M/S. Harsha Constructions And Ors vs Vkm Projects Private Limited And Ors on 28 July, 2026

    0
    5
    ADVERTISEMENT

    Calcutta High Court

    M/S. Harsha Constructions And Ors vs Vkm Projects Private Limited And Ors on 28 July, 2026

                        IN THE HIGH COURT AT CALCUTTA
                             COMMERCIAL DIVISION
                                 ORIGINAL SIDE
    
                           RESERVED ON: 22.06.2026
                           DELIVERED ON: 28.07.2026
    
                                   PRESENT:
                    THE HON'BLE MR. JUSTICE GAURANG KANTH
    
                                APOT 297 OF 2025
    
                      IA NO: GA-COM/1/2025, GA-COM/2/2025
    
                     M/S. HARSHA CONSTRUCTIONS AND ORS.
                                     VS
                    VKM PROJECTS PRIVATE LIMITED AND ORS.
    
    Appearance: -
    
    Mr. Jishnu Choudhury, Sr. Adv.
    Mr. Avijit Ghoshal, Adv.
    Ms. Sreeja Mukherjee , Adv.
                                            ........................... for the Appellants
    
    Mr. Rachit Lakhmani, Adv.
    Mr. Aditya Chakraborty, Adv.
    Ms. Pooja Sah, Adv.
    Mr. Siddharth Makkar, Adv.
                                                   .............. for the Respondents
    
                                     JUDGMENT
    

    Gaurang Kanth, J. :-

    1. The appellants have preferred the present appeal under Section 37(2)(b) of

    the Arbitration and Conciliation Act, 1996, assailing the order dated

    10.06.2025 passed by the learned Sole Arbitrator whereby an application

    filed by the respondents (claimants before the learned Arbitral Tribunal)

    under Section 17 of the Arbitration and Conciliation Act, 1996 was allowed,

    directing the appellants (respondents before the Arbitral Tribunal) to

    produce and disclose documents pertaining to a contract entered into

    between the appellants and a third party, M/s Rapiscan Systems Pvt. Ltd.
    2

    2. The appellants herein were the respondents before the learned Arbitral

    SPONSORED

    Tribunal, while the respondents herein were the claimants therein. The

    facts giving rise to the present appeal are set out hereinafter.

    3. M/s Rapiscan Systems Private Limited had entered in to a principal

    contract with the Syama Prasad Mookherjee Port Trust, Kolkata, for the

    installation of an X-ray based Drive Through Container Scanner (DTCS).

    As per the said principal contract, M/s Rapiscan Systems Private Limited

    was permitted to engage sub contractors for carrying out various works

    associated with it.

    4. A joint venture Agreement dated 06.09.2021, was executed between the

    appellants, and respondents (M/s VKM Projects Pvt. Ltd and Marketing

    Point, a partnership firm in which Respondent Nos. 2-3 are partners).

    Pursuant thereto, respondent no. 1, Marketing Point and appellant no. 1

    agreed to collaborate for securing and executing civil and structural works

    associated with the delivery and installation of DTCS System at the Syama

    Prasad Mookherjee Port Trust, Kolkata in terms of its principal contract,

    with appellant no. 1 acting as the entity through which quotations would

    be submitted. On the same date, the parties also entered into a

    Supplementary Agreement recording, inter alia, that the sub-contract, if

    awarded, would stand in the name of appellant no. 1 and that respondent

    no. 1 and Marketing Point would receive remuneration for their marketing

    and consultancy services at the rate of 5% each of the value of every bill

    raised under the sub-contract, together with applicable taxes, payable

    upon receipt of payment by appellant no. 1.

    5. Thereafter, on 16.09.2021, M/s Rapiscan Systems Private Limited issued a

    Notification of Award in favour of appellant no. 1. A formal Sub-Contractor
    3

    Contract was also executed on the same date between M/s Rapiscan

    Systems Private Limited and the appellants.

