Sri M L Shankarlingappa vs M/S Kundur Constructions Pvt Ltd on 4 August, 2026

    0
    3
    ADVERTISEMENT

    Karnataka High Court

    Sri M L Shankarlingappa vs M/S Kundur Constructions Pvt Ltd on 4 August, 2026

                                                -1-
                                                        COMAP No. 120 of 2024
    
    
    
                        IN THE HIGH COURT OF KARNATAKA AT BENGALURU
    
                            DATED THIS THE 4TH DAY OF AUGUST, 2026
    
                                             PRESENT
                           THE HON'BLE MRS. JUSTICE ANU SIVARAMAN
                                               AND
                           THE HON'BLE MR. JUSTICE VENKATESH NAIK T
                               COMMERCIAL APPEAL NO.120 OF 2024
                   BETWEEN:
    
                        SRI M.L. SHANKARLINGAPPA
                        AGED ABOUT 68 YEARS
                        RESIDING AT NO.12
                        BASAVESHWARA LAYOUT
                        JAKKUR ROAD, SHIVANAHALLI
                        YELAHANKA
                        BENGALURU-560 064.
                                                                    ...APPELLANT
                        (BY SRI M.L. SHANKARLINGAPPA, PARTY-IN-PERSON)
    
                   AND:
    
                   1.   M/S. KUNDUR CONSTRUCTIONS PVT. LTD.
                        HAVING ITS REGISTERED OFFICE AT
                        FLAT NO G-03, KUNDUR PARK
                        JAKKUR-AMRUTHALLI MAIN ROAD
                        JAKKUR, BENGALURU-560 064
    Digitally           REPRESENTED BY ITS
    signed by           PROJECT MANAGER
    RAKSHA              MR. JAGADISH
    Location:           S/O. MR. SELVARAJU.
    High Court
    of Karnataka   2.   SHRI VISHVANATH V. ANGADI
                        DISTRICT JUDGE (RETD.)
                        SOLE ARBITRATOR
                        ARBITRATOR AND CONCILIATION CENTRE
                        (DOMESTIC AND INTERNATIONAL)
                        KHANIJA BHAVAN
                        RACE COURSE ROAD
                        BENGALURU-560 001.
                                                                  ...RESPONDENTS
                        (BY SRI SANTHOSH KUMAR M.B. FOR
                            SRI CHAMARAJ M., ADVOCATES FOR R-1)
                                    -2-
                                              COMAP No. 120 of 2024
    
    
    
         THIS    COMMERCIAL     APPEAL   IS   FILED   UNDER   SECTION
    13(1)(1A) OF COMMERCIAL COURT ACT 2015 READ WITH SECTION
    37 OF ARBITRATION AND CONCILIATION ACT, 1996, PRAYING TO
    SET ASIDE THE JUDGMENT DATED 20-1-2024 PASSED BY THE 86TH
    ADDITIONAL CITY CIVIL AND SESSIONS JUDGE, BENGALURU (CCH-
    87) IN COM.A.P.NO.117 OF 2022 BY ALLOWING THE ABOVE APPEAL
    WITH COSTS AND ETC.
    
         THIS    COMMERCIAL     APPEAL   HAVING     BEEN   HEARD    AND
    RESERVED ON 08-07-2026, COMING ON FOR PRONOUNCEMENT,
    THIS DAY, THE VENKATESH NAIK T. J., PRONOUNCED THE
    FOLLOWING:
    
    CORAM:      HON'BLE MRS. JUSTICE ANU SIVARAMAN
                and
                HON'BLE MR. JUSTICE VENKATESH NAIK T
    
    
                            CAV JUDGMENT
    

    (PER: HON’BLE MR. JUSTICE VENKATESH NAIK T)

    This appeal arises from the Judgment and Order dated

    SPONSORED

    20.01.2024 passed by the LXXXVI Additional City Civil and

    Sessions Judge (CCH-87), Bengaluru, (‘Commercial Court’) in

    Com.A.P. No.117/2022, whereby the Commercial Court

    dismissed the petition filed by the appellant under Section 34 of

    the Arbitration and Conciliation Act, 1996 (for short, “the

    Arbitration Act“), seeking to set aside the Arbitral Award dated

    08.08.2022 passed by the Arbitral Tribunal in A.C.No.260/2021

    and to allow the counterclaim filed by the appellant before the

    Arbitral Tribunal in A.C. No.260/2021.

