Dlf Homes Panchkula Pvt Ltd vs Surinder Pal Singh & Ors on 24 July, 2026

    0
    15
    ADVERTISEMENT

    Delhi High Court

    Dlf Homes Panchkula Pvt Ltd vs Surinder Pal Singh & Ors on 24 July, 2026

                    *         IN THE HIGH COURT OF DELHI AT NEW DELHI
                                                                  Reserved on: 13.07.2026
                                                              Date of Decision: 24.07.2026
    
                    +         CM(M) 1248/2022, CM APPL. 49631/2022, CM APPL.
                              20963/2025, CM APPL. 20964/2025 & CM APPL. 29491/2026
                              DLF HOMES PANCHKULA PVT LTD                     .....Petitioner
                                                Through:    Mr. Pinaki Misra, Sr. Adv. with
                                                            Ms. Seema Sundd, Mr. Pravin
                                                            Bahadur and Mr. Prabhat
                                                            Ranjan, Advs.
    
                                                versus
    
                              SURINDER PAL SINGH & ORS.             .....Respondents
                                            Through: Mr. Sudhir Kathpalia, Adv.
                                                     Mr. Narender Kumar Sharma
                                                     and Ms. Suman Sharma, Advs.
                                                     for R-2 & 68. (through VC)
    
                              CORAM:
                              HON'BLE MR. JUSTICE AJAY DIGPAUL
                                              JUDGMENT
    

    %

    Factual Matrix

    SPONSORED

    1. The present petition under Article 227 of the Constitution of
    India has been filed by DLF Homes Panchkula Private Limited
    assailing the order dated 12.10.2022 passed by the learned National
    Consumer Disputes Redressal Commission1 in I.A. No. 4407/2022 in
    Consumer Complaint No. 1962/2017. By the impugned order, the
    learned NCDRC dismissed the application filed by the petitioner

    1
    Hereinafter “NCDRC”

    Signature Not Verified
    Signed By:ANKITA CM(M)
    RAI 1248/2022 Page 1 of 44
    Signing Date:25.07.2026
    16:08:56

    questioning the maintainability of the consumer complaint as a
    representative complaint under Section 12(1)(c) of the Consumer
    Protection Act, 19862 (Presently Section 35(1)(c) of the Consumer
    Protection Act, 20193.

    2. The dispute arises out of a residential project known as “The
    Valley”, situated at Panchkula, Haryana, and developed by the
    petitioner. The project was launched in the year 2010 and comprises
    1,799 residential units. Upon obtaining the requisite occupation
    certificate, possession of the units was offered to the allottees during
    2016 and 2017 and that possession of 1,733 units had been taken by
    the respective allottees.

    3. On 12.07.2017, three allottees instituted Consumer Complaint
    No. 1962/2017 before the learned NCDRC against the petitioner. The
    complaint was accompanied by I.A. 10286/2017 under Section
    12(1)(c) of the 1986 Act read with Order I Rule 8 of the Code of Civil
    Procedure
    , 19084, seeking permission for joint petition as the
    Complainants have joint interest and for other allottees of the project
    “The Valley”. The prayer sought in this application is reproduced as
    under:

    “a. Allow the present application in the interest of justice as the
    complainants have similar interest in the present proceeding and
    seeking relief of similar nature and other allotees of “THE
    VALLEY PANCHKULA PROJECT (Haryana)”;

    b. Allow publication of the notice of the matter to all the allottees
    of the project “THE VALLEY PANCHKULA PROJECT
    (Haryana)” and impleading them as parties seeking reliefs of
    similar nature before this Hon’ble Commission;”

    2

    Hereinafter “1986 Act”

    3

    Hereinafter “2019 Act”

    4

    Hereinafter “CPC

    Signature Not Verified
    Signed By:ANKITA CM(M)
    RAI 1248/2022 Page 2 of 44
    Signing Date:25.07.2026
    16:08:56

    4. The Consumer Complaint No. 1962/2017 alleged, inter alia,
    delay in completion of the project and delivery of possession, and
    questioned certain demands raised by the petitioner. The complainants
    sought, amongst other reliefs, delivery of physical and legal
    possession of the respective units in accordance with the apartment
    buyers’ agreements, compensation for delayed possession, issuance of
    the occupation certificate and other requisite approvals; setting aside
    of the demand raised towards increase in the saleable area,
    compensation for the alleged deficiency in service, litigation costs;
    and consequential reliefs. The application under Section 12(1)(c)
    proceeded on the assertion that these grievances and reliefs were
    common to the allottees sought to be represented.

    5. The petitioner filed its written version to the consumer
    complaint as well as a reply opposing the application under Section
    12(1)(c)
    . The petitioner disputed the allegations of deficiency in
    service and, amongst other objections, questioned the existence of a
    common interest amongst all the allottees and the maintainability of
    the complaint in a representative capacity.

    6. The learned NCDRC vide order dated 23.05.2018 allowed the
    application under Section 12(1)(c) and permitted Consumer
    Complaint No. 1962/2017 to proceed as a representative complaint.
    Consequential directions were issued for publication of notice in terms
    of the procedure applicable to representative proceedings. The
    relevant portion from the said order passed by the NCDRC is
    reproduced as under:

    “5. On careful perusal of the complaint, it transpires that
    Brig. Beant Parmar and two others have filed the instant complaint
    on behalf of themselves as also other similarly placed consumers
    who had booked apartments in the subject project having same
    Signature Not Verified
    Signed By:ANKITA CM(M)
    RAI 1248/2022 Page 3 of 44
    Signing Date:25.07.2026
    16:08:56
    interest and they have also sought relief on behalf of all such
    consumers so interested in the outcome of the complaint. Perusal
    of the prayer clause of the complaint would show that relief has
    also been sought not only on behalf of the complainants who are
    party to the complaint but on behalf of other similarly placed
    consumers having same interest in the outcome of the complaint.
    Therefore, in my view, requirement of Section 12 (1) ( c) of the
    Act are fulfilled in this case and this is a fit case for grant of
    permission under section 12 (1) ( c) of the Act.

    6. Counsel for the opposite party developer has contended
    that application is liable to be dismissed as there is no commonality
    of interest amongst the complainants and other allottees of the
    project. Expanding on the argument, learned counsel has
    submitted that bare reading of the complaint would demonstrate
    that complainants do not have commonality of interest with all
    other consumers who had booked apartments in the subject
    project. It is submitted that there are two different sets of allottees
    in the project (a) Non Government Employees and (b) Government
    Employees, the difference being that government employees as per
    the allotment agreement are entitled to additional rebate of 5% on
    basic sale price. I do not find merit in this contention. Difference
    in price payable by the respective consumers by no stretch of
    imagination would make them two different classes of consumers
    so far as relief sought in the complaint is concerned. It is further
    submitted that large number of allottes in the project have filed
    complaints in the State Commission. Therefore, they do not stand
    on same footing as that of three complainants. The submissions of
    learned counsel for the opposite parties is misconceived because
    bare reading of Section 12 (1) ( c) of the Act would show that one
    or more consumers can file the consumer complaint subject to
    fulfilment of requisite condition on behalf of or for the benefit of
    all the consumers so interested. If some of the consumers have
    opted to file independent complaints, it would not make other
    consumers who are not arrayed as complainants not so interested in
    the outcome of the complaint. Similarly, it is contended that about
    770 allottees in the project have already taken over possession and
    conveyance deeds in favour of 160 allottees out of them have been
    executed. If at all it is accepted, then all other similarly placed
    allottees would have some interest in the outcome of the
    complaint. Therefore, on their behalf class action complaint can be
    filed. Thus, I do not find merit in the objection of the opposite
    party. In view of the above, I allow the application under section
    12 (1)
    ( c) of the Act and permit the complainants to proceed with
    the complaint as a class action.

    7. In view of the mandate of Section 13 (6) of the Act, I direct
    that the public notice of this complaint be issued under Order 1
    Rule 8 C.P.C
    in the newspapers “Times of India” (English edition)

    Signature Not Verified
    Signed By:ANKITA CM(M)
    RAI 1248/2022 Page 4 of 44
    Signing Date:25.07.2026
    16:08:56
    and “Navbharat Times” (Hindi Edition). Complainants to take
    steps for publication.

    .8. Complaint is admitted. Opposite Party to file written
    statement within 30 days from today with advance copy to the
    complainants.

    List on 23.10.2018. Rejoinder, if any, be filed in the
    meanwhile.”

    7. On 28.05.2018, the learned NCDRC disposed of another
    representative complaint pertaining to the same project, being
    Consumer Complaint No. 82/2017, titled Surinder Pal Singh and 56
    Others v. DLF Homes Panchkula Private Limited & Anr.. While

    doing so, the complainants therein were granted liberty to seek
    impleadment in Consumer Complaint No. 1962/2017 or to avail such
    other remedies as were available to them in law. The operative portion
    of the order dated 28.05.2018 in Consumer Complaint No. 82/2017 is
    reproduced here for reference:

    “10. In view of the discussion above, I am of the opinion that this
    is not a fit case for grant of permission under section 12 (1) ( c) of
    the Act. Application is accordingly dismissed. As the complainants
    have refused to amend the complaint to restrict it only to one class
    of the complainants seeking similar relief, the complaint is
    dismissed as not maintainable because of misjoinder of parties and
    causes of action. It is pertinent to note that permission under
    section 12 (1) (c) of the Act has already been granted to the
    complainants in Brig. Beant Parmar & Anr. Vs. DLF Homes
    Panchkula Pvt. Ltd.
    in Consumer Complaint No. 1962 of 2017
    relating to the same project. Therefore, it is clarified that
    complainants in this case shall be at liberty to get impleaded in
    Consumer Complaint No. 1962 of 2017, if they so desire. or avail
    of the legal remedy available under law.”

    8. Thereafter in the proceedings of Complaint No. 1962/2017, the
    petitioner filed Review Application No. 169/2018 on 05.06.2018,
    seeking review of the order dated 23.05.2018. The review application
    was dismissed by the learned NCDRC on 08.06.2018, upon finding no
    error apparent on the face of the record.

