The Chief Engineer vs Gvr Infra Projects Limited on 3 August, 2026

    0
    31
    ADVERTISEMENT

    Karnataka High Court

    The Chief Engineer vs Gvr Infra Projects Limited on 3 August, 2026

                                                      -1-
                                                               COMAP No. 127 of 2025
    
    
    
                                 IN THE HIGH COURT OF KARNATAKA AT BENGALURU
    
                                    DATED THIS THE 03RD DAY OF AUGUST, 2026
    
                                                   PRESENT
                                  THE HON'BLE MR. VIBHU BAKHRU, CHIEF JUSTICE
                                                     AND
                                     THE HON'BLE MR. JUSTICE C.M. POONACHA
                                      COMMERCIAL APPEAL NO. 127 OF 2025
                            BETWEEN:
    
                            1.   THE CHIEF ENGINEER
                                 NATIONAL HIGHWAYS ZONE
                                 PUBLIC WORKS DEPARTMENT
                                 GOVERNMENT OF KARNATAKA
                                 P.W.D. ANNEX BUILDING
                                 2ND FLOOR, K.R. CIRCLE
                                 BENGALURU - 560 001
                                                                       ...APPELLANT
                            (BY SRI GIRIDHAR S.V., ADVOCATE)
    
                            AND:
    
                            1.   GVR INFRA PROJECTS LIMITED
               Digitally
               signed by
               YASHAVANT
                                 A COMPANY DULY REGISTERED UNDER
    YASHAVANT  NARAYANKAR
    NARAYANKAR Date:
               2026.08.04
                                 THE PROVISIONS OF
               11:03:18
               +0530
                                 THE INDIAN COMPANIES ACT, 1956
                                 HAVING ITS REGISTERED OFFICE
                                 AT VBC SOLITAIRE
                                 9TH AND 10TH FLOOR
                                 NO.47 AND 49, BAZULLAH ROAD
                                 T. NAGARA, CHENNAI - 600 017
                                 TAMIL NADU AND ITS BRANCH AT
                                 #40, SNEHA NAGAR, 2ND CROSS
                                 GROUND FLOOR
                                 NEAR RELIANCE FRESH
                                   -2-
                                               COMAP No. 127 of 2025
    
    
    
          AMRUTHAHALLI
          BYTARAYANAPURA
          NEW BANGALORE INTERNATIONAL
          AIRPORT ROAD
          BANGALORE - 560 092
    
          REPRESENTED BY ITS
          RESOLUTION PROFESSIONAL
          MS. VANDANA GARG
          [IBBI/IPA-001/IP-PWC
          P00025/2016-2017/10058]
          OFFICE, 252, VEER SAVARKAR MARG
          SHIVAJI PARK, DADAR
          MUMBAI CITY
          MAHARASHTRA - 400 028
                                                     ...RESPONDENT
    (BY SRI YASHODHAR HEGDE, ADVOCATE)
    
           THIS COMMERCIAL APPEAL IS FILED UNDER SECTION
    13 (1-A) OF COMMERCIAL COURTS ACT 2015, READ WITH
    SECTION 37 OF THE ARBITRATION AND CONCILIATION ACT,
    1996 PRAYING TO SET ASIDE THE JUDGMENT PASSED BY
    THE    HON'BLE    LXXXVII   ADDITIONAL         CITY   CIVIL   AND
    SESSIONS     JUDGE,   AT      BANGALORE        (CCH.88)    DATED
    05.09.2024   IN   COMMERCIAL          ARBITRATION       PETITION
    NO.4/2020 AND CONSEQUENTLY ALLOW THIS APPEAL AS
    PRAYED FOR & ETC.
    
           THIS COMMERCIAL APPEAL HAVING BEEN HEARD AND
    RESERVED      FOR     JUDGMENT,            COMING     ON      FOR
    PRONOUNCEMENT          THIS         DAY,      JUDGMENT        WAS
    PRONOUNCED AS UNDER:
                                      -3-
                                               COMAP No. 127 of 2025
    
    
    
    CORAM: HON'BLE MR. VIBHU BAKHRU, CHIEF JUSTICE
           and
           HON'BLE MR. JUSTICE C.M. POONACHA
    
    
                            C.A.V. JUDGMENT
    
    
            (PER: HON'BLE MR. JUSTICE C.M. POONACHA)
    
    
              The present appeal is filed by the National Highways
    
    Authority of India [NHAI] under Section 13(1A) of the Commercial
    
    Courts Act, 2015 [CC Act] read with Section 37 of the Arbitration
    
    and Conciliation Act, 1996 [A & C Act] impugning the judgment
    
    dated 05.09.2024 [impugned judgment] in Commercial Arbitration
    
    Petition No.4/2020 passed by the LXXXVII Additional City Civil and
    
    Sessions Judge at Bangalore [Commercial Court] whereunder the
    
    application filed by the NHAI under Section 34 of the A & C Act
    
    seeking to set aside the Arbitral Award dated 11.10.2019
    
    [impugned award] passed by the Arbitral Tribunal was rejected.
    
    
           2. The respondent-M/s GVR Infra Projects Ltd., [GVR]
    
    instituted arbitral proceedings for resolution of the disputes arising
    
    out of the contract work of Job No.NH-48-KNT-2014-15-734 for the
    
    work of strengthening from KM 216.00 (Gulagabale) to KM 237.00
    
    (Maranahalli) and providing Rigid Pavement from KM 250.620
    
    (Kemphole) to KM 263.00 (Addahole) (Shiradi Ghat) of NH-48
                                         -4-
                                                 COMAP No. 127 of 2025
    
    
    
    Bangalore-Mangalore       Section     in   the   State   of   Karnataka
    
    [contracted works].
    
    
           3. GVR was the successful tenderer in respect of the
    
    contracted   works    awarded     by NHAI for a          total sum   of
    
    ₹90,27,83,520/- (Rupees Ninety Crore Twenty-seven Lakh Eighty-
    
    Three Thousand Five Hundred and twenty only). GVR and NHAI
    
    entered into an agreement on 06.11.2015 [agreement] and the site
    
    was handed over by NHAI to GVR on 23.12.2015, which was the
    
    appointed date.
    
    
           4. In terms of the contract, GVR proceeded with the
    
    construction. However, the work could not be completed for various
    
    reasons. NHAI terminated the agreement on 04.01.2017. Being
    
    aggrieved, GVR initially filed W.P.No.1819/2017 before this Court
    
    which was dismissed on 12.12.2017, wherein GVR was permitted
    
    to raise all the pleas in arbitration proceedings.
    
    
           5. Each of the parties nominated their respective arbitrators.
    
    The said arbitrators nominated the presiding arbitrator. Accordingly,
    
    the Arbitral Tribunal was constituted. The claimant-GVR made a
    
    total of 20 claims. NHAI also made a counterclaim.            Oral and
    
    documentary evidence were adduced before the Arbitral Tribunal.
                                      -5-
                                               COMAP No. 127 of 2025
    
    
    
    The Tribunal, vide the impugned award, partly allowed the claims
    
    made by GVR and rejected the counterclaim made by the NHAI.
    
    
             6. Being aggrieved, NHAI preferred an application under
    
    Section 34 of the A & C Act (COMAP No.4/2020) before the
    
    Commercial Court, the same was dismissed by the impugned
    
    judgment. Being aggrieved, the present appeal is filed.
    
    
    BACKGROUND FACTS:

    7. The scope of work as contemplated under the agreement

    together with the financial component of each item of work is as

    SPONSORED

    under:

    Flexible                                              Rs.22.33
                  216.00Km to 237.00Km         21.00Km
    pavement                                              crores
    Rigid         250.62Km to 263.00Km         12.38Km    Rs.53.17
    pavement                                              crores
    Structures in Reconstruction of            14 CD's
    Rigid         Widening of                  36 CD's
    Pavement(50                                           Rs.2.53
    CDs)                                                  crores
    
    Provision for                                         Rs.12.24
    road                                                  crores
    safety works
                                                    Total Rs.90.27
                                                          crores
    
    
             8.     Both the counsels in the    course of submissions,
    
    

    placed on record a representative sketch which is as under:
    -6-
    COMAP No. 127 of 2025

    9. Schedule-J as per Clause 10.3.2 of the agreement

    contains the project completion schedule which is as under:

    “Schedule-J
    (See Clause 10.3.2)

    PROJECT COMPLETION SCHEDULE

    1. Project Completion Schedule

    During Construction period, the Contractor shall
    comply with the requirements set forth in this
    Schedule I for each of the Project Milestones and
    the Scheduled Completion Date. Within 15 (fifteen)
    days of the date of each Project Milestone, the
    Contractor shall notify the Authority of such
    compliance along with necessary particulars thereof.

    2. Project Milestone-I

    2.1 Project Milestone-I shall occur on the date falling
    on the 180th (one hundred and fiftieth) day from the
    Appointed Date (the “Project Milestone-I”).

    -7-
    COMAP No. 127 of 2025

    2.2 Prior to the occurrence of Project Milestone-I,
    the Contractor shall have commenced construction
    of the Project Highway and submitted to the
    Authority duly and validly prepared Stage Payment
    Statements for an amount not less than 10% (ten
    percent) of the Contract Price.

    3. Project Milestone-II.

    3.1 Project Milestone-II shall occur on the date
    falling on the 365th (three hundred and thirtieth) day
    from the Appointment Date (the “Project Milestone-
    II”).

    Prior to the occurrence of Project Milestone-II, the
    Contractor shall have commenced construction of
    the Project Highway and submitted to the Authority
    duly and validly prepared Stage Payment
    Statements completion schedule in reference to
    Schedule-H Items, Stages and Sub-stages payment
    statements for an amount not less than 30% (thirty
    percent) of the Contract Price.

