Union Of India vs Senbo Engineering Limited on 11 March, 2026

    0
    40
    ADVERTISEMENT

    Calcutta High Court

    Union Of India vs Senbo Engineering Limited on 11 March, 2026

    Author: Debangsu Basak

    Bench: Debangsu Basak

                                               1
    
                                                                    2026:CHC-OS:76-DB
    
                          IN THE HIGH COURT AT CALCUTTA
                         COMMERCIAL APPELLATE JURISDICTION
                                 COMMERCIAL DIVISION
                                     ORIGINAL SIDE
    
    Present:
    The Hon'ble Justice Debangsu Basak
                 And
    The Hon'ble Justice Md. Shabbar Rashidi
    
                                 AO COM 36 of 2024
                                        WITH
                                 AP COM 208 of 2024
                                   Union of India
                                         Vs.
                             Senbo Engineering Limited
                                        With
                                   OCOT 1 of 2025
                                   Union of India
                                         Vs.
                             Senbo Engineering Limited
    For the Appellant        :     Mr. Sidhartha Lahiri, Adv.
                                   Mr. Nandlal Singhania, Adv.
                                   Ms. Amrita Pandey, Adv.
    
    For the Respondent       :     Mr. Pradip Kr. Dutta, Sr. Adv.

    Mr. Nilay Sengupta, Adv.

    Mr. Sujit Banerjee, Adv.

    SPONSORED

    Mr. Mohit Gupta, Adv.

    Hearing Concluded on     :     January 21, 2026
    
    Judgement on             :     March 11, 2026
    
    DEBANGSU BASAK, J.:-
    
    

    1. Appellant has assailed the judgment and order dated August

    5, 2024 passed in AP-COM 208 of 2024 in AO COM 36 of 2024.
    2

    2026:CHC-OS:76-DB

    Respondent has filed a cross objection which was registered as

    OCOT 1 of 2025.

    2. For the sake of convenience the parties in the appeal and the

    cross objection are referred to in the manner as they appear in the

    appeal. Both the appeal and the cross objection were heard

    together.

    3. By the impugned judgment and order, learned Single Judge

    in exercise of powers under Section 34 of the Arbitration and

    Conciliation Act, 1996, has allowed a part of the challenge by

    setting aside a portion of the impugned award of the Arbitral

    Tribunal before it, and allowed and upheld the balance part of the

    award.

    4. Learned advocate appearing for the appellant has contended

    that, a tender dated February 11, 2011 was floated in which, the

    respondent participated. The appellant had issued the Letter of

    Acceptance on July 19, 2011. Finding that, the respondent was not

    executing the contract in terms thereof, appellant had terminated

    the same on November 10, 2017. A notice under Section 21 of the

    Act of 1996 was issued on June 21, 2017. The Arbitral Tribunal

    had entered into reference and in consequence thereto made and
    3

    2026:CHC-OS:76-DB

    published the award on March 9, 2021 with a corrigendum thereof

    on November 27, 2021.

    5. Learned Advocate appearing for the appellant has drawn the

    attention of the Court to the statement of claim. He has contended

    that, all claims made by the appellant before the Arbitral Tribunal

    fell within the excepted clause of the arbitration agreement. In this

    regard, he has referred to the arbitration clause and the excepted

    clause contained in the contract.

    6. Learned advocate appearing for the appellant has contended

    that, out of 11 claims, the Arbitral Tribunal allowed claim nos.

    1,2,7,8 and 11. All of such claims which were allowed by the

    Arbitral Tribunal had fallen within the excepted clause.

    7. Relying upon 2014 Volume 9 Supreme Court Cases 246

    (Harsha Constructions Vs. Union of India and Others), 2022

    Volume 4 Supreme Court Cases 463 (Indian Oil Corporation

    Limited Vs. Shree Ganesh Petroleum Rajgurunagar) and 2023

    Volume 2 Supreme Court Cases 539 (Indian Oil Corporation

    Limited Vs. NCC Limited) learned Advocate appearing for the

    appellant has contended that, since, the disputes adjudicated upon

    fell within the excepted clause, the award cannot be sustained.
    4

    2026:CHC-OS:76-DB

    Learned Judge has erred in sustaining a portion of the award

    passed by the Arbitral Tribunal.