    Signature Not Verified
    Signed By:ANKITA CM(M)
    RAI 1248/2022 Page 5 of 44
    Signing Date:25.07.2026
    16:08:56

    9. The petitioner also challenged the order
    dated 23.05.2018 before this Court in CM(M) 683/2018. The Court
    vide order dated 16.07.2018, stayed the operation of the order
    dated 23.05.2018. The relevant portion of the order passed by this
    Court is reproduced as under:

    “The matter is indicated to be listed for 24.09.2018 and
    taken up on CM APPL. 27639/2018, an application filed on behalf
    of the petitioner seeking to bring on record subsequent
    developments apart from inter alia seeking a stay of the
    proceedings pending before the National Consumer Disputes
    Redressal Commission in CC No.1962/2017 submitting to the
    effect that the Review Petition No.169/18 filed by the petitioner
    seeking a review of the order dated 23.05.2018 pursuant to
    proceedings dated 31.05.2018 of this Court, has already been
    dismissed.

    Notice of the petition and of CM APPL. 27639/2018 be
    issued to the respondent nos.2 to 4 on taking of steps by the
    petitioner, process returnable on 24.09.2018.

    In the meantime, the operation of the order dated
    23.05.2018 of the National Consumer Disputes Redressal
    Commission is stayed.

    Copy of the order be given Dasti, as prayed.”

    10. The complainants thereafter approached the Hon’ble Supreme
    Court against the order dated 16.07.2018 through SLP (Civil) Diary
    No. 4883/2019. The Hon’ble Supreme Court vide order
    dated 15.02.2019, vacated the interim stay granted by this Court. The
    relevant portion of the order passed by the Supreme Court is
    reproduced for reference:

    “In the present matter, by order dated 23.05.2018, the
    National Consumer Disputes Redressal Commission accepted the
    submission of the present petitioners and granted them permission
    to proceed with the complaint as a class action and also directed
    that public notice be issued under Order 1 Rule 8 of the Code of
    Civil Procedure
    , 1908, in the newspapers “Times of India”

    (English Edition) and “Navbharat Times” (Hindi Edition). The
    matter was directed to be listed on 23.10.2018.

    Respondent no.1 thereafter carried the matter by way of a
    petition under Article 227 of the Constitution of India in the High
    Court of Delhi at New Delhi. The High Court vide its order dated
    Signature Not Verified
    Signed By:ANKITA CM(M)
    RAI 1248/2022 Page 6 of 44
    Signing Date:25.07.2026
    16:08:56
    16.07.2018 stayed the operation of the order passed by the National
    Commission, which order is presently under challenge.

    The submission of the petitioners is that though the order
    was passed on 16.07.2018, a copy of the order was served on them
    sometime on 24.08.2018 by which time the advertisements were
    already published in the newspaper.

    Issue notice.

    Pending further consideration, we stay operation of the
    order dated 16.07.2018 passed by the High Court, as a result of
    which the order dated 23.05.2018 passed by the National
    Commission shall become fully operative.

    We direct the parties to appear before the National
    Commission on 19.02.2019 i.e. the date on which the matter is
    listed.

    Let further proceedings be taken to the logical conclusion
    by the National Commission. In case, for any reason, the present
    petitioners wish to withdraw from the proceedings, appropriate
    number of applicant(s) can be substituted in their place and the
    matter shall be proceeded on merits. Considering the fact situation
    in the present matter, we request the National Commission to
    conclude the proceedings as expeditiously as possible.”

    11. During the pendency of Consumer Complaint No. 1962/2017,
    the three original complainants arrived at settlements with the
    petitioner. By an order dated 30.05.2019, their names were deleted
    from the array of parties.

    12. By the same order dated 30.05.2019, the learned NCDRC
    allowed several applications filed by other allottees seeking
    impleadment in the Consumer Complaint No. 1962/2017. The
    impleadment was made subject to the applicants satisfying the certain
    conditions and the substituted complainants were also directed to file
    an amended memo of parties. The relevant portion of the order is
    reproduced as under:

    “The applicants claim to be allottees in the project to which this
    complaint pertains. They are impleaded as parties to this complaint
    provided that (i) they are interested in all the reliefs sought in this
    complaint (ii) they have no other grievance against the OP (iii)
    their allotments have not been cancelled and (iv) they have already
    not approached either this Commission or any other Court/Forum
    Signature Not Verified
    Signed By:ANKITA CM(M)
    RAI 1248/2022 Page 7 of 44
    Signing Date:25.07.2026
    16:08:56
    for the redressal of their grievances. The applications stand
    disposed of.”

    13. CM(M) 683/2018 was thereafter dismissed as withdrawn by this
    Court on 13.08.2019. Consequent thereto, the proceedings before the
    Hon’ble Supreme Court arising from the interim order passed in that
    petition were also disposed of as having become infructuous.

    14. On 08.11.2019, further applications for impleadment were
    allowed by the learned NCDRC in terms of the conditions contained
    in the order dated 30.05.2019.

    15. The proceedings thereafter continued before the learned
    NCDRC and, on 19.05.2022, the petitioner filed I.A. No. 4407/2022
    questioning the maintainability of Consumer Complaint No.
    1962/2017 in the form in which it was then being prosecuted. In
    support of the application, the petitioner relied upon the decision of
    the Hon’ble Supreme Court in Brigade Enterprises Limited v. Anil
    Kumar Virmani & Ors.5
    , wherein it was held that sameness of interest
    constitutes the sine qua non for maintaining a representative complaint
    under Section 12(1)(c) of the 1986 Act.
    Reliance was also placed upon
    the decision of this Court in Lucina Land Development Ltd. v. Union
    of India & Ors.6
    , which reiterated the necessity of establishing
    sameness of interest amongst the consumers sought to be represented.
    On this basis, the petitioner contended that the subsequently
    impleaded complainants did not constitute a homogeneous class, that
    their respective factual positions were materially different, and that the
    complaint, in light of the aforesaid decisions, was not maintainable

    5
    (2022) 4 SCC 138
    6
    2022 SCC OnLine Del 1274
    Signature Not Verified
    Signed By:ANKITA CM(M)
    RAI 1248/2022 Page 8 of 44
    Signing Date:25.07.2026
    16:08:56
    under Section 12(1)(c) and was liable to be dismissed at the threshold.
    The prayer sought in this application is reproduced as under:

    “i. to hear and determine the admissibility and maintainability of
    the present Complaint before proceeding further with the matter;
    ii. to hold that there is no sameness of interest in the class sought to
    be represented, or even amongst the 70 complainants arrayed as
    parties to the present complaint;

    iii. to hold that the present complaint cannot be allowed as a class
    action complaint under section 12(1)(c), on account of lack of
    sameness of interest;

    iv. to hold that the pecuniary value of individual complainants or
    even the average value of the apartment is below the pecuniary
    jurisdiction of this Hon’ble Commission;

    v. to dismiss the present complaint for lack of pecuniary
    jurisdiction; and/ or
    vi. pass any such other order/orders as this Hon’ble Commission
    may deem fit and proper in the facts and circumstances of the
    present case.”

    16. In particular, the petitioner sought to distinguish between
    allottees who had already taken possession, subsequent purchasers,
    persons in whose cases possession had been offered without delay,
    persons who had entered into settlements with the petitioner, persons
    who had accepted payments or compensation, persons who had
    executed conveyance deeds, persons who had sold or let out their units
    and persons who had already pursued proceedings before other
    consumer forums. On that basis, it was contended that the substituted
    complainants neither possessed the same interest nor remained
    interested in all the reliefs originally sought in the complaint.

    17. The learned NCDRC on 23.05.2022, directed the complainants
    to file a reply to I.A. No. 4407/2022. They were also directed to place
    on record a chart containing complainant-wise particulars with
    reference to the objections raised by the petitioner. After the reply was
    filed, the petitioner was granted an opportunity, by an order
    dated 06.07.2022, to file a rejoinder.

    Signature Not Verified
    Signed By:ANKITA CM(M)
    RAI 1248/2022 Page 9 of 44
    Signing Date:25.07.2026
    16:08:56

    18. During the subsequent hearing, the complainants stated that
    they did not propose to press all the reliefs originally sought in
    Consumer Complaint No. 1962/2017 and that they would confine their
    claims to the issue of interest on delayed possession and excess
    saleable area. The said statement was recorded by the learned NCDRC
    in its order dated 27.07.2022.

    19. Pursuant to the earlier directions of the learned NCDRC, the
    complainants filed a chart dated 13.08.2022, setting out the particulars
    and status of the respective complainants.

    20. Arguments on I.A. No. 4407/2022 were heard by the learned
    NCDRC and vide impugned order dated 12.10.2022, the learned
    NCDRC dismissed I.A. No. 4407/2022. The learned NCDRC
    recorded that the three original complainants had withdrawn from the
    proceedings after settling their disputes and that several other allottees
    had thereafter been impleaded. It further recorded that, although 85
    persons had been impleaded at one stage, 71 complainants remained
    before it.

    21. The learned NCDRC also recorded that possession had been
    delivered to and accepted by the complainants then before it. It,
    however, held that the surviving claims for compensation on account
    of delayed possession and in relation to the increased saleable area
    disclosed sufficient sameness of interest to permit the complaint to
    continue as a representative proceeding.

    22. In relation to persons who had transferred their units after
    seeking impleadment, the learned NCDRC observed that their rights
    were required to be considered with reference to the date on which
    they had joined the proceedings and that a subsequent transfer would
    not, by itself, defeat the claim. As regards persons who had entered
    Signature Not Verified
    Signed By:ANKITA CM(M)
    RAI 1248/2022 Page 10 of 44
    Signing Date:25.07.2026
    16:08:56
    into settlements, the learned NCDRC observed that such persons
    could not reopen disputes which had already been settled.