    4. Project Milestone-III

    4.1 Project Milestone-III shall occur on the date
    falling on the 550th (four hundred eightieth) day from
    the Appointed Date (the “Project Milestone-III”).

    4.2 Prior to the occurrence of Project Milestone-III,
    the Contractor shall have continued with
    construction of the Project Highway and submitted to
    the Authority duly and validly prepared Stage
    Payment Statements for an amount not less than
    60% (sixty percent) of the Contract Price.

    5 Schedule Completion Date

    5.1 The Schedule Completion Date shall occur on
    the 650th (seven hundred and thirtieth) day from the
    Appointed Date.

    -8-
    COMAP No. 127 of 2025

    5.2 On or before the Scheduled Completion Date,
    the Contractor shall have completed construction in
    accordance with this Agreement.

    6. Extension of time

    Upon extension of any or all of the aforesaid
    Project Milestones or the Scheduled Completion
    Date, as the case may be, under and in accordance
    with the provisions of this Agreement, the Project
    Completion Schedule shall be deemed to have been
    amended accordingly.”

    10. The work schedule that was to be carried out by GVR,

    as noticed in the Arbitral Award, is as under:

    a) Flexible pavement and widening of 36 numbers of CDs was

    to be done during the period April-2016 to June-2016;

    b) Reconstruction of 14 numbers of CDs coming under the

    rigid pavement and construction of the rigid pavement was to

    be done during the period October-2016 to March-2017;

    11. A request was made by GVR for closing the traffic in

    the rigid pavement section. However, the same was not done. GVR

    had also contended that certain portions of the flexible pavement

    section overlapped with the other tenders issued by NHAI.

    12. Various correspondences were exchanged between

    GVR and NHAI with regard to the progress of the work. NHAI

    issued a memorandum on 24.09.2016 (Ex.C51), debarring GVR.
    -9-
    COMAP No. 127 of 2025

    Vide letters dated 24.10.2016 (Ex.C52), GVR sought for

    reconsideration of the decision of NHAI to debar it. GVR also

    requested to invoke Article 26.2 of the agreement to appoint a

    conciliator. NHAI vide letter dated 18.11.2016 (Ex.C53), revoked

    the debarrement notice with certain conditions.

    13. NHAI issued a notice dated 02.12.2016 (Ex.C29) for

    termination for not procuring 50% of the materials and machinery

    required for carrying out rigid pavement works before closure of the

    traffic at Shiradi Ghat. GVR vide reply dated 12.12.2016 (Ex.C30)

    requested for withdrawal of the termination notice. However, the

    contract was terminated on 04.01.2017 (Ex.C35). NHAI terminated

    the contract on the ground that GVR did not achieve the first

    milestone. The gist of the milestones as per the agreement

    between the parties is as under:

    1st milestone 180 days at 10% Not less than 10% of
    (one hundred and fiftieth day) the contract price

    2nd milestone 360 days at 30% Not less than 30% of
    (three hundred and thirtieth the contract price
    day)

    3rd milestone 550 days at 60% Not less than 60% of
    (four hundred eightieth day) the contract price

    4th milestone 730 days at 100% Completion of the
    th
    (650 days) project
    (seven hundred and thirtieth
    day)

    – 10 –

    COMAP No. 127 of 2025

    14. GVR, inter alia, contended that the road that was to be

    made available for carrying out the rigid pavement works by closing

    the traffic was not done. It was further contended that there was no

    clarity with regard to the work to be done over the flexible

    pavement section with regard to the overlapping extent; as also

    that there was a change in the scope of work. Hence, it is

    contended that the termination was illegal.

    15. Both the parties submitted their draft issues

    consequent to which, ten issues were framed by the Tribunal,

    which are as under:

    “ISSUES

    The 10 Issues framed by the Claimant are as
    under

    i. Whether the duration of the performance under the
    contract is 18 months or 24 months?

    ii. Whether the site of the project highway is
    procured in accordance with the Contract
    Agreement?

    iii. Whether Claimant proves that the ‘Authority
    Engineer’ appointed was required to be an external
    engineer mandatorily and whether the Respondent
    can appoint its own engineer as ‘Authority Engineer?

    iv. Whether the road length from KM 216.00 to
    237.00 of NH-48 requiring strengthening overlapped
    with the work proposed to be taken up by the NHAI
    and whether the Claimant was prevented by the

    – 11 –

    COMAP No. 127 of 2025

    Respondent in completing the flexible pavement
    work from KM 216.00 to 237.00 of NH-48?

    v. Was it possible to allow passage of traffic along
    the existing carriageway between KM 250.620 to KM
    263.00 of NH-48 (Shiradi Ghat) under improvement,
    simultaneously carrying the work of Rigid
    Pavement?

    vi. Whether the termination of the Contract by the
    Respondent is valid and legal?

    vii.Whether the Claimant achieved the 1st Financial
    Milestome in terms of the Contract Agreement?

    viii. Whether the Claimant is entitled to the Claims at
    Serial Nos. 1 to 20 amounting to. Rs. 115.61 Crores
    claimed in the Statement of Claims?

    ix. Whether the Respondent is entitled to the
    Counter-Claim amount from Serial Nos. 1 to 4
    amounting to Rs. 79.65 Crores.

    x. What relief?”

    16. The Arbitral Tribunal, consequent to the oral and

    documentary evidence adduced between the parties, partly allowed

    the claims made by GVR and rejected the counterclaim made by

    NHAI. The abstract of the award amount as is forthcoming from the

    arbitral award is as under:

    ABSTRACT OF AMOUNT AWARD
    SL. Category of Claim Amount Claimed as Awarded amount Remarks
    NO. per SOC (in Rs.)
    (in Rs.)

    1. Claim No.1: Claim for Return, release and 6,82,90,215/- 6,89,90,215/-

    discharge of performance Security Bank Guarantee
    furnished to the Respondent BG 6,77,08,765/-+ BG
    Commission Rs.5,81,450/-

    – 12 –

    COMAP No. 127 of 2025

    2. Claim No.2: Claim for loss of profit @15% on the 12,55,50,124/- 12,14,18,158/-

    balance value of work, which could not be executed
    due to illegal & wrongful termination of the contract:

    3. Claim No.3: Claim for Loss of Business 10,00,00,000/- – Rejected
    Reputation/Loss of future business due to potential
    negative reputation following the termination

    4. Claim No.4: Claim toward delay damages (as per 1,74,98,345/- – Rejected
    Clause 8.3 of contract)

    5. Claim No.5: Claim for Payment due towards Stage 6,57,82,695/- 9,33,29,134/-

    Payment -1, in respect of work done

    6. Claim No.6: Claim for change of Scope items 5,36,14,342/- 2,19,10,515/-

    amounting to Rs.5,36,14,342/-

    7. Claim No.7: Claim for Expenses incurred in carrying 5,77,11,692/- 2,92,87,972/-

    out Road Maintenance Work amounting to
    Rs.5,77,11,692/-

    8. Claim No.8: Claim for additional area of Flexible 47,67,443/- – Rejected
    Pavement works carried out than the average Km.
    area of the total project length Rs.47,67,443/-.

    9. Claim No.9: Claim for loss on Deployment of Plant 2,89,92,000/- 1,99,38,000/-

    and Equipment owned by the Claimant amounting
    to Rs.2,89,92,000/-

    10. Claim No.10: Plant & Equipment deployed in the 7,15,68,484/- 1,64,62,828/-

    Project which are owned by the Official Sub
    Contractor of the Claimant amounting to
    Rs.7,15,68,484/-

    11. Claim No.11: Plant and Equipment Hired by Official 12,78,83,618/- – Rejected
    Contractor of Claimant amounting to
    Rs.12,78,83,618/-

    12. Claim No.12: Expenses incurred in Mobilization & 89,58,596/- 13,43,118/-

          Demobilization    of    plant and      Machinery
          Rs.89,58,596/-
    
    13.   Claim No.13: Recovery of Machinery utilized for            70,01,431/-           -          Rejected
    

    execution of works Rs.70,01,431/- (Negative Claim)

    14. Claim No.14: Claim for Loss of unused Material 5,86,41,696/- 2,93,20,848/-

    Rs.5,86,41,696/-

    15. Claim No.15(a): Claim for Administrative Expenses: 5,15,32,589/- 1,71,77,530/-

    Site Overheads and Establishment Expenses
    Incurred by the Claimant Rs.5,15,32,589/-

    Claim No15(b): Offsite Overheads / Apportionment 2,70,83,506/- – Rejected
    Charges of Claimant @ 3% of Contract Value
    amounting to Rs.2,70,83,506/-

    Claim No.15(c): Off-Site Overheads / 77,93,953/- 77,93,953/-
    Apportionment Charges of official Subcontractor of
    the Claimant Rs. 77,93,953/-

    – 13 –

    COMAP No. 127 of 2025

    16. Claim No. 16: Loss of Bonus for early Completion: 2,70,83,506/- – Rejected
    3% of Project Cost i.e., Rs.2,70,83,506/-

    7. Claim No. 17: Design Charges 3% of Project Cost 2,70,83,506/- – Rejected
    Rs.2,70,83,506/-

    18. Claim No.18: Loss of Maintenance Benefit @ 3% of 2,70,83,506/- – Rejected
    Contract Price i.e., Rs.2,70,83,506/-

    19. Claim No.19: Interest on the duo amounts at the 20,23,71,654/- – Rejected
    rate of 18% p.a amounting to Rs.20,23,71,654/-

    Total 1,15,22,90,038/- 46,62,72,271/-

    20. Claim No.20: Cost incurred on Legal proceedings at 38,14,882/- 38,14,882/-

          High   Court   and      Civil  Court,   Bangalore
          Rs.38,14,882/-
    
    21.   a. The expenditure incurred by the Claimant for 21               3,99,754           1,99,877/-
    

    hearings by AT (both the parties should share the
    amount equally) (Ex: C-93)

    b. The expenditure incurred-by the Claimant for 88,620/- 88,620/-
    arranging the internal meetings of the Arbitrator’s on
    11th ,12th, 14th ,17th ,18th ,23rd ,24th and 25th
    September and 6th, 9th and 10th October (including
    food & other charges)

    1,15,65,93,294/- 43,03,75,650/-

    22. Counter claim 74,51,81,277/- Rejected 45,13,920/-

    Negated by the Tribunal except for refunding of
    excess BG (110%) collected

    Grand total 1.15.65.93.294/- 43,48,89,570/-

    Note:

    a. Interest to be paid for the award amount of
    Rs.42,62,72,271/- from the date: 12.03.2018 (date of
    submission of SOC till the date of Award
    dt:11.10.2019) @15% as per article 31 (7) (a) of
    Arbitration and Conciliation Act 1996.

    b. Interest to be paid for the Award amount of Rs.
    42,62,72,271/- at the rate of 15% up to 90 days,

    c. If not paid the interest to be paid is at 18% from
    the date of award till the date of payment.”