    6. The respondents have averred that following the execution of the aforesaid

    agreements, they participated in various preparatory activities connected

    with the project, including establishment of the site office, obtaining

    requisite permissions and licences, deployment of security personnel and

    engagement of sub-contractors.

    7. It is the case of the respondents before the learned Arbitral Tribunal that

    from October 2021 onwards, they were not provided with information

    concerning the progress and financial status of the project. The

    respondents addressed various communications to the appellants seeking

    information relating to the project, including particulars of payments

    allegedly received under the sub-contract. The parties, however, dispute

    the significance and effect of such communications.

    8. Disputes having arisen between the parties in connection with the Joint

    Venture Agreement and the Supplementary Agreement dated 06.09.2021,

    arbitral proceedings were commenced before the learned Sole Arbitrator.

    9. In the course of the arbitral proceedings, the respondents filed an

    application under Section 17 of the Arbitration and Conciliation Act, 1996

    seeking, inter alia, directions upon the appellants to disclose particulars of

    the running account bills raised upon M/s Rapiscan Systems Private

    Limited and the status of payments received there against; to produce the

    books of accounts, profit and loss statements and balance sheets

    pertaining to the project; and to disclose records evidencing the total

    revenue generated under the sub-contract dated 16.09.2021.
    4

    10. By the impugned order dated 10.06.2025, the learned Sole Arbitrator held

    that the reliefs sought by the respondents fell within the ambit of Section

    17(1)(ii)(a) and Section 17(1)(ii)(c) of the Arbitration and Conciliation Act,

    1996 and that the documents sought were relevant to the disputes

    pending before the Arbitral Tribunal. Accordingly, the learned Sole

    Arbitrator directed the appellants to disclose the particulars of the running

    account bills raised upon M/s Rapiscan Systems Private Limited together

    with their clearance status, to disclose the relevant books of accounts,

    profit and loss statements and balance sheets, and to produce records

    relating to the total revenue generated under the sub-contract, within the

    timelines stipulated therein.

    11. Aggrieved by and dissatisfied with the aforesaid order dated 10.06.2025,

    the appellants have preferred the present appeal.

    Submission on behalf of the Appellants

    12. Mr. Jishnu Choudhury, learned Senior Counsel appearing on behalf of the

    Appellants, submits that the application preferred by the Respondents

    before the learned Sole Arbitrator under Section 17 of the Arbitration and

    Conciliation Act, 1996 was wholly misconceived and that the impugned

    order dated 10.06.2025 is ex facie without jurisdiction and is therefore

    liable to be set aside. It is submitted that no Joint Venture was ever given

    effect to between the parties: Clause 17 of the Sub-Contractor Contract

    dated 16.09.2021 between Rapiscan Private Limited and the Appellants

    expressly barred sub-contracting without Rapiscan’s prior written consent.

    It is contended that no such consent was ever granted in favour of the

    Respondents that the proposed joint venture namely “Maharav Infra

    Projects” was never formed, and that the entire work was executed solely
    5

    by the Appellants without demur from the Respondents until after the

    work had been complete. These facts, going to the root of the Respondents’

    claimed entitlement to the documents sought, were never considered in the

    impugned order.

    13. It is submitted that the jurisdiction of an Arbitral Tribunal under Section

    17 is analogous to, and co-extensive with, that of a Court under Section 9,

    both being confined to granting interim measures of protection; Section 17

    does not empower an Arbitral Tribunal to direct discovery, disclosure or

    compulsory production of documents for the purpose of collecting or

    preserving evidence. The impugned order, directing disclosure of Running

    Account bills, books of accounts, profit and loss statements, balance-

    sheets and relating to the total revenue generated records, under the sub-

    contract is in substance an order for production of evidence, and any such

    direction could only have been issued under Section 19, which governs

    admissibility, relevance and production of evidence, read with Section 27

    of the Act. The source of the power to order discovery is accordingly not

    rooted in Section 17(1)(ii)(c) at all, and any attempt to invoke Section 17 for

    this purpose renders Sections 19 and 27 nugatory, as held in Union of

    India v. Reliance Industries Limited and Others, reported as 2018

    SCC OnLine Del 13018, and in Pennar Aluminium Company Limited

    (PALCO) v. Chairman-cum-Managing Director, National Aluminium Co.