    -3-

    COMAP No. 120 of 2024

    2. For the sake of convenience, the parties are

    referred to as per their ranking before the Tribunal. The

    appellant herein was the respondent, and respondent No.1

    herein was the claimant before the Tribunal.

    3. The brief facts of the case of the appellant – party-

    in-person, are that he is the owner of the immovable property

    bearing Survey No.5BC-306 situated at Hennur Road,

    Banasawadi Layout, 3rd Block, Kacharakanahalli, Bengaluru. He

    entrusted the construction work of a commercial and residential

    apartment on the said property to the first respondent/claimant

    under the contract agreement dated 03.10.2016. Pursuant to a

    dispute that arose between the parties with regard to the

    settlement of the final bill payable by the appellant to the first

    respondent/claimant, respondent No.1/claimant approached

    this Court in CMP No.247/2020. This Court, by its order dated

    27.08.2021, constituted the Arbitral Tribunal and appointed

    respondent No.2 to adjudicate the disputes between the

    parties. Consequently, the first respondent/claimant filed a

    claim statement before the Arbitral Tribunal in

    A.C.No.260/2021, claiming a sum of Rs.29,47,570/- with

    interest at the rate of 24% per annum from 20.06.2018 till

    realization, along with costs, contending that the parties had

    entered into the said contract agreement dated 03.10.2016.
    -4-
    COMAP No. 120 of 2024

    4. It is stated that the cost of construction of the

    building was fixed at Rs.2,40,00,000/- after negotiations

    between the parties. As per Clause 2 of the contract, the

    appellant was required to make payment of the bills within 15

    days from the date of acceptance of the RA bills, after

    necessary deductions. After completion of the construction of

    the building, respondent No.1 handed over possession of the

    building to the appellant and raised the final bill for a sum of

    Rs.2,40,47,570.94/- as per the bill dated 20.06.2018. The

    appellant occupied the building and also let out the same to

    various tenants. The appellant had made payment of

    Rs.1,95,00,000/- and was still due to pay a sum of

    Rs.45,47,570/- to respondent No.1 as on 30.03.2019.

    Thereafter, respondent No.1 called upon the appellant to pay

    the balance amount. Accordingly, the appellant paid a further

    sum of Rs.16,00,000/-, but was still due to pay a sum of

    Rs.29,47,570/-. Hence, respondent No.1 sought the said

    amount along with interest from the appellant.

    5. Upon receipt of notice from the Arbitral Tribunal,

    the appellant appeared and resisted the claim of respondent

    No.1/claimant and contended that the work entrusted to

    respondent No.1/claimant was not completed within the

    stipulated time and that the quality of the work carried out by
    -5-
    COMAP No. 120 of 2024

    respondent No.1/claimant was not in accordance with the

    specifications. Consequently, the appellant filed a counterclaim

    seeking a sum of Rs.74,17,603/- from respondent

    No.1/claimant, together with interest at the rate of 24% per

    annum from 03.10.2017 till its realization.

    6. On the basis of the claim statement filed by

    respondent No.1/claimant and the counterclaim filed by the

    appellant, the Arbitral Tribunal framed in all 18 issues and

    recorded the evidence. After hearing both the parties, the

    Arbitral Tribunal allowed the claim of the claimant and rejected

    the counterclaim of the appellant. Being aggrieved by the

    same, the appellant – party-in-person, filed

    Com.A.P.No.117/2022. In turn, the learned LXXXVI Additional

    City Civil and Sessions Judge, Bengaluru, dismissed the

    arbitration petition filed by the appellant under Section 34 of

    the Arbitration and Conciliation Act, 1996, and confirmed the

    award dated 08.08.2022 passed in A.C. No.260/2021. Being

    aggrieved by the same, the appellant – party-in-person, has

    preferred this appeal.

    7. We have heard Sri M.L. Shankarlingappa, appellant

    – party-in-person, and Sri Santhosh Kumar M.B., learned
    -6-
    COMAP No. 120 of 2024

    counsel appearing for Sri Chamaraj M., learned counsel for

    respondent No.1.