    – 14 –

    COMAP No. 127 of 2025

    17. With regard to Issue No.1 that is whether the time for

    performance was 18 months or 24 months, the Arbitral Tribunal

    noticing Clause 1.4.2 of the agreement, concluded that the time

    was 24 months.

    18. With regard to Issue No.2, the Arbitral Tribunal

    concluded that the site of the project was not procured in

    accordance with the contract. This is with regard to the specific

    contention of GVR that the road for carrying out rigid pavement

    works was required to be closed for traffic.

    19. With regard to issue No.3, the Tribunal concluded that

    NHAI could not have appointed its own engineer as the Authority

    Engineer. It was held that, under the agreement, the appointment

    of Authority Engineer was mandatorily required to be that of an

    External Engineer. The Authority Engineer appointed in the present

    case was the Executive Engineer, NHAI – Mangalore Division. The

    same was in violation of the terms of the Agreement.

    20. Issue No.4 was as to whether GVR was prevented by

    NHAI in completing the flexible pavement work between 216.00

    kms to 237.00 kms. The Tribunal concluded that there was an

    overlap in the work that was to be carried out between 216.00 kms

    – 15 –

    COMAP No. 127 of 2025

    to 219.534 kms and 225.600 kms to 237.000 kms. The NHAI

    delayed in deciding with regard to the overlap of the work and the

    Arbitral Tribunal concluded that GVR was prevented from

    completing the flexible pavement work from 216.00 kms to 237.00

    kms.

    21. With regard to Issue No.5, the Tribunal concluded that

    the rigid pavement work cannot be taken up without closing the

    road between 250.620 kms to 263.00 km of NH 48 (Shiradi Ghat).

    22. While considering Issue No.6, the Tribunal concluded

    that the termination of the contract by NHAI was not valid. With

    regard to Issue No.7, as to whether GVR achieved the first financial

    milestone in terms of the contract, the Tribunal concluded that GVR

    was prevented by NHAI from achieving the first milestone in terms

    of the contract.

    23. Issue No.8 pertains to the damages claimed with

    respect to the claims 1 to 20 made by the claimant. Accordingly,

    the damages were assessed and the claims were awarded in terms

    of the abstract of the amounts awarded as noticed at paragraph

    No.16 (supra).

    – 16 –

    COMAP No. 127 of 2025

    24. Issue No.9 was with regard to the counterclaim made

    by NHAI. The Tribunal concluded that NHAI was not entitled to the

    counterclaim. The counterclaim made by NHAI, inter alia claimed

    the amounts that it had incurred with respect to the fresh tender

    that was called, with respect to unfinished works consequent to the

    termination of the present tender as well as other charges.

    CONTENTIONS:

    25. The primary contention of the learned counsel for the

    appellant/NHAI is that the finding of the Arbitral Tribunal that the

    termination of the agreement with GVR was not justified and is

    patently illegal; NHAI also impugns the finding of the Tribunal that

    the road was required to be closed while rigid pavement work was

    to be carried out. It was also contended that the finding of the

    Tribunal with regard to completion of the first milestone by GVR

    was also patently illegal. The quantification of the damages is also

    pointed out as being patently illegal inasmuch as it is the contention

    of NHAI that the Emden’s Formula is applicable only for

    engineering contracts and was not required to be adopted for the

    agreement in question.

    – 17 –

    COMAP No. 127 of 2025

    26. Per contra, learned counsel for GVR justifies the award

    of the Tribunal and contends that the same is not to be interfered

    with by this Court in exercise of its jurisdiction contained under

    Section 37 of the A & C Act.

    DISCUSSION AND REASONING:

    27. The material on record clearly indicates that the

    contract between the parties consisted primarily of two parts, i.e.,

    the flexible pavement works, which were to be carried out between

    216 kms to 237 kms, i.e., for a total extent of 21 kms. The other

    part of the work was rigid pavement works, which were between

    250.62 kms to 263 kms, i.e., for an extent of 12.38 kms. In the

    entire extent of both the flexible as well as rigid pavement works,

    GVR was also required to carry out reconstruction and widening of

    culverts [referred to as CDs at certain places]; and also, carry out

    other road safety works. As already noticed above, the break-up of

    the financial outlay with regard to the contracted works is as under:

       a) Flexible pavement -                          ₹22.33 crores
       b) Rigid pavement -                             ₹53.17 crores
    

    c) Reconstruction and widening of 50 culverts – ₹2.53 crores

    d) Provision for road safety works – ₹12.34 crores

    Total ₹90.27 crores

    – 18 –

    COMAP No. 127 of 2025

    28. With regard to the flexible pavement works, it is the

    contention of GVR that in respect of certain stretches of the road,

    there was overlapping inasmuch as NHAI had already proposed

    four- laning of the road before the agreement with GVR. The said

    overlapping was between 216 kms to 219.434 kms as well as

    between 225 kms to 237 kms. Hence, it was the contention of GVR

    that the contracted works for the said portions, which overlapped

    with the earlier proposed works, could not be carried out, and there

    was no clarity given by NHAI to the queries raised by GVR in that

    regard. It was contended that the overlapping stretch virtually

    reduced the scope of the project.

    29. With regard to the rigid pavement works, GVR had

    requested NHAI to temporarily close the road and divert the vehicle

    traffic to enable GVR to carry out the rigid pavement works. The

    rigid pavement works were to be carried out between 250.60 km to

    263.00 km.

    30. The NHAI had terminated the agreement, since GVR

    had not even achieved the first financial milestone. In this regard, it

    – 19 –

    COMAP No. 127 of 2025

    is to be noticed that as a first milestone, GVR was required to

    complete 10% of the contract price within 180 days.

    REGARDING THE VALIDITY OF TERMINATION BY NHAI:

    31. As noticed above, the agreement was entered on

    06.11.2015 and the appointed date was 23.12.2015. In terms of the

    completion schedule (Annexure-J to the agreement), the first

    milestone was that GVR was required to complete construction of

    10% of the contract price within 180 days from the appointed date.

    Accordingly, the first milestone was to be completed on or before

    22.06.2016.

    32. As already noticed above, the project contemplated

    carrying out of flexible pavement works of a total extent of 21 kms

    (that is from 216.00 kms to 237.00 kms) as well as rigid pavement

    works of 12.38 kms (that is from 250.62 kms to 263.00 kms). The

    works included NHAI to construct 50 culverts. Out of the 50

    culverts, the works contemplated reconstruction of 14 culverts and

    widening of 36 culverts. The culverts were required to be

    constructed both in the flexible pavement stage as well as the rigid

    pavement stage.

    – 20 –

    COMAP No. 127 of 2025

    33. While it is the contention of GVR that there was

    overlapping in the portion of the road where flexible pavement

    works was to be carried out and that NHAI did not, in any manner,

    clarify the said aspect of the matter, it is clear and forthcoming that

    between the stretch-219.534 kms (Sakleshpur bypass off take) to

    225.600 kms (Sakleshpur bypass exit), which is a length of 6.066

    kms in which stretch the flexible pavement works were required to

    be undertaken, there was no overlapping of work. Hence, the

    extent of 6.066 kms where flexible pavement work was required to

    be undertaken is that stretch of the road where there was no

    dispute between the parties as to the mode and manner of carrying

    out the work.

    34. The contention of GVR is that since certain portions of

    the flexible pavement works were overlapping with an earlier work

    and there was no clarity from NHAI, there was delay in the

    completion of the works and the milestones stipulated in the

    agreement could not be adhered to; and hence, the termination of

    the contract by NHAI was illegal. In order to consider the said

    contention, vis-à-vis the findings of the Arbitral Tribunal regarding

    the same, it is necessary to notice certain correspondences

    exchanged between the parties.

    – 21 –

    COMAP No. 127 of 2025

    35. In the meeting held on 14.03.2016 (part of Ex.R8), it

    was, inter alia, agreed between the parties as under:

    “The contractor has assured to executed the work
    as follows:

    1. 10 pipe culverts and 3 Km flexible pavement by the
    end of March 2016.

    2. 12 pipe culverts and 7 Km flexible pavement by the
    end of April 2016.

    3, 14 pipe culverts and 11 Km flexible pavement by
    the end of May 2016.

    Instructions were issued to the confractor to
    execute 22 CD’s and 10 Kms flexible pavement
    within a period of one month.