    Ltd., reported as 2019 SCC OnLine Ori 370.

    14. It is further submitted that Section 17(1)(ii)(c) is couched in language

    almost identical to Order XXXIX Rule 7 of the Code of Civil Procedure,

    1908, and is, therefore, required to be construed accordingly, as held in

    Augmont Gold Private Limited v. One97 Communication Limited,
    6

    reported as 2021 SCC OnLine Del 4484. Order XXXIX Rule 7 empowers

    the Court to direct detention, preservation and inspection only of the

    property which is the subject matter of the suit, and not of documents

    which are merely of evidentiary value, as held in Ramswarup v. Mst.

    Kesar, reported as AIR 1958 Raj 218 (para 8). It is further submitted

    that even where a question may arise relating to the suit, no commission

    or order can be issued thereunder for the purpose of collecting evidence

    through discovery, as held in Institution of Engineers (India) v. Bishnu

    Pada Bag, reported as AIR 1978 Cal 296, and in The Owners and

    Parties Interested in the Vessel ‘M.V. Baltic Confidence’ v. The State

    Trading Corporation of India Limited, reported as AIR 2000 Cal 91.

    The books of account and RA bills sought by the Respondents cannot, in

    any event, be construed as “property or thing” which is the subject matter

    of dispute, as held in Padam Sen and Another v. State of Uttar

    Pradesh, reported as 1960 SCC OnLine SC 77.

    15. It is submitted that an Arbitral Tribunal, being a private adjudicatory

    forum, is not vested with the coercive powers of a civil court to compel

    production of documents. Even before a civil court, failure to produce

    documents results only in the drawing of an adverse inference under

    Section 114(g) of the Indian Evidence Act, 1872, and not in the issuance of

    a mandatory direction to produce such documents, as held in Rajesh

    Bhatia v. G. Parimala & Ors., reported as 2005 SCC OnLine AP 970,

    and in Krishan Dayal v. Chandu Ram, reported as 1969 SCC OnLine

    Del 134. It is further submitted that under Section 27 of the Act, a party

    is entitled to an opportunity of being heard and to contend that no such

    order ought to be made before a Court renders assistance in taking
    7

    evidence, a safeguard which according to the Appellants was denied to

    them. It is also submitted that the underlying dispute being a pure money

    claim, the money claimed cannot by itself constitute the “subject matter of

    the arbitration” within the meaning of Section 17. At the highest, a party

    may seek attachment or security in respect of the claim, but no order for

    disclosure or production of documents can be justified on this footing,

    since documentary evidence can never assume the character of the subject

    matter of the dispute.

    16. Finally, it is submitted that the impugned order contains no discussion of

    the facts of the case and records no finding as to why the Respondents

    would be entitled to the documents sought, thereby rendering the

    impugned order perverse on this ground alone. For the reasons set out

    above, the impugned order dated 10.06.2025 is wholly unsustainable in

    law, having been passed without jurisdiction and without consideration of

    the relevant facts, and is accordingly liable to be set aside.

    Submission on behalf of the Respondents

    17. Mr. Rachit Lakhmani, learned Counsel for the Respondents submits that

    the impugned order dated 10.06.2025 passed by the learned Sole

    Arbitrator is a well reasoned order passed after due application of mind to

    the facts and circumstances of the case, and does not warrant any

    interference by this Court in exercise of its jurisdiction under Section 37 of

    the Arbitration and Conciliation Act, 1996. It is submitted that the

    question as to whether the documents sought to be produced and

    disclosed form part of the subject matter of the arbitration is essentially

    one which depends upon a careful interpretation of the various clauses of

    the agreements entered into between the parties, requiring a detailed and
    8

    comprehensive analysis of the contractual terms. The learned Sole

    Arbitrator has undertaken precisely such an exercise by carefully

    examining the relevant clauses of the Joint Venture Agreement and the

    Supplementary Agreement dated 06.09.2021, and has arrived at a

    considered finding that the documents in question constitute the subject

    matter of the present arbitration. It is submitted that this Court, while

    exercising its appellate jurisdiction under Section 37 of the Act, is neither

    required nor expected to interfere with such findings of fact and law

    arrived at by the learned Arbitral Tribunal, which fall squarely within the

    domain of the Tribunal’s jurisdiction.

