Conso Feeds vs Alfa Laval (India) Pvt.Ltd on 6 August, 2026

    0
    4
    ADVERTISEMENT

    Bombay High Court

    Conso Feeds vs Alfa Laval (India) Pvt.Ltd on 6 August, 2026

                                                                          CNR No : HCBM020251372018
     2026:BHC-OS:17613
    
                                                                          CARBP-1267-2018 (final).doc
    
    
                                   IN THE HIGH COURT OF JUDICATURE AT BOMBAY
                                         ORDINARY ORIGINAL CIVIL JURISDICTION
                                             IN ITS COMMERCIAL DIVISION
    
                               COMMERCIAL ARBITRATION PETITION NO. 1267 OF 2018
    
                      Conso Feeds                                  ]
                      Eara P.O., Neelamperoor, Alappuzha,          ]
                      District 686534, represented by its Managing ]
                      Partner                                      ]
                                                                       ...Petitioner
    
                               Versus
    
                      Alfa Laval (India) Pvt. Ltd.                   ]
                      Registered Office at Mumbai-Pune Road,         ]
                      Dapodi, Pune - 411012,                         ]
                      Through its Managing Director                  ] ...Respondent
                                                     ------------
                      Mr. Anil D'souza, Mr. Akash Rebello, Mr. Paras Gosar and Mr. Nadeem Shama for
                      the Petitioner.
                      Mr. Sharan Jagtiani, Senior Advocate a/w Mr. Rohil Bandekar, Mr. Nitin Khare,
                      Mr. Ritwik Kulkarni and Mr. Akhil Khupade for the Respondent.
                                                     ------------
                                                             Coram : Sharmila U. Deshmukh, J.
    

    Reserved on : 10th July, 2026.

    Pronounced on : 6th August, 2026.

    SPONSORED

    Judgment :

    1. The present Petition filed under Section 34 of the Arbitration

    and Conciliation Act, 1996 is at the instance of the original Claimant

    being partly aggrieved by the impugned Award to the extent that the

    Claims 15(2) to 15(8) have been held to be barred by Clauses 10 (a) and

    (b) of Techno Commercial Agreement dated 10 th September, 2014 and

    capped by the Arbitrator to the extent of the amount of the Bank

    Sairaj 1 of 36

    Uploaded on – – Downloaded on – 06/08/2026 22:44:33
    CARBP-1267-2018 (final).doc

    Guarantee which is invoked and encashed by the Claimant.

    2. The arbitration agreement was invoked by the Claimant seeking

    resolution of disputes which arose between the parties under an

    Agreement of 10th September, 2013 executed between the Claimant

    and the Respondent for the purchase and installation of fishmeal

    plant.

    3. The Petition sets out that by purchase order of 11 th September,

    2013 read with Techno Commercial Agreement dated 10 th September,

    2013, the Claimant had purchased fishmeal plant from the

    Respondent, which the Respondent was required to supply, erect and

    commission. Despite various attempts, the plant could not be

    commissioned solely due to the faulty design and equipment supplied

    by the Respondent and the Claimant called upon the Respondent to

    take back the plant. As there was no refund of the price of the plant as

    initially claimed by the Claimant, arbitration was invoked. In the Section

    11 application, the learned Sole Arbitrator came to be appointed by

    this Court.

    4. The statement of the claim (SOC) sets out that the pursuant to

    the discussions and negotiations, on 10th September, 2013, the

    Respondent submitted the final quotation with detailed payment

    terms and in response thereof, on 11th September, 2013, the Claimant

    issued the purchase order, which was confirmed. The entire payment of

    Sairaj 2 of 36

    Uploaded on – – Downloaded on – 06/08/2026 22:44:33
    CARBP-1267-2018 (final).doc

    the purchase order was paid in time aggregating to Rs. 4,94,49,669/-

    and Bank guarantee was issued in favor of the Respondent in the sum

    of Rs. 2.45 crores representing the balance payment and performance

    guarantee was given by the Respondent in favor of the Claimant. As

    per the Agreement, the erection and the commissioning of the fish

    meal plant was to be completed by 31 st March, 2014, which was

    delayed for reasons attributable to the Respondent. On 5 th September,

    2014, the Respondent invoked the Bank guarantee which would have

    expired only on 24th September, 2014. On 19th September, 2014, the

    first trial run of the plaint was conducted, which failed. The email

    correspondences are relied upon to substantiate that the subsequent

    eight production trials till 12th December, 2014 also failed.

    5. The Claimant had availed financial assistance to the tune of

    7,06,75,777/- from Federal Bank in addition to incurring huge interest

    amount to the tune of Rs. 2,01,41,515/-. The claim under various heads

    was for sum of Rs. 17,64,81,771/-.

    6. In its Written Statement-cum-Counterstatement of claim, the

    Respondent claimed that the Respondent could not erect and install

    the plant immediately as the site was not ready. The provisions of

    utilities could be made only in September, 2014 when the first trial was

    conducted. The Claimant failed to supply sufficient quantity of raw

    material to run the plaint at its optimum level. The commercial

    Sairaj 3 of 36

    Uploaded on – – Downloaded on – 06/08/2026 22:44:33
    CARBP-1267-2018 (final).doc

    operation of the plant commenced on 12 th November, 2014 without

    any interruption and that there was non-compliance of the conditions

    imposed by the Kerala Pollution Control Board for operating the said

    plant, which was violated resulting in pollution. The Claimant in

    collusion with the ICICI Bank got the performance bank guarantee

    encashed fraudulently much before the expiry date and further sent a

    legal notice on 21st October, 2015 demanding sum of Rs.

    16,46,34,828/-. There was successful and satisfactory commission and

    performance trial of the fishmeal plant giving no cause of action for

    any liability upon the Respondent. The counter claim of the

    Respondent was for a sum of Rs. 44,50,000/- plus interest at the rate of

    15% per annum being encashment of performance bank guarantee by

    the claimant.

    7. The Learned Arbitrator held that there was breach of contract by

    the Respondent and the Claimant had performed its part of obligation

    under the Techno Legal Commercial Agreement dated 10 th September,

    2013 and Purchase Order dated 11th September, 2013. It further held

    that the Claimant had rightly invoked the performance bank guarantee

    and answered the counter claim against the Respondent. Insofar as the

    claim for Rs 17,64,81,771/- is concerned, the learned Arbitrator

    directed refund of purchase price of Rs. 4,45,00,000/- with interest

    therein at the rate of 9% p.a. from the date of Award till the payment

    Sairaj 4 of 36

    Uploaded on – – Downloaded on – 06/08/2026 22:44:33
    CARBP-1267-2018 (final).doc

    and realization and upon such payment, the Respondent was entitled

    to take back its supplies and equipment from the Claimant’s site of the

    fishmeal plant, within a period of six months from the date of payment.

    The claims from 15(2) to 15(8) were held to fall within the ambit of

    Clause 10(a) and (b) of the general terms and conditions in Section VI of

    the Techno Commercial Agreement and held to be limited to amount

    of the bank guarantee which was invoked and encashed by the

    Claimant.