    23. The learned NCDRC further observed that, even if some of the
    complainants did not fall within the definition of “consumer”, they
    could not be denied the benefit of a judgment passed in a
    representative complaint. Having rejected the petitioner’s objection to
    maintainability, the learned NCDRC listed the consumer complaint
    for final hearing.

    24. Aggrieved by the order dated 12.10.2022, the petitioner
    instituted the present petition. When the petition was taken up
    on 20.12.2022, Mr. Pinaki Misra, learned Senior Counsel for the
    petitioner submitted that there was no commonality or sameness of
    relief amongst the respondents; that possession of the units had been
    received by the respondents; that the surviving claims would require
    individual examination; and that the reliefs originally claimed could
    not have been given up merely on the basis of a statement made by
    counsel in the representative proceedings.

    25. This Court also noticed the observation of the learned NCDRC
    that even persons who did not fall within the definition of “consumer”
    could derive the benefit of a judgment passed in the representative
    complaint. A prima facie view was expressed that the said
    observations required consideration and this Court requested the
    learned NCDRC to defer the final hearing to a date beyond the next
    date fixed by this Court.

    26. The order dated 20.12.2022 was challenged by some of the
    respondents before the Hon’ble Supreme Court in SLP(C) No.
    8368/2023. On 04.05.2023, the Hon’ble Supreme Court issued notice

    Signature Not Verified
    Signed By:ANKITA CM(M)
    RAI 1248/2022 Page 11 of 44
    Signing Date:25.07.2026
    16:08:56
    and stayed the operation of the order dated 20.12.2022 until further
    orders.

    27. The SLP was thereafter taken up on 07.11.2023. The Supreme
    Court observed that the proceedings before it arose out of an
    interlocutory order and disposed of the SLP with a request to this
    Court to decide the present petition expeditiously, preferably within
    six months. The parties were directed not to seek adjournments. The
    Hon’ble Supreme Court further requested the learned NCDRC not to
    proceed further with Consumer Complaint No. 1962/2017 until the
    present petition was decided by this Court.

    28. It is in the aforesaid background that the challenge to the order
    dated 12.10.2022 passed by the learned NCDRC falls for
    consideration in the present petition.

    Submissions on behalf of the petitioner

    29. Mr. Pinaki Misra, learned Senior Counsel submits that the very
    foundation of a representative complaint under Section 12(1)(c) of the
    1986 Act is the existence of numerous consumers having the same
    interest. The expression “same interest”, according to him, is not a
    matter of form, nor can it be inferred merely because all the persons
    concerned had purchased units in the same project or seek some form
    of monetary compensation from the same developer. The requirement
    is substantive and mandates that the consumers represented in the
    proceedings must constitute an identifiable and homogeneous class
    having the same grievance arising from the same deficiency in service.

    30. Learned Senior Counsel points out that, though 85 allottees had
    initially been impleaded in Consumer Complaint No. 1962/2017, only
    49 of them presently remain, the disputes of the others having been
    Signature Not Verified
    Signed By:ANKITA CM(M)
    RAI 1248/2022 Page 12 of 44
    Signing Date:25.07.2026
    16:08:56
    settled during the pendency of the proceedings. He submits that the
    progressive alteration in the composition of the complainant body is
    significant, as the complaint is no longer being prosecuted by the three
    original complainants who had framed its pleadings and reliefs. The
    allottees subsequently brought on record have not amended the
    complaint to disclose how their respective grievances are identical or
    how they remain interested in all the reliefs on the basis of which
    permission under Section 12(1)(c) was originally granted.

    31. Mr. Misra submits that the surviving complainants fall within
    several distinct categories and cannot be treated as members of one
    homogeneous class. Some allottees received possession after varying
    periods of delay and continue to retain their units; some accepted
    delay compensation offered by the petitioner; some are subsequent
    purchasers who acquired their units after possession had already been
    offered to the original allottees; some have executed conveyance
    deeds; some have sold or otherwise transferred their units; while
    others had either entered into settlements or pursued proceedings
    before other forums. Each of these circumstances, according to him,
    bears directly upon the existence and extent of the individual allottee’s
    grievance and entitlement, if any, to compensation. The determination
    of the claim would, therefore, necessarily require an allottee-wise
    examination of the date of allotment, contractual terms, date of offer
    and acceptance of possession, period of delay, payments made,
    compensation accepted, subsequent transfer and prior settlement or
    adjudication.

    32. It is submitted that a common circumstance capable of giving
    rise to similar causes of action does not, by itself, establish sameness
    of interest. The mere fact that several allottees may allege delay in
    Signature Not Verified
    Signed By:ANKITA CM(M)
    RAI 1248/2022 Page 13 of 44
    Signing Date:25.07.2026
    16:08:56
    delivery of possession cannot place them in the same class where the
    periods of delay differ materially and their subsequent conduct and
    legal position are distinct. Equally, the circumstance that the surviving
    complainants may ultimately seek monetary compensation cannot cure
    the absence of identity in the underlying grievances. According to
    learned Senior Counsel, the learned NCDRC has effectively treated a
    similarity in the eventual relief as equivalent to sameness of interest,
    which is contrary to the statutory scheme.

    33. In this regard, learned Senior Counsel places considerable
    reliance on the decision of the Hon’ble Supreme Court in Brigade
    Enterprises
    (Supra). He submits that the Supreme Court has drawn a
    clear distinction between a complaint filed jointly by a few consumers
    for redressal of their own grievances and a complaint filed in a
    representative capacity on behalf of numerous consumers. It was held
    that “sameness of cause of action” is not synonymous with “sameness
    of interest” and that the latter must be borne out from the pleadings
    and the reliefs sought in the consumer complaint.

    34. Learned Senior Counsel further submits that Brigade
    Enterprises recognises that, where a few consumers desire to pursue
    their own grievances jointly without representing the entire body of
    consumers, the appropriate course is to institute a joint complaint
    under Section 12(1)(a) of the 1986 Act (Presently Section 35(1)(a) of
    the 2019 Act), rather than invoke Section 12(1)(c). Thus, even if the
    respondents presently before this Court desire to pursue their
    individual claims together, they may do so through a properly
    constituted joint complaint confined to their own grievances. They
    cannot, however, continue to prosecute the present complaint as a
    representative action and bind persons whose grievances and factual
    Signature Not Verified
    Signed By:ANKITA CM(M)
    RAI 1248/2022 Page 14 of 44
    Signing Date:25.07.2026
    16:08:56
    circumstances are not the same. The Supreme Court had itself, upon
    finding the representative character of the complaint before it
    unsustainable, directed that it be treated as a joint complaint confined
    to the actual complainants, while permitting other persons to seek
    impleadment only if their grievance was limited to the grievance
    projected in the complaint.

    35. Reliance is also placed on Lucina Land Development
    Ltd.
    (Supra), wherein this Court applied the principles enunciated in
    Brigade Enterprises. Mr. Misra submits that Lucina Land
    Development holds that sameness of interest must be manifest from
    the pleadings themselves, so that the consumer forum is able to
    identify the consumers whose cause is sought to be represented and
    ascertain that the grievance and the alleged deficiency in service are
    identical qua each of them. A common interest in the eventual
    outcome of the complaint, or an omnibus prayer for a similar relief,
    would not satisfy the statutory requirement. The sameness must relate
    to the underlying grievance and the deficiency alleged against the
    service provider.

    36. Applying the aforesaid principles to the present case, learned
    Senior Counsel submits that the pleadings framed by the three original
    complainants cannot establish sameness of interest amongst the 49
    allottees who now remain. The original complainants had not taken
    possession and had, inter alia, sought delivery of possession, whereas
    the subsequently impleaded allottees occupy materially different
    positions. The attempt made before the learned NCDRC on
    27.07.2022 to confine the complaint to delayed-possession
    compensation and the demand towards increased saleable area could
    not retrospectively create a homogeneous class. On the contrary, the
    Signature Not Verified
    Signed By:ANKITA CM(M)
    RAI 1248/2022 Page 15 of 44
    Signing Date:25.07.2026
    16:08:56
    abandonment of the other reliefs demonstrates that the subsequently
    impleaded complainants were not interested in all the reliefs originally
    claimed and did not satisfy the first condition imposed by the learned
    NCDRC in its order dated 30.05.2019.

    37. Mr. Misra also relies upon the decisions of this Court in DLF
    Homes Rajapura Pvt. Ltd. v. Union of India & Anr.7
    , DLF Homes
    Rajapura Pvt. Ltd. v. Union of India & Ors.8
    and DLF Homes
    Rajapura Pvt. Ltd. v. Amardeep Singh Tiwana & Ors.9
    . It is
    submitted that these decisions consistently apply the principles
    enunciated in Brigade Enterprises and Lucina Land Development
    and recognise that, where the statutory requirement of sameness of
    interest is not met, the complaint cannot be permitted to continue in its
    representative form. At the same time, the consumers remain at liberty
    to institute a properly constituted class action, joint complaint or
    individual proceedings, as may be permissible in law.

    38. Learned Senior Counsel assails, in particular, the reasoning
    contained in paragraphs 6, 7 and 8 of the impugned order. He submits
    that, despite noticing both Brigade Enterprises and Lucina Land
    Development, the learned NCDRC failed to apply the test laid down
    therein. Instead of examining whether the pleadings disclosed an
    identical grievance and deficiency in service qua each surviving
    complainant, the learned NCDRC proceeded on the premise that the
    availability of a claim for compensation to all the complainants was
    sufficient to establish sameness of interest. Such an approach,
    according to him, reverses the statutory test by treating the relief as the

    7
    CM(M) 100/2018
    8
    CM(M) 1333/2019
    9
    CM(M) 572/2022
    Signature Not Verified
    Signed By:ANKITA CM(M)
    RAI 1248/2022 Page 16 of 44
    Signing Date:25.07.2026
    16:08:56
    source of sameness, whereas the sameness must exist in the
    underlying interest and grievance.

