Man Industries (India) Limited vs Gail (India) Limited on 11 March, 2026

    0
    50
    ADVERTISEMENT

    Delhi High Court

    Man Industries (India) Limited vs Gail (India) Limited on 11 March, 2026

    Author: Amit Bansal

    Bench: Amit Bansal

                              *        IN THE HIGH COURT OF DELHI AT NEW DELHI
                                   %                        Judgment Reserved on: 20th February, 2026
                                                            Judgment pronounced on: 11th March, 2026
    
                              +        O.M.P. (COMM) 191/2019
    
                                       MAN INDUSTRIES (INDIA) LIMITED           .....Petitioner
                                                    Through: Mr. Jayant Mehta, Sr. Advocate with
                                                               Ms. Amrita Singh, Mr. Sanket
                                                               Khandelwal, Mr. Prasang Sharma and
                                                               Mr. Vinod Mehta, Advocates.
    
                                                          versus
    
                                       GAIL (INDIA) LIMITED                              .....Respondent
                                                      Through:         Mr. K.M. Natraj, ASG with Mr. Lalit
                                                                       Chauhan, Ms. Laxmi Chauhan, Mr.
                                                                       Manish Yadav and Ms. Nikita
                                                                       Chauhan, Advocates.
    
                              CORAM:
                              HON'BLE MR. JUSTICE AMIT BANSAL
                                                          JUDGMENT
    

    AMIT BANSAL, J.

    1. The present petition has been filed under Section 34 of the Arbitration
    and Conciliation Act, 1996 (hereinafter ‘the Act’) on behalf of the claimant
    in the arbitration proceedings challenging the Award dated 7th January 2019
    (hereinafter ‘Impugned Award’) passed by the Arbitral Tribunal.

    SPONSORED

    2. The petitioner (claimant in the arbitration proceedings) shall
    hereinafter be referred to as ‘Man Industries’ and the respondent (respondent
    in the arbitration proceedings) shall hereinafter be referred to as ‘GAIL’.

    Signature Not Verified
    Digitally Signed O.M.P. (COMM) 191/2019 Page 1 of 26
    By:AANCHAL TAGGAR
    Signing Date:11.03.2026
    17:07:47

    FACTUAL BACKGROUND

    3. Brief facts leading to the present petition are as under:

    3.1. Man Industries is engaged in the business of manufacture of carbon
    steel coated line pipes which are used in the transportation of petroleum/
    natural gas and other related products.

    3.2. GAIL (India) Limited is a public sector undertaking optimising use of
    natural gas and its fractions.

    3.3. GAIL planned to lay onshore a Regassified Liquid Natural Gas
    (RLNG) pipeline, from its despatch terminal at Dabhol, Maharashtra to
    receipt terminal at Bibadi near Bangalore, Karnataka (hereinafter the
    ‘Dabhol-Bangalore project’).

    3.4. GAIL, through its agent M/s Engineers India Ltd. (EIL) invited offers
    against its bid document for procurement of API 5L Grade X-70 PSL 2
    carbon steel line pipes in respect of its Dabhol-Bangalore project.
    3.5. The bid of Man Industries was accepted vide Fax of Acceptance dated
    26th August 2010 (hereinafter ‘FOA’). Thereafter, a formal purchase order
    was issued by GAIL in favour of Man Industries vide Purchase Order dated
    19th October 2010 (hereinafter the ‘Purchase Order’). The Purchase Order
    specifies that all other provisions covered under the bid document, General
    Conditions of Contract-Goods (hereinafter ‘GCC-Goods’) and Special
    Conditions of Contract-Goods (hereinafter ‘SCC-Goods’) would be
    applicable to supply of bare line pipes.

    3.6. In terms of the Purchase Order, Man Industries was required to supply
    the bare line pipes to GAIL as per a progressive delivery schedule. The
    delivery was to be done in a staggered manner, with the first lot to be

    Signature Not Verified
    Digitally Signed O.M.P. (COMM) 191/2019 Page 2 of 26
    By:AANCHAL TAGGAR
    Signing Date:11.03.2026
    17:07:47
    delivered by the 5th month from the date of FOA, i.e. 25th January 2011 and
    the last delivery by the 10th month from the date of FOA, i.e. 25th June 2011.
    The dates of delivery as per the delivery schedule at Annexure-3 of the
    Purchase Order were 25th January 2011, 25th February 2011, 25th March
    2011, 25th April 2011, 25th May 2011 and 25th June 2011.
    3.7. Man Industries was also required to maintain dump yards at
    designated sites for a period of 2 months beyond the last date of delivery of
    the coated pipes at those dumpsites, without being entitled to any payment
    from GAIL for the said period of 2 months.

    3.8. On 3rd August 2012, a ‘No Claim Certificate’ was issued by Man
    Industries to GAIL which stated that a total sum of Rs.64,13,790.57/- was
    due and all other claims under the contract stand fully and finally settled
    except the Price Reduction Schedule (hereinafter ‘PRS’) amount.
    3.9. The total price for supply of the aforesaid coated pipes was
    Rs.125,39,40,190/-. As stipulated in the Purchase Order, 90% of the
    payment was to be made progressively against the receipt of the coated
    pipes at the dumpsites. The balance 10% of the total value was to be paid to
    Man Industries within 30 days from handing over of coated pipes to the
    laying contractor of GAIL.

    3.10. Disputes arose between the parties and Man Industries invoked the
    arbitration clause vide letter dated 18th February 2015. The Arbitral Tribunal
    comprising a Sole Arbitrator was constituted.

    4. Man Industries filed a statement of claim dated 20th May 2016 before
    the Arbitral Tribunal with the following claims:

    (i) Claim No.1: Wrongful withholding of Rs. 3,82,95,630/- towards

    Signature Not Verified
    Digitally Signed O.M.P. (COMM) 191/2019 Page 3 of 26
    By:AANCHAL TAGGAR
    Signing Date:11.03.2026
    17:07:47
    Price Reduction Schedule (PRS)

    (ii) Claim No.2: Wrongful Withholding of Rs. 43,69,038/- towards
    Central Sales Tax (hereinafter ‘CST’)

    (iii) Claim No.3: Interest for the delayed payment of 10% of the total
    value of the Contract

    (iv) Claim No.4 : Interest pre-suit, pendente lite and future

    (v) Claim No.5: Cost of Proceedings
    4.1. On 21st July 2016, GAIL filed its statement of defence before the
    Arbitral Tribunal. An additional statement of defence dated 23rd September
    2017 was also filed on behalf of GAIL.