    8. The appellant – party-in-person, contended that the

    award passed by the Arbitral Tribunal is in conflict with the

    fundamental policy of Indian law and morality, the findings of

    the Arbitral Tribunal suffer from patent illegality. It is further

    contended that the Commercial Court, in its judgment,

    observed that Ex.P9, namely the final bill, discloses the balance

    amount payable. Ex.P9 consists of the description of the work

    carried out by respondent No.1, the measurements, rate per

    CFT/SFT, the total quantity of work, the rate per quantity, and

    the amount. The Commercial Court failed to appreciate the

    oral evidence and exhibited document, which relied upon by the

    appellant in support of his arguments.

    9. It is further contended that respondent

    No.1/claimant quoted exorbitant rates for the respective works

    when compared to the prevailing market rates, and the

    appellant raised objections with regard to the price quoted by

    the respondent. It is further contended that, as per Clauses 26

    and 27 of the contract, respondent No.1/claimant himself

    undertook to execute the wooden and aluminium work for the

    windows of the building/project, but failed to execute the same
    -7-
    COMAP No. 120 of 2024

    and also failed to complete the entire project within the

    stipulated time. It is further contended that respondent

    No.1/claimant did not construct the building in accordance with

    the structural plan and that the roof beams were not laid as per

    the structural plan. Consequently, it is contended that the

    stability and structural strength of the building constructed by

    respondent No.1/claimant are not up to the required standard

    as per the approved building plan.

    10. The appellant, in his counterclaim, contended that,

    as per the valuation certificate, the value of the entire building

    constructed by respondent No.1/claimant was Rs.1,69,30,000/-

    , whereas respondent No.1/claimant had raised a claim for

    Rs.2,40,47,570/-, which was exorbitant. It was further

    contended that respondent No.1/claimant had not furnished

    any break-up of the amounts while raising the final bill. It was

    also contended that the wooden work and aluminium work for

    the windows, amounting to Rs.19,17,000/- and Rs.4,26,000/-

    respectively, were not entrusted to respondent No.1/claimant.

    However, respondent No.1/claimant had not furnished any

    details with regard to the said amount of Rs.23,43,000/-.

    11. The appellant further contended that he had

    requested respondent No.1/claimant to rectify the incomplete
    -8-
    COMAP No. 120 of 2024

    and defective work in the building. However, till date,

    respondent No.1/claimant has not offered any explanation for

    the non-performance of the work entrusted to him. However,

    respondent No.1/claimant made a false claim before the

    Arbitral Tribunal. The Arbitral Tribunal, without properly

    appreciating the oral and documentary evidence on record,

    allowed the claim of respondent No.1/claimant and rejected the

    counterclaim of the appellant – party-in-person. The

    Commercial Court also failed to consider the requirements of

    Section 34(2) of the Arbitration and Conciliation Act, 1996, and

    proceeded to confirm the arbitral award, which is not in

    accordance with law. Therefore, the impugned judgment and

    the arbitral award require interference by this Court.

    12. Per contra, learned counsel for respondent No.1

    vehemently supported and justified the judgment and order

    passed by the Commercial Court as well as the arbitral award

    passed by the Arbitral Tribunal. It was contended that the

    Arbitral Tribunal, after framing the necessary issues,

    considering the pleadings of the parties, appreciating the oral

    and documentary evidence placed on record, and interpreting

    the terms and conditions of the contract agreement, had rightly

    allowed the claim of respondent No.1/claimant and rejected the

    counterclaim of the appellant. It is further contended that the
    -9-
    COMAP No. 120 of 2024

    Commercial Court, while exercising jurisdiction under Section

    34 of the Arbitration and Conciliation Act, 1996, has rightly held

    that none of the grounds contemplated under Section 34(2) of

    the Act were made out for setting aside the arbitral award. It is

    also contended that the appellant is seeking a re-appreciation

    of the evidence, which is impermissible in proceedings under

    Section 34 of the Act and in the present appeal. Therefore, no

    case is made out for interference with the well-reasoned

    judgment of the Commercial Court or the arbitral award.

    Accordingly, prayed to dismiss the appeal.

    13. In view of the rival submissions made by the

    learned counsel for the parties, the following point arises for

    consideration:

    1. Whether the order upholding the award

    warrants interference by this Court?