    8. Mr. D’souza, learned counsel appearing for the Petitioner would

    point out that the claims 15(2) to (7) were in respect of excise duty,

    sales tax, freight charge, etc. which were incurred by the Claimant

    towards the installation of the plant. He would further point out the

    relevant Issue No 5 as to the entitlement of the Claimant to the sum of

    Rs.17,64,81,771/- or any part thereof. He submits that as the Arbitrator

    has directed the refund of the purchase price of the plant, it is

    accepted that there is a breach of contract by the Respondent. He

    would submit that as the breach has been admitted, there was no

    question of application of clause 10(a) and 10(b) of the Agreement to

    direct losses. He submits that the claims raised by the claimant were

    not indirect, but actual expenses incurred and not a claim based on

    reimbursement of actual expenses. He submits that the defense of the

    claims being barred by Clause 10(a) is not the pleaded case of the

    Sairaj 5 of 36

    Uploaded on – – Downloaded on – 06/08/2026 22:44:33
    CARBP-1267-2018 (final).doc

    Respondent and therefore the Claimant did not have an opportunity of

    dealing with the same.

    9. He would submit that there is an inherent contradiction in the

    Award by pointing out that the learned Arbitrator while rejecting other

    claims held it to be barred by Clause 10(a) of the Techno Commercial

    Agreement contrary to its own finding that Clause 10(a) was attracted

    only after the machinery was supplied and commissioned. He submits

    that as the Tribunal has held that the plant has not commissioned,

    there is no question of clause 10(a) being applied to the present case.

    He has taken this Court in detail through the findings of the Arbitrator

    in paragraph 126 to 136 and 147 of the Award. He submits that the

    claim towards payment of interest under Claim 15(7) cannot be

    construed to be an indirect or consequential damage or liability as

    provided in Clause 10 and according to him, there is error in not

    awarding interest from date of payment of purchase price and

    pendente lite. He submits that by the clarificatory order passed under

    Section 33 of Arbitration Act, the Arbitrator has clarified that interest

    pendente lite has not been granted. He submits that once the

    Arbitrator comes to a conclusion that damages are payable due to

    failure to commission the plant, damages by way of interest from date

    of payment of purchase price and pendente lite has to follow. He

    submits that the Claimant is entitled to interest on all the claims as

    Sairaj 6 of 36

    Uploaded on – – Downloaded on – 06/08/2026 22:44:33
    CARBP-1267-2018 (final).doc

    provided in Section 31(7) of the Arbitration Act and the refusal to

    award such interest is against the public policy of India and liable to be

    set aside.

    10. He submits that Claims 15(2) to 15(7) cannot be treated as

    consequential damage or loss of profit as a matter of fundamental and

    substantive law of India. He submits that it is not a question of

    interpretation of contract, but a matter of application of substantive

    law. He submits that any finding to the contrary will be perverse,

    patently illegal as well as violative of public policy. He submits that the

    loss on account of payment of excise duty, sales tax, freight charges,

    etc. were clearly direct and not consequential loss and once the

    Arbitrator arrives at a conclusion that Clause 10(a) relates only to

    consequential damages, he could not have excluded Claims 15(1) to

    15(7). He submits that the claims being direct damages were not

    capable of being excluded by Clause 10(a) and ought have been

    allowed.

    11. He would further submit that upon plain reading of the

    Agreement, clause 10(a) and (b) is superseded by warranty clause and

    offer letter dated 10th September, 2014 by virtue of clause 10(h) as per

    the general terms and conditions. He submits that the warranty clause

    makes it clear that the Respondent is not responsible for any

    consequential or indirect damages and by providing an express clause

    Sairaj 7 of 36

    Uploaded on – – Downloaded on – 06/08/2026 22:44:33
    CARBP-1267-2018 (final).doc

    for damages in the main Agreement, Clause 10(a) and (b) stands

    excluded.

    12. He submits that the Petitioner’s claim is for expenses as well as

    loss of profits which are direct damages and Claim 15(8) which is loss of

    business opportunity is a direct damage and not an indirect damage.

    He submits that the Arbitrator erred in rejecting the arguments of the

    Claimant that the rule of contra proferentem must apply to the

    interpretation of clause 10(a). He submits that the contract must be

    interpreted against the person who has drafted the contract and in the

    present case, the offer sheet has been prepared by the Respondent

    and must be interpreted against the Respondent.

    13. He submits that the reading of the Tribunal of Clause 10(a)

    amounts to rewriting of the contract between the parties and is an

    error apparent on the face of record, perverse and illegal. He submits

    that the interpretation of the Arbitrator of clause 10(a) of the contract

    is an impossible interpretation which would warrant interference under

    Section 34 of Arbitration Act.

    14. He would further submit that the written statement of the

    Respondent does not speak of limitation of liability and despite

    thereof, the Arbitrator has limited the liability to the extent of bank

    guarantee. He submits that the claims set out in paragraph 130 of the

    Award have been accepted by the Arbitrator, however, the Arbitrator

    Sairaj 8 of 36

    Uploaded on – – Downloaded on – 06/08/2026 22:44:33
    CARBP-1267-2018 (final).doc

    has limited the same to the amount of Bank guarantee, which is a

    perverse finding. In support, he relies upon the following decisions :

    Deepak Fertiliser and Petrochemical Corporation vs.
    Davy Mckee (London) Ltd.1

    Union of India vs. Saraswat Trading Agency2

    South East Asia Marine Engineering and
    Constructions Ltd. vs. Oil India Ltd.3

    Delhi Metro Rail Corporation Ltd. vs. Delhi Airport
    Metro Express Pvt. Ltd.4

    15. Per contra, Mr. Jagtiani, learned Senior Advocate appearing for

    the Respondent would submit that the apart from refund of purchase

    price, the other claims were in the nature of damages for the breach of

    the contract. He submits that the contention that the Respondent has

    not taken the defence of Claims 15(2) to 15(8) being excluded by

    Clause 10, cannot be entertained by Section 34 Court as it would

    amount to re-appreciation of evidence. He submits that it is well

    settled that the Arbitrator is the best judge of the quality and quantity

    of evidence. He further points out that the Respondent has specified

    that its liability as per the agreed terms is restricted to the

    performance guarantee and the Claimant had sufficient notice about

    denial of its claim by reason of Clause 10(a) of the Agreement.

    16. He would further submit that the entire submissions of Mr.
    1 (1998) EWCA Civ 1753.

    2 (2009) 16 SCC 504.

    3 (2020) 5 SCC 164.

    4 (2024) 6 SCC 357.

    Sairaj 9 of 36

    Uploaded on – – Downloaded on – 06/08/2026 22:44:33
    CARBP-1267-2018 (final).doc

    D’souza is to assail the interpretation of the contract by the Arbitrator,

    which is impermissible in Section 34 Petition. He submits that the view

    taken by the Arbitrator being a possible view cannot be interfered and

    substituted by view of this Court. He has taken this Court to Clause

    10(a) of the Agreement to contend that the same is divided in two

    parts and in the first part damages on account of the specified

    eventualities are excluded from the Respondent’s liability and second

    part capped the liability of the Respondent at the value of

    performance bank guarantee. He submits that it is also a possible

    interpretation that the warranty clause does not supersede Clause 10

    of general terms and condition. He submits that the Award is founded

    on interpretation of the terms of the contract and there is no issue of

    violation of fundamental and substantive law of India.

    17. He would further submit that power of the Arbitrator to award

    pre-reference interest, pendente lite interest, and post award interest

    under Section 31(7) is well settled and the relief sought in the present

    case was to award future interest and costs against the Respondent.