    4.2. Pleadings were completed in the arbitral proceedings on 8th November
    2017, when rejoinder to the additional statement of defence was filed by
    Man Industries.

    4.3. Both parties led their respective evidence before the Arbitral Tribunal.

    5. Via the Impugned Award, the Sole Arbitrator dismissed all the claims
    of Man Industries.

    6. Aggrieved by the Impugned Award, the present petition has been filed
    on behalf of Man Industries challenging the Impugned Award under Section
    34
    of the Arbitration and Conciliation Act, 1996.
    SUBMISSIONS ON BEHALF OF THE PETITIONER

    7. Mr. Jayant Mehta, Senior Counsel appearing on behalf of Man
    Industries, has made the following submissions claim-wise:

    7.1. Claim No.1 – Wrongful withholding of Rs. 3,82,95,630/- towards
    Price Reduction Schedule (PRS)

    7.1.1. The Arbitral Tribunal has wrongly held that GAIL was prejudiced by

    Signature Not Verified
    Digitally Signed O.M.P. (COMM) 191/2019 Page 4 of 26
    By:AANCHAL TAGGAR
    Signing Date:11.03.2026
    17:07:47
    the delay in delivery. GAIL accepted the deliveries without any objections.
    7.1.2. The last delivery was made by Man Industries on 2nd June 2011, much
    before the scheduled final date of delivery i.e. 25th June 2011, however, the
    pipes were lifted from the designated dumpsites by GAIL only on 9th April
    2012. Even though the contract stipulated that time would be of essence,
    GAIL waived this condition through its conduct. Reliance has been placed
    on Swaran Ramachandran v. Aravacode Chakungal Jayapalan, (2004) 8
    SCC 689.

    7.1.3. In a mechanical manner, GAIL withheld a sum of Rs.3,82,95,630/-

    from the amount payable to Man Industries, towards liquidated damages
    termed under the contract as ‘Price Reduction Schedule’/ ‘PRS’. GAIL did
    not produce any evidence to show loss suffered on account of delay in
    supply of the pipes. In this regard, Man Industries has placed reliance on
    Kailash Nath Associates v. DDA, (2015) 4 SCC 136, Bharat Heavy
    Electricals Limited v. Kanohar
    , 2024 SCC Online Del 1453 and Indian Oil
    Corporation v. Standard Casting, 2025 SCC OnLine Del 8393.

    7.2. Claim No.2 – Wrongful refusal to reimburse the increase in
    Central Sales Tax (CST) from 4% to 5% amounting to Rs. 43,69,038/-
    7.2.1. It an admitted position that the CST increased from 4% to 5% on 11 th
    April 2011 during the contractual period i.e. 25th January 2011 to 25th June
    2011. Hence, Man Industries was not required to produce any evidence in
    this regard and the Arbitral Tribunal grossly erred in rejecting the claim of
    Man Industries for reimbursement of the differential rate of tax.

    7.3. Claim No.3 – Interest for the delayed payment of 10% of the total
    value of the Contract

    Signature Not Verified
    Digitally Signed O.M.P. (COMM) 191/2019 Page 5 of 26
    By:AANCHAL TAGGAR
    Signing Date:11.03.2026
    17:07:47
    7.3.1. The Arbitral Tribunal failed to appreciate that Man Industries was
    under economic duress due to more than a year’s delay on the part of GAIL
    in making balance payment and in these circumstances, a ‘No Claim
    Certificate’ was issued in favour of GAIL. A ‘No Claim Certificate’ does
    not bar a party from raising a claim if there is an acceptable claim.

    7.4. Claim No.4 – Interest pre-suit, pendente lite and future
    7.4.1. Since the Award pertaining to first three claims is patently illegal, the
    finding in this claim also deserves to be set aside.

    7.5. Claim No.5 – Cost of Proceedings
    7.6. Man Industries has already paid cost of Rs.1,80,000/- for
    adjournments sought during arbitral proceedings, which has been recorded
    in the Impugned Award. Yet, the Arbitral Tribunal imposed a cost of
    Rs.10,00,000/- on the basis of these adjournments and for the expenses
    incurred by GAIL towards Arbitrator’s fee and secretarial expenses.

    SUBMISSIONS ON BEHALF OF THE RESPONDENT

    8. Mr. K.M. Natraj, ASG appearing on behalf of GAIL, has made the
    following submissions claim-wise:

    8.1. Claim No.1 – Wrongful withholding of Rs. 3,82,95,630/- towards
    Price Reduction Schedule (PRS)
    8.1.1. The Arbitral Tribunal has correctly held that the amount to be
    deducted on account of PRS is not penalty or liquidated damages. The PRS
    clause cannot be disregarded as the parties are bound by the terms of the
    Contract. Man Industries, on its own volition, deducted the PRS amount
    from its Running Account Bills dated 5th April 2011, 25th April 2011, 10th
    May 2011 and 4th June 2011.

    Signature Not Verified
    Digitally Signed O.M.P. (COMM) 191/2019 Page 6 of 26
    By:AANCHAL TAGGAR
    Signing Date:11.03.2026
    17:07:47

    8.1.2. In the alternative, if PRS clause was considered to be a liquidated
    damages clause, it gives a genuine pre-estimate of the loss which may be
    suffered by GAIL due to delayed deliveries of the pipes.
    8.1.3. Considering that the Dabhol-Bangalore pipeline project was a project
    of national importance involving multiple players, any delay in monthly
    deliveries would have affected the timelines drawn up by GAIL for
    completion of different stages of the project. Taking into account the nature
    of the project, GAIL was not required to prove any actual loss. In this
    regard, GAIL has placed reliance on Fateh Chand v. Balkishan Dass,
    (1964) 1 SCR 515, ONGC v. Saw Pipes, (2003) 5 SCC 705, Gail v. Punj
    Lloyd
    , 2017 SCC OnLine Del 8301 and Tamilnadu Telecommunications
    Ltd. v. Bharat Sanchar Nigam Ltd., 2016 SCC OnLine Del 5939.

    8.2. Claim No.2 – Wrongful refusal to reimburse the increase in
    Central Sales Tax (CST) from 4% to 5% amounting to Rs. 43,69,038/-
    8.2.1. The lack of evidence adduced by Man Industries demonstrates that
    Man Industries is not entitled to reimbursement for the differential rate of
    tax. By way of the present petition, Man Industries is attempting to invite the
    Court to re-appreciate the evidence.