    14. We have perused the material available on record.

    The case of the appellant – party-in-person, is that he and

    respondent No.1 entered into a contract agreement for the

    construction of a commercial-cum-residential building for a

    total consideration of Rs.2,40,00,000/-. After completion of the

    construction, i.e., on 20.06.2018, respondent No.1 raised the

    final bill for a sum of Rs.2,40,47,560.97/-. It is the case of the

    – 10 –

    COMAP No. 120 of 2024

    appellant that, as on 30.03.2019, he had paid a sum of

    Rs.1,95,00,000/-. Thereafter, respondent No.1 demanded the

    balance amount of Rs.45,47,570/-, pursuant to which the

    appellant paid a further sum of Rs.16,00,000/-. Even

    thereafter, a sum of Rs.29,47,570/- remained due.

    15. The notice issued through e-mail dated 02.03.2020

    discloses that the appellant herein replied to the reminder

    notice through e-mail. Thereafter, respondent No.1 approached

    this Court in CMP No.270/2020 seeking appointment of an

    Arbitrator. Accordingly, an Arbitrator was appointed, and

    respondent No.1 filed a claim petition before the Arbitral

    Tribunal in Arbitration Case No.260/2021. The Arbitral Tribunal,

    in turn, allowed the claim of respondent No.1 and rejected the

    counterclaim filed by the appellant. Being aggrieved by the

    award passed by the Arbitral Tribunal, the appellant preferred

    an arbitration petition before the Commercial Court. The

    Commercial Court dismissed the arbitration petition. Hence, the

    appellant has preferred the present appeal before this Court.

    16. It is not in dispute that the appellant and

    respondent No.1 entered into a contract agreement for

    construction work and that the appellant entrusted the

    construction work to respondent No.1 under the contract

    – 11 –

    COMAP No. 120 of 2024

    agreement dated 03.10.2016. It is also not in dispute that the

    appellant initially paid a sum of Rs.1,90,00,000/- and

    subsequently a further sum of Rs.16,00,000/- to respondent

    No.1. It is the case of the appellant that the Arbitral Tribunal

    failed to consider the terms and conditions of the contract

    agreement marked as Ex.P1. It is further contended that

    Clause 3.6 of the agreement was also not taken into

    consideration by the Arbitral Tribunal as well as the Commercial

    Court.

    17. While considering a petition under Section 34 of the

    Arbitration and Conciliation Act, 1996, the Commercial Court

    can interfere with an award passed by the Arbitral Tribunal only

    if the award is in conflict with the fundamental policy of Indian

    law or with justice or morality, or if the findings of the Arbitral

    Tribunal suffer from patent illegality. A perusal of the arbitral

    award clearly demonstrates that the findings recorded by the

    Arbitral Tribunal are neither arbitrary, capricious, nor perverse.

    Further, the appellant has failed to make out any of the

    grounds contemplated under Section 34(2) of the Arbitration

    and Conciliation Act, 1996.

    – 12 –

    COMAP No. 120 of 2024

    18. Hence, it is just and necessary to analyse Section

    34 of the Arbitration and Conciliation Act, 1996, which reads as

    under:

    “34. Application for setting aside arbitral
    award.– (1) Recourse to a Court against an arbitral
    award may be made only by an application for
    setting aside such award in accordance with sub-
    section (2) and sub-section (3).

    (2) An arbitral award may be set aside by the Court
    only if–

    (a) the party making the application [establishes
    on the basis of the record of the arbitral tribunal
    that]–

    (i) a party was under some incapacity, or

    (ii) the arbitration agreement is not valid
    under the law to which the parties have
    subjected it or, failing any indication thereon,
    under the law for the time being in force; or

    (iii) the party making the application was not
    given proper notice of the appointment of an
    arbitrator or of the arbitral proceedings or was
    otherwise unable to present his case; or

    (iv) the arbitral award deals with a dispute
    not contemplated by or not falling within the
    terms of the submission to arbitration, or it
    contains decisions on matters beyond the scope
    of the submission to arbitration:

    Provided that, if the decisions on matters
    submitted to arbitration can be separated from
    those not so submitted, only that part of the
    arbitral award which contains decisions on
    matters not submitted to arbitration may be set
    aside; or

    (v) the composition of the arbitral tribunal or
    the arbitral procedure was not in accordance
    with the agreement of the parties, unless such
    agreement was in conflict with a provision of

    – 13 –

    COMAP No. 120 of 2024

    this Part from which the parties cannot
    derogate, or, failing such agreement, was not in
    accordance with this Part; or

    (b) the Court finds that–

    (i) the subject-matter of the dispute is not
    capable of settlement by arbitration under the law
    for the time being in force, or

    (ii) the arbitral award is in conflict with the public
    policy of India.