    18. It is further submitted that the Joint Venture Agreement dated 06.09.2021

    was entered into between all the parties herein, whereunder appellant no.

    1 holds a 34% share in the joint venture, respondent no. 1 holds a 33%

    share, and respondents nos. 2 to 4, being partners of the partnership firm

    Marketing Point, collectively hold the remaining 33% share. It is submitted

    that prior to the formation of the joint venture, all three entities were

    already actively associated with and working on the project in connection

    with M/s. Rapiscan Systems Private Limited. On the same date, the parties

    also executed a Supplementary Agreement. Since the formation of a new

    legal entity would have taken considerable time, an interim arrangement

    was mutually agreed upon by all the parties, whereby appellant no. 1 was

    permitted to submit the bid and receive the sub-contract in its own name

    as a temporary measure pending the constitution of the joint venture

    entity. Learned Counsel for the respondents draws the attention of this

    Court to Clause 5.2 of the Joint Venture Agreement, which according to

    him expressly creates a right in favour of the respondents to inspect the
    9

    records of the joint venture and correspondingly imposes a duty upon the

    appellants to disclose all details pertaining to the operations of the joint

    venture, including the books of accounts. It is therefore submitted that the

    obligation of disclosure cast upon the appellants is not merely a

    procedural requirement but a substantive contractual right vested in the

    respondents as joint venture partners.

    19. It is also submitted that the Supplementary Agreement expressly

    acknowledges the efforts and contributions of the respondents towards the

    project and categorically records that the sub-contract was awarded by

    M/s. Rapiscan Systems Private Limited as a direct result of the combined

    marketing efforts of respondent no. 1 and the partnership firm represented

    by respondents nos. 2 to 4. The appellant was merely authorised to obtain

    the sub-contract in its name as an interim measure. The Supplementary

    Agreement further reflects that the respondents had already rendered

    services in connection with the project prior to its formal award. Under the

    terms of the said agreement, the appellant was obligated to raise bills upon

    M/s. Rapiscan Systems Pvt. Ltd and the respondents were entitled to

    receive their respective shares within 10 days from the receipt of each

    payment from M/s. Rapiscan systems Pvt. Ltd. It is therefore submitted

    that the respondents are not mere sub-contractors engaged by the

    appellant for the execution of work under the appellant’s instructions but

    are joint venture partners entitled to profit sharing. The Joint Venture

    Agreement having been incorporated by reference into the Supplementary

    Agreement, the appellant is under a clear contractual obligation to disclose

    all accounts and details of the bills raised to the respondents in their

    capacity as joint venture partners.