    8.3. Claim No.3 – Interest for the delayed payment of 10% of the total
    value of the Contract
    8.3.1. Even the own witness of Man Industries admitted in front of the
    Arbitral Tribunal that this claim was in the nature of an afterthought. Once
    Man Industries has discharged all claims against GAIL at the time of
    issuance of full and final settlement, it cannot revive such a claim. The plea
    of economic duress raised by Man Industries was not proved by way of

    Signature Not Verified
    Digitally Signed O.M.P. (COMM) 191/2019 Page 7 of 26
    By:AANCHAL TAGGAR
    Signing Date:11.03.2026
    17:07:47
    evidence before the Arbitral Tribunal.

    8.4. Claim No.4 – Interest pre-suit, pendente lite and future
    8.4.1. Since all the claims have been rejected, the Arbitral Tribunal has
    correctly rejected the claim of interest.

    8.5. Claim No.5 – Cost of Proceedings
    8.5.1. The Arbitral Tribunal has correctly assessed the costs in favour of
    Man Industries.

    ANALYSIS AND FINDINGS

    9. I have heard counsel for the parties and perused the material on
    record.

    10. The Supreme Court has defined the scope of interference by courts in
    a petition challenging an Award passed by the Arbitrator under Section 34
    of the Arbitration and Conciliation Act, 1996 (hereinafter ‘the Act’) in a
    plethora of judgments.

    11. In Ssangyong Engineering and Construction Company Limited v.
    National Highways Authority of India (NHAI
    ), (2019) 15 SCC 131, the
    Supreme Court made the following observations with regard to scope of
    interference under Section 34 of the Act:

    “37. Insofar as domestic awards made in India are concerned, an
    additional ground is now available under sub-section (2-A), added by the
    Amendment Act, 2015, to Section 34. Here, there must be patent
    illegality appearing on the face of the award, which refers to such
    illegality as goes to the root of the matter but which does not amount to
    mere erroneous application of the law. In short, what is not subsumed
    within “the fundamental policy of Indian law”, namely, the contravention
    of a statute not linked to public policy or public interest, cannot be
    brought in by the backdoor when it comes to setting aside an award on
    the ground of patent illegality.

    38. Secondly, it is also made clear that reappreciation of evidence,
    which is what an appellate court is permitted to do, cannot be permitted

    Signature Not Verified
    Digitally Signed O.M.P. (COMM) 191/2019 Page 8 of 26
    By:AANCHAL TAGGAR
    Signing Date:11.03.2026
    17:07:47
    under the ground of patent illegality appearing on the face of the
    award.

    39. To elucidate, para 42.1 of Associate Builders [Associate Builders v.
    DDA
    , (2015) 3 SCC 49 : (2015) 2 SCC (Civ) 204], namely, a mere
    contravention of the substantive law of India, by itself, is no longer a
    ground available to set aside an arbitral award.
    Para 42.2 of Associate
    Builders [Associate Builders v. DDA
    , (2015) 3 SCC 49 : (2015) 2 SCC
    (Civ) 204], however, would remain, for if an arbitrator gives no reasons
    for an award and contravenes Section 31(3) of the 1996 Act, that would
    certainly amount to a patent illegality on the face of the award.

    40. The change made in Section 28(3) by the Amendment Act really
    follows what is stated in paras 42.3 to 45 in Associate Builders
    [Associate Builders v. DDA
    , (2015) 3 SCC 49 : (2015) 2 SCC (Civ) 204],
    namely, that the construction of the terms of a contract is primarily for
    an arbitrator to decide, unless the arbitrator construes the contract in a
    manner that no fair-minded or reasonable person would; in short, that
    the arbitrator’s view is not even a possible view to take. Also, if the
    arbitrator wanders outside the contract and deals with matters not
    allotted to him, he commits an error of jurisdiction. This ground of
    challenge will now fall within the new ground added under Section
    34
    (2-A).

    41. What is important to note is that a decision which is perverse, as
    understood in paras 31 and 32 of Associate Builders [Associate Builders
    v. DDA
    , (2015) 3 SCC 49 : (2015) 2 SCC (Civ) 204], while no longer
    being a ground for challenge under “public policy of India”, would
    certainly amount to a patent illegality appearing on the face of the
    award. Thus, a finding based on no evidence at all or an award which
    ignores vital evidence in arriving at its decision would be perverse and
    liable to be set aside on the ground of patent illegality. Additionally, a
    finding based on documents taken behind the back of the parties by the
    arbitrator would also qualify as a decision based on no evidence
    inasmuch as such decision is not based on evidence led by the parties,
    and therefore, would also have to be characterised as perverse.”

    [emphasis supplied]

    12. In paragraph 40 of Ssangyong (supra) set out above, the Supreme
    Court has categorically stated that construction of the terms of the contract
    falls within the exclusive domain of the arbitrator. The court cannot interfere
    unless the interpretation of the arbitrator is such that no reasonable or fair-
    minded person could have adopted. If the view taken by the Arbitral

    Signature Not Verified
    Digitally Signed O.M.P. (COMM) 191/2019 Page 9 of 26
    By:AANCHAL TAGGAR
    Signing Date:11.03.2026
    17:07:47
    Tribunal is a plausible view, no interference is called for.

    13. The Supreme Court has reiterated the same principles in Delhi Metro
    Rail Corporation Limited v. Delhi Airport Metro Express Private Limited
    ,
    (2024) 6 SCC 357 and OPG Power Generation Private Limited v. Enexio
    Power Cooling Solutions India Private Limited
    , (2025) 2 SCC 417.
    The
    position of law with regard to scope of interference with an Arbitral Award
    under Section 34 of the Act has been summarized by the Supreme Court in
    OPG Power Generation (supra), the relevant paragraph of which is set out
    below:

    “Scope of interference with an arbitral award

    74. The aforesaid judicial precedents make it clear that while exercising
    power under Section 34 of the 1996 Act the Court does not sit in appeal
    over the arbitral award. Interference with an arbitral award is only on
    limited grounds as set out in Section 34 of the 1996 Act. A possible view
    by the arbitrator on facts is to be respected as the arbitrator is the
    ultimate master of the quantity and quality of evidence to be relied
    upon. It is only when an arbitral award could be categorized as
    perverse, that on an error of fact an arbitral award may be set aside.
    Further, a mere erroneous application of the law or wrong appreciation
    of evidence by itself is not a ground to set aside an award as is clear
    from the provisions of sub-section (2-A) of Section 34 of the 1996 Act.”

