

    16. At repeated requests of the petitioner, the respondent company vide
    letter dated 18.02.1999 appointed Mr. Ashwani Chaudhary as a new

    Digitally Signed
    By:MAYANK
    Signing Date:12.03.2026 O.M.P. (COMM) 568/2016 Page 4 of 37
    19:10:21
    surveyor to reassess the loss suffered by the petitioner company. After
    his visit, in a report dated 23.03.1999, he recommended a net amount
    of Rs. 3,17, 935/- only for 15 sheets without undertaking the analysis
    as to the number of sheets actually lost or damaged. The petitioner did
    not accept this assessment of loss, and the respondent also refused to
    make the payment of the said assessed amount until it is accepted for
    full satisfaction.

    17. The policy contained a dispute resolution clause being Clause No. 13,
    which was invoked by the petitioner vide its letter dated 13.08.1999
    and filed a Claim petition. The petitioner made several efforts to
    resolve the dispute even after issuing of arbitration invocation notice
    but to no avail.

    18. The petitioner herein was the claimant before the Arbitrator and the
    respondent herein was the respondent in the said Arbitral proceedings.
    IMPUGNED AWARD

    19. Initially, the Arbitral Tribunal consisted of Hon’ble Mr. Justice A.P.
    Chowdhri (Retd.), Presiding Arbitrator, Shri D.B. Malik, Arbitrator
    and Shri Girish Aggrawal, Arbitrator. However, the two Arbitrators,
    namely Shri D.B. Malik and Shri Girish Aggrawal recused themselves
    from the Arbitral proceedings on 02.02.2009 and then the parties
    agreed to continue with the presiding Arbitrator Hon’ble Mr. Justice
    A.P. Chowdhri (Retd.) as the Sole Arbitrator. However, Justice
    Chowdhri also resigned from the proceedings on 31.07.2009.
    Thereafter, by mutual consent of the parties Hon’ble Mr. Justice K.S.
    Gupta (Retd.) was appointed as the Sole Arbitrator to adjudicate the
    disputes between the parties and the petitioner was consequently

    Digitally Signed
    By:MAYANK
    Signing Date:12.03.2026 O.M.P. (COMM) 568/2016 Page 5 of 37
    19:10:21
    awarded Rs. 3,17,935/- along with interest at the rate of 10% per
    annum to be calculated from 27.08.1999 vide Award dated
    17.03.2012.

    SUBMISSIONS ON BEHALF OF THE PETITIONER

    20. Mr. Kapur, learned senior counsel for the petitioner, at the outset
    states that the Award suffers from patent error, perversity and has
    been passed without considering the materials and evidence placed on
    record.

    21. He states that the Arbitrator made an erroneous finding without any
    application of mind by relying on on-site physical verification as
    conducted by the initial surveyor Mr. JK Sharma, despite him stating
    that he never had the opportunity to calculate the number of damaged
    sheets.

    22. The Arbitrator completely disregarded the statements made by Mr. JK
    Sharma during his cross-examination, wherein he categorically made
    three admissions, firstly that he has not calculated the total number of
    damaged sheets, secondly that he was offered full cooperation by the
    petitioner to assess the damage on-site, and thirdly the survey report is
    based on his memory.

    23. It is further submitted that the Arbitrator has not considered the stock
    register maintained by the petitioner which clearly proves the
    replacement of 90 sheets after the damage.

    24. The findings of the Arbitrator are inconsistent and contradictory as he
    accepted the total number of damaged sheets to be 15 but at the same
    time also recorded an observation as to how this substantial number of
    damaged sheets can be replaced by the petitioner in a mere duration of

    Digitally Signed
    By:MAYANK
    Signing Date:12.03.2026 O.M.P. (COMM) 568/2016 Page 6 of 37
    19:10:21
    3 days. It is argued 15 sheets could not be called substantial number of
    sheets.

    25. The Arbitrator in holding that the repair work started without
    informing the respondent in violation of Clause No. 6(i) of the terms
    and conditions, has failed to appreciate the fact that the nature and
    environment in which floriculture is practised in very sensitive and
    vulnerable and any further delay in repair would have caused damage
    to the entire crop.

    26. The Arbitrator has also committed an error in accepting the argument
    advanced by the respondent that there was a delay in lodging the
    claim, and the same is in violation Clause No. 6(i) as the clause
    required any claim to be lodged forthwith. It was only because of
    another storm which struck the farm of the petitioner on 04.06.1998,
    the claim was lodged forthwith i.e. on 05.06.1998.

    27. He also submits that Clause No. 6(i) of the insurance policy required a
    notice is to be addressed to the respondent within 15 days of the
    damage or loss. In the present case, the incident occurred on
    02.06.1998 and 04.06.1998, and accordingly a notice was addressed
    on 05.06.1998 which is duly proved. The petitioner acted in a
    reasonable and prudent manner even in absence of the full Insurance
    policy document.

    28. In case the notice dated 05.06.1998 was in clear violation of Clause
    No. 6(i), the claim of the petitioner would not have been entertained
    by the respondent at all.

    29. Additionally, it is submitted that the Arbitrator has failed to ensure
    compliance with the mandatory statutory requirement as laid down

    Digitally Signed
    By:MAYANK
    Signing Date:12.03.2026 O.M.P. (COMM) 568/2016 Page 7 of 37
    19:10:21
    under Section 12 of the Act. He failed to make disclosure in writing of
    the “circumstances likely to give rise to justifiable doubts as to his
    impartiality and independence”. The Arbitrator was informed by the
    petitioner company vide letter dated 14.03.2012 that he was related to
    the Managing director (“M.D.”) of the petitioner company and
    because of internal family conflicts, the Arbitrator was requested to
    recuse. This conduct of refusal to recuse and non-compliance by the
    Arbitrator give rise to justifiable doubts regarding his impartiality.
    SUBMISSIONS ON BEHALF OF THE RESPONDENT

    30. Mr. Gaur, learned counsel for the respondent, states that the Award is
    a detailed Award passed after taking into consideration all the relevant
    evidence and material placed on record.