    Since the working period for the above work is
    only from October to April end, instructions were
    given to the Superintending Engineer to monitor the
    progress of work for a period of 1 month, if contractor
    fails to achieve the above said progress in this period
    and instructed to submit the specific proposal with
    recommendations whether to take up the work with
    the same agency or to rescind the contract.”

    (emphasis supplied)

    36. Vide letter dated 04.04.2016 (part of Ex.R10), GVR

    has, inter alia, furnished the details of the materials procured as

    well as the status of the culvert works. The relevant portion of the

    status regarding the culvert works is as under:

    “3. The modified programme will be submitted on
    07.04.2016. As per modified programme the flexible
    pavement of 7 Kms and 6 No’s Culverts already
    completed and 16 No’s of Pipe/slab culverts will be

    – 22 –

    COMAP No. 127 of 2025

    completed in all respects by the end of April 2016.
    The balance stretch will be completed after monsoon.

    4. The Rigid Pavement work cannot be tackled until
    closure of Road due to restricted width in ghat
    section as the Slip form paver blocks the flow of
    traffic and also in the interest of safety of the Road
    users as traffic is prohibited during the laying of rigid
    payment as per the norms.

    5. xxxxx

    6. Further it is reported that we have taken up
    construction and widening of 26 nos. of Pipe / Slab
    culverts wherever it is found that the safety road is
    not affected due to widening/reconstruction work. The
    remaining structures cannot be tackled until closure
    of Road in the safety interest of the Road users. In
    this regard we wish to submit that as there is no
    change in formation levels the widening of these
    culverts have been taken up based on the existing
    top of culvert levels and the work is not stopped as
    reported in your letter and they are in progress and
    will be completed well before the onset of monsoon.
    The present status of structures are as below”

    Sl. Type of Units As per Completed Work Balance
    No. Structures Agreement in Status
    Progress

    Widening
    st
    1 Slab Culverts No’s 12 0 10 2 Walls 1 lift
    in progress

    2 Pipe Culverts No’s 24 6 10 8 Head wall 1st
    nd
    & 2 lift in
    progress

    Reconstruction

    3 Slab Culverts No’s 14 0 0 14 Will start
    after Closure
    of road.

    (emphasis supplied)

    – 23 –

    COMAP No. 127 of 2025

    37. In response to the said letter dated 04.04.2016 NHAI

    vide its letter dated 05.04.2016 (part of Ex.R.9) intimated GVR

    regarding the start of flexible pavement works as under:

    “The proposal submitted vide your letter cited
    above has been examined and as such to start the
    work of flexible pavement work from Km 216.00 to
    Km 237.00 may be taken up subject to the following
    conditions:-

    1. Quality Assurance, Monitoring and Supervision
    should be as per Article 11 of the agreement.

    2. Original agreement between M/s BSCPL
    infrastructure Limited and M/s GVR Infra Projects
    Ltd is not yet furnished till date.

    3. The Batch Mix plant may be got inspected by
    the Regional Officer (Mechanical) for the condition
    and fitness of the plant.

    4. Quality tests for the materials collected may be
    got done both from your end and National
    Highway Quality Control Authorities.

    5. The Design Mix may be got approved from the
    competent Authority.

    6. As traffic flow in this stretch is around 17,000
    PCU, all safety measures may be taken and
    ensure that there is free flow of traffic during
    execution of the work.

    7. Suitable Traffic signals may be provided in this
    stretch during execution of the work.”

    (emphasis supplied)

    38. In the meeting dated 27.04.2016 (part of Ex.R8), it was

    noticed that in the previous meeting dated 14.03.2016 GVR had

    – 24 –

    COMAP No. 127 of 2025

    assured that the culvert works would be completed (as noticed in

    para 35 above). However, it was noticed by NHAI that no progress

    has been achieved as per the said assurance. It was also noticed

    that GVR had opened 25 culverts and not carried out the work

    which was hazardous to the safety of the road users. Hence, GVR

    was instructed to close the culverts and make the same safe for

    road users. It was also noticed that since the rigid pavement work

    was very important, if GVR proceeded with the same speed for the

    execution of the work, the closing of the Shiradi Ghat highway for a

    period of three to four months would be very difficult.

    39. A meeting was held on 02.05.2016 (part of Ex.R8)

    between the representatives of the NHAI and GVR. It is relevant to

    notice the minutes of the said meeting, which are as under:

    “The above work was entrusted to M/S GVR Infra
    projects Ltd Chennai, on 06/11/2015. The site was handed
    over on 23-12-2015 and the same has been declared as
    appointed date by the Authority Engineer.

    The Chief Engineer noted with displeasure regarding nil
    progress of the above Project up to the end of April-2016,
    even though it was assured by the agency to complete 22
    nos of culverts and 10 Kms of flexible pavement during the
    meeting held on 14-03-2016.

    It is also reiterated by the Chief Engineer that the
    monsoon rains will start from second week of May, and
    observing the present methodology adopted by the agency

    – 25 –

    COMAP No. 127 of 2025

    it would be vague to say that all the 22 culverts and 10 Km
    of flexible pavement would be completed in next 10 days
    and it clearly Indicates that it is not possible to complete
    culverts and flexible pavement works before the onset of
    monsoon. Hence it is very difficult to achieve the first mile
    stone progress of 10% as on 23-06-2016 i.e, 180 days from
    the appointed date at this juncture.

    However once again the agency assured that the above
    shortfall of progress will be made good by completing all the
    25 nos of culverts which are already tackled by providing
    necessary traffic safety measures alongwith 10 Kms of
    flexible pavement before 12-05-2016. It is also discussed
    and opined in the meeting that since there is lack of time for
    bleeding for bituminous work and the pavement shall only
    be made after monsoon.

    The Assistant Executive Engineer, National Highway
    Sub Division Sakaleshpura stated that, the approval to the
    OGLs, Design and Drawings may be obtained from the
    competent authority prior to commencement of any work.

    The Chief Engineer instructed the agency to get the
    approval to the OGLs, Design and Drawings from the
    competent authority before commencement of any work.

    Conclusion of the meeting:

    It is instructed the field staff to closely monitor the day to
    day progress of the work up to 12-05-2016 and final
    decision of termination of contract will be taken on 12-05-
    2016 after reviewing the progress of the work and a clear
    decision would be taken with respect to termination of the
    contract as discussed in the meeting held on 27th April-2016
    and directed the Managing Director, M/S GVR Infra projects
    Ltd Chennai asked to be present on that day.

    The meeting was concluded with thanks to all the
    officers present.”

    (emphasis supplied)

    – 26 –

    COMAP No. 127 of 2025

    40. It is pertinent to notice here that GVR vide its letter

    dated 06.04.2016 intimated NHAI that it would be starting the

    flexible pavement works between 216.00 km to 237.00 km. The

    same was reiterated by GVR vide its letter dated 20.05.2016 (both

    the letters are part of Ex.R.10). In response to the same, the NHAI

    vide its letter dated 23.05.2016 (Ex.C.20) replied to GVR, wherein it

    is stated as under:

    “Please refer to your letter Dtd: 20.05.2016 cited
    above wherein it is stated that the work of flexible
    pavement work from Km 216.00 to 237.00 would be
    stated as the material and machinery for laying crack
    seal, DBM & BC is mobilized and also the batch mix
    plant on lease basis from BSCPL is available at
    Km.160 of NH 48.

    Prior to this letter, in your letter Dtd: 04.04.2016
    (ref 2), it was also stated the work of flexible
    pavement would be started and this office vide letter
    Dtd: 05.04.2016(ref 3) accorded permission subject
    to certain conditions. Even then, no action has been
    taken.

    It is at this juncture, especially during the third
    week of May 2016 wherein the pre-monsoon
    showers have already begun, it is stated in your
    letter Dtd: 20.05.2016 that the work would be started.

    In this regard, in the proceeding of the meeting
    held on 02.05.2015 (ref 1) under the chairmanship of
    the Chief Engineer along with the officers concerned
    and the representatives Shri Gangaprasad,
    Managing Director, Shri Gopalkrishna and Shri
    Venkateshwaralu were also present, the chief
    Engineer reiterated that the monsoon rains would

    – 27 –

    COMAP No. 127 of 2025

    start from second week of May, 2016 and observing
    the present methodology adopted by the agency, it
    would be vague to say that all the 22 culverts and 10
    Kms of flexible pavement would be completed in next
    10 days and it clearly indicated that it is not possible
    to complete culverts and flexible, pavement works
    before the onset of monsoon and it is very difficult to
    achieve the first mile stone progress of 10% as on
    23.06.2016 i.e., 180 days from the appointed date at
    this juncture.

    In the meeting your representatives assured that
    the above shortfall of progress will be made good by
    completing all the 25 nos of culverts which are
    already tackled by providing necessary traffic safety
    measures alongwith 10 kms of flexible pavement
    before 12.5.2016 and it was also discussed and
    opined in the meeting that since there is lack of time
    for bleeding for bituminous work and the pavement
    shall only be made after monsoon.

    Also as many as 25 culverts as against 22 have
    been tackled and it is required that these culverts
    should be immediately tackled and completed before
    the onset of monsoon. It is also should be that at one
    culvert before the inspection of the Secretary, PWD
    which was intended on 10.05.2016 concrete was laid
    and the following day no curing was done. Also
    during the inspection of the undersigned, it was
    observed that the machinery were laying idle.