    He submits that the Arbitrator by the additional award has declined the

    Claimant’s relief of grant of pendente lite interest. He submits that

    discretion has been rightly exercised by the arbitrator, no interference

    is warranted. To support his contentions, reliance is placed on the

    following decisions:

    Sairaj 10 of 36

    Uploaded on – – Downloaded on – 06/08/2026 22:44:33
    CARBP-1267-2018 (final).doc

    Securitrans India Pvt. Ltd. vs. FIS Payment
    Solutions and Services Pvt. Ltd.5

    United India Insurance Company Ltd. vs. UPL
    Limited6

    Thermax Ltd. vs. Rashtriya Chemicals and
    Fertilizers7

    Associate Builders vs. Delhi Development
    Authority8

    Oil and Natural Gas Corporation Ltd. vs. Saw Pipes
    Ltd.9

    Sangyong Engineering and Construction Company
    Ltd. vs. National Highways Authority of India10

    Larsen Air Conditioning and Refrigration Company
    vs. Union of India11

    Batliboi Environmental Engineers Ltd. vs.
    Hindustan Petroleum Corporation Limited12

    Reliance Infrastructure Limited vs. State of Goa13

    S. V. Sundaram vs. State of Karnataka14

    Rajasthan State Mines and Minerals Ltd. vs.
    Eastern Engineering Enterprises15

    Associated Engineering Co. vs. Government of
    Andhra Pradesh16

    5 Judgment dated 23.12.2023 passed in CARBP No. 750 of 2024.
    6 2026 SCC OnLine Bom 2679.

    7 2025 SCC Online Bom 5010.

    8 (2015) 3 SCC 49.

    9 (2003) 5 SCC 705.

    10 (2019) 15 SCC 131.

    11 2023 SCC OnLine SC 982.

    12 (2024) 2 SCC 375.

    13 (2024) 1 SCC 479.

    14 (2024) 3 SCC 623.

    15 (1999) 9 SCC 283.

    16 (1991) 4 SCC 93.

    Sairaj 11 of 36

    Uploaded on – – Downloaded on – 06/08/2026 22:44:33
    CARBP-1267-2018 (final).doc

    Ramnath International Construction (P) Ltd. vs.
    Union of India17

    Vilayati Ram Mittal (P) Ltd. vs. Reserve Bank of
    India18

    John Peter Fernandes vs. Saraswati Ramchandra
    Ghanate
    since deceased and Others19

    Pam Developments Private Limited vs. State of
    West Bengal20

    UHL Power Company Limited vs. State of Himachal
    Pradesh21

    Dyna Technologies Private Limited vs. Crompton
    Greaves Limited22

    Parsa Kente Collieries Limited vs. Rajasthan Rajya
    Vidyut Utpadan Nigam Limited23

    Rashtriya Ispat Nigam Limited vs. Dewan Chand
    Ram Saran24

    South East Asia Marine Engineering and
    Constructions Limited vs. Oil India Limited25

    Morgan Securities and Credits Private Limited vs.
    Videocon
    industries Limited26

    Hyder Consulting (UK) Limited vs. Governor, State
    of Orissa
    through Chief Engineer27

    Secretary, Irrigation Department, Government of

    17 (2007) 2 SCC 453.

    18 2017 SCC OnLine Bom 8479.

    19 2023 SCC OnLine Bom 676.

    20 2024 SCC OnLine SC 2247.

    21 (2022) 4 SCC 116.

    22 (2019) 20 SCC 1.

    23 (2019) 7 SCC 236.

    24 (2012) 5 SCC 306.

    25 (2020) 5 SCC 164.

    26 (2023) 1 SCC 602.

    27 (2015) 2 SCC 189.

                      Sairaj                           12 of 36
    
    
    
    
    Uploaded on - -                                          Downloaded on - 06/08/2026 22:44:33
                                                                                CARBP-1267-2018 (final).doc
    
    
                                    Orissa vs. G. C. Roy28
    
                                    NHAI vs. M. Hakeem29
    
                                    S. V. Sundaram vs. State of Karnataka30
    
    

    18. In rejoinder, Mr. D’souza would submit that there is a patent

    illegality as Clause 10(a) does not include interest and therefore, the

    Arbitrator could not have limited the claim for interest while capping

    the liability. He submits that the Award is severable as claim 15(1) has

    been granted and claim 15(2) to 15(8) has been rejected, which are

    different heads of the claim and therefore, good part of the Award can

    be retained while severing the bad part of the Award. He submits that

    the decision in the case of OPG Power Generation Private Limited vs.

    Enexio Power Cooling Solutions India31 will apply when the ultimate

    conclusion is not disturbed and not when there is an inherent

    contradiction and ultimate conclusion would change. He would further

    distinguish the judgment on interest cited by Mr. Jagtiani to contend

    that the bank interest claimed is pendente lite interest and Section

    31(7) discretion has not been exercised. He submits that the bank

    interest is raised as claim only to show what has been paid as interest.

    19. Rival contentions now fall for determination.

    20. At the heart of controversy is Clause 10(a) and (b) and Warantee

    28 (1992) 1 SCC 508.

    29 (2021) 9 SCC 1.

    30 (2024) 3 SCC 623.

    31 2024 INSC 711.

    Sairaj 13 of 36

    Uploaded on – – Downloaded on – 06/08/2026 22:44:33
    CARBP-1267-2018 (final).doc

    Clause of the Techno-Commercial Agreement dated 10 th September,

    2013. In so far as refund of purchase price is concerned, the Learned

    Arbitrator has held that there is breach of contract by the Respondent

    and had awarded refund of purchase price and rejected Claims 15(2) to

    15(8). Claims 15(2) and 15(3) are claims for amounts of excise duty,

    state tax, freight and insurance charges. Claim 15(4) is a claim for

    expenses incurred for accommodation of Respondent’s engineers and

    officials. Claim 15(5) is a claim for expenses incurred for upgradation of

    infrastructure to suit contracted plant and supporting machinery

    including drier. Claim 15(6) is claim for raw material cost for seven

    trials. Claim 15(7) claims bank interest upto 31 st October, 2016 and

    Claim 15(8) is damage suffered on account of business opportunity

    loss, mental agony and loss of reputation.