    31. The Courts in exercise of Section 34 jurisdiction cannot reappreciate
    evidence, and the Award cannot be challenged on ground of
    evidentiary objections like inadmissibility or impropriety of evidence.

    32. It is further submitted that the conduct of petitioner was in clear
    violation of the Clause No. 6(i), which contemplated a notice to be
    addressed forthwith on the happening of the incident but in the present
    case the notice was addressed to the respondent company on
    05.06.1998 after getting the replacement work done. The petitioner
    not only conducted the replacement work without informing the
    respondent but also failed to furnish proof of payment made to the
    persons employed/hired in the said work of getting the sheets
    replaced.

    Digitally Signed
    By:MAYANK
    Signing Date:12.03.2026 O.M.P. (COMM) 568/2016 Page 8 of 37
    19:10:21

    33. Further, the surveyor had assessed damage only to extent of 14.5
    sheets and the same was duly assessed and offered to the petitioner in
    full and final settlement but not accepted by them.

    34. The Arbitrator has correctly held that the claim filed by the petitioner
    is not substantiated by evidence and accordingly he was only entitled
    to Rs. 3,17,935/- with interest.

    35. It is also submitted that the Arbitrator has correctly relied on the
    survey report as the same is in consonance with law laid down in
    United India Insurance Co. Ltd. v. Roshan Lal Oil Mills Ltd.1, D.N.
    Bhadoni v. Oriental Insurance Co. Ltd.2
    ANALYSIS AND FINDINGS

    36. I have heard the learned counsels for the parties and perused the
    material and documents placed on record.

    SCOPE OF INTERFERENCE UNDER SECTION 34 OF THE
    ACT

    37. The scope of interference under Section 34 of the Act is now clearly
    established. The Court is not required to sit in appeal as an Appellate
    Court over the Award, it cannot venture an inquiry into the Award by
    reappreciation of evidence or reinterpretation of the terms of the
    contractual agreement merely because there is another probable view.
    Judicial intervention with the Award is permissible only on limited
    and specific grounds, as enumerated under Section 34 of the Act.
    These instances warranting interference include incapacity of a party,
    invalidity of the arbitration agreement, procedural irregularities, non-

    1

    (2000) 10 SCC 19.

    2

    1 (2012) C.P.J. 272 (NC).

    Digitally Signed
    By:MAYANK
    Signing Date:12.03.2026 O.M.P. (COMM) 568/2016 Page 9 of 37
    19:10:21
    compliance with the principles of natural justice and the Award being
    in conflict with the public policy of India. The Court is not
    required/empowered to reappreciate evidence or substitute its own
    view for that of the Arbitral Tribunal. As constantly reiterated, Section
    34
    of the Act, embodies the principle of minimal judicial interference,
    thereby preserving the foundational precept of the Act, the finality and
    efficacy of Arbitral Awards. Reliance is placed on Associate Builders
    v. DDA3and Delhi Airport Metro Express (P) Ltd.
    v. DMRC4.

    38. Section 34(2)(b)(ii) of the Act stipulates another ground of
    challenging the Arbitral award i.e. public policy of India, which was
    delineated by the Hon’ble Apex Court in the case of OPG Power
    Generation (P) Ltd. v. Enexio Power Cooling Solutions (India) (P)
    Ltd.5
    , this phrase “public policy of India” is explained with its
    contours in both the pre-amendment and the post-amendment position.
    The phrase must be accorded a restricted meaning post the 2015
    amendments, and a mere contravention of law is not sufficient. The
    fundamental principles which form the very basis of administration of
    justice and law fallwithin the scope of “Fundamental Policy of Indian
    Law”. The relevant paragraphs read as under:

    “39. Following the expansive view of the concept “contrary
    to public policy”, in DDA v. R.S. Sharma &
    Co. [DDA
    v. R.S. Sharma & Co., (2008) 13 SCC 80] , which
    related to a matter arising from a proceeding under Section
    34
    , as it stood prior to the 2015 Amendment, a two-Judge
    3
    (2015) 3 SCC 49.

    4

    (2022) 1 SCC 131.

    5

    (2025) 2 SCC 417.

    Digitally Signed
    By:MAYANK
    Signing Date:12.03.2026 O.M.P. (COMM) 568/2016 Page 10 of 37
    19:10:21
    Bench of this Court, on the scope of the power to set aside
    an arbitral award, summarised the general principles as
    follows : (SCC pp. 91-92, para 21)
    “21. … (a) An award, which is

    (i) contrary to substantive provisions of law; or

    (ii) the provisions of the Arbitration and Conciliation
    Act, 1996
    ; or

    (iii) against the terms of the respective contract; or

    (iv) patently illegal; or

    (v) prejudicial to the rights of the parties;
    is open to interference by the court under Section 34(2)
    of the Act.

    (b) The award could be set aside if it is contrary to:

    (a) fundamental policy of Indian law; or

    (b) the interest of India; or

    (c) justice or morality.

    (c) The award could also be set aside if it is so unfair
    and unreasonable that it shocks the conscience of the
    court.

    (d) It is open to the court to consider whether the
    award is against the specific terms of contract and if
    so, interfere with it on the ground that it is patently
    illegal and opposed to public policy of India.”