    As regards flexible pavement it is reiterated that
    as already discussed in the meeting held on
    02.05.2016, and it was also discussed and opined in
    the meeting that since there is lack of time for
    bleeding for bituminous work and the payment shall
    only be made after monsoon. Further, it is opined
    that since there is already intermittent monsoon rains
    and after completion of bituminous work there will not
    be time for bleeding also. If there is no time for

    – 28 –

    COMAP No. 127 of 2025

    bleeding there is every chance of damages to the
    bituminous layer during monsoon.

    The subject was discussed with the Chief
    Engineer, National Highways and with the
    Superintending Engineer, National Highways who
    reiterated to adhere to the minutes of the
    proceedings held on 02.05.2016.

    Further, The Superintending Engineer, National
    Highway circle has opined to start the work of flexible
    pavment from reach 219.534(Kollahalli, starting point
    of Sakaleshpura bypass) to Km 225.600 (Anemahal,
    ending point of Sakleshpura bypass) at present
    stage.

    “Hence it is once again instructed to adhere to the
    minutes of the meeting held on 02.05.2016”.

    This is for information and further necessary
    action.”

    (emphasis supplied)

    41. It is clear and forthcoming from the aforesaid

    communications that NHAI had been following up with GVR

    regarding construction of culverts from 14.03.2016 (as noticed in

    Para 35 above) and even as on 23.05.2016 the construction of

    culverts had not been completed by the agency. It is also

    forthcoming from the said communications that the flexible

    pavement works were required to be carried out consequent to the

    completion of the culvert works. However, the said works had not

    commenced till 23.05.2016, which has led NHAI to apprehend

    – 29 –

    COMAP No. 127 of 2025

    regarding the quality of the asphalting work if the monsoon

    commences. Hence, it is clear that it was not for the first time, that

    NHAI had, vide the said letter dated 23.05.2016 (Ex.C20), called

    upon GVR to commence the flexible pavement works.

    42. NHAI vide its communication dated 24.06.2016

    (Ex.C17) had in detail noticed the various works and the progress

    of various work was adduced. It was noticed that “since about six

    months there is no considerable progress and only meagre

    progress is achieved”; that with regard to flexible pavement stretch,

    the preliminary work concluded till about 2.20 kms. It was also

    noticed that work on 25 culverts was started in December 2015 and

    the widening had not been completed and that all the 25 culverts

    had become hazardous locations. That road safety signs of 25

    culverts were not provided and that work had completely stopped

    due to litigation over the settlement of dues of the supervisory staff

    and labourers of GVR. The mobilisation of material was also

    noticed to be less than 50%. An explanation from GVR was sought

    for all the deficiencies that were pointed out in the said letter.

    43. NHAI vide its communication dated 30.06.2016

    (Ex.R.21), notified GVR that it has not completed the first milestone

    – 30 –

    COMAP No. 127 of 2025

    of 10% of the financial progress of the contract within 180 days

    (i.e., within 22.06.2016). Hence, GVR was notified that the said

    works were required to be completed within the cure period of 45

    days from 23.06.2016. In the said letter-Ex.R21, the details of the

    materials and equipment that had not been mobilised were set out.

    Further, the progress of construction of the culverts (both pipe

    culverts and slab culverts) was set out. It was specifically noted

    that in respect of the said culvert works, only 15% of the physical

    progress was achieved, i.e., 0.41% of the whole work. Further, with

    regard to the flexible pavement works, physical progress is

    achieved only up to 1.54%, i.e., 1.29% of the whole work.

    Accordingly, GVR was notified that 1.70% physical progress has

    been achieved as against 10% of the progress as required under

    the agreement.

    44. NHAI vide letter dated 16.07.2016 (Ex.C.44), which

    had been issued during the cure period, notified GVR that despite

    the notice- Ex.R21, action for making good the shortfall has not

    been reported. It was also reported that progress has been

    reviewed as on 12.07.2016, i.e., about 20 days of the cure period

    having been completed and there was no significant progress in

    the project site except collection of GSB material of 1900 COM.

    – 31 –

    COMAP No. 127 of 2025

    Hence, GVR was called upon to explain as to how the shortfall

    would be made good in the remaining period of 25 days of the cure

    period.

    45. At this juncture, it is pertinent to notice that there is no

    material on record to indicate that GVR had responded to the said

    cure period notice -Ex.R21. It is further pertinent to note that in all

    the correspondence until the issuance of the said cure period

    notice, GVR had not raised the contention that portions of the road

    where the flexible pavement work was required to be carried out

    overlapped with an earlier work. In fact, in the letter dated

    05.04.2016 (part of Ex. R.9) (which has been noticed at para 37

    hereinabove) GVR has been specifically called upon to carry out

    the flexible pavement works. However, in none of the

    correspondence thereafter, the issue with regard to the overlap has

    been raised. In all the correspondences the only aspect that has

    been repeatedly raised by NHAI with GVR is the fact that the

    culvert work had not been completed and the flexible pavement

    work had not commenced; as also the materials as well as

    machinery had not been mobilized as required.

    – 32 –

    COMAP No. 127 of 2025

    46. The inspection note of the inspection dated 22.09.2016

    (Ex.C46) also discloses that the material at the site was 42.15%. It

    is also noticed that no labourers were engaged during monsoon for

    maintenance work. With regard to the extent of work, it is

    necessary to extract the relevant portion of the inspection note,

    which reads as under:

    “On the day of inspection the patching of pot holes
    at Km:232 in flexible pavement reach is in progress.
    In the balance reach of flexible pavement lot of pot
    holes has been observed the same shall be covered
    immediately to avoid inconvenience to the road
    commuters.

    In the proposed Rigid Pavement reach from
    Km:250.620 to 263.000, lot of pot holes are observed
    causing inconvenience to the road users the same
    may be covered and road shall be maintained traffic
    worthy by providing Wet Mix Mecadam immediately
    by engaging more maintenance batches as it is the
    primary responsibility of the tender agency.

    The centering/shuttering for three half done
    culverts has been erected in Km:259. It is reported by
    the contractor that the concrete batch of 40 members
    has been arrived at the project site. The contractor
    has been instructed to mobilize still more concrete
    batches to complete the culvert work in time.

    A meeting has been convened in the Shiradi Ghat
    inspection bungalow with the officials and the
    contractor.

    It is briefed to the agency regarding the meeting to
    be held on 26-09-2016 under the chairmanship of
    Principal Secretary, PWP & IWT Dept. Government
    of Karnataka with all the District Commissioners and
    Superintendent of Police of the concerned districts to
    discuss regarding the traffic closure from 15-10-2016.

    – 33 –

    COMAP No. 127 of 2025

    But during the discussion the contractor is requesting
    for traffic closure from 01-11-2016 due to the
    following reasons:

    • The work could not be started since the
    monsoon rains are still continuing.

    • The scope of work in respect of culvert
    widening is increased.

    • Mobilizing the Slip form paver with automatic
    dowel bar inserter is taking time.

    • The agency sought permission for starting the
    bituminous work and culvert works up to 01-
    11-2016, which in turn helps to cash flow for
    further work.

    Regarding traffic closure, it is instructed to adhere
    as was committed in the meeting which held under
    the chairmanship of Chief Engineer, National
    Highways on 16-09-2016. It is instructed the agency
    to prepare the programme on stage construction
    basis. Culvert works shall be completed in the first
    stage of 5 kms from where the rigid pavement work
    could start shall be completed first.

    It is also instructed to keep continuing the material
    collection like sand and aggregates.

    Regarding flexible pavement, the bituminous work
    may be get started if the rain stops.”

    (emphasis supplied)

    47. The NHAI vide the Official Memorandum [OM] dated

    24.09.2016 (Ex.C51) [debarment order] debarred the participation

    of GVR in all future tenders of the NHAI-Zone of PWD, Karnataka

    and as also recommended to the Ministry of Road Transport and

    Highways, Government of India [MORTH], to take similar action of

    – 34 –

    COMAP No. 127 of 2025

    debarment till 23.09.2017 or the further notice, whichever, is earlier

    of GVR in other centrally sponsored works elsewhere in the

    country. It is forthcoming that the OM dated 24.09.2016 (Ex.C51)

    was issued having regard to the fact that GVR had delayed in the

    execution of three contracted works, in which the present

    contracted work was also included.

    48. GVR vide letter dated 24.10.2016 (Ex.C52), requested

    for withdrawal to revoke the said debarment order. In the said

    reply, GVR has set out the progress of works in each of the

    contracts which was the subject matter of the debarment order. It

    had been represented by GVR that the contracted works were a

    special type of project wherein, the methodology of execution is

    totally different from other road construction projects, as the road

    traverses in the ghat section and reserve forest area. It was also

    stated that the said region experiences one of the highest rainfalls

    starting from May to October end and that the works can be

    executed only during November to April. Hence, it was stated that

    “huge quantities of materials have to be procured for uninterrupted

    progress of work during the available non-seasonal rainfall period

    of four months”. GVR also set out the status of its collection of

    material, as well as the mobilization of equipment.

    – 35 –

    COMAP No. 127 of 2025

    49. The inspection note of the inspection held on

    25.10.2016 (Ex.C45) in the presence of the representatives of

    NHAI and M/s. Suryodaya Infra Pvt Ltd (stated to be the sub-

    contractor of GVR) noticed that GVR had failed to achieve the

    assurances that were given by them in the meeting held on

    13.10.2016. Further, the sub-contractor agreed to complete 36 out

    of the 71 culverts by 15.11.2016, which is a prerequisite for closing

    of the road. It was decided to give a last and final chance to GVR

    for making use of the working period from October, 2015 to April

    2016, even though 18 months is stipulated as the working period

    as per the agreement. It was also noticed that the material that was

    mobilised was 42.15%. It is also pertinent to note that GVR was

    required to take up the undisputed extent of 6.06 kms and there is

    reference to submission of a change of scope proposal to be

    submitted.