    39. Mr. Misra further submits that the learned NCDRC failed to
    examine whether the subsequently impleaded allottees complied with
    the four express conditions subject to which impleadment had been
    permitted on 30.05.2019. Persons who had already settled their
    disputes, approached another court or forum, or were not interested in
    all the reliefs claimed could not have been allowed to continue as
    members of the representative class. The objections raised by the
    petitioner in I.A. No. 4407/2022 were supported by complainant-wise
    particulars identifying the separate categories of allottees; yet, the
    impugned order contains no meaningful consideration of the effect of
    these distinctions.

    40. Learned Senior Counsel lastly takes exception to the
    observation in the impugned order that, even if some of the
    complainants did not fall within the definition of “consumer”, they
    could not be denied the benefit of a judgment passed in a class-action
    complaint. He submits that the said observation is fundamentally
    contrary to the jurisdictional scheme of the 1986 Act. The jurisdiction
    of a consumer forum can be invoked only by a person who answers
    the statutory description of a consumer in respect of a consumer
    dispute. The procedure of a representative complaint cannot confer
    substantive consumer status upon a person who does not otherwise
    possess it, nor can a relief which is unavailable directly be obtained
    indirectly through the medium of a class action.

    41. On the aforesaid premises, Mr. Misra submits that the
    impugned order suffers from a patent failure to apply the jurisdictional
    pre-requisites contained in Section 12(1)(c) of the 1986 Act. He
    Signature Not Verified
    Signed By:ANKITA CM(M)
    RAI 1248/2022 Page 17 of 44
    Signing Date:25.07.2026
    16:08:56
    accordingly prays that the order dated 12.10.2022 be set aside and that
    Consumer Complaint No. 1962/2017 be held incapable of proceeding
    in its existing representative form, while leaving the surviving
    complainants at liberty to pursue such joint, individual or properly
    constituted representative remedy as may be available to them in
    accordance with law.

    Submissions on behalf of the respondents

    42. Mr. Sudhir Kathpalia, learned Counsel for the respondents,
    submits that the principal question sought to be raised by the
    petitioner, which is whether Consumer Complaint No. 1962/2017
    could proceed as a representative complaint under Section 12(1)(c) of
    the 1986 Act, had already attained finality in the earlier round of
    proceedings. According to him, it is not open to the petitioner to
    reagitate the same issue at the stage of final adjudication of the
    consumer complaint by characterising the subsequent changes in the
    array of complainants as a fresh question of maintainability.

    43. Learned Counsel refers, in this regard, to the order dated
    23.05.2018, whereby the learned NCDRC had allowed the application
    under Section 12(1)(c) and permitted the complaint to proceed as a
    representative action. The said order was challenged by the petitioner
    before this Court in CM(M) 683/2018, in which its operation was
    stayed on 16.07.2018. The respondents thereafter approached the
    Supreme Court in SLP(C) Diary No. 4883/2019, whereby the
    Supreme Court vide order dated 15.02.2019 vacated the stay granted
    by this Court and directed that, if the persons then prosecuting the
    complaint desired to withdraw, an appropriate number of applicants
    could be substituted in their place and the matter would thereafter
    Signature Not Verified
    Signed By:ANKITA CM(M)
    RAI 1248/2022 Page 18 of 44
    Signing Date:25.07.2026
    16:08:56
    proceed on merits. Mr. Kathpalia submits that the necessary effect of
    the said order was to permit the consumer complaint to continue in its
    representative character notwithstanding the subsequent withdrawal of
    the original complainants. The public-notice and representative
    process already directed by the learned NCDRC consequently stood
    revived, and substitution of other interested allottees was expressly
    contemplated by the Hon’ble Supreme Court.

    44. Learned counsel points out that the petitioner thereafter
    withdrew CM(M) 683/2018 on 13.08.2019, whereupon the
    proceedings before the Supreme Court were also disposed of as
    having become infructuous. He contends that, once the challenge to
    the order dated 23.05.2018 was withdrawn and the Supreme Court’s
    order permitting substitution and continuation of the proceedings
    remained undisturbed, the representative character of the complaint
    could not subsequently be questioned through I.A. No. 4407/2022.
    The petitioner, according to him, cannot indirectly reopen an issue
    which it had elected not to pursue in the earlier proceedings.

    45. Reliance is placed upon the principles of res judicata,
    constructive res judicata and issue estoppel. Learned Counsel submits
    that an issue finally determined at an earlier stage of the same
    proceedings cannot ordinarily be reopened at a later stage. In support
    thereof, he relies upon Satyadhyan Ghosal v. Deorajin Debi10,
    Daryao v. State of U.P.11, State of Uttar Pradesh v. Nawab Hussain12
    and Forward Construction Co. v. Prabhat Mandal (Regd.),
    Andheri13
    . The foundational requirement of sameness of interest, it is

    10
    AIR 1960 SC 941
    11
    AIR 1961 SC 1457
    12
    (1977) 2 SCC 806
    13
    (1986) 1 SCC 100
    Signature Not Verified
    Signed By:ANKITA CM(M)
    RAI 1248/2022 Page 19 of 44
    Signing Date:25.07.2026
    16:08:56
    argued, was adjudicated when permission under Section 12(1)(c) was
    granted, and the petitioner cannot seek a second determination merely
    because the proceedings have since progressed and the circumstances
    of some members have changed.

    46. Learned Counsel further relies upon Kunhayammed & Ors. v.
    State of Kerala & Anr.14
    . He submits that the precise effect of the
    order dated 15.02.2019 must be understood in the light of its operative
    directions and the nature of jurisdiction exercised by the Supreme
    Court. According to him, if the said order is understood as an
    appellate or merits determination, the order of the learned NCDRC
    would stand merged in the order of the Supreme Court and could not
    retain an independent existence susceptible to indirect reconsideration
    under Article 227. In any event, even apart from the doctrine of
    merger, judicial discipline precludes any court or tribunal from
    adopting a position contrary to the express direction of the Supreme
    Court in the same litigation.

    47. Mr. Kathpalia further submits that the subsequent impleadment
    of the present respondents was undertaken in pursuance of the liberty
    recognised by the Supreme Court and under orders passed by the
    learned NCDRC. The impleadment orders were not challenged by the
    petitioner at the relevant time. The petitioner participated in the
    proceedings, filed its additional written version and evidence and
    permitted the matter to progress substantially. It was only when the
    consumer complaint had reached the stage of final hearing that the
    petitioner again raised the issue of maintainability by filing I.A. No.
    4407/2022 on 19.05.2022.

    14

    (2000) 6 SCC 359
    Signature Not Verified
    Signed By:ANKITA CM(M)
    RAI 1248/2022 Page 20 of 44
    Signing Date:25.07.2026
    16:08:56

    48. Learned Counsel submits that the petitioner’s reliance upon
    Brigade Enterprises and Lucina Land Development Ltd. is
    misplaced. According to him, those decisions arose at the stage when
    permission under Section 12(1)(c) was being granted or examined and
    did not concern a case where permission had already been granted,
    public notice had been issued, the challenge had travelled to the
    Supreme Court, additional complainants had been impleaded and the
    representative proceedings had continued for several years.

    49. It is submitted that Brigade Enterprises treats sameness of
    interest as a prerequisite to be examined at the stage of granting
    permission under Section 12(1)(c). It does not create a recurring right
    in favour of the service provider to reopen the permission order at
    every subsequent stage on account of individual developments relating
    to some members of the represented class. The present issue,
    therefore, is not whether permission initially should have been
    granted, but whether a threshold determination which has attained
    finality between the parties can be reopened when the complaint is
    ripe for final adjudication.

    50. Mr. Kathpalia submits that permitting such reopening would
    have consequences extending beyond the present dispute. Every order
    granting permission under Section 12(1)(c) would remain provisional
    and susceptible to repeated challenges whenever some members take
    possession, transfer their units or settle their claims. This would
    deprive representative proceedings of procedural stability and enable a
    developer, after participating in the proceedings for several years, to
    seek dismantling of the representative action at the stage of final
    arguments. Such an approach, according to him, would frustrate the

    Signature Not Verified
    Signed By:ANKITA CM(M)
    RAI 1248/2022 Page 21 of 44
    Signing Date:25.07.2026
    16:08:56
    object of Section 12(1)(c) and Order I Rule 8 of the CPC, which is to
    facilitate collective adjudication and avoid multiplicity of proceedings.

    51. Learned counsel submits that the impugned order dated
    12.10.2022 cannot be viewed in isolation from this procedural history.
    The learned NCDRC was conscious of the withdrawal of the original
    complainants, the substitution of the subsequently impleaded allottees,
    the earlier proceedings before this Court and the Supreme Court, and
    the reliefs which remained to be adjudicated. After considering the
    objections of the petitioner and the complainant-wise material placed
    before it, the learned NCDRC concluded that the surviving claims
    relating to delayed-possession compensation and increased saleable
    area disclosed sufficient commonality to permit the complaint to
    continue.

    52. According to learned Counsel, the common foundational
    grievance remains the delay in delivery of possession by the same
    developer and the consequential claim for compensation. Differences
    concerning unit particulars, dates, amounts or subsequent events do
    not, by themselves, extinguish that common interest. Subsequent
    delivery of possession cannot retrospectively extinguish a claim which
    had already accrued for the preceding period of delay. Similarly, a
    transfer or settlement may affect the ultimate entitlement of the
    particular complainant concerned, but does not necessarily destroy the
    representative proceeding qua the remaining members. A person who
    has settled may be disentitled to any further recovery, without the
    settlement extinguishing the surviving claims of those who continue to
    prosecute the complaint.

    53. Mr. Kathpalia also places reliance upon the order dated
    23.03.2022 passed by the learned NCDRC. The said order records that
    Signature Not Verified
    Signed By:ANKITA CM(M)
    RAI 1248/2022 Page 22 of 44
    Signing Date:25.07.2026
    16:08:56
    the Supreme Court, by its order dated 15.02.2019, had directed the
    learned NCDRC to conclude the proceedings as expeditiously as
    possible. It further records that, despite a last opportunity having been
    granted on 14.02.2022, the petitioner had not filed its evidence. The
    learned NCDRC accordingly imposed costs of ₹10,000/- upon the
    petitioner, granted it a further period of two weeks to file evidence and
    listed the consumer complaint for final hearing on 28.04.2022.