    55. The legal position which emerges from the aforesaid
    discussion is that after “the 2015 Amendments” in Section

    Digitally Signed
    By:MAYANK
    Signing Date:12.03.2026 O.M.P. (COMM) 568/2016 Page 11 of 37
    19:10:21
    34(2)(b)(ii) and Section 48(2)(b) of the 1996 Act, the phrase
    “in conflict with the public policy of India” must be
    accorded a restricted meaning in terms of Explanation 1.
    The expression “in contravention with the fundamental
    policy of Indian law” by use of the word “fundamental”
    before the phrase “policy of Indian law” makes the
    expression narrower in its application than the phrase “in
    contravention with the policy of Indian law”, which means
    mere contravention of law is not enough to make an award
    vulnerable. To bring the contravention within the fold of
    fundamental policy of Indian law, the award must
    contravene all or any of such fundamental principles that
    provide a basis for administration of justice and
    enforcement of law in this country.

    56. Without intending to exhaustively enumerate instances
    of such contravention, by way of illustration, it could be
    said that:

    (a) violation of the principles of natural justice;

    (b) disregarding orders of superior courts in India or
    the binding effect of the judgment of a superior court;
    and

    (c) violating law of India linked to public good or
    public interest, are considered contravention of the
    fundamental policy of Indian law.

    However, while assessing whether there has been a
    contravention of the fundamental policy of Indian law,

    Digitally Signed
    By:MAYANK
    Signing Date:12.03.2026 O.M.P. (COMM) 568/2016 Page 12 of 37
    19:10:21
    the extent of judicial scrutiny must not exceed the limit
    as set out in Explanation 2 to Section 34(2)(b)(ii).

    63. As we have already noticed, the object of
    inserting Explanations 1 and 2 in place of earlier
    explanation to Section 34(2)(b)(ii) was to limit the scope of
    interference with an arbitral award, therefore the
    amendment consciously qualified the term “justice” with
    “most basic notions” of it. In such circumstances, giving a
    broad dimension to this category [In conflict with most
    basic notions of morality or justice.] would be deviating
    from the legislative intent. In our view, therefore,
    considering that the concept of justice is open-textured, and
    notions of justice could evolve with changing needs of the
    society, it would not be prudent to cull out “the most basic
    notions of justice”. Suffice it to observe, they [ Most basic
    notions of justice.] ought to be such elementary principles of
    justice that their violation could be figured out by a prudent
    member of the public who may, or may not, be judicially
    trained, which means, that their violation would shock the
    conscience of a legally trained mind. In other words, this
    ground would be available to set aside an arbitral award, if
    the award conflicts with such elementary/fundamental
    principles of justice that it shocks the conscience of the
    Court. …”

    39. Perversity as a ground for setting aside an Arbitral Award is to be
    generally examined on the touchstone of the principle of

    Digitally Signed
    By:MAYANK
    Signing Date:12.03.2026 O.M.P. (COMM) 568/2016 Page 13 of 37
    19:10:21
    reasonableness. An Award which is founded on reasons and evidence,
    however limited or compendious they might be, cannot be categorised
    as perverse. When the view adopted by the Arbitrator is a plausible
    view, the same must be upheld.

    40. At the outset, Mr. Gaur, learned counsel for the respondent, states that
    the present petition is not maintainable as an Arbitral Award cannot be
    challenged on the ground of wrong conclusion by the Arbitrator
    seeking reappreciation of evidence by the Court. The Award is a
    detailed Award substantiated by the evidence available on record and
    the same does not suffer from any vice as enumerated under Section
    34
    of the Act warranting interference by this Court.

    41. With the scope of Section 34 of the Act in mind, I shall now deal with
    the rival contentions.

    REPORT OF THE SURVEYOR

    42. The petitioner has contended that the Award is patently erroneous as
    the Arbitrator has squarely relied on the survey report of Mr. J.K.
    Sharma, while he himself admitted during cross-examination that the
    report was based on his memory and he never actually had the
    opportunity to calculate the number of damaged sheets. The operative
    portions of the Award read as under:

    “Claim in this case has been made for 90 sheets whereas
    J.K. Sharma, surveyor confined the number of damaged
    sheets to 14.5 which has been increased to 15 by A.K.
    Choudhary, surveyor. It was pointed out by Shri Vachher,
    advocate that neither any inventory of the damaged
    property was prepared nor measurements, were taken by

    Digitally Signed
    By:MAYANK
    Signing Date:12.03.2026 O.M.P. (COMM) 568/2016 Page 14 of 37
    19:10:21
    J.K. Sharma, and the conclusion reached by this surveyor
    about damage of 14.5 sheets is erroneous. Report of another
    surveyor-A.K. Choudhary too is incorrect as he had taken
    for assessment of loss the number of sheets to be 15 based
    on the report of J.K. Sharma. Alongwith the affidavit of
    D.N. Shakkarwal, Deputy Manager, copy of the insurance
    policy in question was filed. Condition No. 6(i) of the policy
    provides that “on the happening of any loss or damage the
    insured shall forthwith give notice thereof to the company
    and shall within 15 days after the loss or damage or such
    further time as the company may in writing allow in that
    behalf, deliver to the company.” In cross- examination it
    was suggested to Shri Sakkarwal that the terms and
    conditions forming part of the policy in question were not
    supplied to the insured which suggestion he denied
    emphatically. As admitted by the Claimant the greenhouses
    was started sometime in January 1994 and claimant had
    purchased similar policy in previous years. Claimant must
    have been supplied the terms and conditions subject to
    which the policies were issued. In case the terms and
    conditions including condition No. 6(i) forming part of the
    policy in question was not supplied, the Claimant ought to
    have brought that fact to the notice of Insurance Company
    which it seem to have not done. There appears to be no
    reason not to believe, Shri Sakkarwal that the terms and
    conditions of the policy in question were also supplied to the