    21. In paragraph no. 15 of the SOC, the Claimant has set out various

    claims against the Respondent, as under:

    1. Price of the Plant Rs. 4,45,00,000.00

    2. Excise Duty, Sales Tax Rs. 49,49,669.000

    3. Freight charges and insurance Rs. 4,33,608.000

    4. Expenses for accommodation of Alfalaval’s
    Engineers and Officials Rs. 4,15,250.000

    5. For up-gradation of infrastructure to suit
    contracted Plant and supporting machinery
    including drier Rs. 2,61,27,517.000

    6. Raw Materials cost for seven trial runs Rs. 18,22,335.000

    7. Bank interest upto 31.10.2016 Rs. 2,26,83,392.000

    8. Damage suffered on account of business

    Sairaj 14 of 36

    Uploaded on – – Downloaded on – 06/08/2026 22:44:33
    CARBP-1267-2018 (final).doc

    loss’ opportunity loss, mental agony and loss
    of reputation limited to Rs. 8,00,00,000.00
    Total Rs. 18,09,31,771.00

    Less : Amount of performance Guarantee
    enforced to mitigate the loss without
    prejudice to any of the claims as above Rs. 44,50,000.00
    Balance Payable Rs. 17,64,81,771.00

    22. The Learned Arbitrator has held that Claims 15(2) to 15(8) fall

    within the ambit of Clause 10(a) and capped the same to the limit of

    bank guarantee. The general terms and conditions are contained in

    Clause 10(a), 10(b), 10(h) of the Agreement dated 10 th September, 2013

    and reads as under :

    “10. General

    a) Consequential Damages

    We shall not be liable for any consequential damages,
    loss of profit, costs and/or expenses if any incurred by
    you or by any other person employed by you or
    representing you directly or indirectly, any third party
    obligations entered into by you or any statutory / legal
    obligation, awards, damages, statutory or legal action,
    costs or expenses in relation to the performance or any
    other feature of the plant supplied and / or erected
    and / or commissioned by us. Our obligation in this
    contract including all causes and any representations
    made by us to you shall not exceed the value of the
    performance bank guarantee/corporate guarantee or
    any other compensation agreed by us in the contract and
    shall be applicable only to faults noticed and not
    corrected in the performance of the equipment during
    the warranty period. All the obligations under the
    warranty period given by us shall be subject to your
    operating the plant and equipment as per the agreed
    method of operation as normally
    understood/specifically mentioned by us. The

    Sairaj 15 of 36

    Uploaded on – – Downloaded on – 06/08/2026 22:44:33
    CARBP-1267-2018 (final).doc

    performance warranty obligations are strictly subject to
    the battery limits, exclusions and output parameters
    mentioned in the contract.

    b) Secondary Liability

    Secondary liability such as indemnification for any loss
    caused by stoppage of the plant or due to any other
    reasons concerning this contract will under no
    circumstances be acceptable to us and we shall not be
    responsible for such losses.

    h) Order of Precedence

    Wherever any clauses as mentioned in this Contract are
    partly or fully at variance with the General Terms and
    Conditions of Sale, the printed form of which is
    enclosed, then clauses specifically entered into as part
    of this Contract shall have precedence and shall override
    the corresponding clauses in the General Terms and
    Conditions of Sale.”

    23. The Respondent in paragraph 8 of its written statement cum

    counterstatement of claim specifically denied the liability for any

    consequential damages or any secondary liability, including

    indemnification for any reason concerning the contract and capping of

    the liability to the value of performance bank guarantee referrable to

    Clause 10(a) and (b) of the contract. The impugned Award records at

    paragraph 123, the case of the Respondent that the claims made in

    paragraph 15 of SOC are in teeth of Clause 10(a) and (b) and in nature

    of damages without any averments in support thereof by relying on

    Section 73 of Contract Act. In paragraph 124, the submission of

    Respondent is recorded that claims would be limited to warranty

    Sairaj 16 of 36

    Uploaded on – – Downloaded on – 06/08/2026 22:44:33
    CARBP-1267-2018 (final).doc

    clause and there is no clause for refund. The defence of the

    Respondent was that none of the claims could be granted by the

    Learned Arbitrator as Clause 10(a) and 10(b) of the contract excluded

    the claims. The Respondent denied even Claim 15(1) seeking refund of

    purchase price.

    24. In the background of such submission, the Learned Arbitrator

    considered whether Clause 10(a) and (b) can be pressed into service by

    the Respondent to oppose the claims made by the Claimant and held in

    paragraph no. 126 as under:

    “126. The next question, then is, whether Clause 10 (a) and

    (b) forming part of the General Terms and Conditions in
    Section V of the Techno Commercial Agreement dated
    10.9.2013 and the clause relating to Warantee in Section IV
    of the said document relating to Price Schedule &
    Commercial Terms and Conditions can be pressed into
    service by the Respondent to oppose the claims made by the
    Claimant. In my opinion, a reading of the two clauses, it will
    be seen that the clause relating the Consequential Damages
    and Secondary Liability would apply in the event of the fish
    meal plant being supplied as contracted and it being
    commissioned by the Respondent and got ready for
    commercial operations without any defects or operational
    glitches. It is not material that the plant was not operated at
    the fullest capacity for any reason, but in the present case
    the plant was not able to function satisfactorily and certainly
    not demonstrated to be fit for commercial operations, free
    from any defect or deficiencies, which were found in one
    area or the other. Clause 10(a) of the Agreement dated
    10.9.2013 dealing with Consequential Damages relates to
    indirect damages and not damages or compensation arising
    out of the direct consequences of the Respondent’s failure
    to perform its obligations under the contract of supplying a
    functional fishmeal plant which can be taken to smooth

    Sairaj 17 of 36

    Uploaded on – – Downloaded on – 06/08/2026 22:44:33
    CARBP-1267-2018 (final).doc

    commercial operations. At the highest, Clause 10(a) of the
    Techno Commercial Agreement will restrict only to the
    consequential or indirect damages or the damages
    mentioned in the said clause. However, this clause is also
    inclusive of certain foreseeable losses mentioned therein
    (which can be termed as direct consequences) and have been
    factored in by the parties for the purpose of exclusion. In my
    opinion, the claims of the Claimant on account of loss of
    profit, costs and expenditure incurred on the provision of
    raw materials for the trials, etc would fall within the ambit of
    this clause, since notwithstanding the fact they are included
    under the clause relating to consequential damages, they
    find place in the limitations on liability covered by the said
    clause and are intended to be part of the limited liability of
    the Respondent. Damages on account of direct consequence
    of the breach of the contract or non-performance of the
    contract which fall outside the specified consequences or
    other than those specified only will not fall within the ambit
    of either of the clauses 10(a) and 10(b). The claimant will
    therefore be entitled to claim only such damages for direct
    losses or compensation as is warranted and not specifically
    excluded on account of breach of contract and the failure to
    perform the contract by the Respondent. I do not agree with
    the submission of the Counsel for the Claimant, that the
    doctrine of contra-proferentum should be applied in the
    facts of the present case to interpret the contract against
    the Respondent, or to hold that the Claimant was not aware
    of this clause in the agreement, it not having been brought
    to its notice, as there is no material on record to support this
    argument.

    25. It would also be apposite to reproduce paragraph 129 and 130

    of the Award which reads as under:

    “129. As mentioned before the Claimant has claimed
    a total amount Rs. 17,64,81,771.00 from the
    Respondent as a sum total of the various heads of
    claim. The first claim of Rs. 4,45,00,000/- being the
    price of the plant. There is no dispute that the

    Sairaj 18 of 36

    Uploaded on – – Downloaded on – 06/08/2026 22:44:33
    CARBP-1267-2018 (final).doc

    Respondent has received the said amount from the
    Claimant. Having held that the Respondent has
    failed to supply, erect, commission and provide a
    fishmeal plant as contemplated under the Contract
    between the parties, Claimant is presently saddled
    with the equipment which it is not in a position to
    use or operate. The Respondent having failed to
    provide a plant as per the contract, the Claimant will
    be entitled to compensatory damages as a direct
    result of its failures. I do not read the Clauses in the
    agreement relating to consequential damages and
    warrantee to hold that such compensation is barred
    or excluded and there is no specific bar (as was in the
    case law relied upon by the Counsel for the
    Respondent) to the grant of compensation for the
    direct loss arising on the failure of the Respondent.
    In my view, the loss of price paid for the defective
    and deficient supply, erection and defaults in setting
    up and commissioning the fish meal plan is a direct
    consequence of the Respondent’s failure and the
    Claimant is entitled to be compensated for it. I
    therefore hold that the Respondent is liable to pay
    to the Claimant the amount of Rs.4,45,00,000/ as
    compensation. The claimant will be entitled to
    interest at the rate of 9% p.a. from the date of the
    Award till payment and realisation.