    [emphasis supplied]

    14. With this background, I shall now proceed to apply the aforesaid
    principles in the facts and circumstances of the present case in relation to
    objections raised by Man Industries.

    Claim No. 1 – Wrongful withholding of Rs. 3,82,95,630/- towards Price
    Reduction Schedule (PRS)

    15. At the outset, it may be relevant to refer to Clause 25.2 of the GCC-
    Goods which provides for options available with the purchaser in case of
    delay in delivery. For ease of reference, Clause 25.2 of the GCC-Goods is

    Signature Not Verified
    Digitally Signed O.M.P. (COMM) 191/2019 Page 10 of 26
    By:AANCHAL TAGGAR
    Signing Date:11.03.2026
    17:07:47
    set out below:

    “25. Delays In The Seller’s Performance
    25.1 … … …

    25.1 Any unexcusable delay by the SELLER or his subcontractor shall
    render the SELLER liable, without prejudice to any other terms of the
    Contract, to any or all of the following sanctions: forfeiture of Contract
    performance guarantee, imposition of price reduction for delay in
    delivery and termination of the contract for default.”

    [Emphasis supplied]

    16. Clause 26 of the GCC-Goods provides for Price Reduction Schedule
    for delay of delivery, the same is set out below:

    “26. Price Reduction Schedule For Delayed Delivery
    26.1 Subject to Article -29, if the SELLER fails to deliver any or all of the
    GOODS or performance the services within the time period (s) specified
    in the CONTRACT, the PURCHASER shall, without prejudice to his
    other remedies under the CONTRACT, deduct from the CONTRACT
    PRICE, a sum calculated on the basis of the CONTRACT PRICE,
    including subsequent modifications.

    26.1.1 Deductions shall apply as per following formula: In case of
    delay in delivery of equipment/materials or delay in completion, total
    contract price shall be reduced by ½ % (half percent) of the total
    contract price per complete week of delay or part thereof subject to a
    maximum of 5% (five percent) of the total contract price.
    26.2 In case of delay in delivery on the part of Seller, the
    invoice/document value shall be reduced proportionately for the delay
    and payment shall be released accordingly.

    26.3 In the event the invoice value is not reduced proportionately for the
    delay, the PURCHASER may deduct the amount so payable by SELLER,
    from any amount falling due to the SELLER or by recovery against the
    Performance Guarantee.

    Both seller and PURCHASER agree that the above percentages of
    price reduction are genuine pre estimates of the loss/damage which the
    PURCHASER would have suffered on account of delay/breach on the
    part of the SELLER and the said amount will be payable on demand
    without there being any proof of the actual loss/or damage caused by
    such breach/delay. A decision of the PURCHASER in the matter of

    Signature Not Verified
    Digitally Signed O.M.P. (COMM) 191/2019 Page 11 of 26
    By:AANCHAL TAGGAR
    Signing Date:11.03.2026
    17:07:47
    applicability of price reduction shall be final and binding.”

    [Emphasis supplied]

    17. Price reduction on account of delay also finds a reference in Clause 17
    of the Special Conditions of Contract-Goods, which is set out below:

    “17. PRICE REDUCTION SCHEDULE (PRS)
    17.1. In partial modification of provisions of GCC-Goods 26.0 and
    pursuant to clause 4 of SCC-Goods, in case of delay in delivery of
    specified item wise monthly quantity of line pipes as given in delivery
    schedule for respective item as specified in Clause 4 of SCC-Goods, the
    contract price shall be reduced by 1/2 % (half percent) of the total price
    of the undelivered quantity of line pipes covered in monthly quantity
    for which delivery is delayed, per week of delay or part thereof subject
    to a maximum of 5%(five percent) of total Contract Price.
    17.2. Item wise monthly quantity specified in delivery schedule shall be
    considered separately for applying PRS in case of delay as described
    above. However, the total amount of PRS shall be limited to 5% of the
    total Contract Price.”

    [Emphasis supplied]

    18. Clause 6 of the Purchase Order also makes a reference to Clause 17 of
    SCC-Goods. For ease of reference, the same is reproduced below:

    “6.0 PRICE REDUCTION SCHEDULE FOR DELAY IN DELIVERY
    (PRS):

    6.1 Price reduction schedule (PRS) shall be as per clause no. 17.0 of
    Special Conditions of Contract (Goods) SCC (Goods).”

    19. In terms of Clause 26 of GCC-Goods read with Clause 17 of SCC-
    Goods, in case there is a delay in delivery of the monthly quantity of pipes
    as given in the delivery schedule, the purchaser shall be entitled to price
    reduction in terms of the Price Reduction Schedule, which shall be
    considered a genuine pre-estimate of loss/damages that may be suffered by

    Signature Not Verified
    Digitally Signed O.M.P. (COMM) 191/2019 Page 12 of 26
    By:AANCHAL TAGGAR
    Signing Date:11.03.2026
    17:07:47
    the purchaser.

    20. It is an admitted position that there was a delay in supply of the
    monthly quantity of pipes as provided in the delivery schedule by Man
    Industries. Man Industries gave certain justifications for the said delay.
    However, the Arbitral Tribunal held that the delay was not excusable.

    21. The case set up by Man Industries before the Arbitral Tribunal was
    that the entire material had been delivered to GAIL on 2nd June 2011, way
    ahead of the due date of 25th June 2011, as per the delivery schedule.

    22. The Arbitral Tribunal has rejected this contention holding that as per
    the delivery schedule, specific quantities had to delivered on a monthly
    basis. It was further held that Man Industries was only one of the players in
    the entire project and delay by one of the players would result in a chain
    reaction causing delay in schedules of the remaining players, thus causing
    overall delay in the competition of the project.

    23. Clause 17 of SCC-Goods specifically provided that the delivery has to
    be made on a monthly basis. In the opinion of this Court, there is no
    infirmity in the finding of the Arbitral Tribunal rejecting the aforesaid
    contention of Man Industries. As noted above, the Arbitral Tribunal has
    given cogent reasons for the same.