    54. According to learned Counsel, the aforesaid order demonstrates
    that the consumer complaint had been delayed on account of the
    petitioner’s repeated failure to complete its evidence and its successive
    challenges to the proceedings. He submits that I.A. No. 4407/2022
    was filed only after the parties had completed their pleadings and
    evidence and the complaint was ripe for final hearing. The filing of the
    said application, followed by the present petition upon its dismissal, is
    therefore characterised as another attempt to postpone adjudication of
    the respondents’ claims on merits.

    55. Learned Counsel argues that the respondents have been
    awaiting adjudication of a complaint instituted as far back as
    12.07.2017. The petitioner cannot be permitted, after participating in
    the representative proceedings for several years and withdrawing its
    earlier challenge, to turn the clock back and require the respondents to
    institute fresh proceedings under Section 12(1)(a) of the 1986 Act.
    Such a course would defeat the earlier orders of the Supreme Court
    and render the proceedings undertaken before the learned NCDRC
    over several years worthless.

    56. Mr. Kathpalia submits that the petitioner’s reliance on the
    subsequent settlements entered into by some of the complainants does
    not affect the maintainability of the complaint qua the remaining
    Signature Not Verified
    Signed By:ANKITA CM(M)
    RAI 1248/2022 Page 23 of 44
    Signing Date:25.07.2026
    16:08:56
    respondents. A person who has settled may not be entitled to obtain
    any further relief, as was also recognised in the impugned order.
    However, the settlement of some members of the class cannot
    extinguish the common claims of those who continue to prosecute the
    proceedings. The reduction in the number of complainants from those
    originally impleaded to the persons presently remaining is, therefore,
    stated to have no bearing upon the representative character of the
    complaint.

    57. It is lastly submitted that the petitioner is inviting this Court to
    undertake an appellate reconsideration of the procedural and factual
    conclusions reached by the learned NCDRC. The supervisory
    jurisdiction under Article 227, according to learned counsel, cannot be
    invoked to reopen an issue which has already travelled to the Hon’ble
    Supreme Court and in respect of which the petitioner had withdrawn
    its earlier challenge. In the absence of any jurisdictional error in the
    impugned order, Mr. Kathpalia accordingly prays that the present
    petition be dismissed and that the learned NCDRC be permitted to
    conclude Consumer Complaint No. 1962/2017 on merits without any
    further delay.

    Analysis

    58. Before entering into the rival contentions on merits, it is
    necessary to delineate the scope of interference under Article 227 of
    the Constitution. The jurisdiction conferred by Article 227 is
    supervisory and not appellate in character. Its object is to ensure that
    courts and tribunals subordinate to the High Court remain within the
    bounds of their authority and discharge their functions in the manner
    required by law. This Court would, therefore, not reappreciate the
    Signature Not Verified
    Signed By:ANKITA CM(M)
    RAI 1248/2022 Page 24 of 44
    Signing Date:25.07.2026
    16:08:56
    material on record, substitute its own conclusions for those of the
    learned NCDRC, or interfere merely because another view may also
    be possible. The power is required to be exercised sparingly,
    principally where the authority below has acted without or in excess of
    jurisdiction, failed to exercise jurisdiction vested in it, disregarded a
    mandatory statutory prescription, or rendered a finding so perverse or
    manifestly unreasonable that its continuance would occasion grave
    injustice. Among the decisions of the Hon’ble Supreme Court
    delineating the scope of interference under Article 227 are Shalini
    Shyam Shetty v. Rajendra Shankar Patil15
    and Garment Craft v.
    Prakash Chand Goel16
    .

    59. Consequently, the enquiry in the present petition is not whether
    this Court would, on an independent appraisal, have arrived at the
    same conclusion as the learned NCDRC. The limited question is
    whether, while permitting the complaint to continue under Section
    12(1)(c)
    of the 1986 Act, the learned NCDRC applied the
    jurisdictional requirements prescribed by the statute and the binding
    law governing representative consumer proceedings. If the impugned
    order proceeds upon an erroneous jurisdictional test, overlooks
    material statutory conditions, or exercises the jurisdiction vested in the
    learned NCDRC in a manner impermissible in law, such an error
    would fall within the supervisory ambit of Article 227.

    60. With this brief preface, and having heard learned counsel for
    the parties and perused the record, this Court may now advert to the
    issues arising for consideration in the present petition.

    15

    (2010) 8 SCC 329
    16
    (2022) 4 SCC 181
    Signature Not Verified
    Signed By:ANKITA CM(M)
    RAI 1248/2022 Page 25 of 44
    Signing Date:25.07.2026
    16:08:56

    61. The first and the most important objection which falls for
    consideration is whether the maintainability of Consumer Complaint
    No. 1962/2017 as a representative complaint stood finally concluded
    by the orders passed in the earlier round of proceedings. The
    respondents contend that, once the Supreme Court vide its order dated
    15.02.2019, vacated the stay granted by this Court against the order
    dated 23.05.2018, permitted substitution of appropriate applicants in
    the event of withdrawal by the original complainants and directed the
    matter to proceed on merits, it was no longer open to the petitioner to
    question the representative character of the complaint. This Court is
    unable to accept the objection.

    62. Mr. Kathpalia’s reliance upon the doctrine of merger also does
    not advance the case of the respondents. The Hon’ble Supreme
    Court’s order dated 15.02.2019 was passed at the stage of
    consideration of the special leave petition and does not record either
    the grant of leave or the conversion of the proceedings into a civil
    appeal. As explained in Kunhayammed (Supra), the doctrine of
    merger is attracted when the appellate jurisdiction of the Supreme
    Court is invoked upon grant of leave and the appeal is thereafter
    decided. An order passed at the stage of special leave does not, by
    itself, result in the merger of the order under challenge. The express
    directions contained in the order dated 15.02.2019 are undoubtedly
    binding and have to be given full effect. However, their binding effect
    extends to what was actually directed and decided, i.e. vacation of the
    interim stay, issuance of public notice, substitution of an appropriate
    number of applicants upon withdrawal of the original complainants,
    and continuation of the complaint on merits. The said order did not
    adjudicate whether every person subsequently impleaded would
    Signature Not Verified
    Signed By:ANKITA CM(M)
    RAI 1248/2022 Page 26 of 44
    Signing Date:25.07.2026
    16:08:56
    satisfy the requirement of sameness of interest, nor did it foreclose
    examination of the continued maintainability of the complaint upon a
    material alteration in the composition of the represented class.

    63. The Hon’ble Supreme Court vide order dated 15.02.2019
    employed the express language and the direction was that an
    “appropriate number” of applicants could be substituted and that the
    matter would thereafter proceed on merits. The use of the expression
    “appropriate” necessarily contemplated that the persons seeking
    substitution would have to be eligible to prosecute the representative
    complaint in accordance with law. Indeed, the learned NCDRC itself
    did not regard the Supreme Court’s order as authorising unconditional
    impleadment. By the subsequent NCDRC order dated 30.05.2019,
    impleadment was permitted subject to four express conditions: “(i)
    they are interested in all the reliefs sought in this complaint (ii) they
    have no other grievance against the OP (iii) their allotments have not
    been cancelled and (iv) they have already not approached either this
    Commission or any other Court/Forum for the redressal of their
    grievances.” Thus, even the learned NCDRC proceeded on the basis
    that the entitlement of the substituted complainants to remain in the
    representative proceedings required independent scrutiny.

    64. The plea of finality is liable to be rejected on the grounds that,
    the I.A. No. 4407/2022 was not a disguised attempt to reopen the
    order dated 23.05.2018 on the same factual foundation. When
    permission under Section 12(1)(c) was originally granted, the
    complaint was being prosecuted by the three original complainants on
    the basis of the pleadings and reliefs framed by them. Thereafter, the
    original complainants settled their disputes and withdrew from the
    proceedings. This Court would like to emphasise that numerous
    Signature Not Verified
    Signed By:ANKITA CM(M)
    RAI 1248/2022 Page 27 of 44
    Signing Date:25.07.2026
    16:08:56
    other allottees were subsequently impleaded, and their factual
    circumstances revealed materially distinct categories, including
    persons who had taken possession after varying periods of delay,
    subsequent purchasers, persons who had accepted compensation,
    persons who had executed conveyance deeds, persons who had
    transferred their units, and persons who had pursued or settled
    their claims before other forums. These circumstances arose, or
    became identifiable, only after the earlier round of proceedings.

    65. The question raised in I.A. No. 4407/2022 was, therefore, not
    whether the three original complainants could have been permitted to
    institute the complaint in a representative capacity on the material
    available on 23.05.2018. The question was whether the complaint,
    after its complete reconstitution and in the form in which it was being
    prosecuted in the year 2022, continued to satisfy the jurisdictional
    conditions of Section 12(1)(c). A representative proceeding must
    continue to fulfil the conditions upon which its representative
    character depends. An initial order granting permission cannot
    immunise the proceedings from examination where subsequent
    developments have fundamentally altered the class which is
    prosecuting the complaint.

    66. It is true that the doctrine of finality prevents a party from
    avoiding an earlier adverse adjudication merely by reformulating the
    same challenge under a different procedural provision. Equally,
    however, that principle applies where the matter was earlier directly
    and substantially in issue and was heard and finally decided. It does
    not bar consideration of a later application founded upon genuinely
    subsequent facts which materially alter the subject matter of the
    enquiry. The present application, in this Court’s view, falls in the
    Signature Not Verified
    Signed By:ANKITA CM(M)
    RAI 1248/2022 Page 28 of 44
    Signing Date:25.07.2026
    16:08:56
    latter category as it was neither based upon the same factual position
    nor directed against an issue previously adjudicated on merits.