    130. The claims under the other heads viz. Claim of
    Rs. 49,49,669/ towards of payment of excise duty,
    sales tax etc i.e. claim 15(2); Claim of Rs. 4,33,608/
    towards freight charges and insurance i.e. Claim 15
    (3); Claim of Rs. 4,12,250 towards expenses for the
    accommodation of Alfa Laval’s engineers and
    officials i.e. Claim 15 (4); Claim of Rs. 2,61,27,517/
    towards upgradation of infrastructure to suit
    contracted plant and supporting machinery; Claim of
    Rs. 18,22,335/ towards raw materials for the cost of
    seven trial runs i.e. Claim 15(6); claim of
    Rs.2,26,83,392/ towards bank interest upto
    31.10.216 i.e. Claim 15(7); and Rs.8,00,00,000/
    towards damage suffered on account of business
    loss, opportunity loss, mental agony, and loss of
    reputation i.e. Claim 15(8), would, in my opinion, all

    Sairaj 19 of 36

    Uploaded on – – Downloaded on – 06/08/2026 22:44:33
    CARBP-1267-2018 (final).doc

    fall within the ambit of Clause 10(a) and (b) of the
    General Terms and Conditions in Section VI of the
    Techno Commercial Agreement. These claims are
    limited to the amount of the bank guarantee which
    is invoked and encashed by the Claimant.”

    26. The learned Arbitrator has interpreted Clause 10(a) to be

    restricted to consequential or indirect damages, damages specified

    therein and even direct consequences for purpose of exclusion. Clause

    10(a) specified loss of profits, cots/expenses, statutory obligation

    apart from consequential/indirect damages. The latter portion of

    Clause 10(a) restricted the liability to extent of performance

    guarantee. By reason of specific mention of loss of profits, costs and

    expenses, etc. in clause 10(a), though under the heading of

    consequential damages, the learned Arbitrator has held that the Claims

    15(2) to 15(8) fall within ambit of Clause 10(a) and capped to the limit

    of performance bank guarantee. The learned Arbitrator has

    interpreted Clause 10(a) as an agreement between the parties

    specifying certain liabilities of the Respondent to be limited to the

    extent of performance bank guarantee.

    27. A case of inconsistency in paragraph 126 of the Award is sought

    to be raised by Mr. D’souza contending that in first part of paragraph

    126, the Learned Arbitrator has held that Clause 10(a) and (b) do not

    apply to the present case on account of non commissioning of the

    Sairaj 20 of 36

    Uploaded on – – Downloaded on – 06/08/2026 22:44:33
    CARBP-1267-2018 (final).doc

    plant as contracted, whereas in the second part of paragraph 126, the

    Arbitrator has denied the claims of Claimant by taking recourse to

    Clause 10(a). A conjoint reading of paragraph 126, 129 and 130 would

    disclose that the Learned Arbitrator has first put all claims in the

    basket of Clause 10(a) and (b) of contract in view of the defence that

    none of the claims can be granted by reason of the said Clause.

    Thereafter by an interpretative process, the Learned Arbitrator has

    analysed the claims in the context of Clause 10(a) and (b) to hold that

    Claim 15(1) pertaining to refund of purchase price is a direct result of

    the failure of Respondent to provide the plant and would not be

    covered by the contract clauses relating to consequential damages and

    warrantee to hold that such compensation is barred or excluded.

    Though a contention was raised about Section 73 of Contract Act, the

    Learned Arbitrator has granted Claim 15(1) by interpreting Clause 10(a)

    for its exclusion from the said clause. The learned Arbitrator has not

    applied the principles of Section 73 of Contract Act to grant Claim

    15(1), but has interpreted Clause 10(a) to hold that the claim 15(1) is

    direct result of failure which will not be covered by clause of

    consequential damages and warantee. It is pertinent to note that there

    is no sequiter to the finding in the first part of paragraph 126. The

    Claimant is a beneficiary of the interpretation of Clause 10(a) as the

    learned Arbitrator has ruled that the claim for refund of purchase price

    Sairaj 21 of 36

    Uploaded on – – Downloaded on – 06/08/2026 22:44:33
    CARBP-1267-2018 (final).doc

    does not form part of consequential damages and is direct result of the

    failure.

    28. The second portion of paragraph 126 of the Award read with

    paragraph 129 and 130 makes it abundantly clear that Clause 10(a) is

    held to be applicable to the claims raised by the Claimant. If the Award

    is read as a whole, the same clearly proceeds on the applicability of

    clause 10(a) and renders findings on various claims raised by the

    Claimant. The interpretation placed by the learned Arbitrator on

    Clause 10(a) as recorded in second part of paragraph 126 is not only a

    possible interpretation but it appeals to this Court. In the case of

    Securitrans India Pvt. Ltd. vs. FIS Payment Solutions and Services

    Pvt. Ltd. (supra), the Co-ordinate Bench has held that the Award has to

    be read in its entirety and finding of perversity can be recorded when

    there are absolutely no reasons for reaching the conclusion. Such is not

    the case here.

    29. The first part of Clause 10(a) of contract excludes the liability of

    Respondent in respect of (a) consequential damage (b) loss of profit (c)

    costs and/or expenses incurred by the Claimant (d) statutory obligation

    (e) awards, (f) damages (g) statutory or legal action and (g) costs or

    expenses in relations to performance or any other feature of the plant

    supplied and/or erected. The learned Arbitrator has interpreted this

    clause to grant Claim 15(1) and to cap Claim 15(2) to 15(8) to the

    Sairaj 22 of 36

    Uploaded on – – Downloaded on – 06/08/2026 22:44:33
    CARBP-1267-2018 (final).doc

    extent of performance bank guarantee.

    30. The rejection of Claim 15(2) to 15(8) to the fullest extent is

    assailed as being violative of fundamental and substantive law. In Vijay

    Karia and Others vs Prysmian Cavi E Sistemi SRL and Others 32, the

    Hon’ble Apex Court has held that the fundamental policy of Indian law

    must amount to breach of some legal principle or legislation which is

    so basic to Indian law that it is not susceptible of being compromised.

    “Fundamental Policy” refers to the core values of India’s public policy

    as a nation, which may find expression not only in statutes but also

    time-honoured, hallowed principles which are followed by Courts.