    24. As regards the contention of Man Industries that the time was not the
    essence of the contract, reference may be made to Clause 24.1 of the GCC-
    Goods, which provides as under:

    “24. Time As Essence of Contract
    24.1 The time and date of delivery/completion of the GOODS/SERVICES
    as stipulated in the Contract shall be deemed to be the essence of the
    Contract.”

    Signature Not Verified
    Digitally Signed O.M.P. (COMM) 191/2019 Page 13 of 26
    By:AANCHAL TAGGAR
    Signing Date:11.03.2026
    17:07:47

    25. It has been reiterated in Clause 3 of the Purchase Order that time was
    of essence in the contract. Clause 3 of the Purchase Order is set out below:

    “3.0 DELIVERY PERIOD
    3.1 Delivery is the essence of this Purchase Order and the Seller shall try
    to improve upon the same.

    3.2 The contractual delivery schedule of bare line pipes for each item
    shall be as per progressive Delivery Schedule specified in Annexure – 3
    enclosed herewith. This shall be governed by the conditions specified
    under Special Conditions of Contract for Goods (SCC-Goods) i.e.
    Section-IIIB of Bidding Document and Commercial Corrigendum No. 1
    & 2 to the Bidding Document.”

    26. A reference may also be made to the Clause 25 of the GCC-Goods,
    which provides for consequences in case of breach of delivery schedule and
    Clause 26 of the GCC-Goods which provides for Price Reduction Schedule
    (‘PRS’) for delayed delivery.

    27. Relying on the aforesaid clauses, the Arbitral Tribunal rejected the
    contention of Man Industries that time was not of essence in the contract.
    The Arbitral Tribunal further noted that Man Industries itself has admitted
    that the project was “a time bound, prestigious gas project of national
    importance”.

    28. On the aforesaid aspect, Man Industries has relied upon a judgment of
    the Supreme Court in Swaran Ramachandran (supra). In the facts of the
    said case, the Supreme Court had held that time was not an essence of the
    contract in the said case. The said finding was based on the provisions of the
    contract in the said case and the evidence led by the parties. The contract in
    the said case was with regard to the sale and purchase of property and
    therefore, would have no relevance in the present case.

    29. Therefore, no fault can be found with the finding of the Arbitral

    Signature Not Verified
    Digitally Signed O.M.P. (COMM) 191/2019 Page 14 of 26
    By:AANCHAL TAGGAR
    Signing Date:11.03.2026
    17:07:47
    Tribunal that time was of essence in the contract.

    30. On the aspect of deduction in terms of PRS, the Arbitral Tribunal held
    that GAIL was justified in imposing PRS on account of delay. The relevant
    observations of the Arbitral Tribunal in this regard are set out below:

    “In my opinion it is not necessary to minutely examine whether the
    above clause is a penalty clause or not. For the present purpose, it
    would be necessary to only examine whether the Respondent could
    invoke the said Clause to effect a price reduction. Since both the parties
    are bound by the terms of the Contract, and since the delay in the
    delivery of the pipes was “unexcusable”, as already held by me, the
    Respondent was justified in imposing PRS for the delay in accordance
    with the said clause. I am inclined to think that it is unnecessary in the
    present case to examine the question whether the Respondent is under
    a duty to prove that it actually suffered loss on account of the delay.
    The Clause 25.2 does not profess to import any notions of liquidated
    damages so that it can give rise to the controversy whether it is for the
    Respondent to prove actual loss or not. All that the Respondent has to
    show is that there was a delay in supplying the pipes and the delay was
    unexcusable. If these two conditions are satisfied, the Respondent
    would be entitled to impose price reduction. In my opinion, these two
    conditions are present and therefore, the Respondent was clearly in the
    right in effecting PRS.”

    [Emphasis supplied]

    31. The Arbitral Tribunal has duly interpreted the various clauses of the
    Contract to come to a conclusion that Clause 26 of the GCC-Goods is
    neither a penal clause nor does it provide for levy of liquidated damages. It
    is no longer res integra that interpretation of the Contract is the sole domain
    of the Arbitral Tribunal unless the Contract is interpreted by the Arbitrator
    in a completely irrational or arbitrary manner.

    32. In the alternative, the Arbitral Tribunal held that, even if it is
    presumed that the aforesaid clause provides for liquidated damages, the
    clause provides for a pre-estimate of loss that GAIL may suffer on account

    Signature Not Verified
    Digitally Signed O.M.P. (COMM) 191/2019 Page 15 of 26
    By:AANCHAL TAGGAR
    Signing Date:11.03.2026
    17:07:47
    of delay and therefore, GAIL was not bound to prove the loss. In this regard,
    the Arbitral Tribunal placed reliance on the judgment of the Supreme Court
    in Fateh Chand v. Balkishan Dass (supra), which was followed by this
    Court in Gail v. Punj Lloyd (supra).

    33. The Arbitral Tribunal held that the parties knew at the time of making
    the Contract that some loss is likely to result in the delivery of pipes and
    therefore, provided for an estimate of that loss in the Contract itself.

    34. In this regard, a reference may be made to the following observations
    of the Supreme Court in ONGC v. Saw Pipes (supra):

    “64. It is apparent from the aforesaid reasoning recorded by the Arbitral
    Tribunal that it failed to consider Sections 73 and 74 of the Indian
    Contract Act and the ratio laid down in Fateh Chand case [Fateh Chand
    v. Balkishan Dass
    , AIR 1963 SC 1405 : (1964) 1 SCR 515] wherein it is
    specifically held that jurisdiction of the court to award compensation in
    case of breach of contract is unqualified except as to the maximum
    stipulated; and compensation has to be reasonable. Under Section 73,
    when a contract has been broken, the party who suffers by such breach is
    entitled to receive compensation for any loss caused to him which the
    parties knew when they made the contract to be likely to result from the
    breach of it. This section is to be read with Section 74, which deals with
    penalty stipulated in the contract, inter alia (relevant for the present
    case) provides that when a contract has been broken, if a sum is named
    in the contract as the amount to be paid in case of such breach, the party
    complaining of breach is entitled, whether or not actual loss is proved to
    have been caused, thereby to receive from the party who has broken the
    contract reasonable compensation not exceeding the amount so named.