    67. This Court is conscious that an order granting permission under
    Section 12(1)(c) of the 1986 Act cannot be treated as perpetually
    provisional or reopened merely because some individual development
    occurs during the pendency of the complaint. Procedural stability is
    necessary in representative proceedings, and the mere settlement,
    transfer or change in the circumstances of an isolated member would
    not ordinarily justify reconsideration of the permission already
    granted. At the same time, the doctrine of finality cannot be invoked
    to perpetuate a proceeding which, owing to subsequent material
    developments, is alleged to have ceased to satisfy the statutory
    requirements governing its maintainability. The respondents’
    contention that the representative character of the complaint under
    Section 12(1)(c) had attained finality must, therefore, be considered in
    the context of the nature and extent of the subsequent changes. The
    present case does not involve a routine or isolated development. The
    three persons who instituted the complaint and framed its pleadings
    and reliefs ceased to prosecute it, whereafter a substantially different
    body of allottees was brought on record subject to express conditions.
    The objection raised in I.A. No. 4407/2022 was not directed against
    the correctness of the initial permission in the abstract, but concerned
    whether the complaint, after such reconstitution, continued to remain
    within the statutory limits of Section 12(1)(c). Examination of that
    question does not render every permission order provisional. It merely
    recognises that finality cannot operate as a shield against the
    examination of an alleged jurisdictional or statutory defect arising
    from material subsequent events, and that a representative proceeding
    Signature Not Verified
    Signed By:ANKITA CM(M)
    RAI 1248/2022 Page 29 of 44
    Signing Date:25.07.2026
    16:08:56
    cannot continue in a form substantially different from the one for
    which permission was granted without the forum satisfying itself that
    its statutory foundation continues to subsist.

    68. There was also an intervening judgment of the Hon’ble
    Supreme Court in Brigade Enterprises. The decision clarified that
    sameness of cause of action is not equivalent to sameness of interest
    and that purchasers occupying different positions, such as those who
    accepted compensation, accepted it under protest or declined it, or
    suffered materially different periods of delay cannot automatically be
    treated as one homogeneous class. The judgment was delivered while
    Consumer Complaint No. 1962/2017 was still pending and before I.A.
    No. 4407/2022 was decided. It was, therefore, incumbent upon the
    learned NCDRC to apply the law so declared while examining
    whether the reconstituted complaint continued to meet the
    requirements of Section 12(1)(c).

    69. Though Brigade Enterprises was rendered while examining the
    grant of permission under Section 12(1)(c), the decision explains the
    substantive content of the expression “same interest” occurring in the
    said provision. The relevance of that principle to the present case does
    not arise from any proposition in Brigade Enterprises permitting
    every order granting permission to be reopened at a subsequent stage.
    However in the present set of facts, it arises because I.A. No.
    4407/2022 raised the distinct question that whether the complaint,
    after a material alteration in its composition, continued to satisfy the
    statutory requirements of Section 12(1)(c), an issue which had not
    been examined in the earlier proceedings before the learned NCDRC.

    70. This Court emphasises once again that Brigade Enterprises,
    where the legal basis governing a pure question of law and jurisdiction
    Signature Not Verified
    Signed By:ANKITA CM(M)
    RAI 1248/2022 Page 30 of 44
    Signing Date:25.07.2026
    16:08:56
    is authoritatively clarified, the doctrine of res judicata cannot be
    invoked to compel a court or tribunal to decide a pending proceeding
    contrary to the law declared by the Supreme Court. This Court finds it
    pertinent to refer to certain paras from Canara Bank v. N.G.
    Subbaraya Setty17
    :

    “30. An appeal from the Division Bench judgment pursuant to the
    Full Bench decision [State of Punjab v. Nand Kishore, 1974 SCC
    OnLine P&H 126 : AIR 1974 P&H 303] resulted in the decision
    in Nand Kishore v. State of Punjab [Nand Kishore v. State of
    Punjab, (1995) 6 SCC 614 : 1996 SCC (L&S) 57] . A brief resume
    of the facts shows that the appellant had been compulsorily retired,
    having completed only ten years’ qualifying service in pursuance of
    Rule 5.32(b) of the Punjab Civil Services Rules, Vol. II. A writ
    petition that was moved by the appellant against the compulsory
    retirement order was dismissed on 2-2-1962. The appellant had not
    questioned the validity of Rule 5.32(b) in the aforesaid writ
    petition.
    However, in Moti Ram Deka v. North East Frontier
    Railway [Moti Ram Deka v. North East Frontier Railway, (1964) 5
    SCR 683 : AIR 1964 SC 600] , this Court held that if the
    compulsory retirement rule permitted an authority to retire a public
    servant at a very early stage of his career, such rule might be
    constitutionally invalid. The appellant, spurred by the decision
    in Moti Ram Deka [Moti Ram Deka v. North East Frontier
    Railway
    , (1964) 5 SCR 683 : AIR 1964 SC 600] , filed a suit in
    1964 for a declaration that Rule 5.32 of the aforesaid Rules was
    constitutionally invalid.
    A pari materia rule to that of Rule 5.32
    was struck down by this Court in Gurdev Singh Sidhu v. State
    ofPunjab [Gurdev Singh Sidhu v. State of Punjab, (1964) 7 SCR
    587 : AIR 1964 SC 1585 : (1964) 2 Cri LJ 481] . However, since a
    writ petition had been filed by the appellant earlier, the State of
    Punjab, in its written statement to the suit filed by the appellant,
    took up the plea of constructive res judicata. This plea found
    favour with the Full Bench of the High Court on 8-5-1974 [State of
    Punjab v. Nand Kishore
    , 1974 SCC OnLine P&H 126 : AIR 1974
    P&H 303] , following which a Division Bench allowed the appeal
    of the State of Punjab on 13-8-1974. It is from this judgment that
    an appeal landed up before this Court, as is stated hereinabove.

    This Court, on 6-12-1990, advised the appellant to file a special
    leave petition from the order of the High Court dismissing his writ
    petition dated 15-2-1962 [Nand Kishore Vaid v. State of Punjab,
    1962 SCC OnLine P&H 47 : PLR (1962) 64 P&H 469] , with an
    appropriate application for condonation of delay.
    The delay was

    17
    (2018) 16 SCC 228
    Signature Not Verified
    Signed By:ANKITA CM(M)
    RAI 1248/2022 Page 31 of 44
    Signing Date:25.07.2026
    16:08:56
    condoned by this Court in the interest of justice in the special
    circumstances of this case under Article 142, and the said belated
    appeal was allowed following Gurdev Singh [Gurdev Singh
    Sidhu v. State of Punjab
    , (1964) 7 SCR 587 : AIR 1964 SC 1585 :

    (1964) 2 Cri LJ 481] and striking down the order of compulsory
    retirement of the appellant. Despite having so decided, this Court
    went into the doctrine of constructive res judicata and decided that
    the constitutionality of a provision of law stands on a different
    footing from other questions of law. As there is a presumption of
    constitutionality of all statutes, the “might and ought” rule of
    constructive res judicata cannot be applied. Instead what was
    applied by this Court was that part of the decision in Mathura
    Prasad [Mathura Prasad Bajoo Jaiswal v. Dossibai N.B.
    Jeejeebhoy
    , (1970) 1 SCC 613] which stated that when the law
    has, since the earlier decision in the appellant’s writ petition,
    been altered by a competent authority, res judicata cannot apply.

    The Full Bench of the Punjab High Court was expressly
    overruled on the point that a “competent authority” can also be a
    court. Hence, a changed declaration of law would also fall within
    an earlier decision being altered by a competent authority. This
    Court, therefore, held that since this Court itself had altered the
    law when it declared the pari materia rule as unconstitutional,
    the doctrine of res judicata could not apply.

    xxx
    34.1. The general rule is that all issues that arise directly and
    substantially in a former suit or proceeding between the same
    parties are res judicata in a subsequent suit or proceeding between
    the same parties. These would include issues of fact, mixed
    questions of fact and law, and issues of law.

    xxx
    34.3. Another exception to this general rule follows from the
    matter in issue being an issue of law different from that in the
    previous suit or proceeding. This can happen when the issue of
    law in the second suit or proceeding is based on different facts
    from the matter directly and substantially in issue in the first suit
    or proceeding. Equally, where the law is altered by a competent
    authority since the earlier decision, the matter in issue in the
    subsequent suit or proceeding is not the same as in the previous
    suit or proceeding, because the law to be interpreted is different.”

    [Emphasis Supplied]

    71. This Court would also like to refer to Hope Plantations Ltd. v.
    Taluk Land Board18
    , wherein the Hon’ble Supreme Court has held:

    18

    (1999) 5 SCC 590
    Signature Not Verified
    Signed By:ANKITA CM(M)
    RAI 1248/2022 Page 32 of 44
    Signing Date:25.07.2026
    16:08:56
    “31. Law on res judicata and estoppel is well understood in
    India and there are ample authoritative pronouncements by various
    courts on these subjects. As noted above, the plea of res judicata,
    though technical, is based on public policy in order to put an end to
    litigation. It is, however, different if an issue which had been
    decided in an earlier litigation again arises for determination
    between the same parties in a suit based on a fresh cause of
    action or where there is continuous cause of action. The parties
    then may not be bound by the determination made earlier if in
    the meanwhile, law has changed or has been interpreted
    differently by a higher forum. But that situation does not exist
    here. Principles of constructive res judicata apply with full force. It
    is the subsequent stage of the same proceedings. If we refer to
    Order XLVII of the Code (Explanation to Rule 1) review is not
    permissible on the ground
    “that the decision on a question of law on which the judgment
    of the Court is based has been reversed or modified by the
    subsequent decision of a superior court in any other case, shall
    not be a ground for the review of such judgment”.”

    [Emphasis Supplied]

    72. Having rejected the objection raised upon finality, the next
    question concerns the continued maintainability of Consumer
    Complaint No. 1962/2017 under Section 12(1)(c) of the 1986 Act.
    This would require an examination of whether the complainants
    presently prosecuting the complaint possess the “same interest”

    contemplated by the said provision and whether they satisfy the
    conditions subject to which their impleadment was permitted by the
    learned NCDRC on 30.05.2019.

