Become a member

Get the best offers and updates relating to Liberty Case News.

― Advertisement ―

HomeSupreme Court - Daily OrdersIndra Sistemas S.A vs Kolkata Metro Rail Corporation Ltd on 23 February,...

Indra Sistemas S.A vs Kolkata Metro Rail Corporation Ltd on 23 February, 2026

Supreme Court – Daily Orders

Indra Sistemas S.A vs Kolkata Metro Rail Corporation Ltd on 23 February, 2026

                                               IN THE SUPREME COURT OF INDIA
                                                CIVIL ORIGINAL JURISDICTION


                                           ARBITRATION PETITION NO.73/2025


                         INDRA SISTEMAS S.A                                                ...PETITIONER



                                                                 VERSUS



                         KOLKATA METRO RAIL CORPORATION LTD.                               ...RESPONDENT


                                                             O R D E R

1. We have heard the learned counsel for the parties

and perused the record.

2. By way of the instant petition under Section 11(6)

of the Arbitration and Conciliation Act, 1996 (“Act”),

the Petitioner seeks appointment of the Respondent’s

Nominee Arbitrator as well as the third/presiding

Arbitrator. Such appointment is sought under Clause 17.9

of the General Conditions of Contract (“GCC”), as

amended by Clause 49B of the Special Conditions of

Contract (“SCC”), which form part of the Contract

Agreement dated 10.09.2014 (“Contract”) entered into

between the parties.

Signature Not Verified

Digitally signed by
ARJUN BISHT
Date: 2026.02.25
16:49:23 IST
Reason: 3. To broadly set out the sequence of events, the

Petitioner is a company registered under the laws of

1
Spain and engaged in the business of metro rail traffic

management and fare collection systems, while the

Respondent is a Government of India enterprise

implementing the Kolkata (East-West Metro) Corridor

Project (“Project”).

4. Under the Contract, the Petitioner was entrusted

with the design, manufacture, supply, installation,

testing and commissioning of the Automatic Fare

Collection (AFC) System for the Project. The works under

the Contract were structured in two phases, namely Phase

I and Phase II, the latter encompassing the Backup

Control Centre (“BCC”). The Contract incorporates the

GCC and SCC, which contain the arbitration agreement

under Clause 17.9 of the GCC as modified by Clause 49B

of the SCC. The relevant part of the modified Arbitration

agreement reads as follows:

“49B Sub-Clause 17.9 — Arbitration
Paragraphs (a), (b) & (c) are replaced by the
following paragraphs:

a) The Arbitration Board will consist of three
Arbitrators. The Contractor and the Employer
shall appoint their own Arbitrator and the two
appointed Arbitrators shall appoint the third
Arbitrator in accordance with Section 11 of
Arbitration and Conciliation Act, 1996 of India.

All Arbitrators shall be Indian nationals
ordinarily residing in India with technical
competence and experience. The Arbitrator(s)
shall be appointed within a period of 30 days
from the date of receipt of written
notice/demand of appointment of Arbitrator from
either party. Neither party shall be limited in
the proceedings before such arbitrator(s) to the

2
evidence or arguments put before the Engineer
for the purpose of obtaining his decision. No
decision given by the Engineer in accordance
with the foregoing provisions shall disqualify
him from being called as a witness.

The parties shall be entitled to produce
evidence and giving evidence before the
arbitrator(s) on any matter whatsoever relevant
to dispute or difference referred to
arbitrator(s). The arbitration proceedings shall
be held in Kolkata only. The language of
proceedings, that of documents and communication
shall be English.

Para b) Not used.

Para c) The award of the majority of the three
arbitrators shall be binding on all parties.”

5. The Contract was subsequently amended by a

supplementary agreement dated 13.02.2019 in respect of

certain software deliverables forming part of the AFC

System works.

6. It appears that the dispute between the parties

initially arose from delay-related costs and damages

incurred by the Petitioner, prompting it to issue a

notice of dispute dated 03.08.2023. Being dissatisfied

with the Respondent’s reply, the Petitioner invoked

conciliation under Clause 17.6 of the GCC on 29.09.2023,

which the Respondent accepted on 26.10.2023. However,

conciliation proceedings did not commence despite the

lapse of more than 1.5 years.