    10

    20. It is submitted that Section 17(1)(ii)(c) of the Arbitration and Conciliation

    Act, 1996 expressly empowers an Arbitral Tribunal to pass an order for the

    detention, preservation or inspection of any property or thing which is the

    subject matter of the dispute in arbitration, or as to which any question

    may arise therein. It is further authorises any person to enter upon any

    land or building in the possession of any party, or authorises any samples

    to be taken, or any observation to be made, or any experiment to be tried,

    which may be necessary or expedient for the purpose of obtaining full

    information or evidence. It is submitted that the expression “thing” as used

    in Section 17(1)(ii)(c) is a deliberate and significant addition, going beyond

    the language of Order XXXIX Rule 7 of the Code of Civil Procedure, 1908,

    which does not employ the said expression. This addition reflects the

    legislative intent to confer wider powers upon an Arbitral Tribunal so as to

    encompass any property or thing which constitutes the subject matter of

    the dispute. Learned Counsel submits that the correct legal position,

    which is also supported by the decision of the Hon’ble Delhi High Court in

    Reliance Industries Ltd. (supra), is that where the documents or records

    in question relate to the subject matter of the dispute in arbitration, an

    order directing their production and inspection can competently be passed

    under Section 17 of the Act. It is only where the documents sought do not

    relate to the subject matter of the dispute that recourse to Section 19 of

    the Act would be appropriate. In the present case, the learned Sole

    Arbitrator has, after a thorough examination of the contractual documents,

    arrived at a finding that the running account bills, books of accounts, and

    revenue records sought by the respondents are directly referable to and

    form part of the subject matter of the arbitration. Learned Counsel also
    11

    places reliance upon the definition of “subject matter” as contained in

    Black’s Law Dictionary in support of the submission that the documents

    sought fall squarely within the ambit of the said definition and that the

    impugned order is therefore well within the jurisdiction conferred upon the

    learned Sole Arbitrator under Section 17 of the Act.

    21. Learned Counsel for the Respondent also sought to distinguish the

    judgments cited by the Appellant. It is accordingly prayed that the present

    appeal be dismissed with costs.

    Legal Analysis

    22. This Court has heard the arguments advanced by the learned Senior

    Counsel for the appellant and learned counsel for the respondent,

    examined the documents placed on record, and perused the judgments

    cited at the Bar.

    23. The present appeal under Section 37(2)(b) of the Arbitration and

    Conciliation Act, 1996 arises out of the order dated 10.06.2025 passed by

    the learned Sole Arbitrator, whereby an application filed by the

    respondents under Section 17 of the Arbitration and Conciliation Act,

    1996 was allowed, directing the appellants to disclose the particulars of

    running account bills raised against M/s. Rapiscan Systems Private

    Limited, to produce their books of accounts, profit and loss statements and

    balance sheets, and to submit duly validated records relating to the total

    revenue generated under the sub-contract dated 16.09.2021.

    24. The main dispute between the parties centres around the interpretation

    and enforceability of two agreements dated 06.09.2021, namely a Joint

    Venture Agreement and a Supplementary Agreement, executed between

    the appellants and the respondents. The respondents contend that
    12

    pursuant to the said agreements, they rendered marketing and

    consultancy services which resulted in the award of the sub-contract by

    M/s. Rapiscan Systems Private Limited in favour of the appellants,

    entitling them to receive 10% of the value of each running account bill. The

    appellants dispute the enforceability of both agreements, contending that

    the Joint Venture Agreement was never acted upon and was consciously

    abandoned, that the Supplementary Agreement was void for want of prior

    written consent of M/s. Rapiscan Systems Private Limited as required

    under Clause 17 of the sub-contract, and that the documents sought

    pertain exclusively the contractual relationship between the appellants and

    M/s. Rapiscan System Private Limited, a third party. It is therefore

    contended that the impugned order directing production of such

    documents has been passed without jurisdiction and in excess of the

    powers conferred under Section 17 of the Act.

    25. Before analysing the core issue involved in the present appeal, it is

    necessary to set out Section 17(1) of the Act:

    Interim measures ordered by arbitral tribunal.

    (1) A party may, during the arbitral proceedings [***], apply to the
    arbitral tribunal-

    (i) for the appointment of a guardian for a minor or person of
    unsound mind for the purposes of arbitral proceedings; or

    (ii) for an interim measure of protection in respect of any of the
    following matters, namely:-

    (a) the preservation, interim custody or sale of any goods which are
    the subject-matter of the arbitration agreement;

    (b) securing the amount in dispute in the arbitration;

    (c) the detention, preservation or inspection of any property or thing
    which is the subject-matter of the dispute in arbitration, or as to
    which any question may arise therein and authorising for any of
    the aforesaid purposes any person to enter upon any land or
    building in the possession of any party, or authorising any
    13

    samples to be taken, or any observation to be made, or
    experiment to be tried, which may be necessary or expedient for
    the purpose of obtaining full information or evidence;

    (d) interim injunction or the appointment of a receiver;

    (e) such other interim measure of protection as may appear to the
    arbitral tribunal to be just and convenient, and the arbitral
    tribunal shall have the same power for making orders, as the
    court has for the purpose of, and in relation to, any proceedings
    before it.”