    Section 74 emphasises that in case of breach of contract, the party
    complaining of the breach is entitled to receive reasonable compensation
    whether or not actual loss is proved to have been caused by such breach.
    Therefore, the emphasis is on reasonable compensation. If the
    compensation named in the contract is by way of penalty, consideration
    would be different and the party is only entitled to reasonable
    compensation for the loss suffered. But if the compensation named in
    the contract for such breach is genuine pre-estimate of loss which the

    Signature Not Verified
    Digitally Signed O.M.P. (COMM) 191/2019 Page 16 of 26
    By:AANCHAL TAGGAR
    Signing Date:11.03.2026
    17:07:47
    parties knew when they made the contract to be likely to result from the
    breach of it, there is no question of proving such loss or such party is
    not required to lead evidence to prove actual loss suffered by him.
    Burden is on the other party to lead evidence for proving that no loss is
    likely to occur by such breach. …

    ***

    67. … In our view, in such a contract, it would be difficult to prove exact
    loss or damage which the parties suffer because of the breach thereof. In
    such a situation, if the parties have pre-estimated such loss after clear
    understanding, it would be totally unjustified to arrive at the conclusion
    that the party who has committed breach of the contract is not liable to
    pay compensation. It would be against the specific provisions of Sections
    73
    and 74 of the Contract Act, 1872. There was nothing on record that
    compensation contemplated by the parties was in any way
    unreasonable. It has been specifically mentioned that it was an agreed
    genuine pre-estimate of damages duly agreed by the parties. It was also
    mentioned that the liquidated damages are not by way of penalty. It was
    also provided in the contract that such damages are to be recovered by
    the purchaser from the bills for payment of the cost of material
    submitted by the contractor. No evidence is led by the claimant to
    establish that the stipulated condition was by way of penalty or the
    compensation contemplated was, in any way, unreasonable. There was
    no reason for the Tribunal not to rely upon the clear and unambiguous
    terms of agreement stipulating pre-estimate damages because of delay
    in supply of goods. Further, while extending the time for delivery of the
    goods, the respondent was informed that it would be required to pay
    stipulated damages.”

    [Emphasis supplied]

    35. The judgment in ONGC v. Saw Pipes (supra) has been followed by
    the Supreme Court in Construction and Design Services v. Delhi
    Development Authority, (2015) 14 SCC 263, where the Court was dealing
    with the question whether the stipulated liquidated damages for breach of
    contract are in the nature of penalty or are a measure of compensation for
    loss. The relevant paragraph from the said judgment is set out below:

    Signature Not Verified
    Digitally Signed O.M.P. (COMM) 191/2019 Page 17 of 26
    By:AANCHAL TAGGAR
    Signing Date:11.03.2026
    17:07:47

    “15. Once it is held that even in the absence of specific evidence, the
    respondent could be held to have suffered loss on account of breach of
    contract, and it is entitled to compensation to the extent of loss
    suffered, it is for the appellant to show that stipulated damages are by
    way of penalty. In a given case, when the highest limit is stipulated
    instead of a fixed sum, in the absence of evidence of loss, part of it can be
    held to be reasonable compensation and the remaining by way of
    penalty. The party complaining of breach can certainly be allowed
    reasonable compensation out of the said amount if not the entire amount.
    If the entire amount stipulated is genuine pre-estimate of loss, the
    actual loss need not be proved. Burden to prove that no loss was likely
    to be suffered is on the party committing breach, as already observed.”

    [Emphasis supplied]

    36. In GAIL v. Punj Lloyd (supra), the appellant-GAIL had deducted
    liquidated damages on account of failure of the respondent-Punj Lloyd to
    complete the works at intermediate dates fixed under the contract for laying
    pipelines for the Dahej-Vijaipur Pipeline Project. The relevant clause in the
    contract provided for price reduction/ liquidated damages for delay in
    delivery.

    37. Relying upon the judgments of the Supreme Court in Fateh Chand v.
    Balkishan Dass
    (supra), ONGC v. Saw Pipes (supra) and Kailash Nath
    Associates v. DDA
    (supra), the Division Bench rejected the contention of
    Punj Lloyd that GAIL had to prove actual damages to recover the amounts
    agreed under the contract. The Division Bench also rejected the submission
    of Punj Lloyd that intermediate delays, which did not impact the final
    commissioning schedule, were condonable. The observations of the Division
    Bench are set out below:

    “34. The commissioning of the three spreads was over a period of 7 to
    7½ months each. The performance of these contracts, treated as one
    whole meant that Punj Lloyd had to ensure that equipment was in place,

    Signature Not Verified
    Digitally Signed O.M.P. (COMM) 191/2019 Page 18 of 26
    By:AANCHAL TAGGAR
    Signing Date:11.03.2026
    17:07:47
    the requisite material and men were on site and all necessary work
    (welding, joining etc) was done according to a pre-arranged schedule.
    Now, there is no dispute that there were intermediate delays – to the
    extent of about 65 days. If one sees from the perspective of the contractor
    (Punj Lloyd) that this did not impact the final commissioning schedule,
    undoubtedly the imposition of the liquidated damages clause would seem
    unjustified. However, two aspects are to be kept in mind here : first, that
    when bidding was done, there was every likelihood of different
    contractors being declared successful in respect of different spreads,
    which would have meant that as far as they were concerned this
    condition was essential to ensure compliance with timelines. That one
    party (Punj Lloyd) secured three spreads was providential, perhaps a
    coincidence. Secondly, the objective of this condition was to ensure that
    timelines were adhered to. For instance, if one spread were completed
    in time and the other not completed in time, there could potentially be
    an adverse impact on the commissioning/overall pipeline laying
    schedule. Furthermore, at the time when the delays occurred, the final
    picture was unknown. The nuanced nature of the condition, introduced
    as an amendment meant that the parties were alive to these details and
    voluntarily agreed that such compensation was recoverable. The court
    finds insubstantial the argument of Punj Lloyd that omission to the
    reference to the liquidated damages from the later condition, agreed to
    by the parties, meant that necessarily GAIL had to prove actual
    damage, to recover the amounts agreed. It is well settled that the nature
    of a condition does not depend on its nomenclature, but on its effect
    having regard to the overall circumstances of the case.