    [(2A) An arbitral award arising out of arbitrations
    other than international commercial arbitrations,
    may also be set aside by the Court, if the Court finds
    that the award is vitiated by patent illegality
    appearing on the face of the award:

    Provided that an award shall not be set aside
    merely on the ground of an erroneous application of
    the law or by reappreciation of evidence.]

    (3) An application for setting aside may not be
    made after three months have elapsed from the date
    on which the party making that application had
    received the arbitral award or, if a request had been
    made under section 33, from the date on which that
    request had been disposed of by the arbitral
    tribunal:

    Provided that if the Court is satisfied that the
    applicant was prevented by sufficient cause from
    making the application within the said period of three
    months it may entertain the application within a
    further period of thirty days, but not thereafter.

    (4) On receipt of an application under sub-section
    (1), the Court may, where it is appropriate and it is
    so requested by a party, adjourn the proceedings for
    a period of time determined by it in order to give the
    arbitral tribunal an opportunity to resume the arbitral
    proceedings or to take such other action as in the
    opinion of arbitral tribunal will eliminate the grounds
    for setting aside the arbitral award.

    [(5) An application under this section shall be
    filed by a party only after issuing a prior notice to the
    other party and such application shall be

    – 14 –

    COMAP No. 120 of 2024

    accompanied by an affidavit by the applicant
    endorsing compliance with the said requirement.]

    [(6) An application under this section shall be
    disposed of expeditiously, and in any event, within a
    period of one year from the date on which the notice
    referred to in sub-section (5) is served upon the
    other party.]”

    19. The appellant has filed this Commercial Appeal

    under Section 13(1)(1A) of the Commercial Court Act, 2015,

    which reads as under:

    “13. Appeals from decrees of Commercial
    Courts and Commercial Divisions.–

    [(1) Any person aggrieved by the judgment or
    order of a Commercial Court below the level of a
    District Judge may appeal to the Commercial
    Appellate Court within a period of sixty days from
    the date of judgment or order.

    (1A) Any person aggrieved by the judgment or
    order of a Commercial Court at the level of District
    Judge exercising original civil jurisdiction or, as the
    case may be, Commercial Division of a High Court
    may appeal to the Commercial Appellate Division of
    that High Court within a period of sixty days from
    the date of the judgment or order:

    Provided that an appeal shall lie from such
    orders passed by a Commercial Division or a
    Commercial Court that are specifically enumerated
    under Order XLIII of the Code of Civil Procedure,
    1908 (5 of 1908) as amended by this Act and section
    37
    of the Arbitration and Conciliation Act, 1996 (26
    of 1996).]

    20. The appellant also relied upon Section 37 of the

    Arbitration and Conciliation Act, which reads as under:

    “37. Appealable orders.– (1)[Notwithstanding
    anything contained in any other law for the time

    – 15 –

    COMAP No. 120 of 2024

    being in force, an appeal] shall lie from the following
    orders (and from no others) to the Court authorised
    by law to hear appeals from original decrees of the
    Court passing the order, namely:–

    [(a) refusing to refer the parties to arbitration
    under section 8;

    (b)granting or refusing to grant any measure
    under section 9;

    (c)setting aside or refusing to set aside an
    arbitral award under section 34.]

    (2)An appeal shall also lie to a Court from an
    order of the arbitral tribunal.–

    (a)accepting the plea referred to in sub-

    section (2) or sub-section (3) of section 16; or

    (b)granting or refusing to grant an interim
    measure under section 17.

    (3) No second appeal shall lie from an order
    passed in appeal under this section, but nothing in
    this section shall affect or take away any right to
    appeal to the Supreme Court.”

    21. Insofar as the claim for damages is concerned,

    respondent No.1 claimed a sum of Rs.29,47,570/- together

    with interest at the rate of 24% per annum towards the

    outstanding invoice payable by the appellant in terms of the

    agreement. The Arbitral Tribunal awarded the said claim in

    favour of respondent No.1, together with interest.