7. In the meantime, a further dispute arose in

relation to the BCC, pursuant to which the Respondent

took the position that the Petitioner had failed to

3
supply the BCC in accordance with the Contract and

proceeded to procure the same from third parties, while

effecting recoveries of the alleged differential cost

from the payments due to the Petitioner

8. Apprehending the invocation of bank guarantees by

the Respondent in terms of the Contract, the Petitioner

approached the High Court of Calcutta by filing petition

bearing AP-COM No. 621 of 2025 under Section 9 of the Act

seeking certain interim relief(s). During the pendency of

the aforesaid proceedings before the High Court, the

Petitioner terminated the aforementioned conciliation

proceedings vide letter dated 06.08.2025. Ultimately, the

High Court vide order dated 12.08.2025 declined to grant

interim relief but directed the Petitioner to proceed

with the constitution of the Arbitral Tribunal.

9. The Petitioner, consequently, issued a Notice

Invoking Arbitration dated 19.08.2025 and nominated

Justice Sanjib Banerjee, former Chief Justice of the

Meghalaya High Court, as its arbitrator. The Respondent,

however, did not appoint its Nominee arbitrator within

the stipulated 30-day period. Instead, vide letter dated

16.09.2025, the Respondent raised an objection to the

eligibility of the Petitioner’s nominee under Clause 49B

of the SCC and requested the Petitioner to select an

arbitrator from a panel of five arbitrators suggested by

4
it. The Petitioner responded to the said communication by

its letter dated 18.09.2025, disputing the objection

raised by the Respondent. Thereafter, the Respondent did

not proceed to appoint its Nominee Arbitrator, which has

led to the instant petition being instituted.

10. Learned counsel for the parties have fairly

acknowledged that the arbitration agreement provides for

the seat of arbitration to be in Kolkata and that it

would be procedurally governed by the Act. During the

course of the hearing, learned counsel for the Respondent

also stated that they have no objection to the arbitrator

nominated by the Petitioner and, to that effect, have

placed on record a letter dated 26.11.2025, thereby

approving the appointment of Justice Sanjib Banerjee as

the Nominee Arbitrator of the Petitioner.

11. Furthermore, the learned counsel for the

Respondent proposed Justice Jyotirmay Bhattacharya,

former Chief Justice of the Calcutta High Court, as the

Respondent’s nominee, to which the Petitioner raised no

objection.

12. Having regard to the facts and circumstances of

the case and the provisions of the Contract governing the

appointment of arbitrators, Justice Jyotirmay

Bhattacharya is appointed as the Nominee Arbitrator on

5
behalf of the Respondent. The third/presiding arbitrator

shall be nominated by the two learned arbitrators, in

accordance with the agreed procedure, expeditiously, and

preferably within three weeks.

13. In accordance with the agreement entered into by

the parties, the proceedings shall be held in Kolkata,

West Bengal, India. The Arbitrators shall have the

liberty to fix their own remuneration/fees. Initially,

the parties shall pay the cost of arbitration equally.

14. Ordered accordingly.

15. The Arbitration Petition is disposed of in the

above terms. Pending interlocutory applications, if any,

shall stand closed.

……………………..CJI.

(SURYA KANT)

………………………..J.
(JOYMALYA BAGCHI)

NEW DELHI;

  FEBRUARY 23, 2026




                                  6
ITEM NO.35               COURT NO.1                  SECTION PIL-W

                S U P R E M E C O U R T O F      I N D I A
                        RECORD OF PROCEEDINGS

Petition(s) for Arbitration No(s).73/2025

INDRA SISTEMAS S.A Petitioner(s)

VERSUS

KOLKATA METRO RAIL CORPORATION LTD Respondent(s)

IA No. 328201/2025 – PERMISSION TO FILE ADDITIONAL
DOCUMENTS/FACTS/ANNEXURES

Date : 23-02-2026 This matter was called on for hearing today.

CORAM : HON’BLE THE CHIEF JUSTICE
HON’BLE MR. JUSTICE JOYMALYA BAGCHI

For Petitioner(s) :Mr. Prashant Pakkhidey, Adv.

Mr. Manav Gill, Adv.

Ms. Saksha Jha, Adv.

Ms. Mrinal Kanwar, AOR
Mr. Vaibhav Rajsingh Rathore, Adv.

Mr. Dinesh Kumar Chouhan, Adv.

For Respondent(s) :Mr. Partha Sil, AOR
Mr. Utkarsh Dwivedi, Adv.

Mr. Srijit Datta, Adv.

UPON hearing the counsel the Court made the following
O R D E R

1. The Arbitration Petition is disposed of in terms of the signed

order.

2. All pending applications, if any, also stand disposed of.

(ARJUN BISHT)                                   (PREETHI T.C.)
ASTT. REGISTRAR-cum-PS                        ASSISTANT REGISTRAR
                (signed order is placed on the file)




                                  7



Source link