    26. Two features of this provision merit immediate attention. First, the powers

    conferred are interim and protective in nature, designed to preserve the

    status quo pending the conclusion of the arbitral proceedings. Secondly,

    the provision is confined to property or things which are the subject matter

    of dispute, or as to which a question may arise therein. On a plain reading,

    Section 17 does not contemplate or authorise an Arbitral Tribunal to

    compel a party to produce documents as evidence in support of the other

    side’s claim. Matters relating to procedure and evidence are governed by

    Section 19 of the Act. This distinction between preservation of subject

    matter and compelled production of evidence is fundamental and goes to

    the root of the jurisdictional question.

    27. The scope of Section 17 was examined by the Hon’ble Delhi High Court in

    Reliance Industries Ltd. (supra), a decision relied upon by both parties.

    That judgment draws a clear distinction between (a) orders preserving and

    protecting documents that constitute the subject matter of the dispute

    itself, which fall within the ambit of Section 17, and (b) orders requiring a

    party to affirmatively produce or disclose documents to enable the other

    side to establish or quantify its claim, which are, in substance, orders for

    discovery and production of evidence properly governed by Section 19 of

    the Act. It is the character and purpose of the order, not the label attached
    14

    to it, that determines which provision applies. This Court respectfully

    adopts this position.

    28. Learned Senior Counsel for the appellants has additionally submitted that

    Section 17(1)(ii)(c) is couched in language substantially similar to Order

    XXXIX Rule 7 of the Code of Civil Procedure, 1908, and that the principles

    governing that provision furnish a useful interpretative aid, as recognised

    in Augmont Gold Private Limited (Supra). It has been submitted, relying

    on Ramswarup (supra), that Order XXXIX Rule 7 authorises detention,

    preservation and inspection only of property which is the subject matter of

    the suit, and does not extend to documents which are merely of

    evidentiary value. This Court finds the said analogy to be instructive: as it

    reinforces, from a parallel statutory provision, the very distinction already

    drawn in Reliance Industries Ltd. (supra) between preservation of subject

    matter and production of evidence.

    29. It has further been submitted, relying upon Institution of Engineers

    (India) (Supra), and The Owners and Parties Interested in the Vessel

    ‘M.V. Baltic Confidence‘ (Supra), that even where a question may arise

    relating to the suit, no commission or order can be issued for the purpose

    of collecting evidence through discovery. This Court accepts that this

    principle applies with equal, if not greater, force to an Arbitral Tribunal

    exercising an analogous power under Section 17(1)(ii)(c) of the Act: a

    provision permitting inspection of the subject matter cannot be stretched

    into a general discovery mechanism, whether the forum is a civil court

    acting under Order XXXIX Rule 7 of the Code of Civil Procedure, 1908 or

    an Arbitral Tribunal acting under Section 17 of the Act.
    15

    30. The learned Senior Counsel for the appellants has also placed reliance

    upon Rajesh Bhatia (supra), which reinforces that the powers of an

    Arbitral Tribunal under Section 17 are analogous to those of a Court under

    Section 9, and are confined to granting interim measures of protection. An

    Arbitral Tribunal, being a private adjudicatory forum, does not possess the

    coercive powers of a civil court to compel production of documents or

    leading of evidence; the only consequence of a party’s failure to produce

    documents is the drawing of an adverse inference, a principle also reflected

    in Krishan Dayal (Supra), and consistent with Section 114(g) of the Indian

    Evidence Act, 1872. It would be incongruous if an Arbitral Tribunal were

    held to possess wider powers to compel production of evidence than a civil

    court itself.