    8. Learned Senior Advocate appearing for the respondent has

    contended that, none of the claims allowed by Arbitral Tribunal fell

    within the excepted clause. He has relied upon 2011 Volume 5

    Supreme Court Cases 758 (J.G. Engineers Private Limited Vs.

    Union of India and Another) and 2025 SCC Online SC 419 (Dr.

    Poornima Advani and Anr Vs. Government of NCT and Anr) in

    support of such contention.

    9. Learned Senior Advocate appearing for the respondent has

    referred to the claims made by the Arbitral Tribunal as also the

    excepted clause. He has contended that, none of the claims fell

    within the excepted clause.

    10. Learned Senior Advocate appearing for the respondent has

    contended that, the learned Judge erred in disallowing claim Nos.

    2,8 and 11 which were granted by the Arbitral Tribunal. He has

    contended that, none of those claims fell within the excepted

    clause.

    11. In course of hearing of the appeal and this cross objection we

    had invited the attention to the learned counsel for the parties to

    2024 SCC Online SC 2632 (Punjab State Civil Supplies
    5

    2026:CHC-OS:76-DB

    Corporation Limited Versus Sanman Rice Mills) on the scope

    and ambit of Section 37 of the Act of 1996. The learned Counsel for

    the respective parties had made their submissions on the same.

    12. The appellant had invited bids comprising of a technical and

    financial construction of viaduct including related works for 2.16

    km length including substructure on pile foundation with

    substructure and superstructure work of Dum Dum cantonment

    station building. The respondent had participated in such tender

    process and was successful therein. Appellant had issued a work

    order dated July 19, 2011 to the respondent.

    13. The contract between the parties had reciprocal obligations to

    be performed by each of the parties. Disputes and differences had

    arisen between the parties which were referred to arbitration of the

    Arbitral Tribunal.

    14. In the arbitration proceedings, the respondent had filed a

    statement of claim containing 11 heads of claims, which are as

    follows:-

            Claim No.           Description            Claim Amount in
    
                                                            (Rs.)
                                              6
    
                                                                             2026:CHC-OS:76-DB
    
    Claim No. 1   Claim       of    amount         for      Rs. Rs.6,30,01,176.26
    
                  2,47,81,885.20            withheld         in
    
                  CC/30th Account Bill
    
                  Claim of amount withheld/not
    
                  released         towards             CC/7th
    
                  Escalation         Bill        for        Rs.
    
                  2,24,53,931.00 against escalation
    
                  in prices calculated in terms of
    
                  the   formula      provided          in   the
    
                  contract.
    
                  Claim        Amount            for        Rs.
    
                  98,16,012.33 against CC/31st On
    
                  Account Bill submitted.
    
                  Claim        Amount            for        Rs.
    
                  59,49,347.73        towards          CC/8th
    
                  Escalation Bill submitted.
    
    

    Claim No. 2 Recovery of Security deposit as Rs. 10,48,723.00

    retention money from the

    Claimant’s On Account Bills for

    Rs. 10,48,723/-

    Claim No. 3 Claim for Refund of total Bank Rs.22,55,37,111.00

    Guarantees invoked amounting to

    Rs. 22,55,37,111/-

    7

    2026:CHC-OS:76-DB

    Claim No. 4 Loss due to idle on-site and off- Rs.23,65,23,517.00

    site overheads during the entire

    period upto 30-08-2017 = Rs.

    23,65,23,517/-

    Claim No. 5 Loss due to idle machinery upto Rs.30,47,30,000.00

    30-08-2017=Rs. 30,47,30,000/-

    Claim No. 6 Loss of profit during the entire Rs.57,55,40,556.00

    period upto 30-08-2017=Rs.

    57,55,40,556/-

    Claim No. 7 Refund of interest on Mobilization Rs. 2,97,35,112.00

    Advance paid by the Claimant so

    far beyond the original schedule

    and waiver of the same in

    future=Rs. 2,97,35,112/-

    Claim No. 8 Refund of commission paid to Rs. 1,95,10,505.00

    Bank for extension of Bank

    Guarantees from time to time

    beyond the original contractual

    period = Rs. 1,95,10,505/-

    
    Claim No. 9   Non-payment            of       item    for Rs. 1,70,00,000.00
    
                  dismantling       of    hutments        for
    
                  removal of encroachments from
    
                  site and reconstruction of new
    
                  hutments along with improvement
                                                     8
    
                                                                                 2026:CHC-OS:76-DB
    
                          of land and drainage system - Rs.
    