    50. However, it is pertinent to note here that the change in

    the scope of work as referred to in the inspection dated 25.10.2016

    (Ex.C45) is occasioned due to the inability of GVR to complete the

    work within the time stipulated as per its assurances. Despite

    periodic reviews and setting milestones for completion of culvert

    works and commencement of flexible pavement works, GVR failed

    – 36 –

    COMAP No. 127 of 2025

    to complete the said milestones. As already noticed above, the

    flexible pavement work was required to be completed prior to the

    commencement of monsoon. However the culvert work itself, which

    was required to be done prior to commencement of the flexible

    pavement work, was also not done.

    51. Vide OM dated 18.11.2016 (Ex.C53), the debarment

    order was withdrawn since GVR has assured that the work

    specified would be completed within the stipulated period.

    52. A meeting was held on 05.11.2016 between the

    representatives of the parties. The relevant extract of the minutes

    of the meeting (part of Ex.R8) is as under:

    “A meeting was held on 05-11-2016 and the following
    points were discussed:-

    The Chief Engineer has again instructed to adhere the
    dates given by the Principal Secretary, Public Works,
    Ports & Inland Water Transport Department, Bangalore
    during the inspection of Shiradi Ghat on 04-11-2016.

    During the inspection the Agency has assured as
    follows:

    1. Out of 74 CD’s, 46 CD’s will be completed before
    15-11-2016 and balance will be completed by the end
    of December 2016.

    2. DLC Paver will be brought to site on: 07-11-2016.

    – 37 –

    COMAP No. 127 of 2025

    3. Slip form paver will be brought to site on: 20-11-
    2016.

    It is instructed the agency to complete the all the work
    as per his assurance before 20-11-2016 without fail.

    Further, instructions are also issued to the
    Superintending Engineer and Executive Engineer to
    watch the progress of the agency and submit the report
    on daily basis, if progress of the work is not satisfactory
    the Superintending Engineer and Executive Engineer are
    Authorized to Terminate the Contract without taking
    permission from the Chief Engineer’s Office duly
    observing all precautionary measures and action taken
    may be reported to this office.

    It is decided to convey a meeting on 20-11-2016 at
    11.30 A.M to take further action.”

    (emphasis supplied)

    53. It is clear and forthcoming from the said minutes that

    out of 74 culverts, GVR had assured, inter alia, that 46 culverts

    would be completed before 15.11.2016 and the balance would be

    completed by the end of December-2016. Further, the pavers were

    to be brought to the site by 20.11.2016.

    54. A meeting was once again held on 23.11.2016

    between the representatives of the parties. The minutes of the said

    meeting (part of Ex.R8) clearly noted that 42.87% of the materials

    were collected to the site. The equipment brought to the site was

    also noticed. Thereafter, it is also noticed that GVR had failed to

    – 38 –

    COMAP No. 127 of 2025

    complete the progress of the work as assured by them. Hence, in

    the interest of the completion of the work, GVR was also permitted

    to sub-contract the work. Relevant extracts of the said minutes is

    as under:

    “During the last meeting held on 05-11-2016,
    instructions were issued to the agency to complete the all
    the work as per his assurance before 20-11-2016 without
    fail. During the meeting held on 05-11-2016, the MD, M/s
    GVR Infra Projects Limited, Bangalore has reported that if
    agency fails to deploy the slip form paver on or before 20-
    11-2016 any decision may take to rescind the contract or
    to change the subcontract.

    Further, instructions are also issued to the
    Superintending Engineer and Executive Engineer to
    watch the progress of the agency and submit the report
    on daily basis, if progress of the work is not satisfactory
    the Superintending Engineer and Executive Engineer are
    Authorized to Terminate the Contract without taking
    permission from the Chief Engineer’s Office duly
    observing all precautionary measures and action taken
    may be reported to this office.

    In observing the above progress of the agency, till
    today agency has not adhered to the dates assured by the
    agency in any of the work from last one year. This is a
    very important nature of Rigid Pavement work, if
    contractor goes with the same speed in executing the
    above work the closing of Shiradi Ghat highway for a
    period of 3-4 months is not possible which will lead-to-
    Chaos and resentments.

    During the inspection of the Principal Secretary, Public
    Works Department on 04-11-21016, instructions were
    issued to the undersigned to watch the progress of the
    contractor upto 21-11-2016, if contractor fails to achieve

    – 39 –

    COMAP No. 127 of 2025

    progress as per his assurance action may be initiated to
    terminate the contract.

    Under the above circumstances, in observing the
    progress of the subcontractor from last 3-4 months
    contractor fails to achieve the progress as per his
    assurance.

    As discussed with the MD, M/s GVR Infra Projects
    Limited, Bangalore instead of terminating the contract, he
    requested to change the existing sub contract to the M/s
    Ocean Constructions(India) Pvt ltd, Mangalore. The same
    was consented by the SE, NH Circle, Bangalore, EE NH
    Division, Mangalore and AEE NH Sub Division,
    Sakaleshpura since first project was executed by the M/s
    Ocean Constructions (India) Pvt ltd, Mangalore as they
    have all equipments and man power required for the work
    and also they have experience in the last project.

    Hence, in the interest of work and public, it is decided
    allow M/s GVR Infra Projects Limited to sub contract the
    work to the M/s Ocean Constructions (India) Pvt ltd,
    Mangalore since M/s GVR Infra Projects Limited himself
    suggested the name of M/s Ocean Constructions(India)
    Pvt ltd, Mangalore and directions were issued to the M/s
    GVR Infra Projects Limited, Bangalore to give a proposal
    of subcontract in the name of M/s Ocean
    Constructions(India) Pvt ltd, Mangalore immediately and
    make all contractual arrangements within 28-11-2016 and
    directed to attend this office with all records on 28-11-
    2016. If these things are not fulfilled within 28-11-2016 the
    Executive Engineer is directed to terminate the contract
    by 30-11-2016 and report to this office by 01-12-2016.

    Meeting was ended with thanks to the Chair.”

    (emphasis supplied)

    55. It is pertinent to note that in the said meeting held on

    23.11.2016, it has been specifically noticed that GVR has not

    – 40 –

    COMAP No. 127 of 2025

    adhered to the dates assured by it for completion of the work for

    one year. Hence, since GVR was unable to complete the works as

    required, it suggested an appointment of a specific sub-contractor

    which was permitted by NHAI.

    56. Thereafter, vide communication dated 02.12.2016

    (Ex.C.29), NHAI issued a notice for termination as per Clause

    23.1.2 of the agreement. In the said notice, it was intimated that

    180 days from the appointed date expired on 22.06.2016, and that

    10% of the project milestone had not been completed. As per the

    said date, payments have been made only with respect to the first

    and second instalment of the mobilisation advance. GVR was also

    intimated that despite the letter dated 30.06.2016 (Ex.R.21) issued

    by NHAI to cure the said defect, the same had not been done. It

    was further noticed that GVR in the meeting dated 05.11.2016 (part

    of Ex. R.8), had represented that it would complete 46 out of 74

    CDs by 15.11.2016 and the balance by 31.12.2016 and that

    mobilisation would be done by 20.11.2016 at the site. However, in

    the meeting dated 23.11.2016, it was noticed that GVR had failed

    to adhere to the said assurance. Hence, NHAI notified GVR of its

    intention to issue a termination notice and called upon GVR to

    respond within 15 days.

    – 41 –

    COMAP No. 127 of 2025

    57. The said letter dated 02.12.2016 (Ex.C29) was

    responded to by GVR by its letter dated 12.12.2016 (Ex.C30). GVR

    responded by stating that the roads were required to be blocked for

    the entire period of the contract. That the delay in execution of the

    project was not attributable to them and in the meeting held on

    09.11.2016, all the issues were explained, and a request was made

    for change of milestones. It was alleged that the delays were due to

    the government agencies and department officials. GVR intimated

    that they are awaiting the road closure to start the construction

    work. Hence, they requested for withdrawal of the notice for

    termination.

    58. Vide Letter dated 02.01.2017 (Ex.R.22) written by the

    Executive Engineer, NHAI, Mangalore Division to the

    Superintendent Engineer, NHAI, it was placed on record that GVR

    was able to achieve total progress of 3.78% after completion of 11

    months of the 18 months of the tender period. It was further

    specifically noted that in the inspection dated 04.11.2016, GVR had

    assured to procure the materials and complete 46 culverts out of

    74 culverts on 15.11.2016 and the remaining culverts by

    30.12.2016. However, the said progress has not been achieved. It

    was further noticed that on 19.12.2016, the progress of the work

    – 42 –

    COMAP No. 127 of 2025

    was once again reviewed and even after a lapse of more than one

    and a half months from the inspection dated 04.11.2016, only 23

    culverts had reached road level. Further, when an explanation was

    sought from GVR, they gave a commitment letter dated

    21.12.2016, which they had failed to comply with. Hence, it was

    reported that GVR was not able to complete the culverts as per its

    commitment and there was no further collection of aggregates at

    the site. It was also noticed that the requisite pavers with DBI

    (Dowel Bar Inserter) had not been procured.

    59. NHAI issued the termination notice dated 04.01.2017

    (Ex.C35). In the said notice, a detailed reference has been made to

    all the correspondence exchanged between the parties as well as

    the relevant stipulations in the agreement. It was placed on record

    that since the first milestone was not completed, the contract was

    terminated as per Clause 23.1.1 C and 23.1.1.O.