    31. It is therefore not permissible for the Court to interfere even

    when there is breach of substantive law and it must be shown that the

    law so breached forms bedrock of Indian law. The present case is a case

    of interpretation of terms of the contract and whether the claims

    stands excluded by an agreement between the parties. Even accepting

    for the moment that the Claimant, under the law, would be entitled to

    such claims in the event of breach by the Respondent, it is open for the

    parties to arrive at an arrangement by which, the liability is excluded

    and limited. This is precisely the interpretation of Clause 10(a) of

    contract by learned Arbitrator. Mr. D’souza would contend that claims

    of the Claimant were not indirect but actual expenses incurred. The

    32 AIR 2020 SC 1807.

    Sairaj 23 of 36

    Uploaded on – – Downloaded on – 06/08/2026 22:44:33
    CARBP-1267-2018 (final).doc

    submission would require this Court to interpret the nature of claims,

    whether consequential or direct, and substitute its own interpretation

    with the interpretation of the Learned Arbitrator, which is

    impermissible. It is within the jurisdiction of the Learned Arbitrator to

    interpret the terms of the contract and the view taken is a possible

    view that Claims 15(2) to 15(8) are covered by Clause 10(a) to the

    extent of performance guarantee. Clause 10(a) specifically mentions

    loss of profit, costs and/or expenses, statutory obligations for purpose

    of exclusion and limits it only to the performance guarantee. Section 5

    of Arbitration Act must be given its full effect to minimise judicial

    intervention when the view cannot be said to be impossible. It is not

    only a plausible view, but a possible view which is required to be

    upheld.

    32. In the case of Vilayati Ram Mittal (P) vs. Reserve Bank of India

    (supra), the Hon’ble Division Bench of this Court has held that it is for

    the Arbitrator to decide the effect of the clause and deal with the

    same. In that case by virtue of the clause, the contractor was not held

    to be entitled for any loss suffered on account of delay and the Hon’ble

    Division Bench has held that this clause binds both the parties and it is

    not open for the Appellant therein to construe clause 18 so as to seek

    the benefit and contend that the clause is binding between the parties

    but do not bind the Arbitrator or the Court. It further held that if the

    Sairaj 24 of 36

    Uploaded on – – Downloaded on – 06/08/2026 22:44:33
    CARBP-1267-2018 (final).doc

    clause specifically prohibits any claim on the account of delay, by

    ignoring the said clause, the Arbitrator cannot travel beyond his

    jurisdiction as that would constitute the jurisdictional error.

    33. In the case of UHL Power Company Limited vs. State of H. P.

    (supra), the Hon’ble Apex Court has held in paragraph 18, 19 and 22 as

    under :

    “18. It has also been held time and again by this Court that
    if there are two plausible interpretations of the terms and
    conditions of the contract, then no fault can be found, if
    the learned arbitrator proceeds to accept one
    interpretation as against the other. In Dyna Technologies
    (P) Ltd. v. Crompton Greaves Ltd. [Dyna Technologies (P) Ltd
    .

    v. Crompton Greaves Ltd., (2019) 20 SCC 1], the limitations
    on the Court while exercising powers under Section 34 of
    the Arbitration Act has been highlighted thus : (SCC p. 12,
    para 24)

    “24. There is no dispute that Section 34 of the
    Arbitration Act limits a challenge to an award
    only on the grounds provided therein or as
    interpreted by various Courts. We need to be
    cognizant of the fact that arbitral awards
    should not be interfered with in a casual and
    cavalier manner, unless the Court comes to a
    conclusion that the perversity of the award
    goes to the root of the matter without there
    being a possibility of alternative interpretation
    which may sustain the arbitral award. Section
    34
    is different in its approach and cannot be
    equated with a normal appellate jurisdiction.
    The mandate under Section 34 is to respect the
    finality of the arbitral award and the party
    autonomy to get their dispute adjudicated by
    an alternative forum as provided under the law.
    If the Courts were to interfere with the arbitral
    award in the usual course on factual aspects,
    then the commercial wisdom behind opting for
    alternate dispute resolution would stand
    frustrated.”

    Sairaj 25 of 36

    Uploaded on – – Downloaded on – 06/08/2026 22:44:33
    CARBP-1267-2018 (final).doc

    19. In Parsa Kente Collieries Ltd. v. Rajasthan Rajya Vidyut
    Utpadan Nigam Ltd. [Parsa Kente Collieries Ltd.
    v.
    Rajasthan Rajya Vidyut Utpadan Nigam Ltd., (2019) 7 SCC
    236 : (2019) 3 SCC (Civ) 552] , adverting to the previous
    decisions of this Court in McDermott International Inc. v.
    Burn Standard Co. Ltd. [McDermott International Inc.
    v.
    Burn Standard Co. Ltd., (2006) 11 SCC 181] and Rashtriya
    Ispat Nigam Ltd. v. Dewan Chand Ram Saran [Rashtriya
    Ispat Nigam Ltd. v. Dewan Chand Ram Saran, (2012) 5 SCC
    306], wherein it has been observed that an Arbitral
    Tribunal must decide in accordance with the terms of the
    contract, but if a term of the contract has been construed
    in a reasonable manner, then the award ought not to be
    set aside on this ground, it has been held thus : (Parsa
    Kente Collieries case [Parsa Kente Collieries Ltd. v.
    Rajasthan Rajya Vidyut Utpadan Nigam Ltd.
    , (2019) 7 SCC
    236 : (2019) 3 SCC (Civ) 552] , SCC pp. 244-45, para 9)

    “9.1. … It is further observed and held that
    construction of the terms of a contract is
    primarily for an arbitrator to decide unless the
    arbitrator construes the contract in such a way
    that it could be said to be something that no
    fair-minded or reasonable person could do. It
    is further observed by this Court in the
    aforesaid decision in para 33 that when a court
    is applying the “public policy” test to an
    arbitration award, it does not act as a court of
    appeal and consequently errors of fact cannot
    be corrected. A possible view by the arbitrator
    on facts has necessarily to pass muster as the
    arbitrator is the ultimate master of the
    quantity and quality of evidence to be relied
    upon when he delivers his arbitral award. It is
    further observed that thus an award based on
    little evidence or on evidence which does not
    measure up in quality to a trained legal mind
    would not be held to be invalid on this score.

    9.2. Similar is the view taken by this Court in
    NHAI v. ITD Cementation India Ltd. [NHAI v. ITD
    Cementation India Ltd., (2015) 14 SCC 21 :

    (2016) 2 SCC (Civ) 716], SCC para 25 and SAIL v.

    Gupta Brother Steel Tubes Ltd. [SAIL v. Gupta
    Brother Steel Tubes Ltd., (2009) 10 SCC 63 :

    Sairaj 26 of 36

    Uploaded on – – Downloaded on – 06/08/2026 22:44:33
    CARBP-1267-2018 (final).doc

    (2009) 4 SCC (Civ) 16] , SCC para 29.”

    (emphasis supplied)

    22. In the instant case, we are of the view that the
    interpretation of the relevant clauses of the
    implementation agreement, as arrived at by the learned
    sole arbitrator, are both, possible and plausible. Merely
    because another view could have been taken, can hardly
    be a ground for the learned Single Judge to have
    interfered with the arbitral award. In the given facts and
    circumstances of the case, the appellate court has rightly
    held that the learned Single Judge exceeded his
    jurisdiction in interfering with the award by questioning
    the interpretation given to the relevant clauses of the
    implementation agreement, as the reasons given are
    backed by logic.”

    34. The scope of interference under Section 34 of the Arbitration Act

    is well-settled. In Associate Builders vs. Delhi Development Authority

    (supra), the Hon’ble Apex Court has held in paragraph 42.3, 44 and 45

    as under :

    “42.3. (c) Equally, the third subhead of patent illegality is
    really a contravention of Section 28(3) of the Arbitration
    Act, which reads as under:

    “28.Rules applicable to substance of dispute.