                          1,70,00,000/-
    
          Claim           Claim      for     loss        due     to Rs. 4,90,00,000.00
    
          No. 10          unauthorised offloading of work
    
                          between Ch. 3009.945 M to Ch.
    
                          3123.445 M for Rs. 4,90,00,000/-
    
          Claim           Claim for interest
    
          No. 11
    
          Claim           Cost of Arbitration Proceedings =
    
          No. 12          As to be accrued.
    
    

    Total claim Amount is Rs. (Rupees One Hundred Rs.152,16,26,700.26

    Fifty Two crore sixteen lacks twenty six

    thousand seven hundred and paisa twenty six)

    15. The appellant had filed a counter statement and counterclaim

    before the Arbitral Tribunal. In the counter statement and

    counterclaim, the appellant had two heads of claims, namely claims

    on account of damages and claims for costs of arbitration. The

    respondent had filed a rejoinder to the counter statement and

    counterclaim of the appellant.

    16. Arbitral Tribunal had made and published the award on

    March 9, 2021. Arbitral Tribunal had corrected the award on March

    27, 2021. Arbitral Tribunal had by the award as corrected allowed
    9

    2026:CHC-OS:76-DB

    all the 11 claims of the respondent and dismissed the two

    counterclaims of the appellant. The Arbitral Tribunal had rejected

    claims counter No. 1 (iv), 4, 5, 6, 9, and 10 of the respondent. These

    rejections have not been challenged by the respondent.

    17. Appellant had challenged the award dated March 9, 2021 as

    corrected on March 27, 2021 under Section 34 of the Arbitration

    and Conciliation Act, 1996. Such challenge has been partly allowed

    and partly disallowed by the impugned judgement and order.

    18. By the impugned judgement and order, learned Single Judge

    has upheld the challenge in respect of claims Nos. 2, 8 and 11 of

    the respondent before the Arbitral Tribunal while rejecting the

    challenge towards claim Nos. 1, 3 and 7.

    19. The appellant has premised the primary, if not the only,

    ground of challenge to the award upon the Excepted Clause in the

    contract, which is as follows: –

           Existing Clause                  Revised Clause
    
    
           63 -                             63 -
    
    

    Matters finally determined by Matters finally determined

    the Railway – all disputes and by the Railway – All disputes

    differences of any kind and differences of any kind

    whatsoever arising out of or in whatsoever arising out of or
    10

    2026:CHC-OS:76-DB

    connection with the contract, in connection with the

    whether during the progress of contract, whether during the

    the work or after its completion progress of the work or after

    and whether before or after the it’s the determination of the

    determination of the contract, contract, shall be referred by

    shall be referred by the the contractor to the GM

    contractor to the Railway and and the GM shall within 120

    the Railway shall within 120 days after receipt of the

    days after receipt of the Contractor’s representation

    Contractor’s representation make and notify decisions

    make and notify decisions on on all matters referred to by

    all matters referred to by the the contractor in writing

    contractor in writing provided provided that matters for

    that matters for which which provision has been

    provisions has been made in made in clauses 8, 18, 22(5),

    clauses 8, 18, 22(5), 39, 43(2), 39, 43(2), 45(a), 55, 55-A(5),

    45(a), 55, 55-A(5), 57, 57A, 57, 57A, 61(1), 61 (2) and

    61(1), 61 (2) and 62(1) to (xii)(B) 62(1) to (xii)(B) of General

    of General Conditions of Conditions of Contract or in

    Contract or in any clause of the any clause of the special

    special conditions of the conditions of the contract

    contract shall be deemed as shall be deemed as ‘excepted

    ‘excepted matters’ and matters’ shall stand

    decisions of the Railway specifically excluded from
    11

    2026:CHC-OS:76-DB

    authority, thereon shall be final the purview of the

    and binding on the contractor arbitration clause.

    provided further that ‘excepted

    matters’ shall stand specifically

    excluded from the purview of

    the arbitration clause and not

    be referred to arbitration.

