Become a member

Get the best offers and updates relating to Liberty Case News.

― Advertisement ―

HomeHigh CourtJammu & Kashmir High Court2026:Jklhc-Jmu:484 vs University Of Jammu on 20 February, 2026

2026:Jklhc-Jmu:484 vs University Of Jammu on 20 February, 2026

Jammu & Kashmir High Court

2026:Jklhc-Jmu:484 vs University Of Jammu on 20 February, 2026

Author: Sanjeev Kumar

Bench: Sanjeev Kumar

                                                                             2026:JKLHC-JMU:484

                                                                       Sr. No. 03

         HIGH COURT OF JAMMU & KASHMIR AND LADAKH
                         AT JAMMU

Arb P No. 6/2025
                                             Date of pronouncement : 20.02.2026
                                             Date of Uploading    : 23.02.2026

     Shekhar Enterprises Engineer & Builder Contractor,             .....Petitioner(s)
     Congress Bazaar Pathankot through its Partner
     Chander Shekhar Sharma,
     S/o Sh. Subash Chander Sharma,
     R/o H. No. 2294, Sector-18, Abrol Nagar,
     Pathankot-145001, Punjab.

                                Through :- Mr. G S Thakur, Advocate

                         v/s
1. University of Jammu,                                           .....Respondent(s)
   through its Vice Chancellor,
   B R Ambedkar Road, Jammu.
2. Registrar,
   University of Jammu,
   B R Ambedkar Road, Jammu.
3. Executive Engineer,
   University of Jammu,
   Works Department,
   B R Ambedkar Road, Jammu.

                                Through :- Mr. Manik Bhardawaj, Advocate


CORAM: HON'BLE MR. JUSTICE SANJEEV KUMAR, JUDGE

                               ORDER (ORAL)

1. The petitioner was allotted contract work for the construction of a Boys

Hostel Civil and Sanitary work at Kathua Campus of Jammu University,

pursuant to an agreement dated 29.01.2013 executed between the

petitioner and Respondent No. 3/Executive Engineer of Respondent No.

1.

2. The petitioner has contended that there was a delay in execution of the

work owing to one reason or another. However, in terms of letter dated
Arb P No. 6/2025 2 2026:JKLHC-JMU:484

19.05.2014 issued by the Assistant Executive Engineer, it was confirmed

that the work actually commenced on 04.11.2013 after the site was made

available to the contractor. It is further stated that the petitioner

completed the work and raised the claims amounting to Rs. 43,31,861/-

including the earnest money and 10% reserve on work done, however,

the said payment was not released. It is also stated that the petitioner is

entitled to claim an amount of Rs. 2.605 Cr. Along with interest @ 18%.

3. The petitioner claims to have made various representations to the

respondents, seeking release of the payment or, in the alternative, referral

of the dispute to the arbitrator, but to no avail. The petitioner has placed

on record a communication dated 21.10.2024 requesting settlement of

the dispute or in the alternative treat the same as a notice invoking

arbitration in terms of condition No. 26 of General Conditions of

Contract forming part of the contract agreement. On the basis of these

facts, the petitioner has sought appointment of an arbitrator to adjudicate

the dispute arising out of the NIT No. UWD/12-13/4009-20 dated

23.01.2013.

4. The respondents have filed their response stating therein that the

petitioner was required to complete the contract work within a period of

twelve months as per the terms and conditions of the contract agreement,

but inordinate delay was caused by the petitioner itself in execution of

the work. It is further stated that the contract provides that any dispute,

doubt, difference, or question of any kind, except certain matters, shall

be referred to the Vice Chancellor, who has to act as an Arbitrator. The
Arb P No. 6/2025 3 2026:JKLHC-JMU:484

respondents have denied that they are under any obligation to pay the

amount claimed by the petitioner.

5. Heard learned counsel for the parties and perused the record.

6. The existence of the arbitration agreement is not disputed by the

respondents. In view of the admitted existence of an arbitration

agreement and the failure of the respondents to refer the dispute to

arbitration despite due notice, this Court finds that the pre-conditions for

invocation of jurisdiction under Section 11 (6) of the Arbitration and

Conciliation Act, 1996 stand satisfied. Although it is the stand of the

respondents that Vice Chancellor has to act as an Arbitrator, the learned

counsel for the respondents has fairly conceded that the said course is

impermissible due to subsequent amendment.

7. It is well settled that where a named Arbitrator becomes ineligible or is

unable to act, an independent and impartial Arbitrator can be appointed

to ensure adjudication of the disputes between the parties. The disputes

raised by the petitioner arise out of the execution of the contract and are

arbitrable in nature. Accordingly, Sh. S. R. Gandhi, Retired District

Judge is hereby appointed as the Sole Arbitrator to adjudicate the

disputes between the parties arising out of NIT No. UWD/12-13/4009-20

dated 23.01.2013 and the agreement dated 29.01.2013.

8. The learned Arbitrator shall enter upon the reference after furnishing the

disclosure as required under Section 12 (1) of the Arbitration and

Conciliation Act, 1996 and shall conduct the arbitral proceedings in

accordance with the provisions of the Act. The fee of the learned
Arb P No. 6/2025 4 2026:JKLHC-JMU:484

Arbitrator shall be governed by the Fourth Schedule of the Act, unless

otherwise agreed between the parties.

9. The Registry shall send a copy of this order to the learned Arbitrator

forthwith.

10. The petition stands disposed of in the above terms.

(Sanjeev Kumar)
Judge

JAMMU
20.02.2026
Manan

Whether the order is speaking : Yes/No
Whether the order is reportable : Yes/No



Source link