    *** *** ***

    37. This court is of the opinion that considering all these materials on
    record, the stipulation in clause 57.2.1 and the amounts deducted were
    by way of liquidated damages and a genuine pre-estimate of the loss
    calculated in monetary terms. They were not merely precautionary
    conditions not meant to be enforced, but conditions that could be insisted
    upon, as is evident from clause 57.2.2, which clarifies that
    “compensation for Delay/Liquidated Damages stated in sub-clause
    57.2.1 above shall be in addition to compensation for Delay/Liquidated
    Damages stated in sub-clause 57.1.1 of SCC.” Furthermore, the overall
    cap on damages at 20% (Clause 57.3) includes intermediate liquidated
    damages contemplated under clause 57.1.1. These intermediate delay
    liquidated damages were of the kind contemplated in Maula Bux

    Signature Not Verified
    Digitally Signed O.M.P. (COMM) 191/2019 Page 19 of 26
    By:AANCHAL TAGGAR
    Signing Date:11.03.2026
    17:07:47
    (supra) and Bharat Sanchar Nigam (supra), which the parties agreed,
    would be payable by one of them (Punj Lloyd) without proof of actual
    loss.”

    [Emphasis supplied]

    38. The Arbitral Tribunal has correctly placed reliance on the aforesaid
    judgment as the said case also involved levy of liquidated damages on
    account of failure of the contractor to complete the work in a timely manner
    in a contract with GAIL for laying pipelines.

    39. In Tamilnadu Telecommunications Ltd. v. Bharat Sanchar Nigam
    Ltd.
    (supra), the Co-ordinate Bench of this court, was dealing with the case
    where there was a delay of supply of the contracted quantities by the
    supplier/appellant and the Clause in the contract provided for liquidated
    damages. The court observed that since the supplier/appellant did not lead
    any evidence to indicate that the damages are unreasonable and not a
    genuine pre-estimate of damages, the supplier would be bound to pay the
    same. The court also observed that it is difficult to prove in public utility
    projects, the actual loss that may be suffered on account of delay. In the said
    case, it had been specifically pleaded by BSNL that it had suffered loss on
    account of delay in the projects. The relevant paragraph nos. 18 and 19 of
    the said judgment is set out below:

    “18. In the present case, TTL had agreed that the liquidated damages
    would be payable for delay in supply of contracted quantities. TTL has
    not led any evidence to indicate that the measure of damages was
    unreasonable and not a genuine pre-estimate of damages. It is also
    relevant to bear in mind that BSNL is a public utility and it would not
    be easy for BSNL to articulate the loss suffered by it for delays in
    execution of various projects. Undoubtedly, the failure on the part of
    the TTL to supply OFC would have caused a corresponding delay in
    BSNL providing services to its customers. It is difficult to prove with

    Signature Not Verified
    Digitally Signed O.M.P. (COMM) 191/2019 Page 20 of 26
    By:AANCHAL TAGGAR
    Signing Date:11.03.2026
    17:07:47
    any exactitude actual loss suffered by BSNL. However, that does not
    mean that TTL is absolved from its liability to compensate the BSNL.
    …..”

    19. In the present case, BSNL had expressly pleaded that it had
    suffered loss on account of delay in its projects and had also suffered
    loss of goodwill. As noticed above, it is difficult to reasonably estimate
    the damages suffered on the aforesaid account; this coupled with the fact
    that TTL has not led any evidence to indicate that the liquidated damages
    are unreasonable and, therefore, the finding of the Arbitrator that BSNL
    is entitled to recover liquidated damages cannot be held to be perverse
    or contrary to the fundamental policy of the Indian Law.”

    [Emphasis supplied]

    40. Applying the ratio of the aforesaid judgments to the facts of the
    present case, it has specifically been pleaded by GAIL that it has suffered a
    loss on account of delay in suppling the pipes by Man Industries. It was also
    pleaded on behalf of GAIL that the formula for PRS was a genuine pre-
    estimate of the loss to be suffered on account of delay and that it was
    difficult to prove or assess the actual loss. Reference may be made to
    paragraph 4 of Statement of Defence dated 21st July 2016 with respect to the
    loss suffered on account of delay, which is set out below:

    “4. There is an admitted delay by the Claimant, as per the Delivery
    Schedule in delivering the first Pipe to the Varul- Kolhapur-
    Maharashtra dumpsite (the ‘DS-1’) as also to the Chitradurga-
    Karnataka dumpsite (the ‘DS-2’). The delay caused by the Claimant led
    to further cascading delays in the timely completion of the Project. The
    Respondent suffered loss as a result of the delay by the Claimant in
    delivering the Pipes, as a result of which the Respondent was unable to
    supply gas which led to a consequent reduction in the revenue and
    profits of the Respondent. Due to the nature of the loss caused to the
    Respondent, it is difficult for the Respondent to prove the loss caused to
    it as a result of the admitted delays by the Respondent in delivery of the
    Pipes. It is, however, reiterated that the formula for the PRS, as
    contained in clause 17 of the SCC (Goods) and clause 26 of the GCC

    Signature Not Verified
    Digitally Signed O.M.P. (COMM) 191/2019 Page 21 of 26
    By:AANCHAL TAGGAR
    Signing Date:11.03.2026
    17:07:47
    (Goods), is by way of reasonable compensation and is a genuine pre-

    estimate of the loss the parties knew when they made the contract to be
    likely from delay by the Claimant in delivery of the Pipes. The
    imposition of the PRS Amount is valid and legal and as per the
    contract between the parties. Furthermore, it does not lie in the mouth of
    the Claimant to, after admittedly breaching its contractual obligations,
    allege that Respondent is not liable to receive payment of any money
    towards the admitted damages caused to it as a result of the said delay.
    Such an allegation is arbitrary and contrary to principles of natural
    justice and would have the effect of rendering as redundant the various
    provisions of the contract between the parties. Reliance is placed on
    paragraph 1 of the preliminary submissions.”

    [Emphasis supplied]

    41. Man Industries relied upon the judgment of the Supreme Court in
    Kailash Nath Associates v. DDA (supra) in support of its submission that
    the party claiming damages on account of breach of contract must show the
    actual loss suffered.
    In Kailash Nath Associates v. DDA (supra), the
    Supreme Court observed that to avail the benefit of Section 74 of the Indian
    Contract Act, 1872, damage or loss is a sine qua non. In the said case, it was
    held that there was no breach of contract by the appellant-Kailash Nath.
    Further, the respondent-DDA had profited from re-auction of the subject
    land. Therefore, the basic requirement under Section 74 of the Indian
    Contract Act with respect to loss or damage suffered by a party, was not
    fulfilled.
    The relevant paragraph of Kailash Nath Associates v. DDA (supra)
    is set out below:

    “44. The Division Bench has gone wrong in principle. As has been
    pointed out above, there has been no breach of contract by the
    appellant. Further, we cannot accept the view of the Division Bench that
    the fact that DDA made a profit from re-auction is irrelevant, as that
    would fly in the face of the most basic principle on the award of
    damages-namely, that compensation can only be given for damage or
    loss suffered. If damage or loss is not suffered, the law does not provide

    Signature Not Verified
    Digitally Signed O.M.P. (COMM) 191/2019 Page 22 of 26
    By:AANCHAL TAGGAR
    Signing Date:11.03.2026
    17:07:47
    for a windfall.”