    Digitally Signed
    By:MAYANK
    Signing Date:12.03.2026 O.M.P. (COMM) 568/2016 Page 15 of 37
    19:10:21
    Claimant. In regard to the loss/damage on 2nd and 4th June
    1998, admittedly, the Insurance Company was intimated
    only on 5.06.1998 in the evening. J.K. Sharma had visited
    the site immediately on 6.06.1998. In para 5: of the
    Statement of Claim, it is alleged that the work of replacing
    the damaged sheets was carried on 3rd June 1998 and it
    continued on 4th June 1998; few more old sheets were
    damaged in the high wind and rains in the evening of 4th
    June 1998 and out of the stock of 91 sheets available with
    the Claimant, substantial number of sheets were utilized by
    the afternoon of 5th June 1998.It is in the cross-examination
    of Suresh Goel Managing Director that no agency was
    hired for replacement of the polyethylene sheets though the
    sheets were very costly and skilled persons and supervision
    needed to fix them; about 25 to 30 persons /villagers had
    done the job under his direct supervision and Claimant had
    made payment to them. He admitted that the claimant had
    not filed any documentary proof/evidence in regard to the
    payment to the said persons, before the Insurance Company
    or in arbitration proceedings. Replacement of a substantial
    number of sheets even before intimating the Insurance
    Company or visit of the first surveyor to the site is not only
    in contravention of said condition No. 6(i) but raises serious
    doubts in regard to the number of sheets damaged. This
    doubt is further strengthen by non-submission of proof in
    regard to the payment allegedly made to the persons

    Digitally Signed
    By:MAYANK
    Signing Date:12.03.2026 O.M.P. (COMM) 568/2016 Page 16 of 37
    19:10:21
    involved in the work which required skill. Estimate not
    prepared in the presence of J.K. Sharma, surveyor
    forwarded alongwith Claimant’s letter dated 2.11.1998 was
    in response to the letter dated 5.06.1998 and it cannot be
    safely considered for assessment of damage. Much
    importance cannot be attached to the inventory having not
    been prepared by J.K. Sharma and /or the number of sheets
    lying in stock with the Claimant in view of what has been
    found on physical verification at the site by him. Surveyors
    are appointed by the Insurance Company under the
    provisions of Insurance Act and their reports are to be
    given, due importance. One should have sufficient ground
    not to agree with the assessment made by them.(See Shri
    Vekenteshwara Syndicate Vs. Oriental Insurance Company
    Limited
    (2009) 8 SCC 507). For the forgoing discussion, I
    find absolutely no reason not to accept J.K Sharma’s report
    in regard to the number of polyethylene sheets damaged as
    modified by A.K Choudhary’s report. The number of sheets
    damaged must be taken to be 15 instead of 90 as claimed by
    the Claimant. At the cost of repetition it may be stated that
    in his said report A.K. Choudhary, surveyor has made
    additions towards freight charges, C& F charges and
    labour charges, reduced the percentage of depreciation and
    has maintained the value of salvage as suggested by J.K.
    Sharma based on weight. A.K. Choudhary assessed the
    damage at Rs. 4,17,935/- subject to deduction of Excess as

    Digitally Signed
    By:MAYANK
    Signing Date:12.03.2026 O.M.P. (COMM) 568/2016 Page 17 of 37
    19:10:21
    per the policy conditions. Amount of Rs. 3,17935/- seem to
    have been offered towards full and final settlement through
    the letter dated 22.4.1999 considering the deduction
    towards Excess clause of the policy. By the letter dated
    13.08.1999 the Claimant requested the Insurance Company
    to unconditionally make the payment of the said amount
    which was declined by the letter dated 27.08.1999 by the
    Insurance Company. As the Claimant was dissatisfied with
    the said quantum of damage it could not have been legally
    forced to receive amount towards full and final settlement.
    Since that amount is still being retained by the Insurance
    Company, it is liable to make payment thereof alongwith
    interest w.e.f. 27.8.1999 till the payment is made. In the
    facts &circumstances of the case, the rate of interest is
    quantified @ 10% per annum. In addition, the Claimant is
    entitled to the share of fee paid to the arbitrator and the
    amount of stamp duty on the award.

    Resultantly, award of Rs. 3,17,935/- alongwith interest @
    10% per annum w.e.f. 27.08.1999 thereon is passed in
    favour of the Claimant and against the respondent
    Insurance Company. Insurance Company will also pay the
    share of fee paid by the Claimant to the arbitrator and the
    amount of stamp duty on the award.

    Award made and pronounced at New Delhi on 17.03.2012.”

    (Emphasis supplied)

    Digitally Signed
    By:MAYANK
    Signing Date:12.03.2026 O.M.P. (COMM) 568/2016 Page 18 of 37
    19:10:21

    43. The Arbitrator in the Award specifically held that the number of
    sheets damaged must be taken as 15 instead of 90 as claimed by the
    petitioner. The Arbitrator primarily relied on the survey reports of Mr.
    JK Sharma and Mr. A.K. Chaudhary while rejecting the petitioner’s
    claim that 90 sheets were damaged.

    44. The Arbitrator categorically observed in the Award that “…Surveyors
    are appointed by the Insurance Company under the provisions of
    Insurance Act and their reports are to be given due importance…”
    and relied upon Shri Venkenteshwara Syndicate v. Oriental
    Insurance Company Limited6 to support the proposition that one
    should rely on the report of the insurance surveyor and should be
    reluctant to disagree with the findings made therein.