    22. The principles governing compensation for breach

    of contract have been succinctly laid down by the Hon’ble

    Supreme Court in Kailash Nath Associates v. Delhi

    – 16 –

    COMAP No. 120 of 2024

    Development Authority and Another, reported in (2015) 4

    SCC 136, wherein the Hon’ble Apex Court held as under:

    43. On a conspectus of the above authorities,
    the law on compensation for breach of contract
    under Section 74 can be stated to be as follows:

    43.1. Where a sum is named in a contract as a
    liquidated amount payable by way of damages, the
    party complaining of a breach can receive as
    reasonable compensation such liquidated amount
    only if it is a genuine pre-estimate of damages fixed
    by both parties and found to be such by the court. In
    other cases, where a sum is named in a contract as a
    liquidated amount payable by way of damages, only
    reasonable compensation can be awarded not
    exceeding the amount so stated. Similarly, in cases
    where the amount fixed is in the nature of penalty,
    only reasonable compensation can be awarded not
    exceeding the penalty so stated. In both cases, the
    liquidated amount or penalty is the upper limit
    beyond which the court cannot grant reasonable
    compensation.

    43.2. Reasonable compensation will be fixed
    on well-known principles that are applicable to the
    law of contract, which are to be found inter alia in
    Section 73 of the Contract Act.

    43.3. Since Section 74 awards reasonable
    compensation for damage or loss caused by a breach
    of contract, damage or loss caused is a sine qua non
    for the applicability of the section.

    43.4. The section applies whether a person is
    a plaintiff or a defendant in a suit.

    43.5. The sum spoken of may already be paid
    or be payable in future.

    43.6. The expression “whether or not actual
    damage or loss is proved to have been caused
    thereby” means that where it is possible to prove
    actual damage or loss, such proof is not dispensed
    with. It is only in cases where damage or loss is
    difficult or impossible to prove that the liquidated

    – 17 –

    COMAP No. 120 of 2024

    amount named in the contract, if a genuine pre-
    estimate of damage or loss, can be awarded.

    43.7. Section 74 will apply to cases of
    forfeiture of earnest money under a contract. Where,
    however, forfeiture takes place under the terms and
    conditions of a public auction before agreement is
    reached, Section 74 would have no application.

    [Emphasis supplied]

    23. A perusal of the aforesaid observations makes it

    clear that the said principles were subsequently referred to with

    approval by the Hon’ble Supreme Court in Sudha Gupta v.

    Delhi Land and Finance Limited, reported in (2019) 14

    SCC 266.

    24. Thus, in the present case, it was possible to prove

    the actual damages or loss. Such proof is not dispensed with

    and, therefore, respondent No.1/claimant is required to adduce

    evidence in support of his claim. It is well settled that where

    the loss, in terms of money, can be ascertained, the party

    claiming compensation has to prove the loss sustained by him.

    25. As per the contention raised by the appellant, who

    appeared as party-in-person, insofar as the building is not yet

    completed and the respondent has claimed the entire amount

    under the agreement, the appellant has not placed any material

    to show that his building is still under construction and has not

    been completed. The burden was cast on the appellant to prove

    – 18 –

    COMAP No. 120 of 2024

    this contention, but he has not proved it. It is settled law that a

    contention or assertion made in a pleading that is not

    supported by evidence is of no consequence and cannot be

    used by a Court to establish a fact. Hence, the Tribunal

    answered this issue in the negative.

    26. Insofar as the contention of the appellant in respect

    of the wooden and aluminium work for the windows of the

    building is concerned, the respondent himself admitted that he

    did not commence or complete the work and that the same was

    got done by the appellant himself. The evidence clearly

    demonstrates that the respondent has not included any

    expenditure incurred in respect of the wooden and aluminium

    work. The expenses incurred by the appellant towards the

    wooden and aluminium work for the windows of the building

    have been deducted from the total claim. Thus, there is no

    merit in the contention of the appellant in this regard.