    31. Reliance has also been placed upon Padam Sen and Another (Supra), for

    the proposition that the power judicial or quasi judicial forum to direct

    production or collection of evidence cannot be assumed as an incident of a

    general or residuary power where the statute does not specifically confer

    such authority. The said decision lends further support to a narrow,

    textual construction of Section 17(1)(ii)(c). The power of “detention,

    preservation or inspection” of the subject matter cannot, in the absence of

    an express statutory sanction, be read to include a free-standing power to

    direct affirmative disclosure, validation and production of financial records

    such as books of accounts, profit and loss statements and balance sheets,

    which are, at best, evidentiary material and not themselves the “property

    or thing” in dispute.

    32. In this background, it is relevant to examine the operative portion of the

    impugned order. Learned Sole Arbitrator recorded a prima facie
    16

    satisfaction in paragraphs 19 to 21 of the impugned order, holding, in

    effect, that having regard to the pleadings and the Supplementary

    Agreement, an interim measure directing preservation and inspection of

    the running account bills submitted by the appellants to M/s. Rapiscan

    Systems Private Limited, being prima facie the subject matter of dispute,

    would be just and convenient, and accordingly the application under

    Section 17 of the Act was allowed.

    33. Pursuant to that finding, the learned Sole Arbitrator passed operative

    directions in paragraph 22 requiring disclosure of particulars of the

    running account bills and their clearance status; disclosure of books of

    accounts, profit and loss statements and balance sheets; validation of all

    records relating to the total revenue generated under the sub-contract; to

    submit such validated records before the learned Arbitral Tribunal with

    copies to the respondents; and completion of “inspection and discovery” by

    23.06.2025.

    34. A plain reading of these operative directions reveals four distinct directions,

    disclosure of RA bill particulars, disclosure of accounting records,

    validation revenue records, and submission/forwarding of the same with a

    further direction for “discovery” requiring the appellants to produce,

    disclose, validate and furnish the entire array of financial and accounting

    documents pertaining to their sub-contractual dealings with M/s.

    Rapiscan Systems Private Limited.

    35. Upon a careful analysis of the impugned order in light of the statutory

    provisions and the judicial precedents discussed above, including the line

    of authorities of the Code interpreting Order XXXIX Rule 7 and the

    principle laid down in Padam Sen (Supra) , this Court is of the opinion
    17

    that the impugned order suffers from a fundamental legal infirmity in its

    operative directions, even though the prima facie satisfaction recorded in

    the reasoning portion is, to a limited extent, legally defensible.

    36. The prima facie finding that the RA bills form part of the subject matter of

    the present arbitration is a finding of fact arrived at after examining the

    pleadings and the Supplementary Agreement, which on its face ties the

    respondents’ remuneration to the RA bills and incorporates the Joint

    Venture Agreement by reference. This Court, while exercising limited

    appellate jurisdiction under Section 37, is not required to interfere with

    such prima facie finding, particularly since it rests on a plausible reading

    of the contractual documents.

    37. The critical difficulty, however, arises from the operative directions

    themselves. An order restraining the appellants from destroying, damaging

    or disposing of the RA bills pending final adjudication would constitute a

    legitimate exercise of Section 17(1)(ii), falling within detention and

    preservation of the subject matter of the dispute, and would be consistent

    with an analogy drawn from the Order XXXIX Rule 7 of the CPC, 1908 as

    pressed by the appellants. However, a direction to affirmatively disclose the

    particulars of the running account bills, to disclose books of accounts and

    balance sheets, validate revenue records, and submit and forward the

    same is a different matter altogether. Such directions do not preserve the

    subject matter of the dispute; rather they compel production and

    disclosure of evidentiary material to enable the respondents to establish

    and quantify their claim, precisely the species of order that Reliance

    Industries Ltd (Supra)., Rajesh Bhatia (Supra), Institution of Engineers

    (supra), and the M.V. Baltic Confidence (Supra) line of authority hold falls
    18

    outside the ambit of Section 17 (and outside Order XXXIX Rule 7 on the

    civil side), and within the domain of Section 19 of the Act.