    73. The requirement of sameness of interest constitutes the essential
    statutory foundation of a representative consumer complaint. As
    explained by the Supreme Court in Brigade Enterprises, a complaint
    instituted by one or more consumers in a representative capacity is
    distinct from a joint complaint filed by a number of consumers for
    redressal of their own grievances. While several consumers may join
    together to pursue their individual claims, a representative complaint
    Signature Not Verified
    Signed By:ANKITA CM(M)
    RAI 1248/2022 Page 33 of 44
    Signing Date:25.07.2026
    16:08:56
    is prosecuted on behalf of, and binds, numerous other consumers who
    are not necessarily parties to the proceedings. It is for this reason that
    the statutory requirement of sameness of interest assumes particular
    significance.

    74. In the present case, however, determination of the aforesaid
    requirement is connected with an extensive factual enquiry. The
    complaint was originally instituted by three complainants who framed
    the pleadings and sought several reliefs, including delivery of
    possession, compensation for delayed possession and setting aside of
    the demand towards increased saleable area. Those three complainants
    subsequently settled their disputes and withdrew from the
    proceedings. Other allottees were thereafter impleaded subject to the
    conditions recorded in the order dated 30.05.2019. It has further been
    stated before this Court that, out of the 85 allottees who had at one
    stage been impleaded, only 49 presently remain, the others having
    settled their disputes with the petitioner.

    75. Whether the presently surviving complainants constitute one
    homogeneous class cannot be determined merely by reference to the
    fact that they had purchased units in the same project or that some
    monetary relief may be claimed by each of them. The enquiry would
    necessarily require identification of each complainant presently
    prosecuting the complaint and an examination of, inter alia, the date
    and nature of the allotment, whether the complainant is an original or
    subsequent allottee, the date on which possession was offered and
    accepted, the period of delay, the compensation paid or accepted, the
    execution of any conveyance deed, the subsequent sale or transfer of
    the unit, the existence of any settlement and whether the complainant
    had already invoked the jurisdiction of another court or forum.

    Signature Not Verified
    Signed By:ANKITA CM(M)
    RAI 1248/2022 Page 34 of 44
    Signing Date:25.07.2026
    16:08:56

    76. The said exercise would also require the factual position of each
    surviving complainant to be compared with the pleadings and reliefs
    framed by the three original complainants. It would have to be
    determined whether each of the surviving complainants remains
    interested in the reliefs sought in the complaint and whether the
    conditions imposed by the learned NCDRC on 30.05.2019 were
    fulfilled at the time of impleadment and continue to be fulfilled. The
    status of persons who have settled or ceased to pursue the proceedings
    would also have to be appropriately reflected while identifying the
    class, if any, which is presently before the learned NCDRC.

    77. These are not matters which can be satisfactorily determined by
    this Court in the first instance while exercising supervisory
    jurisdiction under Article 227 of the Constitution. Any conclusive
    determination would require this Court to undertake a complainant-
    wise scrutiny of the pleadings, agreements, possession documents,
    conveyance deeds, settlement instruments, compensation records and
    proceedings instituted before other forums. Such an exercise would
    amount to assuming the role of the forum of first instance and entering
    into factual adjudication beyond the limited supervisory jurisdiction
    presently undertaken.

    78. The learned NCDRC, before which the complaint, the amended
    memos of parties, the additional written version, the affidavits of
    evidence and the complainant-wise chart dated 13.08.2022 are on
    record, is the appropriate forum to undertake this enquiry. It is for the
    learned NCDRC to determine, on the basis of the presently subsisting
    party array and the material placed before it, whether the surviving
    complainants possess the sameness of interest required by Section

    Signature Not Verified
    Signed By:ANKITA CM(M)
    RAI 1248/2022 Page 35 of 44
    Signing Date:25.07.2026
    16:08:56
    12(1)(c) and whether they satisfy the conditions stipulated in the order
    dated 30.05.2019.

    79. The survival of an individual cause of action is conceptually
    distinct from the requirement of sameness of interest for maintaining a
    representative proceeding. The question is not merely whether each
    complainant may possess some surviving monetary claim, but whether
    the grievance, deficiency and relief are sufficiently common to enable
    all such claims to be adjudicated through the same representative
    pleadings and to bind the entire class by a common decision.

    80. The impugned order dated 12.10.2022, however, does not
    undertake the aforesaid exercise. The learned NCDRC proceeded
    broadly on the premise that the surviving claims relating to delayed-
    possession compensation and the demand towards increased saleable
    area were sufficient to establish sameness of interest. The distinct
    categories identified by the petitioner and the effect of the conditions
    imposed on 30.05.2019 were not examined complainant-wise. Nor
    does the impugned order disclose any determination as to whether the
    surviving complainants, having regard to their respective factual and
    legal positions, could validly be treated as comprising one
    homogeneous class possessing the “same interest” within the
    meaning of Section 12(1)(c) of the 1986 Act. Such an enquiry
    required the learned NCDRC to examine whether the grievance
    alleged, the deficiency in service complained of and the reliefs
    claimed were substantially common to each of the surviving
    complainants, and whether their claims could be adjudicated on the
    basis of the same pleadings without undertaking materially distinct
    complainant-wise enquiries. The mere circumstance that all of them
    had purchased units in the same project, or that each may claim some
    Signature Not Verified
    Signed By:ANKITA CM(M)
    RAI 1248/2022 Page 36 of 44
    Signing Date:25.07.2026
    16:08:56
    form of monetary compensation, could not by itself establish
    sameness of interest. It was necessary to determine whether their
    differing circumstances relating to possession, delay, transfer,
    acceptance of compensation, execution of conveyance deeds,
    settlement and prior litigation permitted them to be represented
    through a single complaint and bound by a common adjudication.

    81. The learned NCDRC also observed that, in the case of persons
    who had transferred their units after seeking impleadment, their rights
    were required to be considered with reference to the date on which
    they had joined the proceedings and that a subsequent transfer would
    not, by itself, defeat their claims. There may be substance in the
    limited proposition that a transfer effected during the pendency of the
    proceedings does not automatically extinguish a claim which had
    already accrued prior thereto. That question, however, is distinct from
    whether such a person, after having transferred the unit, continues to
    possess the same interest as the other members of the represented class
    and remains entitled to prosecute the reliefs sought in the complaint
    for the purposes of Section 12(1)(c) of the 1986 Act. The nature of the
    rights transferred, the terms of the transfer, the period for which
    compensation is claimed and the entitlement, if any, retained by the
    transferor would require a complainant-wise examination. The
    impugned order does not undertake that exercise.

    82. The omission of undertaking the adequate exercise in the
    impugned order as discussed above, assumes significance because
    Brigade Enterprises requires a clear distinction to be maintained
    between consumers jointly seeking redressal of their own grievances
    and consumers prosecuting a complaint on behalf of an entire class.
    The Hon’ble Supreme Court recognised that, where representative
    Signature Not Verified
    Signed By:ANKITA CM(M)
    RAI 1248/2022 Page 37 of 44
    Signing Date:25.07.2026
    16:08:56
    proceedings are impermissible, the complaint may, depending upon
    the facts, be treated as a joint complaint confined to the actual
    complainants, and that other persons may be impleaded only where
    their grievance is limited to that projected in the complaint. The
    precise procedural course to be adopted must, however, depend upon
    the pleadings, reliefs and factual position of the persons who continue
    to prosecute the complaint. At this stage, it would be apposite to
    reproduce relevant paragraphs of Brigade Enterprises:

    “20. The Explanation under Order 1 Rule 8 is of significance. It
    distinguishes persons having the same interest in one suit from
    persons having the same cause of action. To establish sameness of
    interest, it is not necessary to establish sameness of the cause of
    action.

    21.The Explanation under Order 1 Rule 8, is a necessary
    concomitant of the provisions of Rules 1 and 3 of Order 1. Order 1
    Rule 1 CPC
    , allows many persons to join in one suit as plaintiffs.
    Order 1 Rule 3 allows many persons to be joined in one suit as
    defendants. But to fall under Order 1 Rule 1 or Order 1 Rule 3, the
    right to relief should arise out of or be in respect of the same act or
    transaction allegedly existing in such persons, jointly, severally or
    in the alternative. To some extent, Rules 1 and 3 of Order 1 are
    founded upon the sameness of the cause of action. This is why the
    Explanation under Order 1 Rule 8 distinguishes sameness of
    interest from the sameness of the cause of action.

    22. Since “sameness of interest” is the prerequisite for an
    application under Order 1 Rule 8 CPC read with Section 35(1)(c)
    of the Consumer Protection Act, 2019, it was necessary for the
    respondents to include in the consumer complaint, sufficient
    averments that would show sameness of interest. As we have
    pointed out earlier, the total number of residential apartments
    constructed in three blocks comprising of about 20 wings (7 wings
    each in Amber and Blue Blocks and 6 wings in Crimson Block)
    were 1134. There are no pleadings insofar as the purchasers of 386
    residential apartments in the 7 wings of Amber Block are
    concerned. Even in respect of the owners of the remaining 748
    residential apartments in Blue Block and Crimson Block, the
    complaint does not contain any specific averments regarding
    sameness of interest. The delay in handing over possession of the
    residential apartments might have given rise to a cause of action for
    Signature Not Verified
    Signed By:ANKITA CM(M)
    RAI 1248/2022 Page 38 of 44
    Signing Date:25.07.2026
    16:08:56
    the individual purchasers of flats to sue the builder. But sameness
    of the cause of action is not equal to sameness of interest. The
    existence of sameness of interest, has been questioned by the
    appellant builder on the ground that delay compensation as
    stipulated in the agreements was offered to the purchasers and that
    some of them accepted the same without any demur or protest,
    while a few others have refused to accept. It is not clear from the
    consumer complaint as to how:

    (i) those who have accepted the compensation under
    protest;

    (ii) those who accepted without protest; and

    (iii) those who refused to accept the compensation, have
    the sameness of interest.