    45. However, a perusal of the Award reveals that the Arbitrator himself
    recorded serious deficiencies in the survey report. The petitioner’s
    counsel pointed out that neither was any inventory of the damaged
    property was prepared nor measurements were taken by Mr. JK
    Sharma, and the conclusion reached by this surveyor regarding
    damage to 14.5 sheets is erroneous. The Arbitrator did not
    categorically deal with these contentions but nonetheless accepted the
    survey report by stating that “Much importance cannot be attached to
    the inventory having not been prepared by J.K. Sharma and/or the
    number of sheets lying in stock with the Claimant in view of what has
    been found on physical verification at the site by him. Surveyors are
    appointed by the Insurance Company under the provisions of
    Insurance Act and their reports are to be given, due importance. …”

    6

    2009 (8) SCC 507.

    Digitally Signed
    By:MAYANK
    Signing Date:12.03.2026 O.M.P. (COMM) 568/2016 Page 19 of 37
    19:10:21

    46. A perusal of the cross-examination of the surveyor Mr. JK Sharma
    reveals the following crucial admissions on his part:

    i. He admitted that he did not actually calculate the total number
    of damaged sheets.

    ii. He stated that the report was based on his memory.
    iii. He mentioned that he was offered full cooperation by the
    petitioner to assess the damage on-site.
    iv. He acknowledged that he could not complete a thorough count
    of the damaged sheets.

    v. No inventory of damaged property was prepared.
    vi. No measurements were taken during the site visit.

    47. The relevant portions of the cross-examination of the surveyor Mr. JK
    Sharma, read as under:

    “Q. Is there any term or condition in the policy issued to the
    Claimant which provided that the Claimant was required to
    provide staff or labourers at the site to you for measuring
    the damaged sheets?

    Ans. The policy does not contain any such term/condition.
    Photographs are generally taken by us. On the spot I had
    not prepared any rough estimate/report. Inventory of the
    damaged insured goods was also not prepared. It is correct
    to suggest that the survey report was prepared on the basis
    of memory. The report was prepared after physical
    verification. In this case I had taken the photographs of the
    site and those have been filed along with my affidavit. As
    per Ext. RW2/1 photographs are not filed with the survey

    Digitally Signed
    By:MAYANK
    Signing Date:12.03.2026 O.M.P. (COMM) 568/2016 Page 20 of 37
    19:10:21
    report. There is no mention of the photographs in the Survey
    Report which I have seen. It is incorrect to suggest that no
    photographs were taken at the site. I admit that a meeting
    was held on 17.9.1998 at the office of the Claimant along
    with Ashok Sharma who is an employee of the Insurance
    Company and in that meeting it was decided that another
    visit would be made to the site. I visited the site thereafter
    on 19.9.1998. On that date I was alone when I visited the
    site. I admit that the Claimant had provided labourers and
    offered to measure the loss. They had co-operated in
    measuring the loss. Number of the sheets damaged is shown
    as 13 in the Survey Report. The Claimant had claimed that
    the number of sheets damaged were 94. I have seen the copy
    of the Claim Form which would show that the Claimant had
    claimed damage for 90 sheets. A letter was sent on
    5.10.1998 to the Claimant. I admit that thereafter I had not
    visited the site. Claimant had sent reply to the letter dated
    2.11.1998. Copy of the letter dated 2.11.1998 was shown to
    me which does not contain acknowledgement of receipt with
    my signature. I had received this letter. Claimant must have
    sent the letter dated 2.11.1998 to the respondent-Insurance
    Company also. On page 19 of the report, it is stated that the
    Claimant had claimed that the number of the sheets which
    were damaged were 104. It is incorrect to suggest that the
    report was prepared on the basis of surmises and
    conjectures and not on the basis of the number of the sheets

    Digitally Signed
    By:MAYANK
    Signing Date:12.03.2026 O.M.P. (COMM) 568/2016 Page 21 of 37
    19:10:21
    which were damaged. The Claim was allowed for 14.5
    sheets in the Survey Report.

    Q. Can you furnish any explanation as to why when in your
    report you had mentioned that the number of sheets
    damaged were 13, you had recommended for payment of
    claim for 14.5 sheets?

    Ans. Total number of damaged sheets was calculated by me.
    They have a standard on each roll and then after division
    the result is calculated about the number of damaged rolls.
    On the first visit I had spent 4 or 5 hours. Subsequent visits
    also were of the same duration. I admit that the area of the
    Farm House was approximately 15 acres. It is incorrect to
    suggest that some of the pieces of the torn/damaged sheets
    were blown in the air and the damaged sheets were 90 in
    number. It is correct that there is always a difference in
    colour between a new sheet and an old sheet.”

    (Emphasis supplied)

    48. Though a report of the surveyor is important and holds substantial
    value in the eyes of law but the same is neither sacrosanct not binding,
    it is only a piece of evidence. The Hon’ble Division Bench of this
    Court in its judgment titled United India Insurance Co. Ltd v. M/S
    Valley Iron & Steel Co. Ltd.7
    , while discussing issue-wise assessment
    traced down a catena of Supreme Court judgments. The relevant
    paragraphs of the judgment read as under:

    7

    FAO(OS) (COMM) 165/2025, pronounced on 24.12.2025.

    Digitally Signed
    By:MAYANK
    Signing Date:12.03.2026 O.M.P. (COMM) 568/2016 Page 22 of 37
    19:10:21
    “20.4.3 Appellant’s contention that surveyor’s report ought
    to have been accepted at face value, does not hold water,
    particularly in the light of the law by the Supreme Court.