    Note : Existing Clause be read

    with Correction Slip No. 2

    issued vide Board’s letter No.

    96/CE-I/CT/29 dated 22-2-

    2021.

    20. Harsha Constructions (supra) has held that, even if a non

    arbitrable dispute is referred to arbitration or even if an issue is

    framed by arbitrator as to such dispute, it is not open for an

    arbitrator to arbitrate on such non arbitrable dispute since it was

    beyond his jurisdiction.

    21. Shree Ganesh Petroleum Rajgurunagar (supra) has held

    that, award on issues and matters beyond the scope of arbitration

    clause are invalid.

    12

    2026:CHC-OS:76-DB

    22. NCC Limited (supra) has held that, an arbitration clause is

    required to be strictly construed. Any expression in the clause must

    unequivocally express the intent of arbitration. If a clause stipulates

    that under certain circumstances there can be no arbitration and

    they are demonstrably clear thus the controversy pertaining to

    appointment of arbitrator has to be put to rest.

    23. J.G. Engineers Private Limited (supra) has considered the

    excepted matter clause in the contract. It has held that, a contract

    cannot provide that one party will be the arbitrator to decide

    whether he committed breach or the other party committed the

    breach. Consequently, it has held that, the question whether the

    employer or the contractor was responsible for the delay in the

    execution of work was arbitrable.

    24. Dr. Poornima Advani (supra) has held that, if on the facts of

    the case, the doctrine of restitution is attracted interest should

    follow. It has held that, when a person is deprived of the use of his

    money to which he is legitimately entitled, he has a right to be

    compensated for the deprivation which may be called interest or

    compensation.

    25. Arbitral Tribunal has dealt with the plea of Excepted Clause

    as follows: –

    13

    2026:CHC-OS:76-DB

    ” 7.2 Excepted Matters
    7.2.1. Respondent’s Case: The Respondent took a plea of
    various Matters being Excepted Matters in terms of the
    contract with regard to various claims like measurements,
    determination of rates for new items etc.
    7.2.2. Claimant’s Case: The Railway have taken the plea
    of Excepted matters with regard to the final measurements,
    and rates for newly introduced item E2 for affecting
    reduction. The claimant argued that they were not
    associated in either the final measurements not the
    determination of the new negative rate and his
    protestations were also simply ignored. Without following
    the due process as per GCC of associating the Contractor or
    entertaining his representation, the Claimant argued that
    the Railway’s plea of Excepted matter has no merit.
    7.2.3. Deliberations of the AT: A Contract has to be read
    in its totality. AT is of the view that the exceptions like
    Excepted Matter cannot be applied in isolation. To take the
    Respondent’s argument regarding Measurement of
    quantities, undoubtedly there is a contractual provision that
    it is an ‘excepted matter’, but subject to certain pre-

    conditions enjoined in the agreement being observed. The
    Railway cannot on one hand not follow the requisite
    procedure for jointly recording measurements, formally
    resolving representations etc. and then hide behind the plea
    of Excepted Matter. Hence while AT takes note and record
    that the Respondent have made this plea from time to time
    but nevertheless, the Respondent have been amiss in not
    following the due process as provided in the Contract, which
    would have made the Excepted matter immune to Arbitral
    interference. Hence, AT is not convinced of the Respondent’s
    plea of treating such matters as Excepted Matters. However
    14

    2026:CHC-OS:76-DB

    AT will again discuss this matter in the Claims awards
    discussion where the Respondent has taken the plea of
    “Excepted Matter.”

    26. Arbitral Tribunal has dealt with the plea of excepted matters

    specifically. In the award, Arbitral Tribunal has dealt with

    contentions of the respective parties on such an issue. Arbitral

    Tribunal has held that, a contract has to be read in its totality.

    Arbitral Tribunal has noted the quality of the claims of the

    respective parties. It has held that, new items of claim with respect

    to the bills not paid, forfeiture of security deposit are inextricably

    linked to the dispute and are within the scope of arbitration.