    23. The period of delay in the completion of the project and the
    handing over of possession, does not appear to be uniform in all
    1134 cases. The respondent complainants cannot project
    sameness of interest for the purchasers in whose case the period
    of delay was negligible and those in whose cases there was a
    huge delay.

    24. We may have to look at the issue also from the point of view of
    the buyers. The delay in handing over possession need not
    necessarily be the only deficiency in service on the part of the
    appellant builder. Some of the purchasers of flats may also have
    other complaints and their right to proceed against the appellant
    cannot be stultified by a few individuals invoking Section 35(1)(c).
    That a few purchasers have chosen to approach the Karnataka State
    Consumer Disputes Redressal Commission to ventilate their
    individual grievances shows that all the 1134 buyers do not have
    the same interest as that of the respondents. At least if the
    respondents have given the names of purchasers of all flats on
    whose behalf the present complaint could be entertained, they
    would have been better off. But they have not done so.

    xxx

    30. All the above decisions show that for allowing an application
    under Section 12(1)(c) of the 1986 Act or Section 35(1)(c) of the
    2019 Act, the pleadings and the reliefs are to be considered. If so
    considered, the National Commission could not have granted
    permission to the respondents in this case, to file the complaint in
    a representative capacity for and on behalf of the owners of all
    the 1134 flats.

    xxx

    34. Section 35(1) reads as under:

    Signature Not Verified
    Signed By:ANKITA CM(M)
    RAI 1248/2022 Page 39 of 44
    Signing Date:25.07.2026
    16:08:56

    “35. Manner in which complaint shall be made.–(1) A
    complaint, in relation to any goods sold or delivered or agreed to
    be sold or delivered or any service provided or agreed to be
    provided, may be filed with a District Commission by–

    (a) the consumer–

    (i) to whom such goods are sold or delivered or agreed to be
    sold or delivered or such service is provided or agreed to be
    provided; or

    (ii) who alleges unfair trade practice in respect of such goods or
    service;

    (b) any recognised consumer association, whether the
    consumer to whom such goods are sold or delivered or agreed to be
    sold or delivered or such service is provided or agreed to be
    provided, or who alleges unfair trade practice in respect of such
    goods or service, is a member of such association or not;

    (c) one or more consumers, where there are numerous
    consumers having the same interest, with the permission of the
    District Commission, on behalf of, or for the benefit of, all
    consumers so interested; or

    (d) the Central Government, the Central Authority or the State
    Government, as the case may be:

    Provided that the complaint under this sub-section may be filed
    electronically in such manner as may be prescribed.”

    xxx

    38. We may take for example a case where a residential apartment
    is purchased by the husband and wife jointly or by a parent and
    child jointly. If they have a grievance against the builder, both of
    them are entitled to file a complaint jointly. Such a complaint will
    not fall under Section 35(1)(c) but fall under Section 35(1)(a).

    Persons filing such a complaint cannot be excluded from Section
    2(5)(i)
    on the ground that it is not by a single consumer. It cannot
    also be treated as one by persons falling under Section 2(5)(v)
    attracting the application of Order 1 Rule 8 CPC read with Section
    38(11)
    .

    xxx

    40. It must be remembered that the provisions of the Consumer
    Protection Act
    are in addition to and not in derogation of the
    provisions of any other law for the time being in force, by virtue of
    Section 100. Even Section 38 which prescribes the procedure to be
    followed by the Commission for enquiring into the complaint, does
    not expressly exclude the application of the provisions of CPC.
    Though sub-sections (9), (11) and (12) of Section 38 make specific
    reference only to a few provisions of the Code of Civil Procedure,
    the principle behind Order 1 Rule 1 enabling more than one person
    Signature Not Verified
    Signed By:ANKITA CM(M)
    RAI 1248/2022 Page 40 of 44
    Signing Date:25.07.2026
    16:08:56
    to join in a suit as plaintiff is not expressly excluded.

    xxx

    41. Therefore, we are of the considered view that while the
    National Commission was wrong in this case, in the peculiar facts
    and circumstances in permitting an application under Section
    35(1)(c)
    read with Order 1 Rule 8 CPC, it does not mean that the
    complaint filed by the respondents itself is liable to be thrown out.
    The complaint filed by the respondents may have to be treated as a
    joint complaint and not a complaint in a representative capacity on
    behalf of 1134 purchasers. The purchasers of other flats, such as
    the intervenors herein may join as parties to the consumer
    complaint, if they so desire. As a matter of fact, it is stated by the
    intervenors that pursuant to the impugned order [Anil Kumar
    Virmani v. Brigade Enterprises Ltd.
    , 2021 SCC OnLine NCDRC
    417] , advertisements were issued and the intervenors have already
    filed impleadment application before the National Commission.
    They are entitled to be impleaded.”

    [Emphasis Supplied]

    83. Mr. Misra has urged that, in view of Brigade Enterprises, the
    respondents should pursue their claims through a joint complaint
    under Section 12(1)(a), rather than continue under Section 12(1)(c).
    This Court does not consider it appropriate to render a final opinion on
    that submission in the present proceedings. Whether the complaint
    may continue as a representative complaint, whether it may proceed as
    a joint complaint confined to the surviving complainants, or whether
    any identifiable group of complainants may be permitted to pursue a
    common grievance, are matters which must first be considered by the
    learned NCDRC after undertaking the requisite factual enquiry.

    84. For the same reason, this Court refrains from deciding on
    whether the statement recorded on 27.07.2022, by which the
    complainants confined their claims to delayed-possession
    compensation and increased saleable area, amounted to an
    abandonment of part of the representative claim attracting Order I
    Signature Not Verified
    Signed By:ANKITA CM(M)
    RAI 1248/2022 Page 41 of 44
    Signing Date:25.07.2026
    16:08:56
    Rule 8(4) of the CPC. The legal effect of that statement cannot be
    examined in isolation from the identity of the persons represented by
    the complaint, the reliefs in which they were interested and the
    representative character, if any, in which the proceedings may
    continue. The said issue is, therefore, also left open for determination
    by the learned NCDRC.

    85. The conclusion reached by the learned NCDRC cannot,
    therefore, be sustained. This is not because this Court has itself
    determined that the surviving complainants lack sameness of interest,
    but because the necessary factual and statutory enquiry preceding such
    a conclusion was not undertaken. The failure to apply the
    jurisdictional requirements of Section 12(1)(c) to the presently
    surviving complainants and to examine compliance with the
    conditions imposed on 30.05.2019 renders the impugned order
    vulnerable to interference under Article 227.

    86. Accordingly, the order dated 12.10.2022 passed by the learned
    NCDRC in I.A. No. 4407/2022 is liable to be set aside and the matter
    remitted to the learned NCDRC for consideration afresh. The learned
    NCDRC shall ascertain the current status and factual position of each
    surviving complainant and determine, in accordance with law:

    i. whether the surviving complainants, or any legally identifiable
    group amongst them, possess the “same interest” required for
    continuation of a representative complaint under Section
    12(1)(c)
    ;

    ii. whether the conditions imposed by the order dated 30.05.2019
    stand satisfied;

    Signature Not Verified
    Signed By:ANKITA CM(M)
    RAI 1248/2022 Page 42 of 44
    Signing Date:25.07.2026
    16:08:56

    iii. whether, having regard to Brigade Enterprises (Supra), the
    proceedings may continue as a representative complaint, or as a
    joint complaint confined to the complainants actually before it,
    or in any other manner permissible under the 1986 Act;
    iv. the effect of the settlements, transfers, conveyances,
    compensation accepted and proceedings pursued before other
    forums;

    v. the effect of the statement recorded on 27.07.2022 in the
    context of Order I Rule 8(4) of the CPC; and
    vi. any other ancillary or consequential issue which the learned
    NCDRC considers necessary for the effective and complete
    adjudication of the complaint.

    87. It is clarified that this Court has expressed no final opinion on
    the merits of the aforesaid questions. All contentions of the parties in
    that regard are left open to be urged before and decided by the learned
    NCDRC on the basis of the updated array of parties, the material
    already on record and such further material as may be permitted to be
    placed before it.

    88. This Court is mindful of the concern raised by respondents that,
    after the complaint has remained pending for several years, the
    surviving complainants should not be left to recommence the entire
    process or be deprived of adjudication merely because some members
    of the original class have settled or ceased to pursue the proceedings.
    At the same time, the claims of those who continue to prosecute the
    complaint must be examined within the statutory framework. In these
    circumstances, the appropriate course would be to request the learned
    NCDRC to undertake the aforesaid exercise and conclude the
    Signature Not Verified
    Signed By:ANKITA CM(M)
    RAI 1248/2022 Page 43 of 44
    Signing Date:25.07.2026
    16:08:56
    proceedings as expeditiously as possible, preferably within a period of
    six months from the date of receipt of a copy of this judgment.

    89. In view of the aforesaid discussion, CM APPL. 29491/2026,
    filed by respondent no. 19 seeking a direction to the petitioner to hand
    over physical and vacant possession of Unit No. B1-38, Ground Floor,
    “The Valley”, Panchkula, Haryana, is also disposed of. The relief
    sought therein is left open to be considered and decided by the learned
    NCDRC, in accordance with law, while adjudicating Consumer
    Complaint No. 1962/2017.

    90. Accordingly, the present petition is allowed to the extent
    indicated hereinabove. The petition, along with all pending
    applications, stands disposed of.

    91. The judgment be uploaded on the website forthwith.

    92. The Registry is directed to send a copy of this judgment to the
    learned NCDRC.

    AJAY DIGPAUL, J.

    JULY 24, 2026/gs/yr

    Signature Not Verified
    Signed By:ANKITA CM(M)
    RAI 1248/2022 Page 44 of 44
    Signing Date:25.07.2026
    16:08:56



    Source link

    LEAVE A REPLY

    Please enter your comment!
    Please enter your name here