    The Supreme Court, in a catena of judgments, has
    consistently held that a surveyor’s report, though statutorily
    recognised, is only a piece of evidence, is neither sacrosanct
    nor binding, and may be departed from where it suffers
    from infirmities or is outweighed by more reliable material
    on record. For the purpose of reference, said decisions are
    extracted as under:

    ii. National Insurance Co. Ltd. v. Hareshwar Enterprises
    (P) Ltd.
    (2021) 17 SCC 682:

    “13. In that view of the matter the only question on merits
    which needs consideration herein is with regard to the loss
    assessed towards destruction of the stock-intrade in the fire
    incident. On this aspect, the learned counsel for the
    appellant while contending that Ncdrc has committed an
    error in relying on the surveyor report as sacrosanct
    without giving credence to the investigation report has
    referred to the decision in New India Assurance Co. Ltd. v.
    Pradeep Kumar [New India Assurance Co. Ltd.
    v. Pradeep
    Kumar, (2009) 7 SCC 787 : (2009) 3 SCC (Civ) 314] and

    Digitally Signed
    By:MAYANK
    Signing Date:12.03.2026 O.M.P. (COMM) 568/2016 Page 23 of 37
    19:10:21
    referred to paras 21 and 22 which read as hereunder :
    (SCC pp. 791-92)

    14. In the said decision, it is no doubt held that though the
    assessment of loss by an approved surveyor is a prerequisite
    for payment or settlement of the claim, the surveyor report
    is not the last and final word. It is not that sacrosanct that it
    cannot be departed from and it is not conclusive. The
    approved surveyor’s report may be the basis or foundation
    for settlement of a claim by the insurer in respect of loss
    suffered by insured but such report is neither binding upon
    the insurer nor insured. On the said proposition, we are
    certain that there can be no quarrel. The surveyor’s report
    certainly can be taken note as a piece of evidence until more
    reliable evidence is brought on record to rebut the contents
    of the surveyor’s report.

    17. Having noted the said decisions, we are of the opinion
    that the same cannot alter the position in the instant case.
    On the proposition of law that the surveyor’s report cannot
    be considered as a sacrosanct document and that if there is
    any contrary evidence including investigation report,
    opportunity should be available to produce it as rebuttal
    material, we concur. However, the issue to be noted is as to
    whether the surveyor’s report in the instant case adverts to

    Digitally Signed
    By:MAYANK
    Signing Date:12.03.2026 O.M.P. (COMM) 568/2016 Page 24 of 37
    19:10:21
    the consideration of stock position in an appropriate
    manner and in that circumstance whether an investigation
    report which is based on investigation that was started
    belatedly should take the centre stage. The fact remains that
    the surveyor’s report is the basic document which has
    statutory recognition and can be made the basis if it inspires
    the confidence of the adjudicating forum and if such forum
    does not find the need to place reliance on any other
    material, in the facts and circumstances arising in the case.
    …”

    (Emphasis supplied)

    49. In this view of the matter, the recommendation/report of the surveyor
    is only evidentiary in nature and not a binding or sacrosanct
    document. When the report is perfunctory, casual or suffers from
    infirmity, the same has to be rejected by the Arbitrator.

    50. In the present case, the cross-examination of Mr. J.K. Sharma itself
    reveals casualness and a perfunctory manner in which the report was
    prepared. A survey is an integral and most important cog in the
    wheelof insurance claim settlements. The survey report is a
    foundational document on which the first assessment of loss is made.
    The survey report dated 09.11.1998 of Mr. JK Sharma which forms
    the fountainhead of the Award is without actual measurement of loss
    and based on the surveyor’s memory. This survey report at best is the
    guesswork of the surveyor. The petitioner in his cross-examination has

    Digitally Signed
    By:MAYANK
    Signing Date:12.03.2026 O.M.P. (COMM) 568/2016 Page 25 of 37
    19:10:21
    clearly been able to demolish the surveyor’s method to assess loss,
    and its evidentiary value for quantification of loss.

    51. The evidence led by the witnesses of the petitioner namely Suresh
    Goel, M.D. (CW-1), Gautam Goel, Director (CW-2), Zuruddiun (CW-

    3) and Sanjeev Tyagi (CW-4), as well as stock registers attached as
    exhibit-CW-1/10 in the Claim petition, had not even been discussed in
    the Award. Even though the Arbitrator has stated that these witnesses
    of the petitioner duly tendered their evidence and that the same was
    also subjected to the rigour of cross examination, but the Arbitrator
    failed to analyse, even in one single paragraph, the evidence led on
    behalf of the petitioner and has squarely relied on the respondent’s
    version on the basis of the report of the surveyor.

    52. The Arbitrator while performing its adjudicatory function even in
    presence of a survey report was required to examine, consider and
    weigh the evidence of the claimant also, which in the present case had
    not been adverted to at all, and in fact, the Award is only based on the
    observations of the surveyor made in the survey report.

    53. The paragraph No. 18 (i) of the affidavit furnished in evidence by Mr.
    Suresh Goel (CW-1) mentions that the surveyor in his report has
    categorically stated that the requisite measurement was undertaken for
    each damaged sheet in front of the directors of the petitioner company.
    However, this statement is inconsistent with the surveyor’s letter dated
    05.10.1998 wherein he specifically mentioned that the measurement
    of the damaged polyethylene sheets could not be carried out as the
    petitioner failed to provide him with proper labour for the said

    Digitally Signed
    By:MAYANK
    Signing Date:12.03.2026 O.M.P. (COMM) 568/2016 Page 26 of 37
    19:10:21
    purpose. The relevant portions of the report dated 09.11.1998 reads as
    under:

    “Methodology for assessment of loss.

    Damage to the polyethylene sheets, was assessed after
    measuring each damaged sheet. The damages were
    critically examined with respect to the cause of accident
    mentioned in the claim form.