    60. The Issue No.6 is whether the termination by NHAI is

    valid and legal. Issue No.7 is whether GVR achieved the first

    financial milestone in terms of the contract. The Arbitral Tribunal,

    while coming to the conclusion that the action of the NHAI in

    terminating that contract is not valid and legal, has merely noticed

    – 43 –

    COMAP No. 127 of 2025

    some of the communication between the parties. However, the

    arbitral tribunal did not notice the communications in terms of the

    sequence of events so as to appreciate and adjudicate as to

    whether the GVR had completed the first milestone. Further, while

    considering Issue No.7, the Arbitral Tribunal concluded that the

    GVR was prevented by NHAI in completing the works in terms of

    the contract. The said conclusion was arrived at having regard to

    the finding recorded in Issue No.4.

    REGARDING FLEXIBLE PAVEMENT WORKS:

    61. Issue No.4 was with regard to whether there was

    overlapping in the flexible pavement works and as to whether GVR

    was prevented from completing the flexible pavement works. The

    Tribunal, while considering Issue No.4, held and concluded as

    under:

    “Thus A.T finds that,

    i) The Claimant was prevented from carrying out
    flexible pavement work upto 23.05.2016. The
    claimant completed the work of flexible pavement in
    the Town Limit of Sakaleshpur from Km 219.534 to
    Km 225.600 for a length of 6.06.Km on 09.06.2016.

    ii) The Authority instructed the Claimant on
    25.10.2016 (Ex C-45) to carry out the remaining

    – 44 –

    COMAP No. 127 of 2025

    length of 14.558 Km by providing.30 mm B.C, which
    resulted in Change in Scope of work.

    iii) No directions to the claimant were given by the
    Authority/Authority Engineer between 23.05.2016 to
    25.10.2016 regarding carrying out flexible pavement
    work

    iv) The respondent has also not included this flexible
    pavement stretch while inviting tender.

    The AT comes to the conclusion that

    i) The road length from KM 216.000 to Km. 219.534
    and Km.225.600 to KM 237.000 over lapse with work
    proposed to be taken up by the NHẠI.

    ii) The delay in taking the decision by the Authority
    has prevented the Claimant in completing the flexible
    pavement work from KM 216 to KM 237 before June
    2016 as per programme submitted by him.”

    62. The said finding was recorded by the Arbitral Tribunal

    noticing the letter of NHAI dated 23.05.2016 (Ex.C-20) written to

    GVR; the inspection note dated 25.10.2016 (Ex.C-45) and the letter

    dated 05.01.2017 (Ex.C-87) written by the NHAI-Mangalore

    Division to the NHAI, KR Circle, Bangalore.

    63. At this juncture, it is pertinent to note that the entire

    contents of the letter-Ex.C20 have been extracted at paragraph 40

    supra. The context of the letter i.e., the previous correspondence,

    has also been noticed at paragraphs 35 to 39 supra. It is clear and

    forthcoming from a plain reading of the same that the GVR was

    – 45 –

    COMAP No. 127 of 2025

    called upon to start the flexible pavement work in Sakleshpur Town

    limit between 219.432 KM to 225.50 KM (6.07 KM), which is the

    undisputed portion at that point of time. This was in the context of

    NHAI noticing that GVR had consistently defaulted in completing

    the works as was required to be done by them.

    64. With regard to the inspection note dated 25.10.2016

    (Ex.C-45), which has been extracted by the Arbitral Tribunal, it is

    noticed that the preamble of the said inspection note has been

    extracted in the findings of the Arbitral Tribunal. In the said

    inspection note, consequent to the review of the progress, it was

    noticed as under:

    “The Agency has agreed to complete 36 culverts out of 71
    within 15-11-2016 which is a prerequisite for closing the
    road. The Assistant Executive Engineer briefed the
    necessity of the construction of guard wall on valley side
    and drain on hillock side before laying GSB wherever the
    width constraints are encountered for ensuring confinement
    to the GSB as well as safe passage to the slip from paver
    movement. The agency has instructed to deploy additional
    concrete batches immediately for such locations.”

    (emphasis supplied)

    – 46 –

    COMAP No. 127 of 2025

    65. Further, in the said inspection note, it was also noticed

    that the mobilisation of material by GVR was of a cumulative of

    42.15% and that there was no progress achieved since the

    previous meeting. The GVR had given various assurances with

    regard to further mobilization of material. Hence, in the inspection

    note, it was concluded that the assurance of GVR about the

    progress would be reviewed on 15.11.2016 and a final decision will

    be taken.

    66. It is clear and forthcoming from the said inspection and

    all the prior communications between the parties, as well as the

    Minutes of the Meetings that GVR had never completed the work in

    terms of the contract. The consistent defaults of GVR had been

    repeatedly noticed and placed on record by NHAI in the various

    communications and meetings. The timelines were reviewed

    periodically by NHAI merely to ensure compliance of the same by

    GVR, which has also not yielded any result. It is pertinent to notice

    here that even as on the said date of inspection i.e., 25.10.2016

    i.e., after lapse of more than four months of the expiry of the first

    milestone period of 180 days, the GVR was yet to complete even

    the construction and modification of culverts.

    – 47 –

    COMAP No. 127 of 2025

    67. With regard to the contention of GVR regarding closure

    of the road, the request of GVR for closure of the road for carrying

    out rigid pavement work was made vide letter dated 04.04.2016

    (part of Exhibit R10). In response to the said request, the Assistant

    Executive Engineer, NHAI Sakleshpur in its communication dated

    20.04.2016 (Ex.C.25) to the Executive Engineer, NHAI, Bangalore

    Division, a copy of which was marked to GVR has inter alia stated

    as under:

    “Since this is an important time bound state
    project, the above project site is located on the main
    National Highway No-48, connecting Capital city
    Bangalore and port city Mangalore. The construction
    of rigid pavement work is to be taken up by totally
    closing the vehicular traffic on the above project
    stretch for as minimum period as possible to avoid
    inconvenience to the road users. There will be lot of
    pressure from the Public as well as from the elected
    representatives to complete the work early in view of
    traffic closure.

    Keeping in view the above condition of the project
    it is instructed the tender agency to collect minimum
    of 50% of total requirement of the construction
    materials so that the progress of the work should not
    be hampered or stopped in the middle for want of
    construction materials. Sometimes there may be
    imposition of ban on the mining activities of sand and
    metal from the district administration side time to
    time, which in turn affect the progress of the project.

    Keeping in view of the above consequences the
    tender agency may be instructed to explore the
    possibility of hiring the level ground for collection of

    – 48 –

    COMAP No. 127 of 2025

    construction materials, the same has been done by
    the adjacent contractor while executing the work of
    “Providing Rigid pavement from Km:237.000 to
    Km:263.000 (Shiradi Ghat) of NH-48, B-M section”

    and identified several stacking yards nearby and
    collected 50% of construction material in advance.”

    (emphasis supplied)

    68. It is clear that the work of construction and modification

    of culverts and other works were to be completed before the task of

    asphalting the road could be done. This aspect has been

    specifically stipulated as is forthcoming from the Minutes of the

    Meeting held on 16.09.2016 (Ex.C.19). Perusal of the said minutes

    indicates that NHAI has specifically stipulated that the culverts of at

    least 5 km stretch of the road should be completed before the start

    of the rigid pavement work. It was also noticed that the requisite

    material was not available at the site. A schedule for the

    procurement of machinery was also specified. Since a request was

    made by GVR for closure of the road, it is noticed that NHAI has

    specifically briefed GVR of the inconvenience caused due to

    closure of road which is an important national highway connecting

    the capital city-Bangalore and the port city-Mangalore; as also the

    sensitiveness of the project. It is in the said context, the NHAI had

    specifically stipulated that the closure of the road could be done

    – 49 –

    COMAP No. 127 of 2025

    only if the requisite material is available at the site and the culvert

    work was completed. GVR was called upon to give a programme

    of work in which the requisite stipulated works would be carried out.

    However, the said aspect of the matter which is forthcoming from

    material on record has not been noticed by the Arbitral Tribunal

    while recording its findings.

    69. The Tribunal has also noticed the letter dated

    05.01.2016-Ex.C87, whereunder the NHAI-Mangalore Division had

    reported to the NHAI-K.R.Circle, Bangalore regarding the other

    works as well as the present contract in question. In this context,

    NHAI, Mangalore Division had opined to the NHAI, Bangalore

    Division that the work pertaining to the present contract was

    required to be done in precedence over the other works. The same

    clearly falsifies the contentions ought to be taken by GVR that it

    had been orally asked not to carry out the works which was

    overlapping with the present works.

    70. It is clear from the sequence of communication

    between the parties as well as the minutes of the meeting (as

    noticed at paragraphs 35 to 54 herein above) that GVR had

    defaulted in the timelines stipulated for completion of the various

    – 50 –

    COMAP No. 127 of 2025

    works. The periodic assurances given by GVR from time to time in

    the various meetings and letters have not been adhered to. It is

    pertinent to notice (at cost of repetition) that the first milestone of

    180 days from the appointed date expired on 22.06.2016, within

    which GVR was required to complete 10% of the value of the

    contract. The NHAI had vide its communication dated 30.06.2016

    (Ex.R.21) notified GVR that since the first milestone was not

    completed within the stipulated time, the same was required to be

    completed within 45 days from 23.06.2016 (cure period). A

    reminder was issued vide letter-Ex.C.44 during the cure period

    whereunder it was indicated that there was no significant progress

    in the work. Despite the same the requisite work was not

    completed even during the cure period. Subsequently, the

    debarment order (Ex.C.51) was issued, which was withdrawn (vide

    Ex.C53 dated 18.11.2016). Further, the notice for termination dated

    02.12.2016 (Ex.C.29) was issued consequent to which the

    termination notice dated 04.1.2017 (Ex.C35) has been issued.