    27. Insofar as the contention of the appellant with

    regard to the valuation of the entire building is concerned, he

    has contended that, as per the valuation report at Ex.R3, the

    cost of the entire building is Rs.1,69,30,000/-, whereas

    respondent No.1/claimant has claimed an amount of Rs.2.4

    crores as if he had completed the entire building. Insofar as

    – 19 –

    COMAP No. 120 of 2024

    this contention is concerned, the appellant has not examined

    the valuer who inspected the building and filed report as

    requested by the appellant. However, a copy of the valuation

    report of M/s. S.M. Engineers and Valuers dated 29.01.2022

    was marked as Ex.R3 before the Arbitral Tribunal, and the

    author of Ex.R3 was not examined to substantiate the

    contention of the appellant. The contents of Ex.R3 clearly

    demonstrate that, while conducting the valuation of the

    building, the claimant and the appellant’s architect were not

    present. Though RW2 speaks about the contents of Ex.R3, but

    who is not competent to speak with regard to contents of

    Ex.R3. If a building valuer is not examined as a witness, the

    valuation report generally loses its legal efficacy and primary

    evidentiary value, leaving the fact unproved unless supported

    by other direct evidence. A written valuation report is an expert

    opinion under Section 45 of the Indian Evidence Act, but the

    document itself is typically hearsay or inadmissible unless the

    expert steps into the witness box to prove it. Without the

    expert’s examination and the opportunity for cross-

    examination, the report carries no evidentiary weight.

    Therefore, the appellant has failed to prove that the valuation

    of the entire building was Rs.1,69,30,000/-. On the other

    hand, the respondent/claimant has produced oral and

    – 20 –

    COMAP No. 120 of 2024

    documentary evidence to show that the valuation of the

    appellant’s building exceeds Rs.2.4 crores. Hence, the appellant

    has failed to prove his contention before the Arbitral Tribunal as

    well as before the Commercial Court.

    28. The aforesaid findings of the Arbitral Tribunal in

    awarding compensation and the findings of the Commercial

    Court in affirming the same are based on the ground that the

    appellant failed to establish that the arbitral award suffers from

    patent illegality or that it is contrary to the public policy of

    India. Therefore, when the appellant is found liable for breach

    of the contract, respondent No.1 is entitled to damages.

    29. Insofar as interest is concerned, the Arbitral Tribunal

    has awarded interest at the rate of 18% per annum in favour of

    respondent No.1-claimant. The quantum of interest to be

    awarded, if it is to be awarded, will depend on the facts and

    circumstances of the case. In the present case, respondent

    No.1 constructed the building way back in the year 2018, and

    the appellant has taken possession of the building soon after its

    completion. However, the appellant has not paid the remaining

    amount of Rs.29,47,570/- along with interest till date.

    30. In the present case, the interest awarded by the

    Commercial Court at 18% per annum is excessive. Section

    – 21 –

    COMAP No. 120 of 2024

    31(7)(a) of the Arbitration and conciliation Act, 1996, states

    that, unless otherwise agreed by the parties, the Arbitral

    Tribunal may include in the sum awarded, interest at such rate

    as it deems reasonable on the whole or part of the money, for

    the whole or part of the period commencing from the date on

    which the cause of action arose until the date on which the

    award is made. In respect of post-award interest, Section

    31(7)(b) states that, unless the award otherwise provides, the

    sum directed to be paid by the award shall carry interest at a

    rate of 2% higher than the current rate of interest prevailing on

    the date of the award, from the date of the award till the date

    of payment.

    31. The Hon’ble Apex Court in case of Gayatri

    Balasamy v. ISG Novasoft Technologies Ltd., reported in

    (2025) 7 SCC 1 has elaborately dealt with the issue of interest

    in commercial transactions and awarded current interest, and

    held that the sum awarded shall carry interest at a rate of 2%

    higher than the current rate of interest prevailing on the date of

    the award, from the date of the award till the date of payment.

    32. In the facts and circumstances of the case, interest

    at the rate of 11% per annum would be fair and reasonable.

    Accordingly, the impugned order stands modified to the extent

    – 22 –

    COMAP No. 120 of 2024

    that the rate of interest is reduced from 18% per annum to

    11% per annum.

    33. In the result, the impugned judgment and order

    dated 20.01.2024 in Com.A.P.No.117/2022 passed by the

    Commercial Court, as well as the arbitral award dated

    08.08.2022 passed in A.C.No.260/2021 by the Arbitral

    Tribunal, insofar as it relate to the grant of damages on account

    of the outstanding invoice, are hereby confirmed. Insofar as it

    relate to the interest is concerned, it is reduced from 18% per

    annum to 11% per annum. Accordingly, the Commercial

    Appeal is allowed in part.

    All pending Interlocutory Applications, if any, shall stand

    disposed of.

    Sd/-

    (ANU SIVARAMAN)
    JUDGE

    Sd/
    (VENKATESH NAIK T)
    JUDGE

    AM



    Source link

    LEAVE A REPLY

    Please enter your comment!
    Please enter your name here