    Damage to sheets were counted in front of insured’s
    representative. Then we measured length and width of each
    sheet. All the sheets were of standard size of 46 X8.50
    meters. …”

    (Emphasis supplied)

    54. The said observation in the report of the surveyor, which forms the
    basis of the report and the Award, is totally contrary to the evidence of
    the surveyor in his cross-examination. Mr. JK Sharma categorically
    admitted in his cross-examination that no inventory or rough estimate
    was prepared at the site. He further stated that, the report was prepared
    on the basis of his memory and that he last visited the site on
    19.09.1998. Even though, in his cross-examination, the surveyor
    stated that he had taken photographs of the damaged sheets at that
    relevant time, however they were neither filed with the survey report,
    nor mentioned in the report. The relevant portions of the cross-
    examination read as under:

    “…I visited the site thereafter on 19.9.1998. On that date I
    was alone when I visited the site. I admit that the Claimant
    had provided labourers and offered to measure the loss.

    Digitally Signed
    By:MAYANK
    Signing Date:12.03.2026 O.M.P. (COMM) 568/2016 Page 27 of 37
    19:10:21
    They had co-operated in measuring the loss. Number of the
    sheets damaged is shown as 13 in the Survey Report. The
    Claimant had claimed that the number of sheets damaged
    were 94. I have seen the copy of the Claim Form which
    would show that the Claimant had claimed damage for 90
    sheets. A letter was sent on 5.10.1998 to the Claimant. I
    admit that thereafter I had not visited the site. …
    Q. I put it to you that between 2.6.1998 and 5.6.1998, the
    Claimant had replaced around 90 sheets and the difference
    of the colour in the sheets was clearly visible?
    There was no colour difference and one could easily make
    out that the sheets had never been replaced.
    It is incorrect to suggest that the salvage of the damaged
    sheets was lying at the site. It is incorrect that despite the
    salvage of the damaged 90 sheets at the site, I had not
    measured the same. I admit that I had not measured the
    damaged/salvaged sheets up to 5.10.1998. I have a vague
    idea that A.K. Chaudhary was appointed as a Surveyor later
    on by the respondent-Insurance Company. I have no idea
    that A.K. Chaudhary was appointed since my report was
    erroneous. It is incorrect to suggest that I had not stayed for
    more than 2 hours on any of my visits at the site. It is
    incorrect to suggest that I am deposing falsely. …”

    (Emphasis Supplied)

    55. A bare perusal of the letter dated 05.10.1998 also reveals that the
    measurement of the polyethylene sheets could not be undertaken on

    Digitally Signed
    By:MAYANK
    Signing Date:12.03.2026 O.M.P. (COMM) 568/2016 Page 28 of 37
    19:10:21
    the date of earlier visit due to the petitioners lack of cooperation with
    the surveyor in getting the waste sheets counted. The relevant letter is
    reproduced as under:

    Digitally Signed
    By:MAYANK
    Signing Date:12.03.2026 O.M.P. (COMM) 568/2016 Page 29 of 37
    19:10:21
    Digitally Signed
    By:MAYANK
    Signing Date:12.03.2026 O.M.P. (COMM) 568/2016 Page 30 of 37
    19:10:21

    56. This letter is also clearly contradicted by the evidence of Mr. JK
    Sharma, who in his cross-examination has categorically stated that the
    petitioner had provided adequate labour. The relevant portion of the
    cross-examination reads as under:

    “…I admit that the Claimant had provided labourers and
    offered to measure the loss. They had co-operated in
    measuring the loss. …”

    57. In view of the above, there is material inconsistency in the statements
    made by the surveyor. While the report of the surveyor dated
    09.11.1998 records that each damaged sheet was measured in the
    presence of the insured’s representatives, his earlier letter dated
    05.10.1998, as well as his categorical admission during cross-
    examination, reveal that no such measurement exercise was actually
    conducted owing to non-availability of proper labour and lack of
    cooperation from the petitioner. This contradiction is apparent on the
    face of the record and shakes the reliability and authenticity of the
    report of the surveyor. This ground of inconsistency was raised before
    the Arbitrator by the petitioner but the same was not considered by
    him.

    58. A survey report based merely on memory, without proper calculation,
    verification, inventory preparation or measurements, cannot form the
    sole basis for determining the quantum of insurance claim, especially
    when the petitioner has placed on record documentary evidence in the
    form of stock registers showing replacement of 90 sheets. These stock
    registers maintained in ordinary course of business have not even been
    discussed in the Award.

    Digitally Signed
    By:MAYANK
    Signing Date:12.03.2026 O.M.P. (COMM) 568/2016 Page 31 of 37
    19:10:21

    59. In the present case, the Arbitrator erred by placing reliance on the
    survey report despite its deficiencies, which were duly admitted by the
    surveyor himself in his cross-examination, while simultaneously not
    considering the petitioner’s evidence at all.

    60. In this view of the matter, it is crucial to point out that the Arbitrator
    has failed to consider the contentions raised by the petitioner, material
    placed on record and has also erred in accepting the survey report on
    its face value without giving reasoned analysis and findings. Thus, the
    Award which clearly ignores the evidence available on record and is
    based on findings which are in contradiction to the clear admissions
    on record, cannot be sustained.

    61. Even though the Arbitrator is the master of quality and quantity of
    evidence in Arbitral proceedings, an Award which ignores material
    evidence and gives findings contrary to the evidence on record is
    perverse and deserves to be set aside. The relevant paragraph of
    Associate Builders v. DDA (Supra) reads as under:

    “31. The third juristic principle is that a decision which is
    perverse or so irrational that no reasonable person would
    have arrived at the same is important and requires some
    degree of explanation. It is settled law that where:

    (i) a finding is based on no evidence, or

    (ii) an Arbitral Tribunal takes into account something
    irrelevant to the decision which it arrives at; or

    (iii) ignores vital evidence in arriving at its decision,
    such decision would necessarily be perverse.”