    27. It is trite law that, an Arbitral Tribunal has the jurisdiction to

    decide on the parameters of the arbitrable disputes. In the facts and

    circumstances of the present case, Arbitral Tribunal has come to

    the finding that, all claims are inextricably intertwined with each

    other and therefore, the excepted clause will not apply. In addition

    thereto, Arbitral Tribunal has noted that the appellant before us,

    conducted its affairs contemporaneously in such a manner so as

    not to distinguish between excepted matters and matters which are

    arbitral at the time of execution of contract.
    15

    2026:CHC-OS:76-DB

    28. The view taken by the Arbitral Tribunal on the issue of

    excepted matters being plausible, no interference is called for by the

    Court exercising its jurisdiction under Section 34 of the Arbitration

    and Conciliation Act, 1996 or under Section 37 thereof.

    29. A Court exercising jurisdiction under Section 37 of the Act of

    1996 is to consider whether, the Section 34 of the Act of 1996,

    Court exercised jurisdiction within the parameters of law or not. In

    the facts and circumstance of the present case, Section 34 Court

    has set aside the award in respect of claim nos. 2, 8 and 11. Claim

    no. 2 is on account of recovery of security deposit while claim no. 8

    is on account of refund of commission paid to bank for extension of

    bank guarantee and claim no. 9 is on account of interest.

    30. So far as the claim no. 2 is concerned, the

    claimant/respondent herein, is entitled to the security deposit

    which was deducted from bills of the claimant/respondent from

    time to time. When the Arbitral Tribunal has held that, the

    appellant before us, was guilty of delay in handing over the work

    site, deleting and adding to the contract, and unilaterally

    introducing new item causing reduction in rates of RCC items and

    that to with retrospective effect, and where the Arbitral Tribunal

    has arrived at the finding that, the appellant created circumstances
    16

    2026:CHC-OS:76-DB

    for making the respondent unable to perform its obligation under

    the contract and where, the Arbitral Tribunal has concluded that

    the termination of contract is without merit, then, claim no. 2 on

    account of recovery of security deposit should be allowed.

    31. Similarly, claim no. 8 is inextricably intertwined with the

    other claims. It has been established before the Arbitral Tribunal

    that, the appellant had brought about a circumstance which

    prevented the respondent from executing the contract. Arbitral

    Tribunal has recorded a finding that the termination of contact

    itself is without any merit. Arbitral Tribunal has also held that,

    there was undue delay on the part of the appellant in handing over

    work sites, deletion and addition of contract and introducing new

    items. Therefore, the respondent was required to extend the bank

    guarantee from time to time for no fault of theirs. Consequently, it

    is just and proper that, the respondent be reimbursed with the

    commission paid to the bank for extension of the bank guarantee.

    Contract had required the respondent to furnish a bank guarantee

    which the respondent did. Respondent had from time to time

    extended such bank guarantee. Obtaining such extensions of bank

    guarantee was obviously at a cost to the respondent. The appellant

    being guilty of delay with regard to the execution of the contract,
    17

    2026:CHC-OS:76-DB

    has to compensate the respondent for the commission that the

    respondent was required to pay for extension of bank guarantee.

    32. The issue of claim for interest under claim no. 11 has to be

    considered in light of the ratio of Dr. Poornima Advani (supra).

    Delay in execution of contract being attributable to the appellant

    and the termination of the contract by the appellant being held to

    be illegal, and, the appellant being found to be withholding money

    belonging to the respondents wrongfully, then, the natural course of

    compensation for the wrongful withholding money belonging the

    respondent is a compensation by way of interest being awarded in

    favour of the respondent.

    33. In view of the above discussions, we find that, the Court

    exercising powers under Section 34 of the Act of 1996 did not apply

    the parameters of law for setting aside a portion of the award,

    appropriately. Learned Single Judge did not find, claim nos. 2, 8

    and 11 which were disallowed were severable from the other parts

    of the award itself.

    34. In view of the irregular exercise of jurisdiction by the Section

    34 Court, we set aside the impugned judgment and order dated

    August 05, 2024. Challenge to the award consequently fails.
    18

    2026:CHC-OS:76-DB

    35. AO COM 36 of 2024 is dismissed without any order as to

    costs.

    36. OCOT 1 of 2025 is allowed. No order as to costs.

    [DEBANGSU BASAK, J.]

    37. I agree.

    [MD. SHABBAR RASHIDI, J.]



    Source link

    LEAVE A REPLY

    Please enter your comment!
    Please enter your name here