    –(1)-(2)***
    (3) In all cases, the Arbitral Tribunal shall decide
    in accordance with the terms of the contract
    and shall take into account the usages of the
    trade applicable to the transaction.”

    This last contravention must be understood
    with a caveat. An Arbitral Tribunal must decide
    in accordance with the terms of the contract,
    but if an arbitrator construes a term of the
    contract in a reasonable manner, it will not
    mean that the award can be set aside on this
    ground. Construction of the terms of a contract
    is primarily for an arbitrator to decide unless
    the arbitrator construes the contract in such a
    way that it could be said to be something that
    no fair-minded or reasonable person could do.

    Sairaj 27 of 36

    Uploaded on – – Downloaded on – 06/08/2026 22:44:33
    CARBP-1267-2018 (final).doc

    In MSK Projects (I) (JV) Ltd. v. State of Rajasthan [(2011)
    10 SCC 573 : (2012) 3 SCC (Civ) 818] , the Court held : (SCC
    pp. 581-82, para 17)

    “17. If the arbitrator commits an error in the
    construction of the contract, that is an error
    within his jurisdiction. But if he wanders
    outside the contract and deals with matters
    not allotted to him, he commits a jurisdictional
    error. Extrinsic evidence is admissible in such
    cases because the dispute is not something
    which arises under or in relation to the contract
    or dependent on the construction of the
    contract or to be determined within the award.
    The ambiguity of the award can, in such cases,
    be resolved by admitting extrinsic evidence.
    The rationale of this rule is that the nature of
    the dispute is something which has to be
    determined outside and independent of what
    appears in the award. Such a jurisdictional error
    needs to be proved by evidence extrinsic to the
    award. (See Gobardhan Das v. Lachhmi Ram
    [(1954) 1 SCC 566 : AIR 1954 SC 689], Thawardas
    Pherumal v. Union of India
    [AIR 1955 SC 468],
    Union of India v. Kishorilal Gupta & Bros. [AIR
    1959 SC 1362], Alopi Parshad & Sons Ltd. v.

    Union of India [AIR 1960 SC 588] , Jivarajbhai
    Ujamshi Sheth v. Chintamanrao Balaji
    [AIR 1965
    SC 214] and Renusagar Power Co. Ltd. v. General
    Electric Co.
    [(1984) 4 SCC 679 : AIR 1985 SC
    1156] )”

    (emphasis supplied)

    In Rashtriya Ispat Nigam Ltd. v. Dewan Chand Ram Saran
    [(2012) 5 SCC 306] , the Court held : (SCC pp. 320-21,
    paras 43-45)

    “43. In any case, assuming that Clause 9.3 was
    capable of two interpretations, the view taken
    by the arbitrator was clearly a possible if not a
    plausible one. It is not possible to say that the
    arbitrator had travelled outside his jurisdiction,
    or that the view taken by him was against the
    terms of contract. That being the position, the
    High Court had no reason to interfere with the

    Sairaj 28 of 36

    Uploaded on – – Downloaded on – 06/08/2026 22:44:33
    CARBP-1267-2018 (final).doc

    award and substitute its view in place of the
    interpretation accepted by the arbitrator.

    (emphasis supplied)

    44. The legal position in this behalf has been
    summarised in para 18 of the judgment of this
    Court in SAIL v. Gupta Brother Steel Tubes Ltd.
    [(2009) 10 SCC 63 : (2009) 4 SCC (Civ) 16] and
    which has been referred to above.
    Similar view
    has been taken later in Sumitomo Heavy
    Industries Ltd. v. ONGC Ltd. [(2010) 11 SCC 296 :

    (2010) 4 SCC (Civ) 459] to which one of us
    (Gokhale, J.) was a party. The observations in
    para 43 thereof are instructive in this behalf.

    45. This para 43 reads as follows : (Sumitomo
    case [(2010) 11 SCC 296 : (2010) 4 SCC (Civ) 459]
    , SCC p. 313)

    ’43. … The umpire has considered the fact
    situation and placed a construction on the
    clauses of the agreement which according to
    him was the correct one. One may at the
    highest say that one would have preferred
    another construction of Clause 17.3 but that
    cannot make the award in any way perverse.

    Nor can one substitute one’s own view in such a
    situation, in place of the one taken by the
    umpire, which would amount to sitting in
    appeal. As held by this Court in Kwality Mfg.
    Corpn. v. Central Warehousing Corpn.
    [(2009) 5
    SCC 142 : (2009) 2 SCC (Civ) 406] the Court
    while considering challenge to arbitral award
    does not sit in appeal over the findings and
    decision of the arbitrator, which is what the
    High Court has practically done in this matter.
    The umpire is legitimately entitled to take the
    view which he holds to be the correct one after
    considering the material before him and after
    interpreting the provisions of the agreement. If
    he does so, the decision of the umpire has to be
    accepted as final and binding.”

    
                                                            (emphasis supplied)
    
    
    
    
                      Sairaj                     29 of 36
    
    
    
    
    Uploaded on - -                                     Downloaded on - 06/08/2026 22:44:33
                                                                              CARBP-1267-2018 (final).doc
    
    
    

    35. The settled position in law prohibits Section 34 Court from

    substituting its own view in place of Arbitrator’s interpretation. The

    error in construction is considered as an error within jurisdiction, which

    does not warrant interference. In my view, the interpretation of Clause

    10(a) of the contract by the impugned Award cannot be said to be an

    impossible view.

    36. In so far as the supersession of Clause 10 by warrantee clause is

    concerned, the learned Arbitrator held in paragraph nos. 127 as under :

    127. In so far as the clause of Warantee is concerned, it
    will not apply in the present case as the plant is
    admittedly not commissioned or handed over to the
    Claimant. Respondent has never called upon the Claimant
    to take over the plant and as asserted by the Claimant in
    its mails, the responsibility in supplying the plant
    remained with the Respondent. The contract between
    the parties is not for the supply of individual parts or only
    equipment. In my opinion the clause of Warantee will
    apply only after the commissioning of the plant as agreed
    by the parties, which has not happened. This will also
    include handing over an operational plant to the
    Claimant. I find this because the warrantee is subject to
    certain conditions which show that the plant should be in
    the entire charge and operations of the purchaser i.e. the
    Claimant. This clause also reiterates that the Respondent
    shall not be responsible for any consequential or indirect
    damages only and does not cover direct damages. These
    clause do not, in my reading, absolve the Respondent on
    liability arising on account of direct damages or
    compensation on account of direct consequences.”

    37. The warrantee clause warrantee all equipment offered by

    Respondent against the material, workmanship, manufacturing defects

    for period of 12 month and that Respondent shall not be responsible

    Sairaj 30 of 36

    Uploaded on – – Downloaded on – 06/08/2026 22:44:33
    CARBP-1267-2018 (final).doc

    for any consequential or indirect damages. The contention is that there

    is an express clause for damages in the main agreement and therefore

    Clause 10(a) and (b) stands excluded by virtue of Clause 10(h) of the

    contract as the warantee clause excludes only consequential damages.