    38. This Court also finds a telling internal inconsistency within the impugned

    order. The reasoning portion employs the language of “preservation and

    inspection,” yet the operative directions go well beyond that, extending to

    disclosure, validation, submission and “discovery.” The operative directions

    thus exceed not only what is contemplated in the reasoning portion of the

    impugned order but also the jurisdiction conferred upon the learned

    Arbitrator under Section 17 of the Act, and are, to that extent liable to be

    set aside.

    39. There is also merit in the submission that, in the context of a money claim,

    mere quantification evidence does not constitute the “subject matter of the

    dispute” so as to attract Section 17 of the Act. The RA bills are relied upon

    principally for the purpose of computing the respondents’ alleged 10%

    share, and to that extent function as evidence bearing on quantum rather

    than as the res of the dispute. As submitted by the appellants relying on

    Padam Sen (Supra), the books of accounts, profit and loss statements and

    balance sheets sought cannot in any event be construed as “property or

    thing” in dispute; treating quantification material as invariably

    constituting the “subject matter” would risk converting Section 17 into a

    general discovery provision in every money claim, a construction which

    this Court is not inclined to adopt.

    40. The respondents’ argument that Clause 5.2 of the JV Agreement creates a

    specific contractual right of inspection, and that the impugned order

    merely enforces it, does not assist them. Any such right, if it exists, must

    be asserted as part of the substantive claim or pursued through interim
    19

    relief framed as an injunction against destruction of records, not through a

    direction compelling production. The sweeping directions in paragraph 22

    travel well beyond the enforcement of any contractual inspection right and

    constitute a general direction for disclosure and production of evidence,

    which falls beyond the scope of Section 17, of the Act.

    41. The appellants have further submitted, by reference to Section 27 of the

    Act and the safeguard contained therein before a Court renders assistance

    in taking evidence, that they were denied an equivalent opportunity to

    contest the production of these documents before the impugned order

    came to be passed. This Court finds force in the submission to the extent

    that it reinforces, rather than displaces, the conclusion already arrived at.

    Where production or discovery of documents is genuinely required for the

    purpose of the arbitration, the appropriate course is for the respondents to

    proceed under Section 19, where such safeguards and procedural

    regularity are built into the process, and not under Section 17.

    42. This Court is conscious that its jurisdiction under Section 37(2)(b) is

    limited, and it is neither required to re-appreciate facts nor to substitute

    its own prima facie satisfaction for that of the Tribunal. The challenge in

    the present appeal is confined to the narrow question of law, as to whether

    the operative directions travel beyond the jurisdictional limits of Section 17,

    and it is on this ground alone that interference with the impugned order is

    warranted.

    43. In view of the foregoing analysis, and having considered the additional

    authorities cited on behalf of the appellants, this Court is of the considered

    opinion that the impugned order dated 10.06.2025 deserves to be set aside

    to the extent indicated. The directions in paragraph 22 of the impugned
    20

    order insofar as they direct affirmative disclosure of RA bill particulars,

    disclosure of books of accounts, profit and loss statements and balance

    sheets, validation and submission of revenue records, and forwarding of

    copies to the respondents, are beyond the scope of Section 17 and are

    accordingly set aside. If the respondents seek production and inspection of

    such documents for the purposes of the arbitral proceedings, they shall be

    at liberty to take appropriate steps before the learned Sole Arbitrator in

    accordance with law.

    44. The appeal is accordingly allowed and disposed of.

    45. It is clarified that any expression of opinion or observation made in this

    judgment is confined to the determination of the present appeal arising out

    of an interim measure and shall not be construed as an expression of

    opinion on the merits of the disputes pending adjudication before the

    learned Sole Arbitrator, who shall adjudicate the same independently and

    uninfluenced by any observation made herein.

    46. All pending application accordingly disposed of.

    (GAURANG KANTH, J.)

    SAKIL AMED P.A



    Source link

    LEAVE A REPLY

    Please enter your comment!
    Please enter your name here