    71. As already noticed above, there were various

    correspondences exchanged and meetings that were held after

    issuance of the debarment order and before its withdrawal; as well

    as after issuance of the notice for termination – Ex.C29 and the

    – 51 –

    COMAP No. 127 of 2025

    termination notice – Ex.C35. In none of the said communication

    there was request by GVR for closure of the road while carrying out

    the flexible pavement works.

    72. The Tribunal had concluded that there was overlapping

    from 216 km., to 219.435 km., and from 225.600 km., to 237.000

    km., and that the delay by NHAI in taking the decision prevented

    GVR from completing the flexible pavement work with regard to the

    said extent of work. However, the Tribunal had also concluded that

    GVR had completed the work of flexible pavement in the town limit

    of Sakleshpura for the undisputed extent of 6.066 km. It was

    concluded that GVR was prevented from carrying out the flexible

    pavement work upto 23.05.2016.

    73. It is clear from the aforementioned discussion that the

    findings of the Tribunal on Issue No.4 as well as Issue No.6 and7

    have been recorded without noticing all the material available on

    record and the said findings are patently illegal.

    REGARDING RIGID PAVEMENT WORKS:

    74. Issue No.5 was with regard to the road between

    250.620 km. to 263.00 km., i.e., the extent of road where the rigid

    – 52 –

    COMAP No. 127 of 2025

    pavement work was required to be carried out. The Tribunal

    concluded that the said work could not be carried out without

    closing the said road.

    75. It is pertinent to note here that the closure of the road

    to carry out the rigid pavement works is not contemplated under the

    agreement. GVR had requested for closure of the road to carry out

    the rigid pavement works. However, the NHAI had acceded to the

    request of GVR with regard to closure of the road upon GVR

    completing the culvert works. The material on record, as already

    noticed above, would clearly indicate that GVR had not even

    completed the work of construction/modification of the culverts in

    the section of the rigid pavement works until the date of termination

    of the agreement. The finding of the Tribunal that the said work

    could not be carried out without closure of the road is without taking

    into consideration the material which indicated that the culvert

    works were required to be completed before contemplating closure

    of the road.

    76. As noticed at para 68 above, the request of GVR for

    closure of the road was acceded to by NHAI only in the interest of

    the works being completed expeditiously subject to certain

    – 53 –

    COMAP No. 127 of 2025

    conditions. Further, it is to be noticed that when the request by

    GVR for closure of the road was made, NHAI considering the same

    request, noticed the importance of the road vis-à-vis its connectivity

    etc., as also noticing that GVR had delayed in the completion of the

    works clearly specified that the request for closure of the road

    would be considered upon completion of the

    construction/modification of the road as well as upon GVR

    mobilizing the requisite material. The aspect regarding mobilizing

    the material was specifically stipulated by NHAI since it had

    apprehended that after closure of the road, GVR would not have

    been able to complete the work within the time stipulated by it. This

    aspect of the matter is clear and forthcoming from the

    communications, as noticed above, which has not been

    appreciated by the Tribunal. Hence, the finding of the Tribunal on

    Issue No.5 is ex-facie patently illegal.

    77. With regard to the scope of this Court as contemplated

    under Section 37 of the A & C Act, it is relevant to notice the

    judgment of the Supreme Court in the case of Dyna Technologies

    – 54 –

    COMAP No. 127 of 2025

    Private Limited v. Compton Greaves Limited1, wherein it has

    been, inter alia, held as under:

    “34. The mandate under Section 31(3) of the
    Arbitration Act is to have reasoning which is
    intelligible and adequate and, which can in
    appropriate cases be even implied by the courts from
    a fair reading of the award and documents referred
    to thereunder, if the need be. The aforesaid provision
    does not require an elaborate judgment to be passed
    by the arbitrators having regard to the speedy
    resolution of dispute.

    35. When we consider the requirement of a
    reasoned order, three characteristics of a reasoned
    order can be fathomed. They are: proper, intelligible
    and adequate. If the reasonings in the order are
    improper, they reveal a flaw in the decision-making
    process. If the challenge to an award is based on
    impropriety or perversity in the reasoning, then it can
    be challenged strictly on the grounds provided under
    Section 34 of the Arbitration Act. If the challenge to
    an award is based on the ground that the same is
    unintelligible, the same would be equivalent of
    providing no reasons at all. Coming to the last aspect
    concerning the challenge on adequacy of reasons,
    the Court while exercising jurisdiction under Section
    34 has to adjudicate the validity of such an award
    based on the degree of particularity of reasoning
    required having regard to the nature of issues falling
    for consideration. The degree of particularity cannot
    be stated in a precise manner as the same would
    depend on the complexity of the issue. Even if the
    Court comes to a conclusion that there were gaps in
    the reasoning for the conclusions reached by the
    Tribunal, the Court needs to have regard to the

    1
    (2019) 20 SCC 1

    – 55 –

    COMAP No. 127 of 2025

    documents submitted by the parties and the
    contentions raised before the Tribunal so that awards
    with inadequate reasons are not set aside in casual
    and cavalier manner. On the other hand, ordinarily
    unintelligible awards are to be set aside, subject to
    party autonomy to do away with the reasoned award.
    Therefore, the courts are required to be careful while
    distinguishing between inadequacy of reasons in an
    award and unintelligible awards.”

    REGARDING ISSUE NO.2 – WHETHER THE SITE WAS PORCURED

    IN ACCORDANCE WITH AGREEMENT:

    78. The Arbitral Tribunal had concluded, while considering

    Issue No.2 that “the project highway site is not procured by the

    parties in accordance with the agreement.” In this context, the

    Tribunal noticing the letter dated 17.12.2015 (Ex.C24) wherein

    GVR was instructed to inspect the site and prepare a memorandum

    as per Article 8.2., held that the parties had not followed the said

    instructions and the conditions of the contract; but simply enclosed

    Schedule-A to the Agreement and road details.

    79. It is relevant to notice that the works that were required

    to be carried out under the agreement were upon an existing

    highway. There was no fresh acquisition of land from any private

    party. The subject matter of the contract was not laying down of a

    – 56 –

    COMAP No. 127 of 2025

    fresh road. Under the circumstances, the finding of the Tribunal on

    Issue No.2 is ex-facie to be interfered with as patently illegal.

    REGARDING THE COUNTERCLAIM OF NHAI:

    80. The NHAI had made a counterclaim of ₹79,65,98,050/-. The

    Tribunal had framed Issue No.9 with regard to the counterclaim of

    NHAI. The said counterclaim was quantified primarily taking into

    account the value of the work that was subsequently entrusted to

    another agency for completion, which was in a sum of ₹74 Crore.

    The other claims are with regard to performance security bank

    guarantee, mobilization advance bank guarantee, legal expenses

    and valuation of unpaid works. However, the said finding recorded

    by the Tribunal rejecting the counterclaim is primarily premised on

    the finding recorded on Issue No.6 that the termination of the

    agreement by NHAI was not proper. The said finding on, inter alia,

    Issue No. 6 being patently illegal, the finding of the Tribunal

    rejecting the counterclaim is also to be set aside. However, the

    parties are at liberty to initiate arbitration proceedings with regard to

    adjudication of the said aspect.

    – 57 –

    COMAP No. 127 of 2025

    OTHER ISSUES:

    81. Issue No.1 framed by the Tribunal is with regard to the

    duration of the contract. The Tribunal had concluded that the

    duration of the agreement was 24 months; the same is on the basis

    of the schedule to the agreement. A perusal of various materials on

    record would clearly indicate that GVR has also admitted that the

    duration of the agreement is 18 months. A specific reference is to

    be made to letter dated 25.11.2015 (Ex.C3) written by GVR while

    furnishing the bank guarantee, whereunder they indicated that they

    were planning to complete the project in 6 months instead of 18

    months. The duration of the agreement as 18 months is also

    mentioned by GVR in its letter dated 25.10.2016 (Ex.C28).

    Accordingly, the finding of the Tribunal in Issue No. 1 is ex facie

    patently illegal.

    82. Issue No.3 is whether the Authority Engineer is

    required to be an independent engineer. The Tribunal concluded

    that NHAI cannot appoint its own engineer as Authority Engineer.

    In this context, it is pertinent to note that NHAI is required to

    appoint an Authority Engineer in terms of Article 18 of the

    Agreement and that a ‘consulting engineering firm’ must be

    – 58 –

    COMAP No. 127 of 2025

    appointed. Appointment of a government entity as an authority

    engineer is also permitted provided that, inter alia, the same should

    not be owned or controlled by NHAI.

    83. The requirement of appointing an Authority Engineer is

    only with the intention of ensuring that an independent perspective

    and advice is available to NHAI when it reviews the work under the

    contract in question. The said appointment would not entitle GVR

    to allege breach of the terms of the agreement. Hence, the findings

    of the Arbitral Tribunal on Issue No.2 are also to be set aside on

    the ground of patent illegality.

    84. In view of the aforementioned discussion, the findings

    of the Arbitral Tribunal on Issue Nos.1 to 7 are set aside.

    Consequently, Issue No.8 whereunder the claims made (Claim 1 to

    20) by GVR were considered and the damages have been

    awarded with respect to some of the claims are also set aside.

    Liberty is reserved to the parties to re-arbitrate on Issue No.9

    regarding counterclaim.

    – 59 –

    COMAP No. 127 of 2025

    85. The appeal is partly allowed in the aforementioned

    terms.

    SD/-

    (VIBHU BAKHRU)
    CHIEF JUSTICE

    SD/-

    (C.M. POONACHA)
    JUDGE

    BS/YAN/PMP/RKM/ND



    Source link

    LEAVE A REPLY

    Please enter your comment!
    Please enter your name here