    The warantee clause binds the Respondent against defects specified

    i.e. against material, workmanship and manufacturing defects for

    particular period. The clause being a warantee clause, the Learned

    Arbitrator has held that the same would not apply as the plant is not

    commissioned and handed over, which cannot be interfered with.

    38. Insofar as the claim on account of interest is concerned, the

    submissions are conflated in as much the interest sought as Claim 15(7)

    is characterised as interest pendente lite as well as a direct

    consequence of the breach suffered by the Respondent. Mr. D’souza

    would contend that the Claim 15(7) which is Bank interest upto 31 st

    October, 2016 paid on financial loan which has been obtained by the

    Claimant, should have been granted as interest pendente lite. The

    concept of interest pendente lite is different from interest claimed as

    head of loss and as a direct consequence of breach. In the present case,

    Claim 15(7) is claimed as head of loss and not as interest pendente lite

    and the award of interest pendente lite would constitute interest for

    the period from filing of the statement of claim till the Award of

    Arbitrator. In the application under Section 33, the claim was for

    Sairaj 31 of 36

    Uploaded on – – Downloaded on – 06/08/2026 22:44:33
    CARBP-1267-2018 (final).doc

    payment of interest pendente lite, which has been declined by Learned

    Arbitrator in exercise of its jurisdiction which meets the parameters of

    Section 31(7) of the Arbitration Act. The Learned Arbitrator has

    considered the claim of interest as indirect loss and has capped it

    within the limited liability clause.

    39. As far as the award of interest pendente lite is concerned, in the

    case of Morgan Securities and Credits Private Limited vs. Videocon

    Industries Limited (supra), the Hon’ble Apex Court considered the

    expression “unless the Award otherwise directs” in Section 31(7)(b) of

    the Act to hold that wide discretion is conferred upon the Arbitrator to

    determine the rate of reasonable pre-award interest.

    40. Dealing with the citations relied upon by Mr. D’souza, in the case

    of Deepak Fertiliser and Petrochemical Corporation vs. Davy Mckee

    (London) Ltd. (supra), the England and Wales Court of Appeal was

    considering an appeal arising under the Commercial Court in respect of

    the contractual claims raised in that case. While dealing with the issue

    as to whether the losses claimed are excluded from recovery by virtue

    of clause 6.8 of the contract therein which provided that the party shall

    not be liable for loss of anticipated profits, catalyst, raw-material and

    products or for indirect or consequential damages by reason of which

    all heads of claims against the party were held to be excluded. It was

    held that direct and natural result of the destruction of plant was that

    Sairaj 32 of 36

    Uploaded on – – Downloaded on – 06/08/2026 22:44:33
    CARBP-1267-2018 (final).doc

    the party was left without a methanol plant, wasted overheads

    incurred during the reconstruction of the plant, as well as profits lost

    during that period, which are no more remote as losses than the cost of

    reconstruction. It held that the costs incurred cannot be categorized as

    an indirect or consequential loss or damage nor could its cost be

    categorized as constituting a loss of profit.

    41. The distinguishing feature, in the present case, is the limited

    powers vested in Section 34 Court, once the Arbitrator has interpreted

    the terms of the contract which view cannot be said to be an

    impossible view. In that case the proceedings arose out of Commercial

    Court litigation which leaves the field wide open for the Appellate

    Court to re-appreciate the findings.

    42. In the case of Union of India vs. Saraswat Trading Agency and

    Others (supra), the Hon’ble Apex Court considered the question of

    interest for pre-reference period and dealt with the power of

    arbitrator to award interest pendente lite and if so on what principles. It

    held that the Arbitrator has the power to award interest pendente lite.

    There is no quarrel with the said decision however, in the present case,

    as discussed above, the claim for interest is claimed as a head of loss

    and not as interest pendente lite. Further, Arbitrator in his discretion

    declined to grant interest pendente lite.

    43. In the case of South East Asia Marine Engineering and

    Sairaj 33 of 36

    Uploaded on – – Downloaded on – 06/08/2026 22:44:33
    CARBP-1267-2018 (final).doc

    Constructions Limited vs. Oil India Limited (supra), the Hon’ble Apex

    Court considered the scope of Section 34 of the Arbitration Act.

    Pertinently, the Court noted the case of Dyna Technologies (P) Ltd. vs.

    Crompton Greaves Limited33 and held that where two views are

    possible, the Court cannot interfere in the plausible view taken by the

    Arbitrator supported by reasoning. In the facts of that case, the

    Hon’ble Apex Court did not subscribe the reasons provided by

    Arbitrator or High Court as it failed to apply the standard of

    consideration of all clauses of contract while interpreting clause 23 of

    the contract therein. In that case, clause in question was in respect of

    change in law which results in additional costs/reduction in cost to

    contractor and which was required to be reimbursed. The Arbitral

    Tribunal had held that clause must be liberally construed and any

    circular of government circular would result in change in law. The High

    Court reasoned that clause 23 is akin to force majeure clause. In such

    facts, the Hon’ble Apex Court considered that the wide interpretation

    by Arbitral Tribunal cannot be accepted and that document forming

    the written contract shall be read as whole which was the basic rule

    ignored by the Arbitral Tribunal while interpreting the contract. The

    decision turned on the terms of the contract contained therein, which

    is rendered in a different factual scenario. The decision cannot be cited

    33 (2019) 20 SCC 1.

    Sairaj 34 of 36

    Uploaded on – – Downloaded on – 06/08/2026 22:44:33
    CARBP-1267-2018 (final).doc

    as a proposition that even if the view taken is possible view, it is open

    for Section 34 Court to substitute its own view.

    44. In the case of Delhi Metro Rail Corporation Limited vs. Delhi

    Airport Metro Express Pvt. Ltd. (supra), the Hon’ble Apex Court

    considered the scope of interference with the Arbitral Award, with

    which there is no quarrel.

    45. The grounds on which the Award can be set aside are set out in

    Section 34 of the Arbitration Act. The learned Arbitrator has

    interpreted the terms of the contract to hold that claims 15(2) to 15(8)

    of the claims raised by the Claimant are covered by clause 10(a) and are

    capped at the limited liability of performance guarantee. The view

    being possible view cannot be said to be patently illegal or so perverse

    that no reasonable person could have arrived at the same. Perversity as

    is settled is a finding based on no evidence and arrived at by ignoring

    the vital evidence, which would be liable to be set aside under the head

    of patent illegality. The error, if any, in construction of contract, is an

    error within jurisdiction incapable of being corrected in Section 34

    jurisdiction.

    46. In light of the discussion above, I do not find the impugned order

    to suffer from perversity or patent illegality or such as violates the

    fundamental policy of Indian law.

    47. Resultantly, the Arbitration Petition fails and stands dismissed.

    Sairaj 35 of 36

    Uploaded on – – Downloaded on – 06/08/2026 22:44:33
    CARBP-1267-2018 (final).doc

    48. Nothing survives for consideration in pending Applications, if

    any, and the same stand disposed of.

    
    
    
                                                                                                     [Sharmila U. Deshmukh, J.]
    
    
    
    
                                                         Sairaj                           36 of 36
    
    
    
    
    Powered by TCPDF (www.tcpdf.org)
                                       Uploaded on - -                                          Downloaded on - 06/08/2026 22:44:33
     



    Source link

    LEAVE A REPLY

    Please enter your comment!
    Please enter your name here