                                                    IN THE SUPREME COURT OF INDIA
                                                     CIVIL APPELLATE JURISDICTION
    
                                       CONTEMPT PETITION (CIVIL) NO. 194 OF 2026
                                                           IN
                                    SPECIAL LEAVE PETITION(CIVIL) NO. 3799 OF 2024
    
            M/S SRI BALAJI CORPORATE                                                                       PETITIONER(S)
            SERVICES & ANR.
                                                                     VERSUS
            DR. S SELVAKUMAR & ORS.                                                               RESPONDENT(S)/
                                                                                            ALLEGED CONTEMNOR(S)
    
    
                                                               O R D E R
    

    1. The land of the petitioner was acquired by Karnataka

    Industrial Area Development Board (KIADB) and handed over to

    SPONSORED

    Bangalore Metro Rail Corporation Limited for execution of the Metro

    Project in Bangalore City. The controversy was whether the

    expropriated land owners are entitled to seek compensation in

    accordance with the provisions of the Right to Fair Compensation

    and Transparency in Land Acquisition, Rehabilitation and

    Resettlement Act, 2013 (“2013 Act”) even though their land is

    acquired under the Karnataka Industrial Area Development Act, 1966

    (KIADA).

    2. To avoid undue hardship to the affected land owners, this

    Court vide interim order dated 09.02.2024 directed that the

    acquisition proceedings will continue and the Award shall be passed

    in accordance with the provisions of the 2013 Act. In purported

    compliance thereto, KIADB passed an alleged award dated 28.11.2022,
    Signature Not Verified

    Digitally signed by

    which, according to the respondents, is in accordance with the
    NITIN TALREJA
    Date: 2026.07.24
    10:22:17 IST
    Reason:

    provisions of the 2013 Act.

    1

    3. The petitioners, however, have contested this claim as,

    according to them, the award does not meet the statutory

    requirements of the 2013 Act.

    4. Their second grievance is regarding deduction of TDS out of

    the compensation amount awarded under the afore-stated award.

    5. The aggrieved petitioners, at the same time, filed an

    application seeking reference under Section 64 of the 2013 Act.

    That application is required to be forwarded by the Land

    Acquisition Collector-cum-Officer to the jurisdictional Reference

    Court. However, no such reference has been made so far.

    6. In this backdrop, the petitioners have three grievances:

    (i) The purported award dated 28.11.2022 is not an award in

    accordance with the provisions of the 2013 Act;

    (ii) Their reference application has not been forwarded to the

    Reference Court; and

    (iii) No TDS could be deducted out of the compensation amount.

    Hence, this contempt proceeding has been initiated before us.

    7. So far as the first grievance of the petitioners is concerned,

    this can be effectively addressed by the Reference Court and

    wherever it is found that provisions of the 2013 Act have not been

    complied with, the Reference Court is empowered to suitably modify

    the award in accordance with law.

    8. As regards the second grievance, namely, the failure of the

    Land Acquisition Collector-cum-Officer to forward the reference

    application for further enhancement of compensation, we see no

    justification for the Land Acquisition Collector-cum-Officer to sit

    over such references, especially when almost three years have

    2
    passed. We, accordingly, direct the State of Karnataka and its Land

    Acquisition Collector-cum-Officer as well as KIADB to ensure that

    the pending applications are immediately forwarded to the

    jurisdictional Reference Court. The needful shall be done within

    four weeks from the date of receipt of a copy of this order.

    9. As regards the deduction of TDS, we are of the considered view

    that since the acquisition is deemed to have been made under the

    2013 Act in terms of the earlier interim order passed by this

    Court, no TDS could be deducted in view of Section 96 of the 2013

    Act. The amount deducted towards TDS is, accordingly, directed to

    be reimbursed to the farmers as early as possible but not later

    than six weeks.

    10. The contempt proceedings are disposed of, in the above terms.

    ……………………CJI.

    (SURYA KANT)

    ……………………..J.
    (JOYMALYA BAGCHI)

    ……………………..J.
    (VIPUL M. PANCHOLI)
    NEW DELHI;

    JULY 21, 2026.

    3

    ITEM NO.32               COURT NO.1                 SECTION IV-A
    
                   S U P R E M E C O U R T O F      I N D I A
                           RECORD OF PROCEEDINGS
    
      Petition(s) for Special Leave to Appeal (C)     No(s).    3798/2024
    
    

    [Arising out of impugned judgment and order dated 27-09-2023 in WA
    No. 892/2022 passed by the High Court of Karnataka at Bengaluru]

    BANGALORE METRO RAIL CORPORATION LIMITED Petitioner(s)

    VERSUS

    L.VENKATARAMANA RAJU & ORS. Respondent(s)

    [ONLY CONMT.PET.(C) No. 194/2026 IS LISTED UNDER THIS ITEM]

    WITH

    CONMT.PET.(C) No. 194/2026 in SLP(C) No. 3799/2024 (IV-A)
    (IA No. 86657/2026 – EXEMPTION FROM FILING O.T.)

    Date : 21-07-2026 This petition was called on for hearing today.

    CORAM : HON’BLE THE CHIEF JUSTICE
    HON’BLE MR. JUSTICE JOYMALYA BAGCHI
    HON’BLE MR. JUSTICE VIPUL M. PANCHOLI

    For Petitioner(s) :Mr. Vaibhav Joshi, AOR

    Mr. Gagan Gupta, Sr. Adv.

    Mr. Mahesh Thakur, AOR
    Mr. Siddhartha Sati, Adv.

    Mr. Narveer Yadav, Adv.

    Mr. Arpith Jacob Varaprasad, Adv.

    Mr. Jasbir Singh, Adv.

    Ms. Ruchi Kumari, Adv.

    For Respondent(s) :Mr. Ashwin V. Kotemath, Adv.

    Mr. Harisha S.r., AOR

    Mr. N. Venkataraman, A.S.G.
    Mr. Sudarshan Lamba, AOR
    Mr. V.C.bharathi, Adv.

    Mr. Shashank Bajpai, Adv.

    Mr. Ishan Kapoor, Adv.

    Ms. Mrigna Shekhar, Adv.

    Mr. Sanchit Garga, AOR
    Mr. Kunal Rana, Adv.

    Mr. Shashwat Jaiswal, Adv.

    4
    Mr. Bhanu Pratap Singh, Adv.

    Ms. Diksha Arora, Adv.

    Mr. Sankalp Mishra, Adv.

    Mr. Nishanth Patil, AOR
    Mr. Nishanth Patil, Adv.

    Mr. Arijit Dey, Adv.

    Mr. Awanish Gupta, Adv.

    Mr. Abhishek Gupta, Adv.

    Ms. Bhumi Agrawal, Adv.

    Mr. Shailesh Madiyal, Sr. Adv.

    Mr. Sudhanshu Prakash, AOR
    Ms. Anisha Agarwal, Adv.

    Mr. Ishrafil Ansari, Adv.

    UPON hearing the counsel the Court made the following

    O R D E R

    Contempt Petition (Civil) No. 194/2026 in SLP(C) No. 3799/2024

    The contempt proceedings are disposed of in terms of the

    signed order.

    Pending application(s), if any, shall stand closed.

    (NITIN TALREJA) (PREETHI DILEEP KUMAR)
    ASTT. REGISTRAR-cum-PS DY. REGISTRAR

    (Signed order is placed on the file)