    (Emphasis Supplied)

    Digitally Signed
    By:MAYANK
    Signing Date:12.03.2026 O.M.P. (COMM) 568/2016 Page 32 of 37
    19:10:21

    62. In view of the above, on this ground alone the impugned Award dated
    17.03.2012, is hereby set aside.

    SECTION 12: NON-DISCLOSURE BY THE ARBITRATOR

    63. Learned counsel for the petitioner has also raised a contention that the
    Arbitrator in the present case has failed/ignored to make disclosure
    which is mandated by the Section 12 of the Act. The petitioner in
    support of its contention relies on a letter dated 14.03.2012 addressed
    by the M.D. of the petitioner Company to the Arbitrator, wherein the
    Arbitrator was requested to recuse himself from the proceedings on
    the ground of being related with the M.D. of the petitioner company,
    thereby raising doubts about the impartiality of the Arbitrator in
    rendering the Award. The relevant letter dated 14.03.2012 reads as
    under:

    Digitally Signed
    By:MAYANK
    Signing Date:12.03.2026 O.M.P. (COMM) 568/2016 Page 33 of 37
    19:10:21
    Digitally Signed
    By:MAYANK
    Signing Date:12.03.2026 O.M.P. (COMM) 568/2016 Page 34 of 37
    19:10:21

    64. The petitioner has only fleetingly invoked the embargo of Section 12
    of the Act. In any event, the petitioner had participated in the Arbitral
    proceedings, knowingly, and being fully aware of the identity of the
    Arbitrator and his relationship with the M.D. of the petitioner
    company. Additionally, it was only three days prior to the passing of
    the Award that the petitioner company requested the Arbitrator to
    recuse himself from the proceedings. No reasons have been given by
    the petitioner for the delay in addressing the letter dated 14.03.2012,
    after a period of about 2 years from the date of appointment of
    Arbitrator on 30.11.2009 by mutual consent of the parties and even
    the allegations of partiality are vague and ambiguous. For the said
    reasons, I am not inclined to entertain this ground of non-disclosure
    raised by the petitioner.

    CLAUSE NO. 6(i) NOTICE AFTER LOSS/DAMAGE

    65. Clause No. 6(i) of the policy which is reproduced in the Award, reads
    as under:

    “On the happening of any loss or damage the insured shall
    forthwith give notice thereof to the company and shall
    within 15 days after the loss or damage or such further time
    as the company may in writing allow in that behalf, deliver
    to the company”

    66. The Arbitrator with respect to the aforesaid clause has held that
    “replacement of a substantial number of sheets even before intimating
    the Insurance Company or visit of the first surveyor to the site is not
    only in contravention of said condition No. 6(i) but raises serious
    doubts in regard to the number of sheets damaged.”

    Digitally Signed
    By:MAYANK
    Signing Date:12.03.2026 O.M.P. (COMM) 568/2016 Page 35 of 37
    19:10:21

    67. To my mind there is substantial compliance of Clause No. 6(i), which
    prescribes the outer limit of 15 days to furnish the requisite
    information and does not unequivocally/mandatorily state that the
    same be furnished immediately. The clause mentions the word
    “forthwith” and the words as used are to be given their intended
    meaning. From a perusal of the aforesaid clause it is clear that the
    insured is required to inform the insurer “forthwith” about the loss
    sustained by it and in the context of this Clause “forthwith” means “as
    soon as possible” and maximum within 15 days unless time extended
    by the insurance company. The first storm hit the greenhouses of the
    petitioner on 02.06.1998 and the second storm on 04.06.1998,
    thereafter the petitioner furnished notice to the insurance company on
    05.06.1998. In view of the matter, the petitioner company has
    informed the respondent “forthwith” about the loss suffered.

    68. The Arbitrator has erred in holding that the replacement of sheets
    prior to any intimation to the insurer violated Clause No. 6(i) of the
    policy. The nature of damage required immediate restoration and the
    representatives of the petitioner acted in a manner as every prudent
    person ought to have. I am of the view that the actions were
    reasonable and in any case, the insured is required to take reasonable
    steps in order to prevent extensive damage to its plants.

    69. An Award which does not analyse the evidence led by the parties and
    ignores vital evidences placed on record deserves to be set aside under
    Section 34 of the Act.

    70. The reasoning of Arbitrator is cryptic, without application of mind,
    ignoring the clear evidence available on record and is consequently

    Digitally Signed
    By:MAYANK
    Signing Date:12.03.2026 O.M.P. (COMM) 568/2016 Page 36 of 37
    19:10:21
    perverse. Thus, the same needs to be set aside by this Court in the
    interest of justice.

    CONCLUSION

    71. The Award is squarely based on a survey report which, though an
    important piece of evidence, is not a sacrosanct document and cannot
    be accepted at face value when it is clearly defective. The Arbitrator
    could not have relied solely on the survey report to deliver its findings
    while disregarding other vital evidence placed on record. Such non-
    consideration of vital evidence and contentions of the petitioner at all
    by the Arbitrator amounts to perversity.

    72. Accordingly, the impugned Award dated 17.03.2012 is hereby set
    aside.

    73. The petition is allowed and disposed of in the aforesaid terms along
    with pending applications, if any.

    JASMEET SINGH, J
    MARCH 12th, 2026/(SS)

    Digitally Signed
    By:MAYANK
    Signing Date:12.03.2026 O.M.P. (COMM) 568/2016 Page 37 of 37
    19:10:21



    Source link

    LEAVE A REPLY

    Please enter your comment!
    Please enter your name here