    [Emphasis supplied]

    Hence, the ratio of the aforesaid judgment would not apply in the facts of the
    present case.

    42. In Bharat Heavy Electricals Limited v. Kanohar (supra) relied by
    Man Industries, the Division Bench upheld the findings of the Arbitrator as
    well as the Single Judge, that there was no legal justification for levy of
    liquidated damages upon the respondent. However, the aforesaid finding
    was premised on the fact that the appellant had failed to plead and
    demonstrate the legal injury. In the present case as noted above, there are
    clear pleadings by the respondent with regard to the loss caused on account
    of delay.

    43. Next, Man Industries has placed reliance on Indian Oil Corporation
    v. Standard Casting
    (supra), where the claim for damages was rejected by
    the Division Bench. However, the said conclusion was based on the fact that
    IOCL, the appellant in the case, had neither pleaded nor produced any
    material to demonstrate its entitlement to damages.

    44. In view of the discussion above, I do not find any perversity in the
    findings of the Arbitral Tribunal in respect of Claim No.1, which would
    require interference under Section 34 of the Act. The view taken by the
    Arbitral Tribunal in the Impugned Award is clearly a plausible view.

    Claim No. 2 – Wrongful refusal to reimburse the increase in Central
    Sales Tax (CST) from 4% to 5% amounting to Rs. 43,69,038/-

    45. The aforesaid claim was on account of failure of GAIL to reimburse
    Man Industries, upon an increase in Central Sales Tax (‘CST’) rate from 4%

    Signature Not Verified
    Digitally Signed O.M.P. (COMM) 191/2019 Page 23 of 26
    By:AANCHAL TAGGAR
    Signing Date:11.03.2026
    17:07:47
    to 5%. The Arbitral Tribunal has held that the petitioner has not produced
    any evidence to show that it has paid CST @ 5%. The aforesaid finding was
    returned on the basis of evidence on record.

    46. In this regard, reference may be made to Clause 33.2 of the GCC-
    Goods, which is set out below:

    “33. Taxes & Duties
    33.1 … … …

    33.2 A domestic Seller shall be entirely responsible for all taxes, duties,
    licence fees etc. incurred until the delivery of the contracted goods to the
    PURCHASER. However, Sales Tax and Excise duty on finished products
    shall be reimbursed by PURCHASER.”

    [Emphasis supplied]

    47. The Arbitral Tribunal has also observed that in terms of Clause 33.2
    of the GCC-Goods, GAIL is liable to reimburse the sales tax to Man
    Industries and reimbursement necessarily implies that the tax would have
    been paid by Man Industries. However, Man Industries did not adduce any
    evidence to show that the differential rate of tax of 1% was paid to the
    government.

    48. The Arbitral Tribunal has specifically noted that Man Industries’
    witness during cross examination had admitted that the claim of the CST
    was not made in the final bill, but was for the first time made in arbitration
    proceedings. Hence, GAIL was not liable to reimburse Man Industries.

    49. The aforesaid finding has been arrived at by the Arbitral Tribunal,
    while interpreting the relevant clause of the Contract and based on the
    evidence produced on behalf of the parties. It is a settled position of law that
    in proceedings under Section 34 of the Act, the Court cannot re-appreciate

    Signature Not Verified
    Digitally Signed O.M.P. (COMM) 191/2019 Page 24 of 26
    By:AANCHAL TAGGAR
    Signing Date:11.03.2026
    17:07:47
    the evidence that was placed before the Arbitral Tribunal.

    50. Hence, no fault can be found with the aforesaid finding of the Arbitral
    Tribunal in respect of Claim No.2.

    Claim No. 3 – Interest for the delayed payment of 10% of the total value
    of the Contract

    51. The Arbitral Tribunal has observed that Man Industries did not make
    this claim in the “No Claim Certificate” dated 3 rd August 2012, wherein it
    was confirmed by Man Industries that other than a sum of Rs. 64,13,790/-
    and the PRS amount, no further amount is due. The Arbitral Tribunal also
    gave a finding that the final settlement was arrived at between the parties
    after mutual negotiations.

    52. As regards the contentions of Man Industries that the ‘No Claim
    Certificate’ was signed under economic duress, the Arbitral Tribunal has
    held that no evidence has been led by Man Industries in this regard and only
    an oral submission was made.

    53. In view thereof, I do not find any infirmity in the finding of the
    Arbitral Tribunal denying the Claim No.3 made by Man Industries.

    Claim No. 4 – Interest pre-suit, pendente lite and future

    54. Since this Court has upheld the Impugned Award in respect of Claim
    Nos.1 to 3, consequently, the finding of the Arbitral Tribunal in respect of
    Claim No.4 is also affirmed.

    Claim No.5 – Cost of Proceedings

    55. Taking into consideration the respondent’s share of Arbitrator’s fees,
    secretarial expenses, expenses for the venue, lawyers’ fees etc., the Arbitral

    Signature Not Verified
    Digitally Signed O.M.P. (COMM) 191/2019 Page 25 of 26
    By:AANCHAL TAGGAR
    Signing Date:11.03.2026
    17:07:47
    Tribunal came to the finding that Man Industries was liable to pay costs of
    Rs.10,00,000/- to GAIL.

    56. No cogent ground for interference has been made out on behalf of
    Man Industries.

    CONCLUSION

    57. In light of the discussion above, I am of the view that the petitioner
    has failed to make out any ground for interference with the Impugned
    Award under Section 34 of the Act.

    58. Accordingly, the petition is dismissed.

    59. All pending applications stand disposed of.

    AMIT BANSAL
    (JUDGE)
    MARCH 11, 2026
    at

    Signature Not Verified
    Digitally Signed O.M.P. (COMM) 191/2019 Page 26 of 26
    By:AANCHAL TAGGAR
    Signing Date:11.03.2026
    17:07:47



    Source link

    LEAVE A REPLY

    Please enter your comment!